CHAPTER 3 Process Costing. Difference Between Job-Order and Process Costing Systems Job-Order...
-
Upload
joseph-turner -
Category
Documents
-
view
239 -
download
1
description
Transcript of CHAPTER 3 Process Costing. Difference Between Job-Order and Process Costing Systems Job-Order...
![Page 1: CHAPTER 3 Process Costing. Difference Between Job-Order and Process Costing Systems Job-Order Costing Each unique product or batch is considered a job.](https://reader034.fdocuments.in/reader034/viewer/2022050807/5a4d1b767f8b9ab0599b71f8/html5/thumbnails/1.jpg)
CHAPTER 3CHAPTER 3
Process CostingProcess Costing
![Page 2: CHAPTER 3 Process Costing. Difference Between Job-Order and Process Costing Systems Job-Order Costing Each unique product or batch is considered a job.](https://reader034.fdocuments.in/reader034/viewer/2022050807/5a4d1b767f8b9ab0599b71f8/html5/thumbnails/2.jpg)
Difference Between Job-Order Difference Between Job-Order and Process Costing Systemsand Process Costing Systems
Job-Order Costing Each unique product or batch is considered
a job Manufacturing costs are traced to specific
jobs
Process Costing Used when homogenous items are produced Total costs are divided by total units
produced
![Page 3: CHAPTER 3 Process Costing. Difference Between Job-Order and Process Costing Systems Job-Order Costing Each unique product or batch is considered a job.](https://reader034.fdocuments.in/reader034/viewer/2022050807/5a4d1b767f8b9ab0599b71f8/html5/thumbnails/3.jpg)
Process Costing ExampleProcess Costing Example
![Page 4: CHAPTER 3 Process Costing. Difference Between Job-Order and Process Costing Systems Job-Order Costing Each unique product or batch is considered a job.](https://reader034.fdocuments.in/reader034/viewer/2022050807/5a4d1b767f8b9ab0599b71f8/html5/thumbnails/4.jpg)
Job-Order Costing SystemJob-Order Costing System
![Page 5: CHAPTER 3 Process Costing. Difference Between Job-Order and Process Costing Systems Job-Order Costing Each unique product or batch is considered a job.](https://reader034.fdocuments.in/reader034/viewer/2022050807/5a4d1b767f8b9ab0599b71f8/html5/thumbnails/5.jpg)
Process Costing SystemProcess Costing System
![Page 6: CHAPTER 3 Process Costing. Difference Between Job-Order and Process Costing Systems Job-Order Costing Each unique product or batch is considered a job.](https://reader034.fdocuments.in/reader034/viewer/2022050807/5a4d1b767f8b9ab0599b71f8/html5/thumbnails/6.jpg)
Product and Cost FlowsProduct and Cost FlowsProduct Flows Through Departments A product typically passes through
multiple departments Conversion Costs (Labor and
Overhead)
![Page 7: CHAPTER 3 Process Costing. Difference Between Job-Order and Process Costing Systems Job-Order Costing Each unique product or batch is considered a job.](https://reader034.fdocuments.in/reader034/viewer/2022050807/5a4d1b767f8b9ab0599b71f8/html5/thumbnails/7.jpg)
Product and Cost FlowsProduct and Cost FlowsCost Flows Through Accounts Direct Material
Direct Labor
Manufacturing Overhead
Transferred-in Cost
![Page 8: CHAPTER 3 Process Costing. Difference Between Job-Order and Process Costing Systems Job-Order Costing Each unique product or batch is considered a job.](https://reader034.fdocuments.in/reader034/viewer/2022050807/5a4d1b767f8b9ab0599b71f8/html5/thumbnails/8.jpg)
Flow of Cost Between Flow of Cost Between Processing DepartmentsProcessing Departments
![Page 9: CHAPTER 3 Process Costing. Difference Between Job-Order and Process Costing Systems Job-Order Costing Each unique product or batch is considered a job.](https://reader034.fdocuments.in/reader034/viewer/2022050807/5a4d1b767f8b9ab0599b71f8/html5/thumbnails/9.jpg)
Study Break #1Study Break #1Which one(s) of the following characteristics are associated with a process costing system?a. Heterogeneous productsb. Homogeneous productsc. Continuous productiond. Discontinuous productione. Costs are traced to jobsf. Costs are traced to processing
departments
Answer:b, c, and f
![Page 10: CHAPTER 3 Process Costing. Difference Between Job-Order and Process Costing Systems Job-Order Costing Each unique product or batch is considered a job.](https://reader034.fdocuments.in/reader034/viewer/2022050807/5a4d1b767f8b9ab0599b71f8/html5/thumbnails/10.jpg)
Study Break #2Study Break #2The best example of a business requiring a process costing system would be a(n):a. Custom cabinet shopb. Antique furniture restorerc. Soap manufacturerd. Automobile repair shop
Answer:c. Soap manufacturer
![Page 11: CHAPTER 3 Process Costing. Difference Between Job-Order and Process Costing Systems Job-Order Costing Each unique product or batch is considered a job.](https://reader034.fdocuments.in/reader034/viewer/2022050807/5a4d1b767f8b9ab0599b71f8/html5/thumbnails/11.jpg)
Study Break #3Study Break #3The costs in a process cost system are traced to:
a. Specific jobsb. Specific customersc. Specific company administratorsd. Specific production departments
Answer:d. Specific production departments
![Page 12: CHAPTER 3 Process Costing. Difference Between Job-Order and Process Costing Systems Job-Order Costing Each unique product or batch is considered a job.](https://reader034.fdocuments.in/reader034/viewer/2022050807/5a4d1b767f8b9ab0599b71f8/html5/thumbnails/12.jpg)
Calculating Unit CostCalculating Unit CostEquivalent Units Partially completed units are
converted to a comparable number of completed units
![Page 13: CHAPTER 3 Process Costing. Difference Between Job-Order and Process Costing Systems Job-Order Costing Each unique product or batch is considered a job.](https://reader034.fdocuments.in/reader034/viewer/2022050807/5a4d1b767f8b9ab0599b71f8/html5/thumbnails/13.jpg)
Equivalent units – Material Equivalent units – Material and Converision costsand Converision costs
![Page 14: CHAPTER 3 Process Costing. Difference Between Job-Order and Process Costing Systems Job-Order Costing Each unique product or batch is considered a job.](https://reader034.fdocuments.in/reader034/viewer/2022050807/5a4d1b767f8b9ab0599b71f8/html5/thumbnails/14.jpg)
Example Exercise #1Example Exercise #1McMillian Tire Company produces tires used on small trailers. The month of June ended with 300 tires in process, 85% complete as to direct materials and 50% complete as to conversion costs; 2,500 tires were transferred to finished goods during the month and 2,300 were started during the month. The beginning WIP inventory was 65% complete as the direct materials and 45% complete as to conversion costs.
1. Determine the denominators to be used in the calculations of cost per equivalent unit for materials and conversion costs.
![Page 15: CHAPTER 3 Process Costing. Difference Between Job-Order and Process Costing Systems Job-Order Costing Each unique product or batch is considered a job.](https://reader034.fdocuments.in/reader034/viewer/2022050807/5a4d1b767f8b9ab0599b71f8/html5/thumbnails/15.jpg)
Example Exercise #1 Example Exercise #1 SolutionSolution
Materials Units completed 2,500 Equivalent units (300*85%) 255
2,755 units
Labor Units completed 2,500 Equivalent units (300*50%) 150
2,650 units
![Page 16: CHAPTER 3 Process Costing. Difference Between Job-Order and Process Costing Systems Job-Order Costing Each unique product or batch is considered a job.](https://reader034.fdocuments.in/reader034/viewer/2022050807/5a4d1b767f8b9ab0599b71f8/html5/thumbnails/16.jpg)
Calculating Unit CostCalculating Unit CostCost Per Equivalent Unit Average unit cost
Formula
Cost in Beginning WIP + Cost incurred in current period
Units completed + Equivalent units in Ending WIP
![Page 17: CHAPTER 3 Process Costing. Difference Between Job-Order and Process Costing Systems Job-Order Costing Each unique product or batch is considered a job.](https://reader034.fdocuments.in/reader034/viewer/2022050807/5a4d1b767f8b9ab0599b71f8/html5/thumbnails/17.jpg)
Example Exercise #2Example Exercise #2The balance in beginning WIP at Bing Rubber Company for direct labor was $135,000. During the month of March, an additional $650,000 of direct labor was incurred, and 25,000 pounds of rubber were produced. At the end of March, 8,000 pounds of rubber were in process and the units were 50% complete. At the start of March, the company had 5,000 pounds of rubber that were 30% complete.
1. Calculate the cost per equivalent unit for labor assuming that labor is added uniformly throughout the production process.
![Page 18: CHAPTER 3 Process Costing. Difference Between Job-Order and Process Costing Systems Job-Order Costing Each unique product or batch is considered a job.](https://reader034.fdocuments.in/reader034/viewer/2022050807/5a4d1b767f8b9ab0599b71f8/html5/thumbnails/18.jpg)
Example Exercise #2 Example Exercise #2 SolutionSolution
Direct Labor Beginning WIP $135,000 March labor $650,000 Total Labor Cost $785,000
Units Units completed 25,000 Equivalent units (8,000*50%) 4,000 Total Units 29,000
Cost per Equivalent Unit $785,000 / 29,000 pounds = $27.07 per
pound
![Page 19: CHAPTER 3 Process Costing. Difference Between Job-Order and Process Costing Systems Job-Order Costing Each unique product or batch is considered a job.](https://reader034.fdocuments.in/reader034/viewer/2022050807/5a4d1b767f8b9ab0599b71f8/html5/thumbnails/19.jpg)
Production Cost ReportProduction Cost Report Reconciliation of Units
Reconciliation of Costs
Details of Cost per Equivalent Unit Calculations
![Page 20: CHAPTER 3 Process Costing. Difference Between Job-Order and Process Costing Systems Job-Order Costing Each unique product or batch is considered a job.](https://reader034.fdocuments.in/reader034/viewer/2022050807/5a4d1b767f8b9ab0599b71f8/html5/thumbnails/20.jpg)
Reconciliation of UnitsReconciliation of Units
![Page 21: CHAPTER 3 Process Costing. Difference Between Job-Order and Process Costing Systems Job-Order Costing Each unique product or batch is considered a job.](https://reader034.fdocuments.in/reader034/viewer/2022050807/5a4d1b767f8b9ab0599b71f8/html5/thumbnails/21.jpg)
Reconciliation of CostsReconciliation of Costs
![Page 22: CHAPTER 3 Process Costing. Difference Between Job-Order and Process Costing Systems Job-Order Costing Each unique product or batch is considered a job.](https://reader034.fdocuments.in/reader034/viewer/2022050807/5a4d1b767f8b9ab0599b71f8/html5/thumbnails/22.jpg)
Basic Steps in Process Basic Steps in Process CostingCosting
Account for the number of physical units
Calculate the cost per equivalent unit for materials, labor, and overhead
Assign cost to items completed and items in ending Work in Process
Account for the amount of product cost
![Page 23: CHAPTER 3 Process Costing. Difference Between Job-Order and Process Costing Systems Job-Order Costing Each unique product or batch is considered a job.](https://reader034.fdocuments.in/reader034/viewer/2022050807/5a4d1b767f8b9ab0599b71f8/html5/thumbnails/23.jpg)
Dealing with Transferred-In Dealing with Transferred-In CostCost
Process Costing Systems generally use multiple processes
Items completed in one processing department, costs are transferred to the next department
When units are completed in the final process, the costs are transferred to finished goods
![Page 24: CHAPTER 3 Process Costing. Difference Between Job-Order and Process Costing Systems Job-Order Costing Each unique product or batch is considered a job.](https://reader034.fdocuments.in/reader034/viewer/2022050807/5a4d1b767f8b9ab0599b71f8/html5/thumbnails/24.jpg)
Process Costing and Process Costing and Incremental AnalysisIncremental Analysis
Incremental Analysis Compare change in revenue with
change in cost
Process Costing Utilizes an average of fixed and
variable costs Could impact decision making when
considering additional production
![Page 25: CHAPTER 3 Process Costing. Difference Between Job-Order and Process Costing Systems Job-Order Costing Each unique product or batch is considered a job.](https://reader034.fdocuments.in/reader034/viewer/2022050807/5a4d1b767f8b9ab0599b71f8/html5/thumbnails/25.jpg)
Full and Incremental CostFull and Incremental Cost