Overcoming Challenges To Integrating Renewable Energy Resources
Challenges Integrating IT in USACE Construction Making ...
Transcript of Challenges Integrating IT in USACE Construction Making ...
![Page 1: Challenges Integrating IT in USACE Construction Making ...](https://reader030.fdocuments.in/reader030/viewer/2022020701/61f935ecc01fd431a233eecf/html5/thumbnails/1.jpg)
Challenges Integrating IT in USACE Construction
Making Buildings Smarter Dana Kennish “Deke” Smith, FAIA Emeritus, ASCE
Current Co-Chair APPA TCO Committee & Executive Director of AiC Former Chief Architect DUSD(I&E) – DoD Business Enterprise Architecture
Former Deputy CIO, Army Research Laboratory Former Executive Director buildingSMART Alliance / BuildingSMART International Board Member
![Page 2: Challenges Integrating IT in USACE Construction Making ...](https://reader030.fdocuments.in/reader030/viewer/2022020701/61f935ecc01fd431a233eecf/html5/thumbnails/2.jpg)
Goals for Smart Buildings How USACE should best shape their contracts to optimize facilities & Infrastructure - including low voltage/SCADA/Building Controls in MILCON projects?
• Smart Buildings, Infrastructure, Cities/Installations • Improve Mission Readiness and Resiliency
• Role of Total Cost of Ownership • Predict and Help Ensure Future Readiness and Proper Resourcing (People and Dollars)
• Strategic Plan for Army by Corps of Engineers • Support Military Capability and Readiness • Support National Infrastructure
![Page 3: Challenges Integrating IT in USACE Construction Making ...](https://reader030.fdocuments.in/reader030/viewer/2022020701/61f935ecc01fd431a233eecf/html5/thumbnails/3.jpg)
Information Assurance • Design in IA from the beginning – cannot be added on effectively
later!
• Basic infrastructure issue • Redundancy does not mean burying two cables in the same ditch • Protecting power as it enter the installation is “too little too late” • For every good aspect of IoT there is a dark side – prepare for it!
![Page 4: Challenges Integrating IT in USACE Construction Making ...](https://reader030.fdocuments.in/reader030/viewer/2022020701/61f935ecc01fd431a233eecf/html5/thumbnails/4.jpg)
What Is Smart? ARL Case Study Goals
• Smart & Secure Communication • Smart & Secure Network • Smart & Secure Buildings and
Infrastructure
Infrastructure Operations Center
• Network Operations Center • Facilities & Spatial Awareness • 24x7x365 Operations • Failover Capability – Tested Monthly • Trained individuals – Tested Business
Processes • Change Management – Using Root
Cause Analysis
Not just one asset, but the entire Installation and Command
![Page 5: Challenges Integrating IT in USACE Construction Making ...](https://reader030.fdocuments.in/reader030/viewer/2022020701/61f935ecc01fd431a233eecf/html5/thumbnails/5.jpg)
Establish Vision & 2001-2005 Strategic Plan Five Year Plan Completed in Three!
Dr. Whalin, Director Dr. Radhakrishnan, CIO
![Page 6: Challenges Integrating IT in USACE Construction Making ...](https://reader030.fdocuments.in/reader030/viewer/2022020701/61f935ecc01fd431a233eecf/html5/thumbnails/6.jpg)
Smart Facilities, Infrastructure & Cities • Network Viability • BIM & GIS can be used for Scenario Planning - create a
Digital Twin of the asset • Operate Facility • Resource Burn Rates • Contingency Planning • Emergency Response • Increase Resiliency • Mission Readiness
Graphic © by APPA Facility Manager July/August 2019
![Page 7: Challenges Integrating IT in USACE Construction Making ...](https://reader030.fdocuments.in/reader030/viewer/2022020701/61f935ecc01fd431a233eecf/html5/thumbnails/7.jpg)
Total Cost of Ownership - A Key Discriminator • The owner (Army) must manage assets for their entire economic life. • The designer and contractor only must deliver a functional facility on day one. • The sustainability of an asset is not a separate effort, even though it comes
from separate pots of money. Plan for the whole. • Sustainability is critically and profoundly impacted by initial design and
construction decisions. • Smart facilities provide the feedback and situational awareness for continued
good decision making and resiliency. • Understanding TCO and sustainability was a big part of the ARL success and why
it is still operational almost 20 years later! • The overall least cost decision is the best decision for the owner! • The Army must add TCO and “Asset Efficiency” to the solicitation and make
them selection criteria.
![Page 8: Challenges Integrating IT in USACE Construction Making ...](https://reader030.fdocuments.in/reader030/viewer/2022020701/61f935ecc01fd431a233eecf/html5/thumbnails/8.jpg)
Recommendations 1. A team approach must be established! 2. Need management and worker buy-in! Establish vision and strategic plan
and distribute to all. 3. Holistic Approach – Not one building at a time, each asset must fit into a
larger system. 4. Not just MILCON but ultimately all procurements. GSA has been using
DBOM, DoD has been trying private public partnerships. Keep trying! 5. Use a Total Cost of Ownership approach to understand ramifications of all
decisions – Consider ANSI recognized APPA 1000™ for TCO – similarities between campus and installation.
6. Using TCO you can identify the impact of shortfalls earlier so that contingency preparations or arguments can be made for more resources.
7. Facilities and Installations must be viewed as integral to mission! 8. If we fail the enemy wins!
Thank You