Challenges in Developing  Coal Power Plants in PakistanPower Plants in Pakistan

Tahir Jawaid

September, 2014

Tahir Jawaid

The Hub Power Company Limited

Page 2: Challenges in Developing Coal Power Plants in Pakistanpii.com.pk/wp-content/uploads/2017/08/6-Mr.-Tahir-Jawaid.pdf · Challenges in Developing Coal Power Plants in Pakistan Tahir

Agenda

I Pakistan’s Energy Crisis  Short VersionI. Pakistan’s Energy Crisis ‐ Short Versiona. Magnitude

b Rb. Reasons

II. Hubco – The Companyba. Hub Power

b. Hub Narowal

L i b Ec. Lairab Energy

d. 660 MW Coal based IPP

III Ch ll  f  C l P  Pl t D l tIII. Challenges for Coal Power Plant Development

IV. Question & Answers

The Hub Power Company Limited

Page 3: Challenges in Developing Coal Power Plants in Pakistanpii.com.pk/wp-content/uploads/2017/08/6-Mr.-Tahir-Jawaid.pdf · Challenges in Developing Coal Power Plants in Pakistan Tahir

Section I: Pakistan’s Energy Crisis ‐ Short Version

The Hub Power Company Limited

Page 4: Challenges in Developing Coal Power Plants in Pakistanpii.com.pk/wp-content/uploads/2017/08/6-Mr.-Tahir-Jawaid.pdf · Challenges in Developing Coal Power Plants in Pakistan Tahir

25 000

Pakistan’s Energy Crisis

20,000

25,000

15,000

5,000

10,000 Computed Peak DemandCorresponding SupplySurplus/Shortfall

0

2009 2010 2011 2012 2013

‐10,000

‐5,0009 3

The Hub Power Company Limited

10,000

Source: NEPRA State of Industry Report 2013

The Hub Power Company Limited

Page 5: Challenges in Developing Coal Power Plants in Pakistanpii.com.pk/wp-content/uploads/2017/08/6-Mr.-Tahir-Jawaid.pdf · Challenges in Developing Coal Power Plants in Pakistan Tahir

Energy Crisis ReasonsOther  0 P ki t

G   %

Coal, 0.1% Hydro, 2

Other, 0.4%

Pakistan

Gas, 29%

Nuclear, 

% y ,9%

Oil, 36%5%

Energy Fuel MixTransmission Losses

Power TheftPower TheftTariff MismatchNon‐Payment

The Hub Power Company Limited

yLow Investment

Page 6: Challenges in Developing Coal Power Plants in Pakistanpii.com.pk/wp-content/uploads/2017/08/6-Mr.-Tahir-Jawaid.pdf · Challenges in Developing Coal Power Plants in Pakistan Tahir

Country Power Demand Projection

Assumptions:• Annual GDP Growth Rate : 4.8% (Low), 5.9% (Normal), 6.5% (High)• Annual Population Growth Rate : 1.7%• Per capita power consumption : Expected to increase from 800 kWh/y

nsion

Per capita power consumption  : Expected to increase from 800 kWh/y presently to 2,538 kWh/y by 2035. In comparison, Malaysia is now at 3,724 kWh/y

Current  DependableCapacity

+  M

W expa

100,000+

The Hub Power Company Limited

Source: National Transmission & Distribution Co. (NTDC), Pakistan

Page 7: Challenges in Developing Coal Power Plants in Pakistanpii.com.pk/wp-content/uploads/2017/08/6-Mr.-Tahir-Jawaid.pdf · Challenges in Developing Coal Power Plants in Pakistan Tahir

Section II: Hubco – The Company

The Hub Power Company Limited

Page 8: Challenges in Developing Coal Power Plants in Pakistanpii.com.pk/wp-content/uploads/2017/08/6-Mr.-Tahir-Jawaid.pdf · Challenges in Developing Coal Power Plants in Pakistan Tahir

Hubco – Operations

Pakistan’s 1st IPP : 1,292 MW Hub Plant

Narowal IPP : 225 MW 

Pakistan’s 1st Hydel IPP : 84 MW Laraib Pakistan s 1 Hydel IPP : 84 MW Laraib 

Total Capacity : 1,601 MW

Generating 10% of Pakistan’s electricity

The Hub Power Company Limited

Page 9: Challenges in Developing Coal Power Plants in Pakistanpii.com.pk/wp-content/uploads/2017/08/6-Mr.-Tahir-Jawaid.pdf · Challenges in Developing Coal Power Plants in Pakistan Tahir

Hub Power Plant – 1292 MW

The Hub Power Company Limited

4x323 MW STG, Fuel: RFO, COD: 1997 

Page 10: Challenges in Developing Coal Power Plants in Pakistanpii.com.pk/wp-content/uploads/2017/08/6-Mr.-Tahir-Jawaid.pdf · Challenges in Developing Coal Power Plants in Pakistan Tahir

Narowal Power Plant – 225MW

The Hub Power Company Limited

11 Engines, 1xSTG, Fuel: RFO, COD: 2012

Page 11: Challenges in Developing Coal Power Plants in Pakistanpii.com.pk/wp-content/uploads/2017/08/6-Mr.-Tahir-Jawaid.pdf · Challenges in Developing Coal Power Plants in Pakistan Tahir

Laraib ‐ Pakistan’s 1st Hydel IPP – 84MW

The Hub Power Company Limited

4x21MW, Run‐of‐River, COD: 2013

Page 12: Challenges in Developing Coal Power Plants in Pakistanpii.com.pk/wp-content/uploads/2017/08/6-Mr.-Tahir-Jawaid.pdf · Challenges in Developing Coal Power Plants in Pakistan Tahir

Hubco – Unique Site with a Future

1500 Acres

4.3 NM / 8 KMKarachi: 35 Miles /  

56 KM

The Hub Power Company Limited

Page 13: Challenges in Developing Coal Power Plants in Pakistanpii.com.pk/wp-content/uploads/2017/08/6-Mr.-Tahir-Jawaid.pdf · Challenges in Developing Coal Power Plants in Pakistan Tahir

Hub‐II – 660 MW Imported Coal Fired IPP

• 2x660MW at Hub Site• 2x660MW at Hub Site• Brownfield vs Greenfield• Super Critical Technology

ld k l d d• World Bank Environmental Standards• Existing Grid ConnectivityExisting Grid Connectivity• Imported Coal 5500 Kcal/Kg NAR• Coastal location, multiple logistic options

The Hub Power Company Limited

Page 14: Challenges in Developing Coal Power Plants in Pakistanpii.com.pk/wp-content/uploads/2017/08/6-Mr.-Tahir-Jawaid.pdf · Challenges in Developing Coal Power Plants in Pakistan Tahir

Section III: Risks & Challenges in Coal Power Plant Section III: Risks & Challenges in Coal Power Plant 

Development

The Hub Power Company Limited

Page 15: Challenges in Developing Coal Power Plants in Pakistanpii.com.pk/wp-content/uploads/2017/08/6-Mr.-Tahir-Jawaid.pdf · Challenges in Developing Coal Power Plants in Pakistan Tahir

Project Financing Challenge• Coal is a dirty fuel & is not a favorite for western yfinancing

• Only option is Chinese based Financing• Chinese institution have little experience in PK Project Financing, most project financed are G‐to‐G

l h ld b d f d l l• Developers should be ready for delays in Financial Close thus exposure to increase in Project Cost

• With number of Power Projects being developed • With number of Power Projects being developed there will be a stress on local debt availability for projects

• Security Structure: IA & PPA guarantees being questioned due to Circular Debt

The Hub Power Company Limited

Page 16: Challenges in Developing Coal Power Plants in Pakistanpii.com.pk/wp-content/uploads/2017/08/6-Mr.-Tahir-Jawaid.pdf · Challenges in Developing Coal Power Plants in Pakistan Tahir

Technological Challenge

• No prior experience of installing & operating coal No prior experience of installing & operating coal based power plants in the country – HR Gap

• Fire & Explosion risk due to coal dust  operating • Fire & Explosion risk due to coal dust, operating regime & equipment selection critical

• Fuel significantly different than gas & oil, solid with different handling, storage & transportation needs

• Un‐processed fuel thus variations depending upon fuel origins posing quality challengesg p g q y g

• New environmental mitigations: FGD, ESP, SCR

The Hub Power Company Limited

• Ash Disposal: 1x660 MW plant produces 250KTPA

Page 17: Challenges in Developing Coal Power Plants in Pakistanpii.com.pk/wp-content/uploads/2017/08/6-Mr.-Tahir-Jawaid.pdf · Challenges in Developing Coal Power Plants in Pakistan Tahir

Power Evacuation Challenge60

60

70

30.339.5

40

50

60

8.9

21.3

6

2014

10

20

30

0

Balochistan Sindh Punjab KP, GB & AJK

I t ll d C it % L d %

• Load Centers in the middle of the country• Transmission infrastructure missing to evacuate power to

Installed Capacity % Load %

• Transmission infrastructure missing to evacuate power toload centers

• Transmission planning not keeping pace with power asset

The Hub Power Company Limited

Transmission planning not keeping pace with power assetdevelopment, NTDC can do 23 KM per month

Page 18: Challenges in Developing Coal Power Plants in Pakistanpii.com.pk/wp-content/uploads/2017/08/6-Mr.-Tahir-Jawaid.pdf · Challenges in Developing Coal Power Plants in Pakistan Tahir

Logistic Challenge• 10x660MW will require say 20 MTPA of Bituminous Coal• 500 Ships of 40KT are required to bring 20 MT coal i‐e 1.5 ships per day

• Ports take 3 to 4 days to off load a ship using on‐board cranes, poor port infrastructure

• 1100 trucks required every day to move coal from port• Moving 10 MTPA on train require 28 trains leaving port e er  da  i e 1 e er  45 mins (don’t get ca ght at a every day i‐e 1 every 45 mins (don’t get caught at a railway crossing)

• Railway requires $4B investment to upgrade• Railway requires $4B investment to upgrade• Port will require significant investment, PQA is getting bulk terminal will solve part of the issue

The Hub Power Company Limited

bulk terminal will solve part of the issue• Delays in coal arrival for an IPP means LD’s

Page 19: Challenges in Developing Coal Power Plants in Pakistanpii.com.pk/wp-content/uploads/2017/08/6-Mr.-Tahir-Jawaid.pdf · Challenges in Developing Coal Power Plants in Pakistan Tahir

Social & Environmental Challenge

2 PicturesPictures Equals

22 Million Words

• If Environment is not respected will create Social & PR issues

The Hub Power Company Limited

p• Weak Regulatory Structure may breed compromises

Page 20: Challenges in Developing Coal Power Plants in Pakistanpii.com.pk/wp-content/uploads/2017/08/6-Mr.-Tahir-Jawaid.pdf · Challenges in Developing Coal Power Plants in Pakistan Tahir

Powering Pakistan

•Short Term: Coastal Power Plants based on •Short Term: Coastal Power Plants based on imported coal & few power assets in Thar, invest in power evacuation South to North

•Medium Term: Imported Coal Power Plants in f fCenter near Load Centers & few Run‐of River

• Long Term: Large Scale Hydro Assets • Long Term: Large Scale Hydro Assets developed in North like Bhasha, Dassu etc.

The Hub Power Company Limited• In‐between: Wind & Solar as grid Stabilizes

Page 21: Challenges in Developing Coal Power Plants in Pakistanpii.com.pk/wp-content/uploads/2017/08/6-Mr.-Tahir-Jawaid.pdf · Challenges in Developing Coal Power Plants in Pakistan Tahir

What Can Insurance Industry do for Coal IPP’s?

• Very rich database of world wide losses in coal • Very rich database of world wide losses in coal fired plants:

• Equipment Damages• Equipment Damages• Bodily Harms

• Knowledge can be made available to industry to • Knowledge can be made available to industry to understand the inherent risks & be able to mitigate themthem

• Win‐Win for both, less accidents, low premium for asset owners & nil loss pay off by insurance asset owners & nil loss pay off by insurance companies