CEOP4005

10
30 June 2011 ISSUE 5 UNCLASSIFIED UNCONTROLLED COPY IF PRINTED Operational Procedure: Underground Cable Testing: High and Low Voltage Change picture according to document 30 June 2011

Transcript of CEOP4005

Page 1: CEOP4005

30 June 2011

ISSUE 5

UNCLASSIFIED

UNCONTROLLED COPY IF PRINTED

Operational Procedure:

Underground Cable

Testing: High and Low Voltage

Change picture according to document

30 June 2011

Page 2: CEOP4005

OPERATIONAL PROCEDURE - Underground Cable Testing: High and Low Voltage

UNCLASSIFIED CEOP4005

30 June 2011 - Issue 5 Approved By: Group Manager Standards and Demand Management Page 2 of 10

UNCLASSIFIED UNCONTROLLED COPY IF PRINTED

PREPARED BY: Underground Construction and Design Manager

AUTHORISED BY: Group Manager Standards and Demand Management

DOCUMENT NUMBER: CEOP4005 – ISSUE 5

This plan is copyright. No part may be reproduced by any process without written permission,

except as permitted under the copyright act.

DISCLAIMER

1 Essential Energy may change the information in this document without notice. All changes

take effect on the date made by Essential Energy. A print version is always an uncontrolled

copy. Before using this document, please ensure that it is still current.

2 This document may contain confidential information. Restrictions on the use and disclosure

of confidential information by employees are set out in your contract of employment.

Restrictions on the use and disclosure of confidential information by contractors are set out in

your contract of engagement with Essential Energy. Sub-contractors are bound by the

confidentiality provisions set out in their contract with the contractor engaged by Essential

Energy.

2011 ESSENTIAL ENERGY

Page 3: CEOP4005

OPERATIONAL PROCEDURE - Underground Cable Testing: High and Low Voltage

UNCLASSIFIED CEOP4005

30 June 2011 - Issue 5 Approved By: Group Manager Standards and Demand Management Page 3 of 10

UNCLASSIFIED UNCONTROLLED COPY IF PRINTED

CONTENTS PAGE

1 INTRODUCTION ............................................................................................. 4

2 TOOLS AND EQUIPMENT ................................................................................. 4

3 TRAINING ..................................................................................................... 4

3.1 Training, Assessment and Authorisation ........................................................... 4

4 PRELIMINARY CHECKS ................................................................................... 4

4.1 Visual Check ................................................................................................. 4

4.2 Notification ................................................................................................... 4

4.3 Worksite Hazard Identification, Risk Assessment and Control (worksite HIRAC) ..... 4

5 METHOD ....................................................................................................... 5

5.1 High Voltage Cable Tests ................................................................................ 5

5.2 Insulated Resistance Test – Level 1 .................................................................. 5

5.3 High Voltage Test – Level 2 (Paper Lead Cables Only) ........................................ 6

5.4 Delayed Connection to Network ....................................................................... 6

5.5 Low Voltage Cable Test .................................................................................. 7

5.6 Continuity – Test 1 ........................................................................................ 7

5.7 Serving Insulation Resistance – Test 2 ............................................................. 8

5.8 Insulation Resistance – Test 3 ......................................................................... 8

5.9 Method – Streetlighting Cable Tests ................................................................. 8

5.9.1 Polarity Test ............................................................................................. 8

5.10 Failure to Comply .......................................................................................... 9

6 RECORDS ..................................................................................................... 9

7 KEY TERMS AND DEFINITIONS ........................................................................ 9

8 REFERENCES ................................................................................................ 10

9 REVISIONS .................................................................................................. 10

Page 4: CEOP4005

OPERATIONAL PROCEDURE - Underground Cable Testing: High and Low Voltage

UNCLASSIFIED CEOP4005

30 June 2011 - Issue 5 Approved By: Group Manager Standards and Demand Management Page 4 of 10

UNCLASSIFIED UNCONTROLLED COPY IF PRINTED

1 INTRODUCTION

This document proves the high and low voltage cable integrity after installation or jointing

work is completed and before connection or reconnection to the Essential Energy‟s Network.

Such testing and commissioning will be undertaken by people, who are both qualified and

authorised, and the relevant test results will be duly entered into the relevant test report

form (refer to CEOF6022 and CEOF6023). This document is intended for use by Essential

Energy‟s Accredited Service Providers and internal staff for testing of cables before being

energised.

2 TOOLS AND EQUIPMENT

Danger HV Test Signs 1000V DC Megger

Insulating Gloves 500V DC Megger

Insulated Ground Matting Low Voltage Tester

Suitable HV Test Equipment Foster Test Set (For paper cable only)

3 TRAINING

3.1 Training, Assessment and Authorisation

Where there is exposure to risk from electrical apparatus a person undertaking work will be

appropriately qualified, trained and assessed as competent and authorised to carry out the

work.

4 PRELIMINARY CHECKS

4.1 Visual Check

A visual check is carried out by the Authorised Person to ensure that the workmanship of

both the installation of the cable and cable jointing work meets Essential Energy‟s

requirements before being connected to the Network.

4.2 Notification

The Quality Control Coordinator will be notified 3 working days prior to the commencement

of the cable tests. The Accredited Service Provider will be responsible for ensuring that the

completed work is tested and test reports are forwarded to the Quality Control Coordinator

promptly. The Quality Control Coordinator may be present to witness the testing

procedure.

4.3 Worksite Hazard Identification, Risk Assessment and Control

(worksite HIRAC)

Tests on underground cables are potentially hazardous to both personnel undertaking the

test and the general public in the vicinity. A Worksite HIRAC will be carried out, by the

Authorised Person, which will determine the precautions that need to be adopted. For

public areas warning signs may need to be displayed and barricades erected around the test

area (including all exposed cable terminations) prior to commencing any testing activity.

Page 5: CEOP4005

OPERATIONAL PROCEDURE - Underground Cable Testing: High and Low Voltage

UNCLASSIFIED CEOP4005

30 June 2011 - Issue 5 Approved By: Group Manager Standards and Demand Management Page 5 of 10

UNCLASSIFIED UNCONTROLLED COPY IF PRINTED

For HV and LV cable Insulation Resistance tests, a Test Access Permit is not

mandatory if the Insulation Resistance test is performed at a 1000 volts DC or less

and the cable is discharged to earth for a time duration equal to the test time. If an

Access Permit for Testing is deemed necessary after a HIRAC evaluation it will be

completed and issued in accordance with CEOP2045 Access Permits. If currently on a

„Work‟ Access Permit, remove earths and cancel the Access Permit

If the cable has previously been commissioned and connected to Essential Energy‟s

System call System Operations and inform them if you require a Test Access Permit to

test a high voltage cable, and at all times give full details of location, open points etc

Insulating gloves and ground matting to be utilised.

5 METHOD

5.1 High Voltage Cable Tests

Authorised Persons will complete the prescribed tests as specified. All cables must be fully

discharged for a time duration equal to the test time upon completion of each test by means

of discharge function on test equipment or an independent earth.

Test results will be recorded on the HV Underground Cable Test Report form, refer to

CEOF6022.

5.2 Insulated Resistance Test – Level 1

Screen to Earth Test for XLPE insulated cables will record an insulation resistance as

per table below at 500V after one (1) minute. This test will be performed first so as to

assist in the reconnection process of the screen to earth connection

Phase to Screen/Earth, and Phase to Phase testing requires the Authorised Person to

measure insulation resistance at 1.kV after one (1) minute duration. Minimum IR as

per table below.

Insulation Resistance (IR) Values for HV Cables

Cable Rated

Voltage kV

Minimum IR

@ 1kV DC New

Cables

Ph-Ph, Ph-E

Minimum IR

@500V

Screen – E

New Cables

Minimum IR

@ 1kV DC

Existing Cables

Ph-Ph, Ph-E

Minimum IR

@ 500V

Screen – E

Existing Cables

11kV 400 megohms 100 megohm 100 megohms 1.0 megohm

22kV 400 megohms 100 megohm 100 megohms 1.0 megohm

33kV 800 megohms 100 megohm 200 megohms 1.0 megohm

66kV 800 megohms 100 megohm 200 megohms 1.0 megohm

132kV 800 megohms 100 megohm 200 megohms 1.0 megohm

Note: Insulation Resistance Tests will be applied for a period of 1 minute for cables less

than 100 m in length and 3 minutes for cables greater than 100 m in length.

Page 6: CEOP4005

OPERATIONAL PROCEDURE - Underground Cable Testing: High and Low Voltage

UNCLASSIFIED CEOP4005

30 June 2011 - Issue 5 Approved By: Group Manager Standards and Demand Management Page 6 of 10

UNCLASSIFIED UNCONTROLLED COPY IF PRINTED

5.3 High Voltage Test – Level 2 (Paper Lead Cables Only)

If the insulation resistance results for Paper Lead (PLY) cables are below the prescribed

minimum values, a high voltage DC test will be applied. See CEOF6022 HV Underground

cable Test Report for the prescribed minimum values. If prescribed minimum values are

required for higher voltage Paper Lead (PLY) cables, contact Quality Control Coordinator.

It is performed by applying a DC voltage between phases and between phases and

sheath. When making these tests, the voltage will be increased gradually to the full

specified value and be maintained for 15 minutes. After 15 minutes, the leakage

current should be steady or falling and less then 0.1mA with no transient spikes

occurring. Higher readings may be acceptable provided they are steady. For further

advice, contact Quality Control Coordinator

Commissioning new cables – a cable not previously energised will be tested by

applying:

11kV cable 22kV cable

34kV DC between phases; and 68 kV DC between phases; and

25kV DC between phases and sheaths 50 kV DC between phases and sheath

The 3 phases can be bonded for the phase to sheath test and only 1 test made unless a

failure occurs. If a failure occurs, each phase will be tested individually to determine the

faulty phase.

Recommissioning Existing Cables – where a cable that has been in service, is to be

tested prior to recommissioning, it will be tested at approximately 75% of the voltages

for a new cable, i.e.

The phases can be bonded for the phase to sheath test, and only one test made

unless a failure occurs.

5.4 Delayed Connection to Network

Insulation Integrity Test

If a cable is to be connected to the Network and the testing has occurred within 4 weeks

preceding this, a visual inspection of the cable location will be undertaken, for any obvious

signs that cable insulation integrity may have been compromised. After 4 weeks has

elapsed the standard test must be repeated before connection is carried out. This time

frame also applies to cables which have been removed from service for repair or have been

decommissioned.

If live line techniques are to be utilised for cable connection a documented cable test must

be carried out (CEOF6022 HV Underground Cable Test Report) to determine the insulation

integrity of the cable prior to carrying out live line technique.

11kV cable 22kV cable

26kV DC between phases; and 52kV DC between phases; and

15kV DC between phases and sheath 30kV DC between phases and sheath

Page 7: CEOP4005

OPERATIONAL PROCEDURE - Underground Cable Testing: High and Low Voltage

UNCLASSIFIED CEOP4005

30 June 2011 - Issue 5 Approved By: Group Manager Standards and Demand Management Page 7 of 10

UNCLASSIFIED UNCONTROLLED COPY IF PRINTED

If an Insulation Integrity test is to be undertaken the live line gang must inform System

Operations of the insulation integrity test before the live line work is carried out. Once the

integrity of the insulation is proven, inform System Operations of the result (if the cable

fails the test, commissioning of the cable will not proceed any further and Quality Control

Coordinator will be contacted for further advice).

Live Line work will be carried out as per switching sheet.

The Standard Tests, Phase to Phase and Phase to earth:

Measure insulation resistance at 1kV after one (1) minute.

Acceptable values for existing cables may be used as cable will now be connected to

switchgear etc.

A Phase to B Phase Greater than 100 megohms

B Phase to C Phase Greater than 100 megohms

C Phase to A Phase Greater than 100 megohms

A Phase to Screen and Earth Greater than 100 megohms

B Phase to Screen and Earth Greater than 100 megohms

C Phase to Screen and Earth Greater than 100 megohms.

All cables must be fully discharged for a time duration equal to the test time upon

completion of each test by means of discharge function on test equipment or an

independent earth.

The purpose of this test is to prove that the integrity of the insulation has not been

damaged since the original test date.

The energising/de-energising of an underground cable which is to be directly connected to

the overhead system and is isolated from the transformer must only be undertaken using a

temporary EDO (cut-out tool) fitted with a 25 amp K class fuse element.

5.5 Low Voltage Cable Test

Authorised Persons will complete the prescribed tests as specified. All cables must be fully

discharged for a time, duration equal to the test time upon completion of each test by

means of the discharge function on test equipment or an independent earth. Test results

will be recorded on CEOF6023 LV Underground Cable Test Report form.

5.6 Continuity – Test 1

The continuity test (DC resistance measurement) will be carried out on each low voltage

circuit from the end of each branch or open point, to the origin of the circuit.

Step 1 At the circuit origin, to be tested, (normally at the Padmount transformer), connect

each of the phase conductors to the neutral of the cable circuit in turn, ensuring all

MEN points are disconnected.

Step 2 At the remote ends of the circuit, check for continuity between each phase and

neutral.

Results very close to a short circuit value should be obtained.

Step 3 At the circuit origin (normally at the Padmount transformer) connect the phase

conductors together, remaining separate from neutral conductor.

Alternatively, if cable is to be energised immediately after testing, neutral polarity

may be tested by „lamping out‟ conductors at each pit or pillar.

Page 8: CEOP4005

OPERATIONAL PROCEDURE - Underground Cable Testing: High and Low Voltage

UNCLASSIFIED CEOP4005

30 June 2011 - Issue 5 Approved By: Group Manager Standards and Demand Management Page 8 of 10

UNCLASSIFIED UNCONTROLLED COPY IF PRINTED

Step 4 Proceed to each pit or pillar on the circuit and check neutral polarity with 500V

megger. If any reading other than an open circuit is recorded between the

connected phases and neutral, it will mean a phase has been connected to the

neutral which will be located, rectified and retested before connection to Essential

Energy‟s Distribution System.

5.7 Serving Insulation Resistance – Test 2

The integrity of the covering sheath will be proved by bonding the 4 cores and applying

500V DC for 1 minute between the bonded cores and earth. The minimum insulation

resistance will be 200 Megohms for new cables and 20 Megohms for cables older than 1

year.

If the cables fail this test, the point of failure will be located, rectified and retested before

connection to Essential Energy‟s Distribution System.

5.8 Insulation Resistance – Test 3

Ensuring all cores are separated from each other and using a 500V instrument measure the

insulation resistance between 2 cores in rotation, i.e.: N-R, R-W, N-W, R-B, N-B, B-W.

The minimum insulation resistance will be 200 Megohms for new cables and 20 Megohms

for cables older than 1 year.

If a cable fails to achieve the required minimum values, contact Quality Control Coordinator

or the Principal‟s Superintendent for further advice.

Ensure all MEN points have been reconnected.

5.9 Method – Streetlighting Cable Tests

5.9.1 Polarity Test

CHECK all connections in the service pit/pillar and ensure they are correct

ENSURE primary fuse is removed or circuit breaker is switched off, incoming neutral

isolated, earths disconnected, PE cell and tubes/globes removed

CONFIRM visually the colour coding of internal wiring at terminal block is correct.

Ensure terminal block is not earthed at light fitting

USING 500V megger measure insulation resistance between internal wiring and

standard (reading to exceed 1 megohm), test for short circuits and reconnect earth if

applicable

TEST and identify streetlight active and neutral. Connect service neutral to streetlight

neutral first, then service active to streetlight active

CHECK all connections in the street light column and ensure they are correct

INSERT PE cell, tube/globe, fuse or circuit breaker. Ensure streetlight operates

CONDUCT “final test” with streetlight on measuring between an independent earth and

neutral and earth or metal work for any voltage.

Page 9: CEOP4005

OPERATIONAL PROCEDURE - Underground Cable Testing: High and Low Voltage

UNCLASSIFIED CEOP4005

30 June 2011 - Issue 5 Approved By: Group Manager Standards and Demand Management Page 9 of 10

UNCLASSIFIED UNCONTROLLED COPY IF PRINTED

5.10 Failure to Comply

If a cable or associated equipment fail a prescribed test, the Accredited Service Provider will

be responsible for the location of the fault, repair or replacement of faulty cable and/or

accessories, and any subsequent testing, as directed by Quality Control Coordinator.

Prior to the application of any fault location methods which have the potential to affect the

long-term insulation integrity of the installation, the Authorised Service Provider will submit

to Essential Energy a proposed fault location methodology. No fault location work will

proceed until Essential Energy‟s Quality Control Coordinator has given approval.

6 RECORDS

The relevant test results will be duly entered on the relevant Test Report form, (See

CEOF6022 and CEOF6023.)

The Cable Test Report will be sighted by the person carrying out the commissioning who

completes the clearance certification by signing, therefore accepting the new asset.

The person carrying out the commissioning will quote the Cable Test Report No. to System

Operations when requesting energisation of new asset. This will be System Operations

record of compliance until paper copy is received.

The Quality Control Coordinator is also responsible for correct distribution of Cable Test

Report copies.

1 Quality Control Coordinator – WHITE

2 Project File – BLUE

3 System Operations – YELLOW

4 Book copy – PINK.

7 KEY TERMS AND DEFINITIONS

Accredited Service Provider: refers to companies/sole traders who have gained

accreditation through the Department of Fair Trading allowing them to perform contestable

works.

Authorised Person: means a person with technical knowledge or sufficient experience who

has demonstrated competency and has been approved by Essential Energy to carry out

specific duties with the supply or use of electricity.

Contestable Works: those works where the customer has a choice of Service Provider.

Continuity test: test to ensure correct cable core identity and continuity.

Essential Energy’s Network: Essential Energy Transmission and Distribution System

Assets.

Insulation Resistance: quantified measurement of insulation value.

Polarity test: test to ascertain correct identification and connection of active and neutral

conductors.

Principal’s Superintendent: Project Manager of the Accredited Service Provider.

Quality Control Coordinator: is the person nominated by Essential Energy with the

responsibility for auditing construction works to Essential Energy‟s standards and quality.

System Operations: Essential Energy 24 hour Operational Control Centre.

Page 10: CEOP4005

OPERATIONAL PROCEDURE - Underground Cable Testing: High and Low Voltage

UNCLASSIFIED CEOP4005

30 June 2011 - Issue 5 Approved By: Group Manager Standards and Demand Management Page 10 of 10

UNCLASSIFIED UNCONTROLLED COPY IF PRINTED

8 REFERENCES

CEOF6022 – HV Underground Cable Test Report

CEOF6023 – LV Underground Cable Test Report

CEOP2018 – Polarity and Neutral Identification Testing

CEOP2045 – Access Permits

CEOP8029 – Network Management Plan

CEOP8030 – Electrical Safety Rules

Olex Cables – Technical Informative PT-I 316 – 24th May 2001

Electricity Supply (Safety and Network Management) Regulation 2002

9 REVISIONS

Revision

Number Section Details of Changes in this Revision

2 All Sections Reduction in Meggering voltages to align with Manufacturer‟s

recommendations.

3

All Sections Document changed to Plain English

Clause 8.1.3

Second paragraph was………………….If live line techniques are to

be utilised for cable connection it maybe prudent to undertake

an insulation integrity test regardless of the elapsed time

period.

Definitions

Accredited Service Provider was……………. refers to

companies/sole traders who have gained accreditation

through NSW Ministry of Energy and Utilities allowing them to

perform contestable works.

4

Clause 5.6

Step 1, Sentence 1 added, ……….. connect “each of” the phase

conductors to the neutral of the cable circuit “in turn”………

Step 2 was

“Each phase and neutral, and

Each phase”

Clause 6

Second paragraph was ……………. The Cable Test Report will

be signed by the Quality Control Coordinator……………..

Third paragraph, first sentence was….. The Quality

Coordinator………………

5 All Update to rebrand to Essential Energy