Celebrating Portfolio for JIRA's First Year with Five Learnings

76
MARTIN SUNTINGER PRINCIPAL PRODUCT MANAGER ATLASSIAN Celebrating Portfolio for JIRA’s First Year with Five Learnings

Transcript of Celebrating Portfolio for JIRA's First Year with Five Learnings

Page 1: Celebrating Portfolio for JIRA's First Year with Five Learnings

MARTIN SUNTINGER • PRINCIPAL PRODUCT MANAGER • ATLASSIAN

Celebrating Portfolio for JIRA’s First Year with Five Learnings

Page 2: Celebrating Portfolio for JIRA's First Year with Five Learnings

• Big cool statistic

• 2,569

• Add-Ons in Marketplace

…one more thing

Summit 2014

Page 3: Celebrating Portfolio for JIRA's First Year with Five Learnings

Summit 2014

Page 4: Celebrating Portfolio for JIRA's First Year with Five Learnings

(holycow)

Image source: https://www.flickr.com/photos/gamerscore/1449650710

Page 5: Celebrating Portfolio for JIRA's First Year with Five Learnings

Plan, manage, and report across all projects and

teams

Page 6: Celebrating Portfolio for JIRA's First Year with Five Learnings

Portfolio for JIRA

active licenses

3000+

Page 7: Celebrating Portfolio for JIRA's First Year with Five Learnings

Learnings

Page 8: Celebrating Portfolio for JIRA's First Year with Five Learnings
Page 9: Celebrating Portfolio for JIRA's First Year with Five Learnings

W H AT ’ S C O M I N G ?

1 Y E A R - 5 L E A R N I N G S

Agenda

Page 10: Celebrating Portfolio for JIRA's First Year with Five Learnings

Data-informed planning: no pain no gain

1

Page 11: Celebrating Portfolio for JIRA's First Year with Five Learnings

vaporwareMVP

I actually don’t know this guy

2 years ago..

Page 12: Celebrating Portfolio for JIRA's First Year with Five Learnings
Page 13: Celebrating Portfolio for JIRA's First Year with Five Learnings

A shared backlog with all data on the table

Page 14: Celebrating Portfolio for JIRA's First Year with Five Learnings

Transparent and objective resourcing

Page 15: Celebrating Portfolio for JIRA's First Year with Five Learnings

Automatic data-driven forecast - “the best we can do from current perspective” random

Page 16: Celebrating Portfolio for JIRA's First Year with Five Learnings

What needs to be done

A realistic forecast

Page 17: Celebrating Portfolio for JIRA's First Year with Five Learnings

A realistic forecast can cause temporary shocks and feelings of disillusion

CAUTION

Page 18: Celebrating Portfolio for JIRA's First Year with Five Learnings

No longer can project managers and directors etc. pick dates out of the air for delivery "targets". Senior stakeholders can work together to figure out how to shuffle priorities. There is no escape from the plan! A C U R R E N T P O R T F O L I O U S E R ( A N O N Y M O U S S U RV E Y )

Page 19: Celebrating Portfolio for JIRA's First Year with Five Learnings

Become Data- Informed

No pain no gain

Agile AND long-termAn automatic forecast helps make decisions today even if things change

A great plan should trigger tough discussions and decisions

Page 20: Celebrating Portfolio for JIRA's First Year with Five Learnings

Portfolio is for everyone ..but not everyone uses it for the same purpose

2

Page 21: Celebrating Portfolio for JIRA's First Year with Five Learnings

¯\_( )_/¯

What we thought would happen…

Image source: http://searchenginewatch.com/IMG/273/252273/managing-seo-small-mid-large-enterprise.jpg?1435038483

Page 22: Celebrating Portfolio for JIRA's First Year with Five Learnings

What actually happened…

(almostawesome)

Image source: http://searchenginewatch.com/IMG/273/252273/managing-seo-small-mid-large-enterprise.jpg?1435038483

Page 23: Celebrating Portfolio for JIRA's First Year with Five Learnings

ReportingPlanning

PlanningReporting

Image source: http://searchenginewatch.com/IMG/273/252273/managing-seo-small-mid-large-enterprise.jpg?1435038483

Page 24: Celebrating Portfolio for JIRA's First Year with Five Learnings

Executives Project Managers

Program Managers

Development Managers

Product Managers

Page 25: Celebrating Portfolio for JIRA's First Year with Five Learnings

Executives Project Managers

Program Managers

Development Managers

Product Managers

Page 26: Celebrating Portfolio for JIRA's First Year with Five Learnings

Get everyone involved with Portfolio

Implement benefits at the team level and move on up

Share your plansContext drives decisions and can have unexpected benefits

From 1 team up

Page 27: Celebrating Portfolio for JIRA's First Year with Five Learnings

Play the numbers and connect with reality

3

Page 28: Celebrating Portfolio for JIRA's First Year with Five Learnings

• Big cool statistic

• 2,569

• Add-Ons in Marketplace

…a safe playground

Image source: https://handsfullofgrass.files.wordpress.com/2012/11/img_0539.jpg

Page 29: Celebrating Portfolio for JIRA's First Year with Five Learnings

…or real time and live?

Image source: http://covers8.com/concert-with-lights-and-hands-up/

Page 30: Celebrating Portfolio for JIRA's First Year with Five Learnings
Page 31: Celebrating Portfolio for JIRA's First Year with Five Learnings
Page 32: Celebrating Portfolio for JIRA's First Year with Five Learnings

• Big cool statistic

• 2,569

• Add-Ons in Marketplace+

Page 33: Celebrating Portfolio for JIRA's First Year with Five Learnings

Load data dynamically from boards, projects

or custom filters

Page 34: Celebrating Portfolio for JIRA's First Year with Five Learnings

JIRA

Portfolio

new issuesedits fields

rankingsprint planning

auto-commit

Page 35: Celebrating Portfolio for JIRA's First Year with Five Learnings

JIRA

Portfolio

Commit changes

TIS-1 edited, 2.0 created, TIS-23 added,…

Page 36: Celebrating Portfolio for JIRA's First Year with Five Learnings

Stay in sync with reality at any time

Different models in planning and reality mean “updating hell”

Improvements comingNeeds work in the product. We’re on it.

Reflect reality

Page 37: Celebrating Portfolio for JIRA's First Year with Five Learnings

Communication eats planning for breakfast

…and reporting for lunch

4

Page 38: Celebrating Portfolio for JIRA's First Year with Five Learnings

Usage data indicates

of plans live a lonesome life

~ 60%Image source: http://www.desk7.net/wallpapers.aspx?typeid=7258

Page 39: Celebrating Portfolio for JIRA's First Year with Five Learnings
Page 40: Celebrating Portfolio for JIRA's First Year with Five Learnings

?

Page 41: Celebrating Portfolio for JIRA's First Year with Five Learnings

We’ve had good progress but s#%t is about to hit the fan

Being “just yellow” this week is a good thing! …last month I lost

all hope for this project

I see a major bottleneck ahead when we do the

planned team shift

Just hired a rockstar dev - even though we’re behind

right now, I’m confident we’ll hit our deadlines

Page 42: Celebrating Portfolio for JIRA's First Year with Five Learnings
Page 43: Celebrating Portfolio for JIRA's First Year with Five Learnings

Focus on communication

Provoke feedback

Have project owners share status via defined channels

Raise red-flagLet stakeholders call bulls@#$t on your plans

Facilitate discussion

Actively invite stakeholders to share their feedback

Page 44: Celebrating Portfolio for JIRA's First Year with Five Learnings

Agile scales best with self-serve information

5

Page 45: Celebrating Portfolio for JIRA's First Year with Five Learnings

empoweredindependentdeliver value fasteragile

Page 46: Celebrating Portfolio for JIRA's First Year with Five Learnings

agile context & informationorganizationculture

knowledgecommitment

skills

Page 47: Celebrating Portfolio for JIRA's First Year with Five Learnings

context & informationagileorganizationculture

knowledgecommitment

skills

Page 48: Celebrating Portfolio for JIRA's First Year with Five Learnings
Page 49: Celebrating Portfolio for JIRA's First Year with Five Learnings
Page 50: Celebrating Portfolio for JIRA's First Year with Five Learnings

Provide self-serve information

From “ask and respond” to “share and consume”

One source of truthDiscover synergies, combine forces if everyone knows what’s in progress and what’s next

Don’t wait to be asked

Page 51: Celebrating Portfolio for JIRA's First Year with Five Learnings

What’s next for Portfolio? A Painted Picture

Page 52: Celebrating Portfolio for JIRA's First Year with Five Learnings

Program manager

Page 53: Celebrating Portfolio for JIRA's First Year with Five Learnings

Reliable timelines

Instantly know about changes

Dependencies

Running dark

Page 54: Celebrating Portfolio for JIRA's First Year with Five Learnings

Reliable timelines

Instantly know about changes

Dependencies

Running dark

Page 55: Celebrating Portfolio for JIRA's First Year with Five Learnings
Page 56: Celebrating Portfolio for JIRA's First Year with Five Learnings
Page 57: Celebrating Portfolio for JIRA's First Year with Five Learnings
Page 58: Celebrating Portfolio for JIRA's First Year with Five Learnings
Page 59: Celebrating Portfolio for JIRA's First Year with Five Learnings
Page 60: Celebrating Portfolio for JIRA's First Year with Five Learnings

(ohcrap) - won’t make our target!

Page 61: Celebrating Portfolio for JIRA's First Year with Five Learnings
Page 62: Celebrating Portfolio for JIRA's First Year with Five Learnings
Page 63: Celebrating Portfolio for JIRA's First Year with Five Learnings
Page 64: Celebrating Portfolio for JIRA's First Year with Five Learnings
Page 65: Celebrating Portfolio for JIRA's First Year with Five Learnings
Page 66: Celebrating Portfolio for JIRA's First Year with Five Learnings
Page 67: Celebrating Portfolio for JIRA's First Year with Five Learnings
Page 68: Celebrating Portfolio for JIRA's First Year with Five Learnings

Scope of trip management has been adjusted to meet the beta timeline - stakeholders are comfortable with reduced feature set.

Page 69: Celebrating Portfolio for JIRA's First Year with Five Learnings
Page 70: Celebrating Portfolio for JIRA's First Year with Five Learnings
Page 71: Celebrating Portfolio for JIRA's First Year with Five Learnings
Page 72: Celebrating Portfolio for JIRA's First Year with Five Learnings
Page 73: Celebrating Portfolio for JIRA's First Year with Five Learnings
Page 74: Celebrating Portfolio for JIRA's First Year with Five Learnings
Page 75: Celebrating Portfolio for JIRA's First Year with Five Learnings

Focus on communication

Get everyone involved

Become data-informed

A year full of learnings

Stay in sync with reality

Scale with self-serve information

Page 76: Celebrating Portfolio for JIRA's First Year with Five Learnings

Thank you!