Case study-optimization-cbm

1
PROJECT OVERVIEW One key area oŌen overlooked by producers is eld producƟon aŌer new wells have brought ush producƟon into an exisƟng system, an example that happens repeatedly. Our hypotheƟcal client is producing 20 MMscf/d and brings in several new wells that test at an addiƟonal 4 MMscf/d. The logical thought process is that now the producer will move 24 MMscf/d, however this rarely happens. In most cases, the increased producƟon will only add 12 MMscf/d. Several reasons aƩribute to this phenomenon, the majority of which are directly Ɵed into the operaƟon and design of the exisƟng gathering and compression systems ACTION An audit of the exisƟng low pressure CBM system with the incorporaƟon of hydraulic modeling of their pipeline and compression equipment for the planned future producƟon provided the necessary system modicaƟons to allow for full producƟon of the new capacity. The client was planning to add 6000 Hp of compression to meet the sales agreement requirements of 30 MMscf/d. Current sales were only at 27,500 MMscf/d. The client uƟlized 6000 Hp of four @ 4 stage electric drive compressors and 10000 Hp of ve 2 and 3 stage gas drive compressors RESULT GCC provided a mulƟ‐eld gathering and compression audit/white paper. The tesƟng of wells and segments of the gathering system supplied proof that addiƟonal producƟon capability was available. GCC modeled and redesigned the gathering pipe and reallocated compression and process resources. This allowed our client to maintain their 30 MMscf/d CBM producƟon, have the unrestricted capability for an addiƟonal 10.0 MMscf/d for their planned future drilling program, while also reducing lease and operaƟon costs over $800,000.00/yr. CASE STUDY: COMPRESSION FACILITY DESIGN AUDIT and OPTIMIZATION GCC INC. 4725 S MONACO STREET SUITE 360 DENVER, COLORADO 80237 303.400.4300 MAIN OFFICE WWW.GCCINC.US For more informaƟon contact: ANDREW HARRAH 720.352.8586 Mobile 303.325.2075 Oce [email protected] Project at a Glance LocaƟon Type Audit & OpƟmizaƟon IniƟal Capacity 20 MMscf/d Final Capacity 30 MMscf/d (+ addiƟonal capability of 10.0 MMscf/d) Overall Savings: $800,000* *in Lease and operaƟng cost “GCC has provided valuable gathering and compressor operaƟon modeling, staƟon engineering, sourced our producƟon equipment and compressors. GCC’s assistance has substanƟally enhanced our producƟon while providing direct cost savings to our operaƟons. ” Aubrey Harper, President, Eastern Washakie Midstream

Transcript of Case study-optimization-cbm

Page 1: Case study-optimization-cbm

PROJECT OVERVIEW 

One key area o en overlooked by producers is field produc on a er new wells

have brought flush produc on into an exis ng system, an example that happens

repeatedly. Our hypothe cal client is producing 20 MMscf/d and brings in several

new wells that test at an addi onal 4 MMscf/d. The logical thought process is that

now the producer will move 24 MMscf/d, however this rarely happens. In most

cases, the increased produc on will only add 1‐2 MMscf/d. Several reasons

a ribute to this phenomenon, the majority of which are directly ed into the

opera on and design of the exis ng gathering and compression systems

ACTION 

An audit of the exis ng low pressure CBM

system with the incorpora on of hydraulic

modeling of their pipeline and compression

equipment for the planned future produc on

provided the necessary system modifica ons

to allow for full produc on of the new capac‐

ity. The client was planning to add 6000 Hp of

compression to meet the sales agreement

requirements of 30 MMscf/d. Current sales

were only at 27,500 MMscf/d. The client

u lized 6000 Hp of four @ 4 stage electric

drive compressors and 10000 Hp of five 2

and 3 stage gas drive compressors

RESULT 

GCC provided a mul ‐field gathering and compression audit/white paper. The

tes ng of wells and segments of the gathering system supplied proof that addi‐

onal produc on capability was available. GCC modeled and redesigned the

gathering pipe and reallocated compression and process resources. This allowed

our client to maintain their 30 MMscf/d CBM produc on, have the unrestricted

capability for an addi onal 10.0 MMscf/d for their planned future drilling program,

while also reducing lease and opera on costs over $800,000.00/yr.

 CASE STUDY: COMPRESSION FACILITY DESIGN 

AUDIT and OPTIMIZATION 

GCC INC. 4725 S MONACO STREET SUITE 360 DENVER, COLORADO 80237 303.400.4300 MAIN OFFICE WWW.GCCINC.US

For more informa on contact: ANDREW HARRAH 720.352.8586 Mobile 303.325.2075 Office [email protected]

Project at a Glance 

Loca on —

Type Audit & Op miza on

Ini al Capacity 20 MMscf/d

Final Capacity

30 MMscf/d (+ addi onal

capability of 10.0 MMscf/d)

Overall Savings: $800,000*

*in Lease and opera ng cost

“GCC has provided valuable 

gathering and compressor opera on 

modeling, sta on engineering, 

sourced our produc on equipment 

and compressors.  GCC’s assistance 

has substan ally enhanced our 

produc on while providing direct 

cost savings to our opera ons. ” 

‐Aubrey Harper, President, Eastern

Washakie Midstream