Chapter 5: Setting Columns - Hansen Pole Buildings 5.pdf · 2021. 1. 5. · crown or bow out,...

7
Page 67 Chapter 5: Setting Columns Most Common Mistakes: 1. Overall building footprint out of square. 2. Failure to check site grade to see if longer columns are required. 3. Neglecting to install uplift plates 4. Improper column orientation in holes. 5. Placing wrong columns in wrong holes. 6. Lumber vendor ships larger dimension columns than on plans and they are used without verifying other problems may be caused (can change needed column spacing at doors, as well as overhead door jambs size and jamb trims). 7. Column rows out of alignment at grade. 8. Failure to double check column spacing before pouring concrete. Why might corner columns be smaller sized? Each building column carries a load equal to ½ distance to next column on each side! This means corner columns are carrying about ½ other column’s loads. Further, on an enclosed building, corner columns are braced in two directions by girts and wall steel (or other sidings). Why might a building have 4x6 columns, rather than 6x6? As mentioned in lumber defects section (Page 37), 4x6 lumber and 6x6 lumber are graded under different “allowable defect” categories. 4x6 material is held to much more stringent guidelines. As an example, if allowable defects from a 4x6 #2 grade, were applied to a 6x6, 6x6 would have to be graded as Select Structural. Conversely, if allowable defects from a 6x6 #2 grade were applied to a 4x6, 4x6 would be less than “utility” grade. These allowable defect characteristics follow through to design values used for structural calculations. Without getting overly technical, 4x6 #2 Fb (fiberstress in bending) value is nearly double 6x6 #2 value. A note about endwall columns: as a general rule, building plans require endwall columns to be long enough to extend to truss BOTTOM chord tops.

Transcript of Chapter 5: Setting Columns - Hansen Pole Buildings 5.pdf · 2021. 1. 5. · crown or bow out,...

Page 1: Chapter 5: Setting Columns - Hansen Pole Buildings 5.pdf · 2021. 1. 5. · crown or bow out, making for a much straighter finished wall. IMPORTANT! If glu-laminated columns have

Page 67

Chapter 5: Setting Columns

Most Common Mistakes: 1. Overall building footprint out of square. 2. Failure to check site grade to see if longer columns are required. 3. Neglecting to install uplift plates 4. Improper column orientation in holes. 5. Placing wrong columns in wrong holes. 6. Lumber vendor ships larger dimension columns than on plans and they are used without verifying other problems may be caused (can change needed column spacing at doors, as well as overhead door jambs size and jamb trims). 7. Column rows out of alignment at grade. 8. Failure to double check column spacing before pouring concrete. Why might corner columns be smaller sized? Each building column carries a load equal to ½ distance to next column on each side! This means corner columns are carrying about ½ other column’s loads. Further, on an enclosed building, corner columns are braced in two directions by girts and wall steel (or other sidings). Why might a building have 4x6 columns, rather than 6x6? As mentioned in lumber defects section (Page 37), 4x6 lumber and 6x6 lumber are graded under different “allowable defect” categories. 4x6 material is held to much more stringent guidelines. As an example, if allowable defects from a 4x6 #2 grade, were applied to a 6x6, 6x6 would have to be graded as Select Structural. Conversely, if allowable defects from a 6x6 #2 grade were applied to a 4x6, 4x6 would be less than “utility” grade. These allowable defect characteristics follow through to design values used for structural calculations. Without getting overly technical, 4x6 #2 Fb (fiberstress in bending) value is nearly double 6x6 #2 value. A note about endwall columns: as a general rule, building plans require endwall columns to be long enough to extend to truss BOTTOM chord tops.

Page 2: Chapter 5: Setting Columns - Hansen Pole Buildings 5.pdf · 2021. 1. 5. · crown or bow out, making for a much straighter finished wall. IMPORTANT! If glu-laminated columns have

Page 68

Distribute pressure treated columns to appropriate augured holes. Columns should be placed outside building, perpendicular to future wall they will become a part of, with any crown or bow up. See Figure 5-1 and Figure 5-2

Figure 5-1: Augured Holes

Figure 5-2: Column Crown Up

Page 3: Chapter 5: Setting Columns - Hansen Pole Buildings 5.pdf · 2021. 1. 5. · crown or bow out, making for a much straighter finished wall. IMPORTANT! If glu-laminated columns have

Page 69

Use duplex nails, or similar fasteners, to attach a roof purlin as a temporary support at “column depth below grade” across what will become column’s “interior face” when placed in hole. See Figure 5-3 Once stood in holes, this will allow for concrete to flow into space below each column bottom in a mono-pour.

Figure 5-3: Column Depth Below Grade

Page 4: Chapter 5: Setting Columns - Hansen Pole Buildings 5.pdf · 2021. 1. 5. · crown or bow out, making for a much straighter finished wall. IMPORTANT! If glu-laminated columns have

Page 70

Photo shows columns suspended in holes by 2x4 horizontal. Prior to placing columns in holes, remove any loose materials or debris from hole bottoms.

Page 5: Chapter 5: Setting Columns - Hansen Pole Buildings 5.pdf · 2021. 1. 5. · crown or bow out, making for a much straighter finished wall. IMPORTANT! If glu-laminated columns have

Page 71

Install uplift plates where noted on building plans. Uplift Plate™ can be installed with a framing hammer. Install with teeth towards column and plate short portion to column bottom end. Make sure teeth are completely embedded into column (see photo below).

Large diameter holes may require a rebar “X” below columns.

Next, place columns in holes so any column crown or bow is “in”. This is contrary to “stick” building stud walls and allows for column straightening in later steps. Temporarily lean towards building inside (away from string lines). If columns are other than square (4x6, 6x8, 6x10 or similar), make certain to check column layout on building plans for proper orientation. Normally (almost always) 6 inch face is towards wind (4-1/8” face for 3 ply glu-laminated columns). Starting with four corners, stand columns in place. Corner column outside to outside is equal to building dimensions. Set columns to plumb at grade, unless columns are perfectly straight (rarely) column tops should now be leaning out.

Page 6: Chapter 5: Setting Columns - Hansen Pole Buildings 5.pdf · 2021. 1. 5. · crown or bow out, making for a much straighter finished wall. IMPORTANT! If glu-laminated columns have

Page 72

Why lean columns out? Trees rarely grow as perfectly straight, so chances of getting a perfectly straight pressure treated timber are fairly small. By having columns lean out slightly, roof system can be used to pull column tops in. This will take some (and in cases all) column crown or bow out, making for a much straighter finished wall.

IMPORTANT! If glu-laminated columns have been provided - set them perfectly plumb.

Reinstall stringlines, once again moving 1-1/2 inches out from nails driven in batter board tops (splash plank width). This is same 1-1/2” from Chapter 4. As columns are set, align by setting column edges 1-1/2 inches inside string line. Remember to hold each column 1-1/2” inside string lines. Use 2x6 or larger girts (or if no walls, purlins) for temporary bracing. If brace will be over 10 feet in unsupported length, place another board 2x4 or larger on top to form a T or an L and temporarily join them with 10d duplex nails or three inch wood screws every 12 inches to prevent brace buckling in weak direction. Securely anchor brace to column (using more than a single fastener). Insure brace end away from building is firmly affixed to an immoveable stake. Consider premix truck access when placing bracing. Locate columns in holes so there is at least a four inch space between column and any hole side. In most cases lower hole portion only (usually about 1/2 to 2/3) will be filled with pre-mix concrete. This is known as a concrete collar. Determine concrete volume required: Multiply ½ hole diameter (in feet) squared, x 3.14 x concrete collar depth (in feet) times hole number, divided by 27. Like math in high school? This is what formula looks like:

(½ X hole diameter)² X 3.14 x concrete collar depth X # of holes 27

While placing extra concrete in hole will not adversely affect your building, avoid overfilling holes with concrete as excess concrete may interfere with later splash plank installation. Doubly important, for animal safety (especially in equestrian facilities), is to have concrete column encasement end below grade level.

We want to save you time, effort and money. Often all three can be saved by having local pre-mix concrete company deliver concrete for holes (even if a “short load” fee is charged), as opposed to mixing on site. If considering using “Sakrete” bags keep in mind over 60 - 60# bags make a concrete yard!

Page 7: Chapter 5: Setting Columns - Hansen Pole Buildings 5.pdf · 2021. 1. 5. · crown or bow out, making for a much straighter finished wall. IMPORTANT! If glu-laminated columns have

Page 73

After pouring concrete collars, and once concrete has firmly set, backfill area around columns (above collar) with compactable fill (can be native soil) clay or organic material free. Tamp soil firmly every six inches of fill depth, or less, to achieve a minimum 2000 psf (pounds per square foot) compaction. To compact properly, use a hand operated 4x4 eight feet in length raising it four feet and dropping four or more times on each four inch square area. Compaction proof: when a 2x4 butt end will not penetrate over 1/8” under 170# of pressure. Do not attempt to compact on or under standing water. If native soil proves inadequate, import good compactable material.

Establishing Grade

After verifying grade with a contractor’s level or transit, shoot from building center in all directions and locate grade marks on columns. Draw grade mark on each column with a pencil, parallel to ground.