Case Study Kee Walk & Kee Guard Top Fix€¦ · m of KeeWalk and 320 Guard TopFix to provide safe...
Transcript of Case Study Kee Walk & Kee Guard Top Fix€¦ · m of KeeWalk and 320 Guard TopFix to provide safe...
Case Study Kee Walk & Kee Guard Top Fix
Hong Kong Sports Institute Project (Swimming Pool Roof)
Name: Hong Kong Sports Institute Project (Swimming Pool Roof)
Location: Shatin, Hong Kong,
Roofing Contractor: Craft Project (Kalzip 400 roof)
Kee Partner: Modern International
Product: KeeGuard Topfix & Kee Walk
Value: US$36k
Installation Date: January 2013
• Hong Kong Sports Institute • Location: Shatin, Hong Kong • Design/Completion: 2007/2013 • Client: Hong Kong Sports Institute
Ltd. • Site Area: 158,650 sq.m • Gross Floor Area: 95,000 sq.m
• The redevelopment of the Hong
Kong Sports Institute (HKSI) includes a new multi-purpose sports hall, a new indoor Olympic swimming pool, a new rowing house and building which accommodates the athletes' hostel and the offices of the HKSI management
Kee Safety LLC in partnership with Modern Engineering Co., Hong Kong designed, supplied and installed 160m of Kee Walk and 320m of Kee Guard TopFix to provide safe walkway access on the Kalzip Standing Seam roofs. The unique modular concept of KEE WALK with the ability for simple site adjustments and speed of installation, made this the system of choice by the Roofing Contractor, 'Craft Projects International Co Ltd'.
Both KEE WALK & KG TOPFIX provide a non-penetrative solution when fixed to a Standing Seam roof ensuring the roof integrity at all times.
The complexity of the roof layout would have made this a challenging project however the entire installation was completed in seven days
KEE SAFETY LLC Dubai Investment Park (DIP), Near Green Community, PO Box 18448, Dubai, UAE
Tel: (+971) 4 8859066 Fax: (+971) 4 8859065 Email: [email protected] Website: www.keesafety.ae