BLACKBOX CONSTRUCTION, LLC.
CE 592
CONSTRUCTION ESTIMATING, PLANNING, AND CONTROL
FALL 2016
PORTERS NECK ELEMENTARY SCHOOL
Abhishek Singh Parth Malhotra Rakeshkumar ‘Ron’ Patel Sai Ruthvik Pabolu Varun Kumar Sampath
BLACK BOX CONSTRUCTION, LLC. 3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
Table of Contents
BID FORMS .............................................................................................................. i
SECTION 1 PROJECT DATA ...................................................................................... 1
1.1 Project Details
1.2 Proposed Construction Team .......................................................................... 2
1.2.1 Meet Our President ................................................................................. 3
1.2.2 Estimator ................................................................................................. 3
1.2.3 Project Manager ...................................................................................... 3
1.2.4 Project Superintendent ............................................................................ 3
1.2.5 Project Engineer....................................................................................... 3
SECTION 2 EXECUTIVE SUMMARY........................................................................ 10
2.1 Project Description ....................................................................................... 10
2.2 Project Description ....................................................................................... 11
2.3 Summary of Main Findings ........................................................................... 12
2.4 Closing Statement ........................................................................................ 13
2.5 Required Bid Documents ............................................................................. 13
SECTION 2 ESTIMATE ............................................................................................ 14
3.1 Rough Order Magnitude Estimate ................................................................ 14
3.2 Summary of Bid ............................................................................................ 17
3.3 Detailed Bid ................................................................................................. 18
3.4 Company Overhead ..................................................................................... 20
3.5 Sales History ................................................................................................ 22
3.6 Labor Burden ............................................................................................... 23
3.7 General Conditions ...................................................................................... 41
SECTION 4 SCHEDULE ........................................................................................... 42
4.1 Work Breakdown Structure .......................................................................... 42
4.2 Schedule ...................................................................................................... 44
BLACK BOX CONSTRUCTION, LLC. 3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
SECTION 5 PROJECT CONTROLS ........................................................................... 46
5.1 Schedule of Values ....................................................................................... 46
5.2 Cash Flow Analysis ....................................................................................... 49
5.3 Value Engineering ........................................................................................ 52
SECTION 6 Appendix ............................................................................................ 54
6.1 Adjusted Sub-contractor Bid Values ............................................................. 54
6.2 Detailed Estimates ....................................................................................... 65
6.2.1 Detailed Estimate for Concrete ...................................................................... 65
6.2.2 Detailed Estimate for Masonry ....................................................................... 66
6.2.3 Detailed Estimate for Paving.......................................................................... 67
6.2.4 Summary of Site Work ................................................................................. 68
6.2.5 Detailed Estimate for Wood Shelving ............................................................... 81
6.2.6 Detailed Estimate for Fire Sprinklers ................................................................ 82
6.2.7 Detailed Estimate for Painting ........................................................................ 83
6.2.8 Detailed Estimate for PVC Roofing .................................................................. 84
6.2.9 Detailed Estimate for Stage Flooring ................................................................ 85
6.2.10 Detailed Estimate for ACM Panel ................................................................... 86
6.2.11 Detailed Estimate for Operable Partition ......................................................... 87
6.2.12 Detailed Estimate for Basket Ball Goals ........................................................... 88
6.2.13 Detailed Estimate for Lockers ....................................................................... 89
6.2.14 Detailed Estimate for HVAC ......................................................................... 90
6.2.15 Detailed Estimate for Safety Padding ............................................................ 109
6.2.16 Detailed Estimate for Traffic Coatings ........................................................... 111
6.2.17 Detailed Estimate for Acoustic Ceiling ........................................................... 112
6.2.18 Detailed Estimate for Acoustic Wall Units ...................................................... 113
BLACK BOX CONSTRUCTION, LLC. 3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
6.2.19 Detailed Estimate for Landscaping and Irrigation ............................................. 114
6.2.20 Detailed Estimate for Final Electricity ........................................................... 115
6.2.21 Detailed Estimate for Spray Fireproofing ....................................................... 115
6.2.22 Detailed Estimate for Structural steel ........................................................... 116
6.2.23 Detailed Estimate for Aluminum Canopies ..................................................... 117
6.2.24 Detailed Estimate for Flagpoles .................................................................. 118
6.2.25 Detailed Estimate for Ceramic Tiles .............................................................. 119
6.2.26 Detailed Estimate for Misc Firestopping ........................................................ 120
6.2.27 Detailed Estimate for Display Cases.............................................................. 121
6.2.28 Detailed Estimate for Louvers .................................................................... 122
6.2.29 Detailed Estimate for Spray Foam Beam Infill .................................................. 123
6.2.30 Detailed Estimate for Foam Insulation .......................................................... 125
6.2.31 Detailed Estimate for Dry Wall- Wall ............................................................ 127
6.2.32 Detailed Estimate for Dry Wall-Ceilings ......................................................... 128
6.2.33 Detailed Estimate for Framing .................................................................... 131
6.2.34 Detailed Estimate for Inwall Blocking ............................................................ 132
6.2.35 Detailed Estimate for Fiber Cement ............................................................. 133
6.2.36 Detailed Estimate for Security .................................................................... 134
6.2.37 Detailed Estimate for Communication .......................................................... 135
6.2.38 Detailed Estimate for Fire Alarm ................................................................. 136
BLACK BOX CONSTRUCTION, LLC. 3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
SECTION 1 – PROJECT DATA
1.1 Project Details:
Project Name:
Porters Neck Elementary School
Owner:
New Hanover County Schools
General Contractor:
Black Box Construction, LLC.
Architect:
LS3P Associates Ltd.
Civil:
Paramounte Engineering, Inc.
Structural:
Woods Engineering, PA
Fire Protection:
Robert E. Porterfield
Plumbing/Mechanical:
Cheatham and Associates, PA
Electrical:
Cheatham and Associates, PA
BLACK BOX CONSTRUCTION, LLC. 3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
1.2 Proposed Construction Team
1.2.1 Meet our President:
Rakeshkumar ‘Ron’ Patel Company President
Ron started his career 26 years ago, as a project engineer. He worked for two construction companies in capacities of a project engineer and eventually project manager before starting Black Box Construction in 1997. Under the leadership of Ron, the company has established itself as an esteemed general contractor in the residential, commercial, and institutional sectors.
Ron has an MS degree in Structural Engineering from North Carolina State University and he is currently pursuing his doctorate degree (PhD) from North Carolina State University.
Ron can be reached at [email protected]
BLACK BOX CONSTRUCTION, LLC. 3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
1.2.2 Project Manager:
Parth Malhotra Project Manager
After completing his MS in Construction Engineering from North Carolina State University, Parth joined the company in 2001 and has been working with the company ever since. Out of his total experience of 16 years, Parth has worked in the capacity of a project engineer for 3 years, as a Assistant Project Manager for 4 years and for the past 7 years, he has been working as the Project Manager for the company. In addition to his responsibilities as a Project Manager, he also oversees the development of our safety program.
Parth can be reached at [email protected]
BLACK BOX CONSTRUCTION, LLC. 3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
1.2.3 Estimator:
Abhishek Singh Chief Estimator
Abhishek has worked in the construction industry since he was 16 years old. His father had a construction business his home country of India and Abhishek used to work for him since he was in high school. After graduating with a Bachelor’s degree in Civil Engineering from National Institute of Technology – India, he worked as a Project Engineer for three years on an airport project before moving to US for his master’s degree in Construction Engineering from NCSU. After completing his masters’ degree, Abhishek worked in Turner for 3 years as a Estimator and as a Senior Estimator for 4 years at Bechtel.
Abhishek joined the Black Box team in 2007 as a Chief Estimator. His vast experience in the construction industry and his expertise in project management are one of the biggest assets of our company. He is also currently developing a pull based workflow system to introduce lean construction principles in our company.
Abhishek can be reached at [email protected]
BLACK BOX CONSTRUCTION, LLC. 3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
1.2.4 Project Superintendent:
Varun Kumar Sampath Project Superintendent
Varun has been with Black Box Construction since its inception in 1997 and has been instrumental in the success of some of our most prestigious projects. Varun began his career at Samet to support himself while concurrently pursuing his master’s degree at North Carolina State University with full time course load. Upon graduating, Varun continued to work with Samet for 12 years before joining Black Box in 2012. Varun is a thorough team player and has exceptional communication skills. He has diverse problem solving and analytical skills which enable him to maintain the schedule on the most complex and challenging projects.
Varun can be reached at [email protected]
BLACK BOX CONSTRUCTION, LLC. 3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
1.2.5 Project Engineer:
Sai Ruthvik Pabolu Project Engineer
Ruthvik joined the Black Box family in the Summer of 2012 as an intern while he was pursuing his construction engineering degree at North Carolina State University. Upon graduation, Ruthvik began working full time as a project engineer with Black Box Construction. Ruthvik has worked on estimating, CAD drawings, submittals, change order, safety orientations, task co-ordination and personnel management. Ruthvik has been also involved in labor productivity studies and he has also been doing research on ways to reduce construction wastage and improve labor productivity while concurrently working towards his P.E. certification.
Ruthvik can be reached at [email protected]
BLACK BOX CONSTRUCTION, LLC. 3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
1.3 About our Company
In July ,1997 Mr. Rakeshkumar ‘Ron’ Patel, with a loan of $25,000 from his father established the company in his garage. The company initially began as a masonry sub-contractor and quickly proliferated in to a general contracting company. Over the years, the company has grown from a residential contractor in to a diversified company with experience in building commercial, institutional, and public buildings.
Black Box Construction specializes in construction of high end residential homes, shopping malls, schools, libraries, museums, theaters, and courthouses.
Since, 2012 the company has grown about twice in size and we expect it to grow with the same pace in future with the vision to be North Carolina’s premier construction organization by achieving extraordinary results for our customers, building satisfying careers for our people, and earning a fair return on the value we deliver.
Our mission and core values are a starting point that help clearly define who we are and what we stand for as a company. They underlie the passion that drives us to be better and different; they allow us the freedoms of our entrepreneurial organization, where people can make a difference with their ideas and hard work
Mission: To be the preeminent provider of superior construction services by consistently improving the quality of our services; to add value for clients through innovation, foresight, integrity, and to serve with character and purpose.
Core Values:
Ethics We are uncompromising in our integrity, honesty, and fairness.
Safety & Health We are relentless in keeping people safe from harm, and we provide a healthy work environment.
Quality We are passionate about excellence and doing our work right the first time. Our reputation depends on our delivered value in the eyes of every customer and community.
People We inspire each other with important work full of purpose, challenging development opportunities, and rewarding careers. We aspire to be the employer of choice in our industry.
Relationships We build positive, long-term relationships with our customers, joint-venture partners, subcontractors, suppliers, and colleagues that are built on trust, respect, and collaboration.
BLACK BOX CONSTRUCTION, LLC. 3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
1.3.1 Past Projects:
Davidson Middle School
Value: $14.1 million
Location: Thomasville, NC
Brunswick County Court House
Value: $10.4 million
Location: Bolivia, NC
Hodgson Residence
Value: $8 million
Location: Wilmington, NC
BLACK BOX CONSTRUCTION, LLC. 3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
Fairfield Inn and Suite, Merrett
Value: $13.27 million
Myrtle Beach, SC
Status: Under Construction.
Completion date: April 20,2017.
Status on November 2,2016 4:35:02pm
Product at Completion
BLACK BOX CONSTRUCTION, LLC. 3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
SECTION 2 – EXECUTIVE SUMMARY
2.1 Project Description
Black Box Construction was presented with the opportunity to develop a bid proposal for providing construction services for the Porters Neck Elementary School to be built in Wilmington, NC. The project is a two storey 81,201 SF school.
The project delivery method for the project is Design-Bid-Build with a Single Prime Bid contract. This report contains information on the project estimation, schedule, building system, cost summaries, client information, project delivery system, and staffing organization.
The following items are required to be provided to the owner before commencement of construction:
1. A bid for furnishing general contracting services that includes all labor, equipment, materials, and subcontracting work for the complete scope of work as per the construction documents provided.
2. A work breakdown structure of all the activities required to complete the project. 3. A list of activities with the quantities, productivity and estimated duration needed for the
completion of each activity required to complete the project. 4. A verifiable Activity on Node (AON) diagram that details the logic sequence of the entire
construction process. 5. A CPM schedule for the project to identify the critical path for the project. 6. A schedule of values, schedule of estimated payments and a cash flow that details the flow
of money throughout the duration of project. 7. Value engineering suggestions that could be beneficial for the owner.
BLACK BOX CONSTRUCTION, LLC. 3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
2.2 Project Description:
One most important aspects of a construction project are to form an effective project team to manage the construction project effectively. The decisions made by the project team towards the management of the project ultimately impact the construction of the project. Effective management ensures on-schedule and on-budget completion of the project which is crucial for any project.
At Black Box Construction, our team recognizes the importance of the Porters Neck Elementary School project. The school is significant for the nearby community since will impact the development of children of the community.
The team at Black Box Construction adopted the following process for the completion of the scope of work of the project:
1. A detailed study of the construction documents and specification was carried out to effectively plan the scope of work.
2. The team developed pricing for various items included in the scope of work by performing detailed quantity take-offs for the self-performed work and by obtaining prices from sub-contractors for the sub-contracted work.
3. A bid was prepared by incorporating the required company overhead, profit, and contingency to the direct costs. A schedule of values was also concurrently developed.
4. The sub-contractor bids received had the sub-contractor general conditions listed as a separate item. The general conditions were proportionally distributed among the activities and the cost was adjusted for January 2017 (Refer to Appendix, )
5. Upon finalizing the cost estimate, the team started the development of a construction schedule. A work breakdown structure was developed from which the activities were logically laid out to obtain a construction schedule and the critical path for the project was identified. The schedule was developed using Primavera P6.
6. After the schedule was developed, the team focused on developing the project cash flow. The project cash flow is a representation of the expected inflow-outflow of money during the execution of the project.
7. In the final stages of the process, value engineering alternatives were discussed and the most beneficial suggestions were incorporated in the project manual subjected to the approval of the owner/architect.
BLACK BOX CONSTRUCTION, LLC. 3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
2.3 Summary of Main Findings:
Black Box Construction is pleased to provide a Single Prime Bid of $ 14,263,759 for the construction of Porters Neck Elementary School at 416 Edgewater Club Road, Wilmington, NC 28411. Please refer to Section 3, Page 14 for Bid Summary details.
The project consists of the construction of a new 80,349 sf elementary school including complete site development, roadway improvements, utilities, structural concrete, masonry and steel construction, roofing, exterior and interior finishes, equipment, fixtures, furnishing, and complete fire sprinkler, plumbing, HVAC, and electrical systems.
The Single Prime Bid provided is based on documents developed by LS3P Associates Ltd., dated August 10, 2015. The bid also incorporates adjustments in the scope of work as per Addendum 1, Addendum 2 and Addendum 3, dated August 21, 2015; August 28, 2015 and September 4, 2015 respectively.
As per the construction schedule developed for the project based on the scope of work, the estimated duration for the project is 554 Calendar Days (19 Months). Refer to Section 4, for the CPM Schedule
The project cash flow based on the 19-month project duration can be found in Section 5.2
For Value Engineering suggestions, refer to Section 5.4
For additional references, such as back-up documentation and detailed quantity take-offs, refer to Section 6, Appendix
BLACK BOX CONSTRUCTION, LLC. 3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
2.4 Closing Statement:
Black Box Construction is pleased to submit the bid proposal for general contracting services for the Porters Neck Elementary School. Our team recognizes the objectives and significance of the project and its impact on the future of the community.
Porters Neck Elementary School is a critical project for the development of the community and the future of the children of the community. A project of such significance requires a contractor who has prior experience in delivering similar projects and who is recognized for the quality of its work. Black Box Construction has worked throughout North Carolina on a wide variety of projects. More importantly, our team has prior experience of constructing public and institutional buildings such as courthouses, libraries, and schools. Our previous school project, Davidson Middle School located in Thomasville, NC was very similar in scope with the proposed project and we believe that our experience from the project would be tremendously beneficial in the successful delivery of the proposed project.
Our stellar past performance coupled with an extremely talented and dedicated core team makes us one of the frontrunners for this project. At Black Box Construction, we always put our customers first. Customer Satisfaction and Relationships has always been the priority for the company.
We hope that our bid proposal meets your expectations and we look forward to the opportunity to present our work and highlight our project management approach for the project
BLACK BOX CONSTRUCTION, LLC. 3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
SECTION 3 - ESTIMATE
3.1 Rough Order of Magnitude Estimate
A rough order of magnitude estimate is used to provide an approximate value of final construction. It is much easier and faster to arrive upon when compared to detailed estimates and is typically used in the conceptual phase, to determine project feasibility. Its accuracy is around ±20% as compared to detailed estimate.
The RS Means Building Construction Cost database provides us with data to calculate ROM for typical building construction in the United States of America. It correlated 4 different factors with the built-up space and does not include the cost of land, A/E fee and other supplemental. These factors essentially include quality of construction, size of built up area, project location and time of construction. It is important to include all these factors to arrive upon the ROM to customize the costs for our project. RS Means costs are based on a typical size project on an average city in the US.
The following process with direct us through determining ROM for our project
The following parameters have been identified from the bid documents and will enable us to arrive upon the ROM.
Parameter Constraint Construction Size 81,201 sq. ft. Quality High (Includes Site Work & Equipment) Location Wilmington, NC Time of Construction January 2017
Quality Factor
Size Factor
Location Factor
Time Factor
ROM Value
BLACK BOX CONSTRUCTION, LLC. 3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
Using RS Means data,
Per sq. ft. cost of construction:
Per sq. ft. cost for “high” quality construction for Elementary School from RS Means is $172
Size modifier:
Typical size of an elementary school from RS Means is 41,000 sq. ft. The proposed building area is 80,201 sq. ft. Size factor = Proposed building area / Typical Size Size factor = 81,201 sq. ft. / 41,000 sq. ft. Size factor = 1.98
The size modifier (cost multiplier) for the size factor of 1.98 as per the cost modifier curve is 0.95
Location modifier
Wilmington City Cost Index = 81.0 Location modifier, Wilmington = (City Cost Index Wilmington)/ (Average city USA cost index)
= 81.0 / 100 = 0.81
The location modifier for Wilmington, NC is equal to 0.81 Time modifier
Using data from ENR over RS Means for higher accuracy, the time modifier for January 2017 has been derived as follows:
May 2016 = 5,637
June 2016 = 5,636;
July 2016 = 5,660;
Aug 2016 = 5,670; ∆ Average = 11 January 2017 = July 2016 + 6 * 11 January 2017 = 5726
∆ = -1
∆ = 24
∆ = 10
BLACK BOX CONSTRUCTION, LLC. 3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
Time modifier = January 2017 Index / January 2015 Index Time modifier = 5726/5497 Time modifier = 1.04 The time modifier to adjust cost for October 2016 is equal to 1.04 ROM = Size of the building (sq. ft.) * Per square feet cost * location modifier * Size modifier *
Time modifier
ROM = 81,201 sq. ft. * $172 * 0.81 * 0.95 * 1.04 ROM = $ 11, 177, 168
Rough Order Magnitude Estimate
1 Square footage of building (sq. ft.) 81,201
2 Per sq ft. cost ($/sq ft) $172
3 Location Modifier 0.81
4 Size Modifier 0.95
5 Time Modifier 1.04
Total ROM $11,177,168
From the above calculations, the rough order magnitude estimate for the proposed school building is $11,177,168.
BLACK BOX CONSTRUCTION, LLC.
DIV Description Material ($) Labor ($) Equipment ($) Subcontractors ($) Sub-Total($)
1 General Conditions $17,806.25 $593,719.63 $56,133.73 $256,279.02 $923,938.63
2 Site Work $635,979.72 $350,787.98 $282,351.74 $0.00 $1,269,119.44
3 Concrete $253,516.49 $161,570.86 $4,938.51 $0.00 $420,025.86
4 Masonry $359,985.57 $423,520.56 $0.00 $0.00 $783,506.13
5 Metals $990,402.42 $990,402.42
6 Wood, Plastics and Composites $216,290.00 $216,290.00
7 Thermal and Moisture Protection $444,863.24 $444,863.24
8 Openings $379,003.57 $379,003.57
9 Finishes $1,391,528.89 $1,391,528.89
10 Specialities $632,261.56 $632,261.56
11 Equipment $259,075.18 $259,075.18
12 Furnishings $75,178.28 $75,178.28
14 Conveying Equipment $251,217.60 $251,217.60
21 Fire Supression $1,054,680.98 $1,054,680.98
22 Plumbing $629,995.43 $629,995.43
23 HVAC $1,470,781.29 $1,470,781.29
27 Communications $383,335.93 $383,335.93
28 Electronic Safety and Security $59,013.86 $59,013.86
32 Exterior Improvements $266,385.12 $266,385.12
33 Utilities $397,860.98 $397,860.98
Total Direct Cost $12,298,464.40
Company Overhead (CoOH) (7.98% of Direct Cost) $981,417.46
Profit (4% of Direct Cost) $491,938.58
Contingency (4% of Direct Cost) $491,938.58
Total Mark-Up (15.98% of Direct Cost) $1,965,294.61$14,263,759
For General Conditions, Refer to Page 41
For Company Overhead Calculation, Refer to Page 20
Total Project Cost (BID VALUE)
3.2 SUMMARY OF BID
17
BLACK BOX CONSTRUCTION, LLC.
DIV Direct Cost Material Labor Equipment Subcontractors Sub-TotalDIV 1 General Conditions $ 923,938.63
Field Supervision $0.00 $582,734.13 $31,208.67 $0.00 $613,942.80Site Office $0.00 $0.00 $8,281.40 $14,156.67 $22,438.06Site Access $17,806.25 $10,985.50 $3,960.00 $0.00 $32,751.75Temporary Utilities/Storage $0.00 $0.00 $9,298.67 $52,814.67 $62,113.33Site Construction Facilities $0.00 $0.00 $0.00 $13,000.00 $13,000.00Small Tools and Equipments $0.00 $0.00 $2,000.00 $0.00 $2,000.00Permits $0.00 $0.00 $1,385.00 $176,307.68 $177,692.68
DIV 2 Site Work $1,269,119.44Grading, Stone, Paving, Utilities, Survey $285,107.65 $319,240.44 $255,057.98 $0.00 $859,406.07Paving $333,758.88 $23,250.24 $27,293.76 $0.00 $384,302.88Termite Treatment $17,113.19 $8,297.30 $0.00 $0.00 $25,410.49
DIV 3 Concrete $420,025.86Spread Footings $10,636.98 $6,166.37 $37.51 $0.00 $16,840.86Reinforcment for Spread Footings $808.70 $682.34 $0.00 $0.00 $1,491.05Strip Footings $38,750.40 $24,335.25 $0.00 $0.00 $63,085.65Elevated Slabs $32,600.88 $17,311.32 $131.41 $0.00 $50,043.61Slab on Grade $82,588.90 $43,855.34 $332.92 $0.00 $126,777.16Stair Concrete $2,308.18 $549.24 $158.37 $0.00 $3,015.79Site Concrete Aggregate $14,783.95 $11,638.43 $629.10 $0.00 $27,051.49Site Concrete $56,304.84 $55,361.18 $0.00 $0.00 $111,666.02Precast Material and Erection $14,733.66 $1,671.38 $3,649.19 $0.00 $20,054.23
DIV4 Masonry $783,506.13Masonry (CMU) $189,036.33 $255,440.03 $0.00 $444,476.35Anchor Bolts for Brick Vaneer $7,707.96 $5,180.76 $12,888.72Brickwork $163,241.28 $162,899.77 $326,141.06
DIV 5 Metals $990,402.42Structural and Misc Steel $968,749.28 $968,749.28Misc. Steel $18,997.30 $18,997.30Column Covers $2,655.84 $2,655.84
DIV 6 Wood, Plastics and Composites $216,290.00Millwork and Window Seals $216,290.00 $216,290.00
DIV 7 Thermal and Moisture Protection $444,863.24Waterproof Membrane & Sheet Waterproofing $14,216.20 $14,216.20Extensions Joints/Caulking $14,665.68 $14,665.68Roof Nailers $33,889.12 $33,889.12Traffic Coatings $6,045.52 $6,045.52PVC Roofing $242,340.65 $242,340.65ACM Panel $44,746.63 $44,746.63Roof Expansion Joints $7,642.58 $7,642.58Spray Foam Beam Infill $3,645.17 $3,645.17Foam Insulation $77,671.70 $77,671.70
DIV 8 Openings $379,003.57Coiling Doors $25,150.00 $25,150.00Aluminum Storefront $349,886.80 $349,886.80Louvers $3,966.77 $3,966.77
DIV 9 Finishes $1,391,528.89Dry Wall- Wall $168,206.60 $168,206.60Dry Wall-Ceilings $8,701.55 $8,701.55Framing $100,372.15 $100,372.15Inwall Blocking $18,207.59 $18,207.59Fiber Cement $4,726.14 $4,726.14ACT Ceilings $600,630.30 $600,630.30ACT Wall Panels $17,207.64 $17,207.64Ceramic Tiles $82,043.97 $82,043.97VCT Tile $175,504.69 $175,504.69Carpet Tiling $20,575.40 $20,575.40Stage Flooring $6,350.29 $6,350.29Painting $140,135.40 $140,135.40Wall Graphics $3,018.00 $3,018.00Wall Padding $32,923.09 $32,923.09Window Treatments $12,926.09 $12,926.09
3.3 DETAILED ESTIMATE BY DIVISION
18
BLACK BOX CONSTRUCTION, LLC.
DIV 10 Specialities $632,261.56Hollow Metal, Wood Dorrs, Toilet Part, Toilet acc, FEC $271,248.79 $271,248.79Signage and Marquee $24,850.21 $24,850.21Basket Ball Goals $6,514.59 $6,514.59Lockers $1,355.25 $1,355.25Banners $672.98 $672.98Operable Partititon $124,399.16 $124,399.16Aluminum Canopies $190,735.40 $190,735.40Flagpoles $12,485.18 $12,485.18
DIV 11 Equipment $259,075.18Food Service Equipment $227,356.00 $227,356.00Kiln $4,315.74 $4,315.74Residential Appliances $7,492.69 $7,492.69Stage Curtains, Folding Stages, Cubicle Curtains $19,910.75 $19,910.75
DIV 12 Furnishings $75,178.28Wood Shelving $70,340.78 $70,340.78Display Cases $4,837.50 $4,837.50
DIV 14 Conveying Equipment $251,217.60Elevators $251,217.60 $251,217.60
DIV 21 Fire Supression $1,054,680.98Spray Fireproofing $449,541.93 $449,541.93Misc Firestopping $195,558.75 $195,558.75Fire Sprinklers $409,580.29 $409,580.29
DIV 22 Plumbing $629,995.43Plumbing System Sub-Contract $629,995.43 $629,995.43
DIV 23 HVAC $1,470,781.29HVAC System Sub-Contract $1,470,781.29 $1,470,781.29
DIV 26 Electrical $383,335.93Electrical System Sub-Contract $383,335.93 $383,335.93
DIV 27 Communications $59,013.86Communication System $59,013.86 $59,013.86
DIV 28 Electronic Safety and Security $266,385.12Fire Alarm $146,465.21 $146,465.21Security $119,919.91 $119,919.91
DIV 32 Exterior Improvements $397,860.98Fencing $35,284.98 $35,284.98Landscaping and Irrigation $362,576.00 $362,576.00
19
CASH FLOW
Activities SOV Work Type 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17General Conditions 516,978$ Self Performed 32,311$ 32,311$ 32,311$ 32,311$ 32,311$ 32,311$ 32,311$ 32,311$ 32,311$ 32,311$ 32,311$ 32,311$ 32,311$ 32,311$ 32,311$ 32,311$ Site work 284,695$ Self Performed 284,695$ Grading and Footing Excavation 444,319$ Self Performed 133,296$ 311,023$ Utility Pipelines 199,935$ Self Performed 119,961$ 79,974$ Foundation 166,970$ Self Performed 166,970$ Steel 894,611$ Sub-Contracted 894,611$ Concrete Slab 246,949$ Sub-Contracted 49,390$ 197,559$ Caulking 12,706$ Sub-Contracted 12,706$ Masonary 620,758$ Sub-Contracted 248,303$ 372,455$ H.V.A.C 1,274,271$ Sub-Contracted 127,427$ 318,568$ 318,568$ 318,568$ 191,141$ Plumbing 736,769$ Sub-Contracted 221,031$ 294,708$ 221,031$ Electrical 353,999$ Sub-Contracted 106,200$ 247,799$ Elevator 217,653$ Sub-Contracted 217,653$ Exterior Finishings 1,183,747$ Sub-Contracted 591,874$ 591,874$ Brick Veneer 951,998$ Sub-Contracted 380,799$ 571,199$ Roof 303,662$ Sub-Contracted 242,929$ 60,732$ Partition walls 145,297$ Sub-Contracted 58,119$ 36,324$ 36,324$ 14,530$ Dry Wall 209,668$ Sub-Contracted 146,767$ 62,900$ Speciality Rough-ins 729,034$ Sub-Contracted 218,710$ 291,613$ 218,710$ Interior finishes 1,256,042$ Sub-Contracted 125,604$ 62,802$ 125,604$ 502,417$ 314,010$ 125,604$ Door and Windows 453,716$ Sub-Contracted 45,372$ 90,743$ 45,372$ 272,230$ Paint 147,507$ Sub-Contracted 44,252$ 103,255$ Exterior Landscaping 334,828$ Sub-Contracted 284,604$ 50,224$ Hardware 258,876$ Sub-Contracted 194,157$ 64,719$ Miscellaneous 62,809$ Sub-Contracted 3,140$ 6,281$ 53,387$ Kitchen Appliances 274,652$ Sub-Contracted 274,652$ Cleaning 6,378$ Self Performed 6,378$ Final Punch List 117,650$ Self Performed 117,650$
570,263$ 423,308$ 199,281$ 976,312$ 490,879$ 1,598,469$ 1,860,448$ 840,668$ 681,907$ 697,804$ 799,949$ 877,994$ 700,027$ 581,194$ 836,689$ 271,282$ DC as a % of SOV (85%) (1) 484,723$ 359,812$ 169,389$ 829,865$ 417,248$ 1,358,699$ 1,581,380$ 714,568$ 579,621$ 593,134$ 679,956$ 746,295$ 595,023$ 494,015$ 711,186$ 230,590$ COOH as a % of SOV (10%) (2) 57,026$ 42,331$ 19,928$ 97,631$ 49,088$ 159,847$ 186,045$ 84,067$ 68,191$ 69,780$ 79,995$ 87,799$ 70,003$ 58,119$ 83,669$ 27,128$ P+C as a & of SOV (5%) (3) 28,513$ 21,165$ 9,964$ 48,816$ 24,544$ 79,923$ 93,022$ 42,033$ 34,095$ 34,890$ 39,997$ 43,900$ 35,001$ 29,060$ 41,834$ 13,564$ $ paid or spent by the GC 541,750$ 402,143$ 189,317$ 30,696$ 30,696$ 30,696$ 30,696$ 30,696$ 30,696$ 30,696$ 30,696$ 30,696$ 30,696$ 30,696$ 30,696$ 139,892$ $ paid or spent by subs 896,801$ 435,640$ 1,487,850$ 1,736,730$ 767,939$ 617,116$ 632,219$ 729,256$ 803,398$ 634,330$ 521,439$ 764,159$ 117,826$ $ Billed to the client 570,263$ 423,308$ 199,281$ 976,312$ 490,879$ 1,598,469$ 1,860,448$ 840,668$ 681,907$ 697,804$ 799,949$ 877,994$ 700,027$ 581,194$ 836,689$ 271,282$ % Retained by the client (5%) 57,026$ 42,331$ 19,928$ 97,631$ 49,088$ 159,847$ 186,045$ 84,067$ 68,191$ 69,780$ 79,995$ 87,799$ 70,003$ 58,119$ 83,669$ 27,128$ Money Received from client 513,236$ 380,978$ 179,353$ 878,681$ 441,792$ 1,438,622$ 1,674,403$ 756,601$ 613,716$ 628,024$ 719,954$ 790,194$ 630,024$ 523,075$ 753,020$ 244,154$ $ Billed by subs to GC 896,801$ 435,640$ 1,487,850$ 1,736,730$ 767,939$ 617,116$ 632,219$ 729,256$ 803,398$ 634,330$ 521,439$ 764,159$ 117,826$ % Retained by GC on Sub (5%) 89,680$ 43,564$ 148,785$ 173,673$ 76,794$ 61,712$ 63,222$ 72,926$ 80,340$ 63,433$ 52,144$ 76,416$ 11,783$ Total amount of money paid to sub by GC 807,121$ 392,076$ 1,339,065$ 1,563,057$ 691,145$ 555,405$ 568,997$ 656,330$ 723,059$ 570,897$ 469,295$ 687,743$ 106,044$ Net Paid or spent by GC -$ 541,750 $ 111,093 $ 191,660 $ 148,658 $ 40,864 $ 19,020 $ 68,862 $ 80,651 $ 34,761 $ 27,616 $ 28,332 $ 32,928 $ 36,440 $ 28,432 $ 23,084 -$ 74,615 $ 364,287Cumulative of net paid by GC -$ 541,750 -$ 430,656 -$ 238,996 -$ 90,338 -$ 49,474 -$ 30,454 $ 38,408 $ 119,058 $ 153,819 $ 181,435 $ 209,767 $ 242,695 $ 279,135 $ 307,567 $ 330,651 $ 256,036 $ 620,324
GC is going to submit the bills at end of every month and GC will get paid after one month of the billing.Subcontractor will submit their bill at end of each month and will get paid by GC after one month of billing.Retainage will be 5% for the GC and Subcontractor.
-$ 600,000
-$ 400,000
-$ 200,000
$ 0
$ 200,000
$ 400,000
$ 600,000
$ 800,000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Series1
BLACK BOX CONSTRUCTION, LLC.
Q1 Q3 Q4
P1 P2 P3 P4 P5
Sales $12,200,000 $1,275,000 $2,335,000 $4,010,000 $1,130,000 $20,950,000PoOH $1,464,000 $153,000 $280,200 $481,200 $135,600 $2,514,000Labor $3,721,000 $318,750 $553,750 $1,223,050 $344,650 $6,161,200Materials $3,660,000 $372,500 $700,500 $1,203,000 $339,000 $6,275,000Equipment $1,586,000 $165,750 $303,550 $521,300 $126,900 $2,703,500Subcontractors - $63,519 $190,000 - - $253,519Direct Cost (DC) $10,431,000 $1,073,519 $2,028,000 $3,428,550 $946,150 $17,907,219CoOH $771,894 $62,420 $162,292 $271,285 $71,495 $1,339,386Profit $997,106 $139,061 $144,708 $310,165 $112,355 $1,703,395
$17,907,219
$1,339,386
$1,703,395
7.48
3.5 Sales History - 2015
Black Box Construction, LLC., Sales History - 2015
DescriptionQ2
Total
The increase of 0.5% is to take into consideration a 5% salary increase (An increase of $ 60,960) that is proposed for the employees and also the increase in the CoOH to account for increase in the cost of utilities such as Electricity, Internet, Legal Services, Maintenance costs, Insurance costs etc.
Total Direct Cost for 2015
Company Overhead for 2015
Profit
CooH as a percentage of Direct Costs
For, the school project we propose a CoOH of 7.98%
22
BLACK BOX CONSTRUCTION, LLC.
Employee Base Salary Rate Burdened Salary BurdenPresident $150,000 1.32 $197,714 $47,714CFO $120,000 1.34 $161,219 $41,219Sr .Estimator $85,000 1.42 $121,073 $36,073Estimator $75,000 1.37 $103,093 $28,093Sr. Scheduler $75,000 1.46 $109,740 $34,740Scheduler 65,000$ 1.41 $91,361 $26,361Safety Manager (60%) $34,800 1.80 $62,766 $27,966Office Manager $50,000 1.37 $68,316 $18,316Bid Co-ordinator $50,000 1.37 $68,316 $18,316Acountant $50,000 1.37 $68,316 $18,316Administrator $45,000 1.28 $57,412 $12,412HR $45,000 1.28 $57,412 $12,412Receptionist $37,440 1.40 $52,467 $15,027Total $882,240 $1,219,205 $336,965
Employee Base Salary Rate Burdened Salary BurdenProject Manager $75,000 1.56 $116,693 $41,693Field Superintendent $60,000 1.60 $96,011 $36,011Project Engineer $55,000 1.62 $88,834 $33,834General Superintendent (40% of Time)$26,000 1.59 $41,276 $15,276Safety Manager (40%) $23,200 1.80 $41,844 $18,644Total $239,200 $384,659 $145,459
General Superintendent - 40% on this project, 60% on other projects
3.6 Labor Burden
*Refer to Labor Burden Sheets for Calculations
Labor Burden (Part of PoOH)
Labor Burden (Part of CoOH)
Safety Manager - Base Salary - $58,000 is split 60% in Office and 40% in Field
23
BLACK BOX CONSTRUCTION, LLC.
Base Yearly Salary 150,000.00$ per yearEquivalent "Base" Wage Per Hour 72.12$ "Base" Hourly Wage 72.12$ per hour WORK DAYS:Contracted Work Hours (CWH) 52 weeks 40 hours/week 2080 hours per year 260This is the Hourly "Base" Rate Used for Labor Burden Calculation 72.12$
Vacation 10 days 8 hours/day 80 hours per yearHolidays 10 days 8 hours/day 80 hours per year
Sick Leave 5 days 8 hours/day 40 hours per yearCompany Wide Meetings/Employer Required Training 1 days 4 hours/day 4 hours per year
Bad Weather Minimum Show-Up Time 0 days 0 hours/day 0 hours per yearMorning Meetings 235 days 0 hours/day 0 hours per year
Rest Breaks 235 days 0 hours/day 0 hours per yearEffective Work Hours = Contracted - Unbillable 1876 hours per year
Company Paid Overtime Work Time (If Any) 0.0% as a % of CWH overtime rate 108.18$ per hourCompany Paid Overtime 0 hours/year per year -$ -$ per/hr
Company Paid Allowance for Use of Personal Car $0 per month per year -$ -$ per/hrCompany Paid Health Care Allowance* $300 per month per year 3,600.0$ 1.92$ per/hr
Company Paid Bonus 0 per month per year -$ -$ per/hrCost of Taxable, Company Paid, Allowances and Cash Equivalents 1.92$ per/hrHourly Rate a): Inclusive of Portion 1 (Used for Wcomp and Building Risk and Pub Liability Insurance Cost Calc) 74.04$ per/hrPreTax Payments Made By Employee for Insurance -$ per month per year -$ -$ per/hrHourly Rate b) Incluse of Portion 1 (Used for SS and Medicare Tax Calc) 74.04$ per/hr
Required Insurance and Taxes Enter EMR 0.85 per hourWorkers Compensation Ins. 1.50 1.275 % of Hourly Rate a) 0.94$ per hour
Builders Risk and Public Liability Ins. 8.00 per 1,000 of Hourly Rate a) 0.59$ per hourFederal Unemployment Tax 0.25 % 9,000.00$ is Co's Federal Tax Base 0.01$ per hour
State Unemployment Tax 3.00 % 24,400.00$ is Co's State Tax Base 0.39$ per hourSocial Security Tax 6.20 % of Hourly Rate b) 4.59$ per hour
Medicare, Medicaid Tax 1.45 % of Hourly Rate b) 1.07$ per hour Cost of Government Required Insurance and Taxes 7.60$ per/hrHourly Rate c): Inclusive of Portion 2 81.64$ per/hr
Vacation 80 hours 81.64$ per hour 6,531.3$ 3.48$ per/hrHolidays 80 hours 81.64$ per hour 6,531.3$ 3.48$ per/hr
Sick Leave 40 hours 81.64$ per hour 3,265.7$ 1.74$ per/hrCompany Wide Meetings/Training 4 hours 81.64$ per hour 326.6$ 0.17$ per/hr
Bad Weather Minimum Show-Up Time 0 hours 81.64$ per hour -$ -$ per/hrMorning Meetings 0 hours 81.64$ per hour -$ -$ per/hr
Rest Breaks 0 hours 81.64$ per hour -$ -$ per/hr 16,654.86$ 8.88$ per/hr
Hourly Wage d): Inclusive of Portion 3 90.52$ per/hr
Group Health Insurance (includes Dental)* 100.00$ per month 1,200.0$ per year 0.64$ per hour Disability Insurance (Short Term) 10.00$ per month 120.0$ per year 0.06$ per hourDisability Insurance (Long Term) 10.00$ per month 120.0$ per year 0.06$ per hour
401K 20.00$ per month 240.0$ per year 0.13$ per hour Company Provided Car 500.00$ per month 6,000.0$ per year 3.20$ per hour
Company Provided Cell Phone 70.00$ per month 840.0$ per year 0.45$ per hour Cost of Non-Taxable, Company Paid, Fringes 4.54$ per/hrHourly Wage e): Inclusive of Portion 4 95.06$ per/hr
BURDEN FOR THIS EMPLOYEE IS: 72.12$ "Base" Rate Compared To: 95.06$ 1.32
Labor Burden -President
Portion 1 of Labor Burden: Cost of Taxable, Company Paid, Cash Allowances and Other Taxable Cash Equivalents
Portion 2 of Labor Burden: Cost of Government Required Insurance and Taxes
Portion 3 of Labor Burden: Cost of Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Portion 4 of Labor Burden: Cost of Non Taxable, Company Paid, Fringes
Company Unbillable Paid Time: Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
24
BLACK BOX CONSTRUCTION, LLC.
Base Yearly Salary 120,000.00$ per yearEquivalent "Base" Wage Per Hour 57.69$ "Base" Hourly Wage 57.69$ per hour WORK DAYS:Contracted Work Hours (CWH) 52 weeks 40 hours/week 2080 hours per year 260This is the Hourly "Base" Rate Used for Labor Burden Calculation 57.69$
Vacation 10 days 8 hours/day 80 hours per yearHolidays 10 days 8 hours/day 80 hours per year
Sick Leave 5 days 8 hours/day 40 hours per yearCompany Wide Meetings/Employer Required Training 1 days 4 hours/day 4 hours per year
Bad Weather Minimum Show-Up Time 0 days 0 hours/day 0 hours per yearMorning Meetings 235 days 0 hours/day 0 hours per year
Rest Breaks 235 days 0 hours/day 0 hours per yearEffective Work Hours = Contracted - Unbillable 1876 hours per year
Company Paid Overtime Work Time (If Any) 0.0% as a % of CWH overtime rate 86.54$ per hourCompany Paid Overtime 0 hours/year per year -$ -$ per/hr
Company Paid Allowance for Use of Personal Car $0 per month per year -$ -$ per/hrCompany Paid Health Care Allowance* $300 per month per year 3,600.0$ 1.92$ per/hr
Company Paid Bonus 0 per month per year -$ -$ per/hrCost of Taxable, Company Paid, Allowances and Cash Equivalents 1.92$ per/hrHourly Rate a): Inclusive of Portion 1 (Used for Wcomp and Building Risk and Pub Liability Insurance Cost Calc) 59.61$ per/hrPreTax Payments Made By Employee for Insurance -$ per month per year -$ -$ per/hrHourly Rate b) Incluse of Portion 1 (Used for SS and Medicare Tax Calc) 59.61$ per/hr
Required Insurance and Taxes Enter EMR 0.85 per hourWorkers Compensation Ins. 1.50 1.275 % of Hourly Rate a) 0.76$ per hour
Builders Risk and Public Liability Ins. 8.00 per 1,000 of Hourly Rate a) 0.48$ per hourFederal Unemployment Tax 0.25 % 9,000.00$ is Co's Federal Tax Base 0.01$ per hour
State Unemployment Tax 3.00 % 24,400.00$ is Co's State Tax Base 0.39$ per hourSocial Security Tax 6.20 % of Hourly Rate b) 3.70$ per hour
Medicare, Medicaid Tax 1.45 % of Hourly Rate b) 0.86$ per hour Cost of Government Required Insurance and Taxes 6.20$ per/hrHourly Rate c): Inclusive of Portion 2 65.81$ per/hr
Vacation 80 hours 65.81$ per hour 5,264.7$ 2.81$ per/hrHolidays 80 hours 65.81$ per hour 5,264.7$ 2.81$ per/hr
Sick Leave 40 hours 65.81$ per hour 2,632.3$ 1.40$ per/hrCompany Wide Meetings/Training 4 hours 65.81$ per hour 263.2$ 0.14$ per/hr
Bad Weather Minimum Show-Up Time 0 hours 65.81$ per hour -$ -$ per/hrMorning Meetings 0 hours 65.81$ per hour -$ -$ per/hr
Rest Breaks 0 hours 65.81$ per hour -$ -$ per/hr per year 13,424.86$ 7.16$ per/hr
Hourly Wage d): Inclusive of Portion 3 72.96$ per/hr
Group Health Insurance (includes Dental)* 100.00$ per month 1,200.0$ per year 0.64$ per hour Disability Insurance (Short Term) 10.00$ per month 120.0$ per year 0.06$ per hourDisability Insurance (Long Term) 10.00$ per month 120.0$ per year 0.06$ per hour
401K 20.00$ per month 240.0$ per year 0.13$ per hour Company Provided Car 500.00$ per month 6,000.0$ per year 3.20$ per hour
Company Provided Cell Phone 70.00$ per month 840.0$ per year 0.45$ per hour Cost of Non-Taxable, Company Paid, Fringes 4.54$ per/hrHourly Wage e): Inclusive of Portion 4 77.51$ per/hrBURDEN FOR THIS EMPLOYEE IS: 57.69$ "Base" Rate Compared To: 77.51$ 1.34
Portion 4 of Labor Burden: Cost of Non Taxable, Company Paid, Fringes
Labor Burden -Chief Financial Officer (CFO)
Company Unbillable Paid Time: Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Portion 1 of Labor Burden: Cost of Taxable, Company Paid, Cash Allowances and Other Taxable Cash Equivalents
Portion 2 of Labor Burden: Cost of Government Required Insurance and Taxes
Portion 3 of Labor Burden: Cost of Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
25
BLACK BOX CONSTRUCTION, LLC.
Base Yearly Salary 85,000.00$ per yearEquivalent "Base" Wage Per Hour 40.87$ "Base" Hourly Wage 40.87$ per hour WORK DAYS:Contracted Work Hours (CWH) 52 weeks 40 hours/week 2080 hours per year 260This is the Hourly "Base" Rate Used for Labor Burden Calculation 40.87$
Vacation 10 days 8 hours/day 80 hours per yearHolidays 10 days 8 hours/day 80 hours per year
Sick Leave 5 days 8 hours/day 40 hours per yearCompany Wide Meetings/Employer Required Training 0 days 0 hours/day 0 hours per year
Bad Weather Minimum Show-Up Time 0 days 0 hours/day 0 hours per yearMorning Meetings 235 days 0 hours/day 0 hours per year
Rest Breaks 235 days 0 hours/day 0 hours per yearEffective Work Hours = Contracted - Unbillable 1880 hours per year
Company Paid Overtime Work Time (If Any) 0.0% as a % of CWH overtime rate 61.31$ per hourCompany Paid Overtime 0 hours/year per year -$ -$ per/hr
Company Paid Allowance for Use of Personal Car $250 per month per year 3,000.0$ 1.60$ per/hrCompany Paid Health Care Allowance* $300 per month per year 3,600.0$ 1.91$ per/hr
Company Paid Bonus 0 per month per year -$ -$ per/hrCost of Taxable, Company Paid, Allowances and Cash Equivalents 3.51$ per/hrHourly Rate a): Inclusive of Portion 1 (Used for Wcomp and Building Risk and Pub Liability Insurance Cost Calc) 44.38$ per/hrPreTax Payments Made By Employee for Insurance -$ per month per year -$ -$ per/hrHourly Rate b) Incluse of Portion 1 (Used for SS and Medicare Tax Calc) 44.38$ per/hr
Required Insurance and Taxes Enter EMR 0.85 per hourWorkers Compensation Ins. 1.50 1.275 % of Hourly Rate a) 0.57$ per hour
Builders Risk and Public Liability Ins. 8.00 per 1,000 of Hourly Rate a) 0.36$ per hourFederal Unemployment Tax 0.25 % 9,000.00$ is Co's Federal Tax Base 0.01$ per hour
State Unemployment Tax 3.00 % 24,400.00$ is Co's State Tax Base 0.39$ per hourSocial Security Tax 6.20 % of Hourly Rate b) 2.75$ per hour
Medicare, Medicaid Tax 1.45 % of Hourly Rate b) 0.64$ per hour Cost of Government Required Insurance and Taxes 4.72$ per/hrHourly Rate c): Inclusive of Portion 2 49.10$ per/hr
Vacation 80 hours 49.10$ per hour 3,927.8$ 2.09$ per/hrHolidays 80 hours 49.10$ per hour 3,927.8$ 2.09$ per/hr
Sick Leave 40 hours 49.10$ per hour 1,963.9$ 1.04$ per/hrCompany Wide Meetings/Training 0 hours 49.10$ per hour -$ -$ per/hr
Bad Weather Minimum Show-Up Time 0 hours 49.10$ per hour -$ -$ per/hrMorning Meetings 0 hours 49.10$ per hour -$ -$ per/hr
Rest Breaks 0 hours 49.10$ per hour -$ -$ per/hr per year 9,819.60$ 5.22$ per/hr
Hourly Wage d): Inclusive of Portion 3 54.32$ per/hr
Group Health Insurance (includes Dental)* 100.00$ per month 1,200.0$ per year 0.64$ per hour Disability Insurance (Short Term) 10.00$ per month 120.0$ per year 0.06$ per hourDisability Insurance (Long Term) 10.00$ per month 120.0$ per year 0.06$ per hour
401K 20.00$ per month 240.0$ per year 0.13$ per hour Company Provided Car 400.00$ per month 4,800.0$ per year 2.55$ per hour
Company Provided Cell Phone 70.00$ per month 840.0$ per year 0.45$ per hour Cost of Non-Taxable, Company Paid, Fringes 3.89$ per/hrHourly Wage e): Inclusive of Portion 4 58.21$ per/hrBURDEN FOR THIS EMPLOYEE IS: 40.87$ "Base" Rate Compared To: 58.21$ 1.42
Portion 4 of Labor Burden: Cost of Non Taxable, Company Paid, Fringes
Labor Burden - Senior Estimator
Company Unbillable Paid Time: Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Portion 1 of Labor Burden: Cost of Taxable, Company Paid, Cash Allowances and Other Taxable Cash Equivalents
Portion 2 of Labor Burden: Cost of Government Required Insurance and Taxes
Portion 3 of Labor Burden: Cost of Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
26
BLACK BOX CONSTRUCTION, LLC.
Base Yearly Salary 75,000.00$ per yearEquivalent "Base" Wage Per Hour 36.06$ "Base" Hourly Wage 36.06$ per hour WORK DAYS:Contracted Work Hours (CWH) 52 weeks 40 hours/week 2080 hours per year 260This is the Hourly "Base" Rate Used for Labor Burden Calculation 36.06$
Vacation 10 days 8 hours/day 80 hours per yearHolidays 10 days 8 hours/day 80 hours per year
Sick Leave 5 days 8 hours/day 40 hours per yearCompany Wide Meetings/Employer Required Training 0 days 0 hours/day 0 hours per year
Bad Weather Minimum Show-Up Time 0 days 0 hours/day 0 hours per yearMorning Meetings 235 days 0 hours/day 0 hours per year
Rest Breaks 235 days 0 hours/day 0 hours per yearEffective Work Hours = Contracted - Unbillable 1880 hours per year
Company Paid Overtime Work Time (If Any) 0.0% as a % of CWH overtime rate 54.09$ per hourCompany Paid Overtime 0 hours/year per year -$ -$ per/hr
Company Paid Allowance for Use of Personal Car $250 per month per year 3,000.0$ 1.60$ per/hrCompany Paid Health Care Allowance* $300 per month per year 3,600.0$ 1.91$ per/hr
Company Paid Bonus 0 per month per year -$ -$ per/hrCost of Taxable, Company Paid, Allowances and Cash Equivalents 3.51$ per/hrHourly Rate a): Inclusive of Portion 1 (Used for Wcomp and Building Risk and Pub Liability Insurance Cost Calc) 39.57$ per/hrPreTax Payments Made By Employee for Insurance -$ per month per year -$ -$ per/hrHourly Rate b) Incluse of Portion 1 (Used for SS and Medicare Tax Calc) 39.57$ per/hr
Required Insurance and Taxes Enter EMR 0.85 per hourWorkers Compensation Ins. 1.50 1.275 % of Hourly Rate a) 0.50$ per hour
Builders Risk and Public Liability Ins. 8.00 per 1,000 of Hourly Rate a) 0.32$ per hourFederal Unemployment Tax 0.25 % 9,000.00$ is Co's Federal Tax Base 0.01$ per hour
State Unemployment Tax 3.00 % 24,400.00$ is Co's State Tax Base 0.39$ per hourSocial Security Tax 6.20 % of Hourly Rate b) 2.45$ per hour
Medicare, Medicaid Tax 1.45 % of Hourly Rate b) 0.57$ per hour Cost of Government Required Insurance and Taxes 4.25$ per/hrHourly Rate c): Inclusive of Portion 2 43.82$ per/hr
Vacation 80 hours 43.82$ per hour 3,505.6$ 1.86$ per/hrHolidays 80 hours 43.82$ per hour 3,505.6$ 1.86$ per/hr
Sick Leave 40 hours 43.82$ per hour 1,752.8$ 0.93$ per/hrCompany Wide Meetings/Training 0 hours 43.82$ per hour -$ -$ per/hr
Bad Weather Minimum Show-Up Time 0 hours 43.82$ per hour -$ -$ per/hrMorning Meetings 0 hours 43.82$ per hour -$ -$ per/hr
Rest Breaks 0 hours 43.82$ per hour -$ -$ per/hr per year 8,764.04$ 4.66$ per/hr
Hourly Wage d): Inclusive of Portion 3 48.48$ per/hr
Group Health Insurance (includes Dental)* 100.00$ per month 1,200.0$ per year 0.64$ per hour Disability Insurance (Short Term) 10.00$ per month 120.0$ per year 0.06$ per hourDisability Insurance (Long Term) 10.00$ per month 120.0$ per year 0.06$ per hour
401K 20.00$ per month 240.0$ per year 0.13$ per hour Company Provided Cell Phone 30.00$ per month 360.0$ per year 0.19$ per hour
Cost of Non-Taxable, Company Paid, Fringes 1.09$ per/hrHourly Wage e): Inclusive of Portion 4 49.57$ per/hrBURDEN FOR THIS EMPLOYEE IS: 36.06$ "Base" Rate Compared To: 49.57$ 1.37
Labor Burden - Estimator
Portion 1 of Labor Burden: Cost of Taxable, Company Paid, Cash Allowances and Other Taxable Cash Equivalents
Portion 2 of Labor Burden: Cost of Government Required Insurance and Taxes
Portion 3 of Labor Burden: Cost of Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Portion 4 of Labor Burden: Cost of Non Taxable, Company Paid, Fringes
Company Unbillable Paid Time: Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
27
BLACK BOX CONSTRUCTION, LLC.
Base Yearly Salary 75,000.00$ per yearEquivalent "Base" Wage Per Hour 36.06$ "Base" Hourly Wage 36.06$ per hour WORK DAYS:Contracted Work Hours (CWH) 52 weeks 40 hours/week 2080 hours per year 260This is the Hourly "Base" Rate Used for Labor Burden Calculation 36.06$ Company Unbillable Paid Time: Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Vacation 10 days 8 hours/day 80 hours per yearHolidays 10 days 8 hours/day 80 hours per year
Sick Leave 5 days 8 hours/day 40 hours per yearCompany Wide Meetings/Employer Required Training 0 days 0 hours/day 0 hours per year
Bad Weather Minimum Show-Up Time 0 days 0 hours/day 0 hours per yearMorning Meetings 235 days 0 hours/day 0 hours per year
Rest Breaks 235 days 0 hours/day 0 hours per yearEffective Work Hours = Contracted - Unbillable 1880 hours per year
Company Paid Overtime Work Time (If Any) 0.0% as a % of CWH overtime rate 54.09$ per hourCompany Paid Overtime 0 hours/year per year -$ -$ per/hr
Company Paid Allowance for Use of Personal Car $300 per month per year 3,600.0$ 1.91$ per/hrCompany Paid Health Care Allowance* $300 per month per year 3,600.0$ 1.91$ per/hr
Company Paid Bonus 0 per month per year -$ -$ per/hrCost of Taxable, Company Paid, Allowances and Cash Equivalents 3.83$ per/hrHourly Rate a): Inclusive of Portion 1 (Used for Wcomp and Building Risk and Pub Liability Insurance Cost Calc) 39.89$ per/hrPreTax Payments Made By Employee for Insurance -$ per month per year -$ -$ per/hrHourly Rate b) Incluse of Portion 1 (Used for SS and Medicare Tax Calc) 39.89$ per/hr
Required Insurance and Taxes Enter EMR 0.85 per hourWorkers Compensation Ins. 1.50 1.275 % of Hourly Rate a) 0.51$ per hour
Builders Risk and Public Liability Ins. 8.00 per 1,000 of Hourly Rate a) 0.32$ per hourFederal Unemployment Tax 0.25 % 9,000.00$ is Co's Federal Tax Base 0.01$ per hour
State Unemployment Tax 3.00 % 24,400.00$ is Co's State Tax Base 0.39$ per hourSocial Security Tax 6.20 % of Hourly Rate b) 2.47$ per hour
Medicare, Medicaid Tax 1.45 % of Hourly Rate b) 0.58$ per hour Cost of Government Required Insurance and Taxes 4.28$ per/hrHourly Rate c): Inclusive of Portion 2 44.17$ per/hr
Vacation 80 hours 44.17$ per hour 3,533.6$ 1.88$ per/hrHolidays 80 hours 44.17$ per hour 3,533.6$ 1.88$ per/hr
Sick Leave 40 hours 44.17$ per hour 1,766.8$ 0.94$ per/hrCompany Wide Meetings/Training 0 hours 44.17$ per hour -$ -$ per/hr
Bad Weather Minimum Show-Up Time 0 hours 44.17$ per hour -$ -$ per/hrMorning Meetings 0 hours 44.17$ per hour -$ -$ per/hr
Rest Breaks 0 hours 44.17$ per hour -$ -$ per/hr per year 8,834.08$ 4.70$ per/hr
Hourly Wage d): Inclusive of Portion 3 48.87$ per/hr
Group Health Insurance (includes Dental)* 100.00$ per month 1,200.0$ per year 0.64$ per hour Disability Insurance (Short Term) 10.00$ per month 120.0$ per year 0.06$ per hourDisability Insurance (Long Term) 10.00$ per month 120.0$ per year 0.06$ per hour
401K 20.00$ per month 240.0$ per year 0.13$ per hour Company Provided Car 400.00$ per month 4,800.0$ per year 2.55$ per hour
Company Provided Cell Phone 70.00$ per month 840.0$ per year 0.45$ per hour Cost of Non-Taxable, Company Paid, Fringes 3.89$ per/hrHourly Wage e): Inclusive of Portion 4 52.76$ per/hr
BURDEN FOR THIS EMPLOYEE IS: 36.06$ "Base" Rate Compared To: 52.76$ 1.46
Labor Burden - Senior Scheduler
Portion 1 of Labor Burden: Cost of Taxable, Company Paid, Cash Allowances and Other Taxable Cash Equivalents
Portion 2 of Labor Burden: Cost of Government Required Insurance and Taxes
Portion 3 of Labor Burden: Cost of Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Portion 4 of Labor Burden: Cost of Non Taxable, Company Paid, Fringes
28
BLACK BOX CONSTRUCTION, LLC.
Base Yearly Salary 65,000$ per yearEquivalent "Base" Wage Per Hour 31.25$ "Base" Hourly Wage 31.25$ per hour WORK DAYS:Contracted Work Hours (CWH) 52 weeks 40 hours/week 2080 hours per year 260This is the Hourly "Base" Rate Used for Labor Burden Calculation 31.25$ Company Unbillable Paid Time: Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Vacation 10 days 8 hours/day 80 hours per yearHolidays 10 days 8 hours/day 80 hours per year
Sick Leave 5 days 8 hours/day 40 hours per yearCompany Wide Meetings/Employer Required Training 0 days 0 hours/day 0 hours per year
Bad Weather Minimum Show-Up Time 0 days 0 hours/day 0 hours per yearMorning Meetings 235 days 0 hours/day 0 hours per year
Rest Breaks 235 days 0 hours/day 0 hours per yearEffective Work Hours = Contracted - Unbillable 1880 hours per year
Company Paid Overtime Work Time (If Any) 0.0% as a % of CWH overtime rate 46.88$ per hourCompany Paid Overtime 0 hours/year per year -$ -$ per/hr
Company Paid Allowance for Use of Personal Car $300 per month per year 3,600.0$ 1.91$ per/hrCompany Paid Health Care Allowance* $300 per month per year 3,600.0$ 1.91$ per/hr
Company Paid Bonus 0 per month per year -$ -$ per/hrCost of Taxable, Company Paid, Allowances and Cash Equivalents 3.83$ per/hrHourly Rate a): Inclusive of Portion 1 (Used for Wcomp and Building Risk and Pub Liability Insurance Cost Calc) 35.08$ per/hrPreTax Payments Made By Employee for Insurance -$ per month per year -$ -$ per/hrHourly Rate b) Incluse of Portion 1 (Used for SS and Medicare Tax Calc) 35.08$ per/hr
Required Insurance and Taxes Enter EMR 0.85 per hourWorkers Compensation Ins. 1.50 1.275 % of Hourly Rate a) 0.45$ per hour
Builders Risk and Public Liability Ins. 8.00 per 1,000 of Hourly Rate a) 0.28$ per hourFederal Unemployment Tax 0.25 % 9,000.00$ is Co's Federal Tax Base 0.01$ per hour
State Unemployment Tax 3.00 % 24,400.00$ is Co's State Tax Base 0.39$ per hourSocial Security Tax 6.20 % of Hourly Rate b) 2.17$ per hour
Medicare, Medicaid Tax 1.45 % of Hourly Rate b) 0.51$ per hour Cost of Government Required Insurance and Taxes 3.81$ per/hrHourly Rate c): Inclusive of Portion 2 38.89$ per/hr
Vacation 80 hours 38.89$ per hour 3,111.4$ 1.66$ per/hrHolidays 80 hours 38.89$ per hour 3,111.4$ 1.66$ per/hr
Sick Leave 40 hours 38.89$ per hour 1,555.7$ 0.83$ per/hrCompany Wide Meetings/Training 0 hours 38.89$ per hour -$ -$ per/hr
Bad Weather Minimum Show-Up Time 0 hours 38.89$ per hour -$ -$ per/hrMorning Meetings 0 hours 38.89$ per hour -$ -$ per/hr
Rest Breaks 0 hours 38.89$ per hour -$ -$ per/hr 7,778.53$ 4.14$ per/hr
Hourly Wage d): Inclusive of Portion 3 43.03$ per/hr
Group Health Insurance (includes Dental)* 100.00$ per month 1,200.0$ per year 0.64$ per hour Disability Insurance (Short Term) 10.00$ per month 120.0$ per year 0.06$ per hourDisability Insurance (Long Term) 10.00$ per month 120.0$ per year 0.06$ per hour
401K 20.00$ per month 240.0$ per year 0.13$ per hour Cost of Non-Taxable, Company Paid, Fringes 0.89$ per/hrHourly Wage e): Inclusive of Portion 4 43.92$ per/hr
BURDEN FOR THIS EMPLOYEE IS: 31.25$ "Base" Rate Compared To: 43.92$ 1.41
Labor Burden - Scheduler
Portion 1 of Labor Burden: Cost of Taxable, Company Paid, Cash Allowances and Other Taxable Cash Equivalents
Portion 2 of Labor Burden: Cost of Government Required Insurance and Taxes
Portion 3 of Labor Burden: Cost of Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Portion 4 of Labor Burden: Cost of Non Taxable, Company Paid, Fringes
29
BLACK BOX CONSTRUCTION, LLC.
Base Yearly Salary 50,000.00$ per yearEquivalent "Base" Wage Per Hour 24.04$ "Base" Hourly Wage 24.04$ per hour WORK DAYS:Contracted Work Hours (CWH) 52 weeks 40 hours/week 2080 hours per year 260This is the Hourly "Base" Rate Used for Labor Burden Calculation 24.04$ Company Unbillable Paid Time: Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Vacation 10 days 8 hours/day 80 hours per yearHolidays 10 days 8 hours/day 80 hours per year
Sick Leave 5 days 8 hours/day 40 hours per yearCompany Wide Meetings/Employer Required Training 0 days 0 hours/day 0 hours per year
Bad Weather Minimum Show-Up Time 0 days 0 hours/day 0 hours per yearMorning Meetings 235 days 0 hours/day 0 hours per year
Rest Breaks 235 days 0 hours/day 0 hours per yearEffective Work Hours = Contracted - Unbillable 1880 hours per year
Company Paid Overtime Work Time (If Any) 0.0% as a % of CWH overtime rate 36.06$ per hourCompany Paid Overtime 0 hours/year per year -$ -$ per/hr
Company Paid Allowance for Use of Personal Car $0 per month per year -$ -$ per/hrCompany Paid Health Care Allowance* $300 per month per year 3,600.0$ 1.91$ per/hr
Company Paid Bonus 0 per month per year -$ -$ per/hrCost of Taxable, Company Paid, Allowances and Cash Equivalents 1.91$ per/hrHourly Rate a): Inclusive of Portion 1 (Used for Wcomp and Building Risk and Pub Liability Insurance Cost Calc) 25.95$ per/hrPreTax Payments Made By Employee for Insurance -$ per month per year -$ -$ per/hrHourly Rate b) Incluse of Portion 1 (Used for SS and Medicare Tax Calc) 25.95$ per/hr
Required Insurance and Taxes Enter EMR 0.85 per hourWorkers Compensation Ins. 1.50 1.275 % of Hourly Rate a) 0.33$ per hour
Builders Risk and Public Liability Ins. 8.00 per 1,000 of Hourly Rate a) 0.21$ per hourFederal Unemployment Tax 0.25 % 9,000.00$ is Co's Federal Tax Base 0.01$ per hour
State Unemployment Tax 3.00 % 24,400.00$ is Co's State Tax Base 0.39$ per hourSocial Security Tax 6.20 % of Hourly Rate b) 1.61$ per hour
Medicare, Medicaid Tax 1.45 % of Hourly Rate b) 0.38$ per hour Cost of Government Required Insurance and Taxes 2.93$ per/hrHourly Rate c): Inclusive of Portion 2 28.88$ per/hr
Vacation 80 hours 28.88$ per hour 2,310.4$ 1.23$ per/hrHolidays 80 hours 28.88$ per hour 2,310.4$ 1.23$ per/hr
Sick Leave 40 hours 28.88$ per hour 1,155.2$ 0.61$ per/hrCompany Wide Meetings/Training 0 hours 28.88$ per hour -$ -$ per/hr
Bad Weather Minimum Show-Up Time 0 hours 28.88$ per hour -$ -$ per/hrMorning Meetings 0 hours 28.88$ per hour -$ -$ per/hr
Rest Breaks 0 hours 28.88$ per hour -$ -$ per/hr 5,776.07$ 3.07$ per/hr
Hourly Wage d): Inclusive of Portion 3 31.95$ per/hr
Group Health Insurance (includes Dental)* 100.00$ per month 1,200.0$ per year 0.64$ per hour Disability Insurance (Short Term) 10.00$ per month 120.0$ per year 0.06$ per hourDisability Insurance (Long Term) 10.00$ per month 120.0$ per year 0.06$ per hour
401K 20.00$ per month 240.0$ per year 0.13$ per hour Cost of Non-Taxable, Company Paid, Fringes 0.89$ per/hrHourly Wage e): Inclusive of Portion 4 32.85$ per/hr
BURDEN FOR THIS EMPLOYEE IS: 24.04$ "Base" Rate Compared To: 32.85$ 1.37
Labor Burden - Office Manager
Portion 1 of Labor Burden: Cost of Taxable, Company Paid, Cash Allowances and Other Taxable Cash Equivalents
Portion 2 of Labor Burden: Cost of Government Required Insurance and Taxes
Portion 3 of Labor Burden: Cost of Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Portion 4 of Labor Burden: Cost of Non Taxable, Company Paid, Fringes
30
BLACK BOX CONSTRUCTION, LLC.
Base Yearly Salary 50,000.00$ per yearEquivalent "Base" Wage Per Hour 24.04$ "Base" Hourly Wage 24.04$ per hour WORK DAYS:Contracted Work Hours (CWH) 52 weeks 40 hours/week 2080 hours per year 260This is the Hourly "Base" Rate Used for Labor Burden Calculation 24.04$ Company Unbillable Paid Time: Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Vacation 10 days 8 hours/day 80 hours per yearHolidays 10 days 8 hours/day 80 hours per year
Sick Leave 5 days 8 hours/day 40 hours per yearCompany Wide Meetings/Employer Required Training 0 days 0 hours/day 0 hours per year
Bad Weather Minimum Show-Up Time 0 days 0 hours/day 0 hours per yearMorning Meetings 235 days 0 hours/day 0 hours per year
Rest Breaks 235 days 0 hours/day 0 hours per yearEffective Work Hours = Contracted - Unbillable 1880 hours per year
Company Paid Overtime Work Time (If Any) 0.0% as a % of CWH overtime rate 36.06$ per hourCompany Paid Overtime 0 hours/year per year -$ -$ per/hr
Company Paid Allowance for Use of Personal Car $0 per month per year -$ -$ per/hrCompany Paid Health Care Allowance* $300 per month per year 3,600.0$ 1.91$ per/hr
Company Paid Bonus 0 per month per year -$ -$ per/hrCost of Taxable, Company Paid, Allowances and Cash Equivalents 1.91$ per/hrHourly Rate a): Inclusive of Portion 1 (Used for Wcomp and Building Risk and Pub Liability Insurance Cost Calc) 25.95$ per/hrPreTax Payments Made By Employee for Insurance -$ per month per year -$ -$ per/hrHourly Rate b) Incluse of Portion 1 (Used for SS and Medicare Tax Calc) 25.95$ per/hr
Required Insurance and Taxes Enter EMR 0.85 per hourWorkers Compensation Ins. 1.50 1.275 % of Hourly Rate a) 0.33$ per hour
Builders Risk and Public Liability Ins. 8.00 per 1,000 of Hourly Rate a) 0.21$ per hourFederal Unemployment Tax 0.25 % 9,000.00$ is Co's Federal Tax Base 0.01$ per hour
State Unemployment Tax 3.00 % 24,400.00$ is Co's State Tax Base 0.39$ per hourSocial Security Tax 6.20 % of Hourly Rate b) 1.61$ per hour
Medicare, Medicaid Tax 1.45 % of Hourly Rate b) 0.38$ per hour Cost of Government Required Insurance and Taxes 2.93$ per/hrHourly Rate c): Inclusive of Portion 2 28.88$ per/hr
Vacation 80 hours 28.88$ per hour 2,310.4$ 1.23$ per/hrHolidays 80 hours 28.88$ per hour 2,310.4$ 1.23$ per/hr
Sick Leave 40 hours 28.88$ per hour 1,155.2$ 0.61$ per/hrCompany Wide Meetings/Training 0 hours 28.88$ per hour -$ -$ per/hr
Bad Weather Minimum Show-Up Time 0 hours 28.88$ per hour -$ -$ per/hrMorning Meetings 0 hours 28.88$ per hour -$ -$ per/hr
Rest Breaks 0 hours 28.88$ per hour -$ -$ per/hr 5,776.07$ 3.07$ per/hr
Hourly Wage d): Inclusive of Portion 3 31.95$ per/hr
Group Health Insurance (includes Dental)* 100.00$ per month 1,200.0$ per year 0.64$ per hour Disability Insurance (Short Term) 10.00$ per month 120.0$ per year 0.06$ per hourDisability Insurance (Long Term) 10.00$ per month 120.0$ per year 0.06$ per hour
401K 20.00$ per month 240.0$ per year 0.13$ per hour Cost of Non-Taxable, Company Paid, Fringes 0.89$ per/hrHourly Wage e): Inclusive of Portion 4 32.85$ per/hr
BURDEN FOR THIS EMPLOYEE IS: 24.04$ "Base" Rate Compared To: 32.85$ 1.37
Labor Burden - Bid Co-ordinator
Portion 1 of Labor Burden: Cost of Taxable, Company Paid, Cash Allowances and Other Taxable Cash Equivalents
Portion 2 of Labor Burden: Cost of Government Required Insurance and Taxes
Portion 3 of Labor Burden: Cost of Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Portion 4 of Labor Burden: Cost of Non Taxable, Company Paid, Fringes
31
BLACK BOX CONSTRUCTION, LLC.
Base Yearly Salary 50,000.00$ per yearEquivalent "Base" Wage Per Hour 24.04$ "Base" Hourly Wage 24.04$ per hour WORK DAYS:Contracted Work Hours (CWH) 52 weeks 40 hours/week 2080 hours per year 260This is the Hourly "Base" Rate Used for Labor Burden Calculation 24.04$ Company Unbillable Paid Time: Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Vacation 10 days 8 hours/day 80 hours per yearHolidays 10 days 8 hours/day 80 hours per year
Sick Leave 5 days 8 hours/day 40 hours per yearCompany Wide Meetings/Employer Required Training 0 days 0 hours/day 0 hours per year
Bad Weather Minimum Show-Up Time 0 days 0 hours/day 0 hours per yearMorning Meetings 235 days 0 hours/day 0 hours per year
Rest Breaks 235 days 0 hours/day 0 hours per yearEffective Work Hours = Contracted - Unbillable 1880 hours per year
Company Paid Overtime Work Time (If Any) 0.0% as a % of CWH overtime rate 36.06$ per hourCompany Paid Overtime 0 hours/year per year -$ -$ per/hr
Company Paid Allowance for Use of Personal Car $0 per month per year -$ -$ per/hrCompany Paid Health Care Allowance* $300 per month per year 3,600.0$ 1.91$ per/hr
Company Paid Bonus 0 per month per year -$ -$ per/hrCost of Taxable, Company Paid, Allowances and Cash Equivalents 1.91$ per/hrHourly Rate a): Inclusive of Portion 1 (Used for Wcomp and Building Risk and Pub Liability Insurance Cost Calc) 25.95$ per/hrPreTax Payments Made By Employee for Insurance -$ per month per year -$ -$ per/hrHourly Rate b) Incluse of Portion 1 (Used for SS and Medicare Tax Calc) 25.95$ per/hr
Required Insurance and Taxes Enter EMR 0.85 per hourWorkers Compensation Ins. 1.50 1.275 % of Hourly Rate a) 0.33$ per hour
Builders Risk and Public Liability Ins. 8.00 per 1,000 of Hourly Rate a) 0.21$ per hourFederal Unemployment Tax 0.25 % 9,000.00$ is Co's Federal Tax Base 0.01$ per hour
State Unemployment Tax 3.00 % 24,400.00$ is Co's State Tax Base 0.39$ per hourSocial Security Tax 6.20 % of Hourly Rate b) 1.61$ per hour
Medicare, Medicaid Tax 1.45 % of Hourly Rate b) 0.38$ per hour Cost of Government Required Insurance and Taxes 2.93$ per/hrHourly Rate c): Inclusive of Portion 2 28.88$ per/hr
Vacation 80 hours 28.88$ per hour 2,310.4$ 1.23$ per/hrHolidays 80 hours 28.88$ per hour 2,310.4$ 1.23$ per/hr
Sick Leave 40 hours 28.88$ per hour 1,155.2$ 0.61$ per/hrCompany Wide Meetings/Training 0 hours 28.88$ per hour -$ -$ per/hr
Bad Weather Minimum Show-Up Time 0 hours 28.88$ per hour -$ -$ per/hrMorning Meetings 0 hours 28.88$ per hour -$ -$ per/hr
Rest Breaks 0 hours 28.88$ per hour -$ -$ per/hr per year 5,776.07$ 3.07$ per/hr
Hourly Wage d): Inclusive of Portion 3 31.95$ per/hr
Group Health Insurance (includes Dental)* 100.00$ per month 1,200.0$ per year 0.64$ per hour Disability Insurance (Short Term) 10.00$ per month 120.0$ per year 0.06$ per hourDisability Insurance (Long Term) 10.00$ per month 120.0$ per year 0.06$ per hour
401K 20.00$ per month 240.0$ per year 0.13$ per hour Cost of Non-Taxable, Company Paid, Fringes 0.89$ per/hrHourly Wage e): Inclusive of Portion 4 32.85$ per/hr
BURDEN FOR THIS EMPLOYEE IS: 24.04$ "Base" Rate Compared To: 32.85$ 1.37
Labor Burden - Accountant
Portion 1 of Labor Burden: Cost of Taxable, Company Paid, Cash Allowances and Other Taxable Cash Equivalents
Portion 2 of Labor Burden: Cost of Government Required Insurance and Taxes
Portion 3 of Labor Burden: Cost of Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Portion 4 of Labor Burden: Cost of Non Taxable, Company Paid, Fringes
32
BLACK BOX CONSTRUCTION, LLC.
Base Yearly Salary 45,000.00$ per yearEquivalent "Base" Wage Per Hour 21.63$ "Base" Hourly Wage 21.63$ per hour WORK DAYS:Contracted Work Hours (CWH) 52 weeks 40 hours/week 2080 hours per year 260This is the Hourly "Base" Rate Used for Labor Burden Calculation 21.63$ Company Unbillable Paid Time: Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Vacation 10 days 8 hours/day 80 hours per yearHolidays 10 days 8 hours/day 80 hours per year
Sick Leave 5 days 8 hours/day 40 hours per yearCompany Wide Meetings/Employer Required Training 0 days 0 hours/day 0 hours per year
Bad Weather Minimum Show-Up Time 0 days 0 hours/day 0 hours per yearMorning Meetings 235 days 0 hours/day 0 hours per year
Rest Breaks 235 days 0 hours/day 0 hours per yearEffective Work Hours = Contracted - Unbillable 1880 hours per year
Company Paid Overtime Work Time (If Any) 0.0% as a % of CWH overtime rate 32.45$ per hourCompany Paid Overtime 0 hours/year per year -$ -$ per/hr
Company Paid Allowance for Use of Personal Car $0 per month per year -$ -$ per/hrCompany Paid Health Care Allowance* $0 per month per year -$ -$ per/hr
Company Paid Bonus 0 per month per year -$ -$ per/hrCost of Taxable, Company Paid, Allowances and Cash Equivalents -$ per/hrHourly Rate a): Inclusive of Portion 1 (Used for Wcomp and Building Risk and Pub Liability Insurance Cost Calc) 21.63$ per/hrPreTax Payments Made By Employee for Insurance -$ per month per year -$ -$ per/hrHourly Rate b) Incluse of Portion 1 (Used for SS and Medicare Tax Calc) 21.63$ per/hr
Required Insurance and Taxes Enter EMR 0.85 per hourWorkers Compensation Ins. 1.50 1.275 % of Hourly Rate a) 0.28$ per hour
Builders Risk and Public Liability Ins. 8.00 per 1,000 of Hourly Rate a) 0.17$ per hourFederal Unemployment Tax 0.25 % 9,000.00$ is Co's Federal Tax Base 0.01$ per hour
State Unemployment Tax 3.00 % 24,400.00$ is Co's State Tax Base 0.39$ per hourSocial Security Tax 6.20 % of Hourly Rate b) 1.34$ per hour
Medicare, Medicaid Tax 1.45 % of Hourly Rate b) 0.31$ per hour Cost of Government Required Insurance and Taxes 2.50$ per/hrHourly Rate c): Inclusive of Portion 2 24.13$ per/hr
Vacation 80 hours 24.13$ per hour 1,930.8$ 1.03$ per/hrHolidays 80 hours 24.13$ per hour 1,930.8$ 1.03$ per/hr
Sick Leave 40 hours 24.13$ per hour 965.4$ 0.51$ per/hrCompany Wide Meetings/Training 0 hours 24.13$ per hour -$ -$ per/hr
Bad Weather Minimum Show-Up Time 0 hours 24.13$ per hour -$ -$ per/hrMorning Meetings 0 hours 24.13$ per hour -$ -$ per/hr
Rest Breaks 0 hours 24.13$ per hour -$ -$ per/hr per year 4,826.97$ 2.57$ per/hr
Hourly Wage d): Inclusive of Portion 3 26.70$ per/hr
Group Health Insurance (includes Dental)* 100.00$ per month 1,200.0$ per year 0.64$ per hour Disability Insurance (Short Term) 10.00$ per month 120.0$ per year 0.06$ per hourDisability Insurance (Long Term) 10.00$ per month 120.0$ per year 0.06$ per hour
401K 20.00$ per month 240.0$ per year 0.13$ per hour Cost of Non-Taxable, Company Paid, Fringes 0.89$ per/hrHourly Wage e): Inclusive of Portion 4 27.60$ per/hr
BURDEN FOR THIS EMPLOYEE IS: 21.63$ "Base" Rate Compared To: 27.60$ 1.28
Labor Burden - Administrator
Portion 1 of Labor Burden: Cost of Taxable, Company Paid, Cash Allowances and Other Taxable Cash Equivalents
Portion 2 of Labor Burden: Cost of Government Required Insurance and Taxes
Portion 3 of Labor Burden: Cost of Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Portion 4 of Labor Burden: Cost of Non Taxable, Company Paid, Fringes
33
BLACK BOX CONSTRUCTION, LLC.
Base Yearly Salary 45,000.00$ per yearEquivalent "Base" Wage Per Hour 21.63$ "Base" Hourly Wage 21.63$ per hour WORK DAYS:Contracted Work Hours (CWH) 52 weeks 40 hours/week 2080 hours per year 260This is the Hourly "Base" Rate Used for Labor Burden Calculation 21.63$ Company Unbillable Paid Time: Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Vacation 10 days 8 hours/day 80 hours per yearHolidays 10 days 8 hours/day 80 hours per year
Sick Leave 5 days 8 hours/day 40 hours per yearCompany Wide Meetings/Employer Required Training 0 days 0 hours/day 0 hours per year
Bad Weather Minimum Show-Up Time 0 days 0 hours/day 0 hours per yearMorning Meetings 235 days 0 hours/day 0 hours per year
Rest Breaks 235 days 0 hours/day 0 hours per yearEffective Work Hours = Contracted - Unbillable 1880 hours per year
Company Paid Overtime Work Time (If Any) 0.0% as a % of CWH overtime rate 32.45$ per hourCompany Paid Overtime 0 hours/year per year -$ -$ per/hr
Company Paid Allowance for Use of Personal Car $0 per month per year -$ -$ per/hrCompany Paid Health Care Allowance* $0 per month per year -$ -$ per/hr
Company Paid Bonus 0 per month per year -$ -$ per/hrCost of Taxable, Company Paid, Allowances and Cash Equivalents -$ per/hrHourly Rate a): Inclusive of Portion 1 (Used for Wcomp and Building Risk and Pub Liability Insurance Cost Calc) 21.63$ per/hrPreTax Payments Made By Employee for Insurance -$ per month per year -$ -$ per/hrHourly Rate b) Incluse of Portion 1 (Used for SS and Medicare Tax Calc) 21.63$ per/hr
Required Insurance and Taxes Enter EMR 0.85 per hourWorkers Compensation Ins. 1.50 1.275 % of Hourly Rate a) 0.28$ per hour
Builders Risk and Public Liability Ins. 8.00 per 1,000 of Hourly Rate a) 0.17$ per hourFederal Unemployment Tax 0.25 % 9,000.00$ is Co's Federal Tax Base 0.01$ per hour
State Unemployment Tax 3.00 % 24,400.00$ is Co's State Tax Base 0.39$ per hourSocial Security Tax 6.20 % of Hourly Rate b) 1.34$ per hour
Medicare, Medicaid Tax 1.45 % of Hourly Rate b) 0.31$ per hour Cost of Government Required Insurance and Taxes 2.50$ per/hrHourly Rate c): Inclusive of Portion 2 24.13$ per/hr
Vacation 80 hours 24.13$ per hour 1,930.8$ 1.03$ per/hrHolidays 80 hours 24.13$ per hour 1,930.8$ 1.03$ per/hr
Sick Leave 40 hours 24.13$ per hour 965.4$ 0.51$ per/hrCompany Wide Meetings/Training 0 hours 24.13$ per hour -$ -$ per/hr
Bad Weather Minimum Show-Up Time 0 hours 24.13$ per hour -$ -$ per/hrMorning Meetings 0 hours 24.13$ per hour -$ -$ per/hr
Rest Breaks 0 hours 24.13$ per hour -$ -$ per/hr per year 4,826.97$ 2.57$ per/hr
Hourly Wage d): Inclusive of Portion 3 26.70$ per/hr
Group Health Insurance (includes Dental)* 100.00$ per month 1,200.0$ per year 0.64$ per hour Disability Insurance (Short Term) 10.00$ per month 120.0$ per year 0.06$ per hourDisability Insurance (Long Term) 10.00$ per month 120.0$ per year 0.06$ per hour
401K 20.00$ per month 240.0$ per year 0.13$ per hour Cost of Non-Taxable, Company Paid, Fringes 0.89$ per/hrHourly Wage e): Inclusive of Portion 4 27.60$ per/hr
BURDEN FOR THIS EMPLOYEE IS: 21.63$ "Base" Rate Compared To: 27.60$ 1.28
Labor Burden - HR
Portion 1 of Labor Burden: Cost of Taxable, Company Paid, Cash Allowances and Other Taxable Cash Equivalents
Portion 2 of Labor Burden: Cost of Government Required Insurance and Taxes
Portion 3 of Labor Burden: Cost of Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Portion 4 of Labor Burden: Cost of Non Taxable, Company Paid, Fringes
34
BLACK BOX CONSTRUCTION, LLC.
Equivalent Yearly Wage 37,440.00$ per yearEquivalent "Base" Wage Per Hour 18.00$ "Base" Hourly Wage 18.00$ per hour WORK DAYS:Contracted Work Hours (CWH) 52 weeks 40 hours/week 2080 hours per year 260This is the Hourly "Base" Rate Used for Labor Burden Calculation 18.00$ Company Unbillable Paid Time: Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Vacation 10 days 8 hours/day 80 hours per yearHolidays 10 days 8 hours/day 80 hours per year
Sick Leave 5 days 8 hours/day 40 hours per yearCompany Wide Meetings/Employer Required Training 0 days 0 hours/day 0 hours per year
Bad Weather Minimum Show-Up Time 5 days 4 hours/day 20 hours per yearMorning Meetings 235 days 0 hours/day 0 hours per year
Rest Breaks 235 days 0 hours/day 0 hours per yearEffective Work Hours = Contracted - Unbillable 1860 hours per year
Company Paid Overtime Work Time (If Any) 100.0 hours/year overtime rate 27.00$ per hourCompany Paid Overtime 100 hours/year per year 2,700.0$ 1.45$ per/hr
Company Paid Allowance for Use of Personal Car per month per year -$ -$ per/hrCompany Paid Health Care Allowance* per month per year -$ -$ per/hr
Company Paid Bonus 0 per month per year -$ -$ per/hrCost of Taxable, Company Paid, Allowances and Cash Equivalents 1.45$ per/hrHourly Rate a): Inclusive of Portion 1 (Used for Wcomp and Building Risk and Pub Liability Insurance Cost Calc) 19.45$ per/hrPreTax Payments Made By Employee for Insurance -$ per month per year -$ -$ per/hrHourly Rate b) Incluse of Portion 1 (Used for SS and Medicare Tax Calc) 19.45$ per/hr
Required Insurance and Taxes Enter EMR 0.85 per hourWorkers Compensation Ins. 1.50 1.275 % of Hourly Rate a) 0.25$ per hour
Builders Risk and Public Liability Ins. 8.00 per 1,000 of Hourly Rate a) 0.16$ per hourFederal Unemployment Tax 0.25 % 9,000.00$ is Co's Federal Tax Base 0.01$ per hour
State Unemployment Tax 3.00 % 24,400.00$ is Co's State Tax Base 0.39$ per hourSocial Security Tax 6.20 % of Hourly Rate b) 1.21$ per hour
Medicare, Medicaid Tax 1.45 % of Hourly Rate b) 0.28$ per hour Cost of Government Required Insurance and Taxes 2.30$ per/hrHourly Rate c): Inclusive of Portion 2 21.75$ per/hr
Vacation 80 hours 21.75$ per hour 1,739.9$ 0.94$ per/hrHolidays 80 hours 21.75$ per hour 1,739.9$ 0.94$ per/hr
Sick Leave 40 hours 21.75$ per hour 870.0$ 0.47$ per/hrCompany Wide Meetings/Training 0 hours 21.75$ per hour -$ -$ per/hr
Bad Weather Minimum Show-Up Time 20 hours 21.75$ per hour 435.0$ 0.23$ per/hrMorning Meetings 0 hours 21.75$ per hour -$ -$ per/hr
Rest Breaks 0 hours 21.75$ per hour -$ -$ per/hr per year 4,784.76$ 2.57$ per/hr
Hourly Wage d): Inclusive of Portion 3 24.32$ per/hr
Group Health Insurance (includes Dental)* 100.00$ per month 1,200.0$ per year 0.65$ per hour Disability Insurance (Short Term) 10.00$ per month 120.0$ per year 0.06$ per hourDisability Insurance (Long Term) 10.00$ per month 120.0$ per year 0.06$ per hour
401K 20.00$ per month 240.0$ per year 0.13$ per hour Cost of Non-Taxable, Company Paid, Fringes 0.90$ per/hrHourly Wage e): Inclusive of Portion 4 25.22$ per/hr
BURDEN FOR THIS EMPLOYEE IS: 18.00$ "Base" Rate Compared To: 25.22$ 1.40
Labor Burden - Receptionist
Portion 1 of Labor Burden: Cost of Taxable, Company Paid, Cash Allowances and Other Taxable Cash Equivalents
Portion 2 of Labor Burden: Cost of Government Required Insurance and Taxes
Portion 3 of Labor Burden: Cost of Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Portion 4 of Labor Burden: Cost of Non Taxable, Company Paid, Fringes
35
BLACK BOX CONSTRUCTION, LLC.
Base Yearly Salary 58,000.00$ per yearEquivalent "Base" Wage Per Hour 27.88$ "Base" Hourly Wage 27.88$ per hour WORK DAYS:Contracted Work Hours (CWH) 52 weeks 40 hours/week 2080 hours per year 260This is the Hourly "Base" Rate Used for Labor Burden Calculation 27.88$ Company Unbillable Paid Time: Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Vacation 10 days 8 hours/day 80 hours per yearHolidays 10 days 8 hours/day 80 hours per year
Sick Leave 5 days 8 hours/day 40 hours per yearCompany Wide Meetings/Employer Required Training 0 days 0 hours/day 0 hours per year
Bad Weather Minimum Show-Up Time 0 days 0 hours/day 0 hours per yearMorning Meetings 235 days 0.5 hours/day 117.5 hours per year
Rest Breaks 235 days 0.5 hours/day 117.5 hours per yearEffective Work Hours = Contracted - Unbillable 1645 hours per year
Company Paid Overtime Work Time (If Any) 0.0% as a % of CWH overtime rate 41.82$ per hourCompany Paid Overtime 0 hours/year per year -$ -$ per/hr
Company Paid Allowance for Use of Personal Car $300 per month per year 3,600.0$ 2.19$ per/hrCompany Paid Health Care Allowance* $300 per month per year 3,600.0$ 2.19$ per/hr
Company Paid Bonus 0 per month per year -$ -$ per/hrCost of Taxable, Company Paid, Allowances and Cash Equivalents 4.38$ per/hrHourly Rate a): Inclusive of Portion 1 (Used for Wcomp and Building Risk and Pub Liability Insurance Cost Calc) 32.26$ per/hrPreTax Payments Made By Employee for Insurance -$ per month per year -$ -$ per/hrHourly Rate b) Incluse of Portion 1 (Used for SS and Medicare Tax Calc) 32.26$ per/hr
Required Insurance and Taxes Enter EMR 0.85 per hourWorkers Compensation Ins. 4.00 3.4 % of Hourly Rate a) 1.10$ per hour
Builders Risk and Public Liability Ins. 8.00 per 1,000 of Hourly Rate a) 0.26$ per hourFederal Unemployment Tax 0.25 % 9,000.00$ is Co's Federal Tax Base 0.01$ per hour
State Unemployment Tax 3.00 % 24,400.00$ is Co's State Tax Base 0.44$ per hourSocial Security Tax 6.20 % of Hourly Rate b) 2.00$ per hour
Medicare, Medicaid Tax 1.45 % of Hourly Rate b) 0.47$ per hour Cost of Government Required Insurance and Taxes 4.28$ per/hrHourly Rate c): Inclusive of Portion 2 36.54$ per/hr
Vacation 80 hours 36.54$ per hour 2,923.0$ 1.78$ per/hrHolidays 80 hours 36.54$ per hour 2,923.0$ 1.78$ per/hr
Sick Leave 40 hours 36.54$ per hour 1,461.5$ 0.89$ per/hrCompany Wide Meetings/Training 0 hours 36.54$ per hour -$ -$ per/hr
Bad Weather Minimum Show-Up Time 0 hours 36.54$ per hour -$ -$ per/hrMorning Meetings 117.5 hours 36.54$ per hour 4,293.2$ 2.61$ per/hr
Rest Breaks 117.5 hours 36.54$ per hour 4,293.2$ 2.61$ per/hr per year 15,894.03$ 9.66$ per/hr
Hourly Wage d): Inclusive of Portion 3 46.20$ per/hr
Group Health Insurance (includes Dental)* 100.00$ per month 1,200.0$ per year 0.73$ per hour Disability Insurance (Short Term) 10.00$ per month 120.0$ per year 0.07$ per hourDisability Insurance (Long Term) 10.00$ per month 120.0$ per year 0.07$ per hour
401K 20.00$ per month 240.0$ per year 0.15$ per hour Company provided Pick up Truck 400.00$ 4,800.0$ 2.92$
Company provided cell phone 30.00$ 401K 20.00$ per month 240.0$ per year 0.15$ per hour
Cost of Non-Taxable, Company Paid, Fringes 4.09$ per/hrHourly Wage e): Inclusive of Portion 4 50.29$ per/hr
BURDEN FOR THIS EMPLOYEE IS: 27.88$ "Base" Rate Compared To: 50.29$ 1.80
Labor Burden - Safety Manager (60% Office and 40% Site)
Portion 1 of Labor Burden: Cost of Taxable, Company Paid, Cash Allowances and Other Taxable Cash Equivalents
Portion 2 of Labor Burden: Cost of Government Required Insurance and Taxes
Portion 3 of Labor Burden: Cost of Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Portion 4 of Labor Burden: Cost of Non Taxable, Company Paid, Fringes
36
BLACK BOX CONSTRUCTION, LLC.
Base Yearly Salary 75,000.00$ per yearEquivalent "Base" Wage Per Hour 36.06$ "Base" Hourly Wage 36.06$ per hour WORK DAYS:Contracted Work Hours (CWH) 52 weeks 40 hours/week 2080 hours per year 260This is the Hourly "Base" Rate Used for Labor Burden Calculation 36.06$ Company Unbillable Paid Time: Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Vacation 10 days 8 hours/day 80 hours per yearHolidays 10 days 8 hours/day 80 hours per year
Sick Leave 5 days 8 hours/day 40 hours per yearCompany Wide Meetings/Employer Required Training 0 days 0 hours/day 0 hours per year
Bad Weather Minimum Show-Up Time 0 days 0 hours/day 0 hours per yearMorning Meetings 235 days 0.5 hours/day 117.5 hours per year
Rest Breaks 235 days 0.5 hours/day 117.5 hours per yearEffective Work Hours = Contracted - Unbillable 1645 hours per year
Company Paid Overtime Work Time (If Any) 0.0% as a % of CWH overtime rate 54.09$ per hourCompany Paid Overtime 0 hours/year per year -$ -$ per/hr
Company Paid Allowance for Use of Personal Car $0 per month per year -$ -$ per/hrCompany Paid Health Care Allowance* $300 per month per year 3,600.0$ 2.19$ per/hr
Company Paid Bonus 0 per month per year -$ -$ per/hrCost of Taxable, Company Paid, Allowances and Cash Equivalents 2.19$ per/hrHourly Rate a): Inclusive of Portion 1 (Used for Wcomp and Building Risk and Pub Liability Insurance Cost Calc) 38.25$ per/hrPreTax Payments Made By Employee for Insurance -$ per month per year -$ -$ per/hrHourly Rate b) Incluse of Portion 1 (Used for SS and Medicare Tax Calc) 38.25$ per/hr
Required Insurance and Taxes Enter EMR 0.85 per hourWorkers Compensation Ins. 5.00 4.25 % of Hourly Rate a) 1.63$ per hour
Builders Risk and Public Liability Ins. 8.00 per 1,000 of Hourly Rate a) 0.31$ per hourFederal Unemployment Tax 0.25 % 9,000.00$ is Co's Federal Tax Base 0.01$ per hour
State Unemployment Tax 3.00 % 24,400.00$ is Co's State Tax Base 0.44$ per hourSocial Security Tax 6.20 % of Hourly Rate b) 2.37$ per hour
Medicare, Medicaid Tax 1.45 % of Hourly Rate b) 0.55$ per hour Cost of Government Required Insurance and Taxes 5.32$ per/hrHourly Rate c): Inclusive of Portion 2 43.56$ per/hr
Vacation 80 hours 43.56$ per hour 3,485.2$ 2.12$ per/hrHolidays 80 hours 43.56$ per hour 3,485.2$ 2.12$ per/hr
Sick Leave 40 hours 43.56$ per hour 1,742.6$ 1.06$ per/hrCompany Wide Meetings/Training 0 hours 43.56$ per hour -$ -$ per/hr
Bad Weather Minimum Show-Up Time 0 hours 43.56$ per hour -$ -$ per/hrMorning Meetings 117.5 hours 43.56$ per hour 5,118.8$ 3.11$ per/hr
Rest Breaks 117.5 hours 43.56$ per hour 5,118.8$ 3.11$ per/hr per year 18,950.63$ 11.52$ per/hr
Hourly Wage d): Inclusive of Portion 3 55.08$ per/hr
Group Health Insurance (includes Dental)* 100.00$ per month 1,200.0$ per year 0.73$ per hour Disability Insurance (Short Term) 10.00$ per month 120.0$ per year 0.07$ per hourDisability Insurance (Long Term) 10.00$ per month 120.0$ per year 0.07$ per hour
401K 20.00$ per month 240.0$ per year 0.15$ per hour Cost of Non-Taxable, Company Paid, Fringes 1.02$ per/hrHourly Wage e): Inclusive of Portion 4 56.11$ per/hrBURDEN FOR THIS EMPLOYEE IS: 36.06$ "Base" Rate Compared To: 56.11$ 1.56
Labor Burden - Project Manager
Portion 1 of Labor Burden: Cost of Taxable, Company Paid, Cash Allowances and Other Taxable Cash Equivalents
Portion 2 of Labor Burden: Cost of Government Required Insurance and Taxes
Portion 3 of Labor Burden: Cost of Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Portion 4 of Labor Burden: Cost of Non Taxable, Company Paid, Fringes
37
BLACK BOX CONSTRUCTION, LLC.
Base Yearly Salary 65,000.00$ per yearEquivalent "Base" Wage Per Hour 31.25$ "Base" Hourly Wage 31.25$ per hour WORK DAYS:Contracted Work Hours (CWH) 52 weeks 40 hours/week 2080 hours per year 260This is the Hourly "Base" Rate Used for Labor Burden Calculation 31.25$ Company Unbillable Paid Time: Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Vacation 10 days 8 hours/day 80 hours per yearHolidays 10 days 8 hours/day 80 hours per year
Sick Leave 5 days 8 hours/day 40 hours per yearCompany Wide Meetings/Employer Required Training 0 days 0 hours/day 0 hours per year
Bad Weather Minimum Show-Up Time 0 days 0 hours/day 0 hours per yearMorning Meetings 235 days 0.5 hours/day 117.5 hours per year
Rest Breaks 235 days 0.5 hours/day 117.5 hours per yearEffective Work Hours = Contracted - Unbillable 1645 hours per year
Company Paid Overtime Work Time (If Any) 0.0% as a % of CWH overtime rate 46.88$ per hourCompany Paid Overtime 0 hours/year per year -$ -$ per/hr
Company Paid Allowance for Use of Personal Car $0 per month per year -$ -$ per/hrCompany Paid Health Care Allowance* $300 per month per year 3,600.0$ 2.19$ per/hr
Company Paid Bonus 0 per month per year -$ -$ per/hrCost of Taxable, Company Paid, Allowances and Cash Equivalents 2.19$ per/hrHourly Rate a): Inclusive of Portion 1 (Used for Wcomp and Building Risk and Pub Liability Insurance Cost Calc) 33.44$ per/hrPreTax Payments Made By Employee for Insurance -$ per month per year -$ -$ per/hrHourly Rate b) Incluse of Portion 1 (Used for SS and Medicare Tax Calc) 33.44$ per/hr
Required Insurance and Taxes Enter EMR 0.85 per hourWorkers Compensation Ins. 6.00 5.1 % of Hourly Rate a) 1.71$ per hour
Builders Risk and Public Liability Ins. 8.00 per 1,000 of Hourly Rate a) 0.27$ per hourFederal Unemployment Tax 0.25 % 9,000.00$ is Co's Federal Tax Base 0.01$ per hour
State Unemployment Tax 3.00 % 24,400.00$ is Co's State Tax Base 0.44$ per hourSocial Security Tax 6.20 % of Hourly Rate b) 2.07$ per hour
Medicare, Medicaid Tax 1.45 % of Hourly Rate b) 0.48$ per hour Cost of Government Required Insurance and Taxes 4.99$ per/hrHourly Rate c): Inclusive of Portion 2 38.43$ per/hr
Vacation 80 hours 38.43$ per hour 3,074.2$ 1.87$ per/hrHolidays 80 hours 38.43$ per hour 3,074.2$ 1.87$ per/hr
Sick Leave 40 hours 38.43$ per hour 1,537.1$ 0.93$ per/hrCompany Wide Meetings/Training 0 hours 38.43$ per hour -$ -$ per/hr
Bad Weather Minimum Show-Up Time 0 hours 38.43$ per hour -$ -$ per/hrMorning Meetings 117.5 hours 38.43$ per hour 4,515.3$ 2.74$ per/hr
Rest Breaks 117.5 hours 38.43$ per hour 4,515.3$ 2.74$ per/hr per year 16,716.19$ 10.16$ per/hr
Hourly Wage d): Inclusive of Portion 3 48.59$ per/hr
Group Health Insurance (includes Dental)* 100.00$ per month 1,200.0$ per year 0.73$ per hour Disability Insurance (Short Term) 10.00$ per month 120.0$ per year 0.07$ per hourDisability Insurance (Long Term) 10.00$ per month 120.0$ per year 0.07$ per hour
401K 20.00$ per month 240.0$ per year 0.15$ per hour Cost of Non-Taxable, Company Paid, Fringes 1.02$ per/hrHourly Wage e): Inclusive of Portion 4 49.61$ per/hr
BURDEN FOR THIS EMPLOYEE IS: 31.25$ "Base" Rate Compared To: 49.61$ 1.59
Labor Burden - General Superintendent
Portion 1 of Labor Burden: Cost of Taxable, Company Paid, Cash Allowances and Other Taxable Cash Equivalents
Portion 2 of Labor Burden: Cost of Government Required Insurance and Taxes
Portion 3 of Labor Burden: Cost of Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Portion 4 of Labor Burden: Cost of Non Taxable, Company Paid, Fringes
38
BLACK BOX CONSTRUCTION, LLC.
Base Yearly Salary 60,000.00$ per yearEquivalent "Base" Wage Per Hour 28.85$ "Base" Hourly Wage 28.85$ per hour WORK DAYS:Contracted Work Hours (CWH) 52 weeks 40 hours/week 2080 hours per year 260This is the Hourly "Base" Rate Used for Labor Burden Calculation 28.85$ Company Unbillable Paid Time: Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Vacation 10 days 8 hours/day 80 hours per yearHolidays 10 days 8 hours/day 80 hours per year
Sick Leave 5 days 8 hours/day 40 hours per yearCompany Wide Meetings/Employer Required Training 0 days 0 hours/day 0 hours per year
Bad Weather Minimum Show-Up Time 0 days 0 hours/day 0 hours per yearMorning Meetings 235 days 0.5 hours/day 117.5 hours per year
Rest Breaks 235 days 0.5 hours/day 117.5 hours per yearEffective Work Hours = Contracted - Unbillable 1645 hours per year
Company Paid Overtime Work Time (If Any) 0.0% as a % of CWH overtime rate 43.28$ per hourCompany Paid Overtime 0 hours/year per year -$ -$ per/hr
Company Paid Allowance for Use of Personal Car $0 per month per year -$ -$ per/hrCompany Paid Health Care Allowance* $300 per month per year 3,600.0$ 2.19$ per/hr
Company Paid Bonus 0 per month per year -$ -$ per/hrCost of Taxable, Company Paid, Allowances and Cash Equivalents 2.19$ per/hrHourly Rate a): Inclusive of Portion 1 (Used for Wcomp and Building Risk and Pub Liability Insurance Cost Calc) 31.04$ per/hrPreTax Payments Made By Employee for Insurance -$ per month per year -$ -$ per/hrHourly Rate b) Incluse of Portion 1 (Used for SS and Medicare Tax Calc) 31.04$ per/hr
Required Insurance and Taxes Enter EMR 0.85 per hourWorkers Compensation Ins. 6.00 5.1 % of Hourly Rate a) 1.58$ per hour
Builders Risk and Public Liability Ins. 8.00 per 1,000 of Hourly Rate a) 0.25$ per hourFederal Unemployment Tax 0.25 % 9,000.00$ is Co's Federal Tax Base 0.01$ per hour
State Unemployment Tax 3.00 % 24,400.00$ is Co's State Tax Base 0.44$ per hourSocial Security Tax 6.20 % of Hourly Rate b) 1.92$ per hour
Medicare, Medicaid Tax 1.45 % of Hourly Rate b) 0.45$ per hour Cost of Government Required Insurance and Taxes 4.66$ per/hrHourly Rate c): Inclusive of Portion 2 35.70$ per/hr
Vacation 80 hours 35.70$ per hour 2,856.2$ 1.74$ per/hrHolidays 80 hours 35.70$ per hour 2,856.2$ 1.74$ per/hr
Sick Leave 40 hours 35.70$ per hour 1,428.1$ 0.87$ per/hrCompany Wide Meetings/Training 0 hours 35.70$ per hour -$ -$ per/hr
Bad Weather Minimum Show-Up Time 0 hours 35.70$ per hour -$ -$ per/hrMorning Meetings 117.5 hours 35.70$ per hour 4,195.1$ 2.55$ per/hr
Rest Breaks 117.5 hours 35.70$ per hour 4,195.1$ 2.55$ per/hr per year 15,530.73$ 9.44$ per/hr
Hourly Wage d): Inclusive of Portion 3 45.14$ per/hr
Group Health Insurance (includes Dental)* 100.00$ per month 1,200.0$ per year 0.73$ per hour Disability Insurance (Short Term) 10.00$ per month 120.0$ per year 0.07$ per hourDisability Insurance (Long Term) 10.00$ per month 120.0$ per year 0.07$ per hour
401K 20.00$ per month 240.0$ per year 0.15$ per hour Cost of Non-Taxable, Company Paid, Fringes 1.02$ per/hrHourly Wage e): Inclusive of Portion 4 46.17$ per/hr
BURDEN FOR THIS EMPLOYEE IS: 28.85$ "Base" Rate Compared To: 46.17$ 1.60
Labor Burden - Field Superintendent
Portion 1 of Labor Burden: Cost of Taxable, Company Paid, Cash Allowances and Other Taxable Cash Equivalents
Portion 2 of Labor Burden: Cost of Government Required Insurance and Taxes
Portion 3 of Labor Burden: Cost of Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Portion 4 of Labor Burden: Cost of Non Taxable, Company Paid, Fringes
39
BLACK BOX CONSTRUCTION, LLC.
Base Yearly Salary 55,000.00$ per yearEquivalent "Base" Wage Per Hour 26.44$ "Base" Hourly Wage 26.44$ per hour WORK DAYS:Contracted Work Hours (CWH) 52 weeks 40 hours/week 2080 hours per year 260This is the Hourly "Base" Rate Used for Labor Burden Calculation 26.44$ Company Unbillable Paid Time: Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Vacation 10 days 8 hours/day 80 hours per yearHolidays 10 days 8 hours/day 80 hours per year
Sick Leave 5 days 8 hours/day 40 hours per yearCompany Wide Meetings/Employer Required Training 0 days 0 hours/day 0 hours per year
Bad Weather Minimum Show-Up Time 0 days 0 hours/day 0 hours per yearMorning Meetings 235 days 0.5 hours/day 117.5 hours per year
Rest Breaks 235 days 0.5 hours/day 117.5 hours per yearEffective Work Hours = Contracted - Unbillable 1645 hours per year
Company Paid Overtime Work Time (If Any) 0.0% as a % of CWH overtime rate 39.66$ per hourCompany Paid Overtime 0 hours/year per year -$ -$ per/hr
Company Paid Allowance for Use of Personal Car $0 per month per year -$ -$ per/hrCompany Paid Health Care Allowance* $300 per month per year 3,600.0$ 2.19$ per/hr
Company Paid Bonus 0 per month per year -$ -$ per/hrCost of Taxable, Company Paid, Allowances and Cash Equivalents 2.19$ per/hrHourly Rate a): Inclusive of Portion 1 (Used for Wcomp and Building Risk and Pub Liability Insurance Cost Calc) 28.63$ per/hrPreTax Payments Made By Employee for Insurance -$ per month per year -$ -$ per/hrHourly Rate b) Incluse of Portion 1 (Used for SS and Medicare Tax Calc) 28.63$ per/hr
Required Insurance and Taxes Enter EMR 0.85 per hourWorkers Compensation Ins. 6.00 5.1 % of Hourly Rate a) 1.46$ per hour
Builders Risk and Public Liability Ins. 8.00 per 1,000 of Hourly Rate a) 0.23$ per hourFederal Unemployment Tax 0.25 % 9,000.00$ is Co's Federal Tax Base 0.01$ per hour
State Unemployment Tax 3.00 % 24,400.00$ is Co's State Tax Base 0.44$ per hourSocial Security Tax 6.20 % of Hourly Rate b) 1.77$ per hour
Medicare, Medicaid Tax 1.45 % of Hourly Rate b) 0.42$ per hour Cost of Government Required Insurance and Taxes 4.34$ per/hrHourly Rate c): Inclusive of Portion 2 32.97$ per/hr
Vacation 80 hours 32.97$ per hour 2,637.3$ 1.60$ per/hrHolidays 80 hours 32.97$ per hour 2,637.3$ 1.60$ per/hr
Sick Leave 40 hours 32.97$ per hour 1,318.7$ 0.80$ per/hrCompany Wide Meetings/Training 0 hours 32.97$ per hour -$ -$ per/hr
Bad Weather Minimum Show-Up Time 0 hours 32.97$ per hour -$ -$ per/hrMorning Meetings 117.5 hours 32.97$ per hour 3,873.5$ 2.35$ per/hr
Rest Breaks 117.5 hours 32.97$ per hour 3,873.5$ 2.35$ per/hr per year 14,340.33$ 8.72$ per/hr
Hourly Wage d): Inclusive of Portion 3 41.68$ per/hr
Group Health Insurance (includes Dental)* 100.00$ per month 1,200.0$ per year 0.73$ per hour Disability Insurance (Short Term) 10.00$ per month 120.0$ per year 0.07$ per hourDisability Insurance (Long Term) 10.00$ per month 120.0$ per year 0.07$ per hour
401K 20.00$ per month 240.0$ per year 0.15$ per hour Cost of Non-Taxable, Company Paid, Fringes 1.02$ per/hrHourly Wage e): Inclusive of Portion 4 42.71$ per/hr
BURDEN FOR THIS EMPLOYEE IS: 26.44$ "Base" Rate Compared To: 42.71$ 1.62
Labor Burden - Project Engineer
Portion 1 of Labor Burden: Cost of Taxable, Company Paid, Cash Allowances and Other Taxable Cash Equivalents
Portion 2 of Labor Burden: Cost of Government Required Insurance and Taxes
Portion 3 of Labor Burden: Cost of Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Portion 4 of Labor Burden: Cost of Non Taxable, Company Paid, Fringes
40
BLACK BOX CONSTRUCTION, LLC.
Material Labor Equipment Subcontractor Sub-Total Unit Unit Cost Unit Quantity Unit Material Labor Equipment Subcontractor Total Field Supervision $ 613,942.80
General Superitendent $ 8,877.50 $ 8,877.50 per month $ 295.92 per day 0.4 Ea. 554 -$ 65,575.13$ -$ -$ 65,575.13$
Field Superintendent $ 8,000.00 $ 8,000.00 per month $ 266.67 per day 1 Ea. 554 -$ 147,733.33$ -$ -$ 147,733.33$
Safety Manager $ 8,700.00 $ 8,700.00 per month $ 290.00 per day 0.4 Ea. 554 -$ 64,264.00$ -$ -$ 64,264.00$ Project Manager $ 9,100.00 $ 9,100.00 per month $ 303.33 per day 1 Ea. 554 -$ 168,046.67$ -$ -$ 168,046.67$ Project Engineer $ 7,425.00 $ 7,425.00 per month $ 247.50 per day 1 Ea. 554 -$ 137,115.00$ -$ -$ 137,115.00$ Cellphones $ 50.00 $ 50.00 per month $ 1.67 Ea. 3.8 Ea. 554 -$ -$ 3,508.67$ -$ 3,508.67$ Company vehicles $ 400.00 $ 400.00 per month $ 13.33 Ea. 3.4 Ea. 554 -$ -$ 25,114.67$ -$ 25,114.67$ Ipad $ 35.00 $ 35.00 per month $ 1.17 Ea. 4 Ea. 554 -$ -$ 2,585.33$ -$ 2,585.33$
Site Office $ 22,438.06 Office set up $ 2,500.00 $ 2,500.00 Ea. $ 2,500.00 Ea. 1 Ea. - -$ -$ -$ 2,500.00$ 2,500.00$
Office Trailer Rental $ 300.00 $ 300.00 per month $ 10.00 per day 1 Ea. 554 -$ -$ -$ 5,540.00$ 5,540.00$
Office removal $ 1,500.00 $ 1,500.00 Ea. $ 1,500.00 Ea. 1 Ea. - -$ -$ -$ 1,500.00$ 1,500.00$ Office Equipment Rental $ 250.00 $ 250.00 per month $ 8.33 per day 1 Ea. 554 -$ -$ -$ 4,616.67$ 4,616.67$ Office activity chart/board $ 25.00 $ 25.00 Ea. $ 25.00 Ea. 1 Ea. - -$ -$ 25.00$ -$ 25.00$ Plan review TV (1) $ 400.00 $ 400.00 Ea. $ 400.00 Ea. 1 Ea. - -$ -$ 400.00$ -$ 400.00$ Office clean up/weekly $ 200.00 $ 200.00 per month $ 28.57 per week 1 Ea. 554 -$ -$ 304.40$ -$ 304.40$ Drinking Water $ 50.00 $ 50.00 per month $ 1.67 per day 1 Ea. 554 -$ -$ 923.33$ -$ 923.33$ Under counter refrigerator(1) $ 150.00 $ 150.00 Ea. $ 150.00 Ea. 1 Ea. - -$ -$ 150.00$ -$ 150.00$ Electricity and supply $ 150.00 $ 150.00 per month $ 5.00 per day 1 Ea. 554 -$ -$ 2,770.00$ -$ 2,770.00$ Display Monitors $ 100.00 $ 100.00 Ea. $ 100.00 Ea. 2 Ea. - -$ -$ 200.00$ -$ 200.00$ Office Supplies $ 90.00 $ 90.00 per month $ 3.00 per day 1 Ea. 554 -$ -$ 1,662.00$ -$ 1,662.00$ Internet $ 100.00 $ 100.00 per month $ 3.33 per day 1 Ea. 554 -$ -$ 1,846.67$ -$ 1,846.67$
Site Access $ 32,751.75 Temporary Access road/Parking $ 3.70 $ 2.69 $ 0.51 $ 6.90 SY $ 6.90 SY 2000 SY - 7,400.00$ 5,380.00$ 1,020.00$ -$ 13,800.00$ Construction Fence an Erosion Devices
$ 3.75 $ 2.02 $ - $ 5.77 LF $ 5.77 LF 2775 LF - 10,406.25$ 5,605.50$ -$ -$ 16,011.75$
Temporary Fall Protection(5) 200.00$ $ 200.00 Ea $ 200.00 Ea 5 Ea. - -$ -$ 1,000.00$ -$ 1,000.00$ Temporary Ladders(8) 70.00$ $ 70.00 Ea $ 70.00 Ea 8 Ea. - -$ -$ 560.00$ -$ 560.00$ Safety protection equipments(10) 100.00$ $ 100.00 Ea $ 100.00 Ea 10 Ea. - -$ -$ 1,000.00$ -$ 1,000.00$ Plastic to cover material 38.00$ $ 38.00 per roll $ 38.00 per roll 10 rolls - -$ -$ 380.00$ -$ 380.00$
Temporary Utilities/Storage $ 62,113.33 Water $ 100.00 $ 100.00 per month $ 3.33 per day 1 Ea. 554 -$ -$ 1,846.67$ -$ 1,846.67$
Electricity $ 250.00 $ 250.00 per month $ 8.33 per day 1 Ea. 554 -$ -$ 4,616.67$ -$ 4,616.67$
Waste Disposal/Recycling(5) $ 500.00 $ 500.00 per month $ 16.67 per day 5 Ea. 554 -$ -$ -$ 46,166.67$ 46,166.67$ Portable Toilets $ 90.00 $ 90.00 per month $ 3.00 per day 4 Ea. 554 -$ -$ -$ 6,648.00$ 6,648.00$ Signs $ 50.00 $ 50.00 Ea $ 50.00 Ea. 5 Ea. - -$ -$ 250.00$ -$ 250.00$ Storage Trailer $ 140.00 $ 140.00 per month $ 4.67 per day 1 Ea. 554 -$ -$ 2,585.33$ -$ 2,585.33$ Site Construction Facilities $ 13,000.00 Survey/Layout $ 8,000.00 $ 8,000.00 Allowance $ 8,000.00 Allowance 1 Allowance - -$ -$ -$ 8,000.00$ 8,000.00$
Final Clean up (Interior/Exterior) $ 5,000.00 $ 5,000.00 LS $ 5,000.00 LS 1 LS 1 -$ -$ -$ 5,000.00$ 5,000.00$
Small Tools and Equipments $ 2,000.00 Expendable tools $ 900.00 $ 900.00 LS $ 900.00 LS 1 LS - -$ -$ 900.00$ -$ 900.00$
Non Expendable tools $ 1,100.00 $ 1,100.00 LS $ 1,100.00 LS 1 LS - -$ -$ 1,100.00$ -$ 1,100.00$
Permits $ 177,692.68 Building Permits/Inspections(12) $ 12,000.00 $ 12,000.00 LS $ 12,000.00 LS 1 LS - -$ -$ -$ 12,000.00$ 12,000.00$ Bonding Cost @ 1.2% of project cost
$ 164,307.68 $ 164,307.68 $ 164,307.68 1 LS -$ -$ -$ 164,307.68$ 164,307.68$
Site Security camera Monitoring $ 75.00 $ 75.00 per month $ 2.50 per day 1 Ea. 554 -$ -$ 1,385.00$ -$ 1,385.00$
TOTALS $ - 17,806.25$ 593,719.63$ 56,133.73$ 256,279.02$ 923,938.63$
3.7 GENERAL CONDITIONS Cost Breakdown Quantity Duration
(days) Total Costs
Description
41
S no Activity Predecessor Activity Activity Duration(Days)Pre Construction
1 Notice to Proceed 0
2 Obtain Permits Notice to Proceed 10
3 Secure Laydown Area Obtain Permits 1
4 Develop Bill of Materials Obtain Permits 2
5 Procurement of Materials Notice to Proceed 10
6 Organize crew and ScheduleEquipment Obtain Permits 5
7 Mobilize to Project Site Organize crew and ScheduleEquipment 2
Site Work
8 Survey Mobilize to Project Site 1
9 Clearing & Grubbing Survey 2
10 Underground Utilties Locator Clearing & Grubbing 1
11 Erosion Control and Temporary Road Underground Utilties Locator 2
12 Rough Grading of the site Erosion Control and Temporary Road 2
13 SIte Office and Install Temporary Power service Rough Grading of the site 1
14 Underground Utilities Excavation SIte Office and Install Temporary Power service 7
15 Underground Utilities Installation Underground Utilities Excavation 34
16 Underground Utilities GC Inspection Underground Utilities Installation 9
17 Underground Utilities backfill Underground Utilities GC Inspection 13
18 SWPP & Retainage Pond Underground Utilities backfill 25
Foundation
19 Survey & Excavation for Foundation Underground Utilities backfill 10
20 Place Concrete for Foundation and Precast stairs Survey & Excavation for Foundation 18
21 Foundation Post Inspection Place Concrete for Foundation and Precast stairs 2
22 Sheet Waterproofing of Foundation & Inspection Foundation Post Inspection 4
23 BackFill Foundation and Granuler Fill For the Grade Sheet Waterproofing of Foundation & Inspection 12
24 Masonry work BackFill Foundation and Granuler Fill For the Grade 16
25 Rough in Plumbing-1 and Inspection Masonry work 30
26 Termite Treatment Rough in Plumbing-1 and Inspection 1
27 Grade Slabs Termite Treatment 13
Framing and Dry In28 Steel Column and Beam Erection Grade Slabs 20
29 Frame and Inwall Blocking 1st Floor Steel Column and Beam Erection 15
30 Install joist and lay decking-1st floor Frame and Inwall Blocking 1st Floor 15
31 Frame 2nd Floor walls & Corners Install joist and lay decking-1st floor 15
32 Install Precast Stair Frame 2nd Floor walls & Corners 1
33 Install Roof Joist / trusses Install Precast Stair 8
34 Lay Roof Decking Install Roof Joist / trusses 5
35 Install Sheathing Frame 2nd Floor walls & Corners 7
36 Roof Expansion Joints Lay Roof Decking 4
37 PVC Roofing Roof Expansion Joints 45
38 Roof nailing PVC Roofing 5
39 Exterior Doors & Windows Installation Install Sheathing 15
40 Exterior Framing Inspection Exterior Doors & Windows Installation 4
41 Spray Fire Proofing Lay Roof Decking 60
42 Complete Masonry Work Steel Column and Beam Erection 20
Exterior Finishes
43 Complete Exterior Brick Exterior Framing Inspection 27
44 ACM Wall Panels Complete Exterior Brick 20
45 Fiber Cement Sliding Exterior Framing Inspection 4.5
46 Aluminium Canopies ACM Wall Panels 2
47 Water Proof Membrane Marquee Sign ACM Wall Panels 0.5
48 Install Signage & Marquee sign ACM Wall Panels 5
49 Install Louvers Complete Exterior Brick 3
50 Flagpoles Aluminium Canopies 1
Utility Rough & Complete Concrete
51 Water proofing Elevator Pit Lay Roof Decking 1
52 Elevator Installation Water proofing Elevator Pit 14
53 Rough-in plumbing - 2 Install Joist and Lay Decking-1st Floor 18
54 Conduct Rough-in Plumbing - 2 Inspection Rough-in plumbing - 2 2
55 Rough-in HVAC Rough-in plumbing - 2 70
56 Conduct rough-in HVAC inspection Rough-in HVAC 5
57 Rough-in Fire Sprinkler System Rough-in HVAC 61
58 Conduct rough-in Fire Sprinkler Systerm Inspection Rough-in Fire Sprinkler System 5
59 Rough-in electrical Rough-in HVAC 18
60 Conduct Rough-in Electrical Inspection Rough-in electrical 2
61 Rough-in Security,Communication, Fire Alarm Rough-in electrical 22
62 Conduct Rough-in Security, Communication Fire Alarm Inspection Rough-in Security,Communication, Fire Alarm 4
63 Interior Framing Inspection Conduct Rough-in Security, Communication Fire Alarm Inspection 5
64 Place 1st Floor Concrete Interior Framing Inspection 5
4.1 Work Break Down StructureSECTION - 4
42
Interior Finishes
65 Place 1st Floor wall Insulation Interior Framing Inspection 15
66 Place 2nd Floor wall & Slab Insulation Place 1st Floor wall Insulation 7
67 Place Roof Insulation Place 2nd Floor wall & Slab Insulation 5
68 Conduct Insulation Inspection Place Roof Insulation 2
Dry Wall
69 Install 1st Floor Drywall Conduct Insulation Inspection 12
70 Install 1st Floor Overhead Drywall Install 1st Floor Drywall 3
71 Tape and Float 1st Floor Drywall Install 1st Floor Overhead Drywall 1
72 Install 2nd Floor Drywall Install 1st Floor Overhead Drywall 4
73 Install 2nd Floor Overhead Drywall Install 2nd Floor Drywall 1
74 Tape and Float 2nd Floor Install 2nd Floor Overhead Drywall 0.5
75 Install Interior Doors and Windows Install 1st Floor Drywall 15
Paint, Panels, Stage Flooring
76 Waterproof Membrane stage/platform Install 1st Floor Drywall 2
77 Prime Coat (Paint) Install 1st Floor Overhead Drywall 8
78 Install Stage Flooring Prime Coat (Paint) 5
79 Wall and ACT Panels Installation Install Stage Flooring 30
80 Exterior Painting (Top Coat) Prime Coat (Paint) 3
81 Interior Painting (Top Coat) Prime Coat (Paint) 21
82 Wall Graphics Interior Painting (Top Coat) 1
83 Wall Padding Interior Painting (Top Coat) 10
Cabinets
84 Millwork & Window Sill Interior Painting (Top Coat) 15
85 Wood Shelving Interior Painting (Top Coat) 27
86 Window Treatments Millwork & Window Sill 5
87 Operable Partitions Millwork & Window Sill 4
88 Stage Curtains, Folding Stages and Cubicle Curtains Millwork & Window Sill 5
Finish Plumbing
86 Final Plumbing Installation 1st Floor Interior Painting (Top Coat) 5.5
87 Final Plumbing Installation 2nd Floor Final Plumbing Installation 1st Floor 2.5
88 Final Plumbing Inspection Final Plumbing Installation 2nd Floor 2
Finish Electrical
89 Complete 1st Floor Circuit to Service Panel Interior Painting (Top Coat) 5.5
90 Complete 2nd Floor Circuit Service Panel Complete 1st Floor Circuit to Service Panel 2.5
91 Final Security, Communications , Fire alarm & Inspection Complete 2nd Floor Circuit Service Panel 16
92 Final Electrical Inspection Final Security, Communications , Fire alarm & Inspection 2
Finish HVAC and Fire Sprinkler System
93 Complete 1st Floor HVAC Complete 2nd Floor Circuit Service Panel 8
94 Complete 2nd Floor HVAC Final Security, Communications , Fire alarm & Inspection 4
95 Conduct HVAC Inspection Complete 2nd Floor HVAC 2
96 Complete Fire Sprinkler System and Inspection Conduct HVAC Inspection 7
Carpet, Tile, and Appliances
97 Water proofing & Ceramic Tile installation Interior Painting (Top Coat) 19
98 VCT Interior Painting (Top Coat) 50
99 Expansion Joints and Caulking VCT 6
100 Residental Appliances VCT 5
101 Food Service Equipment Residental Appliances 20
102 Kiln Food Service Equipment 3
103 Outdoor Basket ball and Lockers Residental Appliances 1
104 Column Covers Kiln 1
105 Carpet Kiln 9
106 Hollow metal, Wood Doors, Toilet Partitions & Accessories,FEC VCT 30
Landscaping & Grounds Work
107 Asphalt Paving & Curb Exterior Painting (Top Coat) 14
108 SIte Concrete Aggregate Asphalt Paving & Curb 8
109 Landscape & Irrigation Complete Exterior Brick 27
110 Fencing Asphalt Paving & Curb 2
111 Traffic Coatings Asphalt Paving & Curb 5
Close Out
112 Complete final inspection for certificate of occupancy Hollow metal, Wood Doors,Toilet Partitions &Accessories,FEC 4
113 Cleanup for occupancy Complete final inspection for certificate of occupancy 4
114 Complete Punch List Items of GC Cleanup for occupancy 12
115 Architect Pre Final Inspection Complete Punch List Items of GC 2
116 Workoff Architect Punch List Architect Pre Final Inspection 5
117 Architect Final Inspection Workoff Architect Punch List 1
118 Final completion and Handover to Client Architect Final Inspection 0
43
Activities Status Report
WBS
Activity ID Activity Name Predecessors OriginalDuration
Early Start
Early Finish
Late Start Late Finish
Total Float Free Float
CE 592 Porters Neck
CE 592.11 Pre Construction
A2020 Notice to Proceed 0.00 02-Jan-17 08:00 AM
02-Jan-17 08:00 AM
0.00 0.00
A2030 Obtain Permits A2020 10.00 02-Jan-17 08:00 AM
13-Jan-17 05:00 PM
02-Jan-17 08:00 AM
13-Jan-17 05:00 PM
0.00 0.00
A2040 Secure Laydown Area A2030 1.00 16-Jan-17 08:00 AM
16-Jan-17 05:00 PM
17-Jan-17 08:00 AM
17-Jan-17 05:00 PM
1.00 1.00
A2050 Develop Bill of Materials A2030, A2040
2.00 16-Jan-17 08:00 AM
17-Jan-17 05:00 PM
16-Jan-17 08:00 AM
17-Jan-17 05:00 PM
0.00 0.00
A2060 Procurement of Materials A2020 10.00 02-Jan-17 08:00 AM
13-Jan-17 05:00 PM
02-Jan-17 08:00 AM
13-Jan-17 05:00 PM
0.00 0.00
A2070 Organize crew and Schedule Equipment
A2030, A2050, A2060
5.00 16-Jan-17 08:00 AM
20-Jan-17 05:00 PM
16-Jan-17 08:00 AM
20-Jan-17 05:00 PM
0.00 0.00
A2080 Mobilize to Project Site A2070 2.00 23-Jan-17 08:00 AM
24-Jan-17 05:00 PM
23-Jan-17 08:00 AM
24-Jan-17 05:00 PM
0.00 0.00
Subtotal 17.00 02-Jan-17 08:00 AM
24-Jan-17 05:00 PM
02-Jan-17 08:00 AM
24-Jan-17 05:00 PM
0.00 0.00
CE 592.2 Site Work
A1040 Survey A2080 1.00 25-Jan-17 08:00 AM
25-Jan-17 05:00 PM
25-Jan-17 08:00 AM
25-Jan-17 05:00 PM
0.00 0.00
A1050 Clearing & Grubbing A1040 2.00 26-Jan-17 08:00 AM
27-Jan-17 05:00 PM
26-Jan-17 08:00 AM
27-Jan-17 05:00 PM
0.00 0.00
A1060 Underground Utilties Locator 811
A1050 1.00 30-Jan-17 08:00 AM
30-Jan-17 05:00 PM
30-Jan-17 08:00 AM
30-Jan-17 05:00 PM
0.00 0.00
A1070 Erosion Control and Temporary Road
A1060 2.00 31-Jan-17 08:00 AM
01-Feb-17 05:00 PM
31-Jan-17 08:00 AM
01-Feb-17 05:00 PM
0.00 0.00
A1080 Rough Grading of the site A1070 2.00 02-Feb-17 08:00 AM
03-Feb-17 05:00 PM
02-Feb-17 08:00 AM
03-Feb-17 05:00 PM
0.00 0.00
A1090 SIte Office and Install Temporary Power service
A1080 1.00 06-Feb-17 08:00 AM
06-Feb-17 05:00 PM
06-Feb-17 08:00 AM
06-Feb-17 05:00 PM
0.00 0.00
CE 592 Porters Neck Elementary School
© Oracle Corporation Page 1 of 11
Activities Status Report
WBS
Activity ID Activity Name Predecessors OriginalDuration
Early Start
Early Finish
Late Start Late Finish
Total Float Free Float
A1130 Underground Utilities Excavation
A1090 7.00 07-Feb-17 08:00 AM
15-Feb-17 05:00 PM
07-Feb-17 08:00 AM
15-Feb-17 05:00 PM
0.00 0.00
A1180 Underground Utilities Installation
A1130 34.00 09-Feb-17 08:00 AM
28-Mar-17 05:00 PM
10-Feb-17 08:00 AM
29-Mar-17 05:00 PM
1.00 0.00
A1190 Underground Utilities GC Inspection
A1180 9.00 17-Mar-17 08:00 AM
29-Mar-17 05:00 PM
20-Mar-17 08:00 AM
30-Mar-17 05:00 PM
1.00 0.00
A1220 Underground Utilities backfill A1190 13.00 20-Mar-17 08:00 AM
05-Apr-17 05:00 PM
21-Mar-17 08:00 AM
06-Apr-17 05:00 PM
1.00 1.00
A1450 SWPP & Retainage Pond A1130 25.00 16-Feb-17 08:00 AM
22-Mar-17 05:00 PM
16-Feb-17 08:00 AM
22-Mar-17 05:00 PM
0.00 0.00
Subtotal 51.00 25-Jan-17 08:00 AM
05-Apr-17 05:00 PM
25-Jan-17 08:00 AM
06-Apr-17 05:00 PM
1.00 0.00
CE 592.3 Foundation
A1100 Survey & Excavation for Foundation
A1220, A1450
10.00 23-Mar-17 08:00 AM
05-Apr-17 05:00 PM
23-Mar-17 08:00 AM
05-Apr-17 05:00 PM
0.00 0.00
A1110 Place Concrete for Foundation and Precast Stairs
A1100 18.00 28-Mar-17 08:00 AM
20-Apr-17 05:00 PM
28-Mar-17 08:00 AM
20-Apr-17 05:00 PM
0.00 0.00
A1120 Foundation Post Inspection A1110 2.00 20-Apr-17 08:00 AM
21-Apr-17 05:00 PM
20-Apr-17 08:00 AM
21-Apr-17 05:00 PM
0.00 0.00
A1140 Sheet Waterproofing of Foundation & Inspection
A1120 4.00 24-Apr-17 08:00 AM
27-Apr-17 05:00 PM
24-Apr-17 08:00 AM
27-Apr-17 05:00 PM
0.00 0.00
A1150 BackFill Foundation and Granuler Fill For the Grade Slab
A1140 12.00 28-Apr-17 08:00 AM
15-May-17 05:00 PM
28-Apr-17 08:00 AM
15-May-17 05:00 PM
0.00 0.00
A1160 Masonary work A1150 16.00 16-May-17 08:00 AM
06-Jun-17 05:00 PM
16-May-17 08:00 AM
06-Jun-17 05:00 PM
0.00 0.00
A1170 Rough in Plumbing - 1 and Inspection
A1160 30.00 30-May-17 08:00 AM
10-Jul-17 05:00 PM
30-May-17 08:00 AM
10-Jul-17 05:00 PM
0.00 0.00
A1210 Termite Treatment A1170 1.00 11-Jul-17 08:00 AM
11-Jul-17 05:00 PM
11-Jul-17 08:00 AM
11-Jul-17 05:00 PM
0.00 0.00
A1250 Grade Slabs A1210 13.00 12-Jul-17 08:00 AM
28-Jul-17 05:00 PM
12-Jul-17 08:00 AM
28-Jul-17 05:00 PM
0.00 0.00
Subtotal 92.00 23-Mar-17 28-Jul-17 23-Mar-17 28-Jul-17 0.00 0.00
CE 592 Porters Neck Elementary School
© Oracle Corporation Page 2 of 11
Activities Status Report
WBS
Activity ID Activity Name Predecessors OriginalDuration
Early Start
Early Finish
Late Start Late Finish
Total Float Free Float
CE 592.4 Framing and Dry In
A1200 Steel Column and Beam Erection
A1250 20.00 02-Aug-17 08:00 AM
29-Aug-17 05:00 PM
02-Aug-17 08:00 AM
29-Aug-17 05:00 PM
0.00 0.00
A1230 Frame and Inwall Blocking 1st Floor
A1200 15.00 02-Aug-17 08:00 AM
22-Aug-17 05:00 PM
02-Aug-17 08:00 AM
22-Aug-17 05:00 PM
0.00 0.00
A1330 Install Joist and Lay Decking- 1st Floor
A1230 15.00 23-Aug-17 08:00 AM
12-Sep-17 05:00 PM
23-Aug-17 08:00 AM
12-Sep-17 05:00 PM
0.00 0.00
A1480 Frame and In wall Blocking - 2nd Floor
A1330 10.50 13-Sep-17 08:00 AM
27-Sep-17 12:00 PM
06-Feb-18 08:00 AM
20-Feb-18 12:00 PM
104.00 0.00
A1620 Install Precast Stair A1480 1.00 27-Sep-17 01:00 PM
28-Sep-17 12:00 PM
05-Mar-18 08:00 AM
05-Mar-18 05:00 PM
112.50 0.00
A1630 Install Roof Joist / trusses A1620 8.00 28-Sep-17 01:00 PM
10-Oct-17 12:00 PM
06-Mar-18 08:00 AM
15-Mar-18 05:00 PM
112.50 0.00
A1640 Lay Roof Decking A1630 5.00 05-Oct-17 01:00 PM
12-Oct-17 12:00 PM
13-Mar-18 08:00 AM
19-Mar-18 05:00 PM
112.50 0.00
A1900 Install Sheathing A1480 7.00 27-Sep-17 08:00 AM
05-Oct-17 05:00 PM
20-Feb-18 08:00 AM
28-Feb-18 05:00 PM
104.00 0.00
A2010 Roof Expansion Joints A1640 4.00 12-Oct-17 01:00 PM
18-Oct-17 12:00 PM
03-Apr-18 08:00 AM
06-Apr-18 05:00 PM
122.50 0.00
A2090 PVC Roofing A2010 45.00 12-Oct-17 01:00 PM
14-Dec-17 12:00 PM
03-Apr-18 08:00 AM
04-Jun-18 05:00 PM
122.50 0.00
A2100 Roof nailing A2090 5.00 14-Dec-17 01:00 PM
21-Dec-17 12:00 PM
05-Jun-18 08:00 AM
11-Jun-18 05:00 PM
122.50 122.50
A2110 Exterior Doors & Windows Installation
A1900 15.00 06-Oct-17 08:00 AM
26-Oct-17 05:00 PM
01-Mar-18 08:00 AM
21-Mar-18 05:00 PM
104.00 0.00
A2130 Exterior Framing Inspection A2110 4.00 27-Oct-17 08:00 AM
01-Nov-17 05:00 PM
22-Mar-18 08:00 AM
27-Mar-18 05:00 PM
104.00 0.00
A2220 Spray Fire Proofing A1640 60.00 12-Oct-17 01:00 PM
04-Jan-18 12:00 PM
20-Mar-18 08:00 AM
11-Jun-18 05:00 PM
112.50 112.50
A2230 Complete Masonary Work A1200 20.00 30-Aug-17 08:00 AM
26-Sep-17 05:00 PM
15-May-18 08:00 AM
11-Jun-18 05:00 PM
184.00 184.00
Subtotal 111.50 02-Aug-17 08:00 AM
04-Jan-18 12:00 PM
02-Aug-17 08:00 AM
11-Jun-18 05:00 PM
112.50 0.00
CE 592 Porters Neck Elementary School
© Oracle Corporation Page 3 of 11
Activities Status Report
WBS
Activity ID Activity Name Predecessors OriginalDuration
Early Start
Early Finish
Late Start Late Finish
Total Float Free Float
CE 592.5 Exterior Finishes
A1240 Complete Exterior Brick A2130 27.00 02-Nov-17 08:00 AM
08-Dec-17 05:00 PM
28-Mar-18 08:00 AM
03-May-18 05:00 PM
104.00 0.00
A1800 ACM Wall Panels A1240 20.00 07-Dec-17 08:00 AM
03-Jan-18 05:00 PM
07-May-18 01:00 PM
04-Jun-18 12:00 PM
107.50 0.00
A1810 Fiber Cement Sliding A2130 4.50 02-Nov-17 08:00 AM
08-Nov-17 12:00 PM
05-Jun-18 01:00 PM
11-Jun-18 05:00 PM
153.50 153.50
A1820 Aluminium Canopies A1800 2.00 04-Jan-18 08:00 AM
05-Jan-18 05:00 PM
07-Jun-18 08:00 AM
08-Jun-18 05:00 PM
110.00 0.00
A1830 Water Proof Membrane Marquee Sign
A1800 0.50 04-Jan-18 08:00 AM
04-Jan-18 12:00 PM
04-Jun-18 01:00 PM
04-Jun-18 05:00 PM
107.50 0.00
A1840 Install Signage & Marquee sign A1800, A1830
5.00 04-Jan-18 01:00 PM
11-Jan-18 12:00 PM
05-Jun-18 08:00 AM
11-Jun-18 05:00 PM
107.50 107.50
A1850 Install Louvers A1240 3.00 11-Dec-17 08:00 AM
13-Dec-17 05:00 PM
07-Jun-18 08:00 AM
11-Jun-18 05:00 PM
128.00 128.00
A1890 Flagpoles A1820 1.00 08-Jan-18 08:00 AM
08-Jan-18 05:00 PM
11-Jun-18 08:00 AM
11-Jun-18 05:00 PM
110.00 110.00
Subtotal 50.50 02-Nov-17 08:00 AM
11-Jan-18 12:00 PM
28-Mar-18 08:00 AM
11-Jun-18 05:00 PM
107.50 0.00
CE 592.6 Utility Rough & Complete Concrete
A1260 Water proofing Elevator Pit A1640 1.00 12-Oct-17 01:00 PM
13-Oct-17 12:00 PM
22-May-18 08:00 AM
22-May-18 05:00 PM
157.50 0.00
A1270 Elevator Installation A1260 14.00 13-Oct-17 01:00 PM
02-Nov-17 12:00 PM
23-May-18 08:00 AM
11-Jun-18 05:00 PM
157.50 157.50
A1280 Rough-in plumbing - 2 A1330 18.00 27-Sep-17 08:00 AM
20-Oct-17 05:00 PM
27-Sep-17 08:00 AM
20-Oct-17 05:00 PM
0.00 0.00
A1290 Conduct Rough-in Plumbing - 2 Inspection
A1280 2.00 23-Oct-17 08:00 AM
24-Oct-17 05:00 PM
28-Dec-17 08:00 AM
29-Dec-17 05:00 PM
48.00 48.00
A1300 Rough-in HVAC A1280 70.00 27-Sep-17 08:00 AM
02-Jan-18 05:00 PM
27-Sep-17 08:00 AM
02-Jan-18 05:00 PM
0.00 0.00
CE 592 Porters Neck Elementary School
© Oracle Corporation Page 4 of 11
Activities Status Report
WBS
Activity ID Activity Name Predecessors OriginalDuration
Early Start
Early Finish
Late Start Late Finish
Total Float Free Float
A1310 Conduct rough-in HVAC inspection
A1300 5.00 03-Jan-18 08:00 AM
09-Jan-18 05:00 PM
05-Jun-18 08:00 AM
11-Jun-18 05:00 PM
109.00 109.00
A1320 Rough-in Fire Sprinkler System A1300 61.00 27-Sep-17 08:00 AM
20-Dec-17 05:00 PM
29-Sep-17 08:00 AM
22-Dec-17 05:00 PM
2.00 0.00
A1490 Conduct rough-in Fire SprinklerSysterm Inspection
A1320 5.00 21-Dec-17 08:00 AM
27-Dec-17 05:00 PM
25-Dec-17 08:00 AM
29-Dec-17 05:00 PM
2.00 2.00
A1780 Rough-in electrical A1300 18.00 24-Nov-17 08:00 AM
19-Dec-17 05:00 PM
24-Nov-17 08:00 AM
19-Dec-17 05:00 PM
0.00 0.00
A1880 Conduct Rough-in Electrical Inspection
A1780 2.00 20-Dec-17 08:00 AM
21-Dec-17 05:00 PM
28-Dec-17 08:00 AM
29-Dec-17 05:00 PM
6.00 6.00
A1970 Rough-in Security, Communication, Fire Alarm
A1780 22.00 24-Nov-17 08:00 AM
25-Dec-17 05:00 PM
24-Nov-17 08:00 AM
25-Dec-17 05:00 PM
0.00 0.00
A2000 Conduct Rough-in Security, Communication, Fire Alarm Inspection
A1970 4.00 26-Dec-17 08:00 AM
29-Dec-17 05:00 PM
26-Dec-17 08:00 AM
29-Dec-17 05:00 PM
0.00 0.00
A2240 Interior Framing Inspection A2000, A1290, A1490, A1880
5.00 01-Jan-18 08:00 AM
05-Jan-18 05:00 PM
01-Jan-18 08:00 AM
05-Jan-18 05:00 PM
0.00 0.00
A2250 Place 1st Floor Concrete A2240 5.00 08-Jan-18 08:00 AM
12-Jan-18 05:00 PM
13-Jul-18 08:00 AM
19-Jul-18 05:00 PM
134.00 134.00
Subtotal 78.00 27-Sep-17 08:00 AM
12-Jan-18 05:00 PM
27-Sep-17 08:00 AM
19-Jul-18 05:00 PM
134.00 0.00
CE 592.7 Interior Finishes
CE 592.7.1 Insulation
A1340 Place 1st Floor wall Insulation A2240 15.00 08-Jan-18 08:00 AM
26-Jan-18 05:00 PM
08-Jan-18 08:00 AM
26-Jan-18 05:00 PM
0.00 0.00
A1350 Place 2nd Floor wall & Slab Insulation
A1340 7.00 09-Jan-18 08:00 AM
17-Jan-18 05:00 PM
09-Jan-18 08:00 AM
17-Jan-18 05:00 PM
0.00 0.00
A1360 Place Roof Insulation A1350 5.00 18-Jan-18 08:00 AM
24-Jan-18 05:00 PM
18-Jan-18 08:00 AM
24-Jan-18 05:00 PM
0.00 0.00
A1370 Conduct Insulation Inspection A1360 2.00 25-Jan-18 08:00 AM
26-Jan-18 05:00 PM
25-Jan-18 08:00 AM
26-Jan-18 05:00 PM
0.00 0.00
CE 592 Porters Neck Elementary School
© Oracle Corporation Page 5 of 11
Activities Status Report
WBS
Activity ID Activity Name Predecessors OriginalDuration
Early Start
Early Finish
Late Start Late Finish
Total Float Free Float
Subtotal 15.00 08-Jan-18 08:00 AM
26-Jan-18 05:00 PM
08-Jan-18 08:00 AM
26-Jan-18 05:00 PM
0.00 0.00
CE 592.7.2 Dry Wall
A1380 Install 1st Floor Drywall A1370 12.00 29-Jan-18 08:00 AM
13-Feb-18 05:00 PM
29-Jan-18 08:00 AM
13-Feb-18 05:00 PM
0.00 0.00
A1390 Install 1st Floor Overhead Drywall
A1380 3.00 14-Feb-18 08:00 AM
16-Feb-18 05:00 PM
14-Feb-18 08:00 AM
16-Feb-18 05:00 PM
0.00 0.00
A1400 Tape and Float 1st Floor Drywall
A1390 1.00 19-Feb-18 08:00 AM
19-Feb-18 05:00 PM
26-Feb-18 08:00 AM
26-Feb-18 05:00 PM
5.00 5.00
A1410 Install 2nd Floor Drywall A1390 4.00 19-Feb-18 08:00 AM
22-Feb-18 05:00 PM
19-Feb-18 08:00 AM
22-Feb-18 05:00 PM
0.00 0.00
A1420 Install 2nd Floor Overhead Drywall
A1410 1.00 23-Feb-18 08:00 AM
23-Feb-18 05:00 PM
23-Feb-18 08:00 AM
23-Feb-18 05:00 PM
0.00 0.00
A1430 Tape and Float 2nd Floor Drywall
A1420 1.00 26-Feb-18 08:00 AM
26-Feb-18 05:00 PM
26-Feb-18 08:00 AM
26-Feb-18 05:00 PM
0.00 0.00
A2150 Install Interior Doors and Windows
A1380 15.00 07-Feb-18 08:00 AM
27-Feb-18 05:00 PM
22-May-18 08:00 AM
11-Jun-18 05:00 PM
74.00 74.00
Subtotal 22.00 29-Jan-18 08:00 AM
27-Feb-18 05:00 PM
29-Jan-18 08:00 AM
11-Jun-18 05:00 PM
74.00 0.00
CE 592.7.3 Paint, Panels, Stage Flooring
A1440 Waterproof Membrane stage/platform
A1380 2.00 14-Feb-18 08:00 AM
15-Feb-18 05:00 PM
23-Feb-18 08:00 AM
26-Feb-18 05:00 PM
7.00 7.00
A1500 Prime Coat (Paint) A1390, A1400, A1430, A1440
8.00 27-Feb-18 08:00 AM
08-Mar-18 05:00 PM
27-Feb-18 08:00 AM
08-Mar-18 05:00 PM
0.00 0.00
A1730 Install Stage Flooring A1500 6.00 06-Mar-18 08:00 AM
13-Mar-18 05:00 PM
19-Mar-18 08:00 AM
26-Mar-18 05:00 PM
9.00 0.00
A1870 Wall and ACT Panels Installation
A1730 60.00 07-Mar-18 08:00 AM
29-May-18 05:00 PM
20-Mar-18 08:00 AM
11-Jun-18 05:00 PM
9.00 9.00
CE 592 Porters Neck Elementary School
© Oracle Corporation Page 6 of 11
Activities Status Report
WBS
Activity ID Activity Name Predecessors OriginalDuration
Early Start
Early Finish
Late Start Late Finish
Total Float Free Float
A1920 Exterior Painting (Top Coat) A1500 3.00 06-Mar-18 08:00 AM
08-Mar-18 05:00 PM
08-May-18 08:00 AM
10-May-18 05:00 PM
45.00 0.00
A1950 Interior Painting (Top Coat) A1500 21.00 09-Mar-18 08:00 AM
06-Apr-18 05:00 PM
09-Mar-18 08:00 AM
06-Apr-18 05:00 PM
0.00 0.00
A2160 Wall Graphics A1950 1.00 11-Apr-18 08:00 AM
11-Apr-18 05:00 PM
18-May-18 01:00 PM
21-May-18 12:00 PM
27.50 0.00
A2170 Wall Padding and Display Cases
A2160 11.00 12-Apr-18 08:00 AM
26-Apr-18 05:00 PM
21-May-18 01:00 PM
05-Jun-18 12:00 PM
27.50 0.00
A2180 Banners A2170 0.50 27-Apr-18 08:00 AM
27-Apr-18 12:00 PM
05-Jun-18 01:00 PM
05-Jun-18 05:00 PM
27.50 0.00
A2210 Misc Steel A2180 4.00 27-Apr-18 01:00 PM
03-May-18 12:00 PM
06-Jun-18 08:00 AM
11-Jun-18 05:00 PM
27.50 27.50
Subtotal 75.00 14-Feb-18 08:00 AM
29-May-18 05:00 PM
23-Feb-18 08:00 AM
11-Jun-18 05:00 PM
9.00 0.00
CE 592.7.4 Cabinets
A1460 Millwork & Window Sill A1950 15.00 09-Apr-18 08:00 AM
27-Apr-18 05:00 PM
22-May-18 08:00 AM
11-Jun-18 05:00 PM
31.00 0.00
A1470 Wood Shelving A1950 27.00 09-Apr-18 08:00 AM
15-May-18 05:00 PM
04-May-18 08:00 AM
11-Jun-18 05:00 PM
19.00 19.00
A1930 Window Treatments A1460 5.00 23-Apr-18 08:00 AM
27-Apr-18 05:00 PM
05-Jun-18 08:00 AM
11-Jun-18 05:00 PM
31.00 31.00
A2120 Operable Partitions A1460 4.00 24-Apr-18 08:00 AM
27-Apr-18 05:00 PM
06-Jun-18 08:00 AM
11-Jun-18 05:00 PM
31.00 31.00
A2140 Stage Curtains, Folding Stages,and Cubicle Curtains
A1460 5.00 23-Apr-18 08:00 AM
27-Apr-18 05:00 PM
05-Jun-18 08:00 AM
11-Jun-18 05:00 PM
31.00 31.00
Subtotal 27.00 09-Apr-18 08:00 AM
15-May-18 05:00 PM
04-May-18 08:00 AM
11-Jun-18 05:00 PM
19.00 0.00
CE 592.7.5 Finish Plumbing
A1510 Final Plumbing Installation 1st Floor
A1950 5.50 09-Apr-18 08:00 AM
16-Apr-18 12:00 PM
29-May-18 08:00 AM
05-Jun-18 12:00 PM
36.00 0.00
CE 592 Porters Neck Elementary School
© Oracle Corporation Page 7 of 11
Activities Status Report
WBS
Activity ID Activity Name Predecessors OriginalDuration
Early Start
Early Finish
Late Start Late Finish
Total Float Free Float
A1520 Final Plumbing Installation 2nd Floor
A1510 2.50 16-Apr-18 01:00 PM
18-Apr-18 05:00 PM
05-Jun-18 01:00 PM
07-Jun-18 05:00 PM
36.00 0.00
A2200 Final Plumbing Inspection A1520 2.00 19-Apr-18 08:00 AM
20-Apr-18 05:00 PM
08-Jun-18 08:00 AM
11-Jun-18 05:00 PM
36.00 36.00
Subtotal 10.00 09-Apr-18 08:00 AM
20-Apr-18 05:00 PM
29-May-18 08:00 AM
11-Jun-18 05:00 PM
36.00 0.00
CE 592.7.6 Finish Electrical
A1530 Complete 1st Floor Circuit to Service Panel
A1950 5.50 09-Apr-18 08:00 AM
16-Apr-18 12:00 PM
01-May-18 08:00 AM
08-May-18 12:00 PM
16.00 0.00
A1540 Complete 2nd Floor Circuit Service Panel
A1530 2.50 16-Apr-18 01:00 PM
18-Apr-18 05:00 PM
08-May-18 01:00 PM
10-May-18 05:00 PM
16.00 0.00
A1550 Final Security, Communications, Fire alarm & Inspection
A1540 16.00 16-Apr-18 01:00 PM
08-May-18 12:00 PM
17-May-18 08:00 AM
07-Jun-18 05:00 PM
22.50 0.00
A1860 Final Electrical Inspection A1550 2.00 08-May-18 01:00 PM
10-May-18 12:00 PM
08-Jun-18 08:00 AM
11-Jun-18 05:00 PM
22.50 22.50
Subtotal 23.50 09-Apr-18 08:00 AM
10-May-18 12:00 PM
01-May-18 08:00 AM
11-Jun-18 05:00 PM
22.50 0.00
CE 592.7.7 Finish HVAC and Fire Sprinkler System
A1560 Complete 1st Floor HVAC A1540 8.00 19-Apr-18 08:00 AM
30-Apr-18 05:00 PM
11-May-18 08:00 AM
22-May-18 05:00 PM
16.00 0.00
A1570 Complete 2nd Floor HVAC A1560 4.00 01-May-18 08:00 AM
04-May-18 05:00 PM
23-May-18 08:00 AM
28-May-18 05:00 PM
16.00 0.00
A1580 Conduct HVAC Inspection A1570 3.00 07-May-18 08:00 AM
09-May-18 05:00 PM
29-May-18 08:00 AM
31-May-18 05:00 PM
16.00 0.00
A1790 Complete Fire Sprinkler Systemand Inspection
A1580 7.00 10-May-18 08:00 AM
18-May-18 05:00 PM
01-Jun-18 08:00 AM
11-Jun-18 05:00 PM
16.00 16.00
Subtotal 22.00 19-Apr-18 08:00 AM
18-May-18 05:00 PM
11-May-18 08:00 AM
11-Jun-18 05:00 PM
16.00 0.00
CE 592 Porters Neck Elementary School
© Oracle Corporation Page 8 of 11
Activities Status Report
WBS
Activity ID Activity Name Predecessors OriginalDuration
Early Start
Early Finish
Late Start Late Finish
Total Float Free Float
CE 592.7.8 Carpet, Tile, and Appliances
A1590 Water proofing & Ceramic Tile installation
A1950 19.00 09-Apr-18 08:00 AM
03-May-18 05:00 PM
16-May-18 08:00 AM
11-Jun-18 05:00 PM
27.00 27.00
A1600 VCT A1950 50.00 30-Mar-18 08:00 AM
07-Jun-18 05:00 PM
30-Mar-18 08:00 AM
07-Jun-18 05:00 PM
0.00 0.00
A1610 Expansion Joints and Caulking A1600 6.00 01-Jun-18 08:00 AM
08-Jun-18 05:00 PM
04-Jun-18 08:00 AM
11-Jun-18 05:00 PM
1.00 1.00
A1740 Residental Appliances A1600 5.00 13-Apr-18 08:00 AM
19-Apr-18 05:00 PM
20-Apr-18 08:00 AM
26-Apr-18 05:00 PM
5.00 0.00
A1750 Food Service Equipment A1740 20.00 20-Apr-18 08:00 AM
17-May-18 05:00 PM
27-Apr-18 08:00 AM
24-May-18 05:00 PM
5.00 0.00
A1760 Kiln A1750 3.00 18-May-18 08:00 AM
22-May-18 05:00 PM
25-May-18 08:00 AM
29-May-18 05:00 PM
5.00 0.00
A1910 Outdoor Basket ball and Lockers
A1740 1.00 20-Apr-18 08:00 AM
20-Apr-18 05:00 PM
11-Jun-18 08:00 AM
11-Jun-18 05:00 PM
36.00 36.00
A1960 Column Covers A1760 1.00 23-May-18 08:00 AM
23-May-18 05:00 PM
11-Jun-18 08:00 AM
11-Jun-18 05:00 PM
13.00 13.00
A2190 Carpet A1760 9.00 23-May-18 08:00 AM
04-Jun-18 05:00 PM
30-May-18 08:00 AM
11-Jun-18 05:00 PM
5.00 5.00
A2260 Hollow metal, Wood Doors, Toilet Partitions & Accessories,FEC
A1600 30.00 01-May-18 08:00 AM
11-Jun-18 05:00 PM
01-May-18 08:00 AM
11-Jun-18 05:00 PM
0.00 0.00
Subtotal 52.00 30-Mar-18 08:00 AM
11-Jun-18 05:00 PM
30-Mar-18 08:00 AM
11-Jun-18 05:00 PM
0.00 0.00
Subtotal 111.00 08-Jan-18 08:00 AM
11-Jun-18 05:00 PM
08-Jan-18 08:00 AM
11-Jun-18 05:00 PM
0.00 0.00
CE 592.8 Landscaping & Grounds Work
A1650 Asphalt Paving & Curb A1920 14.00 09-Mar-18 08:00 AM
28-Mar-18 05:00 PM
11-May-18 08:00 AM
30-May-18 05:00 PM
45.00 0.00
A1660 SIte Concrete Aggregate A1650 8.00 29-Mar-18 08:00 AM
09-Apr-18 05:00 PM
31-May-18 08:00 AM
11-Jun-18 05:00 PM
45.00 45.00
CE 592 Porters Neck Elementary School
© Oracle Corporation Page 9 of 11
Activities Status Report
WBS
Activity ID Activity Name Predecessors OriginalDuration
Early Start
Early Finish
Late Start Late Finish
Total Float Free Float
A1670 Landscape & Irrigation A1240 27.00 11-Dec-17 08:00 AM
16-Jan-18 05:00 PM
04-May-18 08:00 AM
11-Jun-18 05:00 PM
104.00 104.00
A1680 Fencing A1650 2.00 27-Mar-18 08:00 AM
28-Mar-18 05:00 PM
08-Jun-18 08:00 AM
11-Jun-18 05:00 PM
53.00 53.00
A1980 Traffic Coatings A1650 5.00 30-Mar-18 08:00 AM
05-Apr-18 05:00 PM
05-Jun-18 08:00 AM
11-Jun-18 05:00 PM
47.00 47.00
Subtotal 86.00 11-Dec-17 08:00 AM
09-Apr-18 05:00 PM
04-May-18 08:00 AM
11-Jun-18 05:00 PM
45.00 0.00
CE 592.9 Close Out
A1690 Complete final inspection for certificate of occupancy
A2260, A2100, A2220, A2230, A1810, A1840, A1850, A1890, A1270, A1310, A2150, A1730, A1870, A2210, A1470, A1930, A2120, A2140, A2200, A1860, A1790, A1590, A1610, A1910, A1960, A2190, A1660, A1670, A1680,
4.00 12-Jun-18 08:00 AM
15-Jun-18 05:00 PM
12-Jun-18 08:00 AM
15-Jun-18 05:00 PM
0.00 0.00
CE 592 Porters Neck Elementary School
© Oracle Corporation Page 10 of 11
Activities Status Report
WBS
Activity ID Activity Name Predecessors OriginalDuration
Early Start
Early Finish
Late Start Late Finish
Total Float Free Float
A1700 Cleanup for occupancy A1690 4.00 18-Jun-18 08:00 AM
21-Jun-18 05:00 PM
18-Jun-18 08:00 AM
21-Jun-18 05:00 PM
0.00 0.00
A1710 Complete Punch List Items of GC
A1700 12.00 22-Jun-18 08:00 AM
09-Jul-18 05:00 PM
22-Jun-18 08:00 AM
09-Jul-18 05:00 PM
0.00 0.00
A1720 Architect Pre Final Inspection A1710 2.00 10-Jul-18 08:00 AM
11-Jul-18 05:00 PM
10-Jul-18 08:00 AM
11-Jul-18 05:00 PM
0.00 0.00
A1770 Workoff Architect Punch List A1720 5.00 12-Jul-18 08:00 AM
18-Jul-18 05:00 PM
12-Jul-18 08:00 AM
18-Jul-18 05:00 PM
0.00 0.00
A1940 Architect Final Inspection A1770 1.00 19-Jul-18 08:00 AM
19-Jul-18 05:00 PM
19-Jul-18 08:00 AM
19-Jul-18 05:00 PM
0.00 0.00
A1990 Final completion and Handover to Client
A1940 0.00 19-Jul-18 05:00 PM
19-Jul-18 05:00 PM
0.00 0.00
Subtotal 28.00 12-Jun-18 08:00 AM
19-Jul-18 05:00 PM
12-Jun-18 08:00 AM
19-Jul-18 05:00 PM
0.00 0.00
Subtotal 404.00 02-Jan-17 08:00 AM
19-Jul-18 05:00 PM
02-Jan-17 08:00 AM
19-Jul-18 05:00 PM
0.00 0.00
CE 592 Porters Neck Elementary School
© Oracle Corporation Page 11 of 11
19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 16 23 30
December 2016 January 2017 February 2017 March 2017 April 2017 May 2017 June 2017 July 2017 August 2017 September 2017 October 2017 November 2017 December 2017 January 2018 February 2018 March 2018 April 2018 May 2018 June 2018 July 2018August 2018
19-Jul-18 05:00 PM, CE 592 Porters Neck
24-Jan-17 05:00 PM, CE 592.11 Pre Construction
Notice to Proceed, 02-Jan-17 08:00 AM
Obtain Permits
Secure Laydown Area
Develop Bill of Materials
Procurement of Materials
Organize crew and Schedule Equipment
Mobilize to Project Site05-Apr-17 05:00 PM, CE 592.2 Site Work
Survey
Clearing & Grubbing
Underground Utilties Locator 811
Erosion Control and Temporary Road
Rough Grading of the site
SIte Office and Install Temporary Power service
Underground Utilities Excavation
Underground Utilities Installation
Underground Utilities GC Inspection
Underground Utilities backfill
SWPP & Retainage Pond28-Jul-17 05:00 PM, CE 592.3 Foundation
Survey & Excavation for Foundation
Place Concrete for Foundation and Precast Stairs
Foundation Post Inspection
Sheet Waterproofing of Foundation & Inspection
BackFill Foundation and Granuler Fill For the Grade Slab
Masonary work
Rough in Plumbing - 1 and Inspection
Termite Treatment
Grade Slabs04-Jan-18 12:00 PM, CE 592.4 Framing and Dry In
Steel Column and Beam Erection
Frame and Inwall Blocking 1st Floor
Install Joist and Lay Decking- 1st Floor
Frame and In wall Blocking - 2nd Floor
Install Precast Stair
Install Roof Joist / trusses
Lay Roof Decking
Install Sheathing
Roof Expansion Joints
PVC Roofing
Roof nailing
Exterior Doors & Windows Installation
Exterior Framing Inspection
Spray Fire Proofing
Complete Masonary Work11-Jan-18 12:00 PM, CE 592.5 Exterior Finishes
Complete Exterior Brick
ACM Wall Panels
Fiber Cement Sliding
Aluminium Canopies
Water Proof Membrane Marquee Sign
Install Signage & Marquee sign
Install Louvers
Flagpoles12-Jan-18 05:00 PM, CE 592.6 Utility Rough & Complete Concrete
Water proofing Elevator Pit
Elevator Installation
Rough-in plumbing - 2
Conduct Rough-in Plumbing - 2 Inspection
Rough-in HVAC
Conduct rough-in HVAC inspection
Rough-in Fire Sprinkler System
Conduct rough-in Fire Sprinkler Systerm Inspection
Rough-in electrical
Conduct Rough-in Electrical Inspection
Rough-in Security, Communication, Fire Alarm
Conduct Rough-in Security, Communication, Fire Alarm Inspection
Interior Framing Inspection
Place 1st Floor Concrete11-Jun-18 05:00 PM, CE 592.7 Interior Finishes
26-Jan-18 05:00 PM, CE 592.7.1 Insulation
Place 1st Floor wall Insulation
Place 2nd Floor wall & Slab Insulation
Place Roof Insulation
Conduct Insulation Inspection27-Feb-18 05:00 PM, CE 592.7.2 Dry Wall
Install 1st Floor Drywall
Install 1st Floor Overhead Drywall
Tape and Float 1st Floor Drywall
Install 2nd Floor Drywall
Install 2nd Floor Overhead Drywall
Tape and Float 2nd Floor Drywall
Actual Level of Effort
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 1 of 2 TASK filter: All Activities
© Oracle Corporation
19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 16 23 30
December 2016 January 2017 February 2017 March 2017 April 2017 May 2017 June 2017 July 2017 August 2017 September 2017 October 2017 November 2017 December 2017 January 2018 February 2018 March 2018 April 2018 May 2018 June 2018 July 2018August 2018
Install Interior Doors and Windows29-May-18 05:00 PM, CE 592.7.3 Paint, Panels, Stage Flooring
Waterproof Membrane stage/platform
Prime Coat (Paint)
Install Stage Flooring
Wall and ACT Panels Installation
Exterior Painting (Top Coat)
Interior Painting (Top Coat)
Wall Graphics
Wall Padding and Display Cases
Banners
Misc Steel15-May-18 05:00 PM, CE 592.7.4 Cabinets
Millwork & Window Sill
Wood Shelving
Window Treatments
Operable Partitions
Stage Curtains, Folding Stages, and Cubicle Curtains20-Apr-18 05:00 PM, CE 592.7.5 Finish Plumbing
Final Plumbing Installation 1st Floor
Final Plumbing Installation 2nd Floor
Final Plumbing Inspection10-May-18 12:00 PM, CE 592.7.6 Finish Electrical
Complete 1st Floor Circuit to Service Panel
Complete 2nd Floor Circuit Service Panel
Final Security, Communications , Fire alarm & Inspection
Final Electrical Inspection18-May-18 05:00 PM, CE 592.7.7 Finish HVAC and Fire Sprinkler System
Complete 1st Floor HVAC
Complete 2nd Floor HVAC
Conduct HVAC Inspection
Complete Fire Sprinkler System and Inspection11-Jun-18 05:00 PM, CE 592.7.8 Carpet, Tile, and Appliances
Water proofing & Ceramic Tile installation
VCT
Expansion Joints and Caulking
Residental Appliances
Food Service Equipment
Kiln
Outdoor Basket ball and Lockers
Column Covers
Carpet
Hollow metal, Wood Doors, Toilet Partitions & Accessories,FEC09-Apr-18 05:00 PM, CE 592.8 Landscaping & Grounds Work
Asphalt Paving & Curb
SIte Concrete Aggregate
Landscape & Irrigation
Fencing
Traffic Coatings19-Jul-18 05:00 PM, CE 592.9 Close Out
Complete final inspection for certificate of occupancy
Cleanup for occupancy
Complete Punch List Items of GC
Architect Pre Final Inspection
Workoff Architect Punch List
Architect Final InspectionFinal completion and Handover to Client,
Actual Level of Effort
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 2 of 2 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name
CE 592 Porters NeckCE 592 Porters Neck
CE 592.11 Pre ConstructionCE 592.11 Pre ConstructionA2020 Notice to Proceed
A2030 Obtain Permits
A2040 Secure Laydown Area
A2050 Develop Bill of Materials
A2060 Procurement of Materials
A2070 Organize crew and Schedule Equipment
A2080 Mobilize to Project Site
CE 592.2 Site WorkCE 592.2 Site WorkA1040 Survey
A1050 Clearing & Grubbing
A1060 Underground Utilties Locator 811
A1070 Erosion Control and Temporary Road
A1080 Rough Grading of the site
A1090 SIte Office and Install Temporary Power service
A1130 Underground Utilities Excavation
A1180 Underground Utilities Installation
A1190 Underground Utilities GC Inspection
A1220 Underground Utilities backfill
A1450 SWPP & Retainage Pond
CE 592.3 FoundationCE 592.3 FoundationA1100 Survey & Excavation for Foundation
A1110 Place Concrete for Foundation and Precast Stairs
A1120 Foundation Post Inspection
A1140 Sheet Waterproofing of Foundation & Inspection
A1150 BackFill Foundation and Granuler Fill For the Grade Slab
A1160 Masonary work
A1170 Rough in Plumbing - 1 and Inspection
A1210 Termite Treatment
A1250 Grade Slabs
CE 592.4 Framing and Dry InCE 592.4 Framing and Dry InA1200 Steel Column and Beam Erection
A1230 Frame and Inwall Blocking 1st Floor
A1330 Install Joist and Lay Decking- 1st Floor
A1480 Frame and In wall Blocking - 2nd Floor
A1620 Install Precast Stair
A1630 Install Roof Joist / trusses
A1640 Lay Roof Decking
A1900 Install Sheathing
A2010 Roof Expansion Joints
A2090 PVC Roofing
A2100 Roof nailing
A2110 Exterior Doors & Windows Installation
A2130 Exterior Framing Inspection
A2220 Spray Fire Proofing
A2230 Complete Masonary Work
CE 592.5 Exterior FinishesCE 592.5 Exterior FinishesA1240 Complete Exterior Brick
A1800 ACM Wall Panels
A1810 Fiber Cement Sliding
A1820 Aluminium Canopies
A1830 Water Proof Membrane Marquee Sign
A1840 Install Signage & Marquee sign
A1850 Install Louvers
A1890 Flagpoles
CE 592.6 Utility Rough & Complete ConcreteCE 592.6 Utility Rough & Complete ConcreteA1260 Water proofing Elevator Pit
A1270 Elevator Installation
A1280 Rough-in plumbing - 2
A1290 Conduct Rough-in Plumbing - 2 Inspection
A1300 Rough-in HVAC
A1310 Conduct rough-in HVAC inspection
A1320 Rough-in Fire Sprinkler System
A1490 Conduct rough-in Fire Sprinkler Systerm Inspection
A1780 Rough-in electrical
A1880 Conduct Rough-in Electrical Inspection
A1970 Rough-in Security, Communication, Fire Alarm
A2000 Conduct Rough-in Security, Communication, Fire Alarm Inspection
A2240 Interior Framing Inspection
A2250 Place 1st Floor Concrete
CE 592.7 Interior FinishesCE 592.7 Interior FinishesCE 592.7.1 InsulationCE 592.7.1 Insulation
A1340 Place 1st Floor wall Insulation
A1350 Place 2nd Floor wall & Slab Insulation
A1360 Place Roof Insulation
A1370 Conduct Insulation Inspection
CE 592.7.2 Dry WallCE 592.7.2 Dry Wall
A1380 Install 1st Floor Drywall
A1390 Install 1st Floor Overhead Drywall
A1400 Tape and Float 1st Floor Drywall
A1410 Install 2nd Floor Drywall
A1420 Install 2nd Floor Overhead Drywall
19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 16 23 30
December 2016 January 2017 February 2017 March 2017 April 2017 May 2017 June 2017 July 2017 August 2017 September 2017 October 2017 November 2017 December 2017 January 2018 February 2018 March 2018 April 2018 May 2018 June 2018 July 2018August 2018
19-Jul-18 05:00 PM, CE 592 Porters Neck
24-Jan-17 05:00 PM, CE 592.11 Pre Construction
Notice to Proceed, 02-Jan-17 08:00 AM
Obtain Permits
Secure Laydown Area
Develop Bill of Materials
Procurement of Materials
Organize crew and Schedule Equipment
Mobilize to Project Site05-Apr-17 05:00 PM, CE 592.2 Site Work
Survey
Clearing & Grubbing
Underground Utilties Locator 811
Erosion Control and Temporary Road
Rough Grading of the site
SIte Office and Install Temporary Power service
Underground Utilities Excavation
Underground Utilities Installation
Underground Utilities GC Inspection
Underground Utilities backfill
SWPP & Retainage Pond28-Jul-17 05:00 PM, CE 592.3 Foundation
Survey & Excavation for Foundation
Place Concrete for Foundation and Precast Stairs
Foundation Post Inspection
Sheet Waterproofing of Foundation & Inspection
BackFill Foundation and Granuler Fill For the Grade Slab
Masonary work
Rough in Plumbing - 1 and Inspection
Termite Treatment
Grade Slabs04-Jan-18 12:00 PM, CE 592.4 Framing and Dry In
Steel Column and Beam Erection
Frame and Inwall Blocking 1st Floor
Install Joist and Lay Decking- 1st Floor
Frame and In wall Blocking - 2nd Floor
Install Precast Stair
Install Roof Joist / trusses
Lay Roof Decking
Install Sheathing
Roof Expansion Joints
PVC Roofing
Roof nailing
Exterior Doors & Windows Installation
Exterior Framing Inspection
Spray Fire Proofing
Complete Masonary Work11-Jan-18 12:00 PM, CE 592.5 Exterior Finishes
Complete Exterior Brick
ACM Wall Panels
Fiber Cement Sliding
Aluminium Canopies
Water Proof Membrane Marquee Sign
Install Signage & Marquee sign
Install Louvers
Flagpoles12-Jan-18 05:00 PM, CE 592.6 Utility Rough & Complete Concrete
Water proofing Elevator Pit
Elevator Installation
Rough-in plumbing - 2
Conduct Rough-in Plumbing - 2 Inspection
Rough-in HVAC
Conduct rough-in HVAC inspection
Rough-in Fire Sprinkler System
Conduct rough-in Fire Sprinkler Systerm Inspection
Rough-in electrical
Conduct Rough-in Electrical Inspection
Rough-in Security, Communication, Fire Alarm
Conduct Rough-in Security, Communication, Fire Alarm Inspection
Interior Framing Inspection
Place 1st Floor Concrete11-Jun-18 05:00 PM, CE 592.7 Interior Finishes
26-Jan-18 05:00 PM, CE 592.7.1 Insulation
Place 1st Floor wall Insulation
Place 2nd Floor wall & Slab Insulation
Place Roof Insulation
Conduct Insulation Inspection27-Feb-18 05:00 PM, CE 592.7.2 Dry Wall
Install 1st Floor Drywall
Install 1st Floor Overhead Drywall
Tape and Float 1st Floor Drywall
Install 2nd Floor Drywall
Install 2nd Floor Overhead Drywall
Actual Level of Effort
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 1 of 2 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name
A1430 Tape and Float 2nd Floor Drywall
A2150 Install Interior Doors and Windows
CE 592.7.3 Paint, Panels, Stage FlooringCE 592.7.3 Paint, Panels, Stage FlooringA1440 Waterproof Membrane stage/platform
A1500 Prime Coat (Paint)
A1730 Install Stage Flooring
A1870 Wall and ACT Panels Installation
A1920 Exterior Painting (Top Coat)
A1950 Interior Painting (Top Coat)
A2160 Wall Graphics
A2170 Wall Padding and Display Cases
A2180 Banners
A2210 Misc Steel
CE 592.7.4 CabinetsCE 592.7.4 Cabinets
A1460 Millwork & Window Sill
A1470 Wood Shelving
A1930 Window Treatments
A2120 Operable Partitions
A2140 Stage Curtains, Folding Stages, and Cubicle Curtains
CE 592.7.5 Finish PlumbingCE 592.7.5 Finish Plumbing
A1510 Final Plumbing Installation 1st Floor
A1520 Final Plumbing Installation 2nd Floor
A2200 Final Plumbing Inspection
CE 592.7.6 Finish ElectricalCE 592.7.6 Finish Electrical
A1530 Complete 1st Floor Circuit to Service Panel
A1540 Complete 2nd Floor Circuit Service Panel
A1550 Final Security, Communications , Fire alarm & Inspection
A1860 Final Electrical Inspection
CE 592.7.7 Finish HVAC and Fire Sprinkler SystemCE 592.7.7 Finish HVAC and Fire Sprinkler System
A1560 Complete 1st Floor HVAC
A1570 Complete 2nd Floor HVAC
A1580 Conduct HVAC Inspection
A1790 Complete Fire Sprinkler System and Inspection
CE 592.7.8 Carpet, Tile, and AppliancesCE 592.7.8 Carpet, Tile, and Appliances
A1590 Water proofing & Ceramic Tile installation
A1600 VCT
A1610 Expansion Joints and Caulking
A1740 Residental Appliances
A1750 Food Service Equipment
A1760 Kiln
A1910 Outdoor Basket ball and Lockers
A1960 Column Covers
A2190 Carpet
A2260 Hollow metal, Wood Doors, Toilet Partitions & Accessories,FEC
CE 592.8 Landscaping & Grounds WorkCE 592.8 Landscaping & Grounds WorkA1650 Asphalt Paving & Curb
A1660 SIte Concrete Aggregate
A1670 Landscape & Irrigation
A1680 Fencing
A1980 Traffic Coatings
CE 592.9 Close OutCE 592.9 Close OutA1690 Complete final inspection for certificate of occupancy
A1700 Cleanup for occupancy
A1710 Complete Punch List Items of GC
A1720 Architect Pre Final Inspection
A1770 Workoff Architect Punch List
A1940 Architect Final Inspection
A1990 Final completion and Handover to Client
19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 16 23 30
December 2016 January 2017 February 2017 March 2017 April 2017 May 2017 June 2017 July 2017 August 2017 September 2017 October 2017 November 2017 December 2017 January 2018 February 2018 March 2018 April 2018 May 2018 June 2018 July 2018August 2018
Tape and Float 2nd Floor Drywall
Install Interior Doors and Windows29-May-18 05:00 PM, CE 592.7.3 Paint, Panels, Stage Flooring
Waterproof Membrane stage/platform
Prime Coat (Paint)
Install Stage Flooring
Wall and ACT Panels Installation
Exterior Painting (Top Coat)
Interior Painting (Top Coat)
Wall Graphics
Wall Padding and Display Cases
Banners
Misc Steel15-May-18 05:00 PM, CE 592.7.4 Cabinets
Millwork & Window Sill
Wood Shelving
Window Treatments
Operable Partitions
Stage Curtains, Folding Stages, and Cubicle Curtains20-Apr-18 05:00 PM, CE 592.7.5 Finish Plumbing
Final Plumbing Installation 1st Floor
Final Plumbing Installation 2nd Floor
Final Plumbing Inspection10-May-18 12:00 PM, CE 592.7.6 Finish Electrical
Complete 1st Floor Circuit to Service Panel
Complete 2nd Floor Circuit Service Panel
Final Security, Communications , Fire alarm & Inspection
Final Electrical Inspection18-May-18 05:00 PM, CE 592.7.7 Finish HVAC and Fire Sprinkler System
Complete 1st Floor HVAC
Complete 2nd Floor HVAC
Conduct HVAC Inspection
Complete Fire Sprinkler System and Inspection11-Jun-18 05:00 PM, CE 592.7.8 Carpet, Tile, and Appliances
Water proofing & Ceramic Tile installation
VCT
Expansion Joints and Caulking
Residental Appliances
Food Service Equipment
Kiln
Outdoor Basket ball and Lockers
Column Covers
Carpet
Hollow metal, Wood Doors, Toilet Partitions & Accessories,FEC09-Apr-18 05:00 PM, CE 592.8 Landscaping & Grounds Work
Asphalt Paving & Curb
SIte Concrete Aggregate
Landscape & Irrigation
Fencing
Traffic Coatings19-Jul-18 05:00 PM, CE 592.9 Close Out
Complete final inspection for certificate of occupancy
Cleanup for occupancy
Complete Punch List Items of GC
Architect Pre Final Inspection
Workoff Architect Punch List
Architect Final InspectionFinal completion and Handover to Client,
Actual Level of Effort
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 2 of 2 TASK filter: All Activities
© Oracle Corporation
Project: CE 592 Porters NeckWBS: CE 592.11 Pre Construction
WBS: CE 592.2 Site Work
WBS: CE 592.3 Foundation
WBS: CE 592.4 Framing and Dry In
WBS: CE 592.5 Exterior Finishes
WBS: CE 592.6 Utility Rough & Complete Concrete
WBS: CE 592.7 Interior Finishes
WBS: CE 592.8 Landscaping & Grounds Work
WBS: CE 592.9 Close Out
WBS: CE 592.7.1 Insulation
WBS: CE 592.7.2 Dry Wall
WBS: CE 592.7.3 Paint, Panels, Stage Flooring
WBS: CE 592.7.4 Cabinets
WBS: CE 592.7.5 Finish Plumbing
WBS: CE 592.7.6 Finish Electrical
WBS: CE 592.7.7 Finish HVAC and Fire Sprinkler System
WBS: CE 592.7.8 Carpet, Tile, and Appliances
A2080Mobi lize to Project Si te
A2070Organize crew and
Schedule Equipm ent
A2060Procur ement of
Mate rial s
A2050Dev elop B i ll of
Mat erial s
A2030Obta in Pe rmi ts
A 20 20Noti ce to Pro ceed
A2040Secure Laydo wn Ar ea
A1450SW PP & Retain age
Pond
A1130Underground Ut ili t ie s
Excav ation
A1090SIte Of f ic e a nd Ins tall
Tem porary Power
serv i ce
A 10 80Rough Grading of the
sit e
A 10 70E rosion Control and
Tem porary Road
A10 60Underground Uti lties
Locato r 811
A10 50Clearing & Grubbing
A1040Surv ey
A1220Underground Util it ies
backf ill
A1180Underground Utili t ie s
Inst all ati on
A1190Underground Utili t ies
GC Inspection
A1250Grade S labs
A1210Termi te Tre atmen t
A1170Rough in Plumbing - 1
and Inspection
A1160Masonar y work
A 1150B ac kF il l Fo undation
and Granuler Fi l l F or
t he Grad e S la b
A 1140S he et Wa terp roof in g of
F ou ndation &
Insp ec tion
A1120Fou ndation Post
Inspec tion
A1110Pl ace Concre te for
Fou ndation and Precast
St ai rs
A1100Surv ey & Excav ation
f or Foundat ion
A13 30Inst al l Joi st and Lay
Decking- 1st Floor
A1230Frame and Inwall
Blocking 1st Floor
A1200Steel Column and
Beam Erection
A2230Complete Masonary Work
A2220Spray Fire Proof ing
A2130Ext erior Fra ming
Insp ec tion
A 2110E xt erior Door s &
W indows In stall at io n
A 19 00Inst all Sheat hing
A1640Lay Roo f Dec king
A 16 30I nst all Roof J oist / t rus ses
A 16 20Inst all P recas t S tai r
A2100Roof n aili ng
A2090PVC Roof ing
A2010Roof E xpansion Joints
A14 80Frame and In wall
Bl ocking - 2nd Floor
A1890Flagpoles
A1850Inst all Lou v ers
A1840Inst al l Signage &
Marquee sign
A1830Water Proof Membrane
Marquee Sign
A1820Alumin iu m Cano pies
A1810Fiber Cement S liding
A1800ACM W al l Pa nels
A1240Com plete Exter ior Brick
A2240Interior Framing
Insp ection
A2000Conduct Rough- in
Securi t y,
Com municatio n, F i re
A12 80Rough-in plumbi ng - 2
A1970Rough-in Sec uri ty ,
Com municatio n, F i re
Alarm
A 17 80Rough-in elect rical
A 13 00Rough-in HVA C
A2250Place 1s t F loor
Concrete
A1490Conduct rou gh -in F ire Spr inkler Sys term
Insp ec tion
A1880Conduct Rough- in
Elect ri cal In sp ect ion
A 13 20Rough-in F i re Spr in klerS ys tem
A 13 10Conduct rou gh -in
HVA C insp ect ion
A 12 90Conduct Rough- in P lumbing - 2
Insp ec tion
A1270Elev ator Inst allation
A1260Water proof in g Elev ator Pi t
A13 70Conduct Insulation
Inspection
A1360Place Roof Insulati on
A1350Place 2nd Floor wall &
Slab Insulati on
A1340Place 1s t F loor wal l
Insulation
A1430Tap e and Floa t 2 nd
Floor Dry wal l
A1420Inst all 2nd Flo or
Ov erhea d Dry wal l
A 14 10I nst all 2nd Flo or
Dry wall
A 13 90Inst all 1st Floor
Ov erhead Dry wal l
A 13 80Inst all 1st Floor
Dry wall
A 21 50Inst all I nterior Door s
and W in dows
A 14 00Tap e and Floa t 1 st
F loor Dry wal l
A1950Interior Painting (Top
Coat )
A1500Prim e Coat (Paint)
A 22 10Misc Stee l
A21 80Ban ners
A2170Wall Padding and
Display Cases
A2160Wall Graphics
A1920Exterior Painti ng (Top Coat )
A1730Inst all Stage Flooring
A1870Wall and ACT Panels
Inst al lation
A 14 40W at erproof Membrane
stag e/platf orm
A2140Stage Curtains, Folding Stages, and
Cubicle Curtains
A2120Operable Parti tions
A1930Window Treatments
A1470Wood Shelv ing
A1460Mil lwork & W indow S ill
A22 00Fi nal P lumbing
Inspection
A1520Final P lumbing
Inst al lation 2nd Floor
A1510Final P lumbing
Inst al lation 1st Floor
A 18 60F inal E lectr ic al
Inspec tion
A15 50Fi nal S ecurity ,
Communications , Fi re
alarm & Ins pection
A1540Complete 2nd F loor
Circuit S erv ice Panel
A1530Complete 1st Floor
Circuit t o S erv ice
Panel
A 17 90Com plete Fire
S pr inkler S ys tem a nd
I nsp ec tion
A 15 80Conduct HVA C
Insp ec tion
A 15 70Com pl et e 2nd F lo or
HVA C
A15 60Complete 1st Floor
HVA C
A2260Hollow metal, W ood Doors, Toilet P art itions
& A ccessories,FEC
A1600VCT
A 21 90Carp et
A19 10Outdoor Basket ball and Lockers
A 19 60Colum n Cov ers
A 17 60K i ln
A17 50Foo d S erv ice
Equ ipment
A1740Residental Appliances
A1610Expansion Joints and
Caulking
A1590Water proof ing & Ceramic Til e
installation
A1660SIte Concrete
Aggregate
A1980Traf f i c Coatings
A1680Fencing
A1670Landsc ape & Ir rigation
A1650Asphalt Pav ing & Curb
A19 90Fi nal compl et ion and
Handov er to Client
A1940Architect Final
Inspection
A1770Workoff A rchi tect
Punch List
A1720Architect Pre Final
Inspection
A1710Com plete Punch List
Items of GC
A1700Cleanu p for occup anc y
A1690Com plete f inal
inspection f or
cert if i ca te o f
Abhishek Singh Activity Network Layout
Activity IDActivity Name Page 1 of 2 © Oracle Corporation
Project: CE 592 Porters NeckWBS: CE 592.11 Pre Construction
WBS: CE 592.2 Site Work
WBS: CE 592.3 Foundation
WBS: CE 592.4 Framing and Dry In
WBS: CE 592.5 Exterior Finishes
WBS: CE 592.6 Utility Rough & Complete Concrete
WBS: CE 592.7 Interior Finishes
WBS: CE 592.8 Landscaping & Grounds Work
WBS: CE 592.9 Close Out
WBS: CE 592.7.1 Insulation
WBS: CE 592.7.2 Dry Wall
WBS: CE 592.7.3 Paint, Panels, Stage Floor ing
WBS: CE 592.7.4 Cabinets
WBS: CE 592.7.5 Finish Plumbing
WBS: CE 592.7.6 Finish Electrical
WBS: CE 592.7.7 Finish HVAC and Fire Sprinkler System
WBS: CE 592.7.8 Carpet, Tile, and Appliances
Abhishek Singh Activity Network Layout
Activity IDActivity Name Page 2 of 2 © Oracle Corporation
Activity ID Activity Name
CE 592 Porters NeckCE 592 Porters Neck
CE 592.11 Pre ConstructionCE 592.11 Pre ConstructionA2020 Notice to Proceed
A2030 Obtain Permits
A2050 Develop Bill of Materials
A2060 Procurement of Materials
A2070 Organize crew and Schedule Equipment
A2080 Mobilize to Project Site
CE 592.2 Site WorkCE 592.2 Site WorkA1040 Survey
A1050 Clearing & Grubbing
A1060 Underground Utilties Locator 811
A1070 Erosion Control and Temporary Road
A1080 Rough Grading of the site
A1090 SIte Office and Install Temporary Power service
A1130 Underground Utilities Excavation
A1450 SWPP & Retainage Pond
CE 592.3 FoundationCE 592.3 FoundationA1100 Survey & Excavation for Foundation
A1110 Place Concrete for Foundation and Precast Stairs
A1120 Foundation Post Inspection
A1140 Sheet Waterproofing of Foundation & Inspection
A1150 BackFill Foundation and Granuler Fill For the Grade Slab
A1160 Masonary work
A1170 Rough in Plumbing - 1 and Inspection
A1210 Termite Treatment
A1250 Grade Slabs
CE 592.4 Framing and Dry InCE 592.4 Framing and Dry InA1200 Steel Column and Beam Erection
A1230 Frame and Inwall Blocking 1st Floor
A1330 Install Joist and Lay Decking- 1st Floor
CE 592.5 Exterior FinishesCE 592.5 Exterior Finishes
CE 592.6 Utility Rough & Complete ConcreteCE 592.6 Utility Rough & Complete ConcreteA1280 Rough-in plumbing - 2
A1300 Rough-in HVAC
A1780 Rough-in electrical
A1970 Rough-in Security, Communication, Fire AlarmA2000 Conduct Rough-in Security, Communication, Fire Alarm Inspection
A2240 Interior Framing Inspection
CE 592.7 Interior FinishesCE 592.7 Interior FinishesCE 592.7.1 InsulationCE 592.7.1 Insulation
A1340 Place 1st Floor wall Insulation
A1350 Place 2nd Floor wall & Slab Insulation
A1360 Place Roof Insulation
A1370 Conduct Insulation Inspection
CE 592.7.2 Dry WallCE 592.7.2 Dry Wall
A1380 Install 1st Floor Drywall
A1390 Install 1st Floor Overhead Drywall
1 2 0 0 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3J F M A May 2017 J July 2017 A S O N D J F M A May 2018 J July 2018
19-Jul-18 05:00 PM, CE 592 Porters Neck
24-Jan-17 05:00 PM, CE 592.11 Pre Construction
Notice to Proceed, 02-Jan-17 08:00 AM
Obtain Permits
Develop Bill of Materials
Procurement of Materials
Organize crew and Schedule Equipment
Mobilize to Project Site22-Mar-17 05:00 PM, CE 592.2 Site Work
Survey
Clearing & Grubbing
Underground Utilties Locator 811
Erosion Control and Temporary Road
Rough Grading of the site
SIte Office and Install Temporary Power service
Underground Utilities Excavation
SWPP & Retainage Pond28-Jul-17 05:00 PM, CE 592.3 Foundation
Survey & Excavation for Foundation
Place Concrete for Foundation and Precast Stairs
Foundation Post Inspection
Sheet Waterproofing of Foundation & Inspection
BackFill Foundation and Granuler Fill For the Grade Slab
Masonary work
Rough in Plumbing - 1 and Inspection
Termite Treatment
Grade Slabs12-Sep-17 05:00 PM, CE 592.4 Framing and Dry In
Steel Column and Beam Erection
Frame and Inwall Blocking 1st Floor
Install Joist and Lay Decking- 1st Floor
05-Jan-18 05:00 PM, CE 592.6 Utility Rough & Complete Concrete
Rough-in plumbing - 2
Rough-in HVAC
Rough-in electrical
Rough-in Security, Communication, Fire AlarmConduct Rough-in Security, Communication, Fire Alarm Inspection
Interior Framing Inspection
11-Jun-18 05:00 PM, CE 592.7 Interior Finishes
26-Jan-18 05:00 PM, CE 592.7.1 Insulation
Place 1st Floor wall Insulation
Place 2nd Floor wall & Slab Insulation
Place Roof Insulation
Conduct Insulation Inspection26-Feb-18 05:00 PM, CE 592.7.2 Dry Wall
Install 1st Floor Drywall
Install 1st Floor Overhead Drywall
Actual Level of Effort
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 1 of 2 TASK filter: Critical.
© Oracle Corporation
Activity ID Activity Name
A1410 Install 2nd Floor Drywall
A1420 Install 2nd Floor Overhead Drywall
A1430 Tape and Float 2nd Floor Drywall
CE 592.7.3 Paint, Panels, Stage FlooringCE 592.7.3 Paint, Panels, Stage Flooring
A1500 Prime Coat (Paint)
A1950 Interior Painting (Top Coat)
CE 592.7.4 CabinetsCE 592.7.4 Cabinets
CE 592.7.5 Finish PlumbingCE 592.7.5 Finish Plumbing
CE 592.7.6 Finish ElectricalCE 592.7.6 Finish Electrical
CE 592.7.7 Finish HVAC and Fire Sprinkler SystemCE 592.7.7 Finish HVAC and Fire Sprinkler System
CE 592.7.8 Carpet, Tile, and AppliancesCE 592.7.8 Carpet, Tile, and Appliances
A1600 VCT
A2260 Hollow metal, Wood Doors, Toilet Partitions & Accessories,FEC
CE 592.8 Landscaping & Grounds WorkCE 592.8 Landscaping & Grounds Work
CE 592.9 Close OutCE 592.9 Close OutA1690 Complete final inspection for certificate of occupancy
A1700 Cleanup for occupancy
A1710 Complete Punch List Items of GC
A1720 Architect Pre Final Inspection
A1770 Workoff Architect Punch List
A1940 Architect Final Inspection
A1990 Final completion and Handover to Client
1 2 0 0 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3J F M A May 2017 J July 2017 A S O N D J F M A May 2018 J July 2018
Install 2nd Floor Drywall
Install 2nd Floor Overhead Drywall
Tape and Float 2nd Floor Drywall06-Apr-18 05:00 PM, CE 592.7.3 Paint, Panels, Stage Flooring
Prime Coat (Paint)
Interior Painting (Top Coat)
11-Jun-18 05:00 PM, CE 592.7.8 Carpet, Tile, and Appliances
VCT
Hollow metal, Wood Doors, Toilet Partitions & Accessories,FEC
19-Jul-18 05:00 PM, CE 592.9 Close Out
Complete final inspection for certificate of occupancy
Cleanup for occupancy
Complete Punch List Items of GC
Architect Pre Final Inspection
Workoff Architect Punch List
Architect Final Inspection
Final completion and Handover to Client,
Actual Level of Effort
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 2 of 2 TASK filter: Critical.
© Oracle Corporation
Description Schedule of Values
General Conditions
Field Supervision 712050.8594
Site Office 26023.66462
Site Access 37985.47965
Temporary Utilities/Storage 72039.044
Site Construction Facilities 15077.4
Small Tools and Equipments 2319.6
Permits 206087.9749
Site Work 0
Grading, Stone, Paving, Utilities, Survey 996739.1637
Paving 445714.4802
Termite Treatment 29471.08695
Concrete 0
Spread Footings 19532.03508
Reinforcment for Spread Footings 1729.31747
Strip Footings 73166.73826
Elevated Slabs 58040.58398
Slab on Grade 147036.1461
Stair Concrete 3497.715562
Site Concrete Aggregate 31374.31318
Site Concrete 129510.2463
Precast Material and Erection 23258.89595
Masonry 0
Masonry (CMU) 515503.6758
Anchor Bolts for Brick Vaneer 14948.33746
Brickwork 378258.3977
Metals 0
Structural and Misc Steel 1123555.409
Misc. Steel 22033.07318
Column Covers 3080.243232
Wood, Plastics and Composites 0
Schedule of Values
Millwork and Window Seals 250853.142
Thermal and Moisture Protection 0
Waterproof Membrane & Sheet Waterproofing 16487.94923
Extensions Joints/Caulking 17009.25128
Roof Nailers 39304.6037
Traffic Coatings 7011.591362
PVC Roofing 281066.6891
ACM Panel 51897.13918
Roof Expansion Joints 8863.866604
Spray Foam Beam Infill 4227.663492
Foam Insulation 90083.63713
Openings 0
Coiling Doors 29168.97
Aluminum Storefront 405798.7106
Louvers 4600.659876
Finishes 0
Dry Wall- Wall 195086.0162
Dry Wall-Ceilings 10092.05739
Framing 116411.6147
Inwall Blocking 21117.16244
Fiber Cement 5481.376711
ACT Ceilings 696611.0167
ACT Wall Panels 19957.42268
Ceramic Tiles 95154.59427
VCT Tile 203550.3401
Carpet Tiling 23863.34958
Stage Flooring 7365.067561
Painting 162529.0394
Wall Graphics 3500.2764
Wall Padding 38184.1942
Window Treatments 14991.68382
Specialities 0
Hollow Metal, Wood Dorrs, Toilet Part, Toilet acc, FEC 314594.342
Signage and Marquee 28821.27588
Basket Ball Goals 7555.626723
Lockers 1571.81601
Banners 780.5249543
Operable Partititon 144278.144
Aluminum Canopies 221214.9128
Flagpoles 14480.31677
Equipment 0
Food Service Equipment 263687.4888
Kiln 5005.395252
Residential Appliances 8690.019542
Stage Curtains, Folding Stages, Cubicle Curtains 23092.49017
Furnishings 0
Wood Shelving 81581.23968
Display Cases 5610.533668
Conveying Equipment 0
Elevators 291362.1747
Fire Supression 0
Spray Fireproofing 521378.7291
Misc Firestopping 226809.0434
Fire Sprinklers 475031.2253
Plumbing 0
Plumbing System Sub-Contract 730668.6974
HVAC 0
HVAC System Sub-Contract 1705812.138
Electrical 0
Electrical System Sub-Contract 444593.0076
Communications 0
Communication System 68444.27975
Electronic Safety and Security 0
Fire Alarm 169870.3472
Security 139083.1143
Exterior Improvements 0
Fencing 40923.52376
Landscaping and Irrigation 420515.6393
CASH FLOW
Activities SOV Work Type 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17General Conditions 516,978$ Self Performed 32,311$ 32,311$ 32,311$ 32,311$ 32,311$ 32,311$ 32,311$ 32,311$ 32,311$ 32,311$ 32,311$ 32,311$ 32,311$ 32,311$ 32,311$ 32,311$ Site work 284,695$ Self Performed 284,695$ Grading and Footing Excavation 444,319$ Self Performed 133,296$ 311,023$ Utility Pipelines 199,935$ Self Performed 119,961$ 79,974$ Foundation 166,970$ Self Performed 166,970$ Steel 894,611$ Sub-Contracted 894,611$ Concrete Slab 246,949$ Sub-Contracted 49,390$ 197,559$ Caulking 12,706$ Sub-Contracted 12,706$ Masonary 620,758$ Sub-Contracted 248,303$ 372,455$ H.V.A.C 1,274,271$ Sub-Contracted 127,427$ 318,568$ 318,568$ 318,568$ 191,141$ Plumbing 736,769$ Sub-Contracted 221,031$ 294,708$ 221,031$ Electrical 353,999$ Sub-Contracted 106,200$ 247,799$ Elevator 217,653$ Sub-Contracted 217,653$ Exterior Finishings 1,183,747$ Sub-Contracted 591,874$ 591,874$ Brick Veneer 951,998$ Sub-Contracted 380,799$ 571,199$ Roof 303,662$ Sub-Contracted 242,929$ 60,732$ Partition walls 145,297$ Sub-Contracted 58,119$ 36,324$ 36,324$ 14,530$ Dry Wall 209,668$ Sub-Contracted 146,767$ 62,900$ Speciality Rough-ins 729,034$ Sub-Contracted 218,710$ 291,613$ 218,710$ Interior finishes 1,256,042$ Sub-Contracted 125,604$ 62,802$ 125,604$ 502,417$ 314,010$ 125,604$ Door and Windows 453,716$ Sub-Contracted 45,372$ 90,743$ 45,372$ 272,230$ Paint 147,507$ Sub-Contracted 44,252$ 103,255$ Exterior Landscaping 334,828$ Sub-Contracted 284,604$ 50,224$ Hardware 258,876$ Sub-Contracted 194,157$ 64,719$ Miscellaneous 62,809$ Sub-Contracted 3,140$ 6,281$ 53,387$ Kitchen Appliances 274,652$ Sub-Contracted 274,652$ Cleaning 6,378$ Self Performed 6,378$ Final Punch List 117,650$ Self Performed 117,650$
570,263$ 423,308$ 199,281$ 976,312$ 490,879$ 1,598,469$ 1,860,448$ 840,668$ 681,907$ 697,804$ 799,949$ 877,994$ 700,027$ 581,194$ 836,689$ 271,282$ DC as a % of SOV (85%) (1) 484,723$ 359,812$ 169,389$ 829,865$ 417,248$ 1,358,699$ 1,581,380$ 714,568$ 579,621$ 593,134$ 679,956$ 746,295$ 595,023$ 494,015$ 711,186$ 230,590$ COOH as a % of SOV (10%) (2) 57,026$ 42,331$ 19,928$ 97,631$ 49,088$ 159,847$ 186,045$ 84,067$ 68,191$ 69,780$ 79,995$ 87,799$ 70,003$ 58,119$ 83,669$ 27,128$ P+C as a & of SOV (5%) (3) 28,513$ 21,165$ 9,964$ 48,816$ 24,544$ 79,923$ 93,022$ 42,033$ 34,095$ 34,890$ 39,997$ 43,900$ 35,001$ 29,060$ 41,834$ 13,564$ $ paid or spent by the GC 541,750$ 402,143$ 189,317$ 30,696$ 30,696$ 30,696$ 30,696$ 30,696$ 30,696$ 30,696$ 30,696$ 30,696$ 30,696$ 30,696$ 30,696$ 139,892$ $ paid or spent by subs 896,801$ 435,640$ 1,487,850$ 1,736,730$ 767,939$ 617,116$ 632,219$ 729,256$ 803,398$ 634,330$ 521,439$ 764,159$ 117,826$ $ Billed to the client 570,263$ 423,308$ 199,281$ 976,312$ 490,879$ 1,598,469$ 1,860,448$ 840,668$ 681,907$ 697,804$ 799,949$ 877,994$ 700,027$ 581,194$ 836,689$ 271,282$ % Retained by the client (5%) 57,026$ 42,331$ 19,928$ 97,631$ 49,088$ 159,847$ 186,045$ 84,067$ 68,191$ 69,780$ 79,995$ 87,799$ 70,003$ 58,119$ 83,669$ 27,128$ Money Received from client 513,236$ 380,978$ 179,353$ 878,681$ 441,792$ 1,438,622$ 1,674,403$ 756,601$ 613,716$ 628,024$ 719,954$ 790,194$ 630,024$ 523,075$ 753,020$ 244,154$ $ Billed by subs to GC 896,801$ 435,640$ 1,487,850$ 1,736,730$ 767,939$ 617,116$ 632,219$ 729,256$ 803,398$ 634,330$ 521,439$ 764,159$ 117,826$ % Retained by GC on Sub (5%) 89,680$ 43,564$ 148,785$ 173,673$ 76,794$ 61,712$ 63,222$ 72,926$ 80,340$ 63,433$ 52,144$ 76,416$ 11,783$ Total amount of money paid to sub by GC 807,121$ 392,076$ 1,339,065$ 1,563,057$ 691,145$ 555,405$ 568,997$ 656,330$ 723,059$ 570,897$ 469,295$ 687,743$ 106,044$ Net Paid or spent by GC -$ 541,750 $ 111,093 $ 191,660 $ 148,658 $ 40,864 $ 19,020 $ 68,862 $ 80,651 $ 34,761 $ 27,616 $ 28,332 $ 32,928 $ 36,440 $ 28,432 $ 23,084 -$ 74,615 $ 364,287Cumulative of net paid by GC -$ 541,750 -$ 430,656 -$ 238,996 -$ 90,338 -$ 49,474 -$ 30,454 $ 38,408 $ 119,058 $ 153,819 $ 181,435 $ 209,767 $ 242,695 $ 279,135 $ 307,567 $ 330,651 $ 256,036 $ 620,324
GC is going to submit the bills at end of every month and GC will get paid after one month of the billing.Subcontractor will submit their bill at end of each month and will get paid by GC after one month of billing.Retainage will be 5% for the GC and Subcontractor.
-$ 600,000
-$ 400,000
-$ 200,000
$ 0
$ 200,000
$ 400,000
$ 600,000
$ 800,000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Series1
5.3 Value Engineering
(1) Acoustic Ceiling Tiles1: Design recommends Armstrong "School Zone" ceiling tiles. Black Box recommends Armstrong “Cirrus” Ceiling Tiles. Similar performance specifications which include sound absorption, reflectance, Fire Rating, Humidity & Sag ratings. Cirrus has longer manufacturer warranty of 15 years when compared to “School Zone’s 10-year warranty. Hence it is more durable and required less repairs/replacement as compared to “School Zone”. Additionally, Cirrus is composed of 86% recycled material, while School Zone contains only 57% recycled material. Hence, it’s a more sustainable option.
Material cost difference ~10% increase. Hence net increase in total cost of construction activity is much lesser considering same labor & equipment cost required to install similar product. Return on additional investment over span of additional 5 years (Increase in product life by 50%) yields better result.
(2) Energy Star Certification: ENERGY STAR certified buildings save energy, save money, and help protect the environment by generating fewer greenhouse gas emissions than typical buildings. To be certified as ENERGY STAR, a building must meet strict energy performance standards set by EPA. Specifically, to be eligible for ENERGY STAR certification, a building must earn an ENERGY STAR score of 75 or higher, indicating that it performs better than at least 75 percent of similar buildings nationwide. The ENERGY STAR score accounts for differences in operating conditions, regional weather data, and other important considerations.
We assist our patrons with obtaining Energy Star Certification for our finished product, should they choose to obtain it. We have commissioned several Energy star buildings and our staff are well seasoned with strict standards required.
(3) Use of tank-less water heater instead of conventional “tanked” water heater, which are highly energy efficient as compared with their “tanked” counterparts. Studies suggest around 40-50% energy conservation possible when using tank less water heaters as they provide hot water on demand without having to constantly maintain 50-60 gallons of hot water in tanks.
We will also provide Eemax AutoBooster to further enhance boiler efficiency. This would reduce the number of boilers units required, and hence further reduce energy costs and hence increase overall efficiently. This upgrade is included as part of our base bid, should the patron wish to authorize this value engineering suggestion.
(4) Provide Carbon Monoxide Detectors, especially in confined spaces such as HVAC rooms. Carbon monoxide (CO) is a deadly, colorless, odorless, and poisonous gas. The incomplete burning of fuels produces the gas. A carbon monoxide detector or CO detector is a device that detects the presence of the gas before it reaches dangerous levels. An audible alarm will sound, alerting you to evacuate, or to ventilate the area. Time is of the essence, and so not responding to the alarm can be deadly especially in sensitive buildings such as elementary schools.
1 https://www.armstrongceilings.com/commercial/en-us/commercial-ceilings-walls/cirrus-square-lay-in-and-tegular-ceiling-tiles.html
(5) Motion Sensor/ Occupancy Sensor Light Switches: Black Box Construction highly recommends motion sensor light switches in all Class rooms and office rooms. Motion Sensors monitor the presence of activity inside the room and automatically turns off the lights when the room is empty/ has no activity. This in turn saves energy.
(6) Replace conventional Fluorescent lamps with LEDs. Despite a higher initial investment with LED bulbs, their long-life span as much as four times to that of CFLs (Compact Fluorescent Lamps) and as much as 25 times to that of incandescent lamps provides a much higher return on investment over the product lifecycle, through energy savings. LED’s consume much lesser energy and last much longer than their counterparts. Typical 20-year life cycle savings for a LED lamps is around ~$250. And multiplying that with the number of LED lamps (more than 100 in this project) is $25,000/- over life cycle. Which is a very reasonable investment.
(7) Retrofitting Dry Storm Water Ponds with sediment fore bay. Sediment fore bay in a pond makes dredging quicker and easier since the sediment is confined to a small space. Hence a lower maintenance cost and frequency than conventional ponds. Can retrofit this further to "Bio Pond" by planting Native plants and wildflowers, promoting nutrient uptake, and stimulating ecosystem development. Bio Pond has a much higher filtration capacity.
Code
Number
of Crew Crew
Duration
(days) Quantity Unit Mat. Labor. Equip. Sub. Materials Labor Equip. Sub.
Total Activity
Cost
Footings - - - - - - - - - -
Spread Footings 03 30 53.40 3825 1 C-14C 1.5 61 C.Y. $207.00 $120.00 $0.73 - $12,627.00 $7,320.00 $44.53 $0.00 $19,991.53
Reinforcment for Spread Footings 03 21 11.60 0500 4 1 Rodman 2 1 Ton $960.00 $810.00 - - $960.00 $810.00 $0.00 $0.00 $1,770.00
Strip Footings 03 30 53.40 3935 1 C-14L 7 368 C.Y. $125.00 $78.50 $0.58 - $46,000.00 $28,888.00 $0 $0.00 $74,888.00
Elevated Slabs 03 30 53.40 4650 1 C14-E 5 300 C.Y. $129.00 $68.50 $0.52 - $38,700.00 $20,550.00 $156.00 $0.00 $59,406.00
Slab on Grade 03 30 53.40 4650 1 C14-E 12.5 760 C.Y. $129.00 $68.50 $0.52 - $98,040.00 $52,060.00 $395.20 $0.00 $150,495.20
Stair Concrete 03 41 23.50 0700 1 C-12 1 4 Flights $685.00 $163.00 $47.00 - $2,740.00 $652.00 $188.00 $0.00 $3,580.00
Site Concrete Aggregate 32 06 10.10 0450 2 B-18 8 37,340 S.F. $0.47 $0.37 $0.02 - $17,549.80 $13,815.80 $746.80 $0.00 $32,112.40
Site Concrete 33 06 10.10 0310 8 B-24 9.5 37,340 S.F. $1.79 $1.76 - - $66,838.60 $65,718.40 $0.00 $0.00 $132,557.00
$283,455.40 $189,814.20 $1,530.53 $0.00 $474,800.13
$238,782.83 $159,899.48 $1,289.32 $0.00 $399,971.63
Total
Detailed Estimate: Concrete
Total
Adjusted
Values Adjusted for January 2017
Unit Cost Total Cost
Code
Number
of Crew Crew
Duration
(days) Quantity Unit Mat. Labor. Equip. Sub. Materials Labor Equip. Sub.
Total Activity
Cost
CMU Masonry 04 22 10.28 0300 5 D8 36 63,570 S.F. $3.53 $4.77 - - $224,402.10 $303,228.90 $527,631.00
$189,036.33 $255,440.03 $0.00 $444,476.35
Code
Number
of Crew Crew
Duration
(days) Quantity Unit Mat. Labor. Equip. Sub. Materials Labor Equip. Sub.
Total Activity
Cost
Anchor Bolts for Brick Vaneer 03 15 19.10 0180 4 1 Carp 4 300 Sets $30.50 $20.50 - - $9,150.00 $6,150.00 $15,300.00 $7,707.96 $5,180.76
Brick (Utility) 04 21 13.13 3350 5 D-8 23 40,540 S.F. $4.78 $4.77 - - $193,781.20 $193,375.80 $387,157.00 $163,241.28 $162,899.77
$202,931.20 $199,525.80 $0.00 $0.00 $402,457.00
$170,949.24 $168,080.53 $0.00 $0.00 $339,029.78
Detailed Estimate: Masonry
Adjusted
Total
Adjusted
Values Adjusted for January 2017
Unit Cost Total Cost
Unit Cost Total Cost
Code
Number
of Crew Crew
Duration
(days) Quantity Unit Mat. Labor. Equip. Sub. Materials Labor Equip. Sub.
Total Activity
Cost
Heavy Duty Asphalt Pavement 32 12 16.14 0050 1 B-25C 6 50,000 S.F. $3.57 $0.23 $0.27 - $178,500.00 $11,500.00 $13,500.00 $203,500.00
Light Duty Asphalt Pavement 33 12 16.14 0035 1 B-25C 8 70,000 S.F. $3.11 $0.23 $0.27 - $217,700.00 $16,100.00 $18,900.00 $252,700.00
$396,200.00 $27,600.00 $32,400.00 $0.00 $456,200.00
$333,758.88 $23,250.24 $27,293.76 $0.00 $384,302.88
Unit Cost Total Cost
Detailed Estimate: Paving
Values Adjusted for January 2017
TotalAdjusted
Total
Description Crew Daily Output Unit Quantity Material Labor Equipment Total ($) Duration Schedule
Termite Treatment 13 x 1 Skwk 30,780.00 S.F 61,560.0 $20,315 $9,850 $0 $30,164 2.0 2
$20,315 $9,850 $0 $30,164 2 Days
$17,113.19 $8,297.30 $0.00 $25,410.49
Detailed Estimate: Termite Treatment
Total
Adjusted Total
Values Adjusted for January 2017
Total Cost of Site Work
Description Material Labor Equipment Cost
Grading and Footing Excavation $0.00 $54,044.92 $75,372.86 $129,417.79
Electrical In Concrete $15,780.25 $38,059.07 $0.00 $53,839.32
Interior Water Piping $18,562.57 $32,473.21 $0.00 $51,035.78
Exterior Water Piping $14,464.92 $3,199.83 $339.16 $18,003.90
Storm Water Piping $67,623.39 $75,393.30 $18,823.10 $161,839.79
Sanitary Sewer $2,449.08 $2,150.41 $0.00 $4,599.49
Utility Excavation $17,418.22 $3,082.79 $0.00 $20,501.01
Utility Backfill $23,328.24 $4,390.02 $0.00 $27,718.26
Utility Bedding $103,801.42 $26,866.25 $9,891.66 $140,559.33
Granular Fill $18,576.27 $8,403.55 $884.58 $27,864.40
Rip Rap $1,402.86 $3,228.80 $1,030.99 $5,662.65
Retention Pond $0.00 $66,044.27 $147,194.40 $213,238.67
Total $283,407.21 $317,336.42 $253,536.76 $854,280.39
Adjusted Total $285,107.65 $319,240.44 $255,057.98 $859,406.07
Values Adjusted for January 2017
Summary of Site Work
Description SOV
Grading and Footing Excavation $150,999.34
Electrical In Concrete $62,817.50
Interior Water Piping $59,546.45
Exterior Water Piping $21,006.21
Storm Water Piping $188,828.00
Sanitary Sewer $5,366.49
Utility Excavation $23,919.74
Utility Backfill $32,340.53
Utility Bedding $163,998.84
Granular Fill $32,511.03
Rip Rap $6,606.94
Retention Pond $248,798.09
Site Work Grading and ExcavationMaterial labor Equipment cost Amount Mateiral Labor Equipment Total Cost Productivity Duration Crew
Clearing Trees $0.00 $745.00 $2,525.00 $3,270.00 Per Acre 13.09 Acres $0.00 $9,752.05 $33,052.25 $42,804.30 16 Hours/Acre 209.44 Hours B-10MRough Grading $0.00 $1,950.00 $2,050.00 $4,000.00 /100000SF 777750 SF $0.00 $15,166.13 $15,943.88 $23,607.36 44.44 Hours/100000 345.63 Hours B-11L
$0.00 $2,695.00 $4,575.00 Total: $0.00 $24,918.18 $48,996.13 $66,411.66 555.07 Hours$0.00 $19,959.27 $39,245.53 $53,195.24
17.35 Days Finish Grading $0.00 $1.76 $1.84 $3.60 /SY 20000 SY $0.00 $35,200.00 $36,800.00 $72,000.00 0.008 Hours 160.00 Hours B-11L
Total: $0.00 $35,200.00 $36,800.00 $72,000.00 6.67 Days$0.00 $28,194.94 $29,476.52 $57,671.46
Footing Excavations Material Labor Equipment Cost For each BCY Amount BCY Material Labor Equipment Total Cost ProductivitySpread Footing F1
(B,6.5) $0.00 $6.20 $7.00 $13.20 0.907 BCY $0.00 $5.62 $6.35 $11.97 0.138 Hours Per BCY 0.13 Hours B-12E(B,13) $0.00 $6.20 $7.00 $13.20 0.907 BCY $0.00 $5.62 $6.35 $11.97 0.138 Hours Per BCY 0.13 Hours B-12E(B.3,13) $0.00 $6.20 $7.00 $13.20 0.907 BCY $0.00 $5.62 $6.35 $11.97 0.138 Hours Per BCY 0.13 Hours B-12E(D.9,2) $0.00 $6.20 $7.00 $13.20 0.907 BCY $0.00 $5.62 $6.35 $11.97 0.138 Hours Per BCY 0.13 Hours B-12E(F.4,12.5) $0.00 $6.20 $7.00 $13.20 0.907 BCY $0.00 $5.62 $6.35 $11.97 0.138 Hours Per BCY 0.13 Hours B-12E(F.4,14) $0.00 $6.20 $7.00 $13.20 0.907 BCY $0.00 $5.62 $6.35 $11.97 0.138 Hours Per BCY 0.13 Hours B-12ESpread Footing F2(B,8.5) $0.00 $6.20 $7.00 $13.20 1.778 BCY $0.00 $11.02 $12.45 $23.47 0.138 Hours Per BCY 0.25 Hours B-12E(B,9) $0.00 $6.20 $7.00 $13.20 1.778 BCY $0.00 $11.02 $12.45 $23.47 0.138 Hours Per BCY 0.25 Hours B-12E(B,10.4) $0.00 $6.20 $7.00 $13.20 1.778 BCY $0.00 $11.02 $12.45 $23.47 0.138 Hours Per BCY 0.25 Hours B-12E(B,12) $0.00 $6.20 $7.00 $13.20 1.778 BCY $0.00 $11.02 $12.45 $23.47 0.138 Hours Per BCY 0.25 Hours B-12E(B,12.6) $0.00 $6.20 $7.00 $13.20 1.778 BCY $0.00 $11.02 $12.45 $23.47 0.138 Hours Per BCY 0.25 Hours B-12E(B.2,7) $0.00 $6.20 $7.00 $13.20 1.778 BCY $0.00 $11.02 $12.45 $23.47 0.138 Hours Per BCY 0.25 Hours B-12E(B.8,10.4) $0.00 $6.20 $7.00 $13.20 1.778 BCY $0.00 $11.02 $12.45 $23.47 0.138 Hours Per BCY 0.25 Hours B-12E(B.8,12) $0.00 $6.20 $7.00 $13.20 1.778 BCY $0.00 $11.02 $12.45 $23.47 0.138 Hours Per BCY 0.25 Hours B-12E(C,13) $0.00 $6.20 $7.00 $13.20 1.778 BCY $0.00 $11.02 $12.45 $23.47 0.138 Hours Per BCY 0.25 Hours B-12E(D.4,10.4) $0.00 $6.20 $7.00 $13.20 1.778 BCY $0.00 $11.02 $12.45 $23.47 0.138 Hours Per BCY 0.25 Hours B-12E(C,13) $0.00 $6.20 $7.00 $13.20 1.778 BCY $0.00 $11.02 $12.45 $23.47 0.138 Hours Per BCY 0.25 Hours B-12E(D.4,10.4) $0.00 $6.20 $7.00 $13.20 1.778 BCY $0.00 $11.02 $12.45 $23.47 0.138 Hours Per BCY 0.25 Hours B-12E(D.4,12) $0.00 $6.20 $7.00 $13.20 1.778 BCY $0.00 $11.02 $12.45 $23.47 0.138 Hours Per BCY 0.25 Hours B-12E(D.6,10.4) $0.00 $6.20 $7.00 $13.20 1.778 BCY $0.00 $11.02 $12.45 $23.47 0.138 Hours Per BCY 0.25 Hours B-12E(D.8,8.5) $0.00 $6.20 $7.00 $13.20 1.778 BCY $0.00 $11.02 $12.45 $23.47 0.138 Hours Per BCY 0.25 Hours B-12E(D.8,9.6) $0.00 $6.20 $7.00 $13.20 1.778 BCY $0.00 $11.02 $12.45 $23.47 0.138 Hours Per BCY 0.25 Hours B-12E(D.8,12) $0.00 $6.20 $7.00 $13.20 1.778 BCY $0.00 $11.02 $12.45 $23.47 0.138 Hours Per BCY 0.25 Hours B-12E(D.8,13) $0.00 $6.20 $7.00 $13.20 1.778 BCY $0.00 $11.02 $12.45 $23.47 0.138 Hours Per BCY 0.25 Hours B-12E(F.1,12) $0.00 $6.20 $7.00 $13.20 1.778 BCY $0.00 $11.02 $12.45 $23.47 0.138 Hours Per BCY 0.25 Hours B-12E(G.4,9) $0.00 $6.20 $7.00 $13.20 1.778 BCY $0.00 $11.02 $12.45 $23.47 0.138 Hours Per BCY 0.25 Hours B-12E(G.4,10) $0.00 $6.20 $7.00 $13.20 1.778 BCY $0.00 $11.02 $12.45 $23.47 0.138 Hours Per BCY 0.25 Hours B-12E(G.4,12.1) $0.00 $6.20 $7.00 $13.20 1.778 BCY $0.00 $11.02 $12.45 $23.47 0.138 Hours Per BCY 0.25 Hours B-12E(J,9) $0.00 $6.20 $7.00 $13.20 1.778 BCY $0.00 $11.02 $12.45 $23.47 0.138 Hours Per BCY 0.25 Hours B-12ESpread Footing F3(B,6) $0.00 $6.20 $7.00 $13.20 2.778 BCY $0.00 $17.22 $19.45 $36.67 0.138 Hours Per BCY 0.38 Hours B-12E(B,8) $0.00 $6.20 $7.00 $13.20 2.778 BCY $0.00 $17.22 $19.45 $36.67 0.138 Hours Per BCY 0.38 Hours B-12E(D.9,3) $0.00 $6.20 $7.00 $13.20 2.778 BCY $0.00 $17.22 $19.45 $36.67 0.138 Hours Per BCY 0.38 Hours B-12E(D.9,4) $0.00 $6.20 $7.00 $13.20 2.778 BCY $0.00 $17.22 $19.45 $36.67 0.138 Hours Per BCY 0.38 Hours B-12E(D.9,5) $0.00 $6.20 $7.00 $13.20 2.778 BCY $0.00 $17.22 $19.45 $36.67 0.138 Hours Per BCY 0.38 Hours B-12E(D.9,6) $0.00 $6.20 $7.00 $13.20 2.778 BCY $0.00 $17.22 $19.45 $36.67 0.138 Hours Per BCY 0.38 Hours B-12E(D.9,7) $0.00 $6.20 $7.00 $13.20 2.778 BCY $0.00 $17.22 $19.45 $36.67 0.138 Hours Per BCY 0.38 Hours B-12E(D.9,9) $0.00 $6.20 $7.00 $13.20 2.778 BCY $0.00 $17.22 $19.45 $36.67 0.138 Hours Per BCY 0.38 Hours B-12E(F.1,10) $0.00 $6.20 $7.00 $13.20 2.778 BCY $0.00 $17.22 $19.45 $36.67 0.138 Hours Per BCY 0.38 Hours B-12E(F.8,8.7) $0.00 $6.20 $7.00 $13.20 2.778 BCY $0.00 $17.22 $19.45 $36.67 0.138 Hours Per BCY 0.38 Hours B-12E(F.9,14) $0.00 $6.20 $7.00 $13.20 2.778 BCY $0.00 $17.22 $19.45 $36.67 0.138 Hours Per BCY 0.38 Hours B-12E(J.9,14) $0.00 $6.20 $7.00 $13.20 2.778 BCY $0.00 $17.22 $19.45 $36.67 0.138 Hours Per BCY 0.38 Hours B-12E(G.1,14) $0.00 $6.20 $7.00 $13.20 2.778 BCY $0.00 $17.22 $19.45 $36.67 0.138 Hours Per BCY 0.38 Hours B-12E(G.6,14) $0.00 $6.20 $7.00 $13.20 2.778 BCY $0.00 $17.22 $19.45 $36.67 0.138 Hours Per BCY 0.38 Hours B-12E(J,11.4) $0.00 $6.20 $7.00 $13.20 2.778 BCY $0.00 $17.22 $19.45 $36.67 0.138 Hours Per BCY 0.38 Hours B-12ESpread Footing F4(F.4,8.7) $0.00 $6.20 $7.00 $13.20 4 BCY $0.00 $24.80 $28.00 $52.80 0.138 Hours Per BCY 0.55 Hours B-12ESpread Footing LF-1 $0.00(B,5)-(B,5.5) $0.00 $6.20 $7.00 $13.20 1.556 BCY $0.00 9.6472 $10.89 $20.54 0.138 Hours Per BCY 0.21 Hours B-12ESpread Footing LF-2(A,11.2)-(A,11.9) $0.00 $6.20 $7.00 $13.20 1.111 BCY $0.00 $6.89 $7.78 $14.67 0.138 Hours Per BCY 0.15 Hours B-12E
Total $0.00 $586.97 $662.71 $1,249.68 13.45 Hours$0.00 $470.16 $530.83 $1,000.99
Strip Footings SF 1 Material Labor Equipment Cost For each BCY Amount BCY Material Labor Equipment Total Cost Productivity Duration CrewFoundation Plan Area A and B $0.00 $6.20 $7.00 $13.20 183 BCY $0.00 $1,134.60 $1,281.00 $2,415.60 0.138 Hours Per BCY 25.254 Hours B-12EFoundation Partial Area B $0.00 $6.20 $7.00 $13.20 20 BCY $0.00 $124.00 $140.00 $264.00 0.138 Hours Per BCY 2.76 Hours B-12EFoundation Plan Area A,B, and C $0.00 $6.20 $7.00 $13.20 41 BCY $0.00 $254.20 $287.00 $541.20 0.138 Hours Per BCY 5.658 Hours B-12EStrip Footings SF 2Foundation Plan Area A and B $0.00 $6.20 $7.00 $13.20 150 BCY $0.00 $930.00 $1,050.00 $1,980.00 0.138 Hours Per BCY 20.7 Hours B-12EFoundation Partial Area B $0.00 $6.20 $7.00 $13.20 105 BCY $0.00 $651.00 $735.00 $1,386.00 0.138 Hours Per BCY 14.49 Hours B-12EFoundation Plan Area C $0.00 $6.20 $7.00 $13.20 209 BCY $0.00 $1,295.80 $1,463.00 $2,758.80 0.138 Hours Per BCY 28.842 Hours B-12EFoundation Plan Area A,B, and C $0.00 $6.20 $7.00 $13.20 82 BCY $0.00 $508.40 $574.00 $1,082.40 0.138 Hours Per BCY 11.316 Hours B-12EStrip Footings SF 3Foundation Plan Area A and B $0.00 $6.20 $7.00 $13.20 21 BCY $0.00 $130.20 $147.00 $277.20 0.138 Hours Per BCY 2.898 Hours B-12EFoundation Plan Area A,B, and C $0.00 $6.20 $7.00 $13.20 1.5 BCY $0.00 $9.30 $10.50 $19.80 0.138 Hours Per BCY 0.207 Hours B-12EStrip Footings SF 4Foundation Partial Area B $0.00 $6.20 $7.00 $13.20 14 BCY $0.00 $86.80 $98.00 $184.80 0.138 Hours Per BCY 1.932 Hours B-12EFoundation Plan Area C $0.00 $6.20 $7.00 $13.20 49 BCY $0.00 $303.80 $343.00 $646.80 0.138 Hours Per BCY 6.762 Hours B-12EFoundation Plan Area A,B, and C $0.00 $6.20 $7.00 $13.20 55 BCY $0.00 $341.00 $385.00 $726.00 0.138 Hours Per BCY 7.59 Hours B-12E
Strip Footings SF 5
Foundation Plan Area A and B $0.00 $6.20 $7.00 $13.20 77 BCY $0.00 $477.40 $539.00 $1,016.40 0.138 Hours Per BCY 10.626 Hours B-12E
Strip Footings SF 7
Foundation Plan Area A and B $0.00 $6.20 $7.00 $13.20 69 BCY $0.00 $427.80 $483.00 $910.80 0.138 Hours Per BCY 9.522 Hours B-12E
Foundation Plan Area A,B, and C $0.00 $6.20 $7.00 $13.20 15 BCY $0.00 $93.00 $105.00 $198.00 0.138 Hours Per BCY 2.07 Hours B-12E
Total: $0.00 $6,767.30 $7,640.50 $14,407.80 150.627 Hours
$0.00 $5,420.56 $6,119.98 $11,540.54
$0.00 $5,890.72 $6,650.81 $12,541.53 37.65675 Hours4.71 Days
Detailed Estimate: Site Work Grading and Excavation
Total Adjusted:
Duration:Total Adjusted
Duration
Total Adjusted Cost:
Total Footing Cost 4 Crews Duration
Breakdown Cost Breakdown
DurationTotal Adjusted:
Duration With 5 Crews
Duration with 3 Crews
Site Work Electrical In Concrete
Item Quantity (LF) Material Labor Equipment Total Cost Material Labor Equipment Total Cost Production Rate Crew Duration
3/4" PVC Conduit 109.57 $0.56 $1.92 $0.00 $2.48 /LF $61.36 $210.37 $0.00 $271.72 0.035 HR/LF 1 Electrician 0.48 Days2" PVC Conduit 3573.91 $1.52 $3.67 $0.00 $5.19 /LF $5,432.35 $13,116.26 $0.00 $18,548.61 0.067 HR/LF 1 Electrician 29.93 Days4" PVC Conduit 4283.48 $3.00 $7.20 $0.00 $10.20 /LF $12,850.43 $30,841.04 $0.00 $43,691.48 0.123 HR/LF 1 Electrician 65.86 Days1 1/4" PVC Innerduct 673.04 $1.00 $2.59 $0.00 $3.59 /LF $673.04 $1,743.18 $0.00 $2,416.23 0.047 HR/LF 1 Electrician 3.95 Days2 1/2" PVC for Duct Bank 375.65 $1.82 $4.27 $0.00 $6.09 /LF $683.69 $1,604.03 $0.00 $2,287.72 0.077 HR/LF 1 Electrician 3.62 Days
Total: $19,700.87 $47,514.89 $0.00 $67,215.76 1 Electrician 103.84 Days
Total Adjusted: $15,780.25 $38,059.07 $0.00 $53,839.32 11 Electricians 9.44 Days
Total Breakdown
Detailed Estimate: Electrical in Concrete
Area A Area B Area C Total M L E Total Duration M L E Total Cost Total Duration
1 1/2" 132 0 132 $0.45 $0.79 $0.00 $1.24 750 daily $59.40 $104.28 $0.00 $163.68 0.18
2" 1386 456 240 2082 $0.68 $0.86 $0.00 $1.54 686 daily $1,415.76 $1,790.52 $0.00 $3,206.28 3.03
3" 72 930 1002 $1.40 $2.34 $0.00 $3.74 430 daily $1,402.80 $2,344.68 $0.00 $3,747.48 2.33
4" 4014 3486 4098 11598 $1.75 $3.13 $0.00 $4.88 350 daily $20,296.50 $36,301.74 $0.00 $56,598.24 33.14
Total: $23,174.46 $40,541.22 $0.00 $63,715.68 38.68
$18,562.57 $32,473.21 $0.00 $51,035.78Total Adjusted:
Detailed Estimate: Interior Plumbing
Interior Plumbing
Pipe DiameterQuantity (LF) Cost Per Unit Total Cost
Site Work Water Piping Not Including Excavation
Item Quantity Material Labor Equipment Total Cost Material Labor Equipment Total Cost Production Rate Crew Duration
4" C900 PVC 187.00 LF $2.73 $3.88 $0.00 $6.61 /LF $510.51 $725.56 $0.00 $1,236.07 0.084 HR/LF B-20A 1.96 Days4" 45 degree Bends C900 PVC 4.00 $42.00 $10.20 $0.00 $52.20 each $168.00 $40.80 $0.00 $208.80 0.24 Hours Each B-20A 0.12 days8" C900 PVC 375.00 LF $8.05 $5.60 $0.00 $13.65 /LF $3,018.75 $2,100.00 $0.00 $5,118.75 0.121 HR/LF B-20A 5.67 Days8" 45 Degree Bends C900 PVC 2.00 $74.50 $11.35 $0.00 $85.85 each $149.00 $22.70 $0.00 $171.70 0.48 Hours Each B-20A 0.12 Days8" 90 Degree Bend C900 PVC 1.00 $144.00 $12.75 $0.00 $156.75 each $144.00 $12.75 $0.00 $156.75 0.3 Hours Each B-20A 0.04 Days14" Steel Casing Pipe 61.00 LF $231.00 $18.00 $6.95 $255.95 /LF $14,091.00 $1,098.00 $423.95 $15,612.95 0.123 HR/LF B-21A 0.94 Days
Total: $18,081.26 $3,999.81 $423.95 $22,505.02 1 of each crew 8.85 Days
Total Adjusted: $14,464.92 $3,199.83 $339.16 $18,026.35
Total Breakdown
Detailed Estimate: Water Piping
Site Work Storm Water Piping Not Including Excavation
Item Quantity Material Labor Equipment Total Cost Material Labor Equipment Total Cost Production Rate Crew Duration
RCPIII 18" 156.00 LF $20.00 $14.60 $2.77 $37.37 /LF $3,120.00 $2,277.60 $432.12 $5,829.72 0.364 HR/LF B-13 7.10 DaysRCP III 24" 713.00 LF $22.00 $19.25 $3.65 $44.90 /LF $15,686.00 $13,725.25 $2,602.45 $32,013.70 0.48 HR/LF B-13 42.78 DaysRCPIII 30" 74.00 LF $38.00 $26.50 $8.50 $73.00 /LF $2,812.00 $1,961.00 $629.00 $5,402.00 0.636 HR/LF B-13 5.88 DaysRCPIII 36" 337.00 LF $59.50 $32.00 $10.40 $101.90 /LF $20,051.50 $10,784.00 $3,504.80 $34,340.30 0.778 HR/LF B-13 32.77 DaysHDPE 6" 249.00 LF $3.00 $4.00 $0.00 $7.00 /LF $747.00 $996.00 $0.00 $1,743.00 0.028 HR/LF B-13 0.87 DaysHDPE 8" 93.00 LF $5.00 $10.00 $0.00 $15.00 /LF $465.00 $930.00 $0.00 $1,395.00 0.031 HR/LF B-13 0.36 DaysHDPE 12" 613.00 LF $9.00 $18.00 $6.95 $25.00 /LF $5,517.00 $11,034.00 $4,260.35 $15,325.00 0.066 HR/LF B-13 5.06 DaysHDPE 15" 379.00 LF $10.00 $30.00 $5.00 $45.00 /LF $3,790.00 $11,370.00 $1,895.00 $17,055.00 0.088 HR/LF B-13 4.17 DaysHDPE 18" 622.00 LF $16.00 $25.00 $6.00 $50.00 /LF $9,952.00 $15,550.00 $3,732.00 $31,100.00 0.1 HR/LF B-13 7.78 DaysHDPE 24" 291.00 LF $20.00 $27.00 $8.00 $55.00 /LF $5,820.00 $7,857.00 $2,328.00 $16,005.00 0.21 HR/LF B-13 7.64 DaysHDPE 30" 588.00 LF $28.00 $30.00 $7.00 $65.00 /LF $16,464.00 $17,640.00 $4,116.00 $38,220.00 0.323 HR/LF B-13 23.74 Days
Total: $84,424.50 $94,124.85 $23,499.72 $198,428.72 1 of each crew 62.05 Days
Total Adjusted: $67,623.39 $75,393.30 $18,823.10 $158,939.92
Total Breakdown
Detailed Estimate: Storm Water Piping
M L E Total Duration M L E Total Duration
RCP 36 630 3 $1.30 $0.23 $0.00 $1.53 300 $819.00 $144.90 $0.00 $963.90 2.10
18 172 3 $1.30 $0.23 $0.00 $1.53 300 $223.60 $39.56 $0.00 $263.16 0.57
24 713 3 $1.30 $0.23 $0.00 $1.53 300 $926.90 $163.99 $0.00 $1,090.89 2.38
30 74 3 $1.30 $0.23 $0.00 $1.53 300 $96.20 $17.02 $0.00 $113.22 0.25
36 55 3 $1.30 $0.23 $0.00 $1.53 300 $71.50 $12.65 $0.00 $84.15 0.18
6 249 3 $0.86 $0.15 $0.00 $1.01 450 $214.14 $37.35 $0.00 $251.49 0.55
8 93 3 $1.30 $0.23 $0.00 $1.53 300 $120.90 $21.39 $0.00 $142.29 0.31
12 613 3 $1.30 $0.23 $0.00 $1.53 300 $796.90 $140.99 $0.00 $937.89 2.04
15 379 3 $1.30 $0.23 $0.00 $1.53 300 $492.70 $87.17 $0.00 $579.87 1.26
18 622 3 $1.30 $0.23 $0.00 $1.53 300 $808.60 $143.06 $0.00 $951.66 2.07
24 291 3 $1.30 $0.23 $0.00 $1.53 300 $378.30 $66.93 $0.00 $445.23 0.97
30 588 3 $1.30 $0.23 $0.00 $1.53 300 $764.40 $135.24 $0.00 $899.64 1.96
Exterior gas Copper 1 1/4 247 1 $0.49 $0.09 $0.00 $0.58 800 $120.87 $22.20 $0.00 $143.07 0.31
Interior Gas Copper 1 1/4 2802 1 $0.49 $0.09 $0.00 $0.58 800 $1,372.98 $252.18 $0.00 $1,625.16 3.50
PVC 4 167 2 $0.60 $0.10 $0.00 $0.70 700 $100.20 $16.70 $0.00 $116.90 0.24
PVC 8 375 2 $1.11 $0.19 $0.00 $1.30 350 $416.25 $71.25 $0.00 $487.50 1.07
Steel 14 61 2 $1.11 $0.19 $0.00 $1.30 350 $67.71 $11.59 $0.00 $79.30 0.17
1 1/2 132 2 $0.56 $0.10 $0.00 $0.66 700 $73.92 $13.20 $0.00 $87.12 0.19
2 2082 2 $0.56 $0.10 $0.00 $0.66 700 $1,165.92 $208.20 $0.00 $1,374.12 2.97
3 1002 2 $0.56 $0.10 $0.00 $0.66 700 $561.12 $100.20 $0.00 $661.32 1.43
4 11598 2 $0.56 $0.10 $0.00 $0.66 700 $6,494.88 $1,159.80 $0.00 $7,654.68 16.57
Sanitary Sewer PVC 4 747 5.5 $1.30 $0.23 $0.00 $1.53 300 $970.67 $171.73 $0.00 $1,142.41 2.49
3/4 110 1.5 $0.52 $0.09 $0.00 $0.61 750 $56.97 $9.86 $0.00 $66.83 0.15
1 1/4 673 1.5 $0.52 $0.09 $0.00 $0.61 750 $349.98 $60.57 $0.00 $410.56 0.90
2 3574 1.5 $0.52 $0.09 $0.00 $0.61 750 $1,858.43 $321.65 $0.00 $2,180.09 4.77
2 1/2 376 1.5 $0.52 $0.09 $0.00 $0.61 750 $195.34 $33.81 $0.00 $229.15 0.50
4 4283 1.5 $0.52 $0.09 $0.00 $0.61 750 $2,227.41 $385.51 $0.00 $2,612.92 5.71
Total: $21,745.80 $3,848.71 $0.00 $25,594.51 55.62
Total Adjusted: $17,418.22 $3,082.79 $0.00 $20,501.01
Per Unit Total
Electrical PVC
Detailed Estimate: Utlities Excavation
Storm sewer
RCPIII
HDPE
Exterior water
Interior water Cast Iron
Utilities Excavation
Utility Type Material Pipe
Diameter (in)
Pipe
Length (Ft)
Excavation
Depth (Ft)
M L E Total Duration M L E Total Duration
RCP 36 630 3 $2.23 $0.42 $0.00 $2.65 135 $1,404.90 $264.60 $0.00 $1,669.50 4.6718 172 3 $2.23 $0.42 $0.00 $2.65 135 $383.56 $72.24 $0.00 $455.80 1.2724 713 3 $2.23 $0.42 $0.00 $2.65 135 $1,589.99 $299.46 $0.00 $1,889.45 5.2830 74 3 $2.23 $0.42 $0.00 $2.65 135 $165.02 $31.08 $0.00 $196.10 0.5536 55 3 $2.23 $0.42 $0.00 $2.65 135 $122.65 $23.10 $0.00 $145.75 0.416 249 3 $1.67 $0.31 $0.00 $1.98 180 $415.83 $77.19 $0.00 $493.02 1.388 93 3 $2.23 $0.42 $0.00 $2.65 135 $207.39 $39.06 $0.00 $246.45 0.6912 613 3 $2.23 $0.42 $0.00 $2.65 135 $1,366.99 $257.46 $0.00 $1,624.45 4.5415 379 3 $2.23 $0.42 $0.00 $2.65 135 $845.17 $159.18 $0.00 $1,004.35 2.8118 622 3 $2.23 $0.42 $0.00 $2.65 135 $1,387.06 $261.24 $0.00 $1,648.30 4.6124 291 3 $2.23 $0.42 $0.00 $2.65 135 $648.93 $122.22 $0.00 $771.15 2.1630 588 3 $2.23 $0.42 $0.00 $2.65 135 $1,311.24 $246.96 $0.00 $1,558.20 4.36
Exterior gas Copper 1 1/4 247 1 $0.38 $0.07 $0.00 $0.45 800 $93.73 $17.27 $0.00 $111.00 0.31Interior Gas Copper 1 1/4 2802 1 $0.38 $0.07 $0.00 $0.45 800 $1,064.76 $196.14 $0.00 $1,260.90 3.50
PVC 4 167 2 $0.56 $0.10 $0.00 $0.66 540 $93.52 $16.70 $0.00 $110.22 0.31PVC 8 375 2 $1.50 $0.28 $0.00 $1.78 200 $562.50 $105.00 $0.00 $667.50 1.88Steel 14 61 2 $1.50 $0.28 $0.00 $1.78 200 $91.50 $17.08 $0.00 $108.58 0.31
1 1/2 132 2 $0.75 $0.14 $0.00 $0.89 400 $99.00 $18.48 $0.00 $117.48 0.332 2082 2 $0.75 $0.14 $0.00 $0.89 400 $1,561.50 $291.48 $0.00 $1,852.98 5.213 1002 2 $0.75 $0.14 $0.00 $0.89 400 $751.50 $140.28 $0.00 $891.78 2.514 11598 2 $0.75 $0.14 $0.00 $0.89 400 $8,698.50 $1,623.72 $0.00 $10,322.22 29.00
Sanitary Sewer PVC 4 747 5.5 $1.50 $0.28 $0.00 $1.78 200 $1,120.01 $209.07 $0.00 $1,329.07 3.733/4 110 1.5 $0.57 $0.11 $0.00 $0.68 530 $62.45 $12.05 $0.00 $74.50 0.21
1 1/4 673 1.5 $0.57 $0.11 $0.00 $0.68 530 $383.63 $74.03 $0.00 $457.67 1.272 3574 1.5 $0.57 $0.11 $0.00 $0.68 530 $2,037.13 $393.13 $0.00 $2,430.26 6.74
2 1/2 376 1.5 $0.57 $0.11 $0.00 $0.68 530 $214.12 $41.32 $0.00 $255.44 0.714 4283 1.5 $0.57 $0.11 $0.00 $0.68 530 $2,441.58 $471.18 $0.00 $2,912.77 8.08
Total: $29,124.17 $5,480.73 $0.00 $34,604.90 96.80
Total Adjusted: $23,328.24 $4,390.02 $0.00 $27,718.26
Per Unit Total
Electrical PVC
Detailed Estimate: Utilities Backfill
Storm sewer
RCPIII
HDPE
Exterior water
Interior water Cast Iron
Utilities Backfill
Utility Type Material Pipe
Diameter (in)
Pipe
Length (Ft)
Excavation
Depth (Ft)
Utility BeddingLocation Depth Volume Material Labor Equipment Cost Materials Labor Equipment Cost Crew Productivity Duration
RCP 630 LF 6 Inches 630.00 CY $25.50 $6.60 $2.43 $34.53 /CY $16,065.00 $4,158.00 $1,530.90 $21,753.90 B-6 0.16 hr/CY 100.80 HoursRCP 172 LF 6 Inches 172.00 CY $25.50 $6.60 $2.43 34.53 /CY $4,386.00 $1,135.20 $417.96 $5,939.16 B-6 0.16 hr/CY 27.52 HoursRCP 713 LF 6 Inches 713.00 CY $25.50 $6.60 $2.43 34.53 /CY $18,181.50 $4,705.80 $1,732.59 $24,619.89 B-6 0.16 hr/CY 114.08 HoursRCP 74 LF 6 Inches 74.00 CY $25.50 $6.60 $2.43 34.53 /CY $1,887.00 $488.40 $179.82 $2,555.22 B-6 0.16 hr/CY 11.84 HoursRCPIII 55 LF 6 Inches 55.00 CY $25.50 $6.60 $2.43 34.53 /CY $1,402.50 $363.00 $133.65 $1,899.15 B-6 0.16 hr/CY 8.80 HoursRCPIII 249 LF 6 Inches 249.00 CY $25.50 $6.60 $2.43 34.53 /CY $6,349.50 $1,643.40 $605.07 $8,597.97 B-6 0.16 hr/CY 39.84 HoursRCPIII 93 LF 6 Inches 93.00 CY $25.50 $6.60 $2.43 34.53 /CY $2,371.50 $613.80 $225.99 $3,211.29 B-6 0.16 hr/CY 14.88 HoursRCPIII 613 LF 6 Inches 613.00 CY $25.50 $6.60 $2.43 34.53 /CY $15,631.50 $4,045.80 $1,489.59 $21,166.89 B-6 0.16 hr/CY 98.08 HoursRCPIII 379 LF 6 Inches 379.00 CY $25.50 $6.60 $2.43 34.53 /CY $9,664.50 $2,501.40 $920.97 $13,086.87 B-6 0.16 hr/CY 60.64 HoursRCPIII 622 LF 6 Inches 622.00 CY $25.50 $6.60 $2.43 34.53 /CY $15,861.00 $4,105.20 1511.46 $21,477.66 B-6 0.16 hr/CY 99.52 Hours RCPIII 291 LF 6 Inches 291.00 CY $25.50 $6.60 $2.43 34.53 /CY $7,420.50 $1,920.60 707.13 $10,048.23 B-6 0.16 hr/CY 46.56 HoursHDPE 588 LF 6 Inches 588.00 CY $25.50 $6.60 $2.43 34.53 /CY $14,994.00 $3,880.80 1428.84 $20,303.64 B-6 0.16 hr/CY 94.08 Hours4" C900 PVC 167 LF 6 Inches 167.00 CY $25.50 $6.60 $2.43 34.53 /CY 4258.5 1102.2 405.81 $5,766.51 B-6 0.16 hr/CY 26.72 Hours8" C900 PVC 375 LF 6 Inches 375.00 CY $25.50 $6.60 $2.43 34.53 /CY 9562.5 2475 911.25 $12,948.75 B-6 0.16 hr/CY 60.00 Hours14" Steel Casing Pipe 61 LF 6 Inches 61.00 CY $25.50 $6.60 $2.43 34.53 /CY 1555.5 402.6 148.23 $2,106.33 B-6 0.16 hr/CY 9.76 Hours
Total: $129,591.00 $33,541.20 $12,349.26 $175,481.46 813.12
Total Adjusted: $103,801.42 $26,866.25 $9,891.66 $140,559.33
Cost Breakdown
Size
Detailed Estimate: Utility Bedding
Granular Fill (Slab on Grade)
Location Area Materials Labor Equipment Cost Materials Labor Equipment Total Cost Productivity Crew Duartion
Plan Area A (D.9-H),(3-13) 8405 sf $0.42 $0.19 $0.02 0.63 $/SF $3,530.10 $1,596.95 $168.10 5295.15 $ 0.005 hr/SF B-37 42.025 HoursPlan Area A (B-E),(5-13) 10790 sf $0.42 $0.19 $0.02 0.63 $/SF $4,531.80 $2,050.10 $215.80 6797.7 $ 0.005 hr/SF B-37 53.95 HoursPlan Area A (B.2-D.9),(2-5) 4980 sf $0.42 $0.19 $0.02 0.63 $/SF $2,091.60 $946.20 $99.60 3137.4 $ 0.005 hr/SF B-37 24.9 HoursPlan Area B (F-F.9),(14,16) 2916 sf $0.42 $0.19 $0.02 0.63 $/SF $1,224.72 $554.04 $58.32 1837.08 $ 0.005 hr/SF B-37 14.58 HoursPlan Area B (E-F),(13-16) 960 sf $0.42 $0.19 $0.02 0.63 $/SF $403.20 $182.40 $19.20 604.8 $ 0.005 hr/SF B-37 4.8 HoursPlan Area B (C-E),(13-15) 2400 sf $0.42 $0.19 $0.02 0.63 $/SF $1,008.00 $456.00 $48.00 1512 $ 0.005 hr/SF B-37 12 HoursPlan Area B (D-E),(15-16) 1785 sf $0.42 $0.19 $0.02 0.63 $/SF $749.70 $339.15 $35.70 1124.55 $ 0.005 hr/SF B-37 8.925 HoursPlan Area C (M-N),(9.5,12.1) 336 sf $0.42 $0.19 $0.02 0.63 $/SF $141.12 $63.84 $6.72 211.68 $ 0.005 hr/SF B-37 1.68 HoursPlan Area C (L-M),(8.6-14) 10988 sf $0.42 $0.19 $0.02 0.63 $/SF $4,614.96 $2,087.72 $219.76 6922.44 $ 0.005 hr/SF B-37 54.94 HoursPlan Area C (K-L),(9-13.8) 1022 sf $0.42 $0.19 $0.02 0.63 $/SF $429.24 $194.18 $20.44 643.86 $ 0.005 hr/SF B-37 5.11 HoursPlan Area C (J.5-K),(8.6-14) 902 sf $0.42 $0.19 $0.02 0.63 $/SF $378.84 $171.38 $18.04 568.26 $ 0.005 hr/SF B-37 4.51 HoursPlan Area A,B,C (J-J.5),(8.7-14) 3854 sf $0.42 $0.19 $0.02 0.63 $/SF $1,618.68 $732.26 $77.08 2428.02 $ 0.005 hr/SF B-37 19.27 HoursPlan Area A,B,C (G.4-J),(10.1-14) 1674 sf $0.42 $0.19 $0.02 0.63 $/SF $703.08 $318.06 $33.48 1054.62 $ 0.005 hr/SF B-37 8.37 HoursPlan Area A,B,C (F.1-G.4),(8.7-14) 3486 sf $0.42 $0.19 $0.02 0.63 $/SF $1,464.12 $662.34 $69.72 2196.18 $ 0.005 hr/SF B-37 17.43 HoursSlab for Shed 360 sf $0.42 $0.19 $0.02 0.63 $/SF $151.20 $68.40 $7.20 226.8 $ 0.005 hr/SF B-37 1.8 HoursSlab for Shed 360 sf $0.42 $0.19 $0.02 0.63 $/SF $151.20 $68.40 $7.20 226.8 $ 0.005 hr/SF B-37 1.8 Hours
$23,191.56 $10,491.42 $1,104.36 34787.34 $ 276.09 Hours
Total Adjusted: $18,576.27 $8,403.55 $884.58 27864.398 $
Cost Breakdown
TOTAL:
Detailed Estimate: Granular Fill
RiprapLocation Material Labor Equipment Cost Materials Labor Equipment Cost Crew Productivity Duration
Pond Emergency Spillway 111 SY $6.30 $14.50 $4.63 $25.43 /SY $699.30 $1,609.50 $513.93 $2,822.73 B-36C 0.008 hr/SY 0.89 HoursInfiltration Basin Emergency Spillway 167 SY $6.30 $14.50 $4.63 $25.43 /SY $1,052.10 $2,421.50 $773.21 $4,246.81 B-36C 0.008 hr/SY 1.34 HoursApron 11 SY $6.30 $14.50 $4.63 $25.43 /SY $69.30 $159.50 $50.93 $279.73 B-36C 0.008 hr/SY 0.09 HoursApron 11 SY $6.30 $14.50 $4.63 $25.43 /SY $69.30 $159.50 $50.93 $279.73 B-36C 0.008 hr/SY 0.09 Hours
Total: $1,751.40 $4,031.00 $1,287.14 $7,069.54 2.22
Total Adjusted: $1,402.86 $3,228.80 $1,030.99 $5,662.65
Cost Breakdown
Size
Detailed Estimate: Rip Rap
Retention PondLocation Material Labor Equipment Cost Materials Labor Equipment Cost Crew Productivity Duration
Wet Detention Basin Excavation 20928 CY $0.00 $0.40 $0.99 $1.39 /CY $0.00 $8,371.20 $20,718.72 $29,089.92 B-10L 0.009 hr/CY 188.35 HoursOff-site Detention Excavation 14532 CY $0.00 $0.40 $0.99 $1.39 /CY $0.00 $5,812.80 $14,386.68 $20,199.48 B-10L 0.009 hr/CY 130.79 HoursInfiltration Basin Excavation 8398 CY $0.00 $0.40 $0.99 $1.39 /CY $0.00 $3,359.20 $8,314.02 $11,673.22 B-10L 0.009 hr/CY 75.58 HoursWet Detention Basin Hauling 20928 CY $0.00 $1.48 $3.20 $4.68 /CY $0.00 $30,973.44 $66,969.60 $97,943.04 B-34B 0.037 hr/CY 774.34 HoursOff-site Detention Hauling 14532 CY $0.00 $1.48 $3.20 $4.68 /CY $0.00 $21,507.36 $46,502.40 $68,009.76 B-34B 0.037 hr/CY 537.68 HoursInfiltration Basin Hauling 8398 CY $0.00 $1.48 $3.20 $4.68 /CY $0.00 $12,429.04 $26,873.60 $39,302.64 B-34B 0.037 hr/CY 310.73 Hours
Total: $0.00 $82,453.04 $183,765.02 $266,218.06 2017.47
Total Adjusted: $0.00 $66,044.27 $147,194.40 $213,238.67
Cost Breakdown
Size
Detailed Estimate: Retention Pond
BLACK BOX CONSTRUCTION, LLC. 3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
Material Labor Equipment Sub-Contractor SubtotalTotal (Incl GC
markup)
General Conditions $17,806.25 $593,719.63 $56,133.73 $256,279.02 $923,938.63 $1,071,584.02Grading, Stone, Utilities, Survey $285,107.65 $319,240.44 $255,057.98 $0.00 $859,406.07 $996,739.16Paving $333,758.88 $23,250.24 $27,293.76 $384,302.88 $445,714.48Termite Treatment $17,113.19 $8,297.30 $0.00 $0.00 $25,410.49 $29,471.09Concrete (Site,Foundations, Slabs, Stairs) $238,782.83 $159,899.48 $1,289.32 $0.00 $399,971.63 $463,887.10Precast Material and Erection $14,733.66 $1,671.38 $3,649.19 $0.00 $20,054.23 $23,258.90CMU Masonry $189,036.33 $255,440.03 $0.00 $444,476.35 $515,503.68Brickwork (Includes Anchor Bolts for Veneer) $170,949.24 $168,080.53 $0.00 $0.00 $339,029.78 $393,206.74Wood Shelving $70,340.78 $81,581.24Fire Sprinklers $409,580.29 $475,031.23Painting $140,135.40 $162,529.04PVC Roofing $242,340.65 $281,066.69Stage Flooring $6,350.29 $7,365.07ACM Panel $44,746.63 $51,897.14Operable Partititon $124,399.16 $144,278.14Basket Ball Goals $6,514.59 $7,555.63Lockers $1,355.25 $1,571.82Waterproof Membrane & Sheet Waterproofing $14,216.20 $16,487.95Extensions Joints/Caulking $14,665.68 $17,009.25Elevators $251,217.60 $291,362.17Wall Padding $32,923.09 $38,184.19VCT Tile $175,504.69 $203,550.34Carpet Tiling $20,575.40 $23,863.35Traffic Coatings $6,045.52 $7,011.59HVAC $1,470,781.29 $1,705,812.14Fencing $35,284.98 $40,923.52ACT Ceilings $600,630.30 $696,611.02ACT Wall Panels $17,207.64 $19,957.42Banners $672.98 $780.52Final Electricity $383,335.93 $444,593.01Landscaping and Irrigation $362,576.00 $420,515.64Spray Fireproofing $449,541.93 $521,378.73Misc Firestopping $195,558.75 $226,809.04Structural and Misc Steel $968,749.28 $1,123,555.41Ceramic Tiles $82,043.97 $95,154.59Aluminum Canopies $190,735.40 $221,214.91Flagpoles $12,485.18 $14,480.32Display Cases $4,837.50 $5,610.53Louvers $3,966.77 $4,600.66Spray Foam Beam Infill $3,645.17 $4,227.66Foam Insulation $77,671.70 $90,083.64Dry Wall- Wall $168,206.60 $195,086.02Dry Wall-Ceilings $8,701.55 $10,092.06Framing $100,372.15 $116,411.61Inwall Blocking $18,207.59 $21,117.16Fiber Cement $4,726.14 $5,481.38Security $119,919.91 $139,083.11Communication $59,013.86 $68,444.28Fire Alarm $146,465.21 $169,870.35Roof Expansion Joints $7,642.58 $8,863.87Aluminum Storefront $349,886.80 $405,798.71Stage Curtains, Folding Stages, Cubicle Curtains $19,910.75 $23,092.49Column Covers $2,655.84 $3,080.24Roof Nailers $33,889.12 $39,304.60Hollow Metal, Wood Dorrs, Toilet Part, Toilet acc, FEC $271,248.79 $314,594.34Coiling Doors $25,150.00 $29,168.97Residential Appliances $7,492.69 $8,690.02
Window Treatments $12,926.09 $14,991.68Misc. Steel $18,997.30 $22,033.07Plumbing $629,995.43 $730,668.70Wall Graphics $3,018.00 $3,500.28Food Service Equipment $227,356.00 $263,687.49Signage and Marquee $24,850.21 $28,821.28Kiln $4,315.74 $5,005.40Millwork & Window Seals $216,290.00 $250,853.14 R2 BSIT (RN)
Total Bid $12,298,464.40 $14,263,759.01
Sub - Contractor Wise Breakup of Bid
Description
Value
Team No. Sub
1Black Box
Construciton
1Atlantic
Contractors
2 White Hats
6Build Beast
R1 BMC (RN)
3 Trident
4 A&A
14
No. Description Total ($) No. Description Total ($) (Including Markup)1 General Conditions $87,739 1 General Conditions $103,8832 Wood Shelving $53,154 2 Wood Shelving $62,9343 Fire Sprinklers $309,503 3 Fire Sprinklers $366,4514 Painting $105,894 4 Painting $125,3795 PVC Roofing $183,127 5 PVC Roofing $216,8226 Stage Flooring $4,799 6 Stage Flooring $5,6827 ACM Panel $33,813 7 ACM Panel $40,0358 Operable Partititon $94,003 8 Operable Partititon $111,3009 Basket Ball Goals $4,923 9 Basket Ball Goals $5,829
10 Lockers $1,024 10 Lockers $1,213TOTAL DIRECT COST $877,978 Total $1,039,526
$78,140$39,509
$43,899$1,039,526BID AMOUNT
Markup = (Profit + Contingency + CoOH)
18.40%
Note: The bid has general conditions listed separately. We need to divide the general conditions proportionally within the activities. Please see the next page for proportional division of general conditions. Also, the prices have been given for October 2016. They have been adjusted for Jan 2017 on the following page.
SECTION 6 - APPENDIX
Atlantic Contractors Bid-Summary
Summary of BID Schedule of Values
CoOH (8.9%)Contingency (4.5%)
Profit (5%)
No. Item DescriptionAdjusted cost with general conditions
distributed among activites
Further Adjustment to
Jan 20171 Wood Shelving $69,921 $70,3412 Fire Sprinklers $407,137 $409,5803 Painting $139,300 $140,1354 PVC Roofing $240,895 $242,3415 Stage Flooring $6,312 $6,3506 ACM Panel $44,480 $44,7477 Operable Partititon $123,657 $124,3998 Basket Ball Goals $6,476 $6,5159 Lockers $1,347 $1,355
$1,039,526 $1,045,763
Total Direct Costs Excluding GC $935,642.92Gen Conditions $103,882.98
Gen Conditions as % of Direct cost excluding GC 11.102844%
Proportional Distribution of General Conditions in the Estimate. The values werer then adjusted for Jan 2017.
Atlantic Contractors Bid-Summary
Proportional Distribution of General Condition among activitesSummary of Estimate
Final Amount
Increase all activity costs by 11.102844% to proportinally distribute GC among direct costs.
No. Description Labor Equipment Material Subcontractor Total ($) Duration
1 General Conditions $87,739.02 Wood Shelving $48,250.9 $4,978.3 $0.0 $0.0 $53,229.2 27
3 Fire Sprinklers $147,977.8 $161,524.7 $0.0 $0.0 $309,502.5 73
4 Painting $19,408.1 $86,486.3 $0.0 $0.0 $105,894.4 32
5 PVC Roofing $121,179.7 $58,917.0 $3,029.9 $0.0 $183,126.6 45
6 Stage Flooring $2,142.6 $2,535.9 $120.2 $0.0 $4,798.6 6
7 ACM Panel $18,775.8 $15,037.4 $0.0 $0.0 $33,813.1 20
8 Operable Partititon $91,710.4 $2,292.8 $0.0 $0.0 $94,003.2 4
9 Basket Ball Goals $4,358.5 $544.1 $20.2 $0.0 $4,922.8 110 Lockers $930.2 $93.9 $0.0 $0.0 $1,024.1 0.5
$454,734.0 $332,410.3 $3,170.3 $0.0 $878,053.6
$78,057.4
$39,512.4$43,902.7
$1,039,526.0
Atlantic Contractor Bid - Breakdown
BID AMOUNT
CoOH (8.9%)
Contingency (4.5%)Profit (5%)
Total Direct Costs
Summary of BID
Description Size Quantity Unit Material Labor Equipment Total ($) Crew
Daily
Output Duration
Cabinet 2'6" * 2'6" 6 Ea $2,268.00 $234.00 $2,502.00 2 Carp 19.8 0.30303
Cabinet 2'6" * 2'8" 5 Ea $1,890.00 $195.00 $2,085.00 2 Carp 19.82 0.25227
Cabinet 3'0" * 2'8" 32 Ea $12,096.00 $1,248.00 $13,344.00 2 Carp 18.8 1.702128
Cabinet 3'0" * 2'6" 2 Ea $756.00 $78.00 $834.00 2 Carp 18.8 0.106383
Cabinet 1'0" * 2'8" 2 Ea $756.00 $78.00 $834.00 2 Carp 22 0.090909
Cabinet 2'0" * 2'8" 1 Ea $378.00 $39.00 $417.00 2 Carp 20.3 0.049261
Cabinet 1'3" * 2'8" 1 Ea $378.00 $39.00 $417.00 2 Carp 20.3 0.049261
Cabinet 3'0" * 2'6" 11 Ea $4,158.00 $429.00 $4,587.00 2 Carp 20.3 0.541872
Cabinet 1'6" * 2'6" 2 Ea $756.00 $78.00 $834.00 2 Carp 20.9 0.095694
Cabinet 1'0" * 2'6" 2 Ea $756.00 $78.00 $834.00 2 Carp 22 0.090909
Cabinet 2'0" * 2'6" 2 Ea $756.00 $78.00 $834.00 2 Carp 20.3 0.098522
Cabinet 3'0" * 2'10" 8 Ea $3,024.00 $312.00 $3,336.00 2 Carp 20.3 0.394089
Cabinet 2'6" * 2'10" 2 Ea $756.00 $78.00 $834.00 2 Carp 22 0.090909
Cabinet 3'6" * 2'10" 2 Ea $756.00 $78.00 $834.00 2 Carp 20.3 0.098522
Cabinet 1'6" * 2'8" 7 Ea $2,646.00 $273.00 $2,919.00 2 Carp 20.9 0.334928
Cabinet 1'3" * 2'5 2/3" 1 Ea $378.00 $39.00 $417.00 2 Carp 24.8 0.040323
Cabinet 1'6" * 2'5 2/3" 3 Ea $1,134.00 $117.00 $1,251.00 2 Carp 24.8 0.120968
Cabinet 3'0" * 7' 10 Ea $3,780.00 $390.00 $4,170.00 1 Carp 2.7 3.703704
Cabinet 3'0" * 7' 5 Ea $1,890.00 $195.00 $2,085.00 1 Carp 2.7 1.851852
Cabinet 4'0" * 7' 1 Ea $378.00 $39.00 $417.00 1 Carp 2.7 0.37037
Cabinet 3'0" * 7' 2 Ea $756.00 $78.00 $834.00 1 Carp 2.7 0.740741
Cabinet 3'0" * 7' 2 Ea $756.00 $78.00 $834.00 1 Carp 2.7 0.740741
Drawer 1'6" * 2'6" 3 Ea $1,134.00 $117.00 $1,251.00 2 Carp 23.3 0.128755
Drawer 1'6" * 2'10" 1 Ea $378.00 $39.00 $417.00 2 Carp 23.3 0.042918
Drawer 1'6" * 2'6" 1 Ea $378.00 $39.00 $417.00 2 Carp 24.8 0.040323
Drawer 2'0" * 2'6" 1 Ea $378.00 $39.00 $417.00 2 Carp 22.3 0.044843
Drawer 1'0" * 2'10" 1 Ea $378.00 $39.00 $417.00 2 Carp 24.8 0.040323
Drawer 3'4" * 2'6" 3 Ea $1,134.00 $117.00 $1,251.00 2 Carp 22.3 0.134529
Coat Storage 3' * 6' 10 Ea $3,780.00 $390.00 $4,170.00 1 Carp 2.1 4.761905
Fixed Shelves 1'0" * 2'0" 3 Ea $1,134.00 $117.00 $1,251.00 1 Carp 3.6 0.833333
Fixed Shelves 1'3" * 3'9" 2 Ea $756.00 $78.00 $834.00 1 Carp 1.7 1.176471
Fixed Shelves 3'0" * 9" 1 Ea $378.00 $39.00 $417.00 1 Carp 2.2 0.454545
Fixed Shelves 1'7" * 2'8" 2 Ea $756.00 $78.00 $834.00 1 Carp 2.2 0.909091
Fixed Shelves 10" * 6'5" 4 Ea $1,512.00 $156.00 $1,668.00 1 Carp 1.7 2.352941
Fixed Shelves 2'3" * 6" 2 Ea $756.00 $78.00 $834.00 1 Carp 5.5 0.363636
Fixed Shelves 1'0" * 1'0" 1 Ea $378.00 $39.00 $417.00 1 Carp 4.5 0.222222
Fixed Shelves 2'0" * 1'8" 1 Ea $378.00 $39.00 $417.00 1 Carp 3.6 0.277778
Fixed Shelves 1'0" * 2'0" 4 Ea $1,512.00 $156.00 $1,668.00 1 Carp 3.9 1.025641
Adj Shelves 3'0" * 1'4" 1 Ea $378.00 $39.00 $417.00 1 Carp 1.7 0.588235
Adj Shelves 2'6" * 1'0" 1 Ea $378.00 $39.00 $417.00 1 Carp 1.7 0.588235
Adj Shelves 2'0" * 1'4" 1 Ea $378.00 $39.00 $417.00 1 Carp 1.7 0.588235Adj Shelves 4'8" * 1'2" 1 Ea $378.00 $39.00 $417.00 1 Carp 1.7 0.588235
$57,834.00 $5,967.00 $0.00 $63,801.00 27
$48,250.91 $4,978.27 $0.00 $53,229.17 DAYS
Detailed Estimate: Wood Shelving
Wood Shelving
*Adjusted Total = Adjustment for Time (October 2016), Location (Wilmington) and Size
Totals
Adjusted Totals
Atlantic Contractors
Description Quantity Unit Total Quantity Unit Wastage%Adjusted
QuantityPipe Length (Per SF) 1 1/2" Inches 11490 Feet 10 12639
Fire Pump 1 Ea 1 Ea 0 1
Fire Department Connection 1 Ea 1 Ea 0 1
Fire Hydrant 3 Ea 3 Ea 0 3
Upright Sprinkler Head 58 Ea 58 Ea 2 59
Recessed Dry Pendant Sprinkler Head 5 Ea 5 Ea 0 5
Recessed Pendant Sprinkler Head 627 Ea 627 Ea 2 640
Pendant Sprinkler Head with Heavy Duty Guard 31 Ea 31 Ea 2 32
Wet Sprinkler Riser 64 Ea 64 Ea 2 65
Side Wall Sprinkler Head 246 Ea 246 Ea 2 251Institutional 2 Ea 2 Ea 0 2
Description Crew Daily Output Material Labor Equipment Total ($) DurationPipe Length (Per SF) Q1 * 6 426 $139,661 $150,404 $290,065 26.97
Fire Pump Q13 0.58 $17,900 $2,950 $20,850 1.72
Fire Department Connection Q12 1 $520 $162 $682 1.00
Fire Hydrant Q12 5 $1,710 $486 $2,196 0.60
Upright Sprinkler Head 1 Spri 16 $574 $1,624 $2,198 0.19
Recessed Dry Pendant Sprinkler Head 1 Spri 14 $725 $160 $885 4.14
Recessed Pendant Sprinkler Head 1 Spri 10 $8,935 $28,215 $37,150 0.50
Pendant Sprinkler Head with Heavy Duty Guard 2 Spri 32 $471 $868 $1,339 19.59
Wet Sprinkler Riser 1 Spri 16 $634 $1,792 $2,426 1.94
Side Wall Sprinkler Head 1 Spri 16 $6,150 $6,888 $13,038 4.00Institutional 2 Spri 20 $88 $56 $144 12.30
$177,368 $193,605 $0 $370,973
$147,977.79 $161,524.73 $0.00 $309,502.52 72.96
Total
Adjusted Total
Fire Sprinkler System
Description Quantity Unit Waste % Adjusted Unit
Soffits 1,746.00 S.F. 10 1,920.60 S.F.
Metal Panels and Coping 1,619.00 S.F. 10 1,780.90 S.F.Fiber Cement Strips 1,371.00 S.F. 10 1,508.10 S.F.
Interior Wall Finishes 102,347.60 S.F. 10 112,582.36 S.F.
W/ Wastage
Description Crew Daily Output Unit Material Labor Equipment Total ($) Duration
Soffits - Intermediate amd Top Coat 2 Pord 1,495 S.F. $226.98 $873.00 $1,099.98 1.2
Metal Panels and Coping - Primer and 2 Coats 2 Pord 975 S.F. $338.37 $1,068.54 $1,406.91 1.7
Fiber Cement Strips - 1st Coat 1 Pord 1,950 S.F. $105.57 $233.07 $338.64 0.7Fiber Cement Strips - 2nd Coat 1 Pord 2,600 S.F. $75.41 $164.52 $239.93 0.5
Interior Wall Finishes - Surface Prep and 2 Coats 10 Pord 3,250 S.F. $22,516.47 $101,324.12 $123,840.60 31.5
$23,262.80 $103,663.25 $0.00 $126,926.05
$19,408.15 $86,486.25 $0.00 $105,894.40
Detailed Estimate: Painting
32 Day Schedule
Adjusted Total
Painting
W/O Wastage
Exterior Painting
Interior Painting
Painting
Interior Painting
Exterior Painting
Total
Atlantic Contractors
Description Quantity Unit Waste % Adjusted UnitRoofing Area 58,253.00 S.F. 5 61,165.65 S.F.
Overlaps for Membrane (3") 6,087.43 S.F. 5 6,391.80 S.F.
Membrane extension 1" up the wall 1,690.49 S.F. 5 1,775.01 S.F.
Total 66,030.92 S.F. 69,332.46 S.F.Flashing 1,127.00 L.F. 5 1,183.35 L.F.
W/ Wastage
Description Crew Daily Output Unit Material Labor Equipment Total ($) Duration Schedule
PVC Membrane 60 mils G-5 5,100.00 S.F $76,959 $27,403 $3,632 $107,994 12.9 6
Gypsum Cover Board (1/2") 3 Rofc 1,950.00 S.F $34,864 $14,563 $49,428 29.9
Polystyrene Insulation Board (1") 3 Carp 2,400.00 S.F. $32,418 $27,379 $59,797 24.3Flashing 8 Rofc 2,280.00 S.F. $1,006 $1,274 $2,279 25.5 12
$145,247 $70,618 $3,632 $219,497 45 DAYS
27
Total
PVC Roofing
W/O Wastage
Estimate
Description Quantity Unit Waste % Adjusted UnitStage Flooring 758 S.F. 10.00 833.80 S.F.
W/ Wastage
Description Crew Daily Output Unit Material Labor Equipment Total ($) Duration Schedule
Hardwood Flooring 3/4" 1 Clab 130.0 S.F $1,117 $1,751 $2,868 5.8
Plywood 1/2" Subfloor (2 Layers) 2 Carp 1,500.0 S.F $1,101 $758 $1,859 0.5
Waterproof Membrane G-1 3,000.0 S.F. $350 $531 $144 $1,025 0.3$2,568 $3,040 $144 $5,752 6.6
6 Days
Stage Flooring
W/O Wastage
Estimate
Total
Description Quantity Unit Waste % Adjusted Unit
Total Area for ACM Wall Panels 1,600.00 S.F 3.00 1,648.00 S.F.Total Linear Feet of Aluminum Coping 1,690.47 L.F. 5 1,774.99 L.F.
W/ Wastage
Description Crew Daily Output Unit Material Labor Equipment Total ($) Duration Schedule
ACM Wall Panel System 2 Shee 375.0 S.F. $6,707 $3,824 $10,531 4.3
Aluminum Coping D-1 80.0 S.F. $15,797 $14,200 $29,997 20.0$22,504.80 $18,023.95 $0.00 $40,528.75
$18,775.76 $15,037.38 $0.00 $33,813.14
Number
Length Height5'5" X 11' 14 11.00 5.42 59.58 834.17
4' X 5'5" 1 4.00 5.42 21.67 21.67
6'4" X 1'2" 8 6.33 1.17 7.39 59.11
6'4" X 10" 23 6.33 0.83 5.28 121.39
11' X 10" 14 11.00 0.83 9.17 128.33
8'2" X 10" 1 8.17 0.83 6.81 6.81
6' X 10" 1 6.00 0.83 5.00 5.00
8' X 10" 1 8.00 0.83 6.67 6.67
14' X 10" 1 14.00 0.83 11.67 11.67
3'4" X 10" 3 3.33 0.83 2.78 8.33Near Door 2 - - - 397.19
Total Area 1,600.33
Area
A
BD &E
Total 1,690.47
Length of Coping System (L.F)
548.57
370.24771.66
Total Area of Units
(S.F.)
ACM Wall Panels
Coping
13.3" wide with 6" overhang on one side and 8" overhang on the other side
SizeDimensions Area of Single Unit
(S.F.)
Total
Adjusted Total
ACM & Metal Panels
Estimate
20 Days
W/O Wastage
Length 57' 9"
Height 19'Quantity (S.F.) $1,099.25
W/ Wastage
Description Crew Daily Output Unit Material Labor Equipment Total ($) Duration Schedule
Operable Partitions 2 Carp 300.0 S.F. $109,925 $2,748 $112,673 3.7
$109,925 $2,748 $0 $112,673 4 Days
Operable Partitition
W/O Wastage
Estimate
Total
Description Quantity Unit Waste %Adjusted
QuantityUnit
Basket Ball Goal System 2 Ea 0 2 Ea Concrete Base
(18" x18" x 48") * 2 18 C.F 5 18.9 C.F.
W/ Wastage
Description Crew Daily Output Unit Material Labor Equipment Total ($) Duration
Basket Ball System B-1 2.0 Ea $5,162 $610 $5,772 1.0Concrete Base
(18" x18" x 48") C-30 135.0 C.F. $62 $42 $24 $129 0.1
$5,224 $652 $24 $5,901
W/O Wastage
Basket Ball Goals
Estimate
Total
Description Size Quantity UnitMetal Lockers 12"*15"*72" 5 Ea
W/ Wastage W/O Wastage
Description Crew Daily Output Unit Material Labor Equipment Total ($) Duration Schedule
Single Tier Metal Lockers 1 Shee 20.0 Ea $1,115.00 $112.50 $1,227.50 0.3 0.5 Days
Metal Lockers
Estimate
No. QTY UNIT COST PER UNIT Subtotal Total (Incl Markup)1 1 Lump Sum $2.00 $129,539 $160,628.362 5,300 sf $2.00 $10,469 $12,981.563 1 Lump Sum $10,800 $10,800 $13,392.004 1 no $185,000 $185,000 $229,400.005 474 sf $51.20 24,245 $30,063.806 59,000 sy $2.20 $129,244 $160,262.567 614 sy $24.70 $15,152 $18,788.488 2,170 sf $2.05 $4,452 $5,520.489 1 Lump Sum $1,083,103 $1,083,103 $1,343,047.72
$1,974,084.96
24%Markup
White Hats Bid-Summary
Note: The bid has general conditions listed separately. We need to divide the general conditions proportionally within the activities. Please see the next page for proportional division of general conditions. Also, the prices have been given for October 2016. They have been adjusted for Jan 2017.
ConstructionGeneral ConditionsWaterproof Membrane & Sheet Extensions Joints/CaulkingElevatorsWall PaddingVCT TileCarpet TilingTraffic CoatingsHVAC
Grand Total
No. Item DescriptionAdjusted cost with general conditions
distributed among activites
Further Adjustment to
Jan 2017
1 Waterproof Membrane & Sheet Waterproofing $14,131.41 $14,2162 Extensions Joints/Caulking $14,578.21 $14,6663 Elevators $249,719.29 $251,2184 Wall Padding $32,726.72 $32,9235 VCT Tile $174,457.94 $175,5056 Carpet Tiling $20,452.68 $20,5757 Traffic Coatings $6,009.46 $6,0468 HVAC $1,462,009.23 $1,470,781
$1,974,085 $1,985,929
Total Direct Costs Excluding GC $1,813,456.60Gen Conditions $160,628.36
Gen Conditions as % of Direct cost excluding GC 8.857579%
Increase all activity costs by 18.85757% to proportinally distribute GC among direct costs.
Proportional Distribution of General Conditions in the Estimate. The values werer then adjusted for Jan 2017.
Final Amount
White Hats Bid-Summary
Proportional Distribution of General Condition among activites
Summary of Estimate
Height Width
30 24 No 2" 24 28 28 11.6 324.8
30 18 No 2" 24 18,19 37 10.3 381.1
28 18 No 2" 24 11,83,16 110 9.9 1089
28 18 No 2" 24 13,103 126 9.9 1247.4
28 8 No 2" 24 6 6 7.8 46.8
26 14 No 2" 24 20 20 8.6 172
26 18 No 2" 24 67,147 214 9.5 2033
24 10 No 2" 24 12 12 7.3 87.6
24 14 No 2" 24 15 15 8.2 123
24 24 No 2" 24 47,33,38 118 10.3 1215.4
24 18 No 2" 24 14,16 30 9 270
20 14 No 2" 24 6,45,16 67 7.3 489.1
20 18 No 2" 24 17,18 35 8.2 287
20 16 No 2" 24 29,76,24 129 7.8 1006.2
20 10 No 2" 24 19 19 6.5 123.5
18 14 No 2" 24 52 52 6.9 358.8
18 18 No 2" 24 20 20 7.8 156
16 14 No 2" 24 49,17 66 6.5 429
16 16 No 2" 24 26 26 6.9 179.4
14 14 No 2" 24 13,6,11,16,14 60 6 360
14 12 No 2" 24 18 18 5.6 100.8
14 10 No 2" 24 20 20 5.2 104
14 16 No 2" 24 25 25 6.5 162.5
12 14 No 2" 24 22,7 29 5.6 162.4
12 12 No 2" 24 16,13 29 5.2 150.8
12 16 No 2" 24 21,13,58 92 6 552
12 10 No 2" 24 12 12 4.7 56.4
10 10 No 2" 24 31,7,10,23,14 85 4.3 365.5
10 14 No 2" 24 13,32,17 62 5.2 322.4
10 12 No 2" 24 15,8,34 57 4.7 267.9
8 8 No 2" 24 32,16 48 3.4 163.2
Circular
No 2" 24 72 72 5.4 388.8
No 2" 24 3 3 4.7 14.1
No 2" 24 172,6,10,17,15,6,44,61,13,25,14,14 397 4.1 1627.7
No 2" 24 9,202,6,23,34,27,14,21,20,97,18,4 475 3.4 1615
No 2" 24 9,11,2,23 45 2.8 126
No 2" 24 7,14,15,32,16,6,22,8,6,39,30 195 2.2 429
16987.6
Surface area for insulation
24 16987.6/1.156 14695 sft
Duct work quantification:
Area A
Rectangular
Duct SizeLining Insulation Gauge Length
Total
lengthLbs/ft
16
14
12
10
8
6
Total
pounds
Total
Diameter Lining Insulation Gauge Length Total lengthLbs/FootTotal
pounds
Height Width
66 18 No 2" 20 44 44 24.4 1073.6
60 18 No 2" 20 16 16 22.6 361.6
50 18 No 2" 22 62 62 17 1054
40 16 No 2" 22 7 7 14 98
30 18 No 2" 24 26,7 33 10.3 339.9
30 16 No 2" 24 54 54 9.9 534.6
28 16 No 2" 24 45 45 9.5 427.5
28 18 No 2" 24 43,35,32 110 9.9 1089
26 18 No 2" 24 16 16 9.5 152
24 12 No 2" 24 11 11 7.8 85.8
20 12 No 2" 24 15,24 39 6.9 269.1
20 12 No 2" 24 93,2 95 6.9 655.5
20 14 No 2" 24 32,43 75 7.3 547.5
18 14 No 2" 24 24 24 6.9 165.6
18 16 No 2" 24 37 37 7.3 270.1
16 16 No 2" 24 95 95 6.9 655.5
16 12 No 2" 24 19 19 6 114
14 16 No 2" 24 14 14 6.5 91
14 14 No 2" 24 17,58 75 6 450
14 12 No 2" 24 16,20,19 55 5.6 308
14 10 No 2" 24 38 38 5.2 197.6
12 12 No 2" 24 33,18,23,5,14,14,20,19 126 5.2 655.2
10 14 No 2" 24 32 32 5.2 166.4
10 10 No 2" 24 17,5,10,35,47 114 4.3 490.2
10 12 No 2" 24 8,5,36,19 68 4.7 319.6
10 8 No 2" 24 21,58,31 110 3.9 429
8 8 No 2" 24 5,4,6,37,20,8,8 88 3.4 299.2
8 10 No 2" 24 4,10 14 3.9 54.6
8 12 No 2" 24 10 10 4.3 43
Circular
No 2" 24 12 12 4.7 56.4
No 2" 24 6,19,20 45 4.1 184.5
No 2" 24 22,36,28,8,34,22,25,3,7,8,3,25,9,13,3 246 3.4 836.4
No 2" 24 48,36,24,44,18,35,22,12,16,3,24 282 2.8 789.6
No 2" 24 64,75,118,9,27,35,15,8,4,21,12,82,12,18 500 2.2 1100
14364
Surface area for insulation
24 11776.8/1.156 10187.543 sft
22 1152/1.406 819.34566 sft
20 1435.2/1.656 866.66667 sft
Total 11873.556 sft
White Hats
Area B
Rectangular
Duct SizeLining Insulation Gauge Length Total lengthLbs/Foot
14
12
10
8
6
Total
Total
pounds
Diameter Lining Insulation Gauge Length Total lengthLbs/FootTotal
pounds
Height Width
60 18 No 2" 20 7 7 22.6 158.2
50 18 No 2" 22 80 80 17 1360
40 16 No 2" 22 22 22 14 308
40 14 No 2" 22 51 51 13.5 688.5
38 14 No 2" 22 27 27 13 351
30 18 No 2" 24 56 56 10.3 576.8
30 14 No 2" 24 20 20 9.5 190
30 16 No 2" 24 8 8 9.9 79.2
28 14 No 2" 24 43 43 9 387
24 12 No 2" 24 3,3,6,4 16 7.8 124.8
24 16 No 2" 24 35 35 8.6 301
20 16 No 2" 24 22 22 7.8 171.6
20 14 No 2" 24 22,27,34 83 7.3 605.9
20 14 No 2" 24 23,40,27,40 130 7.3 949
18 14 No 2" 24 39 39 6.9 269.1
14 14 No 2" 24 30,55,44 128 6 768
14 12 No 2" 24 20,21 41 5.6 229.6
12 14 No 2" 24 36,23,26,20,15,19,25,27 191 7.8 1489.8
10 8 No 2" 24 52 52 3.9 202.8
10 10 No 2" 24 2 2 4.3 8.6
10 12 No 2" 24 25 25 4.7 117.5
8 8 No 2" 24 13,8 21 3.4 71.4
Circular
No 2" 24 3,3,3,3 12 4.7 56.4
No 2" 24 8 8 4.1 32.8
No 2" 24 39,8,10,64,37,65,64,11,13,16,14,36 378 3.4 1285.2
No 2" 24 3,13,32,3 51 2.8 142.8
No 2" 24 6,6,38,9,17,26,15,29,19,17,17,7,12 218 2.2 479.6
11404.6
Surface area for insulation
24 8538.9/1.156 7386.5917 sft
22 2707.5/1.406 1925.6757 sft
20 158.2/1.656 95.531401 sft
Total 9407.7988 sft
Area c
Rectangular
Duct SizeLining Insulation Gauge Length Total lengthLbs/Foot
Total
pounds
Lbs/FootTotal
pounds
14
12
10
8
Diameter Lining Insulation Gauge Length Total length
6
Total
Height Width
44 14 No 2" 22 13 13 14.5 188.5
40 14 No 2" 22 61,27 88 13.5 1188
36 14 No 2" 22 15 15 12.5 187.5
34 14 No 2" 22 45 45 12 540
30 18 No 2" 24 36 36 10.3 370.8
26 14 No 2" 24 79 79 8.6 679.4
24 18 No 2" 24 50 50 9 450
24 14 No 2" 24 41 41 8.2 336.2
22 12 No 2" 24 21 21 7.3 153.3
20 12 No 2" 24 21,25 46 6.9 317.4
20 14 No 2" 24 51,79 130 7.3 949
18 18 No 2" 24 26 26 7.8 202.8
16 16 No 2" 24 52 52 6.9 358.8
16 12 No 2" 24 18,21 39 6 234
14 12 No 2" 24 23,23,22,11 79 5.6 442.4
14 14 No 2" 24 38 38 6 228
12 12 No 2" 24 22,21,21,18 82 5.2 426.4
10 10 No 2" 24 5,12,22 39 4.3 167.7
8 8 No 2" 24 7 7 3.4 23.8
Circular
No 2" 24 7 7 5.4 37.8
No 2" 24 3,5,6 14 4.7 65.8
No 2" 24 5,2,3,6 16 4.1 65.6
No 2" 24 205,327,261,411,114 265 3.4 901
No 2" 24 7,22,3,53,2 87 2.8 243.6
No 2" 24 61,14 75 2.2 165
8922.8
Surface area for insulation
24 6818.8/1.156 5898.6159 sft
22 2104/1.406 1496.4438 sft
Total 7395.0597 sft
Area D
Rectangular
Duct SizeLining Insulation Gauge Length Total length
16
14
12
10
8
6
Lbs/FootTotal
pounds
Diameter Lining Insulation Gauge Length Total lengthLbs/FootTotal
pounds
Total
Height Width
60 14 No 2" 20 38 38 21.5 817
50 14 No 2" 22 28 28 16 448
48 14 No 2" 22 34 34 15.5 527
48 16 No 2" 22 75 75 16 1200
44 14 No 2" 22 20 20 14.5 290
42 18 No 2" 22 45 45 15 675
40 14 No 2" 22 60 60 13.5 810
30 18 No 2" 24 17 17 10.3 175.1
20 12 No 2" 24 21 21 6.9 144.9
20 14 No 2" 24 4 4 7.3 29.2
16 14 No 2" 24 30 30 6.5 195
14 12 No 2" 24 22,22,27,23 94 5.6 526.4
12 10 No 2" 24 25 25 4.7 117.5
12 14 No 2" 24 9,43 52 5.6 291.2
12 12 No 2" 24 21,29,20 70 5.2 364
10 10 No 2" 24 14,26 40 4.3 172
8 8 No 2" 24 8 8 3.4 27.2
Circular
No 2" 24 4 4 4.7 18.8
No 2" 24 28,3 31 4.1 127.1
No 2" 24 18,14,17,9,75 133 3.4 452.2
No 2" 24 3,18,3,4 28 2.8 78.4
No 2" 24 11,24,3,11 49 2.2 107.8
7593.8
Surface area for insulation
24 2826.8/1.156 2445.3287 sft
22 3950/1.406 2809.3883 sft
20 817/1.656 493.35749 sft
Total 5748.0745 sft
Area E
Rectangular
Duct SizeLining Insulation Gauge Length Total lengthLbs/Foot
14
12
10
8
6
Total
Total
pounds
Diameter Lining Insulation Gauge Length Total lengthLbs/FootTotal
pounds
Duct work cost estimate
Location
Quantity of
duct
materials * Unit
Unit
material
cost
Unit
labor cost
Total
Material
cost
Labor Total
Cost
Area-A 22083 lb 0.61 4.4 13,470.63$ 97,165.20$
Area-B 18673 lb 0.61 4.4 11,390.53$ 82,161.20$
Area-C 14826 lb 0.61 4.4 9,043.86$ 65,234.40$
Area-D 11600 lb 0.61 4.4 7,076.00$ 51,040.00$
Area-E 9872 lb 0.61 4.4 6,021.92$ 43,436.80$
47,002.94$ 339,037.60$
Total 386,040.54$
Current total cost 277,896.38$ * Duct material includes wastage
Duct work insulation cost estimate
Insulation Quantity Units
Unit
material
cost
Unit
labor cost
Total
Material
cost
Labor Total
Cost
AreaA 14695 sf 0.26 2.51 3,820.70$ 36,884.45$
AreaB 11875 sf 0.26 2.51 3,087.50$ 29,806.25$
AreaC 9410 sf 0.26 2.51 2,446.60$ 23,619.10$
AreaD 7400 sf 0.26 2.51 1,924.00$ 18,574.00$
AreaE 5750 sf 0.26 2.51 1,495.00$ 14,432.50$
12,773.80$ 123,316.30$
Total 136,090.10$
Current total cost 97,966.25$ * Quantity includes wastage
Current total cost takes into considerations the size, location, and time factors in order to update the 2015
RSMeans costs to our project.
White Hats
Register, grille and diffuser schedule
Neck size Type
Unit
material
cost
Unit labour
costUnit No
Total material
costTatal labour cost
6"x6" Diffuser 50.00$ 28.00$ ea 66 $3,300.00 $1,848.00
9"x9" Diffuser 66.00$ 30.00$ ea 27 $1,782.00 $810.00
12"X12" Diffuser 84.50$ 37.50$ ea 186 $15,717.00 $6,975.00
12"X12" Diffuser 84.50$ 37.50$ ea 25 $2,112.50 $937.50
15"X15" Diffuser 130.50$ 40.50$ ea 1 $130.50 $40.50
6"x6" Diffuser 50.00$ 28.00$ ea 4 $200.00 $112.00
9"x9" Diffuser 66.00$ 30.00$ ea 2 $132.00 $60.00
12"X12" Diffuser 84.50$ 37.50$ ea 0 $0.00 $0.00
12"X12" Diffuser 84.50$ 37.50$ ea 2 $169.00 $75.00
15"X15" Diffuser 130.50$ 40.50$ ea 0 $0.00 $0.00
12"X6" Register 14.92$ 20.00$ ea 0 $0.00 $0.00
14"X6" Register 15.94$ 20.82$ ea 0 $0.00 $0.00
18"X8" Register 21.00$ 25.00$ ea 0 $0.00 $0.00
18"X12" Register 27.70$ 34.80$ ea 0 $0.00 $0.00
24"X18" Grille 71.00$ 22.50$ ea 1 $71.00 $22.50
22"X22" register 52.27$ 38.15$ ea 80 $4,181.60 $3,052.00
18"X6" register 17.86$ 22.50$ ea 4 $71.44 $90.00
4' diffuser diffuser 60.00$ 29.00$ ea 2 $120.00 $58.00
22"X22" register 52.27$ 38.15$ ea 2 $104.54 $76.30
6"X6" diffuser 50.00$ 28.00$ ea 2 $100.00 $56.00
28,191.58$ 14,212.80$ Total cost 42,404.38$ Current total cost 30,525.35$
Current total cost takes into considerations the size, location, and time factors in order to update the 2015 RSMeans costs to our project.
White Hats
Black steel pipe schedule 40 is used for the entire mechanical piping system for this project.
6 4 3 2 1/2 2 1 1/2 1 1/4 1 3/4
18.97 10.79 7.58 5.79 3.65 2.72 2.73 1.68 1.13
Hot water supply 234 109 99 59 139 0 2524.86 0 0 0 296.48 270.27 99.12 157.1
Hot water return 217 79 19 28 94 126 0 2341.43 598.82 0 0 51.68 76.44 157.92 142.4
Cold water supply 244 24 4628.68 0 0 138.96 0 0 0 0 0
Cold water return 232 26 4401.04 0 0 150.54 0 0 0 0 0
Total 476 451 79 50 0 128 127 153 265 9029.72 4866.29 598.82 289.5 0 348.16 346.71 257.04 299.5
6 4 3 2 1/2 2 1 1/2 1 1/4 1 3/4
18.97 10.79 7.58 5.79 3.65 2.72 2.73 1.68 1.13
Hot water supply 49 2 325 23 71 156 0 0 0 283.71 7.3 884 62.79 119.28 176.3
Hot water return 5 104 44 122 112 205 0 53.95 788.32 254.76 0 331.84 0 188.16 231.7
Cold water supply 50 3 96 0 0 379 17.37 350.4 0 0 0 0
Cold water return 50 3 96 0 0 379 17.37 350.4 0 0 0 0
Total 0 5 204 99 194 447 23 183 361 0 53.95 1546.32 573.21 708.1 1215.8 62.79 307.44 407.9
6 4 3 2 1/2 2 1 1/2 1 1/4 1 3/4
18.97 10.79 7.58 5.79 3.65 2.72 2.73 1.68 1.13
Hot water supply 126 58 52 0 0 0 0 0 0 343.98 97.44 58.76
Hot water return 156 48 31 93 99 0 0 1182.48 277.92 0 84.32 253.89 166.32 0
Total 0 0 156 48 0 31 219 157 52 18.97 10.79 1190.06 283.71 3.65 87.04 600.60 265.44 59.89
6 4 3 2 1/2 2 1 1/2 1 1/4 1 3/4
18.97 10.79 7.58 5.79 3.65 2.72 2.73 1.68 1.13
Hot water supply 53 125 5 102 0 0 0 0 193.45 0 341.25 8.4 115.3
Hot water return 259 34 0 0 0 1499.6 124.1 0 0 0 0
Cold water supply 38 0 0 0 220.02 0 0 0 0 0
Cold water return 39 0 0 0 225.81 0 0 0 0 0
Total 0 0 0 336 87 0 125 5 102 0 0 0 1945.4 317.55 0 341.25 8.4 115.3
White Hats
Area A
Purpose of piping
Pipe diameter in inches Nominal weight of pipe (lbs)
6 4 3 2 1/2 2 1 1/2 1 1/4 1 3/4
Purpose of piping
Pipe diameter in inches Nominal weight of pipe (lbs)
6 4 1 1/4 1
Area B
3/4
Area C
Purpose of piping
Pipe diameter in inches Nominal weight of pipe (lbs)
6 4 3 2 1/2 2
3 2 1/2 2 1 1/2
Purpose of piping
Pipe diameter in inches Nominal weight of pipe (lbs)
6 4 3/43 2 1/2 2 1 1/2 1 1/4 1
1 1/2 1 1/4 1 3/4
Area D
6 4 3 2 1/2 2 1 1/2 1 1/4 1 3/4
18.97 10.79 7.58 5.79 3.65 2.72 2.73 1.68 1.13
Hot water supply 130 51 24 0 0 0 752.7 186.15 353.6 0 0 0
Hot water return 56 25 46 52 0 0 0 0 204.4 68 0 77.28 58.76
Cold water supply 88 45 0 0 667.04 260.55 0 0 0 0 0
Cold water return 88 47 0 0 667.04 272.13 0 0 0 0 0
Total 0 0 176 222 107 49 0 46 52 0 0 1334.08 1285.4 390.55 421.6 0 77.28 58.76
6 4 3 2 1/2 2 1 1/2 1 1/4 1 3/4
18.97 10.79 7.58 5.79 3.65 2.72 2.73 1.68 1.13
Hot water supply 47 0 507.13 0 0 0 0 0 0 0
Hot water return 25 56 474.25 604.24 0 0 0 0 0 0 0
Cold water supply 157 43 2978.29 463.97 0 0 0 0 0 0 0
Cold water return 85 125 1612.45 1348.75 0 0 0 0 0 0 0
Total 267 271 0 0 0 0 0 0 0 5064.99 2924.09 0 0 0 0 0 0 0
6 4 3 2 1/2 2 1 1/2 1 1/4 1 3/4
18.97 10.79 7.58 5.79 3.65 2.72 2.73 1.68 1.13
Hot water supply 26 17 4 53 0 280.54 128.86 23.16 193.45 10.88 0 0 0
Hot water return 22 35 41 0 0 166.76 202.65 149.65 0 0 0 0
Cold water supply 40 50 6 758.8 539.5 45.48 0 0 0 0 0 0
Cold water return 43 50 5 815.71 539.5 37.9 0 0 0 0 0 0
Total 83 126 50 39 94 0 0 0 0 1574.51 1359.54 379 225.81 343.1 10.88 0 0 0
Area E
Purpose of piping
Pipe diameter in inches Nominal weight of pipe (lbs)
6 4 3 2 1/2 2 3/41 1/2 1 1/4 1
Boiler room loop piping
Purpose of piping
Pipe diameter in inches Nominal weight of pipe (lbs)
6 4 2 1 1/2 1 1/4 1
1 1/2 1 1/4 1 3/4
3/4
Mechanical room loop piping
Purpose of piping
Pipe diameter in inches Nominal weight of pipe (lbs)
6 4 3 2 1/2 2
3 2 1/2
Piping Cost estimation
Pipe size
(in)length Unit
material
Unit cost
Labour unit
costMaterial cost Labor cost
6 826 LF 48.50$ 31.50$ 40,061.00$ 26,019.00$
4 853 LF 23.50$ 18.80$ 20,045.50$ 16,036.40$
3 665 LF 16.75$ 16.90$ 11,138.75$ 11,238.50$
2 1/2 794 LF 13.65$ 14.85$ 10,838.10$ 11,790.90$
2 482 LF 8.70$ 11.75$ 4,193.40$ 5,663.50$
1 1/2 600 LF 7.35$ 9.20$ 4,410.00$ 5,520.00$
1 1/4 494 LF 6.60$ 8.10$ 3,260.40$ 4,001.40$
1 544 LF 5.30$ 7.45$ 2,883.20$ 4,052.80$
3/4 832 LF 5.50$ 6.60$ 4,576.00$ 5,491.20$
101,406.35$ 89,813.70$
Total 191,220.05$
Wastage (10%) 19,122.01$
Allowance for weld and fixtures (8%) 16,827.36$
Total 227,169.42$
Current total cost 163,530.91$
Pipe size Thickness Length
Unit
material
cost
Total
material cost
Unit labor
cost
Total labor
cost Thickness length
Unit
material
cost
Total material
cost
Unit labor
cost
Total labor
cost
3/4" 1-1/2" 0 2.89$ -$ 3.43$ -$ 1-1/2" 782 2.89$ 2,259.98$ 3.43$ 2,682.26$
1" 1-1/2" 0 2.93$ -$ 3.59$ -$ 1-1/2" 544 2.93$ 1,593.92$ 3.59$ 1,952.96$
1-1/4" 1-1/2" 0 2.99$ -$ 3.68$ -$ 1-1/2" 494 2.99$ 1,477.06$ 3.68$ 1,817.92$
1-1/2" 1-1/2" 0 3.14$ -$ 3.68$ -$ 1-1/2" 660 3.14$ 2,072.40$ 3.68$ 2,428.80$
2" 1-1/2" 182 3.32$ 604.24$ 3.88$ 706.16$ 2" 290 4.70$ 1,363.00$ 4.09$ 1,186.10$
2-1/2" 1-1/2" 225 3.62$ 814.50$ 4.09$ 920.25$ 2" 569 5.30$ 3,015.70$ 4.33$ 2,463.77$
3" 1-1/2" 287 3.77$ 1,081.99$ 4.46$ 1,280.02$ 2" 378 5.70$ 2,154.60$ 4.60$ 1,738.80$
4" 1-1/2" 268 4.53$ 1,214.04$ 5.25$ 1,407.00$ 2" 585 6.60$ 3,861.00$ 5.65$ 3,305.25$
5" 1-1/2" 4.84$ -$ 5.65$ -$ 2-1/2" 7.35$ -$ 6.15$ -$
6" 1-1/2" 801 4.99$ 3,996.99$ 6.70$ 5,366.70$ 2-1/2" 25 7.65$ 191.25$ 7.35$ 183.75$
8" 1-1/2" 6.55$ -$ 8.20$ -$ 2-1/2" 9.25$ -$ 9.20$ -$
1763 $7,711.76 $9,680.13 4327 17,988.91$ 17,759.61$
Total Insulation cost of pipings 53,140.41$
Current total cost 38,253.83$
Piping Insulation
Chilled water Hot water
Current total cost takes into considerations the size, location, and time factors in order to update the 2015 RSMeans costs to our project.
White Hats
Boiler Output Unit Material cost Labor costBoiler-1 752 ea 9,639.00$ 3,555.00$
Boiler-2 752 ea 9,639.00$ 3,555.00$
Boiler-3 752 ea 9,639.00$ 3,555.00$
28,917.00$ 10,665.00$
Total 39,582.00$
Current total cost 28,493.63$
Symbol Electric kW Material cost Labor cost
EUH-1 7.5 770.00$ 89.00$
EUH-2 7.5 770.00$ 89.00$
EUH-3 7.5 770.00$ 89.00$
2,310.00$ 267.00$
Total 2,577.00$
Current total cost 1,855.09$
Expansion Tank Schedule
Expansion tank Quantity Material Cost labour Cost
211 gallon bladder type 1
6,575.00$ 255.00$
31 gallon bladder type1
2,700.00$ 108.00$
9,275.00$ 363.00$
Total 9,638.00$
Current total cost 6,938.04$
White Hats
HVAC Heating
Boiler Schedule
Unit Heater Schedule
Valve estimation
Ball valve 2-1/2" 12 360.00$ 42.00$ 4,320.00$ 504.00$
Multi purpose valve 2-1/2" 3 532.00$ 141.00$ 1,596.00$ 423.00$
union 2-1/2" 6 155.00$ 30.00$ 930.00$ 180.00$
pressure gauge 2-1/2" 3 180.00$ 52.00$ 540.00$ 156.00$
flow switch 2-1/2" 3 135.00$ 45.00$ 405.00$ 135.00$
thermometer 2-1/2" 3 60.00$ 22.00$ 180.00$ 66.00$
thermometer 4" 3 85.00$ 25.00$ 255.00$ 75.00$
Flow meter 4" 1 135.00$ 45.00$ 135.00$ 45.00$
Pressure relief valve 2-1/2" 3 300.00$ 75.00$ 900.00$ 225.00$
Lock sheild 2-1/2" 3 25.00$ 7.00$ 75.00$ 21.00$
Butterfly valve 6" 2 143.00$ 265.00$ 286.00$ 530.00$
9,622.00$ 2,360.00$
Total 11,982.00$
Current total cost 8,625.40$
Ball valve 1-1/2" 2 360.00$ 42.00$ 720.00$ 84.00$
union 1-1/2" 2 155.00$ 30.00$ 310.00$ 60.00$
pressure gauge 1-1/2" 1 180.00$ 52.00$ 180.00$ 52.00$
Globe valve 1-1/2" 1 785.00$ 59.00$ 785.00$ 59.00$
Check valve 1-1/2" 1 94.50$ 19.75$ 94.50$ 19.75$
Water pressure
reduction valve1-1/2" 1 86.00$ 35.00$ 86.00$ 35.00$
2,175.50$ 309.75$
Total 2,485.25$
Current total cost 1,789.04$
White Hats
Current total cost takes into considerations the size, location, and time factors in order to update the 2015 RSMeans costs to our project.
Total
material
Labor Total
cost
Boiler water make up
station
Pipe size for
coolingQuantity
Material unit
price
Labor Unit
Price
Total
material
cost
Labor Total
cost
ValvePipe size for
heatingQuantity
Material unit
price
Labor Unit
Price
Chiller capacity(tons) unit Material cost Labor Cost
Chiller-1 126.7 ea 106,278.00$ 17,051.00$
Chiller-2 126.7 ea 106,278.00$ 17,051.00$
212,556.00$ 34,102.00$
Total 246,658.00$
Current total cost 177,560.02$ chiller valves
union 4" 4 155.00$ 30.00$ 620.00$ 120.00$
pressure gauge 4" 4 180.00$ 52.00$ 720.00$ 208.00$
flow switch 4" 2 135.00$ 45.00$ 270.00$ 90.00$
thermometer 4" 5 60.00$ 22.00$ 300.00$ 110.00$
thermometer 6" 3 85.00$ 25.00$ 255.00$ 75.00$
Flow meter 4" 1 135.00$ 45.00$ 135.00$ 45.00$
Lock sheild 4" 2 25.00$ 7.00$ 50.00$ 14.00$
Butterfly valve 4" 4 113.00$ 171.00$ 452.00$ 684.00$
Butterfly valve 6" 4 143.00$ 265.00$ 572.00$ 1,060.00$
3,374.00$ 2,406.00$
Total 5,780.00$
Current total cost 4,160.81$ Pressure reducing station valves
Ball valve 1-1/2" 2 360.00$ 42.00$ 720.00$ 84.00$
union 1-1/2" 2 155.00$ 30.00$ 310.00$ 60.00$
pressure gauge 1-1/2" 1 180.00$ 52.00$ 180.00$ 52.00$
Pressure relief
valve 1-1/2" 1300.00$ 75.00$ 300.00$ 75.00$
Globe valve 1-1/2" 1 890.00$ 92.00$ 890.00$ 92.00$
Check valve 1-1/2" 1 94.50$ 19.75$ 94.50$ 19.75$
Water pressure
reduction valve 1-1/2" 186.00$ 35.00$ 86.00$ 35.00$
Air seperator 6" 1 4,675.00$ 400.00$ 4,675.00$ 400.00$
7,255.50$ 817.75$
Total 8,073.25$
Current total cost 5,811.64$
White Hats
HVAC-Cooling
Chiller Schedule
ValvePipe size for
heatingQuantity
Material unit
price
Labor Unit
Price
Current total cost takes into considerations the size, location, and time factors in order to update the 2015 RSMeans costs to our
project.
Total material
cost
Labor Total
cost
ValvePipe size for
heatingQuantity
Material unit
price
Labor Unit
Price
Total material
cost
Labor Total
cost
HVAC
Louversquantity unit
Unit material
cost
Total
materal cost
Unit labor
cost
Total labor
cost
LP-1 9 sft 24.50$ 220.50$ 7.80$ 1,719.90$
LP-2 25 sft 24.50$ 612.50$ 7.80$ 4,777.50$
LP-3 25 sft 24.50$ 612.50$ 7.80$ 4,777.50$
LP-4 25 sft 24.50$ 612.50$ 7.80$ 4,777.50$
2,058.00$ 16,052.40$
Total 18,110.40$
Current total cost 13,037.01$
Teminal
numberCFM unit Material cost Labor cost
1--1 450 ea 800.00$ 79.00$
1--2 325 ea 796.25$ 76.18$
1--3 325 ea 796.25$ 76.18$
1--4 325 ea 796.25$ 76.18$
1--5 400 ea 800.00$ 79.00$
1--6 200 ea 790.00$ 71.50$
1--7 300 ea 795.00$ 75.25$
1--8 1225 ea 892.00$ 127.75$
5--1 800 ea 820.00$ 98.50$
5--2 1350 ea 900.00$ 144.00$
5--3 1150 ea 868.00$ 118.00$
5--4 225 ea 791.25$ 72.43$
5--5 425 ea 800.00$ 79.00$
5--6 1150 ea 868.00$ 118.00$
5--7 200 ea 790.00$ 71.50$
5--8 1150 ea 868.00$ 118.00$
6--1 475 ea 800.00$ 79.00$
6--2 110 ea 785.50$ 68.13$
6--3 1325 ea 900.00$ 140.75$
6--4 1900 ea 960.00$ 183.80$
6--5 1850 ea 952.50$ 177.20$
6--6 2075 ea 982.50$ 197.75$
6--7 1925 ea 963.50$ 187.10$
6--8 950 ea 820.00$ 98.50$
6--9 550 ea 800.00$ 79.00$
7--1 1625 ea 918.75$ 147.50$
7--2 1600 ea 915.00$ 144.20$
7--3 1000 ea 820.00$ 98.50$
8--1 850 ea 820.00$ 98.50$
8--2 1600 ea 915.00$ 144.20$
8--3 375 ea 798.75$ 78.00$
8--4 1200 ea 884.00$ 124.50$
8--5 1625 ea 918.75$ 147.50$
8--6 800 ea 820.00$ 98.50$
8--7 1150 ea 868.00$ 118.00$
8--8 1600 ea 915.00$ 144.20$
8--9 1825 ea 948.75$ 173.90$
8--10 800 ea 820.00$ 98.50$
8--11 750 ea 815.00$ 93.53$
8--12 950 ea 820.00$ 98.50$
Total 38,631.72$
Current total cost 27,809.55$
HVAC Louvered Pent house
VAV Terminal Box Schedule
Current total cost takes into considerations the size, location, and time factors in order to update the 2015
RSMeans costs to our project.
White Hats
Pump symbol GPM Hp Material cost Labor Cost
P-1 245 10 4,450.00$ 650.00$
p-2 245 10 4,450.00$ 650.00$
P-3 255 7.5 3,563.00$ 645.00$
P-4 255 7.5 3,563.00$ 645.00$
P-5 100 7.5 3,563.00$ 645.00$
P-6 100 7.5 3,563.00$ 645.00$
P-7 50 1 2,975.00$ 330.00$
P-8 50 1 2,975.00$ 330.00$
P-9 50 1 2,975.00$ 330.00$
32,077.00$ 4,870.00$
Total 36,947.00$
Current total cost 26,596.79$ Valves associated with pumps
ValveChilled
waterChiller Hot water
Total
quantity
Unit
material
price
Unit Labor
Cost
Total
Material
Cost
Total labor
cost
Ball valve 2 0 0 2 360.00$ 42.00$ $ 720.00 $ 84.00
Multi purpose valve 4 4 4 12532.00$ 141.00$
$ 6,384.00 $ 1,692.00
thermometer 2 0 2 4 60.00$ 22.00$ $ 240.00 $ 88.00 Butterfly valve 2 2 2 6 113.00$ 171.00$ $ 678.00 $ 1,026.00 Check valve 0 2 0 2 94.50$ 19.75$ $ 189.00 $ 39.50
8,211.00$ 2,929.50$
Total 11,140.50$
Current total cost 8,019.64$
Pump Schedule
Current total cost takes into considerations the size, location, and time factors in order to update the 2015 RSMeans costs to our project.
Symbol Supply CFM Unit Material cost Labor Cost
AHU-1 3550 ea 8,575.00$ 885.00$
AHU-2 4200 ea 8,575.00$ 885.00$
AHU-3 4200 ea 8,575.00$ 885.00$
AHU-4 4000 ea 8,575.00$ 885.00$
AHU-5 6450 ea 13,900.00$ 1,000.00$
AHU-6 11000 ea 21,700.00$ 1,300.00$
AHU-7 4225 ea 8,575.00$ 885.00$
AHU-8 12700 ea 24,900.00$ 1,450.00$
103,375.00$ 8,175.00$
Total 111,550.00$
Current total cost 80,300.74$
Dedicated outdoor air unit schedule
Symbol Supply CFM Unit Material cost Labor Cost
DOAS-1 4300 ea 23,800.00$ 2,675.00$
DOAS-2 3300 ea 17,800.00$ 2,500.00$
DOAS-3 4100 ea 23,800.00$ 2,675.00$
65,400.00$ 7,850.00$
Total 73,250.00$
Current total cost 52,729.98$
Air Handling Units Schedule
Current total cost takes into considerations the size, location, and time factors
in order to update the 2015 RSMeans costs to our project.
Symbol
Supply
CFM Unit
material
cost labour cost
F-1 100 ea 104.00$ 45.50$
F-2 75 ea 104.00$ 45.50$
F-3 100 ea 104.00$ 45.50$
F-4 1000 ea 385.00$ 30.50$
F-5 400 ea 124.00$ 62.50$
F-6 1425 ea 420.00$ 35.50$
F-7 1800 ea 475.00$ 47.50$
F-8 100 ea 104.00$ 45.50$
F-9 100 ea 104.00$ 45.50$
F-10 225 ea 164.00$ 45.50$
F-11 125 ea 104.00$ 45.50$
F-12 100 ea 104.00$ 45.50$
F-13 100 ea 104.00$ 45.50$
F-14 125 ea 104.00$ 45.50$
F-15 100 ea 104.00$ 45.50$
F-16 500 ea 183.00$ 100.00$
F-17 500 ea 183.00$ 100.00$
F-18 100 ea 104.00$ 45.50$
F-19 100 ea 104.00$ 45.50$
F-20 200 ea 164.00$ 45.50$
F-21 200 ea 164.00$ 45.50$
F-22 100 ea 104.00$ 45.50$
F-23 100 ea 104.00$ 45.50$
F-24 100 ea 104.00$ 45.50$
F-25 100 ea 104.00$ 45.50$
F-26 100 ea 104.00$ 45.50$
F-27 100 ea 104.00$ 45.50$
F-28 100 ea 104.00$ 45.50$
F-29 100 ea 104.00$ 45.50$
F-30 125 ea 104.00$ 45.50$
F-31 650 ea 190.00$ 100.00$
F-32 650 ea 190.00$ 100.00$
F-33 100 ea 104.00$ 45.50$
F-34 100 ea 104.00$ 45.50$
F-35 125 ea 104.00$ 45.50$
F-36 100 ea 104.00$ 45.50$
F-37 825 ea 385.00$ 30.50$
F-38 5200 ea 1,200.00$ 71.00$
F-38 4150 ea 1,000.00$ 61.00$
7,827.00$ 2,012.50$
Total Cost 9,839.50$
Current total cost 7,083.09$
Power Ventilator Scheule
Current total cost takes into considerations the size, location, and time factors in order to update the
2015 RSMeans costs to our project.
Teating, Adjustment and Balancing for HVAC
Item Quantity Unit price Total price
Air conditioning equipment 8 910.00$ 7,280.00$
Pump 9 320.00$ 2,880.00$
Unit heater 3 102.00$ 306.00$
Chiller 2 620.00$ 1,240.00$
Boiler 3 515.00$ 1,545.00$
Diffuse, griller and register 404 70.00$ 28,280.00$
Ductless split system heat pump 7 490.00$ 3,430.00$
Total Cost 44,961.00$
Current total cost 32,365.77$
Current total cost takes into considerations the size, location, and time factors in order to update the
2015 RSMeans costs to our project.
Duct work cost estimate 277,896.38$
Duct work insulation cost estimate 97,966.25$
Piping cost 163,530.91$
Piping insulation cost 38,253.83$
Heating 47,701.20$
Cooling 187,532.46$
Louver 13,037.01$
VAV terminal box 27,809.55$
pumps 56,897.42$
DOAS 52,729.98$
AHU 80,300.74$
7,083.09$
1,050,738.82
32365
1,083,103.82
Safety padding (wall padding)
Material cost:
Room no C107
Dimension of the room - 7'9"x5'9"
Area of wall padding required for the scope
Location L B H Area ThicknessMaterial
cost/Sqft
Total material
cost
2'3" 6' 13.5 2" 15.00$ 202.50$
5'7" 6' 33.5 2" 15.00$ 502.50$
8' 6' 48 2" 15.00$ 720.00$
8' 6' 48 2" 15.00$ 720.00$
Floor 8' 5'7" 45 2" 15.00$ 675.00$
Door 3' 7' 21 2" 15.00$ 315.00$
Door
including
frame
7'4" 3'4" 24.5
Door frame 3.5 1" 12.00$ 42.00$
Total 3,177.00$
Room no E112
Dimension of the room - 7'9"x5'9"
Location L B H Area ThicknessMaterial
cost/Sqft
Total material
cost
2'3" 6' 13.5 2" 15.00$ 202.50$
5'7" 6' 33.5 2" 15.00$ 502.50$
8' 6' 48 2" 15.00$ 720.00$
8' 6' 48 2" 15.00$ 720.00$
Floor 8' 5'7" 45 2" 15.00$ 675.00$
Door 3' 7' 21 2" 15.00$ 315.00$
Door
including
frame
7'4" 3'4" 24.5
Door frame 3.5 1" 12.00$ 42.00$
Total 3,177.00$
Material cost for 2 rooms = 6,354.00$
As per the project specification, the safety padding work will be done by a speciality contractor. For the
purpose of the project, the work is subcontracted to a speciality contractor (Gold safety padding) based
in Lehigh Acres, FL. The speciality contractor will be supplying the material as well as labor for
installation of the materials
Furnish, deliver and install Gold Medal Safety Padding to two (2) rooms at the above facility. The room
named “Time out” C-107 and E-112 are approximately 8’-4” x 6’-0” x 9’-0” in height. Gold Medal
Safety Padding is to be installed on the walls, interior side of the room door and door frame and the floor.
Padding shall be detailed to meet any vision lite in the door.
Wall padding dimension should not be less than 72" inch in height and 2" thickness for walls, floors and
doors and 1" thickness for door frame
Wall
Wall
Wastage (10%) = 635.40$
Total material cost = 6,989.40$
Material transportation cost
Approximate miles (to and fro) = 1500
Cost per mile including rental, fuel and driver wage = 1.50$
Total transportation cost = 2,250.00$
Labor cost calculation
Mobilization cost (Travel) = 500.00$
Labor cost Per hour = 67.50$
Duration (days) = 10
Total labor cost for 2 labors = 10,800.00$
Living allowance for the period of stay = 1,500.00$
Total labor cost = 12,800.00$
Tools for installation are included in the labor burden.
Total labor, material and transportation cost = 22,039.40$
Markup value (10%) = 2,203.94$
Total bid value for the scope of work = 24,243.34$
The speciality contractor has scheduled two experienced skilled labor to complete the scope of work. The
estimated completion of work is 5 days per room.
The material is assumed to be transported from Lehigh acres, FL to the project site location at
wilmington, NC
Traffic coating for second floor electrical rooms:
Room no Area (sft) CoatingUnit Material
cost
Unit
labor
cost
Total
material
cost
Total labor
cost
E206 2057 Primer 0.45 0.24 925.65$ 493.68$
2057 Base coat 0.59 0.49 1,213.63$ 1,007.93$
2057 Immediate coat 0.27 0.24 555.39$ 493.68$
2057 Top coat 0.07 0.21 143.99$ 431.97$
E208 113 Primer 0.45 0.24 50.85$ 27.12$
113 Base coat 0.59 0.49 66.67$ 55.37$
113 Immediate coat 0.27 0.24 30.51$ 27.12$
113 Aggregate 0.07 0.21 7.91$ 23.73$
2,994.60$ 2,560.60$
= 299.46$
Wastage (10% of total material cost) = 329.41$
Total cost = 6,184.07$
Current total cost = 4,451.68$
Accessory materials( joint sealants, sheet flashing,
adhesive, reinforcing strip)-10% of coating cost
Current total cost takes into considerations the size, location, and time factors in order to update the 2015
RSMeans costs to our project.
Direct Costs/ Trades Labor Material Equipment Sub- Contractors Sub -Total
95113 - Acoustic Ceiling $193,600.00 $270,495.00 $0.00 0 $464,095.0098433 - Acoustic Wall Units $4,752.00 $8,544.00 $0.00 0 $13,296.00102800 - Toilet Accessories & Partitions $10,718.00 $33,887.00 $0.00 0 $44,605.00104400 - Fire Protection Specialties $7,628.00 $4,814.00 $0.00 0 $12,442.00108316 - Banners $220.00 $300.00 $0.00 0 $520.00323113 - Fencing $4,000.00 $22,744.00 $520.00 0 $27,264.00Totals $220,918.00 $340,784.00 $520.00 0 $562,222.00Grand Total $562,222.00Sales Tax @5% $28,111.10General Conditions $27,145.00CoOH $38,564.00Sub Total $656,042.00Profit + Contingency @5% $32,802.10Sub Total $688,844.10Bonds (Performance, Payment) @5% $34,442.21
Total Bid Package $723,286.31
Trident Contractors Bid-Summary
Note: Toilet Accessory bid and Fire Protection Specialites bid from BMC will be used. On the next page, these two items have been removed from Trident's Bid
Project Bid
Note: The bid has general conditions listed separately. We need to divide the general conditions proportionally within the activities. Please see the next page for proportional division of general conditions. Also, the prices have been given for October 2016. They have been adjusted for Jan 2017.
Direct Costs/ Trades Labor Material EquipmentSub-
ContractorsSub -Total
95113 - Acoustic Ceiling $193,600.00 $270,495.00 $0.00 0 $464,095.0098433 - Acoustic Wall Units $4,752.00 $8,544.00 $0.00 0 $13,296.00108316 - Banners $220.00 $300.00 $0.00 0 $520.00323113 - Fencing $4,000.00 $22,744.00 $520.00 0 $27,264.00
Totals $202,572.00 $302,083.00 $520.00 $0.00 $505,175.00
Sales Tax @5% $25,258.75General Conditions $24,390.68CoOH $34,651.03Profit + Contingency @5% $29,473.77Bonds (Performance, Payment) @5% $30,947.46
$649,896.69
Item Value ($)
Adjustment for January 2017
95113 - Acoustic Ceiling $597,048.01 $600,630.3098433 - Acoustic Wall Units $17,105.01 $17,207.64108316 - Banners $668.97 $672.98323113 - Fencing $35,074.54 $35,284.98
Total $649,896.52 $653,795.90
Proportional Distribution of General Conditions in the Estimate. The values were then adjusted for Jan 2017.
Trident Contractors Bid-Summary
Schedule of values for the Items to be used
Grand Total
Trident Bid - Items to be used
Mark Up = 28.6478
Estimation
Materials Costs Quantity TotalsAcoustic Ceiling Tiles (Typical, per Sqft) 2.1 57355 $120,445.50
Acoustic Ceiling Tiles (Kitchen, per Sqft) 8 2824 $22,592.00
Metal Suspension System
Class A Suspension System (per Sqft.) 0.99 60179 $59,577.21
Hanging Wire 4' (per Sqft.) 0.37 60179 $22,266.23
Seismic Clips at cross tees (each) 3.02 15045 $45,435.90Acoustic Sealant (5 gal each, minimum quantity) 178 1 $178.00
Total Material Costs $270,495.00
LaborProductivity/
dayQuantity Time in days
Burderned; Per Carpenter ; Per Hour 55
Crew 8 -Carp
Crew Productivity
(Hours/unit)
Acoustic Ceiling Tiles (Typical, Sqft/day, 1 Carpenter) 450 57355 127
Acoustic Ceiling Tiles (Kitchen, Sqft/day, 1 Carpenter) 600 2824 5
Metal Suspension System
Class A Suspension System (Sqft/day, 1 Carpenter) 650 60179 93
Hanging Wire 4' (Sqft/day, 1 Carpenter) 650 60179 93
Seismic Clips at cross tees (each/day, 1 Carpenter) 120 15045 125
Using 8 man carpenter crew, Total Working Days 55
Total Time in hours (8 hour shifts) 3520
Total Labor Costs $193,600
Total Direct Costs $464,095.00
Detailed Estimate: Acoustic Ceiling
*Cost include 7% extra materials - 5% wastage, 2% Spare Storage as described in specifications
Trident Contractos
Costs Units Total
Labor
Burderned; Hourly, Each 55
2 -
Crew Carpenter
Crew Productivity
(Hours/sqft)
Total time (Hours) 0.1
Total Labor Costs ($) 86.4
Time in 1 working day 4752
No. of working days to 8
complete work 5
Materials Cost Quantity Total
Core: Glass Fiber Board (per Sqft) 8.9 864 7689.6
Facing Fabric (Acrylic) (per Sqft) 0.93 864 803.52
Mounting Device: "Z" Clips (Set of 8) 8.5 24 51
Total Material Costs 8544
Total Direct Cost $13,296
Detailed Estimate: Acoustic Wall Units
Trident Contractors
Costs Units Total
Labor
Burderned; Hourly, Each 55
Crew 2 - Carpenter
Crew Productivity (Hours/Each) 0.5
Total time (Hours) 4
Total Labor Costs ($) 220
Time in 1 working day 8
No. of working days to
complete work 1/2 Day
Materials Cost Quantity Total
14*11*10 - Triangular Sail Cloth/ each 35 6 210
15*14*14 - Triangular Sail Cloth/ each 45 2 90
Total Material Costs 300
Total Direct Cost $520
Detailed Estimate: Banners
Trident Contractors
Costs quantity Total
Labor & Equipment
Crew Calculations
Laborers / hour 40 2 80
Truck Driver / hour 45 1 45
Light Truck / day 250 1 250
Manual Fence Auger / day 10 1 10
Productivity
6' black chain link fence;
linear ft/ hour
200 1225 6.125
4' black chain link fence;
linear ft/ hour
400 1260 3.15
Gates (no/hour) 3 12 4
Total Working hours 13.275
Total working days 2
Total Crew Cost $4,520.00
Materials Cost Quantity Total
6' black chainlink fence 9.65 1225 11821.25
4' black chain link fence 7.6 1260 9576
4' wide gates for 4' fence 99.5 6 597
4' wide gates for 6' fence 125 6 750
Fabric Cloth 1.2 2485 2982
Total Material Costs $22,744.00
Total Direct Costs $27,264.00
Detailed Estimate: Fencing
Trident Contractors
Inc. Markup @ 26.64% DC (CoOH+P+C)
Final Electricity $300,892.00 $381,049.63 $383,335.93Landscaping and Irrigation $284,596.90 $360,413.51 $362,576.00Spray Fireproofing $352,859.10 $446,860.76 $449,541.93Misc Firestopping $153,500.00 $194,392.40 $195,558.75Structural and Misc Steel $760,400.70 $962,971.45 $968,749.28Ceramic Tiles $64,398.80 $81,554.64 $82,043.97Aluminum Canopies $149,714.00 $189,597.81 $190,735.40Flagpoles $9,800.00 $12,410.72 $12,485.18
Total $2,076,161.50 $2,629,250.92 $2,645,026.43
A&A Bid-Summary
Note: A&A had CoOH, Profit and Contingency listed separately as percentage values in the bid. It has been incorporated here. The values were then adjusted for Jan 2017
Construction ItemDirect Cost, Inc. Gen.
Conditions
Summary of Bid
Adjustment to Jan 2017
COST OF
LABOR
COST OF
EQUIPMENT
TOTAL COST
$6,156.50 $2,638.10 $8,795.00
$59,934.14 $43,935.40 $189,200.00
$32,390.26 $9,394.77 $54,260.97
$16,837.80 $32,340.90
$115,318.70 $55,968.27 $284,596.87TOTAL
Detailed Estimate: Landscape and Irrigation
A&A Contractors
Planting of trees, shrubs,perennials,
Irrigation of landscaping area
Removal of Existing Trees from site and
Preparation of soil, grading, excavation,
DESCRIPTION
ITEM COST
Panel and Switch Boards $64,939.00
Lights $159,874.00
Switches $35,235.00
Receptacles $25,961.00
Wires $14,883.00
Total Cost $300,892.00
Item Cost In Dollars
Beam $127,464.11
Column $41,373.10
Joist $27,080.11
Wall $124,863.70
Total $320,781.00
Cost Break Down: Spray Fireproofing
A&A Contractors
Breakdown of costs for Final Electricity
DESCRIPTION QUANTITY UNITSCOST OF
LABOR
COST OF
MATERIAL
COST OF
EQUIPMENTTOTAL COST
General Conditions: Transport, delivery of tiles on
site within stipulated time and storage of tiles,
grout according to ANSI A137.1 for labeling tile
packages and supervisory charges$2,700.90 $2,565.45 $589.87 $5,855.00
Structural Steel Columns 10,578.00 LB $4,800.00 $15,883.49 $2,160.00 $ 22843.5
Steel Beams for both floors 2,564.40 LF $5,760.00 $109,848.00 $4,320.00 $ 119928
Steel Joists for both floors 19,984.80 LF $26,640.00 $297,231.80 $15,960.00 $ 339831.8
Steel Deck 96,000.00 SF $26,938.00 $252,600.00 $2,760.00 $ 282298
TOTAL $64,137.60 $671,063.09 $25,200.00 $ 760400.69
A&A Contractors
Detailed Estimate: Structural Steel
DESCRIPTIONCOST OF
LABOR
COST OF
MATERIAL
COST OF
EQUIPMENTTOTAL COST
General Conditions: Site Supervisor,
Transportation are included in this
section. $4,250.00 $9,789.00 $14,039.00
Miscellaneous Fire Stopping including
Excavation,PCC, Drainage material, Pole, Bolts
& Anchorages, Concrete, Sealant
Crew K1$42,500.00 $97,000.00
TOTAL $42,925.00 $106,789.00 $149,714.00
Cost Breakdown: Aluminum Canopies
A&A Contractors
DESCRIPTION COST OF LABOR COST OF
MATERIAL
COST OF
EQUIPMENT
TOTAL COST
General Conditions: Site $ 900Flagpole erection including 2600 5200 1100 $ 8900
TOTAL 2600 5200 1100 $ 9800
Cost Breakdown: Flagpole
A&A Contractors
DESCRIPTION QUANTITY UNITS COST OF LABORCOST OF
MATERIAL
COST OF
EQUIPMENTTOTAL COST
General Conditions: Transport, delivery of tiles on site
within stipulated time and storage of tiles, grout according
to ANSI A137.1 for labeling tile packages and supervisory
charges
$2,700.90
$2,565.45 $589.87 $5,855.00
Flooring Tiles: Laying of Dal Tiles 8 x 8 color 1 graniti
including filling joints and cutting of tiles (Including
wastage)
3385 SF $13,255.66$6,076.70 $1,936.22 $21,268.50
Wall Tiles: Laying of American Olean Ceramic Tiles4 x 4
color 1 graniti including filling joints and cutting of tiles
(Including wastage)
6910 SF $13,742.60
$19,580.18 $3,952.52 $37,275.30
TOTAL 10295 $29,699.16 $28,222.33 $6,478.61 $64,398.80
A&A Contractors
Ceramic Tiles
DESCRIPTION COST OF LABORCOST OF
MATERIAL
COST OF
EQUIPMENTTOTAL COST
General Conditions: Site $14,000.00
Miscellaneous Fire Stopping $42,500.00 $97,000.00 $139,500.00
TOTAL $42,500.00 $97,000.00 $153,500.00
Miscellaneous Firestopping
A&A Contractors
No. Item Description Cost Cost Incl Markup Adjusted Cost*
1 General Conditions $79,739.00 $96,125.00 $81,254.462 Display Cases $4,180.00 $5,039.00 $4,259.473 Louvers $3,428.00 $4,132.00 $3,492.784 Spray Foam Beam Infill $3,150.00 $3,797.00 $3,209.605 Foam Insulation $67,115.00 $80,907.00 $68,390.697 Dry Wall- Wall $145,345.00 $175,213.00 $148,107.558 Dry Wall-Ceilings $7,519.00 $9,064.00 $7,661.809 Framing $86,730.00 $104,553.00 $88,378.65
10 Inwall Blocking $15,733.00 $18,966.00 $16,031.9611 Fiber Cement $4,084.00 $4,923.00 $4,161.4114 Security $103,620.50 $124,915.00 $105,590.6515 Communication $50,993.00 $61,472.00 $51,962.2816 Fire Alarm $126,558.00 $152,566.00 $128,964.04
$841,672.00 $711,465.34
Build Beast Bid-Summary
Time Location for Oct 2016 (Subcontractors Bid Initial Adjustment)
Note: The bid has general conditions listed separately. We need to divide the general conditions proportionally within the activities. Please see the next page for proportional division of general conditions. Also, the prices have been given for October 2016. They have been adjusted for Jan 2017 on the following page.
Summary of Detailed Estimation
Final Amount
*Adjusted Cost = Cost with Time and Location Adjustment
No. Item Description
Adjusted cost with general conditions distributed among
activites
Further Adjustment to Jan 2017
1 Display Cases $4,808.65 $4,837.502 Louvers $3,943.11 $3,966.773 Spray Foam Beam Infill $3,623.43 $3,645.174 Foam Insulation $77,208.45 $77,671.706 Dry Wall- Wall $167,203.38 $168,206.607 Dry Wall-Ceilings $8,649.65 $8,701.558 Framing $99,773.50 $100,372.159 Inwall Blocking $18,099.00 $18,207.59
10 Fibre Cement $4,697.95 $4,726.1413 Security $119,204.68 $119,919.9114 Communication $58,661.89 $59,013.8615 Fire Alarm $145,591.66 $146,465.21
$711,465.35 $715,734.15
Total Direct Costs Excluding GC $630,210.88
Gen Conditions $81,254.46
Gen Conditions as % of Direct cost excluding GC 12.89322%
Increase all activity costs by 12.89322% to distribute GC among direct costs.
Summary of Estimate
Final Amount
Proportional Distribution of General Condition among activites
Build Beast Bid-Summary
S.No Location Size Qty. Cost/Case Labor Total Remarks
1 Grid F/6.4 -8 36" x 60" x 16" 2 1,775$ 630.00$ 4,180.00$ Work will be done
in 1 day.
4,180$
5,039$
S.No.
1
2
A-101 First Floor Plan Area A
A-516 Misc. Details Cont.
Detailed Estimate: Display Cases
Build Beast
4.0 Display Cases
Totalinc. Markup
Drawing references
Drawing Number Description
Dimensions Qty.Material
CostLabor Cost
Equipment
Cost
Total Cost
(in $)
84" * 84" 1 400 18 0 418
84" * 90" 1 450 18 0 468
48" * 48" 1 210 18 0 228
72" * 18" 1 400 18 0 418
36" * 24" 1 150 18 0 168
24" * 18" 1 120 18 0 138
18" * 8" 1 90 18 0 108
HM-12 (6' * 2') 3 400 18 0 1254
HM-16 (3' * 2') 1 210 18 0 228
Total Cost $3,428
4,132$
Drawing References:
*Construction Subsystems & Partition Types A-001
*First Floor Plan Area "A"
*First Floor Plan Area "B"
*First Floor Plan Area "C"
*Second Floor Play Area "D" & "E"
5.0 LouversBare Cost
inc. Markup
Detailed Estimate: Louvers
Build Beast
S.No Location Type L W T Ld Qty.
Surface
Area
(sq. in.)
Material
Costs/sq.in.
Labor +
Eqmpt.
Cost/sq. in.
Total Remarks
1 Grid B/5.5-6 HSS 7 x 7 x 3/8 7 7 0.38 228 1 1425.00 0.02$ 0.01$ 41.36$
HSS 6 x 6 x 1/4 6 6 0.25 326 1 1793.00 0.02$ 0.01$ 52.05$
HSS 8 x 6 x 1/4 8 6 0.25 326 1 2445.00 0.02$ 0.01$ 70.97$
HSS 6 x 6 x 1/4 6 6 0.25 200 7 7700.00 0.02$ 0.01$ 223.51$
HSS 8 x 6 x 1/4 8 6 0.25 200 1 1500.00 0.02$ 0.01$ 43.54$
HSS 6 x 6 x 3/8 6 6 0.38 230 2 2415.00 0.02$ 0.01$ 70.10$
HSS 6 x 6 x 1/4 6 6 0.25 230 1 1265.00 0.02$ 0.01$ 36.72$
5 Grid B/6.5-7.7 HSS 18 x 6 x 1/4 18 6 0.25 320 1 5600.00 0.02$ 0.01$ 162.56$
6 Grid B/7-8 HSS 6 x 6 x 1/4 6 6 0.25 160 1 880.00 0.02$ 0.01$ 25.54$
7 Grid B/12.6-13 HSS 6 x 6 x 1/4 6 6 0.25 122 1 671.00 0.02$ 0.01$ 19.48$
8 Grid B-B3/13 HSS 6 x 6 x 1/4 6 6 0.25 60 1 330.00 0.02$ 0.01$ 9.58$
HSS 6 x 6 x 1/4 6 6 0.25 194 1 1067.00 0.02$ 0.01$ 30.97$
HSS 4 x 6 x 1/4 4 6 0.25 194 1 679.00 0.02$ 0.01$ 19.71$
HSS 10 x 6 x 1/4 10 6 0.25 194 1 1843.00 0.02$ 0.01$ 53.50$
10 Grid D4/10.9-12 HSS 8 x 6 x 1/4 8 6 0.25 194 1 1455.00 0.02$ 0.01$ 42.24$
11 Grid D4/10.9-12 HSS 8 x 6 x 1/4 8 6 0.25 180 1 1350.00 0.02$ 0.01$ 39.19$
32418.00 0.02$ 0.01$ 941$ A
S.No.
12
Grid B/9-10
S2.12 Low Roof Framing Plan - Area A & BS2.13 High roof framing - Area A & B
Detailed Estimate: Spray Foam in-fill for Beams
Build Beast
9 Grid B8/10.9-12
Total
Drawing references
Drawing Number Description
6.0 Spray foam in-fill for Beams
2 Grid B/6-7
3 Grid B/7-9
4
S.No Location Type Size L (in.) W (in.) T (in.) Ld (in.) Qty.(pcs)Surface Area
(sq. in.)
Material
Costs/sq.in.
Labor +
Eqmpt.
Cost/sq. in.
Total Remarks
C1 HSS 5 x 5 x 1/4 5 5 0.25 368 1 1656.00 0.02$ 0.01$ 48.07$
C3 HSS 6 x 6 x 1/4 6 6 0.25 368 12 24288.00 0.02$ 0.01$ 705.03$
C4 HSS 7 x 7 x 1/2 7 7 0.5 368 7 15456.00 0.02$ 0.01$ 448.65$
C5 HSS 7 x 7 x 5/16 7 7 0.31 368 6 14076.00 0.02$ 0.01$ 408.60$
C8 HSS 6 x 6 x 1/4 6 6 0.25 368 3 6072.00 0.02$ 0.01$ 176.26$
2Area A, B, C
(Remaining)C3 HSS 6 x 6 x 1/4 6 6 0.25 224 6 7392.00 0.02$ 0.01$ 214.57$
3 Area E, F C3 HSS 6 x 6 x 1/4 6 6 0.25 326 4 7172.00 0.02$ 0.01$ 208.19$
76112.00 0.02 0.01 2,209.36$ B
S.NoSurface Area
(sq in)
Material
Costs/sq.in.
Labor +
Eqmpt.
Cost/sq. in.
Total Remarks
1 32418.00 0.02$ 0.01$ 941.02$ A
2 76112.00 0.02$ 0.01$ 2,209.36$ B
3 108530.00 0.02 0.01 3,150$ C
3,798$ S.No Description Remarks
1Spray foam
infill
S.No.1
2
34
5
6
Spray foam in-fill overall
7.0 Spray foam in-fill for Columns
1
Area A, B, C
(Grid 5-13/B-
D8)
Total
Total Area (sq. ft.) Daily Output (sq. ft.) Number of Days
Description
Beams
Columns
S5.03 CMU Wall Elevations
S2.12 Low Roof Framing Plan - Area A & B
S2.13 High roof framing - Area A & B
S2.32 2nd Floor Framing Plan - Area D & E
Detailed Estimate: Spray Foam in-fill for Columns
Build Beast
S2.33 High roof framing - Area D & E
S2.34 Enlarged Second Floor Framing Plan
108530.00 1000 1
Drawing references
Drawing Number Description
Totalinc. Markup
Esitmated
Quantites
for Wall
Insulation
Wall
Section
Total
Length
Height
(ft.)
Rigid
Insulation
Area(1.5
inch thick)
(ft2)
Glass Fiber
Blanket
Area (6.0
inch
thick)(ft2)
Sound
Attenuation
Blanket
Area(3.5 inch
thick) (ft2)
Daily
Output
(ft2)
Material
Cost
No of
Labour
Labor
Cost
Equipment
Cost
Cost-Rigid
Insulation
Area(1.5 inch
thick) (ft2)
Cost-Glass
Fiber Blanket
Area (6.0 inch
thick)(ft2)
Cost-Sound
Attenuation
Blanket
Area(3.5 inch
thick) (ft2)
Total Cost
(in $)
W1 350 15 5250 730 1.13 3 0.53 0 8715 8715
W3 750 15 11250 730 1.13 3 0.53 0 18675 18675
W5 10 15 150 730 1.13 3 0.53 0 249 249
W7 100 15 1500 730 1.13 3 0.53 0 2490 2490
W10 75 15 1125 730 1.13 3 0.53 0 1868 1868
Floor 2 W1 400 16 6400 730 1.13 3 0.53 0 10624 10624
W1 350 15 5250 1350 0.39 2 0.29 0 3570 3570
W7 100 15 1500 1350 0.39 2 0.29 0 1020 1020
W10 75 15 1125 1350 0.39 2 0.29 0 765 765
Floor 2 W1 400 16 6400 1350 0.39 2 0.29 0 4352 4352
25 100 15 1500 1600 0.35 1 0.22 0 855 855
31 700 15 10500 1600 0.35 1 0.22 0 5985 5985
40 50 15 750 1600 0.35 1 0.22 0 428 428
41 10 15 150 1600 0.35 1 0.22 0 86 86
31 450 16 7200 1600 0.35 1 0.22 0 4104 4104
36 300 16 4800 1600 0.35 1 0.22 0 2736 2736
40 65 16 1040 1600 0.35 1 0.22 0 593 593
Total Cost $67,113
80,905$ *Total no of crew working for the installation of the Rigid Insulation is "3". Drawing References:
*Total time duration needed for the instalation of Rigid Insulation is 15 days. *Construction Subsystems & Partition Types A-001
*Total no of crew working for the installation of the Glass Fiber Insulation is "2". *First Floor Plan Area "A"
*Total time duration needed for the instalation of Glass Fiber Insulation is 5 days. *First Floor Plan Area "B"
*Total no of crew working for the installation of the Sound Attenuation Blanket is "1". *First Floor Plan Area "C"
*Total time duration needed for the instalation of Sound Attenuation Blanket is 8 days. *Second Floor Play Area "D" & "E"
inc. Markup
Detailed Estimate: Spray Foam Insulation
Build Beast
8.0 Spray Foam InsulationBare Cost
Floor 1
Floor 1
Floor 1
Floor 2
Length Thickness Cost of safety pad Total Material Total
Inch for PAD-Inch per square inch Cost Labour Cost
1 E212 Door 84 36 3024 2 0.04 120.96 0.008 24.192 145.152 2nd Floor Plan Area E
2 E212 Door Frame 88 40 496 1 0.032 15.872 0.008 3.968 19.84 2nd Floor Plan Area E
3 E212 Floor Area 98 93 9114 2 0.04 364.56 0.008 72.912 437.472 2nd Floor Plan Area E
4 E212 Wall Area 191 72 13752 2 0.04 550.08 0.008 110.016 660.096 2nd Floor Plan Area E
5 C107 Door 84 36 3024 2 0.04 120.96 0.008 24.192 145.152 2nd Floor Plan Area F
6 C107 Door Frame 88 40 3520 1 0.032 112.64 0.008 28.16 140.8 2nd Floor Plan Area F
7 C107 Floor Area 98 79 7742 2 0.04 309.68 0.008 61.936 371.616 2nd Floor Plan Area F
8 C107 Wall Area 177 72 12744 2 0.04 509.76 0.008 101.952 611.712 2nd Floor Plan Area F
Total 53416 2104.512 427.328 $2,532
3,052$ 92160 sq inches
1 day
A-103
A-104Reference Drawings
First Floor Plan Area C
Second Floor Area "D" & "E"
9.0 Wall Padding for Time Out Room
S.No Room no Type Width-Inch Area- Sq.In Labour Cost Total Cost Location
Detailed Estimate: Wall Padding for Time out room
Build Beast
inc. Markup
Daily output of 2 carpenter Total days required when 2 carpenter employed
Drywall
typeDescription
Length-
In
Height-
In
Area-
Sq.In
# of
Faces of
G.B
# of
Faces of
TBP
NoteMaterial
Cost
Labor
Cost
Equipment
Cost
Total Cost
($)
Duration
(Hours)
W7 Gypsum Board 5/8" 992 176 174592 2 384102 0 1387 2134 0 3521 40W7-W10 Gypsum Board 5/8" 236 176 41536 2 91379 0 330 508 0 838 10
25 Gypsum Board 5/8" 904 176 159104 1 175014 0 Music Room, Art 632 972 0 1604 1830 Gypsum Board 5/8" 306 176 53856 2 118483 0 Storage 428 658 0 1086 1231 Gypsum Board 5/8" 3001 176 528220 2 1162084 0 Conf,AV,Headend, 4196 6456 0 10652 12143 T.B.P 5/8" 94 176 16610 0 0 2 36542 Storage, PT/OT,Toilet 256 561 0 817 427 Gypsum Board 5/8" 40 176 7040 1 7744 0 28 43 0 71 129 Gypsum Board 5/8" 120 176 21120 1 23232 0 84 129 0 213 2
First Floor Area A Total 1962039 36542 7341 11461 0 18802
W1 Gypsum Board 5/8" 433 176 76142 2 167512 0 605 931 0 1536 17W7-W10 Gypsum Board 5/8" 550 176 96800 2 212960 0 769 1183 0 1952 22
30 Gypsum Board 5/8" 283 176 49808 2 109578 0 B125 Storage 396 609 0 1004 1136 Gypsum Board 5/8" 1244 176 218966 2 481725 0 1740 2676 0 4416 5031 Gypsum Board 5/8" 4948 176 870804 2 1915769 0 6918 10643 0 17561 20041 Tile Backing Panel 5/8" 77 176 13552 0 0 2 29814 209 458 0 667 342 G.B & TBP 5/8" 131 176 23078 1 25386 1 25386 270 531 0 800 543 T.B.P 5/8" 96 176 16896 0 0 2 37171 261 570 0 831 420 Gypsum Board 5/8" 184 176 32384 1 35622 0 129 198 0 327 4
First Floor Area B Total 2948552 92371 11295 17798 0 29094
36 Gypsum Board 5/8" 616 176 108328 2 238322 0 861 1324 0 2185 25W1 Gypsum Board 5/8" 3482 176 612898 2 1348376 0 4869 7491 0 12360 14031 Gypsum Board 5/8" 382 176 67144 2 147717 0 533 821 0 1354 15
31 Gypsum Board 5/8" 2078 176 365794 2 804747 0
Toilet
C133,C128,C129,Sma
ll group 2906 4471 0 7377 84
40 G.B & TBP 5/8" 487 176 85712 1 94283 1 94283
Toilet
C133,C108A,C107 1002 1971 0 2973 2030 Gypsum Board 5/8" 658 176 115808 2 254778 0 Toilet C133,134 920 1415 0 2335 27
36 Gypsum Board 5/8" 2431 176 427834 2 941235 0
Small Group,1st
grade left and right 3399 5229 0 8628 9825 Gypsum Board 5/8" 261 176 45936 1 50530 0 182 281 0 463 5
First Floor Area C Total 3829456 94283 14672 22722 0 37394
First Floor Area B
First Floor Area C
Detailed Esimate: Drywall for walls
Build Beast
10.0 DRYWALL FOR WALLSTotal Area G.B-
Sq.In
Including 10%
waste
Total Area
TBP Sq.In
Including 10 %
waste
First Floor Area A
Drywall
typeDescription
Length-
In
Height-
In
Area-
Sq.In
# of
Faces of
G.B
# of
Faces of
TBP
NoteMaterial
Cost
Labor
Cost
Equipment
Cost
Total Cost
($)
Duration
(Hours)
W1 Gypsum Board 5/8" 1814 192 348360 2 766392 0 On the Right 2768 4258 0 7025 80W1 Gypsum Board 5/8" 1330 192 255360 2 561792 0 On the left 2029 3121 0 5150 59
36 Gypsum Board 5/8" 2202 192 422760 2 930072 0
Parallel to x-axis
(Horizontal) 3359 5167 0 8526 97
31 Gypsum Board 5/8" 2522 192 484200 2 1065240 0
Parallel to x-axis &
Toilet D215,D216 3847 5918 0 9765 11124 Gypsum Board 5/8" 881 192 169104 1 186014 0 672 1033 0 1705 1940 G.B & TBP 5/8" 122 192 23424 1 25766 1 25766 274 539 0 812 546 T.B.P 5/8" 216 192 41472 0 0 1 45619 320 700 0 1020 5
Second Floor Area D Total 3535277 71386 13267 20736 0 34003
W1 Gypsum Board 5/8" 1531 192 293952 2 646694 0 2335 3593 0 5928 6724 Gypsum Board 5/8" 881 192 169104 1 186014 0 3rd Grade D219 672 1033 0 1705 1924 Gypsum Board 5/8" 440 192 84552 2 186014 0 3rd Grade D220 672 1033 0 1705 19
31 Gypsum Board 5/8" 2881 192 553176 2 1216987 0
Jan E203,Hub &
Storage D223,D222 4395 6761 0 11156 127
36 Gypsum Board 5/8" 923 192 177288 2 390034 0 E211 Toilet 1408 2167 0 3575 41
30 Gypsum Board 5/8" 512 192 98304 2 216269 0 781 1201 0 1982 23
Second Floor Area E Total 2842013 0 10263 15789 0 26052
15117337
Total
Area of
TBP
589164 $56,839 $88,506 0 $145,345 1611
175,214$ *-G.B-Gypsum Board
S.No. *-TBP-Tile Backing Panel
1
2 Crew of 10 carpenters complete this work in 20 days
3
4
5
A-103 First Floor Plan Area "C"
A-104 First Floor Plan Area "D" & "E"
Drawing references
Drawing Number Description
A-001 Construction Subsystems & Partition Types
A-101 First Floor Plan Area "A"
Detailed Esimate: Drywall for walls
Build Beast
A-102 First Floor Plan Area "B"
Total Area G.B-
Sq.In
Including 10%
waste
Total Area
TBP Sq.In
Including 10 %
waste Second Floor Area D
Second Floor Area E
Total Gypsum
Board Area for
Wallsinc. Markup
S.No
Base
Area in
Sq.in
Side
Area
Sq.in
Subtract
for
fixtures
Sq.in
Number of
Quantities
Total Area
Sq.in Including
10% waste
NoteMaterial
Cost
Labor
Cost
Equipment
Cost
Total
Cost
Duration
(Hours)
1 2592 1296 0 2 8554 Corridor A117 29.70 57.02 0 87 1.43
2 5280 1320 0 2 14520 Corridor A117 50.42 96.80 0 147 2.42
3 2460 660 0 2 6864 Corridor A117 23.83 45.76 0 70 1.14
4 7488 1872 0 1 10296 Corridor A117 35.75 68.64 0 104 1.72
5 1296 648 0 2 4277 Corridor A117 14.85 28.51 0 43 0.716 2304 432 0 2 6019 Corridor A117 20.90 40.13 0 61 1.00
7 1728 432 0 1 2376 Corridor A117 8.25 15.84 0 24 0.40
8 1440 216 0 2 3643 Corridor A117 12.65 24.29 0 37 0.61
9 5832 1332 320 2 15057 Corridor A117 52.28 100.38 0 153 2.5110 1080 180 0 1 1386 Stair A116 4.81 9.24 0 14 0.2311 2160 1620 0 1 4158 Stair A116 14.44 27.72 0 42 0.6912 44928 6240 0 1 56285 Cafeteria A133 195.43 375.23 0 571 9.3813 18720 16848 0 1 39125 Multipurpose A134 135.85 260.83 0 397 6.5214 33696 936 0 1 38095 Multipurpose A134 132.28 253.97 0 386 6.3515 16848 936 0 1 19562 Stage Curtain 67.93 130.42 0 198 3.2616 33696 25599 0 2 130449 Media Center A104 452.95 869.66 0 1323 21.7417 22646 14696 0 1 41076 Media Center A104-Arc 142.63 273.84 0 416 6.85
401742 1394.94 2678.28 0 4073
1 1108.5 739 0 1 2032.25 7.06 13.55 0 21 0.342 8720 516 1130 1 8916.6 30.96 59.44 0 90 1.493 2592 1296 0 2 8553.6 29.70 57.02 0 87 1.434 2736 456 0 1 3511.2 12.19 23.41 0 36 0.595 24884 6710 0 1 34753.4 Circle between Area A & B 120.67 231.69 0 352 5.796 4416 2920 0 2 16139.2 56.04 107.59 0 164 2.697 2592 2160 0 2 10454.4 36.30 69.70 0 106 1.748 7392 568 0 2 17512 60.81 116.75 0 178 2.929 8160 680 0 2 19448 67.53 129.65 0 197 3.24
121320.65 421.25 808.80 0 1230
11.0 DRYWALL FOR CEILING First Floor Area A
Total Area of Drywall in "A"
First Floor Area B
Total Area of Drywall in "B"
Detailed Estimate: Drywall for Ceiling
Build Beast
S.No
Base
Area in
Sq.in
Side
Area
Sq.in
Subtract
for
fixtures
Sq.in
Number of
Quantities
Total Area
Sq.in Including
10% waste
NoteMaterial
Cost
Labor
Cost
Equipment
Cost
Total
Cost
Duration
(Hours)
1 2496 416 1 3203.2 11.12 21.35 0 32 0.532 13824 1200 1130 1 15283.4 53.07 101.89 0 155 2.553 13824 1200 1130 1 15283.4 53.07 101.89 0 155 2.554 13824 1200 1130 1 15283.4 53.07 101.89 0 155 2.555 13824 1200 1130 1 15283.4 53.07 101.89 0 155 2.556 16164 1200 0 1 19100.4 66.32 127.34 0 194 3.187 11239 0 1130 1 11119.9 38.61 74.13 0 113 1.858 3744 3744 0 1 8236.8 28.60 54.91 0 84 1.379 8736 936 0 1 10639.2 36.94 70.93 0 108 1.77
10 11232 0 0 1 12355.2 42.90 82.37 0 125 2.0611 11232 0 1130 1 11112.2 38.58 74.08 0 113 1.8512 7999 0 1700 1 6928.9 24.06 46.19 0 70 1.15
143829.4 499.41 958.86 0 1458
1 4616 106 0 1 5194.2 Corridor 18.04 34.63 0 53 0.872 2308 1272 0 9 35442 Along Corridor 123.06 236.28 0 359 5.913 7488 3744 0 1 12355.2 Stair D218 42.90 82.37 0 125 2.06
52991.4 184.00 353.28 0 537
1 2308 1200 0 1 3858.8 Corridor 13.40 25.73 0 39 0.642 8238 1029.8 0 1 10194.525 Stair E204 35.40 67.96 0 103 1.703 8074.5 0 1130 1 7638.95 Toilet E211 26.52 50.93 0 77 1.27
21692.275 75.32 144.62 0 220
741575.725 $2,575 $4,944 0 $7,519 124
9,064$
S.No.
1 Crew of 10 carpenters will complete
2 this work in 1.5 days
3
4
5
First Floor Area C
A-001 Construction Subsystems & Partition Types
Total Area of Drywall in "C"
Second Floor Area D
Total Area of Drywall in "D"
Second Floor Area E
Total Area of Drywall in "E"
Total Area of Drywall in Ceilings
A-104 First Floor Plan Area "D" & "E"
Detailed Estimate: Drywall for Ceiling
Build Beast
A-101 First Floor Plan Area "A"
A-102 First Floor Plan Area "B"
A-103 First Floor Plan Area "C"
inc. Markup
Drawing references
Drawing Number Description
First Floor Linear Length- Inch Height-Inch
Area-Sq.In
Including
10% waste
Area-Sq.ft
Including
10% waste
Unit Material Cost Labor CostEquipment
CostTotal Cost
Duration
(Hours)
W1 3915 176 757944 5263.50 L.F 5154.75 4355.44 0 9510.19 789.53
W7 992 176 192051.2 1333.69 L.F 1583.07 1124.27 0 2707.33 200.05
W7-W10 786 176 152169.6 1056.73 L.F 1254.33 890.80 0 2145.13 158.51
20 184 176 35622.4 247.38 S.F 86.58 353.75 0 440.33 37.11
25 1165 176 225544 1566.28 S.F 767.48 2130.14 0 2897.61 234.94
27 40 176 7744 53.78 S.F 27.43 93.57 0 121.00 8.07
29 120 176 23232 161.33 S.F 109.71 225.87 0 335.57 24.20
30 1247 176 241419.2 1676.52 S.F 653.84 1827.41 0 2481.25 251.48
31 10408.875 176 2015158.2 13994.15 S.F 5457.72 15253.63 0 20711.35 2099.12
36 4290.5 176 830640.8 5768.34 S.F 3057.22 6402.86 0 9460.08 865.25
40 487 176 94283.2 654.74 S.F 320.82 890.45 0 1211.28 98.21
41 77 176 14907.2 103.52 S.F 50.73 140.79 0 191.52 15.53
42 131.25 176 25410 176.46 S.F 119.99 247.04 0 367.03 26.47
43 190.375 176 36856.6 255.95 S.F 174.05 358.33 0 532.37 38.39
$52,580 4846.86
Second Floor Linear Length- Inch Height-Inch Area-Sq.In Area-Sq.ft UnitMaterial
CostLabor Cost
Equipment
CostTotal Cost
Duration
(Hours)
W1 4675.375 192 987439.2 6857.22 L.F 6155.91 213.60 0 6369.51 1028.58
24 2201.875 192 465036 3229.42 S.F 1582.41 4392.01 0 5974.42 484.41
30 512 192 108134.4 750.93 S.F 292.86 818.52 0 1111.38 112.64
31 5403 192 1141113.6 7924.40 S.F 3090.52 8637.60 0 11728.11 1188.66
36 3125.25 192 660052.8 4583.70 S.F 2429.36 5087.91 0 7517.27 687.56
40 122 192 25766.4 178.93 S.F 87.68 243.35 0 331.03 26.84
46 216 192 45619.2 316.80 S.F 155.23 430.85 0 586.08 47.52
$33,618 3576.21
56154 $86,730 8423
104,553$
S.No. Drawing Number Crew of 16 carpenters will complete
1 A-001 this work in 65 days
2 A-101
3 A-102
4 A-103
5 A-104
6 S4.10 ~ S4.13
7 S3.01 ~ S3.04
8 A-351 ~ A357
Building Sections
Wall Sections
Build Beast
Detailed Estimate: Framing
Construction Subsystems & Partition Types
First Floor Plan Area "A"
First Floor Plan Area "B"
First Floor Plan Area "C"
First Floor Plan Area "D" & "E"
Framing Section & Details
12.0 FRAMING
Total Area Ceiling Drywall Total Cost Framing
inc. Markup
Drawing references
Description
Wall TypeLength of 2"x4" Inwall
Blocking Strips-Inch
Converting to
MBF + 10%
Waste
Material
Cost
Labor
CostEq. Cost Total Cost
Duration
(Hours)
W1 17180.75 1.0499 598.46 2756.08 0 3355 14.70
W7 1984 0.1212 69.11 318.27 0 387 1.70
W7-W10 1572 0.0961 54.76 252.18 0 307 1.34
24 4403.75 0.2691 153.40 706.43 0 860 3.77
25 2330 0.1424 81.16 373.77 0 455 1.99
30 3518 0.2150 122.54 564.35 0 687 3.01
31 31623.75 1.9326 1101.56 5072.98 0 6175 27.06
36 14831.5 0.9064 516.63 2379.22 0 2896 12.69
40 1218 0.0744 42.43 195.39 0 238 1.04
46 432 0.0264 15.05 69.30 0 84 0.37
41 154 0.0094 5.36 24.70 0 30 0.13
42 262.25 0.0160 9.14 42.07 0 51 0.22
43 380.75 0.0233 13.26 61.08 0 74 0.33
29 240 0.0147 8.36 38.50 0 47 0.21
27 80 0.0049 2.79 12.83 0 16 0.07
20 368 0.0225 12.82 59.03 0 72 0.31
80578.75 Total Cost $15,733 68.94
18,966$
*MBF- Million Board Feet i.e (Length in Inches* Width * Thickness)/144*1000
Crew of 2 members will complete this work in 4.5 days
S.No.
1
2
3
4
5
A-103 First Floor Plan Area "C"
A-104 First Floor Plan Area "D" & "E"
A-102 First Floor Plan Area "B"
Detailed Estimate: Inwall Blocking
Build Beast
A-001 Construction Subsystems & Partition Types
A-101 First Floor Plan Area "A"
13.0 INWALL BLOCKING
Total
Length inc. Markup
Drawing references
Drawing Number Description
S.NoLength-
InchWidth-Inch Area- Sq.In
Area Sq.ft+
10% wasteMaterial Cost Labor Cost
Equipment
costTotal Cost
Duration
(Hours)1 294.5 48 14136 107.98 178.17 188.97 0 367.14 3.24
2 384 300 115200 880.00 1452.00 1540.00 0 2992.00 26.40
3 232.63 120 27915 213.24 351.85 373.17 0 725.01 6.40
$4,084 36.04
4,923$
Crew of 2 member will complete
S.No. this work in 4.5 days
1
2
3
4
5
A-103 First Floor Plan Area "C"
A-104 First Floor Plan Area "D" & "E"
A-102 First Floor Plan Area "B"
Detailed Estimate: Fiber Cement
Build Beast
A-001 Construction Subsystems & Partition Types
A-101 First Floor Plan Area "A"
14.0 FIBER CEMENT
Total Fiber Cementinc. Markup
Drawing references
Drawing Number Description
Remarks
Discription Unit Area-A Area-B Area-C Area-D Area-E Total crew Unit Material Labor Equ.
AUDIO/VEDIO SYSTEM WALL OUTLET ea 2 2 1 3 1 elec 10 0.8 ea 139 42 543 3 Sytem having 30 outlets
PA/INTERCOM SPEAKER ea 35 20 20 20 6 101 11 112 1 elec 8 1 ea 115 52.5 18760 112CLASSROOM AUDIO SOUND
ENHANCEMENT SPEAKER ea 2 5 12 13 1 33 4 37 1 elec 5.33 1.501 ea 132 78.5 7788.5 56
PA SPEAKER ea 3 3 5 11 2 13 1 elec 8 1 ea 115 52.5 2177.5 13WALL SPEAKER FOR MULTIPURPOSE ROOM ea 2 2 1 3 1 elec 8 1 ea 115 52.5 502.5 3BUZZER/BELL ea 1 1 1 2 1 elec 8 1 ea 81.5 52.5 268 2SECURITY CAMERA
ea 20 9 9 1 39 4 43 1 elec 3 2.667 ea 500 140 27520 115 Camera price from net, all other from RS means
SECURITY CAMERA - 360 DEGREE FIELD OF
VIEW ea 1 2 1 3 7 1 8 1 elec 3 2.667 ea 600 140 5920 22 Camera price from net, all other from RS means
DOOR SWITCH/CONTACT ea 6 9 4 19 1 2 22 1 elec 5.3 1.509 ea 57.5 79 3003 32ELECTRIC STRIKE ea 2 2 1 1 4 1 elec 4 2 ea 325 105 1720 6VEDIO INTERCOM STATION FOR 2-WAY
COMMUNICATION FROM FRONT DOOR
ea 4 4 1 5 2 elec 2 8 ea 2275 420 13475 40
KEYPAD ea 4 1 5 1 6 1 elec 4 2 ea 140 105 1470 12 Assumed as per nearly matched item in RS means
MOTION DETECTOR, 360 DEGREE
COVERAGEea 3 1 4 1 1 6 1 elec 2.3 3.478 ea 225 182 2442 18
MOTION DETECTOR, CORRIDOR COVERAGEea 4 4 3 11 1 2 14 1 elec 2.3 3.478 ea 225 182 5698 46
SECURITY SYSTEM CONTROLLER/CONTROL
PANELea 1 1 2 1 1 4 2 elec 2 8 ea 2400 420 11280 24 Assume 20 channel system
PANIC ALARM PUSHBUTTON
ea 2 2 1 3 1 elec 4 2 ea 100 105 615 6Assumed as per nearly matched item in RS means
PUSHBUTTON FOR REMOTE DOOR
RELEASE ea 1 1 1 2 1 elec 4 2 ea 114 105 438 4
TOTAL $103,621 514
124,915$
Crew of 5 electrical person will complete this work in 13 days
S.No. RS means 2013 is used to calculate the the Bare cost of Labour, Material & Equ.
12345
17.0 ESTIMATION FOR SECURITY RELATED ITEMS
QUANTITY 2013 Bare Cost
Electrical 1st Floor Area A Auxiliary Systems Plan
Duration(
in Hrs)
inc. Markup
Extra
material
as per
contract
waste
(10%)
Total
(including
waste)
Daily
output
Labour
HrsTotal cost ($)
E-124 Electrical 1st Floor Area D & E Auxiliary Systems Plan
Detailed Estimate: Security System
Build Beast
http://security.panasonic.com/ is used for camera pricing.
E-122 Electrical 1st Floor Area B Auxiliary Systems PlanE-123 Electrical 1st Floor Area C Auxiliary Systems Plan
Drawing referencesDrawing Number Description
E-002 Electrical Legend E-121
Discription Unit Area-A Area-B Area-C Area-D Area-E Total crew Unit Material Labor Equ. Remarks
IT OUTLET FOR ACCESS POINTea 6 6 12 13 2 39 4 43 1 elec 8 1 ea 94.5 52.5 0.0 6321 43
DATA/TELEPHONE OUTLETea 16 27 5 3 3 54 6 60 1 elec 8 1 ea 94.5 52.5 0.0 8820 60
DATA OUTLET AT FLOOR ea 1 1 1 2 1 elec 8 1 ea 94.5 52.5 0.0 294 2DATA OUTLET AT FLOOR ea 3 3 1 4 1 elec 8 1 ea 94.5 52.5 0.0 588 4EQUIPMENT RACK/CABINET,
19"X7'ea 4 2 3 3 12 2 14 1 elec 1 8 ea 830 420 0.0 17500 112
DATA/TELEPHONE OUTLET ea 6 6 1 7 1 elec 8 1 ea 94.5 52.5 0.0 1029 7SYSTEM PRINTER ea 1 1 1 2 1 elec 8 1 ea 94.5 52.5 0.0 294 2 Assumed as per nearly matched item in RS means
BRIGHTLINK PROJECTORea 1 5 12 12 1 31 4 35 1 elec 8 1 ea 49 52.5 0.0 3552.5 35
DATA/TELEPHONE OUTLET FOR
TEACHER ea 1 5 12 13 1 32 4 36 1 elec 8 1 ea 94.5 52.5 0.0 5292 36
TV OUTLET ea 1 1 1 2 1 elec 8 1 ea 94.5 52.5 0.0 294 2 Assumed as per nearly matched item in RS means
VOIP RINGERea 2 5 12 13 1 33 4 37 1 elec 8 1 ea 94.5 52.5 0.0 5439 37
Assumed as per nearly matched item in RS means
TELEPHONE OUTLET FOR
ELEVATOR COMMUNICATION ea 1 1 1 2 1 elec 8 1 ea 94.5 52.5 0.0 294 2 Assumed as per nearly matched item in RS means
COMMUNICATIONS OUTLET FOR
FIRE ALARM SYSTEM ea 1 1 1 2 1 elec 8 1 ea 160 52.5 0.0 425 2Assumed as per nearly matched item in RS means
COMMUNICATIONS OUTLET FOR
FIRE SECURITY SYSTEM ea 2 1 3 1 4 1 elec 8 1 ea 160 52.5 0.0 850 4Assumed as per nearly matched item in RS means
TOTAL $50,993 348
61,471$
S.No. RS means 2013 is used to calculate the the Bare cost of Labour, Material & Equ.
123
45
Crew of 5 electrical person will complete this work in 9 days
Drawing Number Description
18.0 ESTIMATION FOR COMMUNICATION ITEMS
QUANTITY 2013 Bare Cost
waste
(10%)
Total
(includin
g waste)
Daily
output
Labour
Hrs
Total cost
($)
Duratio
n(in Hrs)
Detailed Estimate: Communication Systems
Build Beast
E-123 Electrical 1st Floor Area C Auxiliary Systems PlanE-124 Electrical 1st Floor Area D & E Auxiliary Systems Plan
E-002 Electrical Legend E-121 Electrical 1st Floor Area A Auxiliary Systems PlanE-122 Electrical 1st Floor Area B Auxiliary Systems Plan
inc. Markup
Drawing references
Remarks
Discription Unit Area-A Area-B Area-C Area-D Area-E Total crew Unit Material Labor Equ.
HORN/STROBE, 15 CANDELAea 4 8 10 5 1 28 2 3 33 1 elec 5.3 1.509 ea 149 79 7524 47
HORN/STROBE, 30 CANDELAea 1 1 1 1 3 1 elec 5.3 1.509 ea 149 79 684 4
HORN/STROBE, 75 CANDELAea 3 1 1 5 1 1 7 1 elec 5.3 1.509 ea 149 79 1596 10
HORN/STROBE, 95 CANDELAea 4 2 6 1 1 8 1 elec 5.3 1.509 ea 149 79 1824 11
HORN/STROBE, 115 CANDELAea 3 3 1 1 5 1 elec 5.3 1.509 ea 149 79 1140 7
STROBE, 15 CANDELAea 10 13 17 3 1 44 2 5 51 1 elec 5.3 1.509 ea 149 79 11628 74
STROBE, 30 CANDELAea 5 4 2 2 13 1 2 16 1 elec 5.3 1.509 ea 149 79 3648 23
STROBE, 75 CANDELAea 3 2 12 16 1 34 2 4 40 1 elec 5.3 1.509 ea 149 79 9120 58
STROBE, 95 CANDELAea 1 1 1 1 3 1 elec 5.3 1.509 ea 149 79 684 4
STROBE, 115 CANDELAea 1 1 1 1 3 1 elec 5.3 1.509 ea 149 79 684 4
CONTROL/RELAY MODULEea 5 3 2 6 16 1 2 19 1 elec 2 4 ea 540 210 14250 72
Assumption & reference from internet for
priceCONTROL/RELAY MODULE FOR SHUNT TRIP
ACTIVATION : PROVIDE POWER LTD WIRING
BARRIER IN J-BOX FOR 120V SEPARATION
ea 2 2 1 1 4 1 elec 2 4 ea 540 210 3000 12Assumption & reference from internet for
price
DUCT DETECTOR; PROVIDED BY FIRE ALARM
VENDOR ea 1 1 2 1 1 4 1 elec 3.2 2.5 ea 320 131 1804 8Installed by mechanical vendor co not
included labor cost
FIELD CHARGING POWER SUPPLY ea 1 2 1 4 1 5 1 elec 8 1 ea 570 52.5 3112.5 5FIRE ALARM PANEL ea 1 1 1 2 1 elec 1 16 ea 765 840 3210 32 Assume 8 zone fire alarm panel
HEAT DETECTOR ea 10 2 1 5 18 1 2 21 1 elec 8 1 ea 50 52.5 2152.5 20HEAT DETECTOR; FOR ELEVATOR SHUNT TRIP
ACTIVATION(SEE SPECIFICATIONS FOR ADDITIONAL
INFO)
ea 3 3 1 1 5 1 elec 8 1 ea 50 52.5 512.5 4
HORN/STROBE, 15 CANDELA
ea 1 1 1 1 3 1 elec 5.3 1.509 ea 149 79 684 4
HORN/STROBE, 75 CANDELA
ea 2 1 3 1 1 5 1 elec 5.3 1.509 ea 149 79 1140 7
MONITOR MODULE FOR FLOW SWITCH
0 0 1 elec 0 0
MONITOR MODULE FOR COOKING EXHAUST HOOD
FIRE SUPPRESSION ea 1 1 1 1 3 1 elec 4 2 ea 380 105 1455 4
MONITOR MODULE FOR TAMPER SWITCH
ea 6 6 1 1 8 1 elec 4 2 ea 380 105 3880 14
19.0 ESTIMATION FOR FIRE ALARM RELATED ITEMS
QUANTITY 2013 Bare Cost
Extra
material
as per
contract
waste
(10%)
Total
(including
waste)
Daily
output
Labour
HrsTotal cost ($)
Duration(
in Hrs)
Detailed Estimate: Fire Alarm Systems
Build Beast
Remarks
Discription Unit Area-A Area-B Area-C Area-D Area-E Total crew Unit Material Labor Equ.
MONITOR MODULE WITH SURGE SUPPRESSOR FOR
CONNECTION OF EXTERNAL CIRCUITRY ea 2 2 1 1 4 1 elec 4 2 ea 380 105 1940 6
MONITOR MODULE FOR MONITORING A DRY
CONTACT CLOSURE DEVICE ea 1 1 1 1 3 1 elec 4 2 ea 380 105 1455 4
POST INDICATOR VALVE TAMPER SWITCH ea 1 1 1 2 1 elec 2 4 ea 120 210 660 8Assumption & reference from internet for
pricePRESSURE SWITCH
ea 2 2 1 3 1 elec 8 1 ea 54.5 52.5 321 3Assumption & reference from internet for
pricePULL STATION ea 3 1 1 5 1 6 1 elec 8 1 ea 54.5 52.5 642 6REMOTE ANNUCIATOR ea 1 1 1 2 1 elec 2.6 6.154 ea 330 320 1300 13REMOTE INDICATOR WITH TEST SWITCH FOR DUCT
DETECTORea 1 1 2 1 3 1 elec 8 1 ea 65 52.5 352.5 3
Assumption & reference from internet for
priceSMOKE DETECTOR ea 55 47 43 38 8 191 12 20 223 1 elec 6.2 1.29 ea 108 67.5 39136.5 273SMOKE DETECTOR ea 6 5 8 2 1 22 2 3 27 1 elec 6.2 1.29 ea 108 67.5 4738.5 33STROBE, 15 CANDELA
ea 1 1 1 1 3 1 elec 5.3 1.509 ea 149 79 684 4
STROBE, 30 CANDELAea 2 2 1 1 4 1 elec 5.3 1.509 ea 149 79 912 5
STROBE, 75 CANDELAea 1 1 1 1 3 1 elec 5.3 1.509 ea 149 79 684 4
TOTAL $126,558 786
152,566$
Crew of 5 electrical person will complete this work in 20 days
S.No. RS means 2013 is used to calculate the the Bare cost of Labour, Material & Equ.
12 http://www.edwards-signals.com/ 345
QUANTITY
inc. Markup
Drawing referencesDrawing Number Description
Extra
material
as per
contract
waste
(10%)
Total
(including
waste)
Daily
output
Labour
HrsTotal cost ($)
Duration(
in Hrs)
2013 Bare Cost
E-123 Electrical 1st Floor Area C Auxiliary Systems PlanE-124 Electrical 1st Floor Area D & E Auxiliary Systems Plan
E-002 Electrical Legend E-121 Electrical 1st Floor Area A Auxiliary Systems Plan is used as internet reference for prices.
E-122 Electrical 1st Floor Area B Auxiliary Systems Plan
CONSTRUCTION ITEM Cost Cost Adjusted for Jan 2017
(Description) ($)
Kiln $4,290.00 $4,315.74
Misc. Steel $18,884.00 $18,997.30
Wall Graphics $3,000.00 $3,018.00
Signage and Marquee $24,702.00 $24,850.21
Plumbing $626,238.00 $629,995.43
Food Service Equipment $226,000.00 $227,356.00
Residental Appliances $7,448.00 $7,492.69
Roof Nailers $33,687.00 $33,889.12
Window Treatments $12,849.00 $12,926.09
Hollow metal, Wood doors, Toilet part, Toilet accessories, FEC
$269,631.00 $271,248.79
Coiling Doors $25,000.00 $25,150.00
Roof Expansion Joints $7,597.00 $7,642.58
Column Covers $2,640.00 $2,655.84
Stage Curtains, Folding stages, Cubicle curtains
$19,792.00 $19,910.75
Alum Storefront $347,800.00 $349,886.80
($)
Best Miscellaneous Construction (BMC) Bid-Summary
CONSTRUCTION ITEM Cost Cost Adjusted for Jan 2017
MILLWORK and WINDOW SEALS
$215,000.00 $216,290.00
Best Sub In Town (BSIT) Bid-Summary
($)(Description) ($)