Chapter 5 Job Order Costing COPYRIGHT © 2012 Nelson Education Ltd.
-
Upload
jessie-lawson -
Category
Documents
-
view
219 -
download
2
Transcript of Chapter 5 Job Order Costing COPYRIGHT © 2012 Nelson Education Ltd.
Chapter 5Job Order Costing
Chapter 5Job Order Costing
COPYRIGHT © 2012 Nelson Education Ltd.
COPYRIGHT © 2012 Nelson Education Ltd.
Learning ObjectivesLearning Objectives
1. Describe the difference between job-order costing and process costing and identify the types of firms that would use each method
2. Compute the predetermined overhead rate and use the rate to assign overhead to units or services produced
3. Identify and set up the source documents used in job-order costing
4. Describe the cost flows associated with job-order costing
5. (Appendix 5A) Prepare the journal entries associated with job-order costing
6. (Appendix 5B) Allocate support department costs to producing departments
5-2
Describe the differences between job-order
costing and identify the types of firms that would
use each method
OBJECTIVE OBJECTIVE 11
COPYRIGHT © 2012 Nelson Education Ltd.
Job-Order Production and CostingJob-Order Production and Costing
Firms operating in job-order industries produce a wide-variety of services or products that are quite
distinct from each other
Printing
5-4
Construction
Furniture making
Medical and dental services
Automobile repair
Beautician services
Example industries:
The key feature is that the cost of one job differs from that of another job and must be kept track of separately
COPYRIGHT © 2012 Nelson Education Ltd.
Process Production and CostingProcess Production and Costing
Firms in process industries mass-produce large quantities of similar or homogeneous products
5-5
Food Cement
ChemicalsPetroleum
Example industries:
The key feature is that the cost of one unit of a product is identical to the cost of another
COPYRIGHT © 2012 Nelson Education Ltd.
Production Costs in Job-Order CostingProduction Costs in Job-Order Costing
Direct materials
5-6
Direct labour
Job #1 Job #2 Job #3
Direct materials and direct labour are fairly easy to trace to individual jobs
COPYRIGHT © 2012 Nelson Education Ltd.
Production Costs in Job-Order CostingProduction Costs in Job-Order Costing
Overhead
5-7
Overhead is not so easy to trace to individual jobs
Instead overhead is applied to production
Compute the predetermined overhead rate and use the rate to assign overhead to units or services provided
OBJECTIVE OBJECTIVE 22
COPYRIGHT © 2012 Nelson Education Ltd.
Actual CostingActual Costing
5-9
Actual costs of direct materials, direct labour, and overhead are used to determine unit cost
Actual overhead can be hard to track
Problems with Actual Costing:• Many overhead costs are not incurred uniformly
through the year• Uneven production levels
– Give rise to fluctuating unit overhead costs
COPYRIGHT © 2012 Nelson Education Ltd.
Normal CostingNormal Costing
5-10
Determine unit cost by adding actual direct materials, actual direct labour,
and estimated overhead
Virtually all firms use normal costing
COPYRIGHT © 2012 Nelson Education Ltd.
Importance of Unit Costs to FirmsImportance of Unit Costs to Firms
• valuing inventory• determining income • making important decisions
For manufacturing firms, essential for:
5-11
• profitability• feasibility of introducing new services
For service firms, used to determine:
COPYRIGHT © 2012 Nelson Education Ltd.
Normal Costing and Estimating OverheadNormal Costing and Estimating Overhead
1. Calculate the predetermined overhead rate2. Apply overhead to production3. Reconcile applied overhead with actual
overhead or allocate applied overhead to WIP and finished goods ending inventories
Three step process:
5-12
COPYRIGHT © 2012 Nelson Education Ltd.
Example: Cornerstone 5-1Example: Cornerstone 5-1
Information:
5-13
At the beginning of the year, Argus Company estimated the following costs:
Overhead$360,000
Direct labour cost$720,000
Argus uses normal costing and applies overhead on the basis of direct labour cost. For the month of
February, direct labour cost was $56,000
How to Calculate the Predetermined Overhead Rate and Apply Overhead to Production
COPYRIGHT © 2012 Nelson Education Ltd.
ExampleExample
• Calculate the predetermined overhead rate for the year• Calculate the overhead applied to production in February
Required:
5-14
COPYRIGHT © 2012 Nelson Education Ltd.
Calculate the Predetermined Overhead RateCalculate the Predetermined Overhead Rate
Overhead Rate =
Estimated Annual Overhead
Formula:
5-15
Estimated Annual Activity Level
Best estimate of manufacturing-related costs, such as factory-related costs, indirect
materials, and indirect labour
Both overhead and activity level are estimated because overhead rate must be calculated at
beginning of year
COPYRIGHT © 2012 Nelson Education Ltd.
ExampleExample
Overhead rate =
Overhead
Direct labour cost
Overhead rate =
$360,000
$720,000
Overhead rate =
50% of direct labour cost
5-16
COPYRIGHT © 2012 Nelson Education Ltd.
Applying Overhead to ProductionApplying Overhead to Production
Applied overhead =
Predetermined overhead rate
Actual activity level
×
5-17
Let’s look at an exampleOverhead applied to February
production
= 50% $56,000×
Overhead Direct labour Cost
Overhead applied to February
production
= $28,000
COPYRIGHT © 2012 Nelson Education Ltd.
Reconciling Applied Overhead with Actual OverheadReconciling Applied Overhead with Actual Overhead
Example:
Proto Company had actual overhead of $400,000 for the year but had applied
$390,000 to production
5-18
COPYRIGHT © 2012 Nelson Education Ltd.
5-19
Reconciling Applied Overhead with Actual OverheadReconciling Applied Overhead with Actual Overhead
Example:
Actual Overhead Applied Overhead
$400,000 $390,000
Actual ≠ Applied This is called an overhead variance
COPYRIGHT © 2012 Nelson Education Ltd.
5-20
Actual Overhead Applied Overhead
$400,000 $390,000
Underapplied – Overhead of $10,000
Actual Overhead > Applied
Overhead = Underapplied Overhead
Actual Overhead < Applied
Overhead = Overapplied Overhead
Reconciling Applied Overhead with Actual OverheadReconciling Applied Overhead with Actual Overhead
COPYRIGHT © 2012 Nelson Education Ltd.
Disposition of Overhead VarianceDisposition of Overhead Variance
At year end, costs reported on the financial statements must be actual, not
estimated, amounts
5-21
Overhead Variance is assigned to Cost of Goods Sold
COPYRIGHT © 2012 Nelson Education Ltd.
Disposition of Overapplied OverheadDisposition of Overapplied Overhead
Actual Overhead > Applied
Overhead =Underapplied
Overhead
Actual Overhead < Applied
Overhead=
Overapplied Overhead
5-22
Underapplied overhead would be SUBTRACTED from Cost of Goods Sold
Underapplied overhead would be ADDED to Cost of Goods Sold
COPYRIGHT © 2012 Nelson Education Ltd.
How to Reconcile Actual Overhead with Applied Overhead
Example: Cornerstone 5-2Example: Cornerstone 5-2
At the beginning of the year, Argus Company estimated the following:
5-23
Information:
Overhead $360,000
Direct labour Cost$720,000
By the end of the year, actual data are:Overhead $375,400
Direct labour Cost$750,000
COPYRIGHT © 2012 Nelson Education Ltd.
ExampleExample
Information continued:Argus uses normal costing and applies overhead on the basis of direct labour cost At the end of the year, cost of goods sold (before adjusting for any overhead variance) is $632,000
5-24
• Calculate the overhead variance for the year• Dispose of the overhead variance by adjusting cost of
goods sold
Required:
COPYRIGHT © 2012 Nelson Education Ltd.
5-25
Overhead Variance CalculationOverhead Variance Calculation
Actual Overhead Applied Overhead
$375,400 $375,000
Overhead Variance – Underapplied = $400
Overhead Rate × Actual labour Cost 0.50 × $750,000
COPYRIGHT © 2012 Nelson Education Ltd.
Unadjusted COGS $632,000
Add: Underapplied variance 400
Adjusted COGS $632,400
Underapplied variances are added since not enough overhead was applied
5-26
Disposition of Overhead VarianceDisposition of Overhead Variance
COPYRIGHT © 2012 Nelson Education Ltd.
Linear Cost and Revenue Functions: Cornerstone 5-3Linear Cost and Revenue Functions: Cornerstone 5-3
Plantwide Overhead Rate
5-27
Departmental Overhead Rate
Single overhead rate calculated using all estimated overhead for a factory and dividing by estimated activity for entire plant
Estimated overhead for a department divided by estimated activity level for that same department
How To Calculate Predetermined Departmental Overhead Rates and Apply Overhead to Production
COPYRIGHT © 2012 Nelson Education Ltd.
ExampleExample
At the beginning of the year, Sorrel Company estimated:Machining
Dept.Overhead $240,000 $360,000Direct labour hours
$600,000
Information:
5-28
Assembly Dept.
Total
135,000 240,000 375,000Machine hours 200,000 --- 200,000
Sorrel uses departmental overhead rates:• Machining dept: overhead is applied on basis of machine
hours• Assembly dept: overhead is applied on basis of direct labour
hours
COPYRIGHT © 2012 Nelson Education Ltd.
ExampleExample
• Calculate the predetermined overhead rates for the machining and assembly departments
• Calculate the overhead applied to production in each department for the month of June
• By how much has each department’s overhead been overapplied? underapplied?
Required:
5-29
COPYRIGHT © 2012 Nelson Education Ltd.
Overhead RatesOverhead Rates
Machining dept. Overhead rates
Estimated overhead
Estimated machine hours=
5-30
Machining department’s overhead is applied on the basis of machine hours
Machining dept. Overhead rates =
$240,000
200,000
Machining dept. Overhead rates
$1.20 per machine hour=
COPYRIGHT © 2012 Nelson Education Ltd.
Overhead RatesOverhead Rates
Assembly dept. overhead rates
Estimated overhead
Estimated direct labour hours=
5-31
Assembly dept. overhead rates =
$360,000
240,000
Assembly dept. overhead rates
$1.50 per direct labour hour=
COPYRIGHT © 2012 Nelson Education Ltd.
ExampleExample
Sorrel Company’s actual data for June:
Machining Dept.
Overhead $22,500 $30,750
Direct labour hours
$53,250
Information continued:
5-32
Assembly Dept.
Total
11,000 20,000 31,000
Machine hours 17,000 --- 17,000
COPYRIGHT © 2012 Nelson Education Ltd.
5-33
Applying Overhead to ProductionApplying Overhead to Production
=Overhead
RateActual Machine
Hours×
Machining Department
Overhead applied in June
$1.20Overhead applied
in June = × 17,000
Overhead applied in June = $20,400
COPYRIGHT © 2012 Nelson Education Ltd.
5-34
Applying Overhead to ProductionApplying Overhead to Production
=Overhead
RateActual Direct labour Hours×
Assembly Department
Overhead applied in June
$1.50 20,000
=
×
$30,000
Overhead applied in June =
Overhead applied in June
COPYRIGHT © 2012 Nelson Education Ltd.
Under of Overapplied Overhead?Under of Overapplied Overhead?
5-35
Machining Dept.
$22,500
Assembly Dept.
Underapplied overhead
$30,750Actual overhead
Applied overhead 20,400 30,000
$2,100 $ 750
Actual overhead exceeded applied overhead in both departments
COPYRIGHT © 2012 Nelson Education Ltd.
Example: Cornerstone 5-4Example: Cornerstone 5-4
At the beginning of the year, Sorrel Company estimated:
Machining Dept.
Overhead $240,000 $360,000
Direct labour hours
$600,000
Information:
5-36
Assembly Dept. Total
135,000 240,000 375,000Machine hours 200,000 --- 200,000
Sorrel has decided to use a plant-wide overhead rate based on direct labour hours
How to Convert Departmental Data to Plantwide Data to Calculate the Overhead Rate and Apply Overhead to Production
COPYRIGHT © 2012 Nelson Education Ltd.
ExampleExample
• Calculate the predetermined plant-wide overhead rate• Calculate the overhead applied to production for the
month of June• Calculate the overhead variance for the month of June
Required:
5-37
COPYRIGHT © 2012 Nelson Education Ltd.
Plantwide Overhead RatePlantwide Overhead Rate
Plantwide overhead rate
Total overhead
Direct labour Hours=
5-38
Plantwide overhead rate =
$600,000
375,000
Plantwide overhead rate
$1.60 per direct labour hour
=
Total Estimated Overhead
COPYRIGHT © 2012 Nelson Education Ltd.
ExampleExample
Sorrel Company’s actual data June:
Machining Dept.
Overhead $22,500 $30,750
Direct labour hours
$53,250
Information continued:
5-39
Assembly Dept.
Total
11,000 20,000 31,000
Machine hours 17,000 --- 17,000
COPYRIGHT © 2012 Nelson Education Ltd.
5-40
Applying Overhead to ProductionApplying Overhead to Production
=Plantwide
overhead rateActual activity
level
$1.60
×
Formula:
Applied Overhead
31,000 direct labour hours
=
×
$49,600
Applied Overhead =
Applied Overhead
Actual direct labour hours for June:Machining 11,000 + Assembly 20,000 hours
COPYRIGHT © 2012 Nelson Education Ltd.
Over or Underapplied Overhead?Over or Underapplied Overhead?
5-41
Applied OverheadActual Overhead -
$53,250 - $49,600
$3,650
Underapplied
Not enough overhead was applied to production
COPYRIGHT © 2012 Nelson Education Ltd.
Unit Costs in the Job-Order SystemUnit Costs in the Job-Order System
• materials used on the job (direct materials)• labour worked on the job (direct labour)• applied overhead
5-42
Unit cost of a job is the total cost of:
Identify and set up the source documents used in
job-order costing
OBJECTIVE OBJECTIVE 33
COPYRIGHT © 2012 Nelson Education Ltd.
Job-Order Cost SheetJob-Order Cost Sheet
• Contains:– Job description– Cost of materials, labour, and overhead
• Jobs are named or numbered• Total of all unfinished job-order cost sheets
should equal the ending balance of the Work In Process account
5-44
COPYRIGHT © 2012 Nelson Education Ltd.
Materials Requisition FormMaterials Requisition Form
• Provides information for assigning direct materials costs to jobs
• Useful for maintaining proper control over a firm’s inventory of direct materials
5-45
COPYRIGHT © 2012 Nelson Education Ltd.
Job Time TicketsJob Time Tickets
• Employees fill out a time ticket that identifies:– His or her name– Wage rate– Hours worked on each job
• Cost accounting department posts cost of direct labour to individual jobs
5-46
COPYRIGHT © 2012 Nelson Education Ltd.
Source Documents as Sources for Account BalancesSource Documents as Sources for Account Balances
5-47
Work in Process
Finished Goods
Cost of Goods Sold
Total of all job-order cost sheets for unfinished jobs
Total of all job-order cost sheets for finished but unsold jobs
Total of all job-order cost sheets for sold jobs
Describe the cost flows associated with
job-order costing
OBJECTIVE OBJECTIVE 44
COPYRIGHT © 2012 Nelson Education Ltd.
Accounting for MaterialsAccounting for Materials
5-49
• Purchases are added to Raw Materials Inventory account
• As they are used in production, direct materials are moved from Raw Materials to Work in Process
◦ Materials used in production are classified by job and recorded in job-order cost sheets
Raw Materials
Purchases Direct Materials used in production
COPYRIGHT © 2012 Nelson Education Ltd.
Accounting for Direct Labour CostAccounting for Direct Labour Cost
5-50
• Time tickets indicate the amount of labour spent on each job
• Labour costs are added to job-order costs sheets
• Total of all direct labour from all jobs is recorded as a debit in the Work In Process account
Work In Process
Direct materials
Direct labour
COPYRIGHT © 2012 Nelson Education Ltd.
Accounting for OverheadAccounting for Overhead
5-51
• Normal costing is used
• Actual overhead is not assigned directly to jobs
• Overhead is applied to each job using a predetermined rate Applied
Overhead
Work In Process
Direct Materials
Direct labour
COPYRIGHT © 2012 Nelson Education Ltd.
Accounting for Actual Overhead CostsAccounting for Actual Overhead Costs
• Never enters Work in Process account• Costs are recorded as debits in
Manufacturing Overhead control account• At end of period, actual overhead is
reconciled with applied overhead
5-52
COPYRIGHT © 2012 Nelson Education Ltd.
Accounting for Finished GoodsAccounting for Finished Goods
5-53
Costs of completed jobs are transferred from Work in Process to Finished Goods
Work in Process
Direct Materials
Direct labour
Applied Overhead
Finished Goods
Completed jobs
Completed jobs
COPYRIGHT © 2012 Nelson Education Ltd.
Accounting for Actual Overhead CostsAccounting for Actual Overhead Costs
5-54
Once job is sold, it is added to cost of goods sold which is reported on income statement
Finished Goods
Completed jobs
Cost of Goods Sold
Sold jobsSold jobs
COPYRIGHT © 2012 Nelson Education Ltd.
Cost of Goods Manufactured StatementCost of Goods Manufactured Statement
5-55
To ensure the accuracy in computing these costs, a cost of goods
manufactured statement is prepared
COPYRIGHT © 2012 Nelson Education Ltd.
Accounting for Cost of Goods SoldAccounting for Cost of Goods Sold
• When jobs are sold: – finished goods inventory is decreased– costs of goods sold is increased
• The selling price is recognized by:– increasing (crediting) sales revenue – increasing (debiting) accounts receivable (or cash)
5-56
COPYRIGHT © 2012 Nelson Education Ltd.
Normal and Adjusted Cost of Goods SoldNormal and Adjusted Cost of Goods Sold
5-57
Normal Cost of Goods Sold
Adjusted Cost of Goods Sold
Cost of Goods Sold before an adjustment for an overhead variance
Cost of Goods Sold after adjusting for an overhead variance
COPYRIGHT © 2012 Nelson Education Ltd.
Example: Cornerstone 5-5Example: Cornerstone 5-5
5-58
Job 78
At the beginning of June, Galway Company had two jobs in process:
Job 79
Direct materials
Direct labour
$1,000
Applied overhead
$ 800
600 1,000750
Balance, June 1 $2,350
1,250
$3,050
Information:
How to Prepare Brief Job-Order Cost Sheets
COPYRIGHT © 2012 Nelson Education Ltd.
ExampleExample
• Calculate the overhead rate based on direct labour cost• Prepare a job-order cost sheet for the four jobs
– Show the balance as of June 1 as well as direct materials and direct labour added in June
– Apply overhead to the four jobs for the month of June, and show the ending balances
• Calculate the ending balances of Work in Process and Finished Goods and of June 30
• Calculate the Cost of Goods Sold for June
Required:
5-59
COPYRIGHT © 2012 Nelson Education Ltd.
Calculating Overhead RateCalculating Overhead Rate
5-60
Actual activity level
Predetermined overhead rate
=
We were not given estimated overhead or estimated direct labour cost. So we will have to
work backwards to find the rate
We can compute the rate using the information from Job 78
Applied Overhead
×
COPYRIGHT © 2012 Nelson Education Ltd.
Calculating Overhead RateCalculating Overhead Rate
5-61
Actual activity level
Predetermined overhead rate
=Applied
Overhead×
$750 =Predetermined overhead rate × $600
$750/$600 =Predetermined overhead rate
1.25 or 125% of direct labour cost
COPYRIGHT © 2012 Nelson Education Ltd.
ExampleExample
5-62
Job 78
During June, two more jobs were started
The following direct materials and direct labour costs were added to the four jobs during the month of June:
Job 79
Direct materials
Direct labour
$500 $1,110
400 1,400
$900 $100
Job 80 Job 81
2,000 320
Information:
COPYRIGHT © 2012 Nelson Education Ltd.
Job-Order Cost SheetsJob-Order Cost Sheets
5-63
Job 78 Job 79
Direct materials
Direct labour
$2,350 $3,050
400
$ 0 $ 0
Job 80 Job 81
2,000
Beg. Bal. June 1
500
Applied overhead 500
1,400
1,110 900 100
320
Direct labour x Overhead Rate
$400 x $1.25 Direct labour x Overhead Rate $1,400
x $1.25
1,750
Direct labour x Overhead Rate $2,000 x $1.25
2,500
Direct labour x Overhead Rate
$320 x $1.25
400
COPYRIGHT © 2012 Nelson Education Ltd.
Job-Order Cost SheetsJob-Order Cost Sheets
5-64
Job 78 Job 79
Direct Materials
Direct labour
$2,350 $3,050
400
$ 0 $ 0
Job 80 Job 81
2,000
Beg. Bal. June 1
500
Applied Overhead 500
1,400
1,110 900 100
320
1,750 2,500 400
Total, June 30 $3,750 $7,310 $5,400 $820
COPYRIGHT © 2012 Nelson Education Ltd.
Computing Ending BalancesComputing Ending Balances
5-65
At the end of June,
Jobs 78, 79 and 80 were completed
Only Job 81 was still in process at June 30
Work in Process = $820
Work in Process
COPYRIGHT © 2012 Nelson Education Ltd.
Computing Ending BalancesComputing Ending Balances
5-66
Finished Goods
On June 1, the balance in Finished Goods was zero. Three jobs were finished during June (Jobs 78, 79 & 80)
Job 79 was sold and transferred out of Finished Goods
Finished goods, June 1
Job 78
Job 80
Finished goods, June 30
$ 0
3,750
5,400
$9,150
COPYRIGHT © 2012 Nelson Education Ltd.
Computing Ending BalancesComputing Ending Balances
5-67
One job, Job 79, was sold during June
June 30 Balance = $7,310
Cost of Goods Sold
COPYRIGHT © 2012 Nelson Education Ltd.
Accounting for Nonmanufacturing CostsAccounting for Nonmanufacturing Costs• Manufacturing costs are not the only costs
incurred by a firm• Selling and general administrative are period
costs• Period costs are shown on the Income
Statement
5-68