Change Documents
-
Upload
masteranulunu -
Category
Documents
-
view
224 -
download
0
Transcript of Change Documents
-
7/31/2019 Change Documents
1/3
TITLE:
SPONSOR:
MANAGER:
PROJECT No:
Issue 1.1
PROJECT CHANGE LOG
CHANGE DESCRIPTIONCR
No:
Line
No:
Date
Raised
Planned Start Date:
Planned End date:
Notes:1. Change Request (CR) can only be ACCEPTED after Impact Assessment.
2. Approval name is authorization signatory of the Change Request (Sponsor or Project Manager as appropr3. Record STATUS as Open (O), Rejected (R) or Completed (C).4. CR cannot be closed until implementation is completed.
Page___ of _
IMPACT
ASSESSED BY:
ENTER CHANGE
REQUEST NUMBER
IN SEQUENCE
GIVE EACH CHANGE
REQUEST A
CONCISE
DESCRIPTIVE TITLE
IDENTIFY
ORIGINATOR
& DATE CR
RAISED
IDENTIFY WHO
CONDUCTSTHE IMPACT
ASSESSMENT
TO VALIDATE
THE CHANGE
INSERT D
ORIGINATORDATE
ACCEPTED
PROJECT No:
Issue 1.1
Planned Start Date:
Planned End date:
e
A
BY
Figure 8.6 Example project change log
-
7/31/2019 Change Documents
2/3
184 l The programme and project processes and techniques
TITLE OF PROJECT:
PROJECT NUMBER:
Date:
PROJECT MANAGER:
PROJECT CHANGE REQUEST
ANY HIGH RISKS ASSOCIATED WITH THE CHANGE: RISK MGMT FORMSATTACHED:
YES
NO
APPROVALS Signature Date
Accepted by:
Approved by:
Issue: 0
ORIGINATOR:
DESCRIPTION OF CHANGE REQUIRED/RECOMMENDED:
BENEFITS:
RESOURCE IMPLICATIONS:
IMPACT ON PROJECT COST:
EFFECT ON PROJECT SCHEDULE:
PROJECT KEY STAGE(S) AFFECTED:CHANGE
REQUEST No:
PROJECT SPONSOR:
PROJECT CUSTOMER:
CONSEQUENCES OF DOING NOTHING:
IMPACT ON PROJECT CONSTRAINTS:
COMPLETE DATA
REQUESTED
WHO IS ORIGINATINGTHE REQUEST?
ORIGINATORCOMPLETES FORM
AS FAR AS POSSIBLE
GIVE CONCISE
DESCRIPTION OF CHANGEREQUIRED
INDICATE KEY STAGES
AFFECTED
WHAT ARE THE BENEFITS TOBE GAINED FROM THE
CHANGE?
LIST MAJOR IMPACT ONCURRENT SCHEDULE
IDENTIFYCONSEQUENCES IF
REQUEST IS REFUSED
DOES THE CHANGEAFFECT THE
BUDGET?DOES THE
CHANGEAFFECT
CURRENTCONSTRAINTS?
ARE THEREANY EFFECTSON RESOURCE
NEEDS?
INDICATE IF RISKMANAGEMENT FORMS
ARE ATTACHED
ENSURE APPROVALS ARECOMPLETED BEFORE
TAKING ANY ACTION TOCHANGE THE SCHEDULES
DOES THE PROPOSEDCHANGE HAVE ANY NEW
RISKS? HAVE THESE BEENANALYSED?
DECISION RECORD:
REJECTED:
ACCEPTED:
REJECTED:
Name Position
CHANGE IMPLEMENTED & COMPLETE (CR CLOSURE)
Approved by:
INDICATE
THE CR
STATUS
CR CLOSE-OUT
APPROVED WHEN
IMPLEMENTATION
OF CHANGE
IS COMPLETE
CONSEQUENCES OF DOING NOTHING:
R
GIVE CONCISE
DESCRIPTION OF CHANGEREQUIRED
INDICATE KEY STAGES
AFFECTED
LIST MAJOR IMPACT ONCURRENT SCHEDULE
IDENTIFYCONSEQUENCES IF
REQUEST IS REFUSED
ARE THEREANY EFFECTSON RESOURCE
NEEDS?
T
DOES THE PROPOSEDCHANGE HAVE ANY NEW
RISKS? HAVE THESE BEENANALYSED?
INDICATE
THE CR
STATUS
CR CLOSE-OUT
APPROVED WHEN
IMPLEMENTATION
OF CHANGE
IS COMPLETE
Figure 8.7 Example change request form
-
7/31/2019 Change Documents
3/3
but always consider whether there is a cost impact for giving something
that is not essential. Remember that the cost implication applies not justduring the project but also, possibly, in the manufacture phase. The sales-people will be delighted with extra features to help them sell yourproduct, but that does not mean the customer will be delighted andprepared to pay more.
HOLDING A LAUNCH MEETING
Now you have prepared everything you need to launch the project. Thefinal steps after completing the baseline plan include:
incorporating any changes required by the PST; preparing work plan charts for the early key stages; deriving a milestone schedule for the project; deciding a progress reporting process with the templates everyone
must use; agreeing a meetings schedule.
This launch meeting is a milestone in your project. It is the point fromwhich all project work starts. Your purpose is to get together all the impor-tant people who are involved with your project and explain the plans insome detail. Decide whom you want to attend:
Launching your project l 185
Table 8.1 Approvals that may be required in a change process
Approval required by
Impact of change Programme Project in Stand-alone Sub-projectprogramme project
No impact on Programme Project Project Project schedule, cost or manager manager manager managerscope
Some impact on Programme Programme Project Project schedule or costs sponsor manager sponsor managerwithin scope of agreedcontingencies
Significant impact on Programme Programme Programme Programme/ scope, objectives and steering team steering team steering team project benefits and affecting sponsor orthe business case Programmemay be beyond steering teamsponsors authority