Regional Drought Task Force: Kick-off Meeting
June 12, 2019
Catalina Water: Drought Contingency Plan
2019JUN 4
US Drought Monitor, http://droughtmonitor.unl.edu
Southern California Edison
Objective
• Task Force introduction to the Catalina Drought Contingency Plan
• Reaffirm Task Force participants
2
Southern California Edison
Agenda
1. Introductions and Background
2. USBR Drought Response Program Overview
3. DCP Task Force
4. DCP Work Plan
5. DCP Elements
6. Communications
7. Questions and Feedback
8. Next Meeting
DCP= Drought Contingency Plan
USBR = United States Bureau of Reclamation (Reclamation)
3
Southern California Edison
Introductions
• Southern California Edison (SCE)
• United States Bureau of Reclamation (USBR)
• Task Force
o Interested stakeholders within the planning area representing different sectors
4
Identified Task Force Members Contact6/12/19
Attendance
Catalina Chamber of Commerce ✔
Catalina Island Company ✔ ✔
Catalina Island Conservancy (CIC) ✔ ✔
CIC Airport ✔ ✔
City of Avalon ✔ ✔
City of Avalon Fire ✔
County of Los Angeles Fire
School District ✔ ✔
Rancho Escondido, Vineyard
Two Harbors
USC Lab ✔
Camps
California Public Utilities Commission (CPUC)
✔ ✔ (SCE Rep)
California Division of Drinking Water (DDW)
✔ ✔ (SCE Rep)
Southern California Edison
Background: USBR WaterSMART Programs
• Drought Contingency Plan• Contract Q2/2019
• Completion Q1/2021
• Water Reliability Study• MOU Q1/2018
• Phase 1 of 5 underway
5
Active Catalina Reclamation Projects: Water Reliability Study Drought Contingency Plan
USBR Program Update June 2019
Southern California Edison
USBR Drought Response Program
• Purpose: Prepare for and address drought in advance of a crisis• Create a legacy of conservation stewardship• Modernize infrastructure• Restore trust with local communities
• Contingency Planning: Develop and update a comprehensive drought plan (Drought Contingency Plan) • Open and inclusive planning efforts to proactively build
long-term drought resilience• Consider impacts of climate change • http://www.usbr.gov/drought/
• Resiliency Projects: Implement projects that will build long-term resiliency to drought (Drought Resiliency Projects)
6
USBR Data Visualization (Drought Response Projects and Contingency Planning)
Southern California Edison
Phase 1: Establish Task Force
• Task Force is a mechanism to:• Exchange information
• Discuss issues and solutions
• Coordinate response activities
• Anticipated meeting cadence: quarterly or as deliverables dictate
7
Deliverables Timing
Establish Task Force Q2/2019
Develop Work Plan Q3/2019
Drought Contingency Plan Development
Q4/2019 toQ4/2020
Plan Finalized and Approved by USBR
Q1/2021
Southern California Edison
Phase 1: Refine The Work Plan
• Introduction• Background
• Planning approach• Roles and responsibilities
• Documentation and reporting• Deliverables
• Reporting
• Review process
• Communication and outreach plan• Stakeholder and public involvement
8
Southern California Edison
Phase 2: Development of Drought Contingency Plan
• Drought Contingency Plan elements• Drought Monitoring
• Vulnerability Assessment
• Mitigation Actions
• Response Actions
• Operational & Administrative Framework
• Plan Update Process
9
Southern California Edison
DCP: Drought Monitoring
• Establish a framework or process for:• Monitoring near and long-term water availability
• Predicting the probability of future droughts
• Collection, analysis, and dissemination of water availability and other drought-related data
10
• Precipitation
• Temperature
• Streamflow levels
• Identifying metrics and triggers drought severity and/or response action
NOAA Water cycle
Southern California Edison
DCP: Vulnerability Assessment
• Evaluate drought risks and impacts • Rural location
• Isolation, Limited Interconnections
• Fractured rock groundwater
• Reliance on single source (groundwater)
• Climate change
• Drives the development of potential mitigation and response actions
11
Southern California Edison
DCP: Mitigation Actions
• Identify, evaluate and prioritize actions that build long-term resiliency ahead of a drought and mitigate risks posed by drought
• Actions, programs, and strategies implemented before drought to address potential risks and impacts
• Intended to decrease sector vulnerabilities and reduce the need for response actions
• Prioritized recommendations• Water portfolio diversity and optimization
• Water Reliability
12
83%
17%
Portfolio, 600 AFY-basis (2008)
Groundwater Desal
33%
26%
41%
Actual, 600 AFY-basis (2013-2017)
Groundwater Desal Conservation
Southern California Edison
DCP: Response Actions
• Identify, evaluate and prioritize actions that can be implemented during a drought to mitigate risks posed by drought
• Specific actions triggered during specific stages of drought to manage the limited supply and decrease the severity of immediate impacts
• Able to be quickly implemented to provide expeditious benefits
13
July 2018
Southern California Edison
DCP: Operational & Administration Framework
• Identifies responsibility for undertaking actions necessary to implement each element of the Drought Contingency Plan• Conduct drought monitoring
• Initiate response actions, including emergency response actions
• Initiate mitigation actions
• Update the Drought Contingency Plan
• Identifies Task Force and stakeholders
• May be integrated into each element or documented in a specific section of the plan
14
Task Lead Member Responsibilities Coordinates With Procedures / Resource
Documentation
Southern California Edison
DCP: Plan Update Process
• Describe the process to update the plan• Stakeholder engagement
• Ongoing evaluation
• Measuring effectiveness
• Cadence of updates
• Data and models used
15
Southern California Edison
Communications
• SCE Program Manager: Luke Schaner, [email protected]
• USBR Program Manager: Leslie Cleveland, [email protected]
16
Southern California Edison
Questions and Feedback
17
Southern California Edison
Next Meeting
18
Southern California Edison
End of Presentation