Challenges Facing the Electricity Sector Industry in Uganda
-
Upload
lucie-bulyaba -
Category
Documents
-
view
160 -
download
2
Transcript of Challenges Facing the Electricity Sector Industry in Uganda
1
CHALLENGES FACING THE ELECTRICITY SECTOR INDUSTRY AND FUTURE OUTLOOK
By Eng.Norbert Semitala (Director, Technical Regulation – ERA)
1.0 Introduction
In 1987, the Government of Uganda adopted the Economic Recovery Program in order to
restore macroeconomic stability. The Economic Recovery Program included the liberalization
of the financial sector and privatization of some state owned enterprises. Privatization in
particular was meant to get rid of the inefficient government parastatals and replace them with
more efficient private companies.
The electricity sector as well was inefficient and loads of investment was required to move it to
efficient levels. The Ministry of Natural Resources then, developed a strategic power sector
plan that sought to lead to the provision of affordable and reliable electricity in order to
enhance economic growth and development.
In June 1999, the GOU put in place the Power Sector Restructuring and Privatisation Strategy
(PSRPS), whose principle objectives were having an efficient and financially viable power
sector, meeting demand and expanding coverage, improving quality of electricity and
encouraging private and local investment into the sector.
The Electricity Act of 1999, came in handy to provide the legal framework in order to achieve
objectives of the power sector strategic plan. The main objectives of the Electricity Act were to
remove the monopoly in the electricity sector by privatizing some of the functions of the then
state owned Uganda Electricity Board (UEB), and put in place a regulatory authority to
oversee the activities in the electricity sector.
The Electricity Regulatory Authority was established in 2000, to regulate the activities of the
electricity industry. With the regulatory body in place, UEB was split into Uganda Electricity
Generation Company Ltd (UEGCL), Uganda Electricity Transmission Company Ltd (UETCL),
and Uganda Electricity Distribution Company Ltd (UEDCL). UEGCL took ownership of the
380MW capacity Nalubaale/Kiira plant, UETCL took charge of the transmission
infrastructure, while UEDCL took over the distribution network.
2
The figure below shows the Electricity Industry setup.
3
UEGCL later concessioned its assets to Eskom (U), while UETCL remains a Government
entity, considering the nature of investments needed in the transmission arm, vis avis the
return, if it were to be operated by a profit motivated company. UEDCL subsequently
concessioned its assets for a 20-year period to Umeme (Ltd).
With the new sector setup, several private companies have since invested particularly in
generation facilities namely; Tronder-Bugoye (13MW), South East Asia Management Systems-
Mpanga (18MW), Aggreko-Mutundwe (50MW), and Jacobsen-Namanve (50MW) among
others. UETCL is the sole transmission company and has the licenses for system operator,
import and export, bulk power supply and operation of high voltage grid. The distribution
companies include Umeme (which accounts for more than 98% of the total end user sales),
Ferdsult Engineering Services (FESL), Kilembe Investments Limited (KIL), Bundibugyo
Energy Cooperative Society (BECS), Pakwach-Abim Community Multi Purpose Energy
Cooperative Society (PACMECS), and West Nile Rural Electrification Company (WENRECO)
among others.
2.0 Tariff Path since 2006.
Prior to 2004, Uganda’s major source of electricity was hydropower. However, due to the
severe drought that affected the country thereafter, the water levels of L.Victoria (which is the
main reservoir for the 380 MW Owen Falls Complex) reduced significantly leading to
insufficient power supply.
A strategic decision that government decided to take at the time was to mitigate the
inadequate electricity supply through short term hire of diesel thermal plants which although
very expensive compared to hydro, can be installed in a very short time and would go a long
way in ensuring the availability of sufficient energy. The Aggreko Lugogo (50MW) was
commissioned in 2005 and later another Aggreko-Kiira (50MW) was also procured in 2006 to
further mitigate the energy shortage. Later in September 2008, another plant Aggreko-
Mutundwe (50MW) was procured through a World Bank loan and this replaced the Aggreko
Lugogo plant.
It was recognized at the time that the costs of running and maintaining these plants is high and
if they were to be passed on and be paid through the tariff, it would impact on the cost of
doing business and render several productive sectors of the economy non-competitive in the
region. A strategic decision was thus adopted by Government to subsidize end user customers.
This strategy would then be supplemented by medium term interventions of encouraging the
private sector through a feed in tariff mechanism to fast rack relatively small hydropower
plants typically up to 20 MW, as the longer term interventions like Bujagali and Karuma
eventually come on board.
4
Notwithstanding that decision, it was also necessary that the consumer should pay more than
what was being paid before 2005, given that at the time the consumer was paying far less than
what was required to meet the sector revenue requirements.
As a result, the tariffs were adjusted upwards in April 2005 by 22%, June 2006 by 35% and
November 2006 by 41%. Towards the end of 2009 however, some favourable conditions
prevailed such as lower oil prices and appreciation of the Shilling against the US Dollar, a
situation that necessitated the review of the tariff downwards with the energy subsidy at the
time projected at only Shs 8 billion in Q1 2010. The events that followed immediately thereafter
(i.e at the beginning of 2010) led to the current subsidy requirement levels that are
unsustainable, if the sector is to be self financing.
Table 1: Tariff Levels since 2005
3.0 Current status
a) Electricity demand –supply balance:
- Peak demand has increased to 443MW in May 2011 compared to 380MW in May 2009.
- Shoulder demand has increased to 351MW in May 2011 compared to 280MW in May
2009.
- Off-peak demand has increased to 302MW in May 2011 compared to 230MW in May
2009.
This increase has been largely driven by growth in economic activities in the country.
Electricity supply has however remained constrained due to hydrological constraints, delays in
reaching commissioning by Bujagali and Mini-hydro plants, and lack of supply by Thermal
generators which have switched off due to delays in payment. The current deficit is indicated in
Graph 1 below.
Code 10.1 Code 10.2/10.3
Code
20
Code
30
Code
50 Code 10.1 Code 10.2/10.3
Code
20
Code
30
Code
50
Domestic Commercial
Medium
Industrial
Large
Industrial
Street-
lights Domestic Commercial
Medium
Industrial
Large
Industrial
Street-
lights
Q1 2005 171.4 164.8 150.3 60.4 162.5 171.4 164.8 150.3 60.4 162.5
Q2 2005 256.4 245.7 234.2 109.6 243.0 212.5 204.4 178.9 71.9 201.5
Q2 2006 525.1 475.2 463.5 328.9 487.5 298.2 286.8 261.5 120.8 282.8
Q4 2006 674.6 605.2 593.6 438.0 620.0 426.1 398.8 369.7 187.2 403.0
Q1 2010 713.0 639.9 615.0 488.4 649.2 385.6 358.6 333.2 184.8 364.3
Period
Cost Reflective Tariff Actual Tariff Paid by end-user
5
Graph1: Current Load shedding on a typical day
b) Energy mix:
In 2006, thermal generation accounted for 23%, currently thermal generation accounts for
46% of Uganda’s energy mix. Thermal generation costs account for about 85% in 2011
compared to 73 % in 2006.
c) Sector Revenue requirements:
The total sector revenue requirement in 2006 amounted to Shs.420 billion and this increased
to Shs.618 billion in 2010 and Shs.1, 076 billion in 2011. The major drivers of the increase in
revenue requirement are thermal generation costs which increased from Shs.155 billion in
2006 to about Shs.670 billion in 2011 largely due to the depreciation of the Shilling,
increasing fuel prices, and increased dispatch. Please note that contract obligations to all the
thermal generators are denominated in USD.
d) Distribution efficiency:
The number of distribution companies has increased from the two (Umeme and WENRECO)
in 2005 to five in 2011. Of these five, Umeme accounts for more than 98% of the market
share. Therefore Umeme is the major driver of the distribution costs.
Distribution losses (technical and non-technical) have reduced from 35% in 2009 to the
targeted 27% for 2011. Correspondingly, Umeme’s collection rates have improved from
0
50
100
150
200
250
300
350
400
450
500
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Total Demand, (MW) Total Generation (MW) Load shedding, MW
6
92.5% in 2009 to 96.2% in 2011. Customer connections have increased from 37,000 in 2010
to the targeted 51,000 in 2011.
It is worthwhile noting that on the basis of the 2011 projection of energy sales to Umeme, for
every percentage loss reduced, the corresponding saving is Shs.5.78 billion. Reducing losses
significantly would therefore lead to a huge saving.
e) Electricity projects:
A number of generators already in operation are shown in table 2 below, while Hydromaxx-
Buseruka (9MW-Hydro) is nearing completing and Electro-Maxx-Tororo is increasing its
capacity to 50MW by the end of 2011.
7
Table 2: Licensed Operational Generation Companies
No. Plant Installed Capacity(MW)
1 Mpanga 18
2 Hydromax 9
3 Ishasha 6.5
4 KML 5
5 KCCL 9.9
6 Bugoye 13
7 Eskom 380
8 Kakira 22
9 Kinyara 7.5
10 Jacobsen 50
11 Electro-Maxx 16
12 Aggreko IDA 50
Total Capacity 587
4.0 Challenges facing the sector
a. Exchange rate depreciation:
Since November 2009, the Shilling has depreciated by over shs600/US$ from
Shs1874/US$. Currently, the sector revenue requirement is estimated at US$400 million,
of which 80% is foreign currency based. On account of depreciation alone, the sector
revenue requirement has increased by about Shs.192 billion over the past 18 months.
b. Increasing fuel prices:
The international oil prices have increased to reach the highs of US$120/barrel against the
earlier forecast of US$60-70/barrel at the beginning of 2010. This increase has had a
significant impact on sector costs.
c. Fixed tariffs: Our tariff has not been adjusted upwards to absorb the effects of the
exchange rate depreciation and high fuel costs. This is contrary to our neighbor Kenya
where there is an automatic adjustment of the tariff for inflation, exchange rate and fuel
prices on a monthly basis. As a result, our tariffs are now much lower than those of Kenya
and the extra burden of financing has been pushed to government in form of increased
subsidies. Table 3 shows the comparison of tariffs in the E. Africa region.
8
Table 3: Tariff Comparison in E. Africa
d. Government subsidies: As a result of unchanged tariffs amidst a depreciating shilling
and increasing fuel prices, the impact on government subsidies has reached unsustainable
levels.
Table of Subsidies (in UShs billion)
2006 2007 2008 2009 2010 2011
107 78 169 229 351 447
e. Constrained Hydrology:
Whereas installed capacity at Kiira and Nalubale is 380MW, the L.Victoria which is with
reservoir is regulated and the allowed water release is usually 800 cumecs, which can only
help generate an average of 138.5MW from the two power stations. There has however
been an increase in the water release to 1000 cumecs in order to mitigate the supply deficit
by generating as much as 172MW.
The issue of hydrology is also affecting mini hydro plants which have just been
commissioned (13MW Bugoye Plant, 18MW Mpanga plant, and the 6.5MW Ishasha
plant).
f. Financing Challenges
There are also challenges related to financing such as the very high interest rates in
Uganda’s financial sector markets. This makes local borrowing difficult hence many
possible investors take long or totally abandon the projects.
Country
Domestic
Consumers Commercial
Medium
Industries
Large
Industries
Street
Lighting
Uganda 0.15 0.14 0.13 0.07 0.14
Kenya 0.18 0.19 0.15 0.14 0.17
Rwanda 0.19 0.19 0.18 0.18 0.19
Tanzania 0.13 0.10 0.06 0.05 0.08
9
g. Long licensing process;
There have also been some complaints regarding the licensing process which takes a long
time period. This is due to the statutory requirements that have to be fulfilled before the
conclusion of the licensing process. On a number of occasions, the prospective licensees
also take long to respond to different questions raised hence dragging the licensing process
further.
h. Domestic factors;
Inadequate and poor road networks as well as absence of transmission networks to
evacuate the generated power are seen as high risk factors. In most instances it is not clear
who will construct the power evacuation lines.
i. Lack of skilled manpower locally;
Developers experience problems finding skilled labour especially in the area of
hydropower development.
5.0 FUTURE OUTLOOK
i. Commissioning of Bujagali and more mini hydro plants. With the commissioning of
Bujagali, the sector revenue requirements (sector costs) are expected to reduce from
Shs1075.8bn Q3 2011 to Shs818.1bn in Q1 2012.
Renewable energy generation from Baggasse and other sources is expected to add
about 50MW to the national grid while mini-hydro plants are expected to add 9MW to
the grid in 2012.
ii. De-commissioning of Diesel Generation Plants: The license for Aggreko –Kiira
(50MW) plant is not going to be extended beyond June 30th 2011. Similarly, the
Aggreko Mutundwe Plant is expected to be de-commissioned by December 2011 after
obtaining 100MW from Bujagali. The remaining HFO plants (Jacobsen Namanve
50MW plant and the 20MW Electromaxx plant in Tororo (to be uprated to 50 MW by
the end of the year) are expected to use crude oil from the Albertine Graben region.
10
iii. Use of our own crude oil in generating some 50MW from Albertine Graben region at
Kaiso-tonya.
iv. Improving Distribution efficiency: The first seven years of Umeme license are ending
in February 2012. Negotiations are about to commence in order to set Umeme a new
set of performance targets. Having monitored Umeme’s performance over these seven
years and given the greater experience from the region and other countries, ERA is
now in a better position to set Umeme more realistic performance targets on losses,
collection rates, customer connections, investments etc.
v. Improvement in operating efficiency of independent power producers. ERA has
embarked on an exercise to audit all independent power producers. This exercise will
help in future benchmarking to ensure prudently incurred costs are allowed in the
tariff.
11
Appendix 1: Permit Holders
Permits
Kyambura HEP,
South Asia Energy Management Systems Nyamwamba Small hydro Power Project, Mini Hydro 14
VS Hydro Siti 1 & 2 Project, Kapchorwa & Bukwo Mini Hydro 25.7
Eco Power (U) Ltd. Rwimi, Kasese/Kabarole Mini Hydro 9.6
LTL Holdings (Pvt) Limited River Nyamagasani Kyarumba Project Mini Hydro 3
Hayleys Industrial Solutions (Pvt) Ltd Kanyampara Hydropower Project Mini Hydro 7.2
Jeyam Hydro Power Limited Sironko Hydropower Project, Mini Hydro 7
Vidullanka Plc River Muvumba Hydropower Project, Mini Hydro 4.5
Elemental Energy Limited Nyamabuye Hydropower Project, Kisoro DistrictMini Hydro 2.2
Carnelian Prime Trust Nyahuka Hydropower Project, Bundibugyo DistrictMini Hydro 1
Sesam Energetics 1 Ltd. Biomass project, Kampala Waste to Energy 33
Kabale Energy Ltd. Generation plant in Kabale Peat 30
Sugar and Allied Industries Limited Generation Plant in Jinja Bagasse cogeneration 20
Energy Systems for Africa Ltd Generation Plant at Namugoga, Busiro Solar-thermal 50
East African Energy Technology Development NetworkRiver Dirigana Project, Sironko Micro Hydro 60kW,
Albatros Energy (U) Limited Generation Plant in Nebbi Heavy-fuel oil 10
Albatros Energy (U) Limited Generation Plant in Tororo Heavy-fuel oil 230
Apac Energy for Agro Processing Centres (U) Ltd Generation plant in Kabale Biomass-fired plant 1
Timex Garments (Pvt) Limited Bukinda Hydropower Project across River Nkusi Mini Hydro 6.5
Red & White Energy Limited Lubilia-3 Hydropower Project, Kasese District Mini Hydro 5
P.A.C.S.P.A Achwa-Agago Hydropower Project Mini Hydro 88.8
Hydraulic & Sanitation Consult Limited Nkusi Hydropower Project Mini Hydro 11
TYAX Holding Incorporated River Nyamagasani Project Mini Hydro 15
Butama Hydro Electricity Company Ltd. Bundibugyo Hydro Project Mini Hydro 7.5
Hydromax (Nkusi) Ltd. Waki, Hoima District Mini Hydro 8-Feb
Greenewus Energy Africa Ltd Kakaka – Kasese District Mini Hydro 7.2
Nsongezi Power Company Limited Nshungyezi HEP Project, Isingiro Mini Hydro (Own distribution & sale to national grid)22
ZIBA Ltd. Mini Hydro 8.3
Jacobsen Elektro AS Nengo Bridge HEP Project, Rukungiri Mini Hydro 6.5 – 7.0
Developer Project Name / Location Technology Option Planned Capacity (MW)