CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

64
CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL AND SOUTHEASTERN EUROPE CURRENT STATUS OF NPP PROJECTS SUMMER SCHOOL 2016 17 th August; 2016 Petr Závodský Director – Nuclear Power Plants Construction [email protected]

Transcript of CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

Page 1: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

CEZ GROUP:

THE LEADER IN POWER MARKETS OF CENTRAL

AND SOUTHEASTERN EUROPE

CURRENT STATUS OF NPP PROJECTS

SUMMER SCHOOL 2016

17th August; 2016

Petr Závodský

Director – Nuclear Power Plants Construction

[email protected]

Page 2: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

SUMMER SCHOOL – NEW NUCLEAR BUILD

CONTENT

ČEZ Group

Current situation and possibilities

Nuclear in the world

ČEZ - nuclear projects - status

1

Page 3: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

… KEY COMPONENTS TO BE ABLE TO BUILD A

NUCLEAR POWER PLANT …

2

6971

68

4649

5659

65

69

54

60

73

75

75

5358

64

66

73

77

62

7072

78

72

64 64

62

72

70

74 69

68

20

40

60

80

100

2000 2001 2002 2004 2005 2006 2007 2008 2009 2011 2012

%

(share of YES answers)

Population Participants Announced participation in referendum

Page 4: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

CEZ GROUP IS AN INTERNATIONAL UTILITY

WITH A STRONG POSITION IN CEE

Source: 2014 data, EUR/CZK=27.533, * 1260 MW of installed capacity is currently offline

Energy Assets

CEZ Group in the Czech Republic

Installed capacity (MW) 13,470

Electricity generation, gross (TWh) 58.3

Generation market share 68%

Distributed electricity (TWh) 32.7

Distribution market shre 57%

Number of employees 20,503

Sales (EUR million) 5,547

CEZ Group in Poland

(100% stake in Skawina, 100% in Elcho)

Installed capacity (MW) 681

Electricity generation, gross (TWh) 2.6

Generation market share 1.8%

Number of employees 396

Sales (EUR million) 156

CEZ Group in Romania

(100% stakes in CEZ Distributie, CEZ Vanzare, Tomis Team,

Ovidiu Development, TMK Hydroenergy Power)

Installed capacity (MW) 622

Electricity generation, gross (TWh) 1.3

Generation market share 2.1%

Distributed electricity (TWh) 6.3

Distribution market share 14%

Number of employees 1,792

Sales (EUR million) 429

CEZ Group in Bulgaria

(67% stake in CEZ Razpredelenie Bulgaria, CEZ Electro

Bulgaria, 100% in TPP Varna, 100% in Free Energy Project

Oreshets )

Installed capacity (MW) 1,265*

Electricity generation, gross (TWh) 0.9

Generation market share 2.3%

Distributed electricity (TWh) 9.1

Distribution market share 29%

Number of employees 3,530

Sales (EUR million) 882

CEZ Group in Turkey

(50% stake in SEDAS through AkCez, 37.36% stake in

Akenerji)

Installed capacity (MW) 1,289

Electricity generation, gross (TWh) 2.7

Generation market share 1.1%

Distributed electricity (TWh) 8.0

Distribution market share 3%

3

Page 5: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

4

A TOP 10 EUROPEAN UTILITY

SOURCE: Bloomberg, Annual reports, companies’ websites and presentations

Top 10 European power utilities Market capitalization in EUR bn, as of April 7, 2016

Top 10 European power utilities Number of retail customers in 2014, in millions

10

1

2

3

4

5

6

8

9

7

EdF

Enel

Iberdrola

E.ON

Engie

CEZ Group

EdP

Fortum

PGE

RWE

PGE 10

Enel 1

EdF 2

Iberdrola 3

E.ON 4

RWE 5

Engie 6

CEZ Group 8

EnBW 9

EdP 7

61,0

38,5

32,6

23,4

23,2

21,6

5,2

5,2

11,0

7,3

37,6

36,8

31,8

18,3

16,3

10,8

10,0

8.0

6,6

5,8

Page 6: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

5

BETTER OFF FINANCIALLY THAN PEERS Net economic debt2/ EBITDA

Net financial debt/EBITDA

Key insights ▪ ČEZ group is one of the most profitable European utilities

▪ Its leverage is low compared to industry standards

EBITDA1

Percent, 2015

Net debt/ EBITDA1

Multiples, 2015

1 As reported by companies

2 Net economic debt = net financial net debt + liabilities from nuclear provisions & liabilities from employee pensions & reclamation provision

5.1

4.8

3.7

3.6

3.6

3.3

2.7

2.6

1.2

-1.7

EDP

EDF

EON

RWE

Iberdrola

Engie

Enel

CEZ Group

PGE

Fortum

2

Average 2.9x

36,6

31,1

26,3

24,4

23,5

23,3

19,8

16,2

14,4

6,5

Fortum

CEZ Group

PGE

EDP

EDF

Iberdrola

Enel

Engie

RWE

EON

Page 7: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

CEZ IS A STRONG AND VERTICALLY INTEGRATED

PLAYER IN THE CZECH ELECTRICITY MARKET

Source: CEZ, ERU, MPO, companies´ data;

data for 2014 (distribution data for 2013)

CEZ fully owns the

largest Czech

mining company

(SD) covering 71%

of CEZ’ s lignite

needs

Remaining 3 coal

mining companies

are privately owned

The Czech

transmission grid is

owned and

operated by CEPS,

100% owned by

the Czech state

Lignite mining Generation Transmission Distribution Supply

CEZ

Others

5 out of 8

distribution

regions

61% of customers

57%

21.6 million tons

2014

43%

16.6 million tons

68%

58.3TWh

32%

27.9 TWh

100%

64.3 TWh 63%

36 TWh 39% of customers

Other competitors –

individual IPPs Other competitors –

E.ON, RWE/EnBW

6

37%

21 TWh

Page 8: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

7

CEZ GROUP’S STRATEGY IS BUILT ON THREE PILLARS

We want to operate power

assets as efficiently as

possible from the point of

view of both shareholders

and customers

We want to pro-actively

react now to the future

design of power sector with

a large proportion of

decentralized and zero-

emission production and

diminishing differences

between producers and

consumers

Be among the best in the

operation conventional

electricity generation

and proactively respond to the

challenges of the 21st century

We want to offer our

customers partnership,

expertise, tools, and

financing to meet their

energy needs - our

customers are much more

active in the control of their

electricity and gas

consumption and use in

general as well as in their

own production

We want to complement this

with additional products that

have synergy with

electricity and gas sales

Offer customers a wide

range of products and

services addressing their

energy needs

We want to maintain our

position among the top 10

energy companies in Europe

take advantage of major

synergies in the operation of

our assets and when offering

new products and servicing

customers

We focus our attention on

regions and countries that

are close to both CEZ and the

Czech Republic in terms of

energy markets, economy,

politics and culture; however,

undisputed profitability

remains the key indicator

Strengthen and consolidate

our position in Central Europe

Vision: deliver innovative solutions to energy needs and contribute to a better quality of life.

Mission: guarantee safe, reliable and positive energy to our clients and the society as a whole.

Note: SME = small and medium-sized enterprises; ESCO = Energy service company

I II III

Page 9: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

KEY STRATEGIC ACHIEVEMENTS OF 2015

2014 dividend to our

shareholders amounting to CZK

21.4 bn

We saved CZK 2.9 bn in fixed

costs compared to year 2014

Mining limits have been extended

for Bílina mine (possibility to

extract additional 100 – 150 m

tones of lignite)

We completed checks of welds on

Units I., II. and III. of Dukovany

nuclear power plant and submitted

an application for operating

license extension for Unit I.

We set up an SPV company for

spinoff of projects of new plants in

Temelín and Dukovany

Be among the best in the

operation of conventional

electricity generation

and proactively respond to the

challenges of the 21st century

Stabilized portfolio of electricity

customers, growing in gas (+36.9

th. connection points)

Customer satisfaction grew

(mainly with price and with product

and service offering) – from 77%

to 84 %

We are offering roof top PV from

CEZ – more than 100 signed

contracts, thousands being

negotiated

We gained majority stake (75%) in

ENESA a.s. focused on EPC

projects

3 extensive technological „smart

grids“ projects are prepared in the

Czech Rep.

Offer a wide range of

products and services to

customers, which address

their energy needs

We reduced financial exposure of

CEZ, a. s. abroad by CZK 9.3 bn

We completed two investments

into German innovative companies

Sonnenbatterie and SunFire (fuel

cells)

Allocation of green certificates

restored for Fântânele Vest and

Cogealac in Romania

We signed a framework

agreement for cooperation with

German group Aquila Capital,

offering investment opportunities

to wind farms in Germany (up to

120 MW)

On Feb 26, 2016 Standard &

Poor's confirmed CEZ rating on

the level of A- with stable outlook

Strengthen and

consolidate our position

in the region of Central

Europe

I II III

SPV - special purpose vehicle; EPC – Energy Performance Contracting

8

Page 10: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

9

CEZ GROUP OPERATES LOW COST GENERATION

FLEET, …

Installed capacity and generation (2015)

CEZ has a long-term competitive

advantage of low and relatively stable

generation costs

2 731 4,4

4 290 26,8

5 237

23,8

2 817

5,3 845 0,5

Installedcapacity

Generation,gross

Hydro and

renewables

Lignite /

Brown coal

Nuclear

15,920 MW 60.9 TWh

Share on

generation

44%

7%

39%

Black coal

9% Coal power plants are using mostly

lignite from CEZ’s own mine

(67% of lignite needs sourced internally,

remaining volume through long-term

supply contracts)

Nuclear plants have very low

operational costs

CCGT

9

Page 11: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

SUMMER SCHOOL – NEW NUCLEAR BUILD

CONTENT

ČEZ Group

Current situation and possibilities

Nuclear in the world

ČEZ - nuclear projects - status

10

Page 12: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

11

Nuclear

Hydro

Pumped-storage

Lignite

Biomass

Power heating plant

Hard coal

Wind

Photovoltaic

Hardcoal with

coke gas

combustion

CCGT

OWNED BY ČEZ, a. s.

OWNED BY A DAUGHTER

COMPANY OF THE CEZ

GROUP

IN THE CZECH REPUBLIC, CEZ GROUP OWNS AND OPERATES A BROAD PORTFOLIO OF POWER PLANTS

NPP Dukovany

VVER 4x440MW (PWR)

increased to 4x510 MW

NPP Temelín

VVER 2x1000MW (PWR)

planned increase to 2x1081 MW

Page 13: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

THERE WILL OCCUR SIGNIFICANT ENERGY DEFICIT

LATEST IN 2035 (EVEN WITH EXPECTATION OF STRONG

DEVELOPMENT OF RES)

0

10 000

20 000

30 000

40 000

50 000

60 000

70 000

80 000

90 000

100 000

20

10

20

11

20

12

20

13

20

14

20

15

20

16

20

17

20

18

20

19

20

20

20

21

20

22

20

23

20

24

20

25

20

26

20

27

20

28

20

29

20

30

20

31

20

32

20

33

20

34

20

35

20

36

20

37

20

38

20

39

20

40

20

41

20

42

20

43

20

44

20

45

GW

h

Hnědé uhlí Černé uhlí

Zemní plyn Ostatní plyny

Ostatní paliva Obnovitelné a druhotné zdroje energie

Jádro Jádro nové

Referenční scénář spotřeby Vysoký scénář spotřeby

Nízký scénář spotřeby Bez recertifikace JEDU

* Optimised scenario of Czech energy strategy 12

Brown coal

Natural gas

Other

Nuclear

Reference scenario

Low scenario

Hard coal

Other gases

Renewables

New Nuclear

High scenario

Decomm. EDU in 2025-27

Page 14: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

SIGNIFICANT PART OF LIGNITE CAPACITY WILL BE

DECOMMISSIONED IN NEXT TWO DECADES

Low cost of domestic lignite

Thermal power plants next to mines –

only costs of internal logistics

Replacement of old units with more

efficient new technology (20% lower

CO2 emissions, from 1t CO2/MWh to

0.8 CO2/MWh)

Secured lignite supplies for the

investment lifetime

Majority of coal fired power plants will

disappeared from the electricity

market till 2035

Additional 1410 MW to be

decommissioned till 2040

Furthermore it is expected that NPP

Dukovany 1-4 (2000 MW) will be

decommissioned between 2035 - 37

5400

800

660

750

2210

Lignite (brown coal) capacity (MW)

Prunéřov (till 2040)

Ledvice (till 2055)

Tušimice (till 2037)

3190 MW

To be decommissioned

before 2035

+ NPP Dukovany

(50 years of operation)

2000 MW

Current capacity

of lignite fired PP Expected capacity

in 2035

13

Electricity production from power

plants of approx. 7 GW shall be

replaced by new build power

plants

Page 15: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

,… WHICH IS A GREAT ADVANTAGE IN THE

CURRENT LOW PRICE ENVIRONMENT

14

20

25

30

35

40

45

50

55

60

65

Development of electricity price (year-ahead baseload, €/MWh)

Czech Republic Germany

Drivers of electricity price

Decline of hard coal prices due to shale gas discoveries in the US and declining Chinese imports

Decline in carbon prices due to oversupply driven by economic slowdown

Growing capacity of subsidized renewables at the time of stagnating/declining electricity demand

** Nuclear fuel costs and CZK50/MWh payment for fuel storage, cash cost of extracting own lignite, carbon costs are considered

* Current power price of 25 €/MWh, 2016 production of

CEZ hedged at €35/MWh, i.e. 10 €/MWh above current

forwards

18

12

4

-6

Nuclear** Lignite ** Hard Coal CCGT

Clean spreads by technology at current power prices* (€/MWh)

Page 16: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

15

LONG TERM CONSUMPTION IN THE CZECH

REPUBLIC

HISTORICKÝ VÝVOJ SPOTŘEBY ELEKTŘINY V ČESKÉ REPUBLICE (tuzemská brutto spotřeba)

0

5 000

10 000

15 000

20 000

25 000

30 000

35 000

40 000

45 000

50 000

55 000

60 000

65 000

70 000

75 000

80 000

1915 1920 1925 1930 1935 1940 1945 1950 1955 1960 1965 1970 1975 1980 1985 1990 1995 2000 2005 2010

tuze

ms

bru

tto

sp

otř

eb

a

[G

Wh

]

2. sv. válka

Hosp. krize

"Sametová"

revoluce

Vnitropolitická

destabilizace

Světová krize

...

Energetická krize,

klimatické výkyvy

Industrializace,

socialistická výstavba

EGÚ Brno, a. s. - 02 / 2011

3 dlouhodobé směrnice:

1. Meziválečné období - asi 190 GWh ročně

2. Socialistická výstavba - asi 1250 GWh ročně

3. Po roce 1989 - asi 1200 GWh ročně Délka poklesů spotřeby:

Hosp. krize 30. léta - 3 roky, o 14 %

2. sv. válka - 1 rok, o 34 %

"Sametová" revoluce - 3 roky, o 10 %

Vnitropolitická destabilizace - 3 roky, o 5 %

Page 17: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

16

THERE IS A CLEAR CONNECTION BETWEEN ECONOMY

SITUATION AND ELECTRICITY CONSUMPTION

21%

4%

50%

source: ČSÚ, ERÚ, ČEZ

Year to year indexes – GDP × electricity consumption

Economic crisis

-8%

-6%

-4%

-2%

0%

2%

4%

6%

8%

1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013

Spotřeba elektřiny

HDP

Consumption

GDP

Page 18: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

17

GERMAN WIND POWER PLANTS ARE CAUSING

PROBLEMS ALL AROUND CENTRAL EUROPE

Page 19: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

18

Minimal CO2 emissions

Stability of fuel supply

Low cost of electricity

Long construction period

High investment

Politically sensitive issue

The only fuel that is available in

our region in sufficient amount

Existing international market

with black coal, import possible

High CO2 emissions

CCS still not commercially available

CO2 price of allowances

High efficiency (CCGT)

Flexible source

Relatively short construction

period and low investment cost

High gas prices

Gas prices are unstable and difficult

to predict in long term

Total dependence on import

No CO2 emissions

Environmentally friendly

Political support

Limited possibilities, strongly

dependant on local conditions

Risk for grid stability

Expensive (depending on subsidies)

Nuclear

Coal

Gas

Renewables

WHAT CZECH REPUBLIC CAN DO ?

(EXCEPT OF UNREALISTIC IMPORT AND MASSIVE SAVINGS)

Page 20: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

19

Assets of the CEZ Group Branch offices

Upgrade of lignite existing plant

Construction started in 2007

Commissioning in 2012

Tusimice (4 x 200 MW)

Ledvice (660 MW)

New supercritical lignite unit

Construction started in 2007

Commissioning in 2015

Prunerov (3×250 MW)

Upgrade of existing lignite plant

In permitting stage

Commissioning in 2015

Pocerady (840 MW)

New combined cycle gas plant

Construction started in 2011

Commissioning in 2013

Fantanele + Cogealac (600 MW)

Wind farm

Construction started in 2007

WE ARE CURRENTLY UNDERTAKING SEVERAL MAJOR INVESTMENTS INTO THE GENERATION FLEET IN THE CZECH REPUBLIC AND ABROAD

Egemer (872 MW, in JV Akenerji)

New combined cycle gas plant

Construction started in 2011

Commissioning in 2014

Page 21: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

0

10

20

30

40

50

60

70

80

90

100

2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020

LONG TERM FORWARD PRICES DON’T INDICATE THE

RECOVERY OF THE INVESTMENT ENVIRONMENT

Power price, Germany, EUR/MWh

CO2 price, EUR/t

In 2008 the market sent

the motivation signal for

investment - before the

crises. The CO2 price

was at the level that

promoting low-carbon

sources.

Intermediate oversupply

and drop in coal and gas

prices decreased the

power price.

Unpredictable support of

renewables threatens the

European power and

CO2 market that should

motivate investment into

the power sources.

Note: 2014 …2020 - baseload forwards (CAL14 – CAL19 EEX) 20

Page 22: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

THE DEMAND FOR ENERGY IS LIKELY TO GROW

21 Source: Eurostat, 2012

Final consumption of electricity per capita

MWh/cap

Further economic

convergence in the

V4 countries

towards the

European core can

be expected

Differences in

consumption

between

comparable

countries are given

by the structural

differences in the

GDP

5,1

2,3

4,2

2,6

3,8

6,0

3,2

5,4

3,5

4,6

0

1

2

3

4

5

6

7

EU15 PL CZ HU SK

1993 2011

- 24 % - 24

+90%

+12%

+74%

+33%

Page 23: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

4

5

6

7

8

9

10

15 20 25 30 35 40 45 50

V ČR NELZE V PŘÍPADĚ EKONOMICKÉ KONVERGENCE

OČEKÁVAT ABSOLUTNÍ POKLES SPOTŘEBY

Spotřeba elektřiny* na osobu [MWh/os] vs.

HDP na osobu [tisíce PPS/os], 2012

Existuje silná korelace

mezi úrovní ekonomiky

a spotřebou elektřiny na

obyvatele

I přes ekonomiku

orientovanou na průmysl

má ČR nižší spotřebu

elektřiny na osobu než

jiné vyspělé

západoevropské země

Spotřeba elektřiny ve

skandinávských zemích

(FI, SE) je na úrovni

dvojnásobku průměru

EU. Např. Norsko

vykazuje 24,5

MWh/osobu

CZ

EU15

PT

GR

ES

IT UK

FR

DE

BE

IE

AT

NL

DK

consum

ption o

f ele

ctr

icity p

er

capita

GDP per capita

Zdroj: Eurostat, ENTSO-E

SK

* Konečná spotřeba včetně ztrát v síti a elektromobility

**Růst HDP ve stejné výši jako OTE (2,4% ročně), ASEK vychází z OTE

CZ 2040

dle ASEK**

CZ 2040

OTE nízký

CZ 2040

OTE vysoký

22

Page 24: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

38

62

DE power price 2014 Nuclear full costs

NUCLEAR OFFERS A LOW – EMISSION, LOW COST

SOLUTION FOR COUNTRIES STILL WORKING ON

ECONOMIC CONVERGENCE TO EU CORE

Electricity price in Germany compared with nuke full cost

EUR/MWh

Electricity

alone

RES

surcharge

100

EUR/MWh

62%

38%

23

Page 25: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

STUDY FOR THE EUROPEAN COMMISSION,

DG ENERGY

24

William D. D’haeseleer

Professor at the University of Leuven (KU Leuven),

Belgium

Page 26: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

SUMMER SCHOOL – NEW NUCLEAR BUILD

CONTENT

ČEZ Group

Current situation and possibilities

Nuclear in the world

ČEZ - nuclear projects - status

25

Page 27: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

26

SOME FIGURES – NPPs IN THE WORLD

* Source: WNA 1.8.2016 ** Including Japan (43)

2006

2010

2011

„Today“*

Units in commercial operation 435 442 434 445**

Installed power GWe 368 376 370 389

Ratio of nuclear power in overall

production 16% 14% 13,8% 11,5%

Under construction 28 63 61 61

On order or planed 64 156 156 170

Proposed 158 322 343 339

Operable = Connected to the grid;

Under Construction = first concrete for reactor poured, or major refurbishment under way;

Planned = Approvals, funding or major commitment in place, mostly expected in operation within 8-10 years;

Proposed = Specific program or site proposals, expected operation mostly within 15 years.

Page 28: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

COUNTRY

Country Profile) No. MWe net No.MWe

grossNo.

MWe

grossNo.

MWe

gross

WORLD** 445 388,777 61 64,589 170 177,685 339 381,6

China 34 30597 20 22596 42 47930 136 156000

Russia 35 26053 8 7104 25 27755 23 22800

India 21 5302 6 4300 22 20700 38 44000

UAE 0 0 4 5600 0 0 10 14400

USA 100 100013 4 5000 18 8312 24 26000

Japan 43 40480 3 3036 9 12947 3 4145

Korea RO 25 23017 3 4200 8 11600 0 0

Pakistan 3 725 3 1841 1 1161 0 0

Belarus 0 0 2 2388 0 0 2 2400

Slovakia 4 1816 2 942 0 0 1 1200

Argentina 3 1627 1 27 2 1950 2 1300

Brazil 2 1901 1 1405 0 0 4 4000

Finland 4 2741 1 1700 1 1200 1 1500

France 58 63130 1 1750 0 0 1 1750

Poland 0 0 0 0 6 6000 0 0

Turkey 0 0 0 0 4 4800 4 4500

United Kingdom 15 8883 0 0 4 6100 9 11800

Vietnam 0 0 0 0 4 4800 6 6700

Canada 19 13553 0 0 2 1500 3 3800

Iran 1 915 0 0 2 2000 7 6300

Egypt 0 0 0 0 2 2400 2 2400

Czech Republic 6 3904 0 0 2 2400 1 1200

Bangladesh 0 0 0 0 2 2400 0 0

Hungary 4 1889 0 0 2 2400 0 0

Ukraine 15 13107 0 0 2 1900 11 12000

Jordan 0 0 0 0 2 2000

Kazakhstan 0 0 0 0 2 600 2 600

Romania 2 1310 0 0 2 1440 1 655

Armenia 1 376 0 0 1 1060

Bulgaria 2 1926 0 0 1 950 0 0

Indonesia 0 0 0 0 1 30 4 4000

Lithuania 0 0 0 0 1 1350 0 0

REACTORS REACTORS REACTORS REACTORS

Page 29: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

WORLD

UAE First "Newcomer" In 27 Years To Start Nuclear Power Plant Construction

The United Arab Emirates is the first country to start the construction of its first nuclear power

plant in 27 years, since construction was started on China's first plant in 1985.

As of 30 August 2012, the Barakah-Unit 1 is reported in the IAEA Power Reactor Information

System (PRIS) as "under construction".

The Emirates Nuclear Energy Corporation (ENEC) poured the first nuclear safety-related

concrete on 18 July 2012, after receiving a construction license from the Federal Authority of

Nuclear Regulation. The first unit of the APR1400 technology supplied by a Korean consortium

led by KEPCO is scheduled to be in operation in 2017 and three additional units are planned to

be operational by 2020.

The UAE has started its nuclear power program to meet increasing demand for electricity.

Other potential "newcomers":

Saudi Arabia, Bangladesh, Indonesia, Jordan, Thailand,Vietnam, …..

Page 30: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

CHINA

1st NPP in operations since 1994

Currently 34 units in operation (except of 2 Candu 6, all are PWR (300, 600 &1000 MWe);

20 units under construction: 23 MWe; 42 planned: 48 MWe (PWR …. AP1000, EPR,

VVER-1000, CPR1000, HL1000, BN-800…)

Page 31: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

30

USA …. NUCLEAR REGULATORY COMMISSION APPROVES

CONSTRUCTION OF FIRST NUCLEAR UNITS IN 30 YEARS

The USA is the world's largest producer of nuclear power, accounting for more than 30%

of worldwide nuclear generation of electricity.

The country's 100 nuclear reactors produced 798 billion kWh in 2015, aprox. 20% of total

electrical output.

Following a 30-year period in which few new reactors were built, it is expected that 4 new

units may come on line by 2020, the first of those resulting from 16 licenses

applications made since mid-2007 to build 24 new nuclear reactors.

However, lower gas prices since 2009 have put the economic viability of some of these

projects in doubt.

Government policy changes since the late 1990‘s have helped pave the way for

significant growth in nuclear capacity. Government and industry are working closely on

expedited approval for construction and new plant designs.

Vogtle, GA AP1000 x 2 2400 Southern Nuclear Operating

Company

24/7/08,

COL Feb 2012

loan guarantee;

11/2016, 11/2017

V. C. Summer,

SC

AP1000 x 2 2400 South Carolina Electric &

Gas

31/3/08,

COL Mar 2012

loan guarantee;

2017, '18

Page 32: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

31 31

EUROPE

Finland

OL3, prep 2 new

units

Rusia

New construction

+ plans

Bulgaria & Romania

Kozloduy, Cernavoda

Hungary

New unit at Paks

France

Construction at

FLA3 prep, Penly

Life Extension

England

Preparation of new

construction / new

legislation

Slovenia

New unit at Krsko

Germany

Phase out till 2022

Sweden

Replacement of

old units

Italy

No nuclear in

referendum

Spain

Life Extension

Ukraine

Plans for new

units

Slovakia

Construction at

Mochovce,

Preparation at

Jaslovské Bohunice

Belorusia

2 new units Lithuania New BWR in

cooperation with

Baltic countries

Turkey

Plans for 6 units

Switzerland

No new nuclear

Belgium

Phase out ??

Poland

Prep. of new 6

GWe

Czech R.

New units

Page 33: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

LAND USE NUCLEAR VS WIND AND SOLAR

32

Hinkley Point C:

- 430 acres, 174 ha,

- 26 TWh/year (3200 MW, 93%

up time), about 7% of the total

UK demand.

Solar:

- - 130 000 acres, 52 609 ha

Wind onshore:

- - 250 000 acres, 101 171 ha

Page 34: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

ANNUAL NUCLEAR SHARE IN ELECTRICITY MIX BY

COUNTRY AND HISTORIC MAXIMUM

33 Source: The World Nuclear Industry Status Report 2014

Page 35: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

WORLD NUCLEAR REACTOR FLEET, 1954–2014

34 Source: The World Nuclear Industry Status Report 2014

Page 36: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

NUCLEAR POWER REACTOR GRID CONNECTIONS

AND SHUTDOWNS, 1954–2014

35 Source: The World Nuclear Industry Status Report 2014

Page 37: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

NUMBER OF NUCLEAR REACTORS UNDER

CONSTRUCTION

36 Source: The World Nuclear Industry Status Report 2014

Page 38: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

AGE DISTRIBUTION OF OPERATING NUCLEAR

REACTORS

37 Source: The World Nuclear Industry Status Report 2014

Page 39: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

SUMMER SCHOOL – NEW NUCLEAR BUILD

CONTENT

ČEZ Group

Current situation and possibilities

Nuclear in the world

ČEZ - nuclear projects - status

38

Page 40: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

39

DUKOVANY NPP 4 x 500 MWe In operation since 1985

Type of reactor: VVER 440 type V 213

Power uprating from 440 MW to 500 MW

Dukovany NPP among top NPPs world-wide as per

operational and safety performance indicators

Safety long time operation program

Total electricity production over 300 TWh

TEMELÍN NPP 2 x 1000 MWe First connection to the grid 2000

Type of reactor: VVER 1000 type V320

Installed capacity 2 x 1000 MW

Temelín NPP is the largest energy source in CR

Temelín NPP is built and designed at the highest

level of safety

Planned power uprating up to 1080 MW (till 2015)

Total electricity production over 150 TWh

ČEZ IS OPERATING 6 NUCLEAR UNITS ON 2 SITES

Page 41: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

ČEZ’S GROUP NUCLEAR COMPETENCIES

The first research reactor was put into operation in the Czechoslovakia in 60’, making the

country the 7th in the world in peaceful use of the Nuclear energy (reactor installed at NRI

Řež).

ČEZ safely operates 6 nuclear units (4×VVER440 at Dukovany NPP, 2 × VVER1000)

ČEZ prepares three new nuclear project (Temelín 3&4, Dukovany 5&6, New unit at

Jaslovske Bohunice NPP – Slovakia).

Škoda Praha was the original general supplier of the technology for all nuclear units in

Czechoslovakia including Temelín 1&2 NPP; Škoda Praha is also an EPC supplier of the

heating plants (coal, gas).

Energoprojekt (currently a division of NRI Řež) was the general designer of all nuclear

units in Czechoslovakia including Temelín 1&2.

NRI Řež is active not only in support of currently operating plant (especially research for

life time extension) but also in generation IV. Research (for example Allegro) as well as

partially in Small modular reactors.

40

Page 42: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

41

Temelín

Construction of Units 3&4

Pressurized Water Reactor

(PWR)

Dukovany

Construction of Unit 5

Pressurized Water Reactor (PWR)

Jaslovské Bohunice

Pressurized Water Reactor

(PWR)

ČEZ‘s PLANS FOR NEW NPP‘s BUILDS

Page 43: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

42

THE BUILDING OF NEW REACTOR UNITS IS A PRIORITY

FOR BOTH ČEZ AND THE CZECH REPUBLIC

State energy concept

Guarantee energy supplies which will be

Reliable

Safe (safe production resources)

Friendly to the environment – almost

zero emissions

For an acceptable price

Supplying continuously even in crisis

situations

Targets

Building 2 new units in

Dukovany and/or

Temelín

Installed capacity

2,000 - 3,300 MWe

PWR Generation III+

reactors

Minimum life 60 years

Other project in

preparation

Jaslovské Bohunice

power plant (JV with

JAVYS)

ČEZ’s attitude

Nuclear energy has always been for

ČEZ profitable

The new nuclear reactors will help ČEZ

to increase the proportion of emission-

free generation facilities

By building new units, ČEZ would

replace decommissioned existing coal

power plants

Page 44: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

EPC TENDER ACC. TO PUBLIC TENDERING – THE WORLD

UNIQUE PROCESS HAS BEEN CLOSE TO SELECTION OF

EPC SUPPLIER …

43

Competitive open

process

Three nuclear

technology leaders

retained

as bidders

Tender procedure compliant with European Union and Czech public tendering

Balanced technical and commercial criteria for offer evaluation

Specifications selected to favour the standard design option with minimum modification

Technical requirements adapted from European Utility Requirements (EUR) as a starting point, modified mainly for:

Site conditions

Legislation requirements and licensing process in the Czech Republic

CEZ operational experience from Dukovany and Temelin (6 units all together)

Technical advisor recommendation

Emphasis on safety and security following Fukushima incident

Selection of EPC contractor independent from partnership process

Westinghouse Electric Company LLC

Westinghouse Electric Czech Republic s.r.o

Areva NP SAS

SKODA JS a.s

ZAO Atomstroyexport

OAO OKB Gidropress

Page 45: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

44

SUMMARY OF PASSED MILESTONES AND NEXT STEPS

REGARDING EPC TENDER

Initiation of EPC

tender

Consultation

meetings I

with qualified

bidders

First round of

tender

changes

implementatio

n

Initiation of

external

assessment of

tender

specification

Consultatio

n meetings

II

Qualification

finished

Aug 2009 Feb 2010 Jun 2010 Feb 2011 Feb 2011 Apr 2011

Decision about

tender changes

Submission of

the tender

specification to

executive and

supervisory

board

Approval of

tender

specification

Tender

specification

issued

Documentation

ready

for second round

of external

assessment

19th-25th May 2011 15th June 2011 20th Sep. 2011 20th Oct. 1011 31st Oct. 2011

Bid submission Approval by MB

and SB of ČEZ

Signature of the

EPC contract

Final notice to

proceed – start of

construction

Finalisation of

the evaluation

and negotiations

2nd July 2012 April 2014 Tender

canceled

Page 46: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

45

SUMMARY OF PASSED MILESTONES

REGARDING EIA PROCESS

Initial EIA

assessment

EIA doc.

published

(+sent to

Germany

and Austria)

Slovakia

requested to

participate on

EIA process

Poland

requested to

participate on

EIA process

All comments

submitted for

assessment

EIA

documentatio

n submitted

Jul 2008 –

Feb 2009 May 2010 Jun 2010 Sep 2010 Dec 2010 Jan-Mar 2011

Second consultation

meeting with Austria

Assessment

ready Public hearing EIA decision

First consultation

meeting

with Bavaria

9th May 2011 May-June 2011 February 2012 June 2012 January 2013

First

consultation

meeting with

Austria

Jan 2011

Page 47: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

Prague

Temelin

Lock chamber

Vrane

Lock chamber

Štěchovice

By-pass

By-pass

By-pass

weir

Kořensko Orlik

Slapy

Kamýk

Page 48: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

47

High consum. scenario

NPP Dukovany till 2027

Keeping limits at ČSA

Low scenario of renewables

No new nuclear

Import of electricity

Natural gas

Gas scenario with limited self sufficiency

Low consum. scenario

NPP Dukovany till 2027

No new nuclear

Keeping limits at ČSA

High scenario of renewables

Renewables

Import of electricity

Green scenario with limited self

sufficiency

Electricity consumption

NPP Decom.

New Nuclear

Lignite mining limits

Renewables development

Key source

Energy balance

Reference scenario

NPP Dukovany till 2037

Three units (2033-2037)

Keeping limits at ČSA

Realistic RES scenario

Nuclear

Full self sufficiency

Optimized scenario according to SEP

Reference scenario

NPP Dukovany beyond 2040

Two units (2030,2032)

Prolomení ÚEL

Realistic RES scenario

Combination

Export remainder

Secure and sefl sufficient

Reference scenario

NPP Dukovany beyond 2040

One unit (2038)

Breaking mining limits

Low scenario of renewables

Possible Import

Conventional sources

Conventional and Economical

Low consum. scenario

NPP Dukovany till 2034

Two units (2033,2038)

Keeping limits at ČSA

High PV, wind

Full self sufficiency

Low carbon sources

Decarburization scenario

STATE ENERGY POLICY HAS BEEN APPROVED IN 2015

Page 49: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

LONG TERM ROLE OF NUCLEAR ENERGY SECTOR

The transition to a low/zero carbon energy sector in 2050 in the context of meeting the

Czech international obligations.

Communication of EU: 2050 – 80% - 95% emissions of GHG compare to 2005 (zero

emission energy sector).

Ensuring energy security (ability of long-term electricity supply even in the absence of

external supply sources).

Creating reserves of uranium fuel for 4 or more years.

Industrial production and export potential.

Nuclear energy industry and infrastructure – 15 000 people, 2 % GDP, potential to double

this share.

The knowledge base of the economy (the leader of hi- tech industrial production,

organizational and structural skills).

High value added, with significant multiplication to other (material R&D, engineering etc.).

48

Page 50: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

CZECH STATE ENERGY POLICY

SUMMARY OF GOALS FOR NUCLEAR ENERGY

Strengthening the role of the nuclear energy in the energy mix of the Czech

Republic, compensation for decreasing production from thermal (coal) power plants

=> up to 50% share on gross electricity generation.

Promote and accelerate the process of negotiation, preparation and execution of

new nuclear units at existing locations with a total capacity to 2,500 MW,

respectively, annual production of around 20 TWh in the period of 2030-2035.

Aim the start of operation around possible shutdown of Dukovany NPP, it means

after 2035.

Creating the conditions for extending the operational period of Dukovany NPP up to

50 (or 60) years.

Ensuring the conditions for the establishment and operation of a secure and

long-term repository of radioactive waste; decide on nuclear repository location

until 2025.

Identification and securing territorial protection for other suitable locations for

potential NPPs.

49

Page 51: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

NATIONAL ACTION PLAN FOR NUCLEAR ENERGY

RECOMENDED STEPS

Immediate continuation of preparatory works for NPP Temelín project and on

NPP Dukovany project

Preparatory works to be done for 2 units on each site (land, permits, licenses)

Current expectation is to build 1 unit on each site only

However with possible extension to 2 units on respective site if needed

Carve out both projects into project companies to enable future entry of the state

or strategic partner

Start discussion with strategic partners

Start the discussion with EU (tender approach, allowable financing models,

assurance of the project feasibility)

Decide and approve the final investment and delivery model in order to assure

feasibility of the project.

Preparation of the Czech legislation modification in order to enable acceleration of

the preparation works

Keep know-how and teams

50

Page 52: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

ČEZ NUCLEAR NEW BUILD PROJECTS

51

New NPP Temelín

SPV (Special Purpose Vehicle) established

Fulfilment of conditions from permission and licenses

issued (EIA, Initial Safety Report/nuclear siting, …)

Related investments (at site, in the region)

Other preparatory works (ČEPS, …)

New NPP Dukovany

Preparation of the project started in 2010

Feasibility study approved

Complex water supply study

EIA process stated

Site investigation under progress

New NPP Jaslovské Bohunice (SK)

JV company (JESS) established in 2009

Joint Czech / Slovak team established

Feasibility study approved

EIA process stated

Site investigation under progress

51

%

49

%

100

%

ČEZB

ČEZ

Page 53: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

PREPARATION AND CONSTRUCTION OF THE NPP IS

LONG JOURNEY AND THEREFORE SHOULD START

IMMEDIATELY

Year

2030 2020 2040

2015 2032

17 years – deterministic

(without risk impact)

2037

22 let – realistic (with risk

impact)

Start of the

project End of commissioning

of the NPP

Fáze:

6-7 years 4-7 years 7-9 years

Construction and

commissioning

Engineering, nuclear

licences, site permit,

construction permit

Selection of the

supplier, EIA, Nuclear

sitting

Start of

construction

52

Page 54: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

NPP DEVELOPMENT AND CONSTRUCTIONS IS A LONG

PROCESS CONTAINING NUMBER OF RISKS Milestone Years

from T0

(risk

free)

Risk and its impact Delay

(in

years)

Delay on

critical

path

Years

from T0

(incl. risk)

EIA process

resulting in

positive EIA

statement

4 Prolongation of the process - complicated process including international hearing and

discussions

Complaint or legal proceeding – strong opposition of NGO , number of obstructions and

complaints

1 0 5

Site permit

(nuclear

regulator)

5,5 Longer preparation of the documentation (need to prepare more information than originally

expected)

Suspension of the process – request for provision of additional information

Law suit based on third party claim

1 0 6,5

EPC tender acc.

to public proc.

law

5,5 Complaint or legal proceeding initiated by rejected of non-successful bidder

Prolongation of the notification process in EC

Prolongation of negotiation and / or of internal approval process

1 1 6,5

Site permit

(ministry of local

development)

7,5 Prolongation of assessment on ministry due to scope and complexity of the project

Suspension of the process - request for provision of additional information

Law suit based on third party claim

0,8 1,8 9,3

Construction

permit (nuclear

regulator)

9,5 Longer preparation of the documentation (need to prepare more information than originally

expected)

Suspension of the process – request for provision of additional information

0,5 2,3 11,8

Construction

permit (ministry

of trade and

industry)

10,5 Prolongation of assessment on ministry due to scope and complexity of the project

Suspension of the process - request for provision of additional information

Law suit based on third party claim

0,5 2,8 13,3

Take over of first

unit 17,5 Delay due to poor performance of Supplier

Delay resulting from change in law

2 4,8 22,3

53

Page 55: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

Rozhodnutí o přípravě jaderných projektů je dnes

rozhodnutím o budování příležitosti, nikoliv o výstavbě

0,00%

2,00%

4,00%

6,00%

8,00%

10,00%

12,00%

14,00%

16,00%

Okamžik

rozhodnutí o

výstavbě

Ilustrativní příklad

Konkrétní

dodavatel

technologie

Investiční

náklady

(%)

54

Page 56: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

PODPORA ROZVOJE JADERNÉ ENERGETIKY V ČR – ČASOVÉ SROVNÁNÍ

Od podzimu 2014 zaznamenán mírný pokles podpory rozvoje jaderné energetiky

v ČR.

55

Q4) Jste Vy osobně pro rozvoj jaderné energetiky v naší republice? (odpovídají všichni respondenti N=500)

(stat. chyba: max. 3,7%) *Pozn.: V letech

1995-1998 a 2010

nerealizováno ZDROJ DO 2012: STEM

56

68

47

6358 59 56

52 54

59 59

6771

54

6467

59

44

32

53

46

36 3329

33

41414648

44414237 41

0

20

40

60

80

100

1994

1995

*

1996

*

1997

*

1998

*

1999

2000

2001

2002

2003

2004

2005

2006

2007

2008

2009

2010

*

2011

2012

2013

2014

2015

%

Určitě + spíše ano Spíše + určitě ne

Pokles podpory JE vlivem havárie v jaderné elektrárně Fukušima I. Pokles podpory JE v důsledku zrušení tendru

na dostavbu ETE.

Pokles podpory JE – může souviset s protesty proti úložištím jaderného odpadu a se zhoršením vnímání bezpečnosti v Evropě a ve světě (terorismus, přírodní katastrofy).

Page 57: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

56 56

Page 58: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

CZECH POWER INDUSTRY ALLIANCE

ŠKODA PRAHA initiative for export of conventional island of the NPPs and

subsequently generally for energy sectors

Initiative substantial also for preparation nuclear projects in ČR (Temelín, Dukovany)

Initiative is also in line with tasks given by the government – Czech government has

approved National Action Plan for Nuclear Energy on 3rd June, 2015. In the chapter

5.3., there is stated the following; Organization of the supply chain:

Although they are private companies owned by various owners, their common interest

is to carry out business in the sector under the powerful control of the state.

Knowledge and the maintenance or development thereof and the involvement of

suppliers are important for the development of the sector as a whole.

It is recommended to initiate the establishment of an organisation which would

associate the industrial undertakings participating in supplies for the nuclear

energy sector. Such an organisation would be a partner of the Committee (with

the representative of the organisation as a member thereof) and could provide for the

transfer of knowledge between the government and the industry, participate in the

assessment of the NAP NE and submit proposals aimed at the Committee and

coordination of members thereof.

ŠKODA PRAHA brings traditional trademark and takes the lead of the Alliance

57

Page 59: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

CZECH POWER INDUSTRY ALLIANCE

EXPORT COORDINATOR OF CZECH DELIVERIES FOR

NUCLEAR POWER PLANTS

Full members:

1. ŠKODA PRAHA a.s.

2. ŠKODA JS a.s.

3. VÍTKOVICE HOLDING, a.s.

4. Doosan Škoda Power s.r.o.

5. SIGMA GROUP a.s.

6. MSA, a.s.

7. I.B.C. Praha spol. s r.o.

Associated members:

1. ALTA, a.s.

2. ZAT a.s.

3. ZVVZ GROUP, a.s.

4. OSC, a.s.

5. KRÁLOVOPOLSKÁ RIA, a.s.

6. Elektro Kroměříž a.s.

CPIA Board:

• Mr. Bodnár – Chairman – Škoda Praha

• Mr. Perlík – Vice-Chairman – Škoda JS

• Mr. Světlík – Member – Vítkovice

• Mr. Koníček – Member – I.B.C. Praha

Potential newcomers:

1. CHEMCOMEX Praha, a.s.

2. FANS, a.s.

3. NOEN, a.s.

4. ETD Transformátory, a.s.

5. ZK – TERMOCHEM s.r.o.

6. JSP, s.r.o.

7. ….

58

Page 60: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

Czech Power Industry Alliance

www.cpia.cz

Page 61: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

DO WE HAVE RESPONSES TO THE FOLLOWING QUESTIONS?

What are the alternatives we have, compared to nuclear. How real are they in the Czech Republic conditions?

Which criteria we are taking into the account (is the current spot price the only criterion we should take into the account)?

What is the social price of the security of supply?

Will we be able to buy electricity at competitive price, if there are no new sources in the Czech Republic?

How the Czech energy sector will look like in 2035 without the investment into new sources?

What is the cost of a black-out in the Czech Republic? How real is the risk?

What is socially acceptable price for electricity and what is current price?

Will not lead postponement of decision on build - up / unsupported build - up new sources to problems, which will be heavy, or impossible manageable in the future?

60

Page 62: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

61

TEMELÍN NOW

Page 63: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

62

TEMELÍN NOW & FUTURE

Page 64: CEZ GROUP: THE LEADER IN POWER MARKETS OF CENTRAL …

THANK YOU FOR YOUR ATTENTION