Bounded Rationality in Rules of Price Adjustment and the ...
Changes to Price Adjustment Provisions Division of Construction Management.
-
Upload
dylan-burbidge -
Category
Documents
-
view
229 -
download
5
Transcript of Changes to Price Adjustment Provisions Division of Construction Management.
3
Bid Indices - What we said in 2009.
• Bituminous Price Adjustment – Continue Use– Current (2009 & Prior)
• C&MS Section 401.20 (Standard Specification Language)• Used in all contracts to adjust the price of liquid asphalt for
all asphalt concrete products based on the PG binder type.
– Proposed Changes (2010)• Use on multi-season projects only.• Change to a PN from the Standard Specification.• Use a single PG grade as the basis for adjustment, PG 64-
22.• Use a single independent reporting source for the index
values such as Asphalt Weekly Monitor.• Change the trigger to 10%.
2010 Conaway Conference
4
Bituminous Price Adjustment - what we did
• Index Changes:– Removed as standard
specification 401.20– Using on contract-by-contract
basis (PN 530 and PN 535)– Using one binder type for all
price adjustments– Using AWM to establish index– Current month’s index available
at beginning of next month
2010 Conaway Conference
5
Remove from Specifications
• Removed specification 401.20 and apply on contract-by-contract basis
• Basis - FHWA Guidance TA 5080.3:
– Price adjustment clauses should not be standard specifications
– Can be applied on a project-by-project basis based on assessment of need
2010 Conaway Conference
6
Use One Binder Type
• Using one binder grade for index, PG64-22
• Basis - Using one index based on one PG binder is the most common method
– 33 states use only one price adjustment index
– Only Alabama determines indexes for all PG binder grades used
2010 Conaway Conference
7
Use Published Binder Pricing
• Using AWM to establish binder price index
• Basis - FHWA Guidance TA 5080.3:– Index must not be “susceptible to
manipulation”
2010 Conaway Conference
8
Increase Trigger
• Increased triggers– 15% on single season projects– 10% on multi season projects
• Basis- FHWA Guidance TA 5080.3:– Price adjustment to be triggered by
“significant change”
2010 Conaway Conference
9
ODOT Continues to Evaluate HMA Prices
2010 Conaway Conference
$- $100.00 $200.00 $300.00 $400.00 $500.00 $600.00 $700.00 $800.00
$10
5.62
$12
6.35
$11
2.78
$12
0.65
$13
1.98
$11
3.63
$15
5.58
$16
1.42
$13
5.50
$20
4.11
$22
4.78
$18
1.26
$17
3.17
$26
1.11
$422.92 $422.92 $422.92 $422.92 $422.92 $422.92 $422.92
$603.60 $603.60 $603.60 $603.60
$756.08 $756.08 $756.08
Average HMA Awarded Unit CostsOld Index vs. New Index
AVE Unit Award Price w/PN530 or PN 535 (10/9/09 - 1/14/10) AVE Unit Award Price (10/8/08 - 1/14/09)
AVE Asphalt Price Index - "New" (10/09 - 1/10) AVE Asphalt Price Index "Old" (9/08- 12/08)
11
Bid Indices - What we said in 2009.
• Steel Price Adjustment – Continue use
– Revise the Index Source to more closely reflect steel pricing for products used in transportation projects.
– Change Designer Note to reflect use on multi-season projects only
2010 Conaway Conference
2010 Conaway Conference
Previous SPA Commodity Table
12
Product Relationship Table B-1
Steel Product (Title)
AMM Product Designation (CB)
USDOL-BLS PPI (MI, BI)
Steel Piling and stay in-place steel casing Structural Steel Structural Steel Expansion/ Contraction Joints Steel Bearing Devices Guardrail Steel Traffic Strain Poles, Supports, and Mast Arms Steel Light Towers, Poles, and Mast Arms Sign Ground Mounted Beam Supports, Rigid Overhead Supports, and Span Wire Supports Steel Railing Corrugated Steel Pipe
Steel Plate, Cut-to-length (National Mills)
Average of,
Metals and Metal
Products (WPU10),
Iron and Steel (WPU101),
and Steel Mill
Products (WPU1017) Prestress and Post tensioning strand
Steel – Rod, high carbon (1050) industrial quality (United States)
Reinforcing Steel Steel – Bar, Merchant Products, Reinforcing Bar (United States)
13
Steel Price Adjustment – What we did
Reduced the list of eligible steel commodities and revised the index sources:
2010 Conaway Conference
Product Relationship Table B-1
Steel Product (Title)
BI, MI
Category 1: Structural Steel Members, Levels UF, 1, 2, and 3 Steel H-Piling
Average of lowest and highest 27” to 36” tall, 10”-12” wide flange beams, up
to 256 lbs./ft., prices plus scrap surcharge from Nucor-Yamato, SDI,
and Gerdau Ameristeel Category 2: Structural Steel Members, Levels 4, 5, and 6 Stay in-place steel casing (Piling & Caissons)
AMM Product Designation: Steel Plate, Cut-to-length
(National Mills)
14
Steel Price Adjustment – What we did
For Category 1, Table B-1:
The adjustment indices shall determine the BI and MI values for wide flange beams plus a scrap surcharge as listed.
• Link: http://www.stld-cci.com/pdf/Price_list.pdf
• Link: http://www.gerdauameristeel.com/products/mp/pl.cfm
• Link: http://www.nucoryamato.com/
For Category 2, Table B-1:
The Department will post monthly data obtained from the American Metal Market (AMM). The adjustment index (MI, BI) determines the adjustment ratio and the BI determines the raw steel material price for Steel Plate, Cut-to-length as reported for National Mills at the time of bid.
2010 Conaway Conference
15
Steel Price Adjustment – What we did
New Designer Note:• For use on all projects expected to be
constructed over a time period of more than one year AND that require steel products listed in Table B-1 of the proposal note.
Old Designer Note:• For use on all projects that require steel of
the types listed in the note.
2010 Conaway Conference
17
Bid Indices - What we said in 2009.
• Fuel Price Adjustment – Continue Use
– Change Designer Note to reflect use on multi-season projects only
2010 Conaway Conference
18
• Added the following items to the FPA:
– Select Granular Backfill, Item 840; 0.75 gal./c.y.
– Rigid Bases and Pavements, Item 888; 1 gal./c.y.
2010 Conaway Conference
Fuel Price Adjustment – What we did
2010 Conaway Conference
Fuel Price Adjustment – What we did
19
Current Designer Note:
This note is to be used on all projects that contain any of the categories of work listed in Table A-1 of this proposal note. Questions regarding this note should be directed to the Office of Construction Administration at 614-387-2173.
No change to date.
Proposed Index Posting Changes
Index Type
Current Index Cut-off Date
Current Index
Effective Month
Proposed Index Cut-off
Date
Proposed Index
Effective Month
Posting Month
AsphaltPN 530/535
Last Wednesday of the month(i.e. Jan. 27, 2010)
Month of Index Date(i.e. Jan. 2010)
No change
No change
Month following Index (i.e. Feb. 2010)
Steel (AMM)PN 525
Last Wednesday of the month(i.e. Jan. 27, 2010)
Month following Index Date(i.e. Feb. 2010)
No change
Change to Month of Index Date(i.e. Jan. 2010)
Month following Index (i.e. Feb. 2010)
Steel (Mill Data)PN 525
Last Wednesday of the month(i.e. Jan. 27, 2010)
Month of Index Date(i.e. Jan. 2010)
No change
No change
Month following Index (i.e. Feb. 2010)
FuelPN 520
Last day of the Month(i.e. Jan. 2010)
Month of Index Date(i.e. Jan. 2010)
No change
No change
Month following Index (i.e. Feb. 2010)2010 Conaway Conference 21
Proposed SPA (PN 525) Changes
• Editorial Changes.– Correct the equations as follows
• SPA = [(MI/BI) – 0.90] x BI x Q or• SPA = [(MI/BI) – 1.10] x BI x Q
For Category 1, Table B-1:The Department will post monthly adjustment indices (BI and MI) for wide flange steel beams plus a scrap surcharge using data obtained from the steel producers listed.
2010 Conaway Conference 22
Proposed SPA (PN 525) Changes
2) Identification of the steel product subject to adjustment.
a. Documentation package number: PN525 – (Insert the steel product “title” from Table B-1) – (Insert sequential package number beginning with “1”). Example: PN525 – Steel Piling– 1, PN 525 – Structural Steel – 2, etc…
2010 Conaway Conference 23
Proposed SPA (PN 525) Changes
For Category 2, Table B-1:The Department will post monthly adjustment indices (BI and MI) for steel using data obtained on the last Wednesday of the month from the American Metal Market (AMM), based on the price for Steel Plate, Cut-to-length as reported for National Mills.
2010 Conaway Conference 24
Proposed SPA (PN 525) Changes
• MI = Mill Shipping Index. - Use the adjustment indices from the month the steel was shipped from the producing mill and properly documented. The adjustment indices will be posted on ODOT’s website.
• BI = Bidding Index. - Use the adjustment indices from the month proceeding the month in which the project is bid. The adjustment indices will be posted on ODOT’s website.
2010 Conaway Conference 25
2010 Conaway Conference 26
1. No new indices planned at this time.2. No retroactive application of
proposed Index Changes.3. All proposed changes are draft.4. Use price adjustments as per the
contract documents – not the information presented here.
Important Points to Note