Change management
-
Upload
iben-engenharia -
Category
Business
-
view
724 -
download
0
description
Transcript of Change management
STEP BY STEP CHANGE MANAGEMENT FOR PROJECTS IN
THE BUILDING SECTOR
CONSTRUTORA IBEN LTDA.
CONSTRUTORA IBEN LTDA.
CHANGE MANAGEMENT IS ONE OF THE MAIN FACTORS AFFECTING PROJECT SUCCESS.CHANGES EXIST AND SHOULD NOT BE IGNORED OR BLOCKED BY RIGID SCOPES OR NORMS.
CHANGES AIM AT INCORPORATING NEW SPECIFICATIONS TO THE PROJECT, REVIEW INITIAL GOALS, ADAPT TO MARKET CHANGES, IMPROVE PRODUCT PERFORMANCE, TO GET AHEAD OF COMPETITORS, ETC.
IT JUST SO HAPPENS THAT, IN REAL LIFE, IN PROJECTS MANAGED BY IMMATURE ORGANIZATIONS, THEY FALL OUTSIDE THE EXPECTATIONS OF THE STAKEHOLDERS AND CREATE ENDLESS DISCUSSIONS ON THE IMPACTS ON COSTS, TIME, QUALITY, ETC.
THE ORGANIZATION MUST ESTABLISH A CHANGE MANAGEMENT POLICY UNDER THE GOVERNANCE OF A PMO IN ORDER TO KEEP THE PROJECT ON TRACK AND ADAPT TO NEW NEEDS WITHOUT DISAPPOINTING ANY OF THE STAKEHOLDERS.
CONSTRUTORA IBEN LTDA.
AS A PRIMORDIAL AXIOM WE MUST STATE THAT:
NO CHANGE IS TO BE INCORPORATED BEFORE IT IS 100% CONFIGURED.
SAID CONFIGURATION MUST UNDERGO CERTAIN PROCESSES THAT WE WILL SUBSEQUENTLY SEE ON A STEP BY STEP BASIS.
CONSTRUTORA IBEN LTDA.
HOWEVER, REMEMBER TO INFORM EVERYBODY THAT:
NO CHANGE IS TO BE INCORPORATED BEFORE IT IS 100% CONFIGURED.
AND HOW MUCH TIME DO WE HAVE TO CONFIGURE THEM?
THE SPEED AND PRECISION OF THIS PROCESS VARY ACCORDING TO THE MATURITY OF A PMO IN TERMS OF CHANGE MANAGEMENT.
REGISTRATION OF LEARNT LESSONS VIA KNOWLEDGE MANAGEMENT IS THE PATH TO IMPROVE THE MATURITY OF THE ORGANIZATION IN THAT WHICH PERTAINS TO CHANGE MANAGEMENT.
CONSTRUTORA IBEN LTDA.
REQUEST FOR CHANGE
CHANGE IS CAUSED BY THE REQUEST FOR IT.
REQUESTS FOR CHANGE MAY COME FROM SEVERAL STAKEHOLDERS ENDOWED WITH THE POWER TO PERFORM SUCH INTERFERENCE IN THE PROJECT SUCH AS, FOR EXAMPLE; SPONSOR, CLIENT, ARCHITECTS, DESIGNERS, WORK MANAGER AND OTHERS.
CONSTRUTORA IBEN LTDA.
DESCRIPTION OF REQUESTED CHANGEThe client, in a meeting held on 19/05/2011, requested the analysis of the replacement of the concrete block brickwork executive standard, determined in the project for the main facade of the Capiche building, to a system that concomitantly is more versatile in the case of future expansion and have a better appearance.
NEED FOR SAID CHANGEThe change aims to incorporate the stakeholders demands, which were not accounted for in project design; said demands are: 1. removable facade; and 2; new aesthetic standards.
PROPOSED SOLUTIONSConstrutora Iben proposed 3 concepts meeting above listed demands, namely: 1) Glass+ Alucobond Set 2) Pre-cast Concrete Façade Slabs; 3) Masterboard Panel System.
REQUEST FOR CHANGE
A CHANGE REQUEST FORM MUST OBLIGATORILY COMPRISE DETAILED DESCRIPTION OF THE REQUESTED CHANGE, THE ACTUAL NEED FOR SAID CHANGE AND ONE OR MORE SOLUTION PROPOSALS.
CONSTRUTORA IBEN LTDA.
ANALYSIS BY THE CHANGE COMMITTEE
THE REQUEST FOR CHANGE MUST BE ANALYZED BY THE CHANGE COMMITTEE, A QUALIFIED BRANCH OF THE PMO, ABLE TO CREATE QUICK RESPONSES TO CHANGE ASSOCIATED IMPACTS.
CONSTRUTORA IBEN LTDA.
ANALYSIS BY THE CHANGE COMMITTEE
THE COMMITTEE ANALYZES THE IMPACT ENSUING FROM REQUESTED CHANGE ON THE NINE PMI® KNOWLEDGE AREAS CHECKING, IN ADDITION TO THE CONSEQUENCES IN TERMS OF COST: WHAT ARE THE IMPACTS ON TIME, SCOPE, AND QUALITY? ARE THERE RISKS ASSOCIATED TO THIS CHANGE? ARE THERE CHANGES IN TERMS OF HUMAN RESOURCES? WHAT HAPPENS TO PURCHASING? ARE THERE NEW STAKEHOLDERS ALTERING THE COMMUNICATION PLAN? ARE THE PROJECT GOALS AFFECTED?
CONSTRUTORA IBEN LTDA.
ANALYSIS BY THE CHANGE COMMITTEEIMPACT ANALYSIS
AREAS OF ANALYSIS OF THE CHANGE
ITEM AREA DESCRIPTION OF THE IMPACTRESPONSIBLE FOR
THE ANALYSISUPDATE PLAN?
.01 SCOPE
The brickwork quantitative is to be reduced, with the addition of the installing of the adopted closure system. Additionally, foundation execution characteristics may come to be altered, depending on choice. It is necessary to review the projects.
PLANNING MANAGER YES
.02 COST
System cost is higher than initially defined values for all cases. Depending on the project alternatives, costs may range from R$ 250,000.00 to R$ 500,000.00. If work falls behind schedule, time related costs are to be assessed. PLANNING MANAGER YES
.03 TIME
Activities begin with the analysis of alternatives and new demands, project development/design, budgeting, negotiations, granting of a contractual amendment instrument, replanning, contracting of fourth parties and beginning of the works.
PROJECT MANAGER YES
.04 ACQUISITIONS
A new work package shall be incorporated to the purchase plan, to be budgeted with fourth parties, the terms of that proposal may cause an impact especially to scope, quality, time and cost. WORK MANAGER YES
.05 PEOPLE
Histogram should be reassessed and the labor mobilization plan should be adjusted to comply with the new collaborator profiles assigned to develop the new scope. WORK MANAGER YES
.06 QUALITY
The flexibility and aesthetic standard requirements shall be met, designers are to assess ensuing impacts on lighting, thermal insulation, acoustic insulation, protection of forklifts, user safety, maintenance, and cleaning. WORK MANAGER NO
.07 RISK
The work would be initiated and the planning would be developed in consecutive waves, i.e., with the project already being implemented. Decisions taken during the activities listed under item 03, Time, will create risks as they are solved. WORK MANAGER YES
.08 COMMUNICATION
It is suggested that a communication plan is prepared, determining the required channels and approval levels for the proposed changes. PROJECT DIRECTOR YES
.09 INTEGRATION
All stakeholders and the project team are to be reintegrated in order to assess the impacts on the project goals.PROJECT DIRECTOR NO
CONSTRUTORA IBEN LTDA.
APPROVAL
IMPACTS ARE TO BE APPROVED INDIVIDUALLY, IN FULL OR WITH RESTRICTIONS, IN ORDER TO DOCUMENT THE CONSENT TO THE DECISION.
THE TASK OF APPROVING OR REJECTING CHANGES IS USUALLY ASSIGNED TO THE CLIENT AND/OR SPONSOR.
REJECTED CHANGE REQUESTS SHALL BE DOCUMENTED TO AVOID THEIR UNDUE INCORPORATION AND THE RE-INSERTION OF NEW REQUESTS OF AN EQUAL NATURE IN THE ANALYSIS AND APPROVAL PROCESS.
DECISION ABOUT A GIVEN CHANGE1. ACCEPTED 2. REJECTED 3. 3. ACCEPTED WITH RESTRICTIONS
AREA NOTES DECIS. RESPONSIBLE FOR THE DECISION.01 SCOPE 1 SPONSOR.02 COST 1 SPONSOR.03 TIME 1 SPONSOR.04 ACQUISITIONS 1 SPONSOR.05 PEOPLE 1 SPONSOR.06 QUALITY 1 SPONSOR.07 RISK 1 SPONSOR.08 COMMUNICATION 1 SPONSOR.09 INTEGRATION 1 SPONSOR
CONSTRUTORA IBEN LTDA.
CHANGE CONFIGURATION
IMPACTS ARE TO BE APPROVED INDIVIDUALLY, IN FULL OR WITH RESTRICTIONS, IN ORDER TO DOCUMENT THE CONSENT TO THE DECISION.
THE TASK OF APPROVING OR REJECTING CHANGES IS USUALLY ASSIGNED TO THE CLIENT AND/OR SPONSOR.
REJECTED CHANGE REQUESTS SHALL BE DOCUMENTED TO AVOID THEIR UNDUE INCORPORATION AND THE RE-INSERTION OF NEW REQUESTS OF AN EQUAL NATURE IN THE ANALYSIS AND APPROVAL PROCESS.
CONSTRUTORA IBEN LTDA.
CHANGE CONFIGURATION
CONSTRUTORA IBEN LTDA.
CHANGE CONFIGURATION
THIS PROCESS ALTERATES THE BASELINES AND INCORPORATES THE PROJECT VIA PLAN UPDATING.
STAKEHOLDERS BECOME AWARE OF ALL IMPACTS ASSOCIATED TO THEIR DECISION AND, IN ACCORDANCE TO THE COMMON INTERESTS, CONSCIOUSLY CHOOSE TO INTEGRATE THEM TO THE PROJECT OR NOT.
CONSTRUTORA IBEN, ON ITS TURN, PRESERVES ITS RELATIONSHIP WITH THE CLIENT AND PROTECTS THE BUSINESS AGAINST UNCHEKED CHANGE AND NON-REFUNDABLE COSTS.
CONSTRUTORA IBEN LTDA.
CHANGE CONFIGURATION
TIPS FOR CHANGE CONFIGURATION
HAVE AN EFFICIENT SYSTEM TO CHANGE BASELINES AS QUICK AS POSSIBLE, SINCE SPEED AND CONSISTENCY IS KEY TO THE SUCCESSFUL INCORPORATION OF CHANGE.
MAINTAIN A REGISTRATION LOG FOR LEARNT LESSONS, MONITOR CHANGE DERIVING IMPACTS AND ASSESS THEIR COMPLIANCE WITH THE PRELIMINARY ANALYSIS.
MAKE USE OF EXPERT OPINIONS AND CLEAR IMPACT ASSESSMENT CRITERIA. YOU MAY BE ASKED TO PRODUCE THE CALCULATION LOG, THUS ALL DOCUMENTS AND FILES ARE TO BE KEPT NEAT AND TIDY.
REMEMBER: CHANGES ARE A GREAT OPPORTUNITY FOR PROJECT DEVELOPMENT AND MUST NOT BE USED TO INCORPORATE ANY NON ASSOCIATED IMPACTS.
CONSTRUTORA IBEN LTDA.
CHANGE CONFIGURATION
TIPS FOR CHANGE CONFIGURATION
NO CHANGE IS TO BE INCORPORATED BEFORE IT IS 100% CONFIGURED.
CONSTRUTORA IBEN LTDA.
WRITTEN BY
EDUARDO MILITÃO ELIAS, MBA / PMP®ID 1396759
SPONSORED BY
CONSTRUTORA IBEN LTDA., RCP PMI®ID 1463462