Central Hollywood Plaza Christian Brothers...
Transcript of Central Hollywood Plaza Christian Brothers...
Design of Central Hollywood Plaza Midtown
Memphis, Tennessee
A Project Assignment Submitted in Partial Fulfillment of the
Requirements for CE 331 Junior Project
By: Buccaneer Engineering Diego Alonso Acosta
Rafael Jahir Arce Maximiliano Gomez-Pedro
Kolbie Anne Seay Victor Leroy Bryan Smith
Department of Civil and Environmental Engineering
Christian Brothers University 650 East Parkway South
Memphis, Tennessee 32104
Central Hollywood Plaza Christian Brothers University Table of Contents CE 331 Nov. 2019____________________________________________________________________________________
(Page Left Blank)
1
Central Hollywood Plaza Christian Brothers University Table of Contents CE 331 Nov. 2019____________________________________________________________________________________
Table of Contents
1. Introduction 8
2. Background 10
3. Site Layout 12
4. Transportation Design 14 4.1 Traffic Analysis and Signalization 14 4.2 Parking Lot Layout 15
4.2.1 Alternative 1: Quarterly-divided 15 4.2.2 Alternative 2: Half-divided 17
4.3 Access Road Design 18 4.4 Drawings 19 4.5 Cost Estimate 19 4.6 Preferred Design Analysis 19
5. Water Resource / Land Development Design 20 5.1 Existing Terrain 20 5.2 Detention Basin 20
5.2.1 Alternative 1: Wet Detention Basin 21 5.2.2 Alternative 2: Dry Detention Basin 22
5.3 Land Development 24 5.4 Piping 26 5.5 Storm Water Pollution Prevention Plan 26 5.6 Drawings 26 5.7 Preferred Design Analysis 26
6. Environmental Design 28 6.1 Construction Environmental Management Plan 28 6.2 Wastewater 29
6.2.1 Alternative 1: Traditional Centralized Wastewater System 29 6.2.2 Alternative 2: Decentralized Wastewater System 29
6.3 Stormwater 30 6.4 Solid/Hazardous Waste 30
6.4.1 Alternative 1: Lighter to Heaviest 31 6.4.2 Alternative 2: Least Amount of Turns 31
2
Central Hollywood Plaza Christian Brothers University Table of Contents CE 331 Nov. 2019____________________________________________________________________________________
6.6 Drawings 31 6.5 Cost Estimate 31 8.5 Preferred Design Analysis 32
7. Structural Design 34 7.1 Constraints 34 7.2 Alternative 1: Steel Structure 34
7.2.1 Load Determination 35 7.2.2 Roof Deck Selection/Design 35 7.2.3 Roof Beam Design 36 7.2.4 Roof Girder Design 36 7.2.5 Column Design 37 7.2.6 Connection Design 37 7.2.7 Foundation Design 38
7.3 Alternative 2: Reinforced Concrete Superstructure 38 7.3.1 Load Determination 38 7.3.2 Roof Deck Selection/Design 39 7.3.3 Roof Beam Design 39 7.3.4 Roof Girder Design 39 7.3.5 Column Design 39 7.3.6 Connection Design 40 7.3.7 Foundation Design 40
7.4 Interior 40 7.5 Architectural Considerations 40 7.6 Drawings 41 7.7 Preferred Design Analysis 41
8. Geotechnical Design 42 8.1 Soil Data 42 8.2 Foundation of Small Structure 42
8.2.1 Alternative 1: Foundation for Steel Structure 42 8.2.2 Alternative 2: Foundation for Concrete Structure 44
8.3 Retaining Wall 45 8.3.1 Alternative 1: Mechanically Stabilized Earth Wall 45 8.3.2 Alternative 2: Gabion Wall 46
8.4 Drawings 47
3
Central Hollywood Plaza Christian Brothers University Table of Contents CE 331 Nov. 2019____________________________________________________________________________________
8.5 Preferred Design Analysis 47
9. Cost Estimate 48
10. Final Design 50
11. Conclusion 52
12. Schedule 54
Acknowledgments 56
References 58
4
Central Hollywood Plaza Christian Brothers University Table of Contents CE 331 Nov. 2019____________________________________________________________________________________
(Page Left Blank)
5
Central Hollywood Plaza Christian Brothers University Table of Contents CE 331 Nov. 2019____________________________________________________________________________________
List of Figures
Figure 2-1. Site Location 10
Figure 3-1. Tentative Proposed Site Layout 13
Figure 4.2.1-1. Quarterly-divided Lot 16
Figure 4.2.2-1. Half-divided Lot 18
Figure 5.2.1-1. Wet Detention Basin Design 22
Figure 5.2.2-1 Example of Dry Detention Basin 23
Figure 5.2.2-2. Dry Detention Basin Design 24
Figure 5.3-1. Gravel Entry and Exit 25
Figure 7.2-1. Steel Structure Example 35
Figure 7.2.2-1. Typical Steel Roof Section 36
Figure 7.2.4-1. Open Web-Steel Joist 37
Figure 7.3-1 Reinforced Concrete Structure Example 38
Figure 8.2.1-1. Spread Footing Foundation 43
Figure 8.2.2-1. Mat Foundation 44
Figure 8.3-1. Location of Retaining Wall. 45
Figure 8.3.1-1. MSE Wall Example 46
Figure 8.3.2-1. Gabion Wall Example 46
Figure 11-1. Proposal Draft and Document Schedule 54
6
Central Hollywood Plaza Christian Brothers University Table of Contents CE 331 Nov. 2019____________________________________________________________________________________
(Page Left Blank)
7
Central Hollywood Plaza Christian Brothers University Section 1: Introduction CE 331 Nov. 2019____________________________________________________________________________________
1. Introduction
A shopping center is to be constructed on the specified site located at the corner of
Central Avenue and Hollywood Street. The site will include a large department store and two
smaller structures. It is also assumed that the site currently has no existing structures of any kind.
Buccaneer Engineering has been tasked with designing all of the major components of
the project, which include the structural, geotechnical, environmental, transportation, and water
resource designs. Each project team member has been assigned a specific component of
designing using knowledge and skills obtained from relevant courses. Every component will
include two alternatives (i.e. concrete structure and steel structure). The project team will also be
responsible for obtaining any necessary information about the site, such as existing topographic
conditions, soil data, local building codes, and more from corporate sponsors Allen & Hoshall,
Inc.
The final design of the project will be dependent upon all of the preferred design
alternatives for each component. All of the team members will converge their preferred designs
into one grand design. The goal for Buccaneer Engineering is to provide to their client with the
most safe, economical, efficient, and environmentally friendly overall design.
8
Central Hollywood Plaza Christian Brothers University Section 1: Introduction CE 331 Nov. 2019____________________________________________________________________________________
(Page Left Blank)
9
Central Hollywood Plaza Christian Brothers University Section 2: Background CE 331 Nov. 2019____________________________________________________________________________________
2. Background
The site selected for this development is located in Midtown Memphis and is surrounded
by Avery Avenue, Flicker Street, Central Avenue, and Hollywood Street. This location is ideal
for a department store anchored development due to its proximity to local areas of interest and
surrounding neighborhoods. Immediately surrounding the site is The Children's Museum of
Memphis, Christian Brothers University, Memphis Fairgrounds, the Liberty Bowl Stadium, and
several residential neighborhoods. This development would offer shopping and amenities within
walking distance for the surrounding neighborhoods and the students of Christian Brothers
University.
Figure 2-1. Site Location.
Large amounts of traffic is generated during University of Memphis football games at the
Liberty Bowl, Memphis Fairground activities, and various festivals in the greater surrounding
neighborhoods. Additionally, located in the greater surrounding area are the established, popular
10
Central Hollywood Plaza Christian Brothers University Section 2: Background CE 331 Nov. 2019____________________________________________________________________________________
neighborhoods of Cooper-Young and Overton Square as well as Overton Park. This location also
allows easy access to Downtown Memphis to the West, East Memphis to the East, and the
Memphis International Airport to the South.
The site is currently home to a telecommunications maintenance facility, the Shelby
County Board of Education, and Tobey Park. For the purpose of the project, the site will be
assumed as undeveloped, open land.
11
Central Hollywood Plaza Christian Brothers University Section 3: Site Layout CE 331 Nov. 2019____________________________________________________________________________________
3. Site Layout
This location chosen is ideal for a large “box store” due to its proximity to areas of high
traffic areas as well as residential ones. The large box store will be located in the Northeast
section of the lot, adjacent to the Avery Avenue and Flicker Street intersection. Apart from the
larger structure, the preliminary project information includes the erection of two smaller
structures, which locations will be determined upon acquirement of further information. One of
the locations will be a fast food restaurant while the second structure is yet to be determined.
The addition of structures that will attract vehicular and pedestrian traffic to the site will
result in thorough planning for the accommodation of such. Parking and island locations will be
analyzed and discussed in Section 4.2 of this report. These areas will be determined upon further
knowledge of structure location and dimensions. These will also rely on information from the
water resources/land development team for further information of the location of water retention
pond.
By the addition of pavement and concrete for lots, walkways, and structures, the runoff of
water will increase. The results of such a large area accounting for minimal water absorption will
require the water resources team to develop a plan to minimize this impact. A water retention
pond will be a great alternative for this problem. Further information on this aspect will be found
in Section 5.2 of this report.
The topography of the land as well as the existing roads along the site require the project
team to introduce a retaining wall. To be located on the Southern portion of the lot, the retaining
wall will provide support for the extreme grade change in this portion of the site. Information
from the existing terrain and location of certain structures will be needed in order to develop a
12
Central Hollywood Plaza Christian Brothers University Section 3: Site Layout CE 331 Nov. 2019____________________________________________________________________________________
solution to this problem. Details of this aspect of the project will be found in Section 8.3 of this
report.
Figure 3-1. Tentative Proposed Site Layout.
13
Central Hollywood Plaza Christian Brothers University Section 4: Transportation CE 331 Nov. 2019____________________________________________________________________________________
4. Transportation Design
The transportation engineering portion of the project will involve the traffic analysis and
signalization due to the presence of the buildings, the parking lot layout depending on the
positioning of such, as well as a possible design of an access road onto the proposed site. This is
a highly collaborative aspect of the project, considering much of the layout is dependent on other
factors. Extensive communication and collaboration among all engineers should be prioritized
for the design to be appropriate. Cost will be analyzed and implemented with each required
alternative.
4.1 Traffic Analysis and Signalization
The traffic analysis will be conducted along Central Avenue, South Hollywood Street,
Avery Avenue, Flicker Street, and all adjoining roads. These studies will develop a basis for
needed signalization due to expansion of vehicular and pedestrian traffic along and within the
site. The analysis will include the use of a capacity software. The addition of a large supermarket
along with smaller structures is bound to increase traffic along the proposed site. The placement
of the site will create a much higher traffic volume along South Hollywood Street. Both Avery
and Central Avenue will also have volume increases. If the traffic volume is studied to be high
enough around the perimeter roads, possible widening of roads and/or dedicated left turn lanes
must be considered. All changes to the design of roads, considering volume numbers, will be a
factor on signalization choices.
If permitted, traffic data will be obtained from the City of Memphis or private entities. In
the case that this is not possible, a viable alternative will be to evaluate these by having actual
vehicle counts for a short period of time and developing an estimate depending on the time of
14
Central Hollywood Plaza Christian Brothers University Section 4: Transportation CE 331 Nov. 2019____________________________________________________________________________________
day. The magnification of these numbers because of the increase of traffic volume in the
proposed area will be the determining factor in the ultimate design.
4.2 Parking Lot Layout
The parking lot layout will be dependent on positioning of structures and points of access
and egress for structures and overall market area. The proximity to residential areas will be
accounted for in terms of pedestrian facilities such as sidewalks, crosswalks, and curb ramps.
These will be designed considering guidelines under Public Rights-of-Way Accessibility
Guidelines provided by the Policy on Geometric Design of Highways and Streets (Green Book).
The parking lot should accommodate sufficient lot spaces and clearance for commercial vehicle
use throughout the site. Positioning of signage and lighting will be studied with sufficient
alternatives throughout the site being developed. Specifications for parking, loading, marking,
curbs, queuing, buffering, etc. will be obtained from Article 4 of the Memphis Unified
Development Code (UDC). Thickness of pavement must be developed and will be dependent on
the amount and type of vehicular traffic along the site, soil characteristics, climate, performance
of pavement in the area, availability of materials, maintenance, and service-life costs. At least
two design alternatives for parking lot layout shall be developed to accommodate for changes
throughout the design process.
4.2.1 Alternative 1: Quarterly-divided
If the proposed restaurant is to be placed in the Southwest corner of the lot, a possible
alternative of the site is to split it into four smaller subsections. These would be broken up by
two major parking lot pathways, with one spanning from South Hollywood St. to Flicker St. and
the other spanning from Central Ave. to Avery Ave. The reasoning for this is to allow maximum
15
Central Hollywood Plaza Christian Brothers University Section 4: Transportation CE 331 Nov. 2019____________________________________________________________________________________
potential parking for the larger structure, which will be located on the Northeast corner of the
proposed site. Possible future erection of a gas station belonging to the large supermarket could
also fit on the top left quadrant if high volumes are achieved with the erection of such store. This
would be possible with the choice of Alternative 1. With the other two structures located in the
Southwest corner of the lot, the traffic volume will be distributed throughout the area.
The detention pond will be located in the Southeast corner of the lot. This will have to be
carefully placed as seepage could become an issue for the geotechnical engineer designing the
retaining wall. A possible plan is to have the detention pond adjacent to the North side of the
Southeast quadrant and implementing a recreation area on the Southmost section. This is
depicted in Figure 4.2.1-1.
Figure 4.2.1-1. Quarterly-divided Lot.
16
Central Hollywood Plaza Christian Brothers University Section 4: Transportation CE 331 Nov. 2019____________________________________________________________________________________
4.2.2 Alternative 2: Half-divided
The proposed site lot layout would be divided into two major halves as pictured in Figure
4.2.2-2. By focusing on keeping most of the high traffic flow on the North portion of the lot,
Buccaneer Engineering decided upon placing the two small structures on the Northwest corner of
the lot, opposite to the department store located on the Northeast corner of the site as already
established. The placement of the smaller structures in proximity to the larger retail store allows
for simplified logistics in terms of public service vehicle flow, parking space layout, as well as
pedestrian and bicycle traffic flow.
The portion on the South of the proposed area will include the detention basin as
designed by the water resources engineer. This area of land will be majorly surrounded by
environmentally friendly landscape. A possible park with a walking trail was one of the ideas
thoroughly discussed among the engineering team involved.
The proposed layout of this alternative will be to ease the overall access and mobility
plans of the center. By addressing the parking layout in a comprehensive and strategic manner
for the entire proposed lot, the grouping of structures with commonalities provided better flow.
The current layout will also support long-term development for an increase in possible structures.
17
Central Hollywood Plaza Christian Brothers University Section 4: Transportation CE 331 Nov. 2019____________________________________________________________________________________
Figure 4.2.2-1. Half-divided Lot.
4.3 Access Road Design
Possible alternatives for the design and placement of an access road will be developed.
The positioning of such will be dependent on the location of structures and should be analyzed to
facilitate incoming and outgoing volume and clearance depending on minimum turning path of
motor vehicles. Guidelines provided by the Policy on Geometric Design of Highways and Streets
will be followed. This will assure that the American Association of State Highway and
Transportation Officials (AASHTO) requirements are met. The Tennessee Department of
Transportation (TDOT) requirements should be studied and met as well.
18
Central Hollywood Plaza Christian Brothers University Section 4: Transportation CE 331 Nov. 2019____________________________________________________________________________________
4.4 Drawings
Detailed drawings for both alternatives will be produced. These drawings will include all
necessary plan views. This will be done using AutoCad.
4.5 Cost Estimate
Detailed cost estimates for both alternatives will be developed regarding cost of
materials, equipment and labor for construction, among other necessary factors
4.6 Preferred Design Analysis
The final design will be based on safety, cost, and efficiency of design.
19
Central Hollywood Plaza Christian Brothers University Section 5: Water Resource / Land Development CE 331 Nov. 2019____________________________________________________________________________________
5. Water Resource / Land Development Design
The water and land development aspect of this construction site will consist of modifying
the existing terrain, storm water drainage, piping, grading due to the building, and sediment
control. Modifying existing terrain will consist of grading and using the topography to the
company’s advantage. Storm water drainage will consist of adding swells, curb and gutter, or
inlets leading to a storm water basin. Sediment control will consist of ensuring sediment does not
exit the construction site in any manner. Buccaneer Engineering will also be responsible for
access to clean water and piping into new structures (see Section 6.2 for wastewater piping).
5.1 Existing Terrain
The current flow of water in the topography shows the water shifting to the Northeast
corner of the site, meaning that the existing terrain will have to be graded to a minimum slope to
direct water runoff into an inlet, a wet detention basin, or a dry detention basin. The land will
have to be graded for the water to flow from the Northwest area of the site to the Southeast area .
5.2 Detention Basin
A detention basin will be temporarily used during construction to prevent water and
sediment runoff. The primary objective is to reduce peak flow discharge and slow the storm
water runoff for a property or development, therefore, reducing flooding downstream. The
secondary objective is to remove suspended sediment, trash, debris, oil, grease, and other
pollutants in order to protect the water quality of Memphis and Shelby County streams and
channels.
20
Central Hollywood Plaza Christian Brothers University Section 5: Water Resource / Land Development CE 331 Nov. 2019____________________________________________________________________________________
5.2.1 Alternative 1: Wet Detention Basin
Wet detention basin satisfies both storm water detention and storm water quality
requirements. According to Shelby County Stormwater Management Manual Volume 3, a wet
detention basin can be enhanced with other stormwater treatments, such as a pretreatment
sediment forebay, baffle box, or storm water quality inlet. A wet detention basin is, generally,
more effective than a dry detention basin at allowing sediments and other pollutants to
completely settle. According to Shelby County Stormwater Management Manual Volume 3,
Outlets structure peak release rate for the 10-year, 24-hour duration storm shall not exceed the
pre-development peak runoff rate, emergency outflow capable of handling 100-year post
development discharge.
Wet detention basins have multiple benefits for passive recreation during dry periods
such as trails, fields, canoeing, etc. Wet detention basins are recommended for large regional
detention facilities, and large areas mainly have minimum base flow. Stormwater coming from
pavement or rooftops must be treated in order to reduce the thermal impacts to the stream,
therefore, the basin will need to be located away from sunlight by using buildings as shades or
using trees.
The storage volume can be divided into two things a live detention storage and pool
storage. The live detention storage provides peak flood control, erosion control and treatment
benefits. Sediment forebay will be recommended in the design, wherever the storm water runoff
enters the wet detention basin. The permanent pool storage provide a quiescent volume for
settling particulate contaminants and the uptake of dissolved contaminants by aquatic plants
between storms.
21
Central Hollywood Plaza Christian Brothers University Section 5: Water Resource / Land Development CE 331 Nov. 2019____________________________________________________________________________________
Figure 5.2.1-1. Wet Detention Basin Design.
According to the Shelby County Stormwater Management Manual Volume 3,
design flow paths to minimize potential short-circuiting by locating the inlets as far away form
the outlet structure as possible.
5.2.2 Alternative 2: Dry Detention Basin
A dry detention basin is a common method for storm water detention; this is applicable
for small or large developments. Dry detention ponds are easy to design and construct and, with
adequate inspections and maintenance, are long lasting and durable. The design for a dry
detention pond must be designed to have adequate detention storage, and outlet structures.
22
Central Hollywood Plaza Christian Brothers University Section 5: Water Resource / Land Development CE 331 Nov. 2019____________________________________________________________________________________
Figure 5.2.2-1. Example of Dry Detention Basin .
Storm water runoff that falls onto rooftops and pavement should be detained and treated
in order to reduce high temperature impacts into the streams, this can be prevented by using trees
or buildings for shade. Memphis and Shelby County require volume control of the 2-year and
5-year rainfall events. According to Shelby County Stormwater Management Manual Volume 3,
Outlets structure peak release rate for the 10-year, 24-hour duration storm shall not exceed the
pre-development peak runoff rate, emergency outflow capable of handling 100-year post
development discharge. The outlet structure must be made out masonry or concrete along with
multiple weirs in order to release the designed storm at pre-development rate. As shown in
Figure 5.2.2-2, the length to width ratio of a basin is preferable to be 3:1.
In order to prevent soil erosion strong growth on vegetation on the side slopes will be
necessary. Steep slopes, particularly on embankments will help cause soil erosion and therefore
23
Central Hollywood Plaza Christian Brothers University Section 5: Water Resource / Land Development CE 331 Nov. 2019____________________________________________________________________________________
reduce the effectiveness of a dry detention basin with respect to water quality. Avoid locating
detention basin above or below steep slope die to impound water may occur and create slope
stability problems.
The best way to maintain a dry detention pond is to do regular inspections especially
after heavy rainfall, remove trash and debris after rain events, check outlet structure for clogging,
removing sediment when aximmulation becomes noticeable (1”-2”). Maintaining a thick and
healthy vegetation is encouraged along with it being mowed and trimmed.
Figure 5.2.2-2. Dry Detention Basin Design.
5.3 Land Development
Tennessee Erosion Prevention and Sediment Control will need to be implemented. Silt
fencing will need to be placed all around the construction site to prevent any kind of sediment
from leaving the site. Gravel entry and exit points (as shown in Figure 5.3-1) will need to be
24
Central Hollywood Plaza Christian Brothers University Section 5: Water Resource / Land Development CE 331 Nov. 2019____________________________________________________________________________________
placed to prevent sediment from exiting the site on vehicles. The gravel entry and exit will be a
minimum length of 50 feet and a minimum width of 20 feet. General aggregate should be
crushed, washed, and well-graded rocks, with 2” to 3” aggregate, at a depth of 6” according to
the Shelby County Stormwater Management Manual Volume 3. According to the topography, the
flow of water will be leading to the Northeast area of the construction site where a large grocery
store will be constructed. The water will need to be shifted to the Southeast corner of the
construction site for the water to flow into the desired direction. The terrain will also need
grading.
Figure 5.3-1. Example of Gravel Entry and Exit.
25
Central Hollywood Plaza Christian Brothers University Section 5: Water Resource / Land Development CE 331 Nov. 2019____________________________________________________________________________________
5.4 Piping
Water piping for this site will need to be precariously laid out to where it does not
overlap with existing pipes or electrical lines. It will also need to be placed around and not
underneath structures. If any problems were to occur in the future, the pipes will need to be made
accessible to the maintenance and repair teams without the delay of traffic in the area. The piping
from the buildings will also need to be connected to existing water lines, manholes, and inlets.
5.5 Storm Water Pollution Prevention Plan
The purpose of Storm Water Pollution Prevention Plan is to identify Best Management
Practices (BMPs) the facility is using to reduce the pollutants in storm water. See Section 6.2 for
further information.
5.6 Drawings
Detailed drawings for both alternatives will be produced. These drawings will include all
necessary plan views, side views, and cut sections. This will be done using AutoCAD.
5.7 Preferred Design Analysis
The final design will be based on the safety, final cost, and efficiency
26
Central Hollywood Plaza Christian Brothers University Section 5: Water Resource / Land Development CE 331 Nov. 2019____________________________________________________________________________________
(Page Left Blank)
27
Central Hollywood Plaza Christian Brothers University Section 6: Environmental CE 331 Nov. 2019____________________________________________________________________________________
6. Environmental Design
The environmental impact in the construction and maintenance of Central Hollywood
Plaza is to be monitored by the environmental engineer. The construction of the project will
impact the surrounding environment by sound and air pollution, and hazardous contaminating
procedures. The environmental engineer is to propose a construction management plan to ensure
that the environmental coordination of contractors and designers is kept to standards. In the
completion of the project design, the maintenance of wastewater, stormwater and
solid/hazardous waste will be necessary. The design of a sanitary sewer layout connecting to the
existing Shelby County sewer line will be proposed in accordance to the layout of any structures
within the site. By the completion of the parking lot layout, a storm water sewer system will be
designed. This system will be will be completed using data collected by the water resource team
to obtain the most convenient control of pre and post conditions. As the structural engineer
completes the layout of the proposed building, the environmental engineer will need to design a
solid waste management routine. Routines will include the collection of solid waste by garbage
and recycling trucks. Solid waste is going to be collected from the garbage storage which needs a
specified location based on best route.
6.1 Construction Environmental Management Plan
Land development will consider earthwork of the terrain which will include topsoil
stripping, stockpiling, and transportation of material for necessary pavement and structures. Air
pollution in the Memphis area has not exceeded ambient air quality, therefore, procedures will
only consider ambient motoring for exhaust emission created by heavy machinery in the site.
Noise modeling will need to be performed to determine if the construction noise levels are
28
Central Hollywood Plaza Christian Brothers University Section 6: Environmental CE 331 Nov. 2019____________________________________________________________________________________
appropriate for surrounding residential areas. During construction, excess wastewater from
equipment and machines will be created, therefore, erosion control plan will be required as
mentioned in Section 5.3.
6.2 Wastewater
A sanitary sewer system will be designed and constructed to connect to existing sewer
lines in the City of Memphis. The layout of the sewer system will consider the location of each
building to obtain total containment of sanitary waste. Design concepts will include size of pipe,
topography, soil conditions, ground water infiltration and exfiltration, and treatment plan. The
direction of drainage flow will be considered to be direct toward Northeast corner of the site.
6.2.1 Alternative 1: Traditional Centralized Wastewater System
Alternative One will consist of a traditional centralized system which collects wastewater
including solids. The system is generally composed of large diameter sewers that extends long
distances to a mechanical treatment plant. In this alternative, the wastewater drainage flow of the
restaurant is to be directed towards the North end. The direction of the flow will be governed by
the location of toilets and sinks within the restaurant.
6.2.2 Alternative 2: Decentralized Wastewater System
Alternative Two will consist of a decentralized system, which includes the collection of
treatment, and disposed/reuse of wastewater at a near location to Central Hollywood Plaza. In
this alternative, the wastewater drainage flow of the restaurant is to be directed to the East.
The alternative to the wastewater system are generalized by the cost. Alternative two will
minimize cost by material, operation and maintenance, and use of disposal/ reuse of treated
wastewater. The selection of a decentralized concepts will convey into an urban centralized
29
Central Hollywood Plaza Christian Brothers University Section 6: Environmental CE 331 Nov. 2019____________________________________________________________________________________
system. The direction of the wastewater drainage flow is important due to the fact that sewer
system may interfere with stormwater sewer. Routing the drainage flow in the most efficient
manner will allow to minimize cost of the system. The material used is to be determined as final
design is developeds
6.3 Stormwater
The base design concept will consider peak flow, runoff volume, and watershed
properties. The City of Memphis and Shelby County StormWater Management Manual will be
used to design the stormwater sewer. A Stormwater Pollution Prevention Plan (SWPPP) will be
created to obtain National Pollutant Discharge Elimination System (NPDES) permit. Runoff
control will be implemented using Best Management Practices (BMPs) to manage the discharge
of stormwater pollutants. The layout of the stormwater sewer system is to be established in order
to control post construction runoff conditions of the Central Hollywood Plaza construction
project. The project will consider a detention storage due to topography on site. All sewers
system will connect to existing sewer lines in Shelby County.
6.4 Solid/Hazardous Waste
Hollywood plaza will have an excess of solid waste but no hazardous waste. Solid waste
will be accumulated in separate containers distributed at best route according to size and
location. The production of solid waste quantified by capacity and permits obtained for Central
Hollywood Plaza. The storage of garbage containers will be in coordination to the capacity of
the building and type of business of location. Collection roads will be designed to route the most
efficient path for garbage and recycling trucks. This will be analyzed and designed by a
collaborative effort with traffic engineers. The City of Memphis will comply with regulations of
30
Central Hollywood Plaza Christian Brothers University Section 6: Environmental CE 331 Nov. 2019____________________________________________________________________________________
solid and hazardous waste, therefore, Buccaneer Engineering will need to abide to all rules
supplemented.
6.4.1 Alternative 1: Lighter to Heaviest
The route in which garbage and recycling trucks will need to take can be from lightest to
heaviest container. In this route the truck driver will not take into consideration the turns that it
needs to make in order to collect all disposed garbage and recycling. This route gives the most
efficient type of collection on Central Hollywood Plaza.
6.4.2 Alternative 2: Least Amount of Turns
The second alternative will only consider the amount of turns to be able to collect all
disposed garbage and recycling. This route will be the most time efficient collection of garbage
and recycling on Central Hollywood Plaza
6.6 Drawings
Detailed drawings for both alternatives will be produced. These drawings will include all
necessary plan views, side views, and cut sections. This will be done using AutoCAD.
6.5 Cost Estimate
The cost estimation for the environmental engineering portion will start accumulating as
preliminary construction permits are obtained. Some applications and fees will be required in
order to initiate and complete Central Hollywood Plaza construction project. The Tennessee
Department of Environmental and Conservation (TDEC) will require permits for activities such
as housing subdivision, commercial and industrial buildings, sewage treatment plants, and roads.
The Construction Stormwater General Permit will include fees for acres of project plus a fee to
31
Central Hollywood Plaza Christian Brothers University Section 6: Environmental CE 331 Nov. 2019____________________________________________________________________________________
submit a Stormwater Pollution Prevention Plan (SWPPP). All cost will reflect the minimal based
on efficiency of maintenance and material.
Table 1. Environmental Cost Estimate.
Fee Description Cost
CGP Fee Per Acres of Project $10,000.00
Initial Primary Operator $100.00
401 Certification or ARAP $2,500.00
Decentralized Wastewater Systems $1,000.00
Stormwater Discharge Permits (Industrial Activities) $690.00
Total = $14,290.00
8.5 Preferred Design Analysis
The final design will be based on the safety, final cost, and efficiency
32
Central Hollywood Plaza Christian Brothers University Section 6: Environmental CE 331 Nov. 2019____________________________________________________________________________________
(Page Left Blank)
33
Central Hollywood Plaza Christian Brothers University Section 7: Structural CE 331 Nov. 2019____________________________________________________________________________________
7. Structural Design The scope of the structural design is to design one of the smaller buildings on the site.
This design will include all the major components of a structure, such as member design,
member connections, load analysis, and some architectural considerations. This structure shall be
a one-story, rectangular partitioned building intended for general retail use to be partitioned as
needed by the owner. Although the design of the partition(s) is not within the scope of the
structural design, the partition(s) shall be accounted for during the load analysis in accordance
with ASCE/SEI 7-16 Minimum Design Loads and Associated Criteria for Buildings and Other
Structures. The structural design of this project will include two alternative designs: a steel
structure and a reinforced concrete structure. Each design will have its own foundation designed
in conjunction with the geotechnical engineer. A cost analysis will also be performed for both
alternatives.
7.1 Constraints
The following are the primary constraints regarding the structural design of the building:
the structure must adhere to the required area specified by Allen & Hoshall, Inc., which is
approximately 10,000 SF. The structure’s dimensions shall be 165 ft x 60 ft. This will yield an
area of 9,900 SF. Additionally, each alternative design must provide adequate strength, stiffness,
serviceability, functionality, and fire resistance as required by ASCE/SEI 7-16 and local building
codes.
7.2 Alternative 1: Steel Structure
This alternative is based on using steel as the main material for the structural frame of the
building and will be designed using the AISC Steel Construction Manual. Since the columns and
34
Central Hollywood Plaza Christian Brothers University Section 7: Structural CE 331 Nov. 2019____________________________________________________________________________________
beams for this design will primarily be W-shape steel members, the preferred material will
primarily be A992 steel, as specified by the AISC Steel Construction Manual.
Figure 7.2-1. Steel Structure Example.
7.2.1 Load Determination
An in-depth load analysis will be performed using Load Resistance Factor Design, in
accordance with ASCE/SEI 7-16 Minimum Design Loads and Associated Criteria for Buildings
and Other Structures. All load types will be considered, which include dead, live, wind, snow,
rain, and seismic loads. The analysis will include the use of Extended Three-Dimensional
Analysis of Building Systems (ETABS) 2016 software.
7.2.2 Roof Deck Selection/Design
The design of the roof of the structure will be dependent on the results from the load
analysis. The roof design will adhere to relevant building codes regarding appropriate drainage.
The roof must also be designed with consideration of plumbing and ventilation systems. The
resulting design will include the roof type (hip, low slope, gable, etc.), material, dimensions, and
35
Central Hollywood Plaza Christian Brothers University Section 7: Structural CE 331 Nov. 2019____________________________________________________________________________________
the location of any openings. The latest version on the Vulcraft Steel Roof & Floor Manual shall
be used as a primary reference.
Fig. 7.2.2-1. Typical Steel Roof Section.
7.2.3 Roof Beam Design
The roof beams of the structure will be identified as the smaller and shorter members
supporting the roof. The beams will be designed using the results obtained from the load analysis
and in accordance with the AISC Steel Construction Manual. All beams will be designed using
their ultimate limit state or serviceability limit state; the more applicable limit state will be used
during design.
7.2.4 Roof Girder Design
The roof girders of the structure will be identified as larger members supporting the roof
and beams. Girders will be designed in accordance with the AISC Steel Construction Manual
and using the results obtained from the load analysis as well as the determined beam design. All
girders will also be designed using their more applicable limit state. Due to their versatility and
practicality, open web-steel joists (OWSJs) will most likely be the member of choice for the
structure’s roof girders.
36
Central Hollywood Plaza Christian Brothers University Section 7: Structural CE 331 Nov. 2019____________________________________________________________________________________
Figure 7.2.4-1. Open Web-Steel Joist.
7.2.5 Column Design
The columns of the structure will be designed in accordance with the AISC Steel
Construction Manual using the results of the load analysis and determined girder design. All
columns will be designed based on their governing failure mode. These failure modes include
local buckling, lateral-torsional buckling, and either elastic or inelastic buckling.
7.2.6 Connection Design
The connections for all members will be designed using the determined loads and designs
for each member type. This will be done in accordance with the AISC Steel Construction
Manual. All connections will be simple connections. Bolted connections will be preferred
throughout the structure over welded connections due to cost, however, welded connections will
be used where they are deemed more practical. If a situation demands it, both bolts and welds
shall be used.
37
Central Hollywood Plaza Christian Brothers University Section 7: Structural CE 331 Nov. 2019____________________________________________________________________________________
7.2.7 Foundation Design
The foundation design of the structure will be done by considering several things: the
overall loads caused by the structure, the geometry of the structure, and the results obtained from
the geotechnical engineering analysis. More information of the foundation can be found in
Section 8.2.1.
7.3 Alternative 2: Reinforced Concrete Superstructure
This alternative is based on using reinforced concrete as the main material for the
structural frame of the building. This design will be in accordance with ACI 318-14 Building
Code Requirements for Structural Concrete. The preferred type of concrete material may differ
throughout the structure.
Figure 7.3-1. Reinforced Concrete Structure Example.
7.3.1 Load Determination
An in-depth load analysis will be performed using Load Resistance Factor Design, in
accordance with ASCE/SEI 7-16 Minimum Design Loads and Associated Criteria for Buildings
38
Central Hollywood Plaza Christian Brothers University Section 7: Structural CE 331 Nov. 2019____________________________________________________________________________________
and Other Structures. All load types will be considered, which include dead, live, wind, snow,
rain, and seismic loads. The analysis will include the use of ETABS 2016 software.
7.3.2 Roof Deck Selection/Design
The design of the roof of the structure will be dependent on the results from the load
analysis. The roof design will adhere to relevant building codes regarding appropriate drainage.
The roof must also be designed with consideration of plumbing and ventilation systems. The
resulting design will include the roof type (hip, low slope, gable, etc.), material, dimensions, and
the location of any openings.
7.3.3 Roof Beam Design
The roof beams of the structure will be identified as the smaller and shorter members
supporting the roof. The beams will be designed using the results obtained from the load analysis
and in accordance with ACI 318-14 Building Code Requirements for Structural Concrete. All
beams will be designed using their ultimate limit state or serviceability limit state; the more
applicable limit state will be used during design.
7.3.4 Roof Girder Design
The roof girders of the structure will be identified as larger members supporting the roof
and beams. Girders will be designed in accordance with ACI 318-14 Building Code
Requirements for Structural Concrete and using the results obtained from the load analysis as
well as the determined beam design.
7.3.5 Column Design
The columns of the structure will be designed in accordance with ACI 318-14 Building
Code Requirements for Structural Concrete using the results of the load analysis and determined
39
Central Hollywood Plaza Christian Brothers University Section 7: Structural CE 331 Nov. 2019____________________________________________________________________________________
girder design. All columns will be designed based on their governing failure mode. These failure
modes include local buckling, lateral-torsional buckling, and either elastic or inelastic buckling.
7.3.6 Connection Design
The connections for all members will be designed using the determined loads and designs
for each member type. This will be done in accordance with ACI 318-14 Building Code
Requirements for Structural Concrete.
7.3.7 Foundation Design
The foundation design of the structure will be done by considering several things: the
overall loads caused by the structure, the geometry of the structure, and the results obtained from
the geotechnical engineering analysis. More information of the foundation can be found in
Section 8.2.2.
7.4 Interior
The interior design of the structure will include the design of interior walls, plumbing and
electrical system considerations, floor layout, and the location and spacing of any additional
structural elements.
7.5 Architectural Considerations
Although the architectural design of the building is not within the scope of this project,
the structural design must be considerate of the architectural principles and elements of the
building in order to provide a cohesive structure. This will be done by considering the purpose of
the building.
40
Central Hollywood Plaza Christian Brothers University Section 7: Structural CE 331 Nov. 2019____________________________________________________________________________________
7.6 Drawings
The final step of the structural design will be to produce detailed drawings for both
alternatives. These drawings will include all necessary plan views, side views, and cut sections.
This will be done using AutoCAD.
7.7 Preferred Design Analysis
The final design will be based on safety, cost, and efficiency of the structure.
41
Central Hollywood Plaza Christian Brothers University Section 8: Geotechnical CE 331 Nov.
2019____________________________________________________________________________________
8. Geotechnical Design
The Geotechnical Engineering aspects of this project will consist of the design of the
foundation for the restaurant and the of a retaining wall on the Southern portion of the site.
8.1 Soil Data
To determine the properties of the soils of the site, testing results will be needed. Since
the site is very large and assumed to be undeveloped for the scope of this project, the soil data
will be assumed consistent across the entire site. Soil data will be obtained to find the soil type,
unit weight, angle of friction, cohesion, and elasticity. Boring logs will need to be acquired to
determine the depth of soils and water table.
8.2 Foundation of Small Structure
The design of the foundation for the general retail building will consist of two
alternatives: a mat foundation and a spread footing foundation. These alternatives will both be
designed to accommodate for the load of the building designed in Section 7. The design will
include a soil bearing capacity analysis and a settlement analysis. The structural design and
reinforcement of each alternative can be found in Section 7. The preferred design will be decided
based on cost estimate and efficiency data. The preferred design will then be used in the final
design in Section 9.
8.2.1 Alternative 1: Foundation for Steel Structure
Design Alternative 1 for the foundation will be a spread footing foundation to support the
steel structure designed in Section 7.2. A spread footing foundation is the chosen design for the
steel structure because its weight will most likely not put too great a stress on the soil to require
42
Central Hollywood Plaza Christian Brothers University Section 8: Geotechnical CE 331 Nov.
2019____________________________________________________________________________________
anything larger. If the soil bearing capacity is low or the steel structure is unexpectedly heavy
causing the spread footings to cover more than 50% of the building area, this design will be
switched to a mat foundation for cost efficiency.
The size and depth of embedment of the spread footing foundations will be determined
using the Terzaghi’s Bearing Capacity Equation. The loading from the building applied to the
foundation can be found in Section 7.2.7. A factor of safety will be applied to the loading during
calculations.
Figure 8.2.1-1. Spread Footing Foundation.
Once the dimensions of the foundation are determined, a settlement analysis will be done.
The allowable settlement for this type of building is usually between one half inch (0.5 in.) and
two inches (2 in.). The types of settlements that will be calculated are elastic settlement, primary
consolidation settlement, and secondary consolidation settlement. If the total settlement of the
43
Central Hollywood Plaza Christian Brothers University Section 8: Geotechnical CE 331 Nov.
2019____________________________________________________________________________________
foundation is outside of the allowable range, the size and depth of embedment of the foundation
will be revisited.
8.2.2 Alternative 2: Foundation for Concrete Structure
Design Alternative 2 for the foundation will be a mat foundation to support the concrete
structure designed in Section 7.3. Concrete structures are heavier relative to steel structures and
thus require more support from the foundation and soil.
The size and depth of embedment of the mat foundations will be determined using the
Meyerhof Bearing Capacity Equation. The loading from the building applied to the foundation
can be found in Section 7.3.7. A factor of safety will be applied to the loading during
calculations.
Figure 8.2.2-1. Mat Foundation.
Once the dimensions of the foundation are determined, a settlement analysis will be done.
The allowable settlement for this type of building is usually between one half inch (0.5 in.) and
two inches (2 in.). The types of settlements that will be calculated are elastic settlement, primary
consolidation settlement, and secondary consolidation settlement. If the total settlement of the
44
Central Hollywood Plaza Christian Brothers University Section 8: Geotechnical CE 331 Nov.
2019____________________________________________________________________________________
foundation is outside of the allowable range, the depth of impediment of the foundation will be
revisited and grade beams may be added.
8.3 Retaining Wall
Due to the slope of the existing land on the South side of the site parallel to Central
Avenue, a retaining wall will be used to stabilize the area and add more usable space above the
wall. The retaining wall will extend from the Southeast corner of the site to the proposed new
entrance to the development as seen in Figure 8.3-1.. This design will consist of two alternatives:
a Mechanically Stabilized Earth Wall (MSE) and a Gabion Wall.
Figure 8.3-1. Location of Retaining Wall.
8.3.1 Alternative 1: Mechanically Stabilized Earth Wall
This alternative will be a Mechanically Stabilised Earth Wall (MSE). MSE walls are one
of the most popular styles of retaining wall due to the ease of installation and being cost
effective. They are comprised of granular soil, metal ties or geosynthetic materials to give the
soil stability, and a cover or skin on the front of the wall.
45
Central Hollywood Plaza Christian Brothers University Section 8: Geotechnical CE 331 Nov.
2019____________________________________________________________________________________
The design of this wall will be a sandy backfill, metal ties, and precast concrete panels.
The metal ties will be designed using the Rankine method. Internal stability checks will be done
against tie breakage and breakout as well as external stability checks for overturning, sliding, and
bearing capacity failure. Factors of safety will be applied during the design of the ties.
Figure 8.3.1-1. MSE Wall Example.
8.3.2 Alternative 2: Gabion Wall
This alternative will be a gabion wall, which is a wall made out of wire cages filled with
rock, sand or soil. This wall will be a gabion wall with rock fill that will be backfilled with sand
on one side.
46
Central Hollywood Plaza Christian Brothers University Section 8: Geotechnical CE 331 Nov.
2019____________________________________________________________________________________
Figure 8.3.2-1. Gabion Wall Example.
The design of the gabion wall will consist of designing the size of the brackets, size and
shape of fill material, and the arrangement of the baskets. Fill material will be chosen based on
its effectiveness, cost, and its ability to be sourced locally. The design of the wall be be done
using the Coulomb’s theory. The wall will be checked for overturning, sliding, and bearing
capacity failure. Factors of safety will be applied during this design.
8.4 Drawings
Detailed drawings for both alternatives will be produced. These drawings will include all
necessary plan views, side views, and cut sections. This will be done using AutoCAD.
8.5 Preferred Design Analysis
The final design will be based on the safety, final cost, and efficiency
47
Central Hollywood Plaza Christian Brothers University Section 9: Final Design CE 331 Nov. 2019____________________________________________________________________________________
9. Cost Estimate
As part of the scope of this project a conceptual cost estimate of the entire development
will be done. This estimate will help determine the viability of the project going forward to
construction. Cost considered in this project will include local material and labor cost. The cost
estimate will be broken down by each individual component with the estimated price of each
given as a unit cost. While cost will be a factor in determining which alternative for each design
element will make it into the final design, this cost estimate will be focused on the cost of the
final design as a whole.
48
Central Hollywood Plaza Christian Brothers University Section 9: Final Design CE 331 Nov. 2019____________________________________________________________________________________
(Page Left Blank)
49
Central Hollywood Plaza Christian Brothers University Section 10: Cost Estimate CE 331 Nov. 2019____________________________________________________________________________________
10. Final Design
The final design will be determined at the conclusion of all prior design and cost
analyses. This design will not be based on cost alone, but should be based on the combination of
safety, efficiency, and cost altogether along with prior approval of all engineers and entities
involved.
50
Central Hollywood Plaza Christian Brothers University Section 10: Cost Estimate CE 331 Nov. 2019____________________________________________________________________________________
(Page Left Blank)
51
Central Hollywood Plaza Christian Brothers University Section 11: Conclusion CE 331 Nov.
2019____________________________________________________________________________________
11. Conclusion
This project will allow the students involved to implement material learned throughout
years of education at Christian Brothers University’s Gadomski School of Engineering. This will
provide a great experience by simulating real-world situations by involving different branches of
civil engineering in a collaborative effort. By the conclusion of the project, the students involved
will have sufficient experience to join the professional workforce thanks to the dedication of
their professors, advisors, corporate sponsors and all else involved.
52
Central Hollywood Plaza Christian Brothers University Section 11: Conclusion CE 331 Nov.
2019____________________________________________________________________________________
(Page Left Blank)
53
Central Hollywood Plaza Christian Brothers University Section 12: Schedule CE 331 Nov. 2019____________________________________________________________________________________
12. Schedule
Figure 11-1. Proposal Draft and Document Schedule.
54
Central Hollywood Plaza Christian Brothers University Section 12: Schedule CE 331 Nov. 2019____________________________________________________________________________________
(Page Left Blank)
55
Central Hollywood Plaza Christian Brothers University Acknowledgments CE 331 Nov. 2019____________________________________________________________________________________
Acknowledgments
Faculty:
Dr. Andrew Assadollahi, P.E. Department Chair, Associate Professor
Dept. of Civil and Environmental Engineering Christian Brothers University Office Phone: (901) 321- 4154
E-mail: [email protected]
Dr. L. Yu Lin P.E. Professor
Dept. of Civil and Environmental Engineering Christian Brothers University OfficePhone: (901) 321-3403
E-mail: [email protected]
Gene McGinnis Associate Professor
Dept. of Civil and Environmental Engineering Christian Brothers University Office Phone: (901) 321-3279 E-mail: [email protected]
Corporate Sponsors:
Allen & Hoshall, Inc. Engineers ⠂Architects ⠂Surveyors 1661 International Dr. Suite 100
Memphis, TN, 38120 Phone: (901) 820-0820 www.allenhoshall.com
56
Central Hollywood Plaza Christian Brothers University Acknowledgments CE 331 Nov. 2019____________________________________________________________________________________
(Page Left Blank)
57
Central Hollywood Plaza Christian Brothers University Bibliography CE 331 Nov.
2019____________________________________________________________________________________
References
A Policy on Geometric Design of Highways and Streets - 2011. 6th ed., American Association of State Highway and Transportation Officials, 2011.
Annual Book of ASTM Standards. American Society for Testing and Materials International. Building Code Requirements for Structural Concrete (ACI 318-11) and Commentary. Michigan:
American Concrete Institute, 2011. Print. Das, Braja M. Fundamentals of Geotechnical Engineering. 4th ed., Cengage Learning, 2013. Memphis and Shelby County Unified Development Code, The. The City of Memphis and Shelby
County. 2019. Minimum Design Loads for Buildings and Other Structures, Standard ASCE 7. American
Society of Civil Engineers. Steel Construction Manual. 15th ed. United States of America: American Concrete Institute,
2017. Segui, William T. Steel Design, 6th ed. Cengage Learning, 2018. Stormwater Management Manual, Volume 1. The City of Memphis and Shelby County
StormWater Management, 2007. Stormwater Management Manual, Volume 2. The City of Memphis and Shelby County
StormWater Management, 2006. Stormwater Management Manual, Volume 3. The City of Memphis and Shelby County
StormWater Management, 2006.
Tennessee Erosion Prevention and Sediment Control
Steel Roof & Floor Deck Manual. Vulcraft, 2018.
58