Transcript of Chapter 9 1. 1.Understand and apply key scheduling terminology. 2.Apply the logic used to create...
![Page 1: Chapter 9 1. 1.Understand and apply key scheduling terminology. 2.Apply the logic used to create activity networks, including predecessor and successor.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cb95503460f94981274/html5/thumbnails/1.jpg)
1
Project Scheduling: Networks, Duration
Estimation, and Critical PathChapter 9
![Page 2: Chapter 9 1. 1.Understand and apply key scheduling terminology. 2.Apply the logic used to create activity networks, including predecessor and successor.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cb95503460f94981274/html5/thumbnails/2.jpg)
2
1. Understand and apply key scheduling terminology. 2. Apply the logic used to create activity networks,
including predecessor and successor tasks. 3. Develop an activity network using Activity-on-Node
(AON) techniques. 4. Perform activity duration estimation based on the use
of probabilistic estimating techniques. 5. Construct the critical path for a project schedule
network using forward and backward passes. 6. Identify activity float and the manner in which it is
determined. 7. Understand the steps that can be employed to reduce
the critical path.
Learning Goals
![Page 3: Chapter 9 1. 1.Understand and apply key scheduling terminology. 2.Apply the logic used to create activity networks, including predecessor and successor.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cb95503460f94981274/html5/thumbnails/3.jpg)
3
Project scheduling requires us to follow some carefully laid-out steps, in order, for the schedule to take shape.
Project planning, as it relates to the scheduling process, has been defined by the PMBoK as:
◦ “The identification of the project objectives and the ordered activity necessary to complete the project including the identification of resource types and quantities required to carry out each activity or task.”
Project Scheduling
![Page 4: Chapter 9 1. 1.Understand and apply key scheduling terminology. 2.Apply the logic used to create activity networks, including predecessor and successor.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cb95503460f94981274/html5/thumbnails/4.jpg)
4
Represents the conversion of project goals into an achievable methodology.
Creates a timetable and reveals the network logic that relates project activities to each other.
A graphical set of sequential relationships between project task which, when performed, result in the completion of the project goals.
Vitally important to obtaining project goals, being on time and on budget.
Project Scheduling
![Page 5: Chapter 9 1. 1.Understand and apply key scheduling terminology. 2.Apply the logic used to create activity networks, including predecessor and successor.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cb95503460f94981274/html5/thumbnails/5.jpg)
5
Allows project teams to use a method for planning and scheduling
There are several advantages when project networks and scheduling are done well
Project Network Diagrams (PND)
Show interdependence
Facilitate communication
Help schedule resources
Identify critical activities
Determine project completion
Show start & finish dates for task
See slide 26 for an example
![Page 6: Chapter 9 1. 1.Understand and apply key scheduling terminology. 2.Apply the logic used to create activity networks, including predecessor and successor.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cb95503460f94981274/html5/thumbnails/6.jpg)
6
Project Scheduling Terms
SuccessorsPredecessorsNetwork diagramSerial activitiesConcurrent
activities
ED
C
B
A F
Merge activitiesBurst activitiesNodePathCritical Path
![Page 7: Chapter 9 1. 1.Understand and apply key scheduling terminology. 2.Apply the logic used to create activity networks, including predecessor and successor.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cb95503460f94981274/html5/thumbnails/7.jpg)
7
Most Common Methods for Constructing Activity Networks
The same mini-project is shown with activities on arrow…
C
ED
B F
E
C
DB F
…and activities on node.
AOA vs. AON
![Page 8: Chapter 9 1. 1.Understand and apply key scheduling terminology. 2.Apply the logic used to create activity networks, including predecessor and successor.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cb95503460f94981274/html5/thumbnails/8.jpg)
8
1. Some determination of activity precedence ordering must be done prior to creating the network.
2. Network diagrams usually flow from left to right.3. An activity cannot begin until all preceding connected
activities have been completed.4. Arrows on networks indicate precedence and logical flow.
Arrows can cross over each other, although it is helpful for clarity’s sake to limit this effect when possible.
5. Each activity should have a unique identifier associated with it (number, letter, code, etc.).
6. Looping, or recycling through activities, is not permitted.7. Although not required, it is common to start a project on a
single node. A single node point also is typically used as a project end indicator.
Rules for Developing Activity Networks
![Page 9: Chapter 9 1. 1.Understand and apply key scheduling terminology. 2.Apply the logic used to create activity networks, including predecessor and successor.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cb95503460f94981274/html5/thumbnails/9.jpg)
9
Information for Network Construction Name: Project Delta
Activity Description PredecessorsA Contract signing None
B Questionnaire design A C Target market ID A D Survey sample B, C E Develop presentation B F Analyze results D G Demographic analysis C H Presentation to client E, F, G
Construct a Network Diagram
Example of Creating a Project Activity Network
![Page 10: Chapter 9 1. 1.Understand and apply key scheduling terminology. 2.Apply the logic used to create activity networks, including predecessor and successor.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cb95503460f94981274/html5/thumbnails/10.jpg)
10
Activity Network Example
A Contract
CMarket ID
BDesign
GDemog.
EDev. Present.
DSurvey
F Analysis
H Present
![Page 11: Chapter 9 1. 1.Understand and apply key scheduling terminology. 2.Apply the logic used to create activity networks, including predecessor and successor.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cb95503460f94981274/html5/thumbnails/11.jpg)
11
College research paper example
Project Activities Linked In Series/Parallel (Concurrent)
![Page 12: Chapter 9 1. 1.Understand and apply key scheduling terminology. 2.Apply the logic used to create activity networks, including predecessor and successor.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cb95503460f94981274/html5/thumbnails/12.jpg)
12
Merge/Burst Activities
Activity A
Activity B
Activity C
Activity D Activity C
Activity B
Activity A
Activity D
![Page 13: Chapter 9 1. 1.Understand and apply key scheduling terminology. 2.Apply the logic used to create activity networks, including predecessor and successor.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cb95503460f94981274/html5/thumbnails/13.jpg)
13
Node Labels
Early Start
Activity Float Activity Descriptor
Late Start
ID Number
Activity Duration
Late Finish
Early Finish
11 D 240 Survey11 13 24
ES ID EFSlack Task NameLS Duration LF
![Page 14: Chapter 9 1. 1.Understand and apply key scheduling terminology. 2.Apply the logic used to create activity networks, including predecessor and successor.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cb95503460f94981274/html5/thumbnails/14.jpg)
14
Duration Estimation
Assumptions◦ Based on normal working methods during normal
hours◦ Durations are always somewhat uncertain◦ Timeframes can be from minutes to weeks
Methods◦ Past experience◦ Expert opinion◦ Mathematical derivation based on Beta Distribution
Most optimistic (a) time – better then planned Most likely (m) time – realistic expectation Most pessimistic (b) time – Murphy’s Law kicks in
There are only two types of estimates…lucky and wrong.
![Page 15: Chapter 9 1. 1.Understand and apply key scheduling terminology. 2.Apply the logic used to create activity networks, including predecessor and successor.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cb95503460f94981274/html5/thumbnails/15.jpg)
15
Critical Path Method (CPM) assumes we know a fixed time estimate for each activity and there is no variability in activity times
Program Evaluation and Review Technique (PERT) uses a probability distribution for activity times to allow for variability
Variability in Activity Times
![Page 16: Chapter 9 1. 1.Understand and apply key scheduling terminology. 2.Apply the logic used to create activity networks, including predecessor and successor.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cb95503460f94981274/html5/thumbnails/16.jpg)
16
Where:
a = Most optimistic time
m = Most likely time
b = Most pessimistic time
Activity Duration Estimation – Beta Distribution
22 =
6
b aActivity Variance
4 = TE
6
a m bActivity Duration
![Page 17: Chapter 9 1. 1.Understand and apply key scheduling terminology. 2.Apply the logic used to create activity networks, including predecessor and successor.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cb95503460f94981274/html5/thumbnails/17.jpg)
17
Project variance is computed by summing the variances of activities on the critical path
Project variance = (variances of activities on critical path)
Probability of Project Completion
Project standard deviation = Project Variance
![Page 18: Chapter 9 1. 1.Understand and apply key scheduling terminology. 2.Apply the logic used to create activity networks, including predecessor and successor.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cb95503460f94981274/html5/thumbnails/18.jpg)
18
Task Predecessor a m b mean variance
Z -- 7 8 15 9.00 1.78
Y Z 13 16 19 16.00 1.00
X Z 14 18 22 18.00 1.78
W Y, X 12 14 16 14.00 0.44
V W 1 4 13 5.00 4.00
T W 6 10 14 10.00 1.78
S T, V 11 14 19 14.33 1.78
1. Determine the expected duration and variance of each activity.
2. Sketch the network described in the table.
3. Determine the expected project time and standard deviation.
Network Example
![Page 19: Chapter 9 1. 1.Understand and apply key scheduling terminology. 2.Apply the logic used to create activity networks, including predecessor and successor.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cb95503460f94981274/html5/thumbnails/19.jpg)
19
Constructing the Network Paths Forward pass – an additive move through
the network from start to finish
Backward pass – a subtractive move through the network from finish to start
Critical path – the longest path from end to end which determines the shortest project length
![Page 20: Chapter 9 1. 1.Understand and apply key scheduling terminology. 2.Apply the logic used to create activity networks, including predecessor and successor.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cb95503460f94981274/html5/thumbnails/20.jpg)
20
Activity Description Predecessors Estimated Duration
A Contract signing None 5
B Questionnaire design A 5
C Target market ID A 6
D Survey sample B, C 13
E Develop presentation B 6
F Analyze results D 4
G Demographic analysis C 9
H Presentation to client E, F, G 2
Constructing the Critical Path Example
Construct the critical path.
![Page 21: Chapter 9 1. 1.Understand and apply key scheduling terminology. 2.Apply the logic used to create activity networks, including predecessor and successor.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cb95503460f94981274/html5/thumbnails/21.jpg)
21
Activity Network with Task Durations and Critical Path
AContract
5
BDesign
5
CMarket ID
6
DSurvey
13
GDemog.
9
FAnalysis
4
EDev. Present
6
HPresent
2
Critical Path is indicated in bold
![Page 22: Chapter 9 1. 1.Understand and apply key scheduling terminology. 2.Apply the logic used to create activity networks, including predecessor and successor.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cb95503460f94981274/html5/thumbnails/22.jpg)
22
Rules for Forward/Backward PassForward Pass Rules (ES & EF)
◦ ES + Duration = EF◦ EF of predecessor = ES of successor◦ Largest preceding EF at a merge point becomes
ES for successor
Backward Pass Rules (LS & LF)◦ LF – Duration = LS◦ LS of successor = LF of predecessor◦ Smallest succeeding LS at a burst point
becomes LF for predecessor
ES ID EFSlack Task NameLS Duration LF
Calculate the forward/backwards pass.
![Page 23: Chapter 9 1. 1.Understand and apply key scheduling terminology. 2.Apply the logic used to create activity networks, including predecessor and successor.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cb95503460f94981274/html5/thumbnails/23.jpg)
23
Activity Network with Forward Pass Added
0 A 5Contract
5
5 B 10Design
5
5 C 11Market ID
6
11 D 24Survey 13
11 G 20Demograph.
9
24 F 28Analysis
4
10 E 16Dev. Present
6
28 H 30Presentation
2
ES ID EFSlack Task NameLS Duration LF
![Page 24: Chapter 9 1. 1.Understand and apply key scheduling terminology. 2.Apply the logic used to create activity networks, including predecessor and successor.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cb95503460f94981274/html5/thumbnails/24.jpg)
24
Activity Network With Backward Pass Added
0 A 5Contract
0 5 5
5 B 10Design
6 5 11
5 C 11Market ID
5 6 11
11 D 24Survey
11 13 24
11 G 20Demograph.
19 9 28
24 F 28Analysis
24 4 28
10 E 16Dev. Present
22 6 28
28 H 30Presentation
28 2 30
ES ID EFSlack Task NameLS Duration LF
![Page 25: Chapter 9 1. 1.Understand and apply key scheduling terminology. 2.Apply the logic used to create activity networks, including predecessor and successor.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cb95503460f94981274/html5/thumbnails/25.jpg)
25
Informs us of the amount an activity can be delayed without delaying the overall project.
It is determined as a result of performing the forward and backward pass through the network.
Calculated either by◦ LF-EF = Slack◦ LS-ES = Slack
The critical path is the network path with “0” slack.*◦ *This assumes a deadline has not been set for LF that is
within our calculated project time. ◦ *Negative float is a result of the project time being longer
than a set project end time.
Activity Float - Slack Time
Calculate the slack time and determine critical path.
![Page 26: Chapter 9 1. 1.Understand and apply key scheduling terminology. 2.Apply the logic used to create activity networks, including predecessor and successor.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cb95503460f94981274/html5/thumbnails/26.jpg)
26
Completed Activity Network With Critical Path And Activity Slack Times Identified
0 A 50 Contract0 5 5
5 B 101 Design6 5 11
5 C 110 Market ID5 6 11
11 D 240 Survey11 13 24
11 G 208 Demograph.
19 9 28
24 F 280 Analysis
24 4 28
10 E 1612 Dev. Present
22 6 28
28 H 30 0 Presentation
28 2 30
ES ID EFSlack Task NameLS Duration LF
Critical Path is indicated in bold
![Page 27: Chapter 9 1. 1.Understand and apply key scheduling terminology. 2.Apply the logic used to create activity networks, including predecessor and successor.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cb95503460f94981274/html5/thumbnails/27.jpg)
27
Task Predecessor Time
A -- 4
B A 9
C A 11
D B 5
E B 3
F C 7
G D, F 3
H E, G 2
K H 1
1. Sketch the network described in the table.
2. Determine the ES, LS, EF, LF, and slack of each activity.
3. Determine the critical path.
Example
![Page 28: Chapter 9 1. 1.Understand and apply key scheduling terminology. 2.Apply the logic used to create activity networks, including predecessor and successor.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cb95503460f94981274/html5/thumbnails/28.jpg)
28
Laddering Activities
Project ABC can be completed more efficiently if subtasks are used. Example: A does not need to be completely finished before work
on B starts.
A(3) B(6) C(9) ABC=18 days
Laddered ABC=12 days
A1(1) A2(1) A3(1)
B1(2) B2(2) B3(2)
C1(3) C2(3) C3(3)
![Page 29: Chapter 9 1. 1.Understand and apply key scheduling terminology. 2.Apply the logic used to create activity networks, including predecessor and successor.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cb95503460f94981274/html5/thumbnails/29.jpg)
29
Hammock Activities
Used as a summary for subsets of activities
0 A 5
0 5 5
5 B15
5 1015
15 C 18
15 3 18
0 Hammock 18
0 18 18
Useful with a complex project or one that has a shared budget
![Page 30: Chapter 9 1. 1.Understand and apply key scheduling terminology. 2.Apply the logic used to create activity networks, including predecessor and successor.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cb95503460f94981274/html5/thumbnails/30.jpg)
30
Eliminate tasks on the critical path◦ remove task with no value
Convert serial paths to parallel when possible Overlap sequential tasks
◦ use laddering when possible Shorten the duration on critical path tasks Shorten
◦ early tasks (have you read “The Goal”)◦ longest tasks◦ easiest tasks◦ tasks that cost the least to speed up – “crashing”
Reducing the Critical Path
![Page 31: Chapter 9 1. 1.Understand and apply key scheduling terminology. 2.Apply the logic used to create activity networks, including predecessor and successor.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cb95503460f94981274/html5/thumbnails/31.jpg)
31
1. Define the following terms: Path, Activity, Early start, Early finish, Late start, Late finish, Forward pass, Backward pass, Node, AON, Float, Critical Path, PERT
2. Distinguish between serial activities and concurrent activities. Why do we seek to use concurrent activities as a way to shorten a project’s length?
3. List three methods for deriving duration estimates for project activities. What are the strengths and weaknesses associated with each method?
Discussion Questions
![Page 32: Chapter 9 1. 1.Understand and apply key scheduling terminology. 2.Apply the logic used to create activity networks, including predecessor and successor.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cb95503460f94981274/html5/thumbnails/32.jpg)
32
4. In your opinion, what are the chief benefits and drawbacks of using beta distribution calculations (based on PERT techniques) to derive activity duration estimates?
5. “The shortest total length of a project is determined by the longest path through the network.” Explain the concept behind this statement. Why does the longest path determine the shortest project length?
6. The float associated with each project task can only be derived following the completion of the forward and backward passes. Explain why this is true.
Discussion Questions
![Page 33: Chapter 9 1. 1.Understand and apply key scheduling terminology. 2.Apply the logic used to create activity networks, including predecessor and successor.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cb95503460f94981274/html5/thumbnails/33.jpg)
33
Now that Joe has agreed to your WBS, he wants to review a schedule and present it to the president. She is a “big picture” thinker and does not usually get involved with the details, so Joe wants to limit the content of the diagram you show her to the basics that concern her.
You have also worked with your team on estimating the durations of each of the work packages in the WBS. Note that in this case, the work packages are the scheduled activities. Here is your current plan for the briefing to the president:
Case Study 5
![Page 34: Chapter 9 1. 1.Understand and apply key scheduling terminology. 2.Apply the logic used to create activity networks, including predecessor and successor.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cb95503460f94981274/html5/thumbnails/34.jpg)
34
Case Study 5
![Page 35: Chapter 9 1. 1.Understand and apply key scheduling terminology. 2.Apply the logic used to create activity networks, including predecessor and successor.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cb95503460f94981274/html5/thumbnails/35.jpg)
35
1. Build a network diagram2. Calculate forward pass, backward pass,
float, and critical path3. Be ready to address—
◦ How long will the project take?◦ When should you begin installing new furniture,
communications equipment, and computers if you want to be in the new office by July 31?
◦ What items are on the critical path?
Case Study 5