CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
-
Upload
adam-rabb-cohen -
Category
Documents
-
view
216 -
download
0
Transcript of CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
1/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
2/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
3/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
4/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
5/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
6/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
7/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
8/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
9/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
10/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
11/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
12/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
13/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
14/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
15/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
16/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
17/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
18/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
19/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
20/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
21/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
22/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
23/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
24/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
25/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
26/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
27/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
28/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
29/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
30/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
31/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
32/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
33/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
34/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
35/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
36/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
37/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
38/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
39/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
40/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
41/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
42/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
43/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
44/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
45/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
46/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
47/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
48/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
49/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
50/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
51/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
52/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
53/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
54/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
55/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
56/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
57/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
58/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
59/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
60/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
61/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
62/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
63/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
64/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
65/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
66/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
67/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
68/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
69/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
70/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
71/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
72/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
73/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
74/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
75/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
76/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
77/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
78/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
79/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
80/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
81/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
82/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
83/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
84/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
85/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
86/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
87/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
88/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
89/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
90/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
91/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
92/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
93/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
94/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
95/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
96/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
97/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
98/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
99/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
100/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
101/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
102/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
103/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
104/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
105/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
106/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
107/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
108/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
109/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
110/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
111/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
112/243
8. There is concern about the main sluice gate operator located inside the station, that is used to cut off the gravity flow draining into the River, whether it is reliable in electric mode. It works in manual mode,but would be very time-consuming to operate manually.
9. Similarly, there is concern there may be electrical problems with the other main sluice gate operator,
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
113/243
y y p g plocated outside the station, that diverts from to the main pump wet well.
10. Heat for the building is now provided by gas unit heaters fueled with natural gas. The original boiler,located in the basement is no longer used.
11. The major issue at the station is that everything is manually operated, and must be monitoredcontinuously when operating and/or when expecting that operation may need to commence.
Additionally, during times of high river elevation, even when there is no storm run-off, the station mustbe manned around the clock to allow monitoring of the drainage inlet to the station, and occasionaloperation of the electric motor driven pump to pump down the inlet bay. During daytime, the operatormay be dispatched from the WWTP, but at times the WWTP is not manned, an operator must be present(paid on overtime) at the Main Station. At the time of my visit, the Connecticut River is running high,because of winter run-off farther north, requiring occasional operation of the electric motor driven pump.The dilema is that the cost to automate will be very high, because anything to be automated must bereplaced with new equipment. The trade-off is to choose the better option, whether to automate toreduce required manpower, but spend money on new equipment, pay personnel to manually operate theexisting old equipment.
12. There do not appear to be issues regarding the capacity of the station, although John noted that hehas observed the station to be in operation with all pumps running.
13. The engines and the right angle drives appear to have some lubricating oil leaks, some of which arecontrolled by absorbant sheets.
The West St. Pumping Station is located near the Mill River adjacent to the crossing of West St., on theprotected side of the flood wall. The pumping station draws from a storm water collection system, andpumps over the flood wall to discharge into the Mill River. The storm water collection system appears toserve a limited area inside the flood wall, that is a low point for collection of storm run-off.
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
114/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
115/243
Appendix B
Drainage Analysis
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
116/243
Summary Tables
Appendix B Drainage Analysis
Table B.1Bridge Street/Meadows Area Drainage AnalysisExisting Conditions Drainage Analysis Summary
Hydrologic Element LocationDrainage
Area(acres)
Tc CNPeak Rate of Runoff (cfs)
2-Yr 10-Yr 25-Yr 50-Yr 100-Yr
2 Lincoln Ave. 26.9 20 84 32.7 55.1 72.9 88.3 108.71 Bridge St. 17.7 20 70 9.1 20.6 30.7 39.9 52.6
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
117/243
B-1106678-80349-03-11
Junction-A 44.6 41.9 75.7 103.6 128.2 161.3Reach-1 39.3 71.3 97.8 121.1 152.5FG2 Fairgrounds Site 10.9 20 80 10.9 19.6 26.7 32.9 41.2FG5 Fairgrounds Site 3.4 25 74 2.2 4.4 6.3 7.9 10.2E-Pond2 21.5 2.2 3.8 4.5 5 5.5FG3 Fairgrounds Site 13.5 20 73 8.8 18.2 26.2 33.5 43.4E-Pump 0.4 0.4 0.4 0.4 0.4E-CP1 9.7 20.8 30 37.7 48.13 Old Ferry Rd. 5.2 15 66 2 5.1 8.1 10.9 14.8Junction-B 50.9 96 132.9 165.3 209.1Reach-2 47 88.1 122 152.5 193.64 Fair St. 10.4 15 85 14.4 24 31.6 38.1 46.8Junction-C 54.8 102.2 141.2 175.4 221.6Reach-3 36.2 67.2 92.9 115.8 146.86 38.7 25 66 12.9 33.4 52.1 69.3 93.4FG1 Fairgrounds Site 20.7 20 72 12.5 26.6 38.8 49.8 64.9FG6 Fairgrounds Site 0.7 15 79 0.7 1.3 1.8 2.3 2.8E-Pond1 24.8 0.7 2.9 11 22.4 39.2FG4 7.5 70 3.9 8.7 13 16.9 22.2E-CP2 32.3 3.9 8.7 15.2 30.8 53.75 Pomeroy Terrace 25.0 30 80 21.3 38.5 52.6 64.9 81.5Wetland 9.6 32.1 107.7 183.1 277.5Reach-4 9.6 31.3 102.3 172.8 265.17 Eastern Ave. 10.0 15 82 12 20.9 28.1 34.4 42.8Junction-E 12.8 32.8 105.5 177.5 273.2Reach-5 10.3 30.8 91.6 152.5 237.28 Valley St. 19.4 30 69 8 18.3 27.5 36.1 48
Appendix B Drainage Analysis
Table B.1 (Contd)Bridge Street/Meadows Area Drainage AnalysisExisting Conditions Drainage Analysis Summary
Hydrologic Element LocationDrainage
Area(acres)
Tc CNPeak Rate of Runoff (cfs)
2-Yr 10-Yr 25-Yr 50-Yr 100-Yr
Junction-E2 18.4 36.7 96.3 160 249.29 William St. 11.1 15 83 14.1 24.1 32.2 39.3 48.6
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
118/243
B-2106678-80349-03-11
10 Henry St. 9.7 15 74 7.2 14.7 21.2 26.9 34.8Junction-F 35.6 68.6 101.8 167.8 260.5Reach-6 35.4 67.9 101.6 167.6 260.311 2.4 15 70 1.3 3 4.4 5.8 7.6G-Mill River 36.6 70.4 102.1 168.3 261.413 Industrial Dr. 82.9 25 84 92.6 155.3 206.4 250.6 309.512 Marshall St. 34.8 30 82 32.9 57.5 77.3 94.6 117.742-inch Pipe 117.7 125.5 212.8 282.6 343.0 423.4
Flood Storage RoutingE-Pond1 (Inflow) 13.2 27.9 40.5 51.9 67.6E-Pond1 (Outflow) 24.8 0.7 2.9 11.0 22.4 39.2Maximum Stage (ft.) 116.5 117.0 117.1 117.2 117.3Spillway Elevation (ft.) 117.0 117.0 117.0 117.0 117.0E-Pond2 (Inflow) 13.0 23.9 32.8 40.7 51.4E-Pond2 (Outflow) 21.5 2.2 3.8 4.5 5.1 5.5Maximum Stage (ft.) 117.4 118.2 118.7 119.1 119.5Spillway Elevation (ft.) 119.5 119.5 119.5 119.5 119.5Wetland(Inflow) 57.3 112.9 165.2 221.7 300.6Wetland(Outflow) 9.6 32.1 107.7 183.1 277.5Maximum Stage (ft.) 115.6 116.5 116.6 116.6 116.7
Spillway Elevation (ft.) 116.5 116.5 116.5 116.5 116.5
Appendix B Drainage Analysis
Table B.2Elm Street Brook Area/Florence Area Drainage Analysis
Existing Conditions Drainage Analysis Summary
Hydrologic Element LocationDrainage
Area(acres)
Tc CNPeak Rate of Runoff (cfs)
2-Yr 10-Yr 25-Yr 50-Yr 100-Yr
A Bridge Rd. 27.1 15 72 17.5 37.5 55 70.8 92.5Junction-1 54.8 27.9 63.4 95.5 124.7 165.1
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
119/243
B-3106678-80349-03-11
B Strawberry Hill Rd. 27.7 15 67 11.8 29 45.3 60.3 81.4Junction-2 73.0 32.4 74.2 112.2 146.9 195C 18.2 15 66 7.1 18 28.5 38.2 51.8Junction-3 113.9 59.3 124.5 181 232.6 304.1D 6.8 15 77 6.2 11.8 16.5 20.6 26.2E 3.1 15 74 2.3 4.8 6.9 8.7 11.3F Straw Avenue 31.0 25 78 25.5 47.2 65.1 80.9 102.5Detention Basin 1 (Inflow) 59.3 124.5 181 232.6 304.1Detention Basin 1 (Outflow) 113.9 27 51.8 55.4 59 64.9Maximum Stage (ft) 186.9 188.1 188.2 188.4 188.5Spillway Elevation (ft) 187.5 187.5 187.5 187.5 187.5Junction-4 157.8 29.4 65.2 80.5 98.7 120.4G 20.7 15 72 13.4 28.7 42.1 54.2 70.8H 17.0 15 62 4.1 13 21.5 29.9 41.9I 6.3 15 61 1.3 4.5 7.5 10.5 14.9Junction-5 180.5 33.8 83 115.2 149.6 192.8J 14.6 15 66 5.7 14.5 22.9 30.7 41.6Detention Basin 2 (Inflow) 5.7 14.5 22.9 30.7 41.6Detention Basin 2 (Outflow) 14.6 3.3 6 7.8 9.2 10.8Maximum Stage (ft) 180.9 181.9 182.9 183.8 185.1Spillway Elevation (ft) 186 186 186 186 186
K 8.1 15 60 1.5 5.4 9.2 13 18.5Junction-6 208.6 34.6 89 128.9 171.6 229.3L 28.1 20 54 1.5 9.4 19.1 29.2 44.6Junction-7 241.6 42.0 108.7 165 222.3 295.5M Depot Avenue 23.0 25 64 6.2 17.5 28.1 37.9 51.9O 10.0 15 68 4.7 11.2 17.2 22.7 30.4
Appendix B Drainage Analysis
Table B.2 (Contd)Elm Street Brook Area/Florence Area Drainage Analysis
Existing Conditions Drainage Analysis Summary
Hydrologic Element LocationDrainage
Area(acres)
Tc CNPeak Rate of Runoff (cfs)
2-Yr 10-Yr 25-Yr 50-Yr 100-Yr
Junction-8 257.9 47.2 118.0 183.7 247.7 333.3P 16.3 15 73 11.3 23.7 34.4 44.1 57.3
J i 9 49 3 38 74 1 104 8 132 8 170 9
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
120/243
B-4106678-80349-03-11
Junction-9 49.3 38 74.1 104.8 132.8 170.9Junction-10 307.3 74.7 171.5 262.7 349.6 471.6Q Locust St. 26.4 15 76 22.5 43.9 61.9 77.9 99.7N North Main St. 23.0 20 74 16 32.3 46.3 58.7 75.7Junction-11 374.3 89.3 209.3 320.8 425.7 573.1S South Main St. 49.4 15 65 17.5 46.1 73.7 99.6 136.2R 17.6 15 61 3.7 12.6 21 29.5 41.7Junction-12 459.1 106.9 254.2 390.6 518.1 697.6Junction-13 478.1 93.2 221.7 340 450.5 607.2Junction-14 509.5 97.6 230.2 353.3 467.3 626.8Junction-15 535.0 101.7 237.8 364.1 481.8 646.4X North Elm St. 17.0 15 73 11.8 24.7 35.8 45.8 59.5Y 8.5 15 74 6.3 13 18.6 23.7 30.6W Hospital Rd. 31.4 15 70 17.5 39.2 58.8 76.6 101.3V Elm St. 19.0 15 73 13.2 27.6 40.1 51.3 66.7U South Main St. 68.4 25 67 25.1 62.5 96.2 127.2 170.3T 16.4 15 60 3 10.9 18.6 26.2 37.448-36-in Diversion 535.0 73.8 157.4 239.2 315.7 423.736-in pipe Junction 4.4 29.0 82.5 127.9 169.6 227CC Federal St. 76.5 15 73 53.0 111.2 161.4 206.6 268.3Z Milton St. 23.2 20 74 16.1 32.6 46.7 59.2 76.4DD Elm St. 4.4 20 82 4.8 8.4 11.2 13.7 17Junction-16 549.2 76.7 161.1 243.2 320.3 429.2
AA 48-inch Pipe 14.3 15 84 18.9 32 42.4 51.4 63.4Junction-17 565.2 76.6 156.7 235 308.5 412.1EE 16.0 15 68 7.6 17.9 27.5 36.4 48.7Junction-18 585.1 80.3 162.4 242.7 317.6 423.1
Appendix B Drainage Analysis
Table B.2 (Contd)Elm Street Brook Area/Florence Area Drainage Analysis
Existing Conditions Drainage Analysis Summary
Hydrologic Element LocationDrainage
Area(acres)
Tc CNPeak Rate of Runoff (cfs)
2-Yr 10-Yr 25-Yr 50-Yr 100-Yr
BB Washington St. 19.8 15 86 28.8 47.3 61.9 74.4 91.1Junction-19 27.5 27.2 82.2 126.3 167 223
D t ti P d 3 (I fl ) 27 2 82 2 126 3 167 223
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
121/243
B-5106678-80349-03-11
Detention Pond 3 (Inflow) 27.2 82.2 126.3 167 223Detention Pond 3 (Outflow) 27.5 26.9 75.7 104.3 150.2 210Maximum Stage (ft) 148.2 150.3 152.4 154.0 154.8Spillway Elevation (ft) 153.55 153.55 153.55 153.55 153.55Sink-1 689.1 123.6 261 376.8 485.6 664.3
Appendix B Drainage Analysis
Table B.3King Street/Market Street/Downtown Area Watershed Drainage Analysis
Existing Conditions Drainage Analysis Summary
Hydrologic Element LocationDrainage Area
Tc CN2-year 10-year 25-year 50-year 100-year
(cfs) (ac-ft) (cfs) (ac-ft) (cfs) (ac-ft) (cfs) (ac-ft) (cfs)(mi 2) (ac)
KS-E 0.0302 19.3 19 95 46.8 5.0 56.7 6.1 70.4 4.8 82.1 9.1 97.7
KS-F 0.0278 17.8 15 83 31.8 3.0 41.6 3.9 55.4 3.5 67.4 6.4 83.4
J-1 King Street @ Church 0 0580 37 1 78 3 8 0 978 10 0 125 2 4 2 148 7 15 4 180 0
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
122/243
B-6106678-80349-03-11
J-1 King Street @ ChurchStreet 0.0580 37.1 78.3 8.0 97.8 10.0 125.2 4.2 148.7 15.4 180.0
KS-G 0.0394 25.2 15 87 52.5 4.9 66.6 6.3 86.5 3.9 103.6 9.9 126.2
King 36" 0.0580 37.1 73.3 8.0 91.6 10.0 117.2 4.2 139.2 15.4 168.4
J-2 King Street @ Finn Street 0.0973 62.3 100.4 12.9 125.6 16.3 161.1 4.1 191.5 25.4 232.0
King 48" 0.0973 62.3 98.9 12.9 123.9 16.3 158.8 4.1 188.8 25.4 228.8
KS-I 0.0249 16.0 15 92 38.8 3.7 47.8 4.6 60.2 4.5 70.9 7.0 84.9
J-3 0.1223 78.3 114.3 16.6 142.9 20.9 182.9 4.2 217.3 32.4 263.0
Div. at North St King Street @ NorthStreet 0.1223 78.3 114.3 16.6 142.9 20.9 182.9 4.2 183.1 31.3 183.1
King 48"/54" 0.1223 78.3 112.8 16.6 141.2 20.9 181.0 4.2 183.1 31.3 183.1
KS-J 0.0258 16.5 15 89 36.7 3.5 46.0 4.4 59.0 4.1 70.2 6.8 84.9
KS-K 0.0324 20.7 15 88 44.6 4.2 56.3 5.3 72.6 4.0 86.6 8.4 105.2
KS-L 0.0425 27.2 15 85 52.7 4.9 67.9 6.4 89.2 3.7 107.7 10.2 132.2
KS-M 0.0070 4.5 15 84 8.4 0.8 10.9 1.0 14.4 3.6 17.5 1.7 21.5
J-8 Trumbull @ State Street 0.0820 52.4 105.7 9.9 135.0 12.7 176.2 3.8 211.8 20.2 258.9
Trumbull 24" 0.0820 52.4 103.8 9.9 132.6 12.7 173.0 3.8 207.8 20.2 253.8
J-7 King Street @ TrumbullRoad 0.2300 147.2 184.0 29.9 234.0 38.0 304.1 4.0 364.3 58.4 443.9
King 54" 0.2300 147.2 183.2 29.9 232.8 38.0 302.4 4.0 362.4 58.4 441.4
KS-Q 0.0386 24.7 15 94 63.1 6.2 76.9 7.6 95.9 4.7 112.2 11.3 133.7
J-9 0.2686 171.9 229.7 36.1 289.7 45.6 373.8 4.1 446.0 69.7 541.7
King 54"/66" 0.2686 171.9 225.1 36.1 283.8 45.6 366.1 4.1 436.8 69.7 529.8
KS-R 0.0230 14.7 15 96 39.1 3.9 47.2 4.8 58.4 4.9 67.9 7.0 80.6
J-10 0.2916 186.6 243.0 40.0 305.4 50.4 392.8 4.2 467.9 76.8 567.1
Div. at Main St King Street @ Strong Ave 0.2916 186.6 232.8 39.6 235.4 47.7 285.2 3.8 285.2 68.3 285.2
King 60"/66" 0.2916 186.6 218.0 39.6 229.4 47.7 282.5 3.8 285.2 68.3 285.2
KS-T 0.0164 10.5 15 97 28.4 2.9 34.1 3.5 42.0 5.0 48.8 5.1 57.8
Appendix B Drainage Analysis
Table B.3 (Contd)King Street/Market Street/Downtown Area Watershed Drainage Analysis
Existing Conditions Drainage Analysis Summary
Hydrologic Element LocationDrainage Area
Tc CN2-year 10-year 25-year 50-year 100-year
(cfs) (ac-ft) (cfs) (ac-ft) (cfs) (ac-ft) (cfs) (ac-ft) (cfs)(mi 2) (ac)
J-12 King Street @ PleasantStreet 0.3079 197.1 221.9 42.5 234.9 51.2 289.1 3.9 292.9 73.4 296.8
King Street Old Mill River 0.3079 197.1 221.9 42.5 234.9 51.2 289.1 3.9 292.9 73.4 296.8
S A 0 0119 6 1 9 19 9 2 0 2 1 2 30 0 8 3 0 3 6 1 6
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
123/243
B-7106678-80349-03-11
KS-U Hampton Avenue 0.0119 7.6 15 95 19.9 2.0 24.1 2.4 30.0 4.8 35.0 3.6 41.6
Old Mill River 0.0119 7.6 19.9 2.0 24.1 2.4 30.0 4.8 35.0 3.6 41.6
KS-A Culvert @ Bikeway 0.0707 45.2 34 78 47.1 6.1 64.1 8.3 88.8 3.0 110.5 14.2 139.9
Brook Rail Trail 0.0707 45.2 45.4 6.1 61.8 8.3 85.5 3.0 106.4 14.2 134.7
KS-B 0.0293 18.7 27 75 18.7 2.2 26.2 3.1 37.2 2.8 47.0 5.4 60.4
J-4 Culvert @ WoodmontRoad 0.0999 63.9 53.3 8.4 72.5 11.3 100.6 3.0 125.3 19.6 158.7
Brook Woodmont Rd 0.0999 63.9 52.9 8.4 72.1 11.3 99.9 3.0 124.5 19.6 157.7
KS-D 0.0233 14.9 31 92 27.8 3.5 34.3 4.3 43.3 4.5 50.9 6.6 61.0
KS-C 0.0145 9.3 15 83 16.6 1.5 21.7 2.0 29.0 3.5 35.2 3.3 43.6
J-5Old Market Street @Highland Avenue 0.1377 88.1 66.5 13.4 89.0 17.7 121.5 3.3 150.2 29.5 188.8
Market 48" 0.1377 88.1 66.0 13.4 88.3 17.7 120.7 3.3 149.1 29.5 187.4
KS-H 0.0097 6.2 15 89 13.8 1.3 17.3 1.6 22.2 4.1 26.4 2.6 31.9
J-6 Old Market Street @North Street 0.1474 94.4 68.9 14.7 90.8 19.3 123.6 3.3 182.1 33.1 264.6
Market 44"/48" 0.1474 94.4 68.0 14.7 89.9 19.3 122.5 3.3 174.8 33.1 255.6
KS-O 0.0480 30.7 19 89 63.5 6.4 79.6 8.1 102.1 4.1 121.3 12.7 146.7
KS-P 0.0065 4.2 20 90 8.7 0.9 10.9 1.1 13.9 4.2 16.5 1.8 19.8
KS-N Market Street @ WalnutStreet 0.0357 22.8 26 82 32.1 3.7 42.3 4.8 56.8 3.4 69.5 8.0 86.4
Market 18"/21" 0.0357 22.8 29.7 3.7 39.2 4.8 52.6 3.4 64.3 8.0 80.0
J-11Old Market Street @Bridge Street 0.2376 152.1 137.1 26.2 193.5 36.1 263.0 4.0 371.2 64.0 543.3
Market 72" 0.2376 152.1 120.5 26.2 189.3 36.1 260.9 4.0 367.1 64.0 534.9
KS-S 0.0370 23.7 16 89 51.7 5.0 64.8 6.3 83.2 4.1 98.8 9.8 119.5
J-13 Old Market Street @Hancock Street 0.2746 175.8 133.3 31.1 199.2 42.4 272.2 4.0 387.0 73.8 558.2
Market 82" 0.2746 175.8 128.6 31.1 198.0 42.4 271.2 4.0 384.6 73.8 553.7
Appendix B Drainage Analysis
Table B.3 (Contd)King Street/Market Street/Downtown Area Watershed Drainage Analysis
Existing Conditions Drainage Analysis Summary
Hydrologic Element Location Drainage Area Tc CN2-year 10-year 25-year 50-year 100-year
(cfs) (ac-ft) (cfs) (ac-ft) (cfs) (ac-ft) (cfs) (ac-ft) (cfs)
KS-W 0.0151 9.7 15 90 22.2 2.1 27.7 2.6 35.3 4.2 41.8 4.1 50.4
KS-V 0.0049 3.1 15 96 8.4 0.8 10.1 1.0 12.5 4.9 14.5 1.5 17.2
J-14 Old Market Street @Holyoke Street 0.2947 188.6 133.6 34.1 202.7 46.0 276.6 4.0 392.7 79.4 563.1
M k t 60" 0 2947 188 6 130 5 34 1 202 2 46 0 275 7 4 0 390 2 79 4 558 5
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
124/243
B-8106678-80349-03-11
Market 60" 0.2947 188.6 130.5 34.1 202.2 46.0 275.7 4.0 390.2 79.4 558.5
KS-X 0.0058 3.7 15 85 7.1 0.7 9.2 0.9 12.1 3.7 14.6 1.4 17.9
J-15 Old Market Street @Hockanum Road 0.3004 192.3 131.5 34.7 203.3 46.9 277.0 4.0 392.0 80.8 560.6
Market Street Old MillRiver 0.3004 192.3 131.5 34.7 203.3 46.9 277.0 4.0 392.0 80.8 560.6
Appendix B Drainage Analysis
Table B.4Austin Circle/Ryan Road Area Drainage AnalysisExisting Conditions Drainage Analysis Summary
Hydrologic Element LocationDrainage Area
Tc CN2-year 10-year 25-year 100-year
(mi 2) (ac) (cfs) (cfs) (cfs) (cfs)RR-A1 Gregory Lane 0.0455 29.1 34 56 5.3 10.6 20.2 44.1Gregory Ln DB 0.0455 29.1 2.1 2.9 3.2 3.8Detention Basin (Inflow) 5.3 10.6 20.2 44.1Detention Basin (Ouflow) 2.1 2.9 3.2 3.8
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
125/243
B-9106678-80349-03-11
( )Maximum Stage (ft) 282.7 283.6 285.1 288.0Peak Storage (acre-ft) 0.3 0.5 1.3 3.2Top of Basin (ft) 288.0 288.0 288.0 288.0RR-A2 Matthew Lane 0.0248 15.9 16 50 1.2 3.3 8.4 23.1Matthew Dr DB 0.0703 45.0 2.3 3.3 4.1 5.6Detention Basin (Inflow) 2.6 5.0 9.9 24.6Detention Basin (Ouflow) 2.3 3.3 4.1 5.6Maximum Stage (ft) 280.2 280.9 281.7 283.7Peak Storage (acre-ft) 0.2 0.3 0.6 1.3Top of Basin (ft) 284.0 284.0 284.0 284.0Matthew Drive Route 0.0703 45.0 2.3 3.3 4.1 10.8RR-A3-1 0.0377 24.1 45 59 5.6 10.2 18.0 36.6RR Elem School 0.0377 24.1 5.6 10.2 18.0 36.5RR-B Penscal Drive Area 0.0100 6.4 15 63 3.5 5.8 9.5 17.8J-1 Outlet at Elementary School 0.1179 75.4 7.0 13.5 24.5 48.1Ryan Road Channel 1 Btw School and Brierwood Dr. 0.1179 75.4 7.0 13.4 24.1 47.4RR-D Brierwood Drive/Austin Circle Area 0.0378 24.2 19 60 8.9 16.1 27.9 55.8J-4 Brierwood Drive Culvert 0.1557 99.6 11.6 20.2 34.9 70.5Ryan Road Channel 2 Btw Brierwood and Acrebrook Dr. 0.1557 99.6 11.5 20.1 34.8 70.3RR-G Acrebrook Drive Area 0.0332 21.2 15 71 21.0 30.6 45.1 76.4
J-5 Acrebrook Drive Culvert 0.1888 120.9 25.1 40.3 64.9 121.5 Acrebrook Drive 0.1888 120.9 25.1 40.3 64.9 121.5
Appendix B Drainage Analysis
Table B.5Bridge Street/Meadows Area Drainage AnalysisFuture Conditions Drainage Analysis Summary
Hydrologic Element LocationDrainage
Area(acres)
Tc(min) CNPeak Rate of Runoff (cfs)
2-Yr 10-Yr 25-Yr 50-Yr 100-Yr
2 Lincoln Ave. 0.0 20 86 35.8 58.5 76.4 91.8 112.21 Bridge St. 0.0 20 71 9.9 21.7 32 41.3 54.1
Junction-A 0.0 45.7 80.2 108.4 133.1 166.3
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
126/243
B-10106678-80349-03-11
Reach-1 0.0 43 75.6 102.4 125.8 157.33 Old Ferry Rd. 0.0 15 67 2.2 5.5 8.5 11.3 15.3Junction-B 0.0 45 80.3 109.4 135 169.4Reach-2 0.0 41.5 73.6 100.1 123.4 154.94 Fair St. 0.0 15 86 15.1 24.7 32.3 38.9 47.6Junction-C 0.0 49.7 87.7 118.9 146.3 183.3Reach-3 0.0 32.9 58 79 97.4 122.2FGP1 Fairgrounds Site 0.0 15 78 34.6 64.8 90 112.1 142FGP7 Fairgrounds Site 0.0 25 74 2.2 4.4 6.3 7.9 10.2Ppond2 0.0 4.4 10.8 13.7 15.5 17.9
SWTC2 0.0 4.4 10.8 13.7 15.5 17.9FGP3 Fairgrounds Site 0.0 15 79 8.4 15.5 21.3 26.5 33.4FGP8 Fairgrounds Site 0.0 15 79 0.7 1.3 1.8 2.3 2.8Ppond4 0.0 1.8 4.8 8.1 10.9 13.1SWCT1 0.0 1.8 4.8 8.1 10.9 13.1FGP2 Fairgrounds Site 0.0 15 82 5.8 10.2 13.7 16.8 20.9Ppond1 0.0 1.4 3.5 5.6 7.4 9.9FGP6 Fairgrounds Site 0.0 15 95 2.1 3 3.8 4.4 5.2SWTC3 0.0 2.5 4.8 7.5 9.7 12.8FGP5 Fairgrounds Site 0.0 15 80 0.6 1.1 1.5 1.9 2.4Ppond3 0.0 7.6 19.4 28.3 35.3 42.7FGP4 Fairgrounds Site 0.0 20 76 1.3 2.5 3.4 4.3 5.5FGP9 0.0 15 87 0.7 1.1 1.4 1.7 2.1P-CP2 0.0 7.9 20.3 30.4 38.2 476 0.0 25 66 12.9 33.4 52.1 69.3 93.45 Pomeroy Terrace 0.0 30 81 22.5 39.9 54.2 66.6 83.1
Appendix B Drainage Analysis
Table B.5 (Contd)Bridge Street/Meadows Area Drainage AnalysisFuture Conditions Drainage Analysis Summary
Hydrologic Element LocationDrainage
Area(acres)
Tc(min) CNPeak Rate of Runoff (cfs)
2-Yr 10-Yr 25-Yr 50-Yr 100-Yr
Wetland 0.0 10.4 41.3 110.2 174.2 253.2Reach-4 0.0 10.4 40 104.5 165.6 242.1
7 Eastern Ave. 0.0 15 83 12.6 21.6 28.9 35.2 43.6J ti E 0 0 13 2 41 7 107 7 170 4 250 3
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
127/243
B-11106678-80349-03-11
Junction-E 0.0 13.2 41.7 107.7 170.4 250.3Reach-5 0.0 10.9 38.5 94 147.9 220.18 Valley St. 0.0 30 70 8.7 19.3 28.7 37.4 49.4Junction-E2 0.0 19.3 40.8 98.7 155.1 232.39 William St. 0.0 15 85 15.5 25.8 33.9 41 50.310 Herny St. 0.0 15 75 7.7 15.4 21.9 27.7 35.7Junction-F 0.0 38.2 72 104.4 162.8 243.1Reach-6 0.0 37.9 71.1 104.1 162.6 242.611 0.0 15 70 1.3 3 4.4 5.8 7.6G-Mill River 0.0 39.1 73.6 104.6 163.3 243.7
13 Industrial Dr. 0.0 25 85 96.9 160.4 211.7 256 314.812 Marshall St. 0.0 30 83 34.6 59.5 79.5 96.8 119.942-inch Pipe 0.0 131.5 219.6 289.7 350.1 430.5
Flood Storage RoutingP-Pond1 (Inflow) 5.8 10.2 13.7 16.8 20.9P-Pond1 (Outflow) 0.0 1.4 3.5 5.6 7.4 9.9Maximum Stage (ft.) 112.3 112.7 113.0 113.3 113.6Pond Surface Elevation (ft.) 115.0 115.0 115.0 115.0 115.0P-Pond2 (Inflow) 36.2 68.4 95.2 118.9 150.8P-Pond2 (Outflow) 0.0 4.4 10.8 13.7 15.5 17.9Maximum Stage (ft.) 114.1 115.1 116.0 119.6 119.9Pond Surface Elevation (ft.) 119.0 119.0 119.0 119.0 119.0P-Pond3 (Inflow) 7.7 19.7 28.7 35.7 43.0P-Pond3 (Outflow) 0.0 7.6 19.4 28.3 35.3 42.7Maximum Stage (ft.) 113.2 113.4 113.6 113.7 113.8
Appendix B Drainage Analysis
Table B.5 (Contd)Bridge Street/Meadows Area Drainage AnalysisFuture Conditions Drainage Analysis Summary
Hydrologic Element LocationDrainage
Area(acres)
Tc(min) CNPeak Rate of Runoff (cfs)
2-Yr 10-Yr 25-Yr 50-Yr 100-Yr
Pond Surface Elevation (ft.) 114.0 114.0 114.0 114.0 114.0Spillway Elevation (ft.) 112.85 112.85 112.85 112.85 112.85
P-Pond4 (Inflow) 9.1 16.8 23.2 28.7 36.2P Pond4 (Outflow) 0 0 1 8 4 8 8 1 10 9 13 1
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
128/243
B-12106678-80349-03-11
P-Pond4 (Outflow) 0.0 1.8 4.8 8.1 10.9 13.1Maximum Stage (ft.) 112.7 113.3 113.8 114.2 114.8Spillway Elevation (ft.) 117.0 117.0 117.0 117.0 117.0Wetland (Inflow) 54.8 119.9 173.5 218.9 280.6Wetland (Outflow) 180.6 10.4 41.3 110.2 174.2 253.2Maximum Stage (ft.) 115.7 116.5 116.6 116.6 116.7Spillway Elevation (ft.) 116.5 116.5 116.5 116.5 116.5
Appendix B Drainage Analysis
Table B.6Elm Street Brook Area/Florence Area Drainage Analysis
Future Conditions Drainage Analysis Summary
Hydrologic Element LocationDrainage
Area(acres)
Tc CNPeak Rate of Runoff (cfs)
2-Yr 10-Yr 25-Yr 50-Yr 100-Yr
G 0.0 15 73 14.4 30.1 43.8 56.0 72.7 A Bridge Rd. 0.0 15 73 18.8 39.4 57.1 73.1 95.0
Reach-A 0.0 17.8 36.2 52.2 66.9 87.0B Strawberry Hill Rd 0 0 15 68 12 2 29 9 46 6 62 0 83 3
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
129/243
B-13106678-80349-03-11
B Strawberry Hill Rd. 0.0 15 68 12.2 29.9 46.6 62.0 83.3Reach-B 0.0 12.0 30.2 46.6 61.5 82.2Junction-1 0.0 29.5 66.1 98.7 128.4 169.3Reach-C 0.0 28.1 61.7 91.6 119.3 157.6C 0.0 15 66 7.1 18.0 28.5 38.2 51.8Junction-2 0.0 33.9 76.7 115.3 150.4 198.9Reach-D 0.0 32.6 72.9 109.7 143.4 190.0D 0.0 15 77 6.2 11.8 16.5 20.6 26.2E 0.0 15 75 2.3 4.8 6.9 8.7 11.3F Straw Avenue 0.0 25 79 27.0 49.0 67.1 83.0 104.8
Junction-3 0.0 62.1 128.4 185.6 237.7 309.7Detention Basin 1 0.0 30.9 52.1 55.8 59.3 65.6Reach-E 0.0 30.2 52.0 55.7 59.3 65.6Junction-4 0.0 33.6 65.9 82.4 101.6 122.5Reach-G 0.0 32.7 64.1 79.3 96.7 116.2H 0.0 15 67 7.4 17.9 27.9 37.1 50.0Reach-F 0.0 7.1 17.6 27.3 36.2 48.6I 0.0 15 62 1.5 4.8 8.0 11.1 15.5Junction-21 0.0 8.6 22.4 35.2 47.0 63.6Reach-Z 0.0 8.2 20.8 32.7 43.9 59.4J 0.0 15 67 6.3 15.4 24.0 31.9 43.0
Detention Basin 2 0.0 3.5 6.2 8.0 9.4 10.9Reach-H 0.0 3.5 6.2 8.0 9.4 10.9K 0.0 15 60 1.5 5.4 9.2 13.0 18.5Junction-5 0.0 39.1 89.8 125.3 159.5 200.3Reach-I 0.0 38.7 88.3 122.8 155.2 195.3
Appendix B Drainage Analysis
Table B.6 (Contd)Elm Street Brook Area/Florence Area Drainage Analysis
Future Conditions Drainage Analysis Summary
Hydrologic Element LocationDrainage
Area(acres)
Tc CNPeak Rate of Runoff (cfs)
2-Yr 10-Yr 25-Yr 50-Yr 100-Yr
L 0.0 20 54 1.5 9.4 19.1 29.2 44.6Junction-6 0.0 39.7 95.6 138.4 181.2 233.4
Reach-J 0.0 39.7 94.9 138.9 180.9 234.7M Depot Avenue 0.0 25 66 7.7 19.8 30.9 41.1 55.4
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
130/243
B-14106678-80349-03-11
M Depot Avenue 0.0 25 66 7.7 19.8 30.9 41.1 55.4Reach-K 0.0 7.2 18.3 28.6 38.2 51.8O 0.0 15 68 4.7 11.2 17.2 22.7 30.4Junction-7 0.0 47.5 117.3 176.8 234.3 306.3Reach-L 0.0 47.4 116.5 176.9 231.4 305.1P 0.0 15 80 17.6 31.8 43.5 53.6 67.3Junction-8 0.0 55.6 129.4 198.6 262.8 346.2Q Locust St. 0.0 15 76 22.5 43.9 61.9 77.9 99.7N North Main St. 0.0 20 78 20.5 38.2 52.8 65.6 83.0Junction-9 0.0 42.5 80.0 111.4 139.8 178.4
Junction-10 0.0 86.2 186.3 279.2 367.8 487.3Reach-M 0.0 84.6 182.1 272.7 356.3 470.6S South Main St. 0.0 15 65 17.5 46.1 73.7 99.6 136.2R 0.0 15 61 3.7 12.6 21.0 29.5 41.7Junction-11 0.0 101.4 224.4 337.6 444.2 590.5Reach-N 0.0 96.0 213.2 321.1 421.4 558.1U South Main St. 0.0 25 68 27.7 66.1 100.5 131.9 175.6T 0.0 15 60 3.0 10.9 18.6 26.2 37.4Junction-12 0.0 120.0 271.6 410.0 539.3 718.0Reach-O 0.0 101.4 230.8 349.2 458.1 610.4V Elm St. 0.0 15 73 13.2 27.6 40.1 51.3 66.7
Junction-13 0.0 104.5 237.1 357.9 469.7 626.3Reach-O1 0.0 104.6 236.1 357.7 470.1 624.5W Hospital Rd. 0.0 15 70 17.5 39.2 58.8 76.6 101.3Junction-14 0.0 109.1 245.6 371.0 486.7 645.7Reach-P 0.0 108.8 245.4 369.4 485.9 646.7
Appendix B
Drainage Analysis
Table B.6 (Contd)Elm Street Brook Area/Florence Area Drainage Analysis
Future Conditions Drainage Analysis Summary
Hydrologic Element LocationDrainage
Area(acres)
Tc CNPeak Rate of Runoff (cfs)
2-Yr 10-Yr 25-Yr 50-Yr 100-Yr
X North Elm St. 0.0 15 73 11.8 24.7 35.8 45.8 59.5Reach-Q 0.0 12.0 24.6 35.4 45.0 58.2
Y 0.0 15 74 6.3 13.0 18.6 23.7 30.6Junction-15 0.0 113.2 253.2 381.6 500.9 665.6
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
131/243
B-15106678-80349-03-11
48-36-in Diversion 0.0 79.6 167.3 250.5 328.1 436.0Reach-S 0.0 78.8 165.9 247.6 324.0 431.1
AA 48-inch Pipe 0.0 15 84 18.9 32.0 42.4 51.4 63.4Junction-16 0.0 82.0 170.9 254.4 332.5 441.5Reach-T 0.0 79.3 162.9 241.4 314.5 416.9EE 0.0 15 68 7.6 17.9 27.5 36.4 48.7Junction-17 0.0 80.8 165.8 245.5 319.9 423.8BB Washington St. 0.0 15 87 30.1 48.7 63.3 75.8 92.4Junction-18 0.0 84.6 171.6 253.1 329.1 434.8
CC Federal St. 0.0 15 74 57.0 116.5 167.5 213.1 275.3Z Milton St. 0.0 20 74 16.1 32.6 46.7 59.2 76.4DD Elm St. 0.0 20 84 5.3 8.9 11.8 14.3 17.636-in pipe Junction 0.0 34.8 88.0 134.1 176.4 233.9Reach-R 0.0 30.7 81.4 123.9 162.6 215.9Junction-19 0.0 33.7 87.3 132.0 173.2 229.3Detention Pond 3 0.0 33.2 78.9 107.8 156.5 216.6Sink-1 689.0 128.7 270.2 387.1 506.5 683.3Detention Basin 1 (Inflow) 62.1 128.4 185.6 237.7 309.7Detention Basin 1 (Outflow) 113.9 30.9 52.1 55.8 59.3 65.6Maximum Stage (ft) 187.1 188.1 188.2 188.4 188.6Spillway Elevation (ft) 187.5 187.5 187.5 187.5 187.5Detention Basin 2 (Inflow) 6.3 15.4 24 31.9 43Detention Basin 2 (Outflow) 14.6 3.5 6.2 8.0 9.4 10.9Maximum Stage (ft) 181.0 182.0 183.0 184.0 185.2Spillway Elevation (ft) 186.0 186.0 186.0 186.0 186.0
Appendix B
Drainage Analysis
Table B.6 (Contd)Elm Street Brook Area/Florence Area Drainage Analysis
Future Conditions Drainage Analysis Summary
Hydrologic Element LocationDrainage
Area(acres)
Tc CNPeak Rate of Runoff (cfs)
2-Yr 10-Yr 25-Yr 50-Yr 100-Yr
Detention Pond 3 (Inflow) 33.7 87.3 132 173.2 229.3Detention Pond 3 (Outflow) 27.5 33.2 78.9 107.8 156.5 216.6
Maximum Stage (ft) 148.4 150.5 152.7 154.1 154.9Spillway Elevation (ft) 153.55 153.55 153.55 153.55 153.55
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
132/243
B-16106678-80349-03-11
Appendix B
Drainage Analysis
Table B.7King Street/Market Street/Downtown Area Watershed Drainage Analysis
Future Conditions Drainage Analysis Summary
Hydrologic Element LocationDrainage Area
Tc CN2-year 10-year 25-year 100-year
(mi 2) (ac) (cfs) (cfs) (cfs) (cfs)KS-E 0.0302 19.3 19 95 46.8 56.7 70.4 97.7KS-F 0.0278 17.8 15 83 34.4 44.3 58.2 86.3J-1 King Street @ Church Street 0.0580 37.1 80.8 100.5 127.9 182.8
KS-G 0.0394 25.2 15 87 52.5 66.6 86.5 126.2King 36" 0.0580 37.1 75.7 94.0 119.7 171.0
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
133/243
B-17106678-80349-03-11
gJ-2 King Street @ Finn Street 0.0973 62.3 102.8 128.2 163.7 234.7King 48" 0.0973 62.3 101.2 126.4 161.4 231.4KS-I 0.0249 16.0 15 92 38.8 47.8 60.2 84.9J-3 0.1223 78.3 116.7 145.4 185.5 265.6Div. at North St King Street @ North Street 0.1223 78.3 116.7 145.4 183.1 183.1King 48"/54" 0.1223 78.3 115.0 143.5 182.5 183.1KS-J 0.0258 16.5 15 89 36.7 46.0 59.0 84.9KS-K 0.0324 20.7 15 88 44.6 56.3 72.6 105.2KS-L 0.0425 27.2 15 85 56.6 71.9 93.4 136.3KS-M 0.0070 4.5 15 84 9.1 11.6 15.1 22.2J-8 Trumbull @ State Street 0.0820 52.4 110.3 139.8 181.2 263.7Trumbull 24" 0.0820 52.4 108.3 137.3 177.8 258.5J-7 King Street @ Trumbull Road 0.2300 147.2 188.9 239.2 309.4 449.1King 54" 0.2300 147.2 188.0 237.8 307.7 446.6KS-Q 0.0386 24.7 15 94 63.1 76.9 95.9 133.7J-9 0.2686 171.9 234.7 295.0 379.3 547.1King 54"/66" 0.2686 171.9 229.9 288.9 371.4 535.0KS-R 0.0230 14.7 15 96 39.1 47.2 58.4 80.6J-10 0.2916 186.6 247.8 310.5 398.1 572.3Div. at Main St King Street @ Strong Ave 0.2916 186.6 234.2 239.0 285.2 285.2King 60"/66" 0.2916 186.6 217.5 232.7 283.2 285.2KS-T 0.0164 10.5 15 97 28.4 34.1 42.0 57.8J-12 King Street @ Pleasant Street 0.3079 197.1 221.2 238.2 289.8 297.0King Street Old Mill River 0.3079 197.1 221.2 238.2 289.8 297.0KS-U Hampton Avenue 0.0119 7.6 15 95 19.9 24.1 30.0 41.6
Appendix B
Drainage Analysis
Table B.7 (Contd)King Street/Market Street/Downtown Area Watershed Drainage Analysis
Future Conditions Drainage Analysis Summary
Hydrologic Element LocationDrainage Area
Tc CN2-year 10-year 25-year 100-year
(mi 2) (ac) (cfs) (cfs) (cfs) (cfs)Old Mill River 0.0119 7.6 19.9 24.1 30.0 41.6KS-A Culvert @ Bikeway 0.0707 45.2 34 78 51.7 69.1 94.3 146.0Brook Rail Trail 0.0707 45.2 49.8 66.6 90.8 140.5
KS-B 0.0293 18.7 27 75 19.7 27.3 38.5 61.9J-4 Culvert @ Woodmont Road 0.0999 63.9 58.0 77.8 106.4 165.0
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
134/243
B-18106678-80349-03-11
@Brook Woodmont Rd 0.0999 63.9 57.7 77.3 105.7 164.0KS-D 0.0233 14.9 31 92 27.8 34.3 43.3 61.0KS-C 0.0145 9.3 15 83 18.0 23.2 30.4 45.1J-5 Old Market Street @ Highland Avenue 0.1377 88.1 71.4 94.4 127.5 195.3Market 48" 0.1377 88.1 70.9 93.7 126.6 193.8KS-H 0.0097 6.2 15 89 15.1 18.6 23.4 33.0J-6 Old Market Street @ North Street 0.1474 94.4 72.8 96.1 129.6 272.0Market 44"/48" 0.1474 94.4 72.2 95.3 128.4 262.8KS-O 0.0480 30.7 19 89 69.4 85.4 107.7 151.8KS-P 0.0065 4.2 20 90 8.7 10.9 13.9 19.8KS-N Market Street @ Walnut Street 0.0357 22.8 26 82 32.1 42.3 56.8 86.4Market 18"/21" 0.0357 22.8 29.7 39.2 52.6 80.0J-11 Old Market Street @ Bridge Street 0.2376 152.1 144.3 199.2 269.9 554.9Market 72" 0.2376 152.1 135.5 195.8 267.6 546.3KS-S 0.0370 23.7 16 89 56.5 69.6 87.7 123.6J-13 Old Market Street @ Hancock Street 0.2746 175.8 149.1 206.1 281.4 570.1Market 82" 0.2746 175.8 144.2 205.0 279.6 565.5KS-W 0.0151 9.7 15 90 24.8 30.2 37.6 52.5KS-V 0.0049 3.1 15 96 8.4 10.1 12.5 17.2J-14 Old Market Street @ Holyoke Street 0.2947 188.6 149.4 210.3 287.4 575.3Market 60" 0.2947 188.6 145.9 209.7 286.1 570.4KS-X 0.0058 3.7 15 85 8.2 10.3 13.2 19.0J-15 Old Market Street @ Hockanum Road 0.3004 192.3 147.0 211.0 287.8 572.6Market Street Old Mill River 0.3004 192.3 147.0 211.0 287.8 572.6
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
135/243
Bridge Street/Meadows Area Drainage Analysis
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
136/243
Bridge Street/Meadows Area Drainage Analysis
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
137/243
2 Y 10 Y 25 Y 50 Y 100 YPeak Rate of Runoff (cfs)
H d l i El L iDrainage Area
( ) T CN
Existing Conditions
Williams Street Brook Drainage AnalysisNorthampton, MA
Drainage Analysis SummaryApril 2011
Table 1
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
138/243
2-Yr 10-Yr 25-Yr 50-Yr 100-Yr2 Lincoln Ave. 26.9 20 84 32.7 55.1 72.9 88.3 108.71 Bridge St. 17.7 20 70 9.1 20.6 30.7 39.9 52.6
Junction-A 44.6 41.9 75.7 103.6 128.2 161.3Reach-1 39.3 71.3 97.8 121.1 152.5
FG2 Fairgrounds Site 10.9 20 80 10.9 19.6 26.7 32.9 41.2FG5 Fairgrounds Site 3.4 25 74 2.2 4.4 6.3 7.9 10.2
E-Pond2 21.5 2.2 3.8 4.5 5 5.5FG3 Fairgrounds Site 13.5 20 73 8.8 18.2 26.2 33.5 43.4
E-Pump 0.4 0.4 0.4 0.4 0.4E-CP1 9.7 20.8 30 37.7 48.1
3 Old Ferry Rd. 5.2 15 66 2 5.1 8.1 10.9 14.8Junction-B 50.9 96 132.9 165.3 209.1Reach-2 47 88.1 122 152.5 193.6
4 Fair St. 10.4 15 85 14.4 24 31.6 38.1 46.8Junction-C 54.8 102.2 141.2 175.4 221.6
Reach-3 36.2 67.2 92.9 115.8 146.86 38.7 25 66 12.9 33.4 52.1 69.3 93.4
FG1 Fairgrounds Site 20.7 20 72 12.5 26.6 38.8 49.8 64.9FG6 Fairgrounds Site 0.7 15 79 0.7 1.3 1.8 2.3 2.8
E-Pond1 24.8 0.7 2.9 11 22.4 39.2FG4 7.5 70 3.9 8.7 13 16.9 22.2
E-CP2 32.3 3.9 8.7 15.2 30.8 53.75 Pomeroy Terrace 25.0 30 80 21.3 38.5 52.6 64.9 81.5
Wetland 9.6 32.1 107.7 183.1 277.5Reach-4 9.6 31.3 102.3 172.8 265.1
7 Eastern Ave. 10.0 15 82 12 20.9 28.1 34.4 42.8Junction-E 12.8 32.8 105.5 177.5 273.2Reach-5 10.3 30.8 91.6 152.5 237.2
8 Valley St. 19.4 30 69 8 18.3 27.5 36.1 48Junction-E2 18.4 36.7 96.3 160 249.2
9 William St 11 1 15 83 14 1 24 1 32 2 39 3 48 6
Hydrologic Element Location (acres) Tc CN
March 2011
Williams Street Brook Drainage AnalysisNorthampton, MA
Drainage Characteristics
Table 2
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
139/243
Total Area Area Impervious
(acres) (sq. mi.) (acres)
1 17.7 0.0277 2.3 13% 70 20 122 26.9 0.0420 12.4 46% 84 20 123 5.2 0.0081 0.7 14% 66 15 94 10.3 0.0162 5.3 51% 85 15 95 25.0 0.0391 9.6 38% 80 30 186 38.7 0.0605 2.7 7% 66 25 157 10.0 0.0156 4.4 45% 82 15 98 19.4 0.0303 3.3 17% 69 30 18
9 11.1 0.0174 6.3 56% 83 15 910 9.7 0.0151 3.4 35% 74 15 911 2.3 0.0037 0.1 6% 70 15 912 34.7 0.0543 11.7 34% 82 30 1813 82.9 0.1296 45.1 54% 84 25 15
FG1 20.7 0.0324 2.9 14% 72 20 12FG2 10.9 0.0171 3.6 33% 80 20 12
FG3 13 5 0 0211 3 2 24% 73 20 12
Existing Conditions
Watershed%Imp.
WeightedCN
Lag Time(Min)
Tc Min)
Existing Conditions
Area 1 Area 2 Area 3
Williams Street Brook Drainage AnalysisNorthampton, MA
Time of Concentration Calculation April 2011
Table 3
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
140/243
Hydraulic Length 1500 ft Hydraulic Length 1500 ft Hydraulic Length 510 ftSlope 0.005 ft/ft Slope 0.007 ft/ft Slope 0.005 ft/ft*Velocity 1.3 fps *Velocity 1.5 fps *Velocity 1.3 fpsTc1 19.2 min Tc2 16.7 min Tc3 6.5 minTc Used 20.0 min Tc Used 20.0 min Tc Used 15.0 minLag Time 0.20 hr Lag Time 0.20 hr Lag Time 0.15 hr
Area 4 Area 5 Area 6Hydraulic Length 990 ft Hydraulic Length 240 ft Hydraulic Length 1740 ftSlope 0.005 ft/ft Slope 0.005 ft/ft Slope 0.005 ft/ft*Velocity 1.3 fps *Velocity 1.3 fps *Velocity 1.3 fpsTc4 12.7 min Tc5-1 3.1 min Tc6 22.3 minTc Used 15.0 min Hydraulic Length 60 ft Tc Used 25.0 minLag Time 0.15 hr Slope 0.170 ft/ft Lag Time 0.25 hr
*Velocity 7.5 fpsArea 7 Tc5-2 0.1 min Area 9
Hydraulic Length 540 ft Hydraulic Length 1950 ft Hydraulic Length 1260 ftSlope 0.009 ft/ft Slope 0.005 ft/ft Slope 0.020 ft/ft*Velocity 1.7 fps *Velocity 1.3 fps *Velocity 2.5 fpsTc7-1 5.3 min Tc5-3 25.0 min Tc9 8.4 minHydraulic Length 360 ft Total TcF 28.2 min Tc Used 15.0 minSlope 0.014 ft/ft Tc Used 30.0 min Lag Time 0.15 hr *Velocity 2.0 fps Lag Time 0.30 hr Tc7-2 3.0 minTotal Tc7 8.3 min Area 8 Area 10Tc Used 15.0 min Hydraulic Length 1440 ft Hydraulic Length 1050 ftLag Time 0.15 hr Slope 0.002 ft/ft Slope 0.005 ft/ft
*Velocity 0.8 fps *Velocity 1.3 fpsArea 11 Tc8 30 0 min Tc10 13 5 min
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
141/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
142/243
2 -Yr 10 -Yr 25-Yr 50-Yr 10 0-Yr2 Lincoln Ave. 26.9 20 86 35.8 58.5 76.4 91.8 112.21 Bridge St. 17.7 20 71 9.9 21.7 32 41.3 54.1
Peak Rate of Runoff (cfs)Hydrologic Element Location
Drainage Area(acres) Tc(min) CN
Future Conditions
Williams Street Brook Drainage AnalysisNorthampton, MA
Drainage Analysis SummaryApril 2011
Table 1
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
143/243
gJunction-A 44.6 45.7 80.2 108.4 133.1 166.3Reach-1 44.6 43 75.6 102.4 125.8 157.3
3 Old Ferry Rd. 5.2 15 67 2.2 5.5 8.5 11.3 15.3Junction-B 49.8 45 80.3 109.4 135 169.4Reach-2 49.8 41.5 73.6 100.1 123.4 154.9
4 Fair St. 10.4 15 86 15.1 24.7 32.3 38.9 47.6Junction-C 60.1 49.7 87.7 118.9 146.3 183.3
Reach-3 60.1 32.9 58 79 97.4 122.2FGP1 Fairgrounds Site 35.9 15 78 34.6 64.8 90 112.1 142FGP7 Fairgrounds Site 3.4 25 74 2.2 4.4 6.3 7.9 10.2
Ppond2 39.3 4.4 10.8 13.7 15.5 17.9SWTC2 39.3 4.4 10.8 13.7 15.5 17.9FGP3 Fairgrounds Site 8.3 15 79 8.4 15.5 21.3 26.5 33.4FGP8 Fairgrounds Site 0.7 15 79 0.7 1.3 1.8 2.3 2.8
Ppond4 9.0 1.8 4.8 8.1 10.9 13.1SWCT1 9.0 1.8 4.8 8.1 10.9 13.1FGP2 Fairgrounds Site 4.9 15 82 5.8 10.2 13.7 16.8 20.9
Ppond1 4.9 1.4 3.5 5.6 7.4 9.9FGP6 Fairgrounds Site 1.0 15 95 2.1 3 3.8 4.4 5.2
SWTC3 5.9 2.5 4.8 7.5 9.7 12.8FGP5 Fairgrounds Site 0.6 15 80 0.6 1.1 1.5 1.9 2.4
Ppond3 54.7 7.6 19.4 28.3 35.3 42.7
FGP4 Fairgrounds Site 1.6 20 76 1.3 2.5 3.4 4.3 5.5FGP9 0.4 15 87 0.7 1.1 1.4 1.7 2.1P-CP2 56.7 7.9 20.3 30.4 38.2 47
6 38.7 25 66 12.9 33.4 52.1 69.3 93.45 Pomeroy Terrace 25.0 30 81 22.5 39.9 54.2 66.6 83.1
Wetland 180.6 10.4 41.3 110.2 174.2 253.2Reach-4 180.6 10.4 40 104.5 165.6 242.1
7 Eastern Ave. 10.0 15 83 12.6 21.6 28.9 35.2 43.6Junction-E 190.6 13.2 41.7 107.7 170.4 250.3Reach-5 190.6 10.9 38.5 94 147.9 220.1
8 Valley St. 19.4 30 70 8.7 19.3 28.7 37.4 49.4Junction-E2 210.0 19.3 40.8 98.7 155.1 232.3
9 William St. 11.1 15 85 15.5 25.8 33.9 41 50.3
10 Herny St 9 7 15 75 7 7 15 4 21 9 27 7 35 7
March 2011
Williams Street Brook Drainage AnalysisNorthampton, MA
Drainage Characteristics
Table 2Future Conditions
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
144/243
Total Area Area Impervious
(acres) (sq. mi.) (acres)
1 17.7 0.0277 2.3 13% 71 20 122 26.9 0.0420 12.4 46% 86 20 123 5.2 0.0081 0.7 14% 67 15 94 10.3 0.0162 5.3 51% 86 15 95 25.0 0.0391 9.6 38% 81 30 186 38.7 0.0605 2.7 7% 66 25 157 10.0 0.0156 4.4 45% 83 15 98 19.4 0.0303 3.3 17% 70 30 189 11.1 0.0174 6.3 56% 85 15 9
10 9.7 0.0151 3.4 35% 75 15 911 2.3 0.0037 0.1 6% 70 15 912 34.7 0.0543 11.7 34% 83 30 1813 82.9 0.1296 30.7 37% 85 25 15
FGP1 35.9 0.0561 12.2 34% 78 15 9FGP2 4.9 0.0076 2.7 55% 82 15 9FGP3 8 3 0 0129 2 0 24% 79 15 9
Future Conditions
Watershed%Imp.
WeightedCN
Lag Time(Min)
Tc Min)
Future Conditions
Area 1 Area 2 Area 3H d li L th 1500 ft H d li L th 1500 ft H d li L th 510 ft
Williams Street Brook Drainage AnalysisNorthampton, MA
Time of Concentration Calculation April 2011
Table 3
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
145/243
Hydraulic Length 1500 ft Hydraulic Length 1500 ft Hydraulic Length 510 ftSlope 0.005 ft/ft Slope 0.007 ft/ft Slope 0.005 ft/ft*Velocity 1.3 fps *Velocity 1.5 fps *Velocity 1.3 fpsTc1 19.2 min Tc2 16.7 min Tc3 6.5 minTc Used 20.0 min Tc Used 20.0 min Tc Used 15.0 minLag Time 0.20 hr Lag Time 0.20 hr Lag Time 0.15 hr
Area 4 Area 5 Area 6Hydraulic Length 990 ft Hydraulic Length 240 ft Hydraulic Length 1740 ftSlope 0.005 ft/ft Slope 0.005 ft/ft Slope 0.005 ft/ft*Velocity 1.3 fps *Velocity 1.3 fps *Velocity 1.3 fpsTc4 12.7 min Tc5-1 3.1 min Tc6 22.3 minTc Used 15.0 min Hydraulic Length 60 ft Tc Used 25.0 minLag Time 0.15 hr Slope 0.170 ft/ft Lag Time 0.25 hr
*Velocity 7.5 fpsArea 7 Tc5-2 0.1 min Area 9
Hydraulic Length 540 ft Hydraulic Length 1950 ft Hydraulic Length 1260 ftSlope 0.009 ft/ft Slope 0.005 ft/ft Slope 0.020 ft/ft*Velocity 1.7 fps *Velocity 1.3 fps *Velocity 2.5 fpsTc7-1 5.3 min Tc5-3 25.0 min Tc9 8.4 minHydraulic Length 360 ft Total TcF 28.2 min Tc Used 15.0 minSlope 0.014 ft/ft Tc Used 30.0 min Lag Time 0.15 hr *Velocity 2.0 fps Lag Time 0.30 hr Tc7-2 3.0 minTotal Tc7 8.3 min Area 8 Area 10Tc Used 15.0 min Hydraulic Length 1440 ft Hydraulic Length 1050 ftLag Time 0.15 hr Slope 0.002 ft/ft Slope 0.005 ft/ft
*Velocity 0.8 fps *Velocity 1.3 fpsArea 11 Tc8 30 0 min Tc10 13 5 min
Future Conditions
tA tB tCHydraulic Length 480 ft Hydraulic Length 600 ft Hydraulic Length 2010 ft
Williams Street Brook Drainage AnalysisNorthampton, MA
Muskingum(K) Calculation April 2011
Table 4
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
146/243
Hydraulic Length 480 ft Hydraulic Length 600 ft Hydraulic Length 2010 ftSlope 0.005 ft/ft Slope 0.004 ft/ft Slope 0.003 ft/ft*Velocity 1.3 fps *Velocity 1.2 fps *Velocity 0.9 fpstA 6.2 min tB 8.3 min tC 39.4 mintA 0.10 hour tB 0.14 hour tC 0.7 hour
tD tE tFHydraulic Length 450 ft Hydraulic Length 1290 ft Hydraulic Length 150 ftSlope 0.005 ft/ft Slope 0.008 ft/ft Slope 0.003 ft/ft*Velocity 1.3 fps *Velocity 1.5 fps *Velocity 0.9 fpstD 5.8 min tE 14.3 min tF 2.8 mintD 0.10 hour tE 0.24 hour tF 0.05 hour
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
147/243
2 -Yr 1 0-Yr 25 -Yr 50 -Yr 1 00 -YrFGP1 Fairgrounds Site 35.9 15 78 34.6 64.8 90 112.1 142FGP7 Fairgrounds Site 3.4 25 74 2.2 4.4 6.3 7.9 10.2
Ppond2 39.3 4.4 10.8 13.7 15.5 17.9SWTC2 39.3 4.4 10.8 13.7 15.5 17.9
Future Conditions (Alternative 1)
Williams Street Brook Drainage AnalysisNorthampton, MA
Drainage Analysis SummaryApril 2011
Table 1
Peak Rate of Runoff (cfs)Hydrologic Element Location
Drainage Area(acres) Tc(min) CN
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
148/243
FGP3 Fairgrounds Site 8.3 15 79 8.4 15.5 21.3 26.5 33.4FGP8 Fairgrounds Site 0.7 15 79 0.7 1.3 1.8 2.3 2.8
Ppond4 9.0 1.8 4.8 8.1 10.9 13.1SWCT1 9.0 1.8 4.8 8.1 10.9 13.1FGP2 Fairgrounds Site 4.9 15 82 5.8 10.2 13.7 16.8 20.9
Ppond1 4.9 1.4 3.5 5.6 7.4 9.9FGP6 Fairgrounds Site 1.0 15 95 2.1 3 3.8 4.4 5.2
SWTC3 5.9 2.5 4.8 7.5 9.7 12.8FGP5 Fairgrounds Site 0.6 15 80 0.6 1.1 1.5 1.9 2.4
Ppond3 54.7 7.6 19.4 28.3 35.3 42.7FGP4 Fairgrounds Site 1.6 20 76 1.3 2.5 3.4 4.3 5.5FGP9 Fairgrounds Site 0.4 15 87 0.7 1.1 1.4 1.7 2.1P-CP2 56.7 7.9 20.3 30.4 38.2 47
6 38.7 25 66 12.9 33.4 52.1 69.3 93.4FS-1 95.5 7.8 17.9 24.6 30.6 47.5
5 Pomeroy Terrace 25.0 30 81 22.5 39.9 54.2 66.6 83.11 Bridge St. 17.7 20 71 9.9 21.7 32 41.3 54.1
Junction-A 17.7 9.9 21.7 32 41.3 54.1Reach-1 17.7 9.3 20.3 30 38.8 50.9
3 Old Ferry Rd. 5.2 15 67 2.2 5.5 8.5 11.3 15.3Junction-B 22.9 11.2 25 37 48 63.1Reach-2 22.9 10.5 23.1 34.1 44.1 58.2
Junction-C 22.9 10.5 23.1 34.1 44.1 58.2Reach-3 22.9 6.5 14.5 21.7 28.3 37.4Wetland 143.4 4.9 12.4 23.6 39.8 72.7Reach-4 143.4 4.9 12.4 23.3 39.2 70.7
7 Eastern Ave. 10.0 15 83 12.6 21.6 28.9 35.2 43.6Junction-E 153.4 12.9 22.3 30 41.1 74.2Reach-5 153.4 10.2 17.7 23.8 39.4 68.9
8 Valley St. 19.4 30 70 8.7 19.3 28.7 37.4 49.49 William St. 11.1 15 85 15.5 25.8 33.9 41 50.3
10 Herny St. 9.7 15 75 7.7 15.4 21.9 27.7 35.7Junction-F 193.5 38 71.2 99.1 123.9 157.5Reach-6 193.5 37.6 70.3 97.7 122 154.9
11 2.4 15 70 1.3 3 4.4 5.8 7.6G-Mill River 195.9 38.8 72.8 101.3 126.6 160.9
13 Industrial Dr. 82.9 25 85 96.9 160.4 211.7 256 314.82 Lincoln Ave. 26.9 20 86 35.8 58.5 76.4 91.8 112.24 Fair St 10 4 15 86 15 1 24 7 32 3 38 9 47 6
Future Conditions (Alternative 1)
April 2011
Williams Street Brook Drainage AnalysisNorthampton, MA
Drainage Characteristics
Table 2
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
149/243
Total Area Area Impervious
(acres) (sq. mi.) (acres)
1 17.7 0.0277 2.3 13% 71 20 12
2 26.9 0.0420 12.4 46% 86 20 123 5.2 0.0081 0.7 14% 67 15 94 10.3 0.0162 5.3 51% 86 15 95 25.0 0.0391 9.6 38% 81 30 186 38.7 0.0605 2.7 7% 66 25 157 10.0 0.0156 4.4 45% 83 15 98 19.4 0.0303 3.3 17% 70 30 18
9 11.1 0.0174 6.3 56% 85 15 910 9.7 0.0151 3.4 35% 75 15 911 2.3 0.0037 0.1 6% 70 15 912 34.7 0.0543 11.7 34% 83 30 1813 82.9 0.1296 45.1 54% 85 25 15
FGP1 35.9 0.0561 12.2 34% 78 15 9FGP2 4.9 0.0076 2.7 55% 82 15 9
FGP3 8 3 0 0129 2 0 24% 79 15 9
( )
Watershed%Imp.
WeightedCN
Lag Time(Min)
Tc Min)
Future Conditions (Alternative 1)
Area 1 Area 2 Area 3Hydraulic Length 1500 ft Hydraulic Length 1500 ft Hydraulic Length 510 ft
Williams Street Brook Drainage AnalysisNorthampton, MA
Time of Concentration Calculation April 2011
Table 3
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
150/243
Slope 0.005 ft/ft Slope 0.007 ft/ft Slope 0.005 ft/ft*Velocity 1.3 fps *Velocity 1.5 fps *Velocity 1.3 fpsTc1 19.2 min Tc2 16.7 min Tc3 6.5 minTc Used 20.0 min Tc Used 20.0 min Tc Used 15.0 minLag Time 0.20 hr Lag Time 0.20 hr Lag Time 0.15 hr
Area 4 Area 5 Area 6Hydraulic Length 990 ft Hydraulic Length 240 ft Hydraulic Length 1740 ftSlope 0.005 ft/ft Slope 0.005 ft/ft Slope 0.005 ft/ft*Velocity 1.3 fps *Velocity 1.3 fps *Velocity 1.3 fpsTc4 12.7 min Tc5-1 3.1 min Tc6 22.3 minTc Used 15.0 min Hydraulic Length 60 ft Tc Used 25.0 minLag Time 0.15 hr Slope 0.170 ft/ft Lag Time 0.25 hr
*Velocity 7.5 fpsArea 7 Tc5-2 0.1 min Area 9
Hydraulic Length 540 ft Hydraulic Length 1950 ft Hydraulic Length 1260 ftSlope 0.009 ft/ft Slope 0.005 ft/ft Slope 0.020 ft/ft*Velocity 1.7 fps *Velocity 1.3 fps *Velocity 2.5 fpsTc7-1 5.3 min Tc5-3 25.0 min Tc9 8.4 minHydraulic Length 360 ft Total TcF 28.2 min Tc Used 15.0 minSlope 0.014 ft/ft Tc Used 30.0 min Lag Time 0.15 hr *Velocity 2.0 fps Lag Time 0.30 hr Tc7-2 3.0 minTotal Tc7 8.3 min Area 8 Area 10Tc Used 15.0 min Hydraulic Length 1440 ft Hydraulic Length 1050 ftLag Time 0.15 hr Slope 0.002 ft/ft Slope 0.005 ft/ft
*Velocity 0.8 fps *Velocity 1.3 fps
A 11 T 8 30 0 i T 10 13 5 i
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
151/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
152/243
2-Yr 10-Yr 25-Yr 50-Yr 100-YrFGP1 Fairgrounds Site 35.9 15 78 9.9 64.8 90 112.1 142FGP7 Fairgrounds Site 3.4 25 74 9.9 4.4 6.3 7.9 10.2
Ppond2 39.3 9.3 10.8 13.7 15.5 17.9SWTC2 39.3 2.2 10.8 13.7 15.5 17.9
Future Conditions (Alternative 2)
Williams Street Brook Drainage AnalysisNorthampton, MA
Drainage Analysis SummaryApril 2011
Table 1
Peak Rate of Runoff (cfs)Hydrologic Element Location
Drainage Area(acres) Tc(min) CN
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
153/243
FGP3 Fairgrounds Site 8.3 15 79 11.2 15.5 21.3 26.5 33.4FGP8 Fairgrounds Site 0.7 15 79 10.5 1.3 1.8 2.3 2.8
Ppond4 9.0 10.5 4.8 8.1 10.9 13.1SWCT1 9.0 6.5 4.8 8.1 10.9 13.1FGP2 Fairgrounds Site 4.9 15 82 34.6 10.2 13.7 16.8 20.9
Ppond1 4.9 2.2 3.5 5.6 7.4 9.9FGP6 Fairgrounds Site 1.0 15 95 4.4 3 3.8 4.4 5.2
SWTC3 5.9 4.4 4.8 7.5 9.7 12.8FGP5 Fairgrounds Site 0.6 15 80 8.4 1.1 1.5 1.9 2.4
Ppond3 54.7 0.7 19.4 28.3 35.3 42.7FGP4 Fairgrounds Site 1.6 20 76 1.8 2.5 3.4 4.3 5.5FGP9 Fairgrounds Site 0.4 15 87 1.8 1.1 1.4 1.7 2.1P-CP2 56.7 5.8 20.3 30.4 38.2 47
6 38.7 25 66 1.4 33.4 52.1 69.3 93.45 Pomeroy Terrace 25.0 30 81 2.1 39.9 54.2 66.6 83.11 Bridge St. 17.7 20 71 2.5 21.7 32 41.3 54.1
Junction-A 17.7 0.6 21.7 32 41.3 54.1Reach-1 17.7 7.6 20.3 30 38.8 50.9
3 Old Ferry Rd. 5.2 15 67 1.3 5.5 8.5 11.3 15.3Junction-B 22.9 0.7 25 37 48 63.1Reach-2 22.9 7.9 23.1 34.1 44.1 58.2
Junction-C 22.9 12.9 23.1 34.1 44.1 58.2
Reach-3 22.9 22.5 14.5 21.7 28.3 37.4Wetland 143.4 38.1 13.6 35.6 70.3 139.9Reach-4 143.4 37 13.6 34.9 67.2 130.2
7 Eastern Ave. 10.0 15 83 12.6 21.6 28.9 35.2 43.6Junction-E 153.4 44 22.6 36.8 70.8 136Reach-5 153.4 39.4 18.1 34.9 64 117.9
8 Valley St. 19.4 30 70 8.7 19.3 28.7 37.4 49.49 William St. 11.1 15 85 15.5 25.8 33.9 41 50.3
10 Henry St. 9.7 15 75 7.7 15.4 21.9 27.7 35.7Junction-F 193.5 56.2 71.4 99.5 124.6 158.9Reach-6 193.5 56 70.5 98.1 122.7 156.5
11 2.4 15 70 1.3 3 4.4 5.8 7.6G-Mill River 195.9 56.6 73 101.7 127.3 162.4
13 Industrial Dr. 82.9 25 85 96.9 160.4 211.7 256 314.8
Future Conditions (Alternative 2)
March 2011
Williams Street Brook Drainage AnalysisNorthampton, MA
Drainage Characteristics
Table 2
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
154/243
Total Area Area Impervious
(acres) (sq. mi.) (acres)
1 17.7 0.0277 2.3 13% 71 20 12
2 26.9 0.0420 12.4 46% 86 20 123 5.2 0.0081 0.7 14% 67 15 94 10.3 0.0162 5.3 51% 86 15 95 25.0 0.0391 9.6 38% 81 30 186 38.7 0.0605 2.7 7% 66 25 157 10.0 0.0156 4.4 45% 83 15 98 19.4 0.0303 3.3 17% 70 30 18
9 11.1 0.0174 6.3 56% 85 15 910 9.7 0.0151 3.4 35% 75 15 911 2.3 0.0037 0.1 6% 70 15 912 34.7 0.0543 11.7 34% 83 30 1813 82.9 0.1296 45.1 54% 85 25 15
FGP1 35.9 0.0561 12.2 34% 78 15 9FGP2 4.9 0.0076 2.7 55% 82 15 9
Watershed%Imp.
WeightedCN
Lag Time(Min)
Tc Min)
Future Conditions (Alternative 2)
Area 1 Area 2 Area 3Hydraulic Length 1500 ft Hydraulic Length 1500 ft Hydraulic Length 510 ftSlope 0 005 ft/ft Slope 0 007 ft/ft Slope 0 005 ft/ft
Williams Street Brook Drainage AnalysisNorthampton, MA
Time of Concentration Calculation April 2011
Table 3
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
155/243
Slope 0.005 ft/ft Slope 0.007 ft/ft Slope 0.005 ft/ft*Velocity 1.3 fps *Velocity 1.5 fps *Velocity 1.3 fpsTc1 19.2 min Tc2 16.7 min Tc3 6.5 minTc Used 20.0 min Tc Used 20.0 min Tc Used 15.0 minLag Time 0.20 hr Lag Time 0.20 hr Lag Time 0.15 hr
Area 4 Area 5 Area 6Hydraulic Length 990 ft Hydraulic Length 240 ft Hydraulic Length 1740 ftSlope 0.005 ft/ft Slope 0.005 ft/ft Slope 0.005 ft/ft*Velocity 1.3 fps *Velocity 1.3 fps *Velocity 1.3 fpsTc4 12.7 min Tc5-1 3.1 min Tc6 22.3 minTc Used 15.0 min Hydraulic Length 60 ft Tc Used 25.0 minLag Time 0.15 hr Slope 0.170 ft/ft Lag Time 0.25 hr
*Velocity 7.5 fpsArea 7 Tc5-2 0.1 min Area 9
Hydraulic Length 540 ft Hydraulic Length 1950 ft Hydraulic Length 1260 ftSlope 0.009 ft/ft Slope 0.005 ft/ft Slope 0.020 ft/ft
*Velocity 1.7 fps *Velocity 1.3 fps *Velocity 2.5 fpsTc7-1 5.3 min Tc5-3 25.0 min Tc9 8.4 minHydraulic Length 360 ft Total TcF 28.2 min Tc Used 15.0 minSlope 0.014 ft/ft Tc Used 30.0 min Lag Time 0.15 hr *Velocity 2.0 fps Lag Time 0.30 hr Tc7-2 3.0 minTotal Tc7 8.3 min Area 8 Area 10Tc Used 15.0 min Hydraulic Length 1440 ft Hydraulic Length 1050 ftLag Time 0.15 hr Slope 0.002 ft/ft Slope 0.005 ft/ft
*Velocity 0.8 fps *Velocity 1.3 fps
Future Conditions (Alternative 2)
tA tB tCHydraulic Length 480 ft Hydraulic Length 600 ft Hydraulic Length 2010 ftSlope 0 005 ft/ft Slope 0 004 ft/ft Slope 0 003 ft/ft
Williams Street Brook Drainage AnalysisNorthampton, MA
Muskingum(K) Calculation April 2011
Table 4
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
156/243
Slope 0.005 ft/ft Slope 0.004 ft/ft Slope 0.003 ft/ft*Velocity 1.3 fps *Velocity 1.2 fps *Velocity 0.9 fpstA 6.2 min tB 8.3 min tC 39.4 mintA 0.10 hour tB 0.14 hour tC 0.7 hour
tD tE tFHydraulic Length 450 ft Hydraulic Length 1290 ft Hydraulic Length 150 ft
Slope 0.005 ft/ft Slope 0.008 ft/ft Slope 0.003 ft/ft*Velocity 1.3 fps *Velocity 1.5 fps *Velocity 0.9 fpstD 5.8 min tE 14.3 min tF 2.8 mintD 0.10 hour tE 0.24 hour tF 0.05 hour
tG tHHydraulic Length 330 ft Hydraulic Length 2820 ftSlope 0.005 ft/ft Slope 0.005 ft/ft*Velocity 1.3 fps *Velocity 1.3 fpstD 4.2 min tD 36.2 min
tD 0.07 hour tD 0.60 hour
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
157/243
2-Yr 10-Yr 25-Yr 50-Yr 100-Yr2 Lincoln Ave. 26.9 20 86 35.8 58.5 76.4 91.8 112.21 Bridge St. 17.7 20 71 9.9 21.7 32 41.3 54.1
Junction-A 44.6 45.7 80.2 108.4 133.1 166.3R h 1 44 6 43 75 6 102 4 125 8 157 3
Future Conditions (Alternative 3)
Williams Street Brook Drainage AnalysisNorthampton, MA
Drainage Analysis SummaryApril 2011
Table 1
Peak Rate of Runoff (cfs)Hydrologic Element Location
Drainage Area(acres) Tc(min) CN
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
158/243
Reach-1 44.6 43 75.6 102.4 125.8 157.33 Old Ferry Rd. 5.2 15 67 2.2 5.5 8.5 11.3 15.3
Junction-B 49.8 45 80.3 109.4 135 169.4Reach-2 49.8 41.5 73.6 100.1 123.4 154.9
4 Fair St. 10.4 15 86 15.1 24.7 32.3 38.9 47.6Junction-C 60.1 49.7 87.7 118.9 146.3 183.3
Reach-3 60.1 32.9 58 79 97.4 122.26 38.7 25 66 12.9 33.4 52.1 69.3 93.4
5 Pomeroy Terrace 25.0 30 81 22.5 39.9 54.2 66.6 83.1Wetland 123.9 7.8 14.6 61.5 120.4 195.0Reach-4 123.9 7.8 14.6 58.3 114.3 183.9
7 Eastern Ave. 10.0 15 83 12.6 21.6 28.9 35.2 43.6Junction-E 133.8 13.2 23.2 61.1 118.4 190.3
Reach-5 133.8 10.6 18.7 54.1 101.8 166.48 Valley St. 19.4 30 70 8.7 19.3 28.7 37.4 49.49 William St. 11.1 15 85 15.5 25.8 33.9 41 50.3
10 Herny St. 9.7 15 75 7.7 15.4 21.9 27.7 35.7Junction-F 174.0 38.2 72 100.4 125.7 187.5Reach-6 174.0 37.9 71.1 99 123.9 186.6
11 2.4 15 70 1.3 3 4.4 5.8 7.6
G-Mill River 176.4 39.1 73.6 102.6 128.5 187.613 Industrial Dr. 82.9 25 85 96.9 160.4 211.7 256 314.812 Marshall St. 34.7 30 83 34.6 59.5 79.5 96.8 119.9
42-inch Pipe 117.7 131.5 219.6 289.7 350.1 430.5FGP1 Fairgrounds Site 35.9 15 78 34.6 64.8 90 112.1 142.0FGP7 Fairgrounds Site 3.4 25 74 2.2 4.4 6.3 7.9 10.2
Ppond2 39.3 4.4 10.8 13.7 15.5 17.9SWTC2 39.3 4.4 10.8 13.7 15.5 17.9FGP3 Fairgrounds Site 8.3 15 79 8.4 15.5 21.3 26.5 33.4FGP8 Fairgrounds Site 0.7 15 79 0.7 1.3 1.8 2.3 2.8
Ppond4 9.0 1.8 4.8 8.1 10.9 13.1SWCT1 9.0 1.8 4.8 8.1 10.9 13.1
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
159/243
Future Conditions (Alternative 3)
Area 1 Area 2 Area 3Hydraulic Length 1500 ft Hydraulic Length 1500 ft Hydraulic Length 510 ftSlope 0.005 ft/ft Slope 0.007 ft/ft Slope 0.005 ft/ft
Williams Street Brook Drainage AnalysisNorthampton, MA
Time of Concentration Calculation April 2011
Table 3
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
160/243
*Velocity 1.3 fps *Velocity 1.5 fps *Velocity 1.3 fpsTc1 19.2 min Tc2 16.7 min Tc3 6.5 minTc Used 20.0 min Tc Used 20.0 min Tc Used 15.0 minLag Time 0.20 hr Lag Time 0.20 hr Lag Time 0.15 hr
Area 4 Area 5 Area 6
Hydraulic Length 990 ft Hydraulic Length 240 ft Hydraulic Length 1740 ftSlope 0.005 ft/ft Slope 0.005 ft/ft Slope 0.005 ft/ft*Velocity 1.3 fps *Velocity 1.3 fps *Velocity 1.3 fpsTc4 12.7 min Tc5-1 3.1 min Tc6 22.3 minTc Used 15.0 min Hydraulic Length 60 ft Tc Used 25.0 minLag Time 0.15 hr Slope 0.170 ft/ft Lag Time 0.25 hr
*Velocity 7.5 fpsArea 7 Tc5-2 0.1 min Area 9
Hydraulic Length 540 ft Hydraulic Length 1950 ft Hydraulic Length 1260 ftSlope 0.009 ft/ft Slope 0.005 ft/ft Slope 0.020 ft/ft
*Velocity 1.7 fps *Velocity 1.3 fps *Velocity 2.5 fpsTc7-1 5.3 min Tc5-3 25.0 min Tc9 8.4 minHydraulic Length 360 ft Total TcF 28.2 min Tc Used 15.0 minSlope 0.014 ft/ft Tc Used 30.0 min Lag Time 0.15 hr *Velocity 2.0 fps Lag Time 0.30 hr Tc7-2 3.0 minTotal Tc7 8.3 min Area 8 Area 10Tc Used 15.0 min Hydraulic Length 1440 ft Hydraulic Length 1050 ftLag Time 0.15 hr Slope 0.002 ft/ft Slope 0.005 ft/ft
*Velocity 0.8 fps *Velocity 1.3 fps
Future Conditions (Alternative 3)
tA tB tCHydraulic Length 480 ft Hydraulic Length 600 ft Hydraulic Length 2010 ftSlope 0.005 ft/ft Slope 0.004 ft/ft Slope 0.003 ft/ft
Williams Street Brook Drainage AnalysisNorthampton, MA
Muskingum(K) Calculation April 2011
Table 4
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
161/243
*Velocity 1.3 fps *Velocity 1.2 fps *Velocity 0.9 fpstA 6.2 min tB 8.3 min tC 39.4 mintA 0.10 hour tB 0.14 hour tC 0.7 hour
tD tE tFHydraulic Length 450 ft Hydraulic Length 1290 ft Hydraulic Length 150 ft
Slope 0.005 ft/ft Slope 0.008 ft/ft Slope 0.003 ft/ft*Velocity 1.3 fps *Velocity 1.5 fps *Velocity 0.9 fpstD 5.8 min tE 14.3 min tF 2.8 mintD 0.10 hour tE 0.24 hour tF 0.05 hour
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
162/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
163/243
Future Conditions (Recommended Plan)
March 2011
Williams Street Brook Drainage AnalysisNorthampton, MA
Drainage Characteristics
Table 2
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
164/243
Total Area Area Impervious
(acres) (sq. mi.) (acres)
1 17.7 0.0277 2.3 13% 71 20 12
2 26.9 0.0420 12.4 46% 86 20 123 5.2 0.0081 0.7 14% 67 15 94 10.3 0.0162 5.3 51% 86 15 95 25.0 0.0391 9.6 38% 81 30 186 38.7 0.0605 2.7 7% 66 25 157 10.0 0.0156 4.4 45% 83 15 98 19.4 0.0303 3.3 17% 70 30 18
9 11.1 0.0174 6.3 56% 85 15 910 9.7 0.0151 3.4 35% 75 15 911 2.3 0.0037 0.1 6% 70 15 912 34.7 0.0543 11.7 34% 83 30 1813 82.9 0.1296 21.0 25% 82 25 15
FGP1 35.9 0.0561 12.2 34% 78 15 9FGP2 4.9 0.0076 2.7 55% 82 15 9
Watershed%Imp.
WeightedCN
Lag Time(Min)
Tc Min)
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
165/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
166/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
167/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
168/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
169/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
170/243
Existing Conditions
Area A Area B Area CHydraulic Length 840 ft Hydraulic Length 840 ft Hydraulic Length 300 ftSlope 0.027 ft/ft Slope 0.040 ft/ft Slope 0.033 ft/ft*Velocity 2.7 fps *Velocity 3.5 fps *Velocity 3.1 fpsTcA1 5.2 min TcB1 4.0 min TcC1 1.6 minHydraulic Length 450 ft Hydraulic Length 390 ft Hydraulic Length 810 ftSlope 0.044 ft/ft Slope 0.026 ft/ft Slope 0.031 ft/ft*Velocity 3.7 fps *Velocity 2.8 fps *Velocity 2.6 fpsTcA2 2.0 min TcB2 2.3 min TcC2 5.2 minHydraulic Length 780 ft Total TcB 6.3 min Total TcC 6.8 minSlope 0.013 ft/ft Tc Used 15.0 min Tc Used 15.0 min*Velocity 2.0 fps Lag Time 0.15 hr Lag Time 0.15 hr TcA3 6.5 minTotal TcA 13.7 minTc Used 15.0 minLag Time 0.15 hr
Area D Area E Area F
Hydraulic Length 660 ft Hydraulic Length 510 ft Hydraulic Length 510 ftSlope 0.091 ft/ft Slope 0.078 ft/ft Slope 0.078 ft/ft*Velocity 5.3 fps *Velocity 4.8 fps *Velocity 4.6 fpsTcD1 2.1 min TcD1 1.8 min TcF1 1.8 minTc Used 15.0 min Tc Used 15.0 min Hydraulic Length 2400 ftLag Time 0.15 hr Lag Time 0.15 hr Slope 0.017 ft/ft
*Velocity 2.2 fpsArea G Area H TcF2 18.2 min
Hydraulic Length 300 ft Hydraulic Length 360 ft Hydraulic Length 150 ftSlope 0.067 ft/ft Slope 0.028 ft/ft Slope 0.200 ft/ft*V l it 4 5 f *V l it 2 9 f *V l it 7 0 f
Elm Street Brook Drainage AnalysisNorthampton, MA
Time of Concentration CalculationMarch 2011
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
171/243
*Velocity 4.5 fps *Velocity 2.9 fps *Velocity 7.0 fpsTcG1 1.1 min TcH1 2.1 min TcF3 0.4 minHydraulic Length 870 ft Hydraulic Length 420 ft Total TcF 20.4 minSlope 0.023 ft/ft Slope 0.024 ft/ft Tc Used 25.0 min*Velocity 2.5 fps *Velocity 2.7 fps Lag Time 0.25 hr TcG2 5.8 min TcH2 2.6 minTotal TcG 6.9 min Total TcH 4.7 minTc Used 15.0 min Tc Used 15.0 minLag Time 0.15 hr Lag Time 0.15 hr
Area I Area J Area KHydraulic Length 510 ft Hydraulic Length 210 ft Hydraulic Length 200 ftSlope 0.078 ft/ft Slope 0.143 ft/ft Slope 0.167 ft/ft*Velocity 4.4 fps *Velocity 5.8 fps *Velocity 7.5 fpsTcI1 1.9 min TcJ1 0.6 min TcI1 0.4 minHydraulic Length 300 ft Hydraulic Length 570 ft Hydraulic Length 510 ftSlope 0.033 ft/ft Slope 0.018 ft/ft Slope 0.029 ft/ft*Velocity 3.3 fps *Velocity 2.4 fps *Velocity 0.9 fpsTcI2 1.5 min TcJ2 4.0 min TcI2 10.0 minTotal TcI 3.4 min Hydraulic Length 60 ft Total TcI 10.4 minTc Used 15.0 min Slope 0.330 ft/ft Tc Used 15.0 minLag Time 0.15 hr *Velocity 9.0 fps Lag Time 0.15 hr
TcJ3 0.1 minArea L Hydraulic L ength 300 f t Area N
Hydraulic Length 450 ft Slope 0.005 ft/ft Hydraulic Length 1380 ftSlope 0.044 ft/ft *Velocity 1.1 fps Slope 0.015 ft/ft*Velocity 1.2 fps TcJ4 4.5 min *Velocity 2.1 fpsTcL1 6.3 min Total TcJ 9.2 min TcN1 11.0 minHydraulic Length 360 ft Tc Used 15.0 min Hydraulic Length 1200 ftSlope 0.028 ft/ft Lag Time 0.15 hr Slope 0.049 ft/ft*Velocity 0.9 fps *Velocity 3.7 fpsTcL2 7.1 min Area M TcN2 5.4 minHydraulic Length 420 ft Hydraulic Length 2250 ft Total TcN 16.4 min
Slope 0.048 ft/ft Slope 0.009 ft/ft Tc Used 20.0 min*Velocity 1.3 fps *Velocity 1.7 fps Lag Time 0.20 hr TcL3 5.4 min TcM1 22.1 minHydraulic Length 90 ft Tc Used 25.0 min Area QSlope 0.440 ft/ft Lag Time 0.25 hr H yd rau li c L en gt h 111 0 f t*Velocity 3.5 fps Slope 0.018 ft/ftTcL4 0.4 min Area P *Velocity 2.4 fpsTotal TcL 19.1 min Hydraulic Length 1050 ft TcQ1 7.7 minTc Used 20.0 min Slope 0.038 ft/ft Hydraulic Length 720 ftLag Time 0.20 hr *Velocity 3.5 fps Slope 0.028 ft/ft
TcP1 5.0 min *Velocity 3.0 fpsArea O Tc Used 15.0 min TcQ2 4.0 min
Hydr aulic Lengt h 240 f t Lag Time 0.15 hr Total TcQ 11.7 minSlope 0.125 ft/ft Tc Used 15.0 min*Velocity 6.0 fps Area R Lag Time 0.15 hr TcO1 0.7 min Hydraulic Length 510 ftHydraulic Length 810 ft Slope 0.078 ft/ft Area SSlope 0.012 ft/ft *Velocity 4.2 fps Hydraulic Length 420 ft*Velocity 1.7 fps TcR1 2.0 min Slope 0.007 ft/ftTcO2 7.9 min Hydraulic Length 450 ft *Velocity 1.5 fpsTotal TcO 8.6 min Slope 0.022 ft/ft TcS1 4.7 min
Existing Conditions
tA tB tCHydraulic Length 540 ft Hydraulic Length 240 ft Hydraulic Length 810 ftSlope 0.005 ft/ft Slope 0.005 ft/ft Slope 0.025 ft/ft*Velocity 1.5 fps *Velocity 1.5 fps *Velocity 2.7 fpstA 6.0 min tB 2.7 min tC 5.0 mintA 0.10 hour tB 0.04 hour tC 0.1 hour
tD tE tF
Elm Street Brook Drainage AnalysisNorthampton, MA
Muskingum(K) CalculationMarch 2011
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
172/243
Hydraulic Length 300 ft Hydraulic Length 450 ft Hydraulic Length 900 ftSlope 0.025 ft/ft Slope 0.011 ft/ft Slope 0.067 ft/ft*Velocity 2.7 fps *Velocity 1.6 fps *Velocity 4.5 fpstD1 1.9 min tE 4.7 min tF 3.3 minHydraulic Length 280 ft tE 0.08 hour tF 0.06 hourSlope 0.005 ft/ft*Velocity 1.2 fps tItD2 3.9 min Hydraulic Length 420 ftTotal tD 5.7 min Slope 0.012 ft/fttD 0.10 hour *Velocity 1.5 fps
tI1 4.7 mintG tH Hydraulic Length 90 ft
Hydraulic Length 480 ft Hydraulic Length 450 ft Slope 0.600 ft/ftSlope 0.005 ft/ft Slope 0.033 ft/ft *Velocity 12.0 fps*Velocity 1.3 fps *Velocity 3.2 fps tI2 0.1 mintG 6.2 min tH 2.3 min Total tD 4.8 mintG 0.10 hour tH 0.04 hour tD 0.08 hour
tJ tK tLHydraulic Length 300 ft Hydraulic Length 1200 ft Hydraulic Length 360 ftSlope 0.100 ft/ft Slope 0.033 ft/ft Slope 0.028 ft/ft*Velocity 5.0 fps *Velocity 2.6 fps *Velocity 2.5 fpstJ 1.0 min tK 7.7 min tL 2.4 mintJ 0.02 hour tK 0.13 hour tL 0.04 hour
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
173/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
174/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
175/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
176/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
177/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
178/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
179/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
180/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
181/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
182/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
183/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
184/243
Future Conditions (Alternative 2)
Total Area Area Impervious(acres) (sq mi ) (acres)
March 2011
Elm Street Brook Drainage AnalysisNorthampton, MA
Drainage Characteristics
Table 2
Watershed%Imp.
WeightedCN
Lag Time(Min)
Tc
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
185/243
(acres) (sq. mi.) (acres)
A 27.0 0.0423 6.6 0.24 73 15 9B 27.7 0.0433 3.7 0.13 68 15 9
C 18.1 0.0284 1.8 0.10 66 15 9D 6.8 0.0106 1.1 0.16 77 15 9E 3.1 0.0049 1.1 0.35 75 15 9F 30.9 0.0484 8.6 0.28 79 25 15G 20.7 0.0324 6.3 0.30 73 15 9H 17.0 0.0265 2.0 0.12 67 15 9I 6.3 0.0098 0.6 0.09 62 15 9
J 14.6 0.0228 3.6 0.25 67 15 9K 8.1 0.0127 0.4 0.05 60 15 9L 28.1 0.0439 4.9 0.17 54 20 12M 23.0 0.0359 9.0 0.39 66 25 15N 23.0 0.0359 13.6 0.59 78 20 12O 10.0 0.0156 2.2 0.22 68 15 9P 16.3 0.0255 8.3 0.51 80 15 9
Watershed ( )
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
186/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
187/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
188/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
189/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
190/243
Future Conditions (Alternative 3)Area A Area B Area C
Hydraulic Length 840 ft Hydraulic Length 840 ft Hydraulic Length 300 ftSlope 0.027 ft/ft Slope 0.040 ft/ft Slope 0.033 ft/ft*Velocity 2.7 fps *Velocity 3.5 fps *Velocity 3.1 fpsTcA1 5.2 min TcB1 4.0 min TcC1 1.6 minHydraulic Length 450 ft Hydraulic Length 390 ft Hydraulic Length 810 ftSlope 0.044 ft/ft Slope 0.026 ft/ft Slope 0.031 ft/ft*Velocity 3.7 fps *Velocity 2.8 fps *Velocity 2.6 fpsTcA2 2.0 min TcB2 2.3 min TcC2 5.2 minHydraulic Length 780 ft Total TcB 6.3 min Total TcC 6.8 minSlope 0.013 ft/ft Tc Used 15.0 min Tc Used 15.0 min*Velocity 2.0 fps Lag Time 0.15 hr Lag Time 0.15 hr TcA3 6.5 minTotal TcA 13.7 minTc Used 15.0 minLag Time 0.15 hr
Area D Area E Area FHydraulic Length 660 ft Hydraulic Length 510 ft Hydraulic Length 510 ft
Slope 0.091 ft/ft Slope 0.078 ft/ft Slope 0.078 ft/ft*Velocity 5.3 fps *Velocity 4.8 fps *Velocity 4.6 fpsTcD1 2.1 min TcD1 1.8 min TcF1 1.8 minTc Used 15.0 min Tc Used 15.0 min Hydraulic Length 2400 ftLag Time 0.15 hr Lag Time 0.15 hr Slope 0.017 ft/ft
*Velocity 2.2 fpsArea G Area H TcF2 18.2 min
Hydraulic Length 300 ft Hydraulic Length 360 ft Hydraulic Length 150 ftSlope 0.067 ft/ft Slope 0.028 ft/ft Slope 0.200 ft/ft*Velocity 4.5 fps *Velocity 2.9 fps *Velocity 7.0 fpsTcG1 1.1 min TcH1 2.1 min TcF3 0.4 minHydraulic Length 870 ft Hydraulic Length 420 ft Total TcF 20.4 minSlope 0.023 ft/ft Slope 0.024 ft/ft Tc Used 25.0 min*Velocity 2.5 fps *Velocity 2.7 fps Lag Time 0.25 hr
Elm Street Brook Drainage AnalysisNorthampton, MA
Time of Concentration CalculationMarch 2011
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
191/243
TcG2 5.8 min TcH2 2.6 minTotal TcG 6.9 min Total TcH 4.7 minTc Used 15.0 min Tc Used 15.0 minLag Time 0.15 hr Lag Time 0.15 hr
Area I Area J Area KHydraulic Length 510 ft Hydraulic Length 210 ft Hydraulic Length 200 ftSlope 0.078 ft/ft Slope 0.143 ft/ft Slope 0.167 ft/ft*Velocity 4.4 fps *Velocity 5.8 fps *Velocity 7.5 fpsTcI1 1.9 min TcJ1 0.6 min TcI1 0.4 minHydraulic Length 300 ft Hydraulic Length 570 ft Hydraulic Length 510 ftSlope 0.033 ft/ft Slope 0.018 ft/ft Slope 0.029 ft/ft*Velocity 3.3 fps *Velocity 2.4 fps *Velocity 0.9 fpsTcI2 1.5 min TcJ2 4.0 min TcI2 10.0 minTotal TcI 3.4 min Hydraulic Length 60 ft Total TcI 10.4 minTc Used 15.0 min Slope 0.330 ft/ft Tc Used 15.0 minLag Time 0.15 hr *Velocity 9.0 fps Lag Time 0.15 hr
TcJ3 0.1 minArea L Hydraulic L ength 300 f t Area N
Hydraulic Length 450 ft Slope 0.005 ft/ft Hydraulic Length 1380 ftSlope 0.044 ft/ft *Velocity 1.1 fps Slope 0.015 ft/ft*Velocity 1.2 fps TcJ4 4.5 min *Velocity 2.1 fpsTcL1 6.3 min Total TcJ 9.2 min TcN1 11.0 minHydraulic Length 360 ft Tc Used 15.0 min Hydraulic Length 1200 ftSlope 0.028 ft/ft Lag Time 0.15 hr Slope 0.049 ft/ft*Velocity 0.9 fps *Velocity 3.7 fpsTcL2 7.1 min Area M TcN2 5.4 minHydraulic Length 420 ft Hydraulic Length 2250 ft Total TcN 16.4 minSlope 0.048 ft/ft Slope 0.009 ft/ft Tc Used 20.0 min
*Velocity 1.3 fps *Velocity 1.7 fps Lag Time 0.20 hr TcL3 5.4 min TcM1 22.1 minHydraulic Length 90 ft Tc Used 25.0 min Area QSlope 0.440 ft/ft Lag Time 0.25 hr H yd rau li c L en gt h 111 0 f t*Velocity 3.5 fps Slope 0.018 ft/ftTcL4 0.4 min Area P *Velocity 2.4 fpsTotal TcL 19.1 min Hydraulic Length 1050 ft TcQ1 7.7 minTc Used 20.0 min Slope 0.038 ft/ft Hydraulic Length 720 ftLag Time 0.20 hr *Velocity 3.5 fps Slope 0.028 ft/ft
TcP1 5.0 min *Velocity 3.0 fpsArea O Tc Used 15.0 min TcQ2 4.0 min
Hydr aulic Lengt h 240 f t Lag Time 0.15 hr Total TcQ 11.7 minSlope 0.125 ft/ft Tc Used 15.0 min*Velocity 6.0 fps Area R Lag Time 0.15 hr TcO1 0.7 min Hydraulic Length 510 ftHydraulic Length 810 ft Slope 0.078 ft/ft Area SSlope 0.012 ft/ft *Velocity 4.2 fps Hydraulic Length 420 ft*Velocity 1.7 fps TcR1 2.0 min Slope 0.007 ft/ftTcO2 7.9 min Hydraulic Length 450 ft *Velocity 1.5 fpsTotal TcO 8.6 min Slope 0.022 ft/ft TcS1 4.7 min
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
192/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
193/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
194/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
195/243
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
196/243
3
Proposed Conditions
2-year 10-year 25-year 100-yearDrainage Area
Hydrologic Element Location (mi 2) (ac) Tc CN (cfs) (cfs) (cfs) (cfs)
KS-E 0.0302 19.3 19 95 46.8 56.7 70.4 97.7KS-F 0.0278 17.8 15 83 34.4 44.3 58.2 86.3J-1 King Street @ Church Street 0.0580 37.1 80.8 100.5 127.9 182.8KS-G 0.0394 25.2 15 87 52.5 66.6 86.5 126.2King 36" 0.0580 37.1 75.7 94.0 119.7 171.0J-2 King Street @ Finn Street 0.0973 62.3 102.8 128.2 163.7 234.7King 48" 0.0973 62.3 101.2 126.4 161.4 231.4KS-I 0.0249 16.0 15 92 38.8 47.8 60.2 84.9J-3 0.1223 78.3 116.7 145.4 185.5 265.6
King Street Watershed Drainage AnalysisNorthampton, MA
Drainage Analysis SummaryMay 2011
-
7/31/2019 CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 2 Appendices
197/243
Div. at North St King Street @ North Street 0.1223 78.3 116.7 145.4 183.1 183.1King 48"/54" 0.1223 78.3 115.0 143.5 182.5 183.1KS-J 0.0258 16.5 15 89 36.7 46.0 59.0 84.9KS-K 0.0324 20.7 15 88 44.6 56.3 72.6 105.2KS-L 0.0425 27.2 15 85 56.6 71.9 93.4 136.3KS-M 0.0070 4.5 15 84 9.1 11.6 15.1 22.2J-8 Trumbull @ State Street 0.0820 52.4 110.3 139.8 181.2 263.7Trumbull 24" 0.0820 52.4 108.3 137.3 177.8 258.5J-7 King Street @ Trumbull Road 0.2300 147.2 188.9 239.2 309.4 449.1King 54" 0.2300 147.2 188.0 237.8 307.7 446.6KS-Q 0.0386 24.7 15 94 63.1 76.9 95.9 133.7J-9 0.2686 171.9 234.7 295.0 379.3 547.1King 54"/66" 0.2686 171.9 229.9 288.9 371.4 535.0KS-R 0.0230 14.7 15 96 39.1 47.2 58.4