Chapter 7 Cost-Management
Transcript of Chapter 7 Cost-Management
Cost Estimating
Cost estimating and Pricing:
Cost estimating: how much will it cost the performing
organization to provide the product or service
involved?
Pricing: how much will the performing organization
charge for the product or service? Business decision.
Estimating should be done by the person doing
the work.
Cost Estimating
Based on the WBS to increase the accuracy.
Project managers should analyze the needs of
the project, to compare and reconcile any
differences with cost requirements from
management.
1. WBS
2. Resource
requirements
3. Resource rates.
4. Act. duration est.
5. Historical info.
6. Chart of accounts
7. Risks
1. Analogous est.
2. Parametric
modeling
3. Bottom-up est.
1. Cost estimates
2. Cost
management plan
Inputs Tools Outputs
Cost Estimating
Cost estimates for all resources that will be
charged to the project.
Generally expressed in units of currency to facilitate
comparisons both within and across projects.
Generally includes appropriate risk response planning.
Supporting detail must include:
Reference to WBS.
How it was developed?
Assumptions made.
Range of possible results.
Cost management plan how cost variances will
be managed.
Cost Budgeting
Allocate the overall cost estimates to individual
activities or work packages to establish a cost
baseline for measuring project performance.
1. Cost estimates
2. WBS
3. Project schedule
4. Cost
management plan
1. Cost budgeting
tools and
techniques
1. Cost baseline
Inputs Tools Outputs
Cost Budgeting
The cost baseline will be used to measure and
monitor cost performance of the project.
Expected
Cash Flow
Cost
Baseline
Cumulative
Values
Time
Estimates vs. Accuracy
Most difficult to estimate as very
little project info is available
Estimate Accuracy
Order of
Magnitude
(Early)
-25%
+75%
Budget
Estimate
-10%
+25
Definitive
Estimate
-5%
10%
Used to finalize the Request for
Authorization (RFA), and establish
commitment
Development stage estimate.
Needed to predict revised project
completion date
Tools for Estimating (and
Budgeting)
Top Down
Estimating
Accuracy depends on experience
Fast, but estimates are rough
Bottom Up
Estimating
Slow, but reliable
High cost (time) / WBS needed
Buy-in from the team
Parametric
Modeling
Mathematical models to predict costs
Two types: REGRESSION ANALYSIS,
and LEARNING CURVE
Delphi
Method
(analogous)
Expert judgment
Tasks need not to be identified
Considerable experience needed
Cost Control
Monitor Cost Performance
Detect and understand variances from plan
Ensure all changes are recorded and agreed upon
Prevent bogus changes from being included in cost baseline
Inform stakeholders of authorized changes
Bring costs within acceptable limits
Cost Control
Understand what is driving variances, good and
bad, and decide what action to take.
1. Cost Baseline
2. Performance
Reports
3. Change Requests
4. Cost
Management
Plan
1. Cost Change
Control System
2. Performance
Measurement
3. Earned Value
Management
4. Additional
Planning
5. Computerized
Tools
1. Revised Cost
Estimates
2. Budget Updates
3. Corrective Action
4. Estimate at
Completion
5. Project Closeout
6. Lessons learned
Inputs Tools Outputs
Cost Control
Work completion methods: • 0/100 Conservative approach. No work, no
money.
• 20/80 20% at start of the project, the rest when
it is completed.
• 50/50 Liberal approach.
Cost Control: Earned Value
Management Earned Value:
Integrates cost, time and scope. Used to forecast future performance and project completion dates
Key concepts:
EV = Earned Value (BCWP) Estimated value of the work actually accomplished
PV = Planned Value (BCWS) Estimated value of the work planned to be done
AC = Actual Cost (ACWP) Actual cost incurred for the work accomplished
Earned Value Management
BAC = Budget At Completion Estimated total cost of the project when done
EAC = Estimate At Completion Forecast of most likely total project cost based on
project
performance and risk quantification
CPI = Cost Performance Index Ratio of budgeted costs to actual cost
SPI = Scheduled Performance Index Estimated total cost of the project when done
Earned Value Management Key Formulas:
CV = Cost Variance = EV- AC Negative is over budget, Positive is under budget
SV = Schedule Variance = EV- PV
Negative is behind schedule, Positive is ahead schedule
CPI = Cost Performance Index = EV / AC
SPI = Schedule Performance Index = EV / PV
EAC = Estimate At Completion = BAC / CPI Most often used formula
AC + ETC
AC + BAC - EV
AC + (BAC - EV) / CPI
EAC = Estimate At Completion = EAC - AC
VAC = Variance At Completion = BAC - EAC
Cost Types
Direct Costs
Related “Directly” to the project
ex. Labor hours, material, equipment,
food, travel. . .
Indirect Costs
Overhead used for more than one project
ex. Building rent, taxes, janitorial
services
Cost Types
A cost by any other name, really isn’t the same! • Variable Cost – Changes with volume
• Fixed Cost – Stay the same, regardless of volume
COST
Volume
TC = VC+FC
VC
FC
Cost Types
Project Costs
Are incurred while the project is being fulfilled.
Life Cycle Costs
Includes the costs after project completion.
There may be temptation to lower project costs at the expense of long term costs. Life Cycle Costing gives the PM a way to consider costs outside of the scope of project fulfillment