Right of Way (ROW) Session – Short Course October 11, 2017
CASE STUDY OF A SUCCESSFUL PROJECT – TYING IT ALL TOGETHER
Right of Way (ROW) Session – Short Course
October 11, 2017
Right of Way (ROW) Session – Short Course October 11, 2017
Overview
2
Team Process1
Case Study – US 281 Phase 22
Questions & Answers3
Contact Information4
Right of Way (ROW) Session – Short Course October 11, 2017
Team Process
3
ROW Section Prioritizes Acquisitions
Design
ROWUtilities
Process Identifies Property Needs
Coordinate Utility Relocations
Communication Communication
Communication
Right of Way (ROW) Session – Short Course October 11, 2017
Case Study – US 281 Phase 2
4
Right of Way (ROW) Session – Short Course October 11, 2017
Case Study – US 281 Phase 2
5
• Expand to Six-lane Expressway with Frontage Roads,
General Purpose and Two HOV Lanes
• Limits: 0.8 Mi. North of Stone Oak Pkwy to Bexar/Comal
County Line
• ROW Increased from 200’ to 500’ (Typical)
• Letting December 2018
• Construction Estimate of $200MNOTE: Highlighted areas are not drawn to scale.
281
1010
410
35
35
16041604
A
SanAntonio
46
1863
Segment 1
Segment 2
Right of Way (ROW) Session – Short Course October 11, 2017
Case Study – US 281 Phase 2
6
DesignROW
AcquisitionClearing
Utility Relocations
Construction
• Schematic Developed Footprint, Included
Utilities
• Identified Required Property
• Created ROW Map w/utility easements
• PS&E Refined Improvements; Emphasized
Reducing Utility Conflicts
Right of Way (ROW) Session – Short Course October 11, 2017
Case Study – US 281 Phase 2
7
DesignROW
AcquisitionClearing
Utility Relocations
Construction
• 54 Parcels Identified
• 47 Parcels Acquired by September 2017
• 24 Eminent Domain Hearings
• 7 Parcels Remaining
• ROW Budget of $ 99 M
Right of Way (ROW) Session – Short Course October 11, 2017
Case Study – US 281 Phase 2
8
DesignROW
AcquisitionClearing
Utility Relocations
Construction
• Acquisitions Prioritized by Traffic Control
Plan & Sequence of Work
• Vegetation Clearing Plan Based on Non-
joint Bid Facilities (OH)
• ROW Clearing Anticipated Completion in
January 2018
• CPS Energy Relocations Scheduled by
TCP and ROW Acquisitions
Right of Way (ROW) Session – Short Course October 11, 2017
Case Study – US 281 Phase 2
9
DesignROW
AcquisitionClearing
Utility Relocations
Construction
• Avoid, Minimize, Accommodate
• Redesigned frontage road
• Engaged Utility Owners Early in Design
• Received Input on Relocation Requirements
and Schedules
• Ongoing utility coordination with SAWS water
& sewer, CPS gas, CPS overhead electric,
AT&T, Spectrum, GVTC, and Level 3
Right of Way (ROW) Session – Short Course October 11, 2017
Case Study – US 281 Phase 2
10
DesignROW
AcquisitionClearing
Utility Relocations
Construction
• 95% Milestone in January 2018
• Non-joint Bid Utilities Begin
• Field Monitoring & Survey Relocations
for 100% Milestone Plans
• Project Lets December 2018
Right of Way (ROW) Session – Short Course October 11, 2017
Case Study – US 281 Phase 2
11
Project Challenges/Solutions
• Knowledge of the Process
Meetings, Phone Calls, Emails, Etc.
• Insufficient Field Conditions Identified
Pre-Design Field Study
• Limited Border Width in Certain Areas
Consultant Revised Design
• Acquisitions from Utility Companies
Maintaining Easements When Present
• Identifying Utility Easements Correctly
Consultant & Utility Owner Verification
Right of Way (ROW) Session – Short Course October 11, 2017
Case Study – US 281 Phase 2
12
Questions & Answers
Right of Way (ROW) Session – Short Course October 11, 2017
Contact Information
13