Caversham Tunnel Civil Work Planning for Success

14
www.fultonhogan.com Caversham Tunnel Civil Work Planning for Success

Transcript of Caversham Tunnel Civil Work Planning for Success

Page 1: Caversham Tunnel Civil Work Planning for Success

www.fultonhogan.com

Caversham Tunnel Civil WorkPlanning for Success

Page 2: Caversham Tunnel Civil Work Planning for Success

www.fultonhogan.com

The Caversham Tunnel• Dual track tunnel

constructed in 1908 to replace old single line tunnel.

• Hand cut drainage channel through out the length

Page 3: Caversham Tunnel Civil Work Planning for Success

www.fultonhogan.com

Back Ground to project

• Drainage issues within Caversham tunnel and approaches, leading to formation failure

• This leads to reduction in level of service from KiwiRail to external clients

• Drainage issues linked to bad ballast and completely blocked drainage system.

• Works designed to increase resilience of network within tunnel against ballast and formation degradation

Page 4: Caversham Tunnel Civil Work Planning for Success

www.fultonhogan.com

Risk Management• Three main risk considerations

– Gas– Network Services– Rockfall

Page 5: Caversham Tunnel Civil Work Planning for Success

www.fultonhogan.com

Gas

Page 6: Caversham Tunnel Civil Work Planning for Success

www.fultonhogan.com

Gas

Page 7: Caversham Tunnel Civil Work Planning for Success

www.fultonhogan.com

Gas

Page 8: Caversham Tunnel Civil Work Planning for Success

www.fultonhogan.com

Network Services

• Up to 28 movements a day• Only 3-5 at night • Trains ran throughout the duration of the project

Page 9: Caversham Tunnel Civil Work Planning for Success

www.fultonhogan.com

Network Services

Compulsory Stop Protection

Page 10: Caversham Tunnel Civil Work Planning for Success

www.fultonhogan.com

Rock fall

• Unlined sandstone tunnel • Rock fall risk in certain area of tunnel

Page 11: Caversham Tunnel Civil Work Planning for Success

www.fultonhogan.com

Planning and Logistics

• Block of Line in two 72 hour periods

• 3 separate contracting groups working together to deliver outcome

• FH to remove old ballast and regrade and compact formation

Page 12: Caversham Tunnel Civil Work Planning for Success

www.fultonhogan.com

Planning and Logistics

Page 13: Caversham Tunnel Civil Work Planning for Success

www.fultonhogan.com

Planning and Logistics

Page 14: Caversham Tunnel Civil Work Planning for Success

www.fultonhogan.com

Planning and Logistics