Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.

31
Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.

Transcript of Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.

Page 1: Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.

Chapter 8

Scheduling

© 2012 John Wiley & Sons Inc.

Page 2: Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.

8-8-22

Useful Abbreviations

CPM - Critical Path MethodPERT - Program Evaluation and Review

Technique

Page 3: Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.

8-8-33

Network Scheduling Advantage

Consistent frameworkShows interdependencesShows when resources are neededEnsures proper communicationDetermines expected completion date Identifies critical activities

Page 4: Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.

8-8-44

Network Scheduling Advantage Continued

Shows which of the activities can be delayed

Determines start datesShows which task must be coordinatedShows which task can be run parallelRelieves some conflictAllows probabilistic estimates

Page 5: Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.

8-8-55

Network Scheduling Techniques: PERT (ADM) and CPM (PDM)

PERT was developed for the Polaris missile/submarine project in 1958

CPM developed by DuPont during the same time

Initially, CPM and PERT were two different approaches– CPM used deterministic time estimates and allowed

project crunching– PERT used probabilistic time estimates

Microsoft Project (and others) have blended CPM and PERT into one approach

Page 6: Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.

8-8-66

Terminology

Activity - A specific task or set of tasks that are required by the project, use up resources, and take time to complete

Event - The result of completing one or more activities

Network - The combination of all activities and events that define a project– Drawn left-to-right– Connections represent predecessors

Page 7: Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.

8-8-77

Terminology Continued

Path - A series of connected activitiesCritical - An activity, event, or path

which, if delayed, will delay the completion of the project

Critical Path - The path through the project where, if any activity is delayed, the project is delayed– There is always a critical path– There can be more than one critical path

Page 8: Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.

8-8-88

Terminology Continued

Sequential Activities - One activity must be completed before the next one can begin

Parallel Activities - The activities can take place at the same time

Immediate Predecessor - That activity that must be completed just before a particular activity can begin

Page 9: Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.

8-8-99

Terminology Continued

Activity on Arrow - Arrows represent activities while nodes stand for events

Activity on Node - Nodes stand for events and arrows show precedence

Page 10: Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.

8-8-1010

AON and AOA Format

Figure 8-3

Figure 8-2

Page 11: Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.

8-8-1111

Constructing the Network

Begin with START activityAdd activities without precedences as

nodes– There will always be one– May be more

Add activities that have those activities as precedences

Continue

Page 12: Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.

8-8-1212

Gantt (Bar) Charts

Developed by Henry L. GanttShows planned and actual progressEasy-to-read method to know the current

status

Page 13: Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.

8-8-1313

Advantages and Disadvantage

Advantages– Easily understood– Provide a picture of the current state of a

projectDisadvantage

– Difficult to follow complex projects

Page 14: Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.

8-8-1414

Microsoft Project Gantt Chart

Figure 8-11

Page 15: Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.

8-8-1515

Microsoft Project AON Network

Figure 8-12

Page 16: Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.

8-8-1616

Solving the Network

Table 8-1

Page 17: Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.

8-8-1717

The AON Network from the previous table

Figure 8-13

Page 18: Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.

8-8-1818

Calculating Activity Times

2

22

6

6

4

ab

bmaTE

Beta Distribution

Page 19: Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.

8-8-1919

The Results

Table 8-2

Page 20: Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.

8-8-2020

Critical Path and Time

Figure 8-15

Page 21: Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.

8-8-2121

Critical Path and Time Continued

Figure 8-16

Page 22: Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.

8-8-2222

Slack

Figure 8-16

Page 23: Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.

8-8-2323

Slack Values

Table 8-3

Page 24: Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.

8-8-2424

Precedence Diagramming

Finish to startStart to startFinish to finishStart to finish

Page 25: Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.

8-8-2525

Precedence Diagramming Conventions

Figure 8-17

Page 26: Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.

8-8-2626

Microsoft Projects

Table 8-4

Page 27: Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.

8-8-2727

Gantt Chart

Figure 8-18

Page 28: Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.

8-8-2828

AON Network

Figure 8-19

Page 29: Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.

8-8-2929

Microsoft Project Calendar

Figure 8-23

Page 30: Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.

8-8-3030

Uncertainty of Project Completion Time

Assume activities are statistically independent

Variance of a set of activities is the sum of the individual variances

Interested in variances along the critical path

Page 31: Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.

8-8-3131

Example

45.52645.1745.543

22.1745.5

7

33

4350)(2

ZD

DZ