Part 1 Marketing Channel Systems. Chapter 1 Marketing Channel Concepts.
Channel 13 (1)
Transcript of Channel 13 (1)
-
8/11/2019 Channel 13 (1)
1/12
Hydraulic (BFC 21103)
Section 4
Channel 13
Guided By:
Mohd Adib Bin Mohammad
Group Members:
Ong Men Jie AF120197Soon Chi Kang AF120178
Tan Kai Siu AF120194
Tang Wai Seng AF120196
Yap Hong Eit AF120189
-
8/11/2019 Channel 13 (1)
2/12
ContentsIntroduction .................................................................................................................................................. 3
Study Area ..................................................................................................................................................... 4
Method and Equipment ................................................................................................................................ 5
Determined the Longitudinal Slope of Channel 13 ................................................................................... 5
Determined the Velocity of Water Flowing in Channel 13 ....................................................................... 6
Determined the Area of Channel 13 ......................................................................................................... 6
Velocity and Discharge of Flow ..................................................................................................................... 8
Conclusion ................................................................................................................................................... 11
Reference .................................................................................................................................................... 12
-
8/11/2019 Channel 13 (1)
3/12
Introduction
-
8/11/2019 Channel 13 (1)
4/12
Study Area
-
8/11/2019 Channel 13 (1)
5/12
Method and Equipment
Determined the Longitudinal Slope of Channel 13
The longitudinal slope of the channel was determined by water level method using a
transparent hollow tube. A water level is a device used for matching elevations of locationsthat are too far apart for aspirit level to span. The procedures include:
Filled the pipe with water till nearly full.
Hold both ends vertically and taps the pipe gently to expel those entrapped air. Then holdthe ends of the tube even with one another, and verify that the water lines up equally.If it
does, you are ready to go. If it does not, you need to continue tapping the tube, as it's
likely that air bubbles are still trapped.
A mark is marked a few centimeters away from both ends to act a guideline when
measuring the slope of the channel. The ends are held vertical, and the rest of the tubing lies on the ground or floor as in
figure below.
The H1 (height of water for one side of the pipe), H2 (height of water for the other side of
the pipe)and L (the length between two mark) for the upstream, middle and downstream
of the channel were measured using a ruler and average was taken. From the average
value, the slope can be calculate using the formula below:
http://en.wikipedia.org/wiki/Spirit_levelhttp://en.wikipedia.org/wiki/Spirit_level -
8/11/2019 Channel 13 (1)
6/12
Determined the Velocity of Water Flowing in Channel 13
The velocity of the water flowing in the channel was determined by:
Poured the water to the channel and allow it to flow.
Once the flow is constant, placed a floating object on upstream of the channel and
allowed it to transit to downstream.
The time taken for the object to flow from upstream to the downstream was recorded.
These processes were repeated several times to obtained higher accuracy data.
The velocity of flow can be calculate using the formula below:
Determined the Area of Channel 13
By using AutoCAD, we can determine the variables for partial circle at bottom of the channel
(circular) and the upper part of the channel (rectangular). Thus, we can determine the area for the
drainage.
-
8/11/2019 Channel 13 (1)
7/12
The area of channel can be calculated using the formula below:
Total Area = Area of A + Area of B
= (T x Y) +
Where T is the top width of rectangular section
Y is the height of rectangular section
D is the diameter of circular section
is the center angle in radian =
Sin is the trigonometry sine function
-
8/11/2019 Channel 13 (1)
8/12
Velocity and Discharge of Flow
1. Calculate the longitudinal slope of channel, s0
From the water level result obtained, h1=14.4 while h2=13.3, therefore the difference in
height h is
From the measurement obtained L= 264 cm
Thus the longitudinal slope can be calculated using the formula below:
2. Calculate the velocity of flow in the channel, v
The velocity can be calculated using the formula below:
Distance travel was set as 1m and the times recorded were 3.58 seconds.
Therefor velocity,
-
8/11/2019 Channel 13 (1)
9/12
3. Calculate the area of channel, A
The area of the channel is:
Thus,
4.
Calculate the wetted perimeter of channel, P
The wetter perimeter equal to:
5. Determine the Manning roughness coefficient , n
The Manning Roughness Coefficient value can be determined from the Table 1: Value of
Manning roughness coefficient, n (Chow, 1959).
According to the characteristic of the channel, which is (1) lined or built-up channel with
(2) nonmetal and (3) made form concrete at the bottom float finished with (4) sides of
random stone in mortar, it manning roughness coefficient is 0.020.
-
8/11/2019 Channel 13 (1)
10/12
6. Determine the Hydraulic Radius, R
The hydraulic radius can be calculated using the formula below:
7. Calculate the rate of flow, V
The rate of flow, Q can be calculated using the formula below:
n = 0.020
A = 426.80cm2= 426.80 x 10
-4m
2
R = 7.86 cm = 7.86 x 10-2
m
So= 1/240
( )
8. Calculate the rate of flow, Q
The rate of flow can be calculated using the formula as shown below:
-
8/11/2019 Channel 13 (1)
11/12
Conclusion
-
8/11/2019 Channel 13 (1)
12/12
Reference1.
Gary P. Merkley. (2014). Channel Cross Sections. Retrieved 23 May 2014, from
http://ocw.usu.edu/Biological_and_Irrigation_Engineering/Irrigation___Conveyance_Control_Sy
stems/6300__L16_ChannelCrossSections.pdf
2.