CEF Networks3ext
Transcript of CEF Networks3ext
-
8/3/2019 CEF Networks3ext
1/19
Research Department Workshop on CEF-Networks www.ces.net
Procurement and lightingof dark fibre
Lada Altmannova
Stanislav Sima
Prague May 25th, 2004
-
8/3/2019 CEF Networks3ext
2/19
Prague May25th 2004
Procurement and lighting of dark
fibre2
Research Department Workshop on CEF-Networks www.ces.net
Main changes in REN design
q Traditional building elements (procured): datatransmission services, routers, terminals, etc.
q Traditional network function: provide best effort IP
connectivityq New building elements: dark fibres, optical
transmission equipment, switches
q New network function: provide E2E circuits
q Multi-vendor networking for feasibility (in multipledomain) and cost effectiveness (in single domain) standards, MSA, etc. are needed. This is similar as oncircuit and computer system design level.
-
8/3/2019 CEF Networks3ext
3/19
Prague May25th 2004
Procurement and lighting of dark
fibre3
Research Department Workshop on CEF-Networks www.ces.net
Dark fibre deployment in RENs
q Increasing and world-wide deployment of dark fibre(acquisition of dark fibres instead of SDH or lambdaservices) without moving back
q Lease of fibres: 0.4 0.5 Euro/m/pair/year, includingmaintenance
q Discounts on long term lease, disadvantages of IRU(prepayment, taxes and bankruptcy)
q Increasing number of customer premises connected by
fibre: to achieve this is more difficult problem than intercityfibre procurement
q Building first mile fibre lines: about 30 Euro/m for 12strand cable, 6 month in ground
-
8/3/2019 CEF Networks3ext
4/19
Prague May25th 2004
Procurement and lighting of dark
fibre4
Research Department Workshop on CEF-Networks www.ces.net
-
8/3/2019 CEF Networks3ext
5/19
Prague May25th 2004
Procurement and lighting of dark
fibre5
Research Department Workshop on CEF-Networks www.ces.net
CEF network architecture will be new
q Prefer network architecture withNIL (single span) linesand without overlaying (concurrent) fibres
q KIS rule for fibres: Keep It Short, includingconnections crossing state borders
q
Realization of lambdas by own equipment and fibres forlong distance data transmission
q Search actively for new fibre providers (railways,highways, power distribution companies, fuel
distribution companies, gas distribution companies,cable TV companies, etc.)
q Search actively for regional authorities and local boardscooperation on laying first mile fibre cables
-
8/3/2019 CEF Networks3ext
6/19
Prague May25th 2004
Procurement and lighting of dark
fibre6
Research Department Workshop on CEF-Networks www.ces.net
How to go from telco services to dark fibres
q Procure dark fibre before lambdas procurement
q Procure your first dark fibre line ASAP to acquire experience (toavoid staff fear of: maintenance, service, lighting fibre,management of in-line equipment, costs, manpower, etc.)
q Do not relay on one provider only, maintain concurrency (forprice and for first mile acquiring)
q If price is not excellent, use annual contracts and re-procurement
q If dark fibre line is not offered but exists, use annual contract for
lambda(s) and re-procure dark fibreq Prefer remote management of in-line equipment with local
assistance of service company (no managed dark fibre servicefrom ISP)
-
8/3/2019 CEF Networks3ext
7/19
Prague May25th 2004
Procurement and lighting of dark
fibre7
Research Department Workshop on CEF-Networks www.ces.net
-
8/3/2019 CEF Networks3ext
8/19
Prague May25th 2004
Procurement and lighting of dark
fibre8
Research Department Workshop on CEF-Networks www.ces.net
-
8/3/2019 CEF Networks3ext
9/19
Prague May25th 2004
Procurement and lighting of dark
fibre9
Research Department Workshop on CEF-Networks www.ces.net
We need non-expensive fibre footprintq
KIS: Connect dark fibres used by NREN by a shortcross-border fibre lines (called also Near overBorder - NoB)
q Use WDM equipment on national and cross-border
fibres for implementation of lambdas between GN2PoPs/end users
q This KIS approach avoids double payment of fibresor lambdas (parallel lines are paid by NREN and
DANTE), in the biggest item of budgetsq Such change of networking strategy is difficult,
feasibility study and testbeds are needed
-
8/3/2019 CEF Networks3ext
10/19
Prague May25th 2004
Procurement and lighting of dark
fibre10
Research Department Workshop on CEF-Networks www.ces.net
Lighting of dark fibre: NIL approach
q Production lines G.652, 1550 nm, EDFA
189 km Praha Pardubice GE since May 2002
235 km Brno Ostrava GE since June 2003
q Experimental lines G.652, 1550 nm, EDFA
235 km Brno Ostrava OC-48 June 2003
286 km Praha Brno GE May 2004 (+Raman)
q More wavelengths possible
-
8/3/2019 CEF Networks3ext
11/19
Prague May25th 2004
Procurement and lighting of darkfibre
11
Research Department Workshop on CEF-Networks www.ces.net
Dark fibre lighting register: see before new line design
Country A B km
Attenuation
(dB at 1550nm) Fibre/Pair Planed
Experi-
mental Operational Transmission Equipment
CZ Praha Brno 285,8 66,7 Pair X
2x Keopsys 27 dBm+Raman laser +optical
filter, CGBIC
CZ Praha Plze 159,4 36,7 Pair X EDFA 2in1 booster 17 dBm+preamplifier -10dBm+optical filter, 2x GBIC ZX
CZ Praha Brno 326,7 81 Pair 10.1.2000 3x ONS15104CZ Praha Liberec 200 Pair XCZ Praha Pardubice 188,6 46,03 Pair 17.5.2002 Keopsys 2x 21 dBm, 2x GBIC ZXCZ Praha Plze 123 33,72 Pair 3.9.2003 Keopsys 2x 10dBm, POS LR 2,5GCZ Praha st n.L. 155,3 36,8 Pair 6.12.2003 Catalyst switch in line, 2x CGBICCZ Brno Olomouc 107 27,5 Pair 25.11.2003 2x CGBIC
CZ Brno Ostrava 235,4 50,55 Pair 6.6.2003 Keopsys 2x 27dBm+2x 10dBm+2x CGBIC
CZ .B. Brno 307,9 69,76 Pair 15.9.2003Keopsys 2x 27dBm+2x 10dBmin line, POSLR 2,5G
CZ .B. Plze 178,3 40,78 Pair 25.7.2003 Keopsys 2x 24dBm, POS LR 2,5GCZ Olomouc Hradec K. 197,4 42,96 Pair 1.2.2004 Keopsys 2x 27dBm, POS LR 2,5GCZ Olomouc Ostrava 189,8 43,51 Pair 1.2.2004 Keopsys 2x 27 dBm, 2x CGBICCZ Olomouc Zln 71,5 22,46 Pair 19.2.2003 2x CGBICCZ Pardubice Hradec K. 30 7,5 Pair 15.1.2002 2x GBIC ZXCZ st n L. Liberec 123 26,23 Pair 30.6.2003 2x CGBIC
CZ .B. J. Hradec 70,7 18,41 Fibre 17.8.2003 MRV 2x EM 316WFC/S4 & WFT/S4, 40-100km
CZ Ostrava Karvin 76,7 20,27 Fibre 24.7.2003MRV 2x EM 316WFC/S4 & WFT/S4, 40-100km
CZ Ostrava Opava 49,9 18,22 Fibre 26.3.2003MRV 2x EM 316WFC/S4 & WFT/S4, 40-100km
CZ Plze Cheb 126,5 35,65 Fibre 16.7.2003MRV 2x EM 316WFC/S5 & WFT/S5, 40-
125km
CZ st n L. D n 34 8,6 Fibre 1.7.2003MRV 2x EM 316WFC/S3 & WFT/S3, 20-50km
-
8/3/2019 CEF Networks3ext
12/19
Prague May25th 2004
Procurement and lighting of darkfibre
12
Research Department Workshop on CEF-Networks www.ces.net
NIL tests in laboratory
q G.652 fibre spools, EDFA + Raman:
325 km GE
250 km OC-48
252 km 2x 10 GE290 km 10 G DWDM
q G.655 fibre spools (recently delivered):
testing
lower cost of dispersion compensation on 10 Gbps
-
8/3/2019 CEF Networks3ext
13/19
Prague May25th 2004
Procurement and lighting of darkfibre
13
Research Department Workshop on CEF-Networks www.ces.net
Let us introduce: PC Lightq Design Kit for wide area fibre networks, based on
racked PCs with build-in optical amplifier modules
q Multi-vendor (multi-source) building elements
q Preliminary comparison of OA (EDFA) costs:
OA from ISP vendor: 40 000 USD OA from optical vendor: 18 000 USD
OA from module vendor: 2 500 USD (two OA in module)
OA from Integrated Circuit vendor: ??? (forthcoming)
q OA costs are the biggest item in long distancetransmission systems costs (e.g. 60%)
=> PC Light helps to radically change WAN/MAN costs
-
8/3/2019 CEF Networks3ext
14/19
Prague May25th 2004
Procurement and lighting of darkfibre
14
Research Department Workshop on CEF-Networks www.ces.net
EDFA 2in1: PC Light equipment example
q PC with build-in OA EDFA booster and preampq Successfully used for NIL GE connection from Plzen
to CzechLight in Prague by dark fibre pair (159.4 km,36.7 dB) since May 2004
q One Side Amplification (OSA NIL approach): thisequipment is placed in Prague only. No OA equipmentis placed in Plzen, so we expect lower service costsand higher availability (we have 24/7 staff in Prague
only)q Advantages: low cost, low size (1U), low power
consumption, Linux, SNMP, reach up to 225 km,possibility of development, .
-
8/3/2019 CEF Networks3ext
15/19
Prague May25th 2004
Procurement and lighting of darkfibre
15
Research Department Workshop on CEF-Networks www.ces.net
EDFA 2in1: EDFA Module in Standard 1U PC with Linux
Alarm
LEDs
BO IN
IDE +5V DCRS 232
PA OUT
BO OUT
FERS232C
USB * Network boot is also possible
PA IN
MicroATX
MainBoard withfanless CPU
Power
Supply
Flash
disc*
Low NF preamplifier
Booster
-
8/3/2019 CEF Networks3ext
16/19
Prague May25th 2004
Procurement and lighting of darkfibre
16
Research Department Workshop on CEF-Networks www.ces.net
PC Light forthcoming
q EDFA 2in1 works on 10 GE (tested in
laboratory)
q GE interface card on 1550 nm
q GE interface card for bidirectional
transmission on single fibre
q
etc.
C
-
8/3/2019 CEF Networks3ext
17/19
Prague May25th 2004
Procurement and lighting of darkfibre
17
Research Department Workshop on CEF-Networks www.ces.net
Prepared CzechLight connections
R h D t t W k h CEF N t k t
-
8/3/2019 CEF Networks3ext
18/19
Prague May25th 2004
Procurement and lighting of darkfibre
18
Research Department Workshop on CEF-Networks www.ces.net
Prepared CzechLight PoP in Brno
q Fibre Praha - Brno 298.3 km,including 257.3 km of G.655 fibre.
q DWDM 10 Gbps cards for Cisco15454
qNIL transmission, if possible
q
June July 2004
R h D t t W k h CEF N t k t
-
8/3/2019 CEF Networks3ext
19/19
Prague May25th 2004
Procurement and lighting of dark19
Research Department Workshop on CEF-Networks www.ces.net
Acknowledgement
q Jan Gruntorad for support and GLIF entry
q Miroslav Karasek and Jan Radil for lighting ofCESNET2 and CzechLight fibres
q
Josef Vojtech for EDFA 2in1 development
q Comment: presented ideas and opinions are result of our ongoingR&D activities and are opened to improvement