Ch12d

download Ch12d

of 26

Transcript of Ch12d

  • 7/28/2019 Ch12d

    1/26

    EOQ: How much to order; ROP: When to order

    Re-Order Point (ROP) in periodic inventory system is the start ofthe period. Where is ROP in a perpetual system?

    ROP in Perpetual System: Quantity on hand drops to apredetermined amount.

    If there were no variations in demand, and demand was reallyconstant; ROP is when inventory on hand is equal to the[average] demand during lead time.

    Lead Time is the time interval from placing an order until receivingthe order.

    When to re-order with EOQ Ordering

  • 7/28/2019 Ch12d

    2/26

    The greater the variability of demand during lead time, the greater

    the need for additional inventory to reduce the risk of shortage(i.e., the greater the safety stock).

    When variability exists in demand or lead time, actual demandduring lead time may exceed average demand during lead time.

    If ROP is equal to average demand during lead time, there is 50%probability of satisfying all the demand.

    But we want this probability to be greater than 50%. We prefer90%, 95%, or 99%.

    Safety Stock (SS): serves to reduce the probability of a stockoutduring the lead time.

    ROP in perpetual inventory control is the inventory level equal tothe average demand during the lead time+ a safety stock(to cover demand variability)

    When to re-order with EOQ Ordering

  • 7/28/2019 Ch12d

    3/26

    Example 1

    Average demand for an inventory item is 200 units per

    day, lead time is three days, there is no variation indemand and lead time and therefore, safety stock iszero. What is the reorder point?

    In a perpetual inventory system, the ROP is the point at whichinventory on hand is equal to the [average] demand inlead time plus safety stock.

    ROP = 3(200)

    Whenever inventory level drops to 600 units we place anorder.

    We receive the order in 3 days. Because there is no variations

    in demand, there is no stock out.

  • 7/28/2019 Ch12d

    4/26

    Example 2

    Average demand for an inventory item is 200 units per

    day, lead time is three days, and safety stock is 100units. What is the reorder point

    In a perpetual inventory system, the ROP is the point at whichinventory on hand is equal to the average demand in leadtime plus safety stock.

    ROP = 3(200)+100

    Whenever inventory level drops to 700 units we place anorder.

    Since there is variation in demand, during the next three days,we may have a demand of 500, 600, 700, or even more.

  • 7/28/2019 Ch12d

    5/26

    Time

    Inve

    ntory

    Demand During Lead Time

  • 7/28/2019 Ch12d

    6/26

    LT

    ROP when demand during lead time is fixed

  • 7/28/2019 Ch12d

    7/26

    Time

    Inve

    ntory

    Demand During Lead Time

  • 7/28/2019 Ch12d

    8/26

    Demand During Lead Time is Variable

  • 7/28/2019 Ch12d

    9/26

    Inventory

    Time

    Demand During Lead Time is Variable

  • 7/28/2019 Ch12d

    10/26

    Average demand

    during lead time

    A large demand

    during lead time

    ROP

    Time

    Quantity

    Safety stock reduces risk of

    stockout during lead time

    Safety Stock

    Safety stock

    LT

  • 7/28/2019 Ch12d

    11/26

    ROP

    Time

    Quantity

    Safety Stock

    LT

  • 7/28/2019 Ch12d

    12/26

    When to re-order (ROP)

    Demand during lead time has Normal distribution.

    We can accept some risk of being out of stock,

    but we usually like a risk of less than 50%.

    If we order when the inventory on hand is equal

    to the average demand during the lead time;

    then there is 50% chance that the demand during

    lead time is less than our inventory.

    However, there is also 50% chance that the

    demand during lead time is greater than our

    inventory, and we will be out of stock for a while.

    We usually do not like 50% probability of stockout

  • 7/28/2019 Ch12d

    13/26

    RO

    P

    Risk of a

    stockout

    Service level

    Probability of

    no stockout

    Safety

    stock

    0 z

    Quantity

    z-scale

    Safety Stock and ROP

    Each Normal variable x is associated with a standard Normal Variable z

    x is Normal (Average x , Standard Deviation x) z is Normal (0,1)

    There is a table for z which tells us

    Given anyprobability of not exceeding z. What is the value of z

    Given anyvalue forz. What is the probability of not exceeding z

    Average

    demand

  • 7/28/2019 Ch12d

    14/26

    Common z Values

    Risk Service level z value0.1 0.9 1.28

    0.05 0.95 1.65

    0.01 0.99 2.33

    RO

    P

    Risk of a

    stockout

    Service level

    Probability of

    no stockout

    Safety

    stock

    0 z

    Quantity

    z-scale

    Average

    demand

  • 7/28/2019 Ch12d

    15/26

    Relationship between z and Normal Variable x

    RO

    P

    Risk of a

    stockout

    Service level

    Probability of

    no stockout

    Safety

    stock

    0 z

    Quantity

    z-scale

    Average

    demand

    z = (x-Average x)/(Standard Deviation of x)

    x = Average x +z (Standard Deviation of x)

    = Average x

    = Standard Deviation of x

    Risk Service z value

    level

    0.1 0.9 1.28

    0.05 0.95 1.650.01 0.99 2.33

    x = +z

  • 7/28/2019 Ch12d

    16/26

    Relationship between z and Normal Variable ROP

    RO

    P

    Risk of a

    stockout

    Service level

    Probability of

    no stockout

    Safety

    stock

    0 z

    Quantity

    z-scale

    Average

    demand

    LTD = Lead Time Demand

    ROP = Average LTD +z (Standard Deviation of LTD)

    ROP = Average LTD +ss

    ss = z (Standard Deviation of LTD)

  • 7/28/2019 Ch12d

    17/26

    Safety Stock and ROP

    RO

    P

    Risk of a

    stockout

    Service level

    Probability of

    no stockout

    Safety

    stock

    0 z

    Quantity

    z-scale

    Risk Service level z value

    0.1 0.9 1.28

    0.05 0.95 1.65

    0.01 0.99 2.33

    Average

    demand

    ss = z (standard deviation of demand during lead time)

  • 7/28/2019 Ch12d

    18/26

    Demand During Lead Time is Variable N(,)

    Average Demand of sand during lead time is 50 tons.

    Standard Deviation of demand during lead time is 5 tons.Assume that management is willing to accept a risk no

    more that 5%.

    What is the service level?Service level = 1-risk of stockout = 1-.05 = 0.95

    What is the z value corresponding to this service level?

    z = 1.65

    What is safety stock (ss)?

    ss = z (standard deviation of demand during lead time)

    ss = 1.65 (5) = 8.25

  • 7/28/2019 Ch12d

    19/26

    What is ROP?

    ROP = Average demand during lead time + ss

    and of demand during lead time

    ROP = 50 + 1.65(5) = 58.25

  • 7/28/2019 Ch12d

    20/26

    Average Demand of sand during lead time is 75 tons.

    Standard deviation of demand during lead time is 10 tons.Assume that the management is willing to accept a risk no

    more that 10%.

    What is the service level?

    Service level = 1-risk of stockout = 1-0.1 = 0.9

    Risk Service level z value0.1 0.9 1.28

    0.05 0.95 1.65

    0.01 0.99 2.33

    Example 2;total demand during lead time is variable

  • 7/28/2019 Ch12d

    21/26

    z= 1.28What is safety stock?

    ss = 1.28(10) = 12.8

    ROP = Average demand during lead time + ss

    ROP = 75 + 12.8 = 87.8

    The general relationship between service level, risk, and

    safety stock: Service level increases

    Risk decreases

    ss increases

    Example 2;total demand during lead time is variable

    f f

  • 7/28/2019 Ch12d

    22/26

    : Demandd

    : Average Demandd

    :Standard deviation of demandd

    : Lead timeLT

    Ifdemand is variable and Lead time is fixed

    Average demand during lead time : ( )LT d

    : LTdLT d

    :Standard deviation of demand during lead timedLT

    and of demand per period and fixed LT

    d f d d i d d fi d LT

  • 7/28/2019 Ch12d

    23/26

    Average Demand of sand is 50 tons per week.

    Standard deviation of the weekly demand is 3 tons.Lead time is 2 weeks.

    Assume that the management is willing to accept a risk

    no more that 10%. z = 1.28

    : 50 tonsd: 2 weeksLT : 3 tonsd

    dROP d LT z LT

    50 2 1.28 2 3ROP

    100 5.43ROP

    and of demand per period and fixed LT

    d f L d Ti d fi d d d

  • 7/28/2019 Ch12d

    24/26

    : Lead timeLT

    : Average Lead timeLT

    :Standard deviation of Lead TimeLT

    Iflead time is variable and demand is fixed

    Average demand during lead time : ( )LT d

    :dLT LT d

    : Demandd

    and of Lead Time and fixed demand

    L d Ti V i bl D d fi d

  • 7/28/2019 Ch12d

    25/26

    Lead Time Variable, Demand fixed

    Demand of sand is fixed and is 50 tons per week.

    The average lead time is 2 weeks.Standard deviation of lead time is 0.5 week.

    Assuming that the management is willing to accept a risk

    no more that 10%. Compute ROP and SS.

    Acceptable risk; 10% z = 1.28

    :50 tonsd : 2 weeksLT : .5 weekLT

    LTROP d LT zd 50 2 1.28 50 .5ROP

    100 32ROP

    A i t 12 d

  • 7/28/2019 Ch12d

    26/26

    (a) Average demand per day is 20 units and lead time is 10 days.

    Assume zero safety stock (ss=0). Compute ROP.

    (b) Average demand per day is 20 units and lead time is 10 days.

    Assume 70 units of safety stock. ss=70. Compute ROP.

    (c) If average demand during the lead time is 200 and standard

    deviation of demand during lead time is 25. Compute ROP at

    90% service level. Compute ss.

    (d) If average demand per day is 20 units and standard deviation

    of demand is 5 per day, and lead time is 16 days. ComputeROP at 90% service level. Compute ss.

    (e) If demand per day is 20 units and lead time is 16 days and

    standard deviation of lead time is 4 days. Compute ROP at

    90% service level Compute ss

    Assignment 12.d