Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's...

376
CASE STUDIES IN SUBCONTRACTING David Anthony Donovan

Transcript of Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's...

Page 1: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

CASE STUDIES IN SUBCONTRACTING

David Anthony Donovan

Page 2: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 3: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

NAVAL POSTGRADUATE SCHOOL

Monterey, California

CASE STUDIES IN SUBCONTRACTING

by

David Anthony Donovan

and

Charles Russell Privateer

Thesis Advisor: CDR P. DeMayo, SC, USN

March 1974

TT159602

kppiovzd iofi public ndLtcML) daX/ubvution untimLtzd.

Page 4: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 5: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

Case Studies in Subcontracting

by

David Anthony , DonovanLieutenant Commander, United States NavyB.S., United States Naval Academy, 1959

and

Charles Russell PrivateerLieutenant Commander, Supply Corps, United States Navy

B.S., Case Institute of Technology, 1962

Submitted in partial fulfillment of therequirements for the degree of

MASTER OF SCIENCE IN MANAGEMENT

from the

NAVAL POSTGRADUATE SCHOOL

March 1974

Page 6: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

//)-•

Page 7: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

ABSTRACT

Subcontractors play a significant role in government

procurement and are essential to an effective procurement

process. Current estimates of DOD procurement show that at

least 50 percent of prime contract funds are subcontracted.

A series of three case studies has been developed to illus-

trate major concerns in subcontracting. The cases are

designed to introduce the student to subcontracting and to

the specific procedures and requirements of Contractor

Procurement System Reviews, subcontract review and consent

by the government, and subcontractor source selection. Par-

ticular attention has been paid to an examination of

subcontracting from the point of view of both the prime con-

tractor and the government as well. Teaching commentaries

are included to assist the instructor.

Page 8: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 9: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

TABLE OF CONTENTS

I. INTRODUCTION 4

II. CONTRACTOR PROCUREMENT SYSTEM REVIEW:A CASE STUDY 7

A. INTRODUCTION 7

B. THE CASE PROBLEM -- 14

C. CPSR RESULTS AND CASE REQUIREMENTS 26

D. TEACHING COMMENTARY 31

III. SUBCONTRACT REVIEW AND CONSENT BY THEGOVERNMENT: A CASE STUDY -- -- -— 35

A. CASE BRIEF AND OBJECTIVES 35

B. CASE PRESENTATION 35

APPENDIX ONE: ASPR MAKE-OR-BUYREQUIREMENTS 51

APPENDIX TWO: ASPR SUBCONTRACT REVIEWAND CONSENT REQUIREMENTS - - 56

C. TEACHING COMMENTARY 62

IV. SUBCONTRACTOR SOURCE SELECTION: ACASE STUDY 70

• A. INTRODUCTION --- - 70

B. CASE BACKGROUND --- 79

C. REVIEWING THE SOURCE SELECTION 92

D. CASE REQUIREMENTS 169

E. TEACHING COMMENTARY 171

BIBLIOGRAPHY -- 181

INITIAL DISTRIBUTION LIST --- 182

FORM DD 1473 --- 183

Page 10: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 11: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

I. INTRODUCTION

Subcontracting is becoming increasingly important in

government procurement. With fewer and more expensive

major weapon system acquisitions, the government is specify-

ing prime contracts that require a large portion of the work

be subcontracted. In 1970, an estimated 50 cents out of

every DOD prime contract dollar went to subcontractors.

The Apollo program alone included some 20,000 subcontractors.

In such circumstances the government could hardly choose to

deal directly with each subcontractor. But even in programs

where the number of subcontractors is relatively small, any

three party arrangement would be highly unworkable. Thus

the prime contractor is tasked by the government to manage

all subcontractors supporting a given prime contract.

While the prime contractor is the manager of all sub-

contracts, the government has developed numerous requirements

which impact directly on the subcontractor. These range from

socio-economic objectives to technical specifications and

accounting procedures. Usually these requirements are

stated in the prime contract which specifies that the pro-

visions "flow-down" in any subsequent subcontract. When a

U.S. Comptroller General Report B-169434, Need to ImproveEffectiveness of Contractor Procurement System Reviews

,

18 August 1970, p. 4.

Page 12: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 13: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

subcontractor enters into a subcontract he agrees to adhere

to these requirements. Despite the many government require-

ments laid on a subcontractor, he has no formal direct access

to the government. The subcontractor has no privity or

legal relationship with the government. By and large

government-subcontractor interaction takes place through the

prime contractor.

The first case deals with the Contractor Procurement

System Review Program. The case illustrates a typical con-

tractor procurement organization and describes the process

by which the government insures that a contractor's procure-

ment practices meet certain standards of efficiency, effec-

tiveness, and contractual compliance. In the second case

the student is introduced to the process by which a govern-

ment contracting officer reviews a proposed subcontract

submitted by a contractor for government consent. Make-or-

buy considerations are also introduced. Case number three

outlines a typical source selection procedure used by a

major defense contractor in awarding subcontracts. Source

selection policy and the mechanical details of source

selection are discussed, as well as controversial aspects

of negotiated procurement and source selection.

Each case lends itself to analysis by the student and

the development of alternative solutions. In addition, each

case illustrates the flexible role of the government contract

Page 14: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 15: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

administration organization in subcontracting and some of

the considerations which bear on the extent of government

involvement in subcontracting.

Page 16: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 17: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

II. THE CONTRACTOR PROCUREMENT SYSTEM REVIEW:A CASE STUDY

A. INTRODUCTION

1. Case Brief and Objective

The purpose of this case is to introduce the student

to the Contractor Procurement System Review Program. The

case will illustrate the performance of a procurement review

at a contractor's plant and the evaluation process subsequent-

ly performed by the cognizant Government agency. By this

means the student will gain an understanding of the review

process and will be made familiar with typical contractor

procurement statistics and their significance.

2

.

The Contractor Procurement System Review Program

The Contractor Procurement System Review (CPSR)

Program is a program by which the DOD reviews the procurement

systems of certain contractors who are performing under

Government contracts. Authority for the program is derived

from Title 10 U. S. Code 2306(e). Section XXIII (Part One)

and Supplement Number One of the Armed Services Procurement

Regulations implement the CPSR program within the DOD.

The purpose of the CPSR program is to determine

whether the contractor is in compliance with statutory re-

quirements and prime contract clauses and provisions related

to purchasing and subcontracting. Reliance upon a contrac-

tor's approved procurement system will usually obviate the

Page 18: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 19: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

need for reviewing and consenting to individual subcontracts.

The objectives of the review are to provide:

1. a means for evaluating the efficiency andeffectiveness with which the contractor spendsGovernment funds;

2. the basis for the administrative contractingofficer to grant, withhold, or withdraw approvalof the contractor's procurement system;

3. reliable current information to the procuringcontracting officer on the contractor's pro-curement system for use in source selection,determining the appropriate type of contract,and establishing profit and fee objectives;

4. an independent review of the contractor's pro-curement system to optimize its effectivenessin complying with Government policy; and

5. current procurement system information forappropriate DOD activities in areas of Govern-ment interest.

Several types and variations of a CPSR are performed

under the program. An Initial Review is a complete,

intensive analysis of a contractor's procurement system

which is being reviewed for the first time. This review will

result in a written report and, upon correction of deficien-

cies, approval of the contractor's procurement system. Sub-

sequently, the cognizant Administrative Contracting Officer

(ACO) must make a determination annually of the need to make

a follow-up review. These Subsequent Reviews as they are

called should generally be limited to areas of weakness or

special importance; however, at the discretion of the ACO,

they may be as extensive as the Initial Review. Again a

written report will be made. Should the ACO decide that a

Page 20: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 21: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

Subsequent Review is not needed during a given year, this

fact must also be documented^

If approval of a contractor's procurement system is

withheld or withdrawn, a follow-up review will be made as

soon as the contractor has completed corrective action. This

review is performed in a manner similar to the Subsequent

Review, but is structured to test the areas of weakness pre-

viously noted. Once again a written report is made.

An Initial Review of a contractor's procurement

system shall be made when he is expected to have sales to

the Government in excess of $5,000,000 during the next

twelve months on other than firm fixed-price with escalation

contracts. In addition, consideration shall be given to

conducting a CPSR when sales to the Government on non-

competitive negotiated contracts (including modifications to

competitively awarded contracts), regardless of contract type,

are expected to exceed $5,000,000 either alone or in combin-

ation with the previously mentioned criteria.

The CPSR program is carried out by the Defense

Contract Administration Service and by the military services

under the Plant Cognizance Program. Under the direction of

a Procurement Methods Analyst, a CPSR gives special attention

to the following areas of a contractor's procurement

operation:

1. the degree of price competition obtained;

2. pricing policies and techniques, including methodsof obtaining accurate, complete, and current costand pricing data, and certification as required;

Page 22: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 23: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

3. the methods of evaluating subcontractors'responsibility;

4. the treatment afforded affiliates;

5. types of subcontracts used;

6. practices pertaining to small business andlabor surplus area programs;

7. attention given to the management of majorsubcontract programs.

The review of a contractor's procurement system must

determine whether subcontracting is done competitively insofar

as possible. This requires ascertaining whether:

1. a sufficient number of sources are solicited;and

2. subcontracting procedures provide other elementsof adequate and effective price competition,including -

a. adequate descriptions of any factors to beevaluated and

b. evaluation of all offers on a common basis.

The scope of the CPSR Program is illustrated by the

following summary for the year ending 1971:

Contracts Administered by DCAS - 170,000

Number of Contractors - 15,000

Face Value of Prime Contracts - $49.0Administered Billion

Prime Contractors in CPSR Program - 171

Contractors with Approved Systems - 140

Contractors with Non-Approved Systems - 20

Contractors Awaiting Initial Review - 11

Face Value of Prime Contracts - $20Held By CPSR Contractors Billion

10

Page 24: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 25: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

Percentage of Contractors - 1%Covered by CPSR Program

Percentage of Dollar Value of - 41%Contracts Covered

The CPSR Process typically consumes about nine weeks

from commencement of planning the review until a final

determination of the status of the contractor's procurement

system is made. The first key event in the process is an

Entrance Conference during which the review team outlines

for the contractor what the team intends to learn from the

review and how the review will be carried out. The detail

work of the review requires from two to three weeks:

interviewing contractor and DCASO personnel, reviewing

procurement directives and contract files, and analyzing

purchasing data. Areas to be looked at and techniques to

be employed are spelled out in a DOD Manual for CPSR's. An

additional week is needed to prepare a report of the review,

after which an Exit Briefing is held to discuss with the

contractor those areas which will generate recommendations.

Upon return to DCASR headquarters, the CPSR team

must present its report to a CPSR Board. Members of the

CPSR Board are selected from within the Directorate of

Contract Administration at DCASR. The Chief, Contractor

Systems Review Branch, who is also the immediate supervisor

of the members of the review team, normally serves as

chairman of the CPSR Board. The Board in turn prepares a

final report with a recommendation to the ACO to approve

or withdraw approval of the contractor's procurement system.

11

Page 26: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 27: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

Only after the ACO takes this final action is the contractor

officially apprised of the findings and recommendations from

the review.

3. Government Contract Administration

Major contract administration responsibility within

DOD rests with the Defense Contract Administration Services

(DCAS) under the Defense Supply Agency. This responsibility

is dispersed geographically among eleven DCAS Regions with

DCASR headquarters located in eleven major cities. The

regions are further subdivided into district and plant

offices, as necessary, in relation to the volume of defense

contracts in areas across the country.

DCAS exercises primary responsibilities in Government

contractor relationships. Major functional areas in which

DCAS is involved include the following:

1. Contract administration

2. Production management

3. Quality assurance

4. Industrial security

5. Data and financial management

6. Support to small business and labor surplusarea programs

7. Miscellaneous tasks, including implementationof the Contractor Procurement System ReviewProgram.

The principle field organization element of the DCAS

system is the region headquarters or DCASR. A typical DCASR

is organized into Directorates of Contract Administration,

12

Page 28: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 29: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

Production, and Quality Assurance. In addition, there are

Offices of Contracts Compliance, Engineering, Industrial

Security, Planning and Management, Finance and Accounting,

and Small Business.

While the bulk of defense contracts are administered

by the DCAS field organizations, a substantial number of

contracts are administered by other defense agencies and

activities, including the military services. Certain plants

and facilities of manufacturers have been assigned to the

military departments for contract administration services

under the Plant Cognizance Program. Contracts performed at

commercial shipyards are administered by the Navy. The

exceptions to DCAS jurisdiction enumerated in ASPR 20-703.2

form an extensive list.

When a procuring activity assigns a contract to a

DCAS field activity for administration, the degree of the

DCAS involvement with the contractor varies from slight to

extensive. The type and value of the contract, the period

of performance, and the nature of the product are only

some of the factors which govern the level of DCAS involvement

Every contract for which DCAS assumes administrative

responsibility is assigned to an Administrative Contracting

Officer (ACO) . This responsibility is exercised by ACO's

located at the various DCASR's and also at DCAS offices

(DCASO's) at contractor plants.

13

Page 30: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 31: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

B. THE CASE PROBLEM

1. The Contractor History and Organization

The Pacific Laboratories Division (PLD) was estab-

lished in 1961 as a subsidiary of the Farraday Corporation.

Since its founding, PLD had concentrated on development and

production of special purpose electronic systems for the

Department of Defense. The bulk of PLD work involved

communication satellite system components. During 1972

there were over 300 employees at PLD and annual sales had

climbed to $119,000,000. However in the following year, total

sales decreased significantly as two major defense contracts

were completed. The scope and nature of PLD's operations is

indicated by the following data:

Government vs Commercial Sales ($000)1972 1975

*Government $105,100 $67,403Commercial 14,500 20,269

Total Sales $119,600 $87,672

* Includes prime contracts only.

Types of Government Contracts Held ($000)1972 1973

FFP 18% ($18,6007 48% ($32,1801NON-FFP 82% ($86,500) 52% ($35,223)

The organization of Pacific Laboratories was typical

of most firms of similar size and business nature. PLD had

begun as a small engineering company. Although not apparent

from the formal structure, the engineering orientation per-

sisted and was consistent with the firm's image of itself as

14

Page 32: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 33: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

a producer of engineering systems of considerable complexity

and reliability. The basic PLD organization, less staff

divisions, is shown in Exhibit One.

The responsibility for purchasing at PLD was largely

centralized in a Purchasing Group under the Production

Manager. The company recognized that centralization of

purchasing authority was essential if profitability was to

be enhanced by purchasing efficiency. Due to the nature of

PLD's products, it was necessary to permit engineering per-

sonnel some leeway to discuss design and quality requirements

with potential vendors. However, once specifications became

firm, purchasing assumed full responsibility for the procure-

ment. The organization of the Purchasing Group is shown in

Exhibit Two. The magnitude of purchases at PLD during the

past two years was:

Sales vs Purchases

1972 1973

Sales $119,600 $87,672Purchases $ 37,717 $22,415Ratio Purchases to Sales 311 261

Personnel Strength

1972 1973

Purchasing Group 68 54PLD Total 3141 2713

PLD contracts were initially administered by DCASR,

Los Angeles. By 1966, the value of PLD contracts and other

factors were sufficient to require performance of contract

15

Page 34: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 35: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

DIVISIONGENERAL MANAGER

rPRODUCTION SALES

5ENGINEERING

g N I N G|

[CONTROL[ j

RECEIVING| |

PURCHASING*]

INSPECTIONTl QUALITYASSURANCE

1ADVANCED

DEVELOPMENT

EXHIBIT ONE

16

Page 36: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 37: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

PURCHASING DIRECTORT

SUPERVISOR

EDITING & OFFICE

EDITER

editerH Jorder

GENERAL PURCHASING AGENT

CAPITAL EQUIPMENT, PLANTMATERIAL, SERVICES

FILES

WRITING

EDITER f—HTR

E

CORDS j

BUYERMATERIALS D

BUYERMATERIALS E

SUBCONTRACTSUPERVISOR

GENERAL PURCHASINGAGENT

PROGRAM REQUIREMENTS"

BUYERMATERIALS A

BUYERMATERIALS B

BUYERMATERIALS C

SUBCONTRACTREPRESENTATIVE

SUBCONTRACTREPRESENTATIVE

EXHIBIT TWO

17

Page 38: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 39: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

administration at PLD on a full time basis. Consequently, a

DCASO was established at the contractor's plant and by 1974,

twenty five personnel had been assigned (see Exhibit Three)

.

Both the Chief, DCASO (PLD) and Mr, George Brown,

Chief of the Contract Administration Division, were desig-

nated Contracting Officers as defined by ASPR 1-201.3.

Responsibility for performing ACO functions with regard to

PLD was specifically assigned to Mr. Brown.

2. Current CPSR Status

Early in its history Pacific Laboratories' sales to

the Government justified inclusion of PLD in the Contractor

Procurement System Review Program. But for a lack of

personnel resources at DCASR, Los Angeles, an Initial Review

of the PLD procurement system was delayed until 1968.

Approval of PLD's procurement system was welcomed by

both the contractor and 1he Administrative Contracting

Officer (ACO) at DCASO (PLD). The contractor looked forward

to greater freedom in placement of subcontracts and a reduc-

tion of administrative lead time. The frequency of require-

ments for advance notification to and prior consent of the

Contracting Officer in placement of subcontracts would be

much less. An approved purchasing system gave PLD a real,

though immeasurable, improvement in its competitive position

relative to future Government \vork. And finally, the value

of Government advice on improving purchasing efficiency

could not be ignored.

18

Page 40: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 41: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

CHIEF, DCASO (PLD)(LTCOL, USA)

ENGINEERING

CHIEF CONTRACT ASM I N I STRATOR(GS - 13) (ACQ)

PRICE ANALYSTS (2)(GS-12)

1PRODUCTION

CONTRACT SPECIALISTS (2)fGS-q . GS-5)

:lerk

EXHIBIT THREE

19

Page 42: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 43: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

For the past two years the ACO and others in the

Contract Administration Division had worked with PLD to

structure an acceptable purchasing system. While an approved

system gave the Government greater assurance of the efficiency

with which PLD spent its funds, a more tangible benefit to

the ACO was a reduction in the time his office had to devote

to overseeing PLD's procurement operations.

In 1974, the ACO, DCASO(PLD), again requested DCASR,

Los Angeles, to conduct a Subsequent Review of PLD in

accordance with Armed Services Procurement Regulations (ASPR)

article 23-101 (b). Examination of areas of weakness noted

in the 1973 review was requested, as well as the following

specific items:

1. the degree of price competition obtained;

2. the methods of evaluating subcontractors'responsibility;

3. pricing policies and techniques, includingmethods of obtaining accurate, complete, andcurrent cost or pricing data;

4. the treatment afforded affiliated and otherconcerns having close working arrangementswith PLD;

5. the performance of PLD in awarding subcontractson a competitive basis to the maximum extentpossible.

Preparation of the CPSR by DCASR, Los Angeles, was

extensive. Agnes Barnum, a senior Procurement Methods

Analyst and a GS-12, was assigned as review team captain.

Two additional PMA's from DCASR, also GS-12's, were included

as members. Pacific Laboratories was informed by letter of

20

Page 44: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 45: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

the forthcoming review and the specific areas to be examined.

The contractor was asked to make available written material

on his procurement organization, procurement directives and

policies, and an extensive statistical package on 1973

purchases, including the procurement files themselves.

Early on the first morning of the in-plant review,

a meeting was held between members of the review team and

key personnel from DCASO(PLD). The meeting served not only

a "get acquainted" function but also allowed identification

of specific responsibilities of members of the two groups.

Much of the information needed by the review team, both

written and unwritten, would be provided by DCASO personnel.

George Brown, the ACO at DCASO, served as unofficial host.

Also present at the meeting was the resident DCAA auditor,

a GS-12.

Later that day the Entrance Conference with the

contractor was held. The meeting was brief and business-like

but friendly. PLD's Production Manager welcomed the CPSR

team and outlined the major programs under contract to PLD.

The Director of the Purchasing Group then outlined major

purchasing operations during the past year and introduced

key members of the Purchasing Group. Mrs. Barnum described

the areas to be reviewed and expressed her intention to com-

plete the in-plant phase in two weeks time if possible. The

conference took less than an hour.

On the following day the review began in earnest.

The examination of purchase order file documents is without

21

Page 46: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 47: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

doubt a most important part of the review procedure. While

a team might like to examine the files for every purchase

order placed during the past year, there is not sufficient

time to do so. Consequently, review teams examine statisti-

cal samples of purchase orders within broad dollar categories,

as well as a sample of currently active subcontracts. The

process is tedious and time consuming, usually dragging on

for a full two weeks. Inevitably, questions are raised

requiring discussion with DCASO contracts personnel and

members of the contractor's purchasing group. Consequently,

completion of the statistical sample provides the review

team not only with raw data but considerable insight into

how the contractor does his purchasing. Following is a

summary of the statistical sample produced during the PLD

review:

OVER $25,000 to $10,000 to UNDERUNIVERSE $100,000 $100,000 $25,000 $10,000 TOTAL

Total No.of POs 17 64 136 24,744 24,961

Value($000) $5,400 $2,900 $2,300 $7,308 $17,908

Selected Sample

Total No.of POs 12 21 17 19 69

Value($000) $2,252 $1,002 $262 $79 $3,595

Total Dollar Value of Universe ($000): $17,908Total Dollar Value of Sample ($000): $3,595

Percentage: 20%

22

Page 48: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 49: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

A principle task of the CPSR team is to determine

the extent to which purchasing (subcontracting) is done com-

petitively to the maximum extent possible. Thus the purchase

order sample was subjected to analysis of the following kind:

Price and Cost Analysis Performed on Subcontracts AwardedWithout Adequate Price Competition

1973 1972

No. of Value No. of Valuea. Price Analysis Orders/ ($000) Orders/ ($000)

Applicable 27/$866 42/$2,205

Accomplished 22/$656 42/$2,205(82%)/(76%) (100%)/(100l)

Accomplished 19/$534 41/$2,194effectively (86%)/ (81*) (98%)/(99%)

b. Cost Analysis

Applicable 10/$1,671 5/$l,695

Accomplished 9/$l,526 5/$l,695(90%)/(91%) (100%)/(100%)

Accomplished 8/$l,371 5/$l,695effectively (89%)/(90%) (100%)/ (100%)

c. Public Law 87-653 (Truth in Negotiations)

Applicable 7/$l,508 5/$l,695

Complied with 5/$l,223 5/$l,695(71%)/(81%) (100%)/(100%)

A measure of PLD's pricing policies and techniques,

including methods of obtaining accurate, complete, and

current cost and pricing data, is apparent from the following

table

:

23

Page 50: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 51: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

Total Number of Subcontracts Over $10,000 SampledCCompetitive vs. Non-Competitive)

1973 1972

Number/Dollars ($000) Number/Dollars ($000)

a. Total PurchaseOrders Reviewed 50/$3,516 91/$10,269

(1) Average Numberof RFQs Issued 3.3 3.8

b. Total Awards Made on Basis of Adequate Price Competition(ASPR 3-807.1) .

1973 1972

Orders 13(26%) 44(491)Value($000) $979(28%) $6,369(62%)

(1) Average Depthof Competition - 1.6 2.9

c. Total Awards Made Without Adequate Price Competition

1973 1972

Orders 37(74%) 47(51%)Value($000) $2,527(72%) $3,900(38%)

After examining purchasing directives and files for

nearly two weeks, during which daily conversations were held

with members of the PLD purchasing group, one major task

remained for the CPSR team: determining the role of purchas-

ing in the PLD organization. The CPSR team needed to deter-

mine also whether other departments shared purchasing

authority and influenced purchasing decisions at the expense

of the Government. While the team had by now some ideas on

these questions, written policy directives and organization

charts did not provide a complete answer.

Contractors frequently employ the project manager

concept in performing defense contracts. PLD was no exception,

24

Page 52: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 53: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

The project managers worked across departmental lines,

dividing their time among engineering, production, purchasing,

and even marketing. This gave the project managers a per-

spective of the company which could not be gained from

looking at each department individually. By interviewing

several project managers, Agnes Barnum was able to gain a

better understanding of the extent to which production and

engineering influence purchasing decisions. As it happened,

PLD project managers also chaired make-or-buy committees,

another area of concern to the CPSR team. In this way the

team was better able to interpret the following data derived

from the statistical sample:

Predominant Justification for Subcontracts AwardedWithout Adequate Price Competition

1973 1972

No. of Value No. of ValueOrders/($000) Orders/ ($000)

a. Customer Directed 6/$444 5/$188

b. Engineering Directed 13/$680 14/$513

c. Proprietary Items 6/$789 2/$568

d. Only Supplier Qualified 1/$11 14/$1 , 857

e. Economically Justified 1/$ 29 6/$ 222(tooling, qualificationtest, delivery, logisticscost)

f

.

Other Justification 10/$584 6/$552

g. No Justification

TOTALS 37/$2,537 47/$3,900

25

Page 54: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 55: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

On the last day of the in-plant review, an Exit

Briefing was held with PLD management to present the general

observations of the review team. The discussion included

areas found to be deficient and other observations made by

the review team. No specific recommendations could be

announced at this time, nor could the decision to continue

or withhold approval of PLD's procurement system be dis-

cussed. These decisions had to await CPSR Board review and,

ultimately, final determination by the ACO. However, it was

clear that the review team had not been impressed with the

PLD operation this year.

3. Preliminary Case Requirement

a. With regard to the Statistical Data presented

thus far, what trends are evident in the contractor's

operations? What are the underlying reasons for such trends?

C. CPSR RESULTS AND CASE REQUIREMENTS

1. Findings and Recommendations of the ContractorReview Team

A CPSR Board was convened at DCASR, Los Angeles, two

weeks after the review team departed the PLD plant. During

this period a CPSR report had been completed and copies

submitted to each of the three members of the Board for their

study. The Board was empowered to modify, add, or delete

any recommendations concerning the contractor's procurement

system, and to make a written recommendation to the ACO con-

cerning continued approval status.

26

Page 56: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 57: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

In addition to the Board members, the meeting was

attended by the ACO, DCASO(PLD) (George Brown), and Agnes

Barnum, CPSR team captain. At the request of the Board,

Mrs. Barnum summarized the report, concluding with the

following remarks:

"The review disclosed deterioration in some of

the significant areas of PLD procurement operations. Vendor

delivery delinquencies continue as a serious problem area.

The incidence of competitive procurement has decreased to

261, and the index of quotations has dropped to an average

of 1.6 responsive quotes for all orders examined. " The

contractor's performance under ASPR and contractual require-

ments for implementation of Public Law 87-653 is less than

minimal and warrants significant improvement. Furthermore,

price analyses of procurements under $100,000 are less than

satisfactory. Based on these findings, the CPSR team

recommends that approval of the contractor's procurement

system be withdrawn."

Mrs. Barnum then drew the attention of the Board to

the statistical summary of PLD procurement, including the

following tables (not previously presented)

:

The index of quotations is the average number ofresponsive quotes per solicitation.

27

Page 58: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 59: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

Purchase Orders Lacking Adequate Negotiation

1973 1972

Number 3 1

Value ($000) $379 $ 11

Purchase Orders Lacking Adequate Documentation

Number 12 2

Value ($000) $878 $184

Expediting and Follow-Up Purchase Orders

Number of POs Reviewed 50 91

Number of POs Delinquent 21 44

Number of POs Delinquentin excess of 15 days 16 33

Type of Subcontracts Used for Awards

1973 1972

No. of/ Value * No. of/ Value *

FFP 48/$3,326 88/$10,173

NON-FFP 2/$190 3/$96

*($000)

The Board Chairman thanked Mrs. Barnum for her report.

Then George Brown was asked if he had any comments to offer

on the results of the review. George. was well acquainted with

the members of the Board having worked with them during a

prior assignment at DCASR. Thus he felt no reticence in offer-

ing his opinion and welcomed the opportunity.

28

Page 60: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 61: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

George began by acknowledging the validity of the

report's findings. "I agree with the deficiencies cited in

the report and noted by Mrs, Barnum. But I don't agree that

they justify penalizing the contractor and the Government

by withdrawing approval.

"There are no definitive standards for judging a

contractor's procurement system, beyond a basic compliance

with the law, with ASPR, and the terms of his contracts.

So I think these deficiencies should be weighed in relation

to the business problems PLD faces and our experience in

doing business with him.

"For one thing, there was only one deficiency left

over from last year's review-vendor delinquency. And if you

ask me, a lot of this problem is due to Government change

orders and administrative delay. The point is, though, that

he corrected eleven other deficiencies, which is more than

some contractors are willing to do."

The Board Chaiman interrupted to agree that moti-

vating contractors to make needed improvements in their

procurement methods was a continuing problem.

George continued. "Last year, PLD merged with

another Farraday division. Purchasing lost out in the organ-

izational shuffle. This may account for the apparent lack

of internal review of non-competitive awards at PLD and the

strong influence Engineering seems to have on source selection

But I am sure PLD will reconsider the organizational structure

in light of the CPSR report.

29

Page 62: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 63: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

"In addition, the high percentage of non-competitive

awards is not necessarily indicative of poor procurement

practice. Neither is the low index of responsive quotes.

PLD's ratio of purchases to sales is fairly low. They make

high quality, specialized products. The volume of work they

can offer to any one supplier is not great. Not many vendors

find PLD as attractive a customer as the firms in the area

making commercial electronic equipments. Subcontracting

with PLD is an administrative hassle which many suppliers

prefer to avoid. The result is a reluctance to bid on PLD

proposals .

"

"What you are saying," remarked Mrs. Barnum, "is

that we should adjust the CPSR Program to fit PLD's parti-

cular circumstances."

"That's exactly right," replied George. "The adjust-

ment takes place when the CPSR Board reviews the report and

takes what it considers to be appropriate action.

"There are some areas where PLD needs to improve and

I feel they will respond to our recommendations to do so.

But if the subcontracts environment PLD faces is not condu-

cive to competitive procurement, then withdrawal of his

procurement system approval won't alter that situation. It

will drive up costs, though. Currently, PLD allocates $200

of administrative cost to each purchase order over $25,000

which has to be processed for ACO consent. There will be

other disfunctions too, also counter to the Government's

30

Page 64: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 65: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

interests. We simply don't have the resources at DCASO(PLD)

to revert to reviewing virtually all of the contractor's

purchases on a real-time basis."

George concluded with a recommendation that the Board

continue PLD's procurement system appproval. The Board then

adjourned the meeting to consider its decision.

2 . The Case Requirements

The student is to prepare responses to the following

questions

:

a. What is your evaluation of George Brown's

argument to the CPSR Board?

b. What action should the CPSR Board take and why?

D. TEACHING COMMENTARY

1. Introduction

The case is based on the actual CPSR history of a

division of a major corporation whose contracts are admin-

istered by the DCAS organization. The statistical informa-

tion provided throughout the case is actual data. George

Brown's outspoken role in the CPSR Board proceedings was

invented to introduce controversy. It represents a realistic

point of view, however, since an approved procurement system

benefits both contractor and ACO.

The CPSR in question resulted in withdrawal of

approval of the contractor's procurement system. Beside the

deficiencies noted in the case, the contractor also had some

minor weaknesses in pricing intercompany transactions.

31

Page 66: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 67: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

Following the review, the contractor worked closely with

the DCASO in making needed improvements in his operation.

Corporate headquarters displayed strong interest in the

CPSR problems of this division. Several key procurement

personnel were discharged from the company following this

review. A Follow-Up review was held six months later and

approval status reinstated.

The CPSR program involves a significant intrusion

into a contractor's affairs. For this reason DCAS tries to

emphasize the positive aspects of the program by pointing

out that the purchasing efficiency inherent in an "Approved

procurement system" leads to increased profits. Of course

fixed-price contractors hardly need to be reminded of this.

To a slight extent the CPSR program contains its own

elements of office politics. It is not unusual for CPSR

teams to be regarded as spies from headquarters by the DCASO's

whose contractors are being inspected.

When a contractor's approval status is lost, both

the Government and the contractor suffer. The ACO's workload

can increase significantly in the area of advance notification

and consent. But on the other hand contractors are not well

motivated to implement CPSR recommendations so long as they

retain approval status.

ASPR provides advantages to contractors possessing

approved procurement systems, in the area of source selection,

profit and fee determination, and type of contract. However,

it is doubtful that PCO's are significantly influenced by these

provisions

.

32

Page 68: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 69: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

Surveillance of a CPSR contractor by a resident

PMA, while still provided for in ASPR, has been abandoned

by DCAS. This action was probably taken in response to GAO

criticism.

2. Discussion Questions

a. With regard to PLD, what trends are evident from

the Statistical Summary: What is their signficance to the

CPSR review team?

Total sales have declined due to the reduction

in sales to the Government. There was some growth in commer-

cial sales but not enough to prevent the company from having

to cut costs wherever it can. The number of personnel in the

Purchasing Group has been cut, probably below the level

needed. The review team might expect to find a less than

thorough procurement operation. There is a significant

decrease in PLD's purchases as a percent of sales; 261, as

against 311 in 1972. The possible causes are numerous; the

general economic and Defense turndown, high material prices

which encourage use of inventories with minimal or postponed

replacement, and the tendency to bring work in house during

times of economic difficulty. As a result of this trend the

CPSR team should give careful attention to contractor's

Value Engineering and Make or Buy Programs.

b. What is your evaluation of George Brown's argu-

ment to the CPSR Board?

George is correct in noting that there are no

rigid standards to apply in considering approval of a con-

tractor's procurement system. Most procurement functions

33

Page 70: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 71: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

cannot be reduced to stereotyped standards, and hence there

must be a certain degree of flexibility in the guidelines

for the CPSR Program. The ultimate decision stemming from

these reviews must be based on judgment.

While the contractor may have a good record in

correcting deficiencies, this fact is largely irrelevant to

judging his procurement system. Similarly, although organi-

zational problems may explain PLD's procurement deficiencies,

they do not excuse them.

George alleges that PLD is unable to attract

sufficient sources to do much competitive procurement. If

this is true, the contractor is obliged to recognize this

situation and then demonstrate effective cost or price

analysis of non-competitive, procurements . Yet his perform-

ance in this latter category is less than satisfactory.

Finally, the added administrative costs, the delays, and

other effects of withdrawing approval, although regrettable,

should in no way influence the Board's decision.

c. What action should the CPSR Board take and why?

Following discussion of the previous questions,

there is clearly only one proper action for the Board to

take -- recommend withdrawing approval of PLD's procurement

system. Comparisons between PLD's current procurement

statistics and those of the past year indicate significant

deterioration of the contractor's system. Article 23-105(a)

of ASPR applies. The ACO in turn would be expected to

implement the Board's recommendation.

34

Page 72: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 73: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

III. SUBCONTRACT REVIEW AND CONSENT BY THEGOVERNMENT: A CASE STUDY

A. CASE BRIEF AND OBJECTIVES

This case has been designed to introduce the basic con-

cepts of subcontract review and consent by the government.

Additionally it was endeavored to provide the student with a

representative consent package for him to review both for

form and content. Make or buy considerations were also

introduced.

B. CASE PRESENTATION

In early March 1974, Lieutenant Ralph Sliden reported

for duty at DCASD Cleveland. The DCASD supported all the

Department of Defense and NASA agencies in their administra-

tion of contracts. This was Sliden' s first procurement

billet after his procurement school and he was anxious to

get involved in the procurement process. After a brief

office orientation he was granted a warrant as a contracting

officer and assigned as Administrative Contracting Officer,

ACO, for several contracts.

To carry out his duties properly Lieutenant Sliden under-

took a detailed review of each of his assigned contracts,

the record of negotiations and the applicable provisions of

the Armed Services Procurement Regulations (ASPR) . Most of

the common responsibilities are spelled out in ASPR paragraph

1-406. He also sought to become more familiar with each of

35

Page 74: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 75: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

the companies with which he would be dealing. The informa-

tion required for the review was readily available from

knowledgeable personnel in the office and from such reports

and publications as pre-award surveys, Defense Contract

Audit Agency findings, Contractor Procurement System Review

(CPSR) Reports, Moody's Handbooks, Standard and Poors, con-

tract status files and others.

One of the more important government contracts assigned

to Sliden was cost plus fixed fee contract valued at

$3,977,257 with Interallied Aerospace Corporation (IAC) for

the development of a radio telemetry measuring device. IAC,

a multi-divisional company, was awarded the contract in

September 1973 and was expected to complete the development

in March 1975. The company's antenna division based in El

Gordo was scheduled to do the majority of the work with some

assistance from other divisions. The antenna division with

its 5000 employees was one of the smaller divisions within

IAC whose total employment was approximately 50,000. IAC

had numerous contracts both fixed price and cost type with

several DOD agencies. All information available to Sliden

indicated that satisfactory progress was being made in the

performance of the contract.

The radio telemetry measuring device, viewed as a signi-

ficant advancement in electronic warfare, was required as

soon as possible for deployed forces. Prior to the contract

award to IAC the basic scientific concepts of the device had

only been demonstrated under laboratory conditions. Its

36

Page 76: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 77: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

feasibility and level of effort for development was still

largely unknown. For these reasons the government desired

to provide in the contract for the maximum engagement possible

between the procuring hardware command and IAC. Additionally,

engagement was formally encouraged to permit the government

to update the contractor's efforts as information was

received from the field further defining the requirements

for the device.

In reviewing the radio telemetry contract Lieutenant

Sliden did not notice any extraordinary items. It contained

the standard type of make or buy list and clause and the

subcontractor consent clause along with many other required

clauses. Briefly stated, the make or buy provision of a

contract is an attempt to determine prior to contract award,

what plans the contractor has to either buy subassemblies/

parts through the use of subcontractors or make the items

in house, what the cost, schedule, performance, management

and other considerations involved are, and what is in the

best interest of the government as regards make or buy. The

subcontract consent or approval clause in a contract con-

tains a procedure that permits the government, in certain

prime contract types, to review proposed subcontracts for

their suitability. Suitability ranges from proper sub-

contract type to adherence to socio-economic guidelines. For

more detailed information regarding make or buy and consent

the appropriate excerpts from ASPR are contained in Appendices

1 and 2

.

37

Page 78: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 79: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

The procurement file did show that lAC's procurement system

had recently been reviewed and approved by the CPSR board.

From the notes and memoranda provided by the contract negoti-

ator it was evident that the contract's make or buy list was

reviewed at length to ensure successful development of the

device at the lowest practicable cost. It had been IAC's

position that the device could be developed inhouse with only

minimum subcontractor support. It was the government negoti-

ator's position that several subassemblies embodied in the

device have been in development and/or production for years

by other companies while IAC would have to develop that

capability. IAC had responded that some design and startup

costs would be incurred but the overall procurement cost

would be less if developed inhouse as sizeable economies in

subcontract procurement and interface integration efforts

would be realized. IAC's position was finally accepted by

the negotiator and the make or buy plan was approved. The

buy portion of the make or buy list totaled less than $100,000

with no single procurement more than $25,000.

On Tuesday, 12 March 1974, Lieutenant Sliden received a

subcontract consent package, under the radio telemetry prime

contract, from IAC. The proposed subcontract for research

and development of an antenna subassembly was a fixed price

subcontract for $104,688 with Raysonream Raytronics, (RR) a

regular supplier to IAC (see exhibits 1-5). Raysonream was

known in the industry as a fine basic research, development,

38

Page 80: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 81: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

and production firm. They had submitted a proposal for the

original radio telemetry prime contract but had been dropped

from competition when final negotiations with IAC commenced.

Sliden's initial reaction was one of surprise because

he hadn't expected a subcontract of this size. He decided

that a thorough review was in order. To properly do this he

decided he should first determine the answers to two ques-

tions: what responsibilities does a prime contractor have in

the placement of a subcontract and, what responsibilities

and options does the ACO have in consenting to a subcontract?

Based on the answers to these questions he would then review

this particular subcontract consent package.

39

Page 82: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 83: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

PREAWARD PROFILE FOR SUBCONTRACT Z53Q72

8 MAR. 74

12 MAR. 74

NUMBER OF RFPs ISSUED: 3 DATE ISSUED 1 FEB. 74

DATE DUE 1 MAR. 74

NUMBER OF PROPOSALS RECEIVED: 1

LONE BIDDER

Raysonream RaytronicsVin Rose, California

NEGOTIATIONS START DATE:

CONTRACT SIGNED:

CONTRACT TYPE:

Firm fixed price

CONTRACT PRICE:

$104,688

CONTRACT DELIVERY DATE:

30 APR. 74

CONTRACT REQUIREMENT:

1. Antenna subassembly capable of meeting specificationsof Interallied Aerospace Corp. drawings #5859QP743-7and 5859QP743-8 and work statement 5859PP001 dated28 January 1974.

EXHIBIT CI)

40

Page 84: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 85: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

STATEMENT OF WORK 58 59PP001

Subcontract #Z53Q72

1.0 The contractor shall provide one (1) antenna sub-

assembly (AS) for use in the radio telemetry measuring

device, APD47-552.

2.0 The AS shall meet the following requirements:

2.1 The configuration and performance shall conform

to the envelope specified in plans #5859QP743-7-8,

2.2 The antenna shall be weighted and balanced to

provide proper center of gravity. (Weights shall

be secured to casting sufficiently to withstand

drops and other tests as specified in AS-2227).

2.3 Mating surfaces shall be compatible to the

antenna subassembly mount produced by IA.

2.4 Material shall be of sufficient strength to

withstand the physical environment specified

in paragraph 3.2.5 of AS-2227.

2.5 The AS shall be supported by RR for all field

failures with RR maintaining item during system

tests

.

6 March 1974

EXHIBIT (2)

41

Page 86: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 87: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

MEMORANDUM OF NEGOTIATIONS

Subcontract #Z53Q72

INTRODUCTION

Negotiations were conducted on Friday 8 March 1974 in

Interallied Aerospace building 52, Conference Room 2, to

arrive at a firm fixed price for subcontract #Z53Q72. The

subcontractor firm is Raysonream Raytronics (RR) of Vin Rose,

California. The subcontract effort is to develop an antenna

subassembly capable of meeting the requirements of Inter-

allied Aerospace Corporation drawings #5859QP743-7 , -8 and

work statement 5859PP001 dated 6 March 1974.

Those in attendance at the negotiations were:

Raysonream Raytronics

P. P. McMacton, Vice President, Finance

D. A. Dreepy, Vice President, Engineering

Interallied Aerospace Corporation

R. F. Smith, General Procurement - Chairman

A. B. Seretti, Program Office

T. A. Bidbadwell, Subcontract Cost Analysis

ESTABLISHING THE REQUIREMENT

The meeting began at approximately 8:30 A.M. After the

principals had been introduced the RR representatives were

furnished a copy of the work statement dated 6 March 74 and

a copy of the firm fixed price contract. The two documents

had been prepared in confirmation of earlier telephone con-

versations between the parties. The work statement, the

EXHIBIT (3) - 1

42

Page 88: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 89: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

subcontract document and the supporting drawings were

reviewed and all participants agreed they understood them.

It was further agreed that the RR proposal was essenti-

ally responsible to the requirements and that a minimum of

effort would be required to negotiate a firm fixed price

contract.

TERMS AND CONDITIONS

It was pointed out that the terms and conditions were

as stated in the proposed subcontract. Time was critical

but as RR had experience in this area the group concluded

that the procurement centered on the development of known

technology items rearranged into a somewhat different con-

figuration. Development efforts would be directed toward

elimination of possible interface problems, occurring as a

result of the component rearrangement.

The RR representatives were asked if they had any

questions concerning the IAC drawings #5858QP743- 7 , 8 or the

statement of work #5859PP001 dated 6 March 74 and they

replied that the requirements were understood.

DP FORM 633 PROPOSAL

The data supporting the DD Form 633 dated 9 Feb. 74 was

next reviewed.

DIRECT MATERIAL - SUBCONTRACTED

None

EXHIBIT (3) - 2

43

Page 90: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 91: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

DIRECT MATERIAL - RAW MATERIAL

The proposed value was $10,659.32. Mr. Dreepy was

questioned concering the applicability of item 11, a tool

for $190.00. The RR representative allowed that the tool's

useful life would extend far beyond the life of the sub-

contract and the $190.00 should be deleted.

The total for this element was then agreed as follows:

Proposed $10,659 IAC $10,469 Agreed $10,469

MATERIAL OVERHEAD

The proposed rate is 11.24%.

The proposed value is 11.241 x 10,659.

This element consists of an overhead factor applied

against the direct material.

The RR representatives when queried how 11.241 was arrived

at responded that it was calculated using last year's

historical cost data adjusted for the current rate of infla-

tion as measured by the wholesale price index.

Since the direct material has been reduced IAC reduced

the material overhead proposal accordingly.

Proposed $1198.07 IAC $1176.72 Agreed $1176.72

DIRECT MANUFACTURING LABOR

The proposed value was $ 51,958.

This element is made up of 10 subelements. IAC's

evaluation agrees with 8 of the 10. The other two, labor

for quality control inspections and labor for shop support>

were discussed.

EXHIBIT (3) - 3

44

Page 92: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 93: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

Quality Control Requirement

The proposed number of hours for this inspection is 2000.

Based on the expected direct manufacturing hours of 571 the

proposal of 3-1/2 quality control inspection hours per hour

of manufacturing appeared excessive. Mr. Dreepy replied that

due to the close requirements of the electrical devices

involved such close and continuing inspection was essential.

IAC's Mr. Bidbadwell stated that IAC ' s past experience

indicated that three hours per manufacturing hour was the

most IAC had ever experienced. After some further discussion

it was agreed that 3-1/4 quality control inspection hours

per manufacturing hour was acceptable.

Proposed IAC Agreed

Hours 2000 1890 1890Cost $12,700 $12,001 $12,001

Clean Room Requirement

The proposal provides for a total of 1500 man hours of

labor in the clean room in addition to the hours noted in

other elements. IA's Mr. Seretti questioned both the need

for the clean room and the costs involved.

Mr. Dreepy stated that the development technique to be

used by RR required the use of the clean room and that its

cost was supported by historical cost data.

Proposed IAC Agreed

Hours 1500 1500 1500Cost $9525 $9525 $9525

EXHIBIT (3) - 4

45

Page 94: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 95: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

MANUFACTURING OVERHEAD

The proposed rate for 1974 "actual" was $5.50 per hour.

The proposed rate for 1974 "projected" was $6.10 per hour.

The proposed rate of $5.50 was used on those functions

that have already occurred and the proposed rate of $6.10 was

used in the proposal for those functions expected to occur

late in the year. The DCAA audit report recommends a rate

of $5.65. Mr. Smith explained that IA was obligated to use

the DCAA recommendation rate or go into extensive element-by-

element review of the make-up of the rate. RR, Mr. McMacton,

agreed to use the rate of $5.65 per hour.

Proposed IAC Agreed

571x6.10 $3226 $3226$3483

GENERAL AND ADMINISTRATIVE

Mr. McMacton reported that the General and Administrative

rate on direct manufacturing labor hours applicable to the

subcontract would be $17.04 per hour. Mr. Seretti questioned

RR's rate as IAC's rate was $12.04 in their comparable divi-

sions. Mr. McMacton replied that contracts/subcontracts for

defense related material caused a buildup of personnel

required to comply with the necessary reporting and other

paperwork requirements. The rate was agreed upon at $17.04.

Proposed $9729 IAC $9729 Agreed $9729

PROFIT

The RR proposal indicates 12% on all costs in the proposal.

It was accepted.

EXHIBIT (3) - 5

46

Page 96: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 97: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

Proposed IAC Agreed

Profit Rate 12% 12% 12%Profit Value $11,758 $11,758 $11,214

CHANGES

Mr. Smith proposed that RR accept and incorporate all

changes proposed by Mr. Smith or Mr. Seretti. All changes

submitted to RR would be priced and agreed upon by both

companies prior to their incorporation in the development.

This was agreed to by RR.

COMPLETION DATE

The completion date would remain as promulgated in the

original request for proposals. Any changes in the date

would be handled under the changes clause. Any completion

date changes proposed by RR would also be handled as a

change and negotiated as such.

TOTAL FIRM FIXED PRICE

Attention was next turned to summarizing the various

estimated costs and agreed to prices. They were listed and

the final firm fixed price for this subcontract agreed to

as follows:

EXHIBIT (3) - 6

47

Page 98: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 99: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

Cost Element Proposed IAC Agreed

Direct Material, Raw Material $10,659 $ 10,469 $ 10,469

Material Overhead 1,198 1,176 1,176

Direct Manufacturing Labor 51,958 51,259 51,259

Manufacturing Overhead 3,483 3,262 3,262

Other Costs 20,955 17,552 17,552

Subtotal 88,251 83,718 83,718

General § Administrative Expense 9,729 9,729 9,729

Subtotal 97,980 93,447 93,447

Profit 11,758 11,241 11,241

Total Firm Fixed Price $109,738 $104,688 $104,688

CONCLUSION

After completion of negotiations, each participant

reassembled their papers in preparation for adjournment. Mr.

Smith advised that he would have to document the details of

negotiations and other aspects of the subcontract and then

obtain Interallied management approval of the actions taken

to date. After that the Interallied customer will be noti-

fied of the definitive subcontract and the formal definitive

document will be issued for signature. It should be mailed

in a few days. Mr. McMacton said that would be satisfactory.

The negotiations were concluded at 6:35 P.M.

F. Smith forINTERALLIED AEROSPACE CORP,

EXHIBIT (3) - 7

48

Page 100: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 101: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

CERTIFICATE OF CURRENT COST OR PRICING DATA

This is to certify that, to the best of my knowledge

and belief, cost or pricing data as defined in ASPR 3-807.3

submitted, either actually or by specific identification

in writing (see ASPR 3-807.3) to the Interallied Aerospace

Corporation in support of DD Form 633 dated 9 Feb. 74 for

Subcontract #Z53Q72 are accurate, complete and current as

of 8 Mar. 74.

RAYSONREAM RAYTRONICS

^KvP. P. McMactonVice-President, Finance

9 March 1974

EXHIBIT (4)

49

Page 102: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 103: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

DEPARTMENT OP DEFENSE

CONTRACT PRICING PROPOSALFor* Appr°**d

Budgit Si/raau No. 21-PtQQ

ThiB foim Is lor use when submission o( cost or pricing d«t« (see ASPR 3-807,3) is requiredRACE NO.

1

NO. OF PAGES

1

r«AMC of offerorRaysonream Raytronics

Supplies and or services to be furnisheo

Development and Production of RadioTelemetry Antenna SubassemblyMOMt OFFICE ADORCSS C/oclutf. ZIP Cod*)

153 North AudleyVin Rose, California 93939

quantity

1

TOTAL AMOUNT OF PROPOSAL

OIVIBIOMISI ANO LOCATION'S; WHERE WORK IS TO BE PIMfORMED GOVERNMENT SOLICITATION NO.

COST ELEMENTSPROPOSED CONTRACT ESTIMATE

TOTAL COST' UNI T COST J REFERENCE 1

<

H

<3l-

OLI

so

• PURCHAltO PARTS*

6. SUBCON IS AC TED ITEMS*

J4

C xu Wz »-

i- 4s

10,659

(2) STANOARDCOMMERCIAL ITEMS 9

(3} INTERDIVISIONAL TRANS-FERS C«f ether than cott) 9

2. MATERIAL OVERHEAD' 1,198

J. INTERDIVISIONALTRANSFERS AT COST*'

A. DIRECT ENGINEERING LABOR'*

5. ENGINEERING OVERHEAD'

6. DIRECT MANUFACTURING L*BOR" 51,958

7. MANUFACTURING OVERHEAD' 3,483

8. OTHER COSTS'* 20,953

9. SUBTOTALS88,251

10. GENERAL ANDADMINISTRATIVE EXPENSES' 9,729

11. ROYALTIES"

12. FEDERAL EXCISE TAX**

'3. SUBTOTALS 97,980

14. PROFIT OR FEE

IS. TOTAL PRICE Mmauntj 109,7381. HAV£ THE DEPARTMENT OF OEFEN5

MISSION PERFORMED any REVIEW OF;. NATIONAL AERONAUTICS ANO SPAYOUR ACCOUNTS OR RECORDS IN CC

CE ADMINISTRATION, OR THE ATOMIC ENERGY COM-NNECTION WITH ANY OTHES GOVERNMENT PRIME

a *« 3D no if Yt S, IDENTIFY BFLOW,NAME ANO ADDRESS OF REVIEWING OFFICE (Include ZIP Code) TELEPHONE NUMBER

II. MILL rOU REOUIIEThE USE OF ANT GOVERNMENT PROPERTY IN THE PERFORMANCE OF THIS PROPOSED CONTRACT'

IT

-! v E » 3C no IF YFS. IDENTIFY ON A SEPARATE PACE.

HI. DO fOu SEQUIRE government CO-i tract Financing TO PERFORM this PROPOSED CONTRAC"

""J YES [_? NO IF YFS. IDENTIFY: f. . ADVANCE Payments ) PROGRESS Pi'MEUT) OP 'i GUARANTEED LOANS

iv.hAvE YOu BEEN AWARDED ant CON tracts OR SuBCOn TRACTS FOR Similar items within Th£ PAST THREE YEARS'

QB yes CD NO IF YES, SHOW CUSTOMER(S) AND CONTRACT NUMBERS BELOW OR ON A SEPARATE PACE.

Y. DOCS THIS COST SUMMARY CONFORM *ITM THE COST PRINCIPLES SET FOP TH IN ASPR. SECT'ON * V <•• 3-A07 .2(c )(2})>

PC1 VEi 11 NO IF NO '

EXPLAIN ON A SEPARATE PACE

This proposal is submitted for use in connection with and in respon

Z53072

seto proposed subcontract

• and reflects our best estimates as of this date.

i

in accordance with the instructions to offerors and the footnotes wh tch follow:

'DESCRIBE PFP. ETC.

T»#C3 NAM* AND TlTt.1

P. P. McMactonVice-President , Finance 'W avis.

NAME OF F|*M

Raysonream Raytronics

DATE OF SUBMISSION I

9 Feb 1974 I

DD. '.?."., 633* - x i-i ARE OBIOlC

EXHIBIT (5)

50

Page 104: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 105: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

3:166 16 April 1973

PROCUREMENT BY NEGOTIATION

PART 9—Make-or-Buy Programs Policies and Procedures

3-901 Scope of Part

(a) This Part sets forth policies and procedures for obtaining, evaluating, and

agreeing to contractors' proposed "make-or-buy" programs. These techniques are

required only where the work is complex, the dollar value is substantial, and there

is not adequate price competition. The evaluation of and agreement upon a con-

tractor's proposed make-or-buy program shall be accomplished during negotia-

tions to the extent practicable.

(b) Although there is a relationship among the evaluation and agreement

upon a contractor's make-or-buy program, the review and approval of procure-

ment systems (see Guide for Conducting Contractor Procurement System Review

(CPSR) (ASPS No. 1 )), and consent to subcontracts (see Section XXIII), each is

a separate and distinct action and the factors to be considered in each vary.

(c) In order to form a basis for contract negotiations, the make-or-buy pro-

gram (3-902) submitted with the contractor's proposal should (i) sufficiently

identify the important segments of the total effort, and (ii) establish the

framework for determining the contractor's in-house effort, the subcontract ef-

fort, and the plant workload with attendant overhead costs.

3-902 Make-or-Buy Programs.

3-902.1 General. The Government buys management from the prime con-

tractor along with goods and services, and places responsibility on him to manageprograms to the best of his ability, including placing and administering subcon-

tracts as necessary to assure performance at the lowest overall cost to the

Government. Although the Government does not expect to participate in every

management decision, it may reserve the right to review the contractor's manage-

ment efforts, including the proposed make-or-buy program. In reviewing the con-

tent of the proposed make-or-buy program effort should be made to have the

prime contractor establish any new facility in or near sections of concentrated

unemployment or underemployment and in areas of persistent or substantial labor

surplus.

3-902.2 Definition and Criteria.

(a) A make-or-buy program is that part of a contractor's written plan which

identifies the major subsystems, assemblies, subassemblies, and components to be

manufactured, developed, or assembled in his own facilities, and those which will

be obtained elsewhere by subcontract. A "make" item is any item produced, or

work performed, by the contractor or his affiliates, subsidiaries, or divisions.

(b) Regardless of the type of contract contemplated, information with

respect to prospective contractors' make-or-buy programs shall be required in all

negotiated procurements except:

(i) when a proposed contract has a total estimated value of less than

$1,000,000, unless the contracting officer specifically determines

that such information is appropriate;

(ii) in research and development contracts, unless the contract is for

prototypes or hardware and it can reasonably be anticipated that sig-

nificant follow-on quantities of the product will be procured;

Appendix 1

51

Page 106: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 107: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

16 April 1973 3:167

PROCUREMENT BY NEGOTIATION

(iii) when the contracting officer determines that the price is based on

adequate price competition, or established catalog or market prices

of commercial items sold in substantial quantities to the general

public, or on prices set by law or regulation; or

(iv) when the contracting officer determines that the work is not com-

plex,

(c) Information with respect to make-or-buy programs and the program

required to be included in any contract (see 3-902.4) shall be confined to items

which, because of their complexity, quantity, or cost or because their production

requires additional facilities, normally would require company management

review of the make-or-buy decision. As a general guideline, the make-or-buy pro-

gram should not include items or work efforts costing less than 1% of the total

estimated contract price or $500,000, whichever is less. Raw materials and off-

the-shelf items shall not be included.

3-902.3 Procedure.

(a) When submission of information with respect to a prospective contrac-

tor's proposed make-or-buy program is required, the solicitation shall so state and

shall clearly set forth any special factors to be used in evaluating the program.

After considering such factors as capability, capacity, availability of small busi-

ness and labor surplus area concerns as subcontract sources, the establishment of

new facilities in or near sections of concentrated unemployment or underemploy-

ment, contract schedules, integration control, proprietary processes, and techni-

cal superiority or exclusiveness, the prospective contractor shall identify in his

proposed make-or-buy program that work which he considers he or his affiliates,

subsidiaries, or divisions (i) must perform as "must make," (ii) must subcontract

as "must buy," and (iii) can either perform or acquire by subcontract as "can

make or buy." The prospective contractor shall state the reasons for his recom-

mendations of "must make" or "must buy" in sufficient detail for the contracting

officer to determine that sound business and technical judgment has been applied

to each major element of the program. When the make-or-buy program is to be

incorporated into the contract and the design status of the article being procured

does not permit accurate precontract identification of major items that should be

included in the make-or-buy program, the prospective contractor shall be notified

that such items must be added to the program, when identifiable, under the

"Changes to Make-or-Buy Program" clause (3-902.4(b)). The prospective con-

tractor shall be required to include in the information furnished with respect to

his proposed make-or-buy program:

(i) a description by which each major item can be identified;

(ii) a recommendation to make or to buy each such item or defer the

decision;

(iii) a recommendation as to make-or-buy for any "can make or buy"

item;

(iv) the proposed subcontractors, if known, including location and size

classification;

(v) designation of the plants or divisions in which the contractor

proposes to make the item, whether the facility is in or near section

of concentrated unemployment or underemployment; and

52

Page 108: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 109: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

3:168 16 April 1973

PROCUREMENT BY NEGOTIATION

(vi) sufficient information to permit the contracting officer to evaluate

the proposed program in accordance with (b) below.

Proposed make-or-buy programs shall be evaluated and negotiated as soon as

practical after receipt of the contractors' proposals and in any event prior to

award.

(b) In reviewing and evaluating a proposed make-or-buy program, the con-

tracting officer shall assure that all appropriate items are included and shall delete

items which should not be included. In conducting his review, the contracting of-

ficer shall obtain the advice of appropriate personnel including small business and

labor surplus area specialists, whose knowledge would contribute to the adequacy

of the review. During such review primary consideration shall be given to the ef-

fect of the contractor's proposed make-or-buy program on price, quality,

delivery, and performance. The contractor has the basic responsibility for make-

or-buy decisions. The contractor's recommendations shall therefore be accepted

unless they adversely affect the Government's interests or are inconsistent with

Government policy. The evaluation of "must make" and "must buy" items should

normally be confined to that necessary to assure that the items are properly

categorized. The effect of the following factors on the interests of the Govern-

ment shall also be considered:

(i) whether the contractor has justified the performance of work in

plant which differs significantly from his operations;

(ii) the consequence of the contractor's projected plant work loading

with respect to overhead costs;

(iii) the contractor's consideration of the competence, ability, ex-

perience, and capacity available in other firms, especially small busi-

ness and labor surplus area concerns (this is particularly significant if

the contractor proposes to request additional Government facilities

in order to perform in-plant work);

(iv) the contractor's make-or-buy history as to the type of item con-

cerned;

(v) whether small business and labor surplus area concerns will be able

to compete for subcontracts; and

(vi) other elements, such as the nature of the items, experience with

similar items, future requirements, engineering, tooling, starting load

costs, market conditions, and the availability of personnel and

materials.

(c) Proposed "make" items normally shall not be agreed to when the

products or services under consideration:

(i) are not regularly manufactured or provided by the contractor, and

are available— quality, quantity, delivery, and other essential factors

considered—from any other firm at prices no higher than if the con-

tractor should make or provide the products or services; or

(ii) are regularly manufactured or provided by the contractor, but are

available—quality, quantity, delivery, and other essential factors con-

sidered—from any other firm at lower prices

Such items may be agreed to, however, if the contracting officer determines that

the overall cost of the contract or of the program to the Government would be in-

creased if the item were bought.

53

Page 110: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 111: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

16 April 1973 3:169

PROCUREMENT BY NEGOTIATION

(d) Before agreeing to a "make-or-buy" program to be incorporated into the

contract (or, when the program is included in a contract, consenting to a change

therein), the contracting officer shall invite the advice and counsel of the activi-

ty's small business and labor surplus area specialist by permitting him to review all

pertinent facts and make recommendations thereon. The proposed program shall

also be made available to the SBA representative for his review and recommenda-

tions. Reviews by the small business and labor surplus area specialist and the SBArepresentative should be scheduled to support the negotiations to be conducted

by the contracting officer.

3-902.4 Incorporation of the Make-or-Buy Program in Contracts.

..(a) Where information with respect to a make-or-buy program has been

required to be submitted in accordance with the foregoing, the make-or-buy pro-

gram, as approved by the contracting officer, shall be included only in cost-reim-

bursement contracts except:

(i) cost-sharing contracts where the contractor's share is 25% or more;

(ii) cost-plus-incentive-fee contracts having a cost incentive which pro-

vides for a swing from target fee of at least 03% and a contractor's

overall share of cost of at least 10% (authority may be requested

(see 1-109) to exclude the make-or-buy program from other cost-

plus-incentive-fee contracts having different incentive and cost-shar-

ing patterns, whenever the contracting officer finds that such other

contracts provide sufficient incentive for control of costs); and

(iii) cost-plus-incentive-fee contracts to which 3-902.5 is applicable.

(b) The following clause shall be incorporated in all contracts in which a

make-or-buy program has been included.

CHANGES TO MAKE-OR-BUY PROGRAM (APR. 1967)

The Contractor shall perform this contract in accordance with the "make-or-buy" program in-

corporated in this contract except as hereinafter provided. If the Contractor proposes to change

the "make-or-buy" program, he shall notify the Contracting Officer thereof in writing at a time

reasonably in advance of the proposed change and shall therewith submit justification in sufficient

detail to permit evaluation of the proposed change. Changes in the place of performance of work

on any "make" items in the "make-or-buy" program are subject to this requirement. With respect

to items deferred at the time of negotiation of this contract for later addition to the "make-or-

buy" program, the Contractor shall notify the Contracting Officer of each proposed addition at

the earliest possible time, together with justification in sufficient detail to permit evaluation. This

contract shall be deemed modified in accordance with such proposed change or addition upon

receipt by the Contractor of the Contracting Officer's written approval thereof.

3-902.5 Price Adjustments.

(a) The following subparagraphs apply only to fixed-price incentive and cost-

plus-incentive-fee contracts.

(b) There may be cases where it is proper to agree that an item of significant

value will be "bought" even though it would usually be more economical to have

it "made," or vice versa. For instance, the contractor may have a unique capabili-

ty for low-cost manufacture of a substantial component but his capacity may be

full during the period necessary for contract performance, so the component must

be subcontracted. In such cases it will be necessary that the "make-or-buy" pro-

54

Page 112: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 113: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

3:170 16 April 1973

PROCUREMENT BY NEGOTIATION

gram as approved by the contracting officer specifically call for what would

usually be the more costly treatment of the item. In that event the consequent

higher costs may be explicitly recognized in establishing the best obtainable con-

tract or target price. Unforeseen changes in the circumstances may arise during

contract performance, however, which induce the contractor to propose changing

the item from "buy" to "make" (or vice versa). If such a change is made, the ele-

ment of the contract price which was intended to compensate the contractor for

the higher costs flowing from the initial make-or-buy decision would the Govern-

ment.

(c) When, during the review of the prospective contractor's "make-or-buy"

program (see 3-902.3), a situation of the kind described in (b). above- is found to

exist, the clause set forth below shall be included in the contract, and any "make-

or-buy" items of the kind described in (b) above shall be specifically designated

in the Schedule (or elsewhere in the contract) as being either a "make" item or a

"buy" item, and as being subject to this clause. The make-or-buy program itself

and the clause in 3-902.4(b) shall not be included in the contract.

PRICE ADJUSTMENT FOR MAKE-OR-BUY CHANGES (APR. 1967)

This clause applies only to items that are designated elsewhere in this contract as being "make"

items or "buy" items subject to this clause. If the Contractor desires to "make" any designated "-

buy" item or to "buy" any designated "make" item, he shall give written notice to the Contract-

ing Officer reasonably in advance of the proposed change and shall include significant and

reasonably available cost and pricing data in sufficient detail to permit evaluation of the proposed

change. Promptly thereafter, if the Contractor proceeds with the change, the Contractor and the

Contracting Officer shall negotiate an equitable reduction in the contract price* to reflect any

decrease in costs which should reasonably result from the change, and the contract shall be

modified in writing accordingly. Failure to agree on an equitable reduction shall be a dispute con-

cerning a question of fact within the meaning of the "Disputes" clause of this contract.

'Substitute "target cost and target fee" for "contract price"

cost-plus-incentive-fee contracts.

55

Page 114: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 115: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

16 April 1973 23:7

SUBCONTRACTING POLICIES AND PROCEDURES

Part 2—Requirement for Consent to Subcontracts

23-200 Scope of Part. This Part sets forth the requirements for consent to

subcontracts.

23-201 Subcontract Clauses.

23-201.1 Clause Entitled"Subcontracts" for Fixed-Price Contracts.

(a) The clause set forth in 7-104.23 shall be inserted in all fixed-price type

contracts.

(b) The clause may be modified to:

(i) lower the $100,000 threshold set forth in (ii) and (Hi) of paragraph

(b) of the clause when it is determined that closer surveillance of

subcontracting is desirable because of such factors as the nature of

the industry involved, the criticality of work which will probably be

subcontracted, the absence of competition in placing the prime con-

tract, uncertainties as to the adequacy of the contractor's procure-

ment system, or the novelty of the supplies or services being

procured;

(ii) delete the requirement for advance notification of, or consent to, any

subcontracts which were evaluated during negotiations;

(Hi) require extraordinary Government surveillance in exceptional cases

of subcontracts or classes of subcontracts selected during negotia-

tion. In this event, insert as paragraph (g) of the 7-104.23 clause, the

provision set forth under 7-104. 23(b).

23-201.2 Clause Entitled "Subcontracts" for Cost-Reimbursement and Letter

Contracts.

(a) The appropriate clause entitled "Subcontracts" from either 7-203.8 or

7—402.8 shall be included in all cost-reimbursement and letter contracts.

(b) (1) Under cost-reimbursement and letter contracts, other than facilities

contracts, consent is required for:

(i) subcontracts for fabrication, purchase, rental, installation, or other

acquisition of special test equipment having a value in excess of

$ 1 ,000 or of any items of industrial facilities; and

(ii) subcontracts for research and development (where the clause in

7-402.8 is used).

(2) Consent is also required for the following additional subcontracts

under cost-reimbursement and letter contracts, unless the contractor's procure-

ment system has been approved:

(i) cost-reimbursement, time and materials or labor-hour subcontracts;

and

(ii) fixed-price subcontracts exceeding either $25,000 or 5% of the total

estimated prime contract price.

(3) See 7-702.33 or 7-703.25 for requirements for approval of subcon-

tracts under facilities contracts.

(c) Purchases by a contractor from General Services Administration supply

sources, under a written authorization by the contracting officer (see 5-906),

shall be treated as having been made with the consent of the contracting officer

as required by the clause set forth in 7-204.28 or 7-403.23.

Appendix 2

56

Page 116: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 117: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

23:8 16 April 1973

SUBCONTRACTING POLICIES AND PROCEDURES

(d) In exceptional circumstances, certain subcontracts or classes of subcon-

tracts may be selected during negotiation for extraordinary Government surveil-

lance. In such circumstances, insert as subparagraph (j) of the 7-203.8 clause, the

provision set forth under 7-203. 8(b) or as subparagraph (j) of the 7-402.8

clause, the provision set forth under 7—402.8(b).

23-201.3 Subcontracts Clause for Time and Materials and Labor-Hour Con-

tracts. See 7-901.10 for requirements for approval of subcontracts under time

and materials and labor-hour contracts.

23-201.4 Clause Entitled "Equal Opportunity Pre-anard Clearance of Subcon-

tracts." The clause set forth in 7-104.22 and repeated below shall be inserted in

"all contracts containing -any of the ''Subcontracts"- clauses prescribed by this

paragraph 23-201.

EQUAL OPPORTUNITY PRE-AWARD CLEARANCE OF SUBCONTRACTS (1971 OCT)

Notwithstanding the clause of this contract entitled "Subcontracts," the Contractor shaJl not

enter into a first-tier subcontract for an estimated or actual amount of S 1 ,000.000 or more

without obtaining in writing from the Contracting Officer a clearance that the proposed subcon-

tractor is in compliance with equal opportunity requirements and therefore is eligible for award.

23-202 Consent to Subcontracts.

(a) In reviewing for the purpose of granting consent, the contracting officer

shall consider:

(i) the technical justification for selection of the particular supplies,

equipment, or services;

(ii) whether the decision to enter into the proposed subcontract is con-

sistent with the contractor's approved "make-or-buy" program, if

any (see 3-902);

(iii) whether the proposed subcontract will require the use of Govern-

ment-furnished facilities and, if so, whether proper consideration has

been obtained;

(iv) the responsibility of the proposed subcontractor (see 1-906);

(v) the basis for selecting the proposed contractor, including the price

competition obtained;

(vi) any cost or price analysis or price comparisons accomplished, with

particular attention to whether cost or pricing data are accurate,

complete, and current, and to whether any required certification has

been obtained (see 3-807.3 and 7-104.42);

(vii) the effectiveness of subcontract management by the prime contrac-

tor;

(viii) the type of subcontract used (see Section III, Part 4);

(ix) the estimated total extent of subcontracting, including procurement

of parts and materials;

(x) the extent to which the prime contractor obtains assurance of the

adequacy of the subcontractors' procurement system;

(xi) availability from Government sources of industrial facilities or spe-

cial test equipment (see Section XIII, Part 3); and

(xii) whether consideration was given to the solicitation of small business

and labor surplus area a subcontract sources.

57

Page 118: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 119: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

16 April 1973 23:9

SUBCONTRACTING POLICIES AND PROCEDURES

(b) In reviewing subcontracts, careful and thorough evaluation is particularly

necessary when:

(i) the prime contractor's procurement system or performance

thereunder is considered inadequate;

(ii) subcontracts are for items for which there is no competition or for

which the. proposed prices appear unreasonable (see 3-807. 10(b));

(iii) close working -arrangements or business or ownership affiliations

exist between the prime and the subcontractor which may preclude

the free use of competition or result in higher subcontract prices

than might otherwise be obtained;

(iv) a subcontract, is being .proposed at a.price less favorable than that

which has been given by the subcontractor to the Government, all

other factors such as manufacturing period and quantity being com-

parable; or

(v) a subcontract is to be placed on a cost-reimbursement, time and

materials, labor-hour, fixed-price incentive, or fixed-price redeter-

minable basis.

Where subcontracts have been placed on a cost-reimbursement, time and materi-

als, or labor-hour basis, contracting officers should be hesitant to consent to the

repetitive or unduly protracted use of such type of subcontracts and should follow

the principles of 3-803(b).

(c) Consent to a subcontract or relief from the requirement for obtaining

consent, by virtue of the approval of the contractor's procurement system, does

not constitute a determination as to the acceptability of the subcontract price

(23-201) or the allowability of costs (7-203.8 or 7-402.8). However, it should

minimize the requirement for retroactive review of subcontracts, except cost-

reimbursement subcontracts, for the purpose of determining reasonableness of

costs, unless there is some indication that the costs may be unreasonable. In all

cases, costs resulting from such subcontracts shall be subject to the test of alloca-

bility.

23-203 Disputes and Arbitration Provisions in Subcontracts.

(a) Consent by the contracting officer to a subcontract does not constitute

approval of the terms and conditions of the subcontract. Nevertheless, the con-

tracting officer shall not consent to a provision in the subcontract purporting to

give the subcontractor the right to obtain a direct decision of the contracting of-

ficer or the right of direct appeal to the Armed Services Board of Contract Ap-

peals. The Government is entitled to the management services of the prime con-

tractor in adjusting disputes between himself and his subcontractors. The con-

tracting officer should act only in disputes arising under the prime contract, and

then only with and through the prime contractor, even if a subcontractor is af-

fected by the dispute between the Government and the prime contractor. The

contracting officer shall not participate in disputes between a prime contractor

and his subcontractors.

(b) However, the contracting officer should not refuse consent to a subcon-

tract, particularly under a cost-reimbursement contract, merely because it con-

tains a clause giving the subcontractor, if he is affected by a dispute arising under

the prime contract, an indirect appeal to the Armed Services Board of Contract

58

Page 120: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 121: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

16 April 1973 7:221

CONTRACT CLAUSES

INSPECTION (1959 FEB)

The Government, through any authorized representatives, has the right at all reasonable times,

to inspect, or otherwise evaluate the work performed or being performed hereunder and the

premises in which it is being performed. If any inspection, or evaluation is made by the Govern-

ment on the premises of the Contractor or a subcontractor, the Contractor shall provide and shall

require his subcontractors to provide all reasonable facilities and assistance for the safety and

convenience of the Government representatives in the performance of their duties. All inspec-

tions and evaluations shall be performed in such a manner as will not unduly delay the work.

(c) When it is desired to require contractors to maintain an inspection

system in accordance with Military Specification MIL-I-45208 (see 14-303), the

'Clause set forth in (a) aboveshall be included in the contract except that the fol-

lowing shall be added as the third sentence of paragraph (a):

The inspection system shall be in accordance with the edition of Military Specification MIL-

I-45208 in effect on the date of this contract. (1967 AUG)

7-402.6 Assignment of Claims. In accordance with 7-103.8, insert the clause

set forth therein.

7-402.7 Examination of Records. In accordance with 7-104.15, insert the

clause set forth therein. In the case of research and development contracts with

nonprofit institutions and subcontracts thereunder, and pursuant to procedures

approved by the Comptroller General, original documentary evidence in support

of costs of the transportation of things will not be required pursuant to said

clause.

7-402.8 Subcontracts.

(a) In accordance with the requirements in 23-201.2, and subject to the in-

structions in (b) and (c) below, insert the following clause.

SUBCONTRACTS (1973 APR)

(a) The Contractor shall notify the Contracting Officer reasonably in advance of entering into

any subcontract which (i) is cost-reimbursement type, time and materials, or labor-hour, or (ii) is

fixed-price type and exceeds in dollar amount either $25,000 or five percent (59c) of the total

estimated cost of this contract, (iii) provides for the fabrication, purchase, rental, installation, or

other acquisition of special test equipment having a value in excess of $ 1 ,000 or of any items of

industrial facilities; or (iv) has experimental, developmental, or research work as one of its pur-

poses.

(b) In the case of a proposed subcontract which (i) is cost-reimbursement, time and materials,

or labor-hour which would involve an estimated amount in excess of $10,000, including any fee,

(ii) is proposed to exceed $100,000, or (iii) is one of a number of subcontracts under this con-

tract with a single subcontractor for the same or related supplies or services which, in the ag-

gregate are expected to exceed $ 100,000, the advance notification required by (a) above shall in-

clude:

( 1 ) a description of the supplies or services to be called for by the subcontract;

(2) identification of the proposed subcontractor and an explanation of why and how the

proposed subcontractor was selected, including the degree of competition obtained;

(3) the proposed subcontract price, together with the Contractor's cost or price analysis

thereof;

(4) the subcontractor's current, complete, and accurate cost or pricing data and Cer-

tificate of Current Cost or Pricing Data when such data and certificate are required

by other provisions of this contract to be obtained from the subcontractor;

(5) identification of the type of subcontract to be used;

59

Page 122: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 123: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

7:222 16 April 1973

CONTRACT CLAUSES

(6) a memorandum of negotiation which sets forth the principal elements of the subcon-

tract price negotiations. A copy of this memorandum shall be retained in the Con-

tractor's file for the use of Government reviewing authorities. The memorandum(hall be in sufficient detail to reflect the most significant considerations controlling

the esnalishment of initial or revised prices. The memorandum should include an ex-

planation of why cost or pricing data was, or was not required, and, if it was not

required in the case of any price negotiation in excess of J 100,000, a statement of

the basis for determining that the price resulted from or was based on adequate price

competition, established catalog or market prices of commercial items sold in sub-

itantial quantities ta the general public, or prices set by law or regulation. If cost or

pricing data was submitted and a certificate of cost or pricing data was required, the

memorandum shall reflect the extent to which reliance was not placed upon the fac-

tual cost or pricing data submitted and the extent to which this data was not used by

the Contractor is determining the total price objective and in negotiating the final

price. The memorandum shall also reflect the extent to which it was recognized in

the negotiation that any cost or pricing data submitted by the subcontractor was not

accurate, complete, or current; the action taken by the Contractor and the subcon-

tractor as a result; and the effect, if any, of such defective data on the total price

negotiated. V/here the total price negotiated differs significantly from the Contrac-

tor's total price objective, the memorandum shall explain this difference; and

(7) when incentives are used, the memorandum of negotiation shall contain an explana-

tion of the incentive fee/profit plan identifying each critical performance element,

management decisions used to quantify each incentive element, reasons for incen-

tives on particular performance characteristics, and a brief summary of trade-off pos-

sibilities considered as to cost, performance, and time.

(c) The Contractor shall obtain the written consent of the Contracting Officer prior to placing

any subcontract for which advance notification is required under (a) above. The Contracting Of-

ficer may, in his discretion, ratify in writing any such subcontract; such action shall constitute the

consent of the Contracting Officer as required by this paragraph (c).

(d) The Contractor agrees that no subcontract placed under this contract shall provide for pay-

ment on a cost-plus-a-percentage-of-cost basis.

(e) The Contracting Officer may, in his discretion, specifically approve in writing any of the

provisions of a subcontract. However, such approval or the consent of the Contracting Officer ob-

tained as required by this clause shall not be construed to constitute a determination of the al-

lowability of any cost under this contract, unless such approval specifically provides that it con-

stitutes a determination of the allowability of such cost.

(f) The Contractor shall give the Contracting Officer immediate notice in writing of any action

or suit filed, and prompt notice of any claim made against the Contractor by any subcontractor or

vendor which in the opinion of the Contractor, may result in litigation, related in any way to this

contract, with respect to which the Contractor may be entitled to reimbursement from the

Government.

(g) Notwithstanding (c) above, the Contractor may enter into subcontracts within (i) and (ii)

of (a) above, without the consent of the Contracting Officer, if the Contracting Officer has ap-

proved in writing the Contractor's procurement system and the subcontract is within the scope of

such approval. (This subparagraph (g) however, shall not be applicable to those subcontracts sub-

ject to subparagraph (j) below, if any.)

(h) The Contractor shall (i) insert in each price redetermination or incentive price revision

subcontract hereunder the substance of the "Limitation on Payments" paragraph set forth in the

appropriate clause prescribed by paragraph 7-108 of the Armed Services Procurement Regula-

tion, including subparagraph (4) thereof, modified to omit mention of the Government and

reflect the position of the Contractor as purchaser and of the subcontractor as vendor, and to

omit that portion of subparagraph (3) thereof relating to tax credits, and (ii) include in each cost-

reimbursement type subcontract hereunder a requirement that each price redctcimination and in-

centive price revision subcontract thereunder will contain the substance of the "Limitation on

Payments" provision, including subparagraph (4) thereof, modified as outlined in (i) above.

(i) To facilitate small business participation in subcontracting under this contract, the Contrac-

tor agrees to provide progress payments on the fixed-price types of subcontracts of those subcon-

60

Page 124: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 125: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

16 April 1973 7:223

CONTRACT CLAUSES

tractors which are small business concerns, in conformity with the standards for customary

progress payments stated in paragraphs 503 and 514 of Appendix E of the Armed Services

Procurement Regulation, as in effect on the date of this contract. The Contractor further agrees

that the need for such progress payments will not be considered as a handicap or adverse factor in

the award of subcontracts.

(b) Insert the following additional subparagraph to theclause in (a) above, in

accordance with 23-20 1.2(d).

(j) Notwithstanding approval of the procurement system, the Contractor shall not enter into

certain subcontracts or classes of subcontracts set forth elsewhere in this contract without the

• « prior written consent of the Contracting Officer: ( 1 967 APR)

(c) In contracts without fee with educational institutions, change "(iii)" in

paragraph (a) of the clause in (a) above to read:

(iii) Provides for (A) the construction, purchase, rental, installation, or other acquisition

of nonseverable industrial facilities, or (B) the fabrication, purchase, rental, installa-

tion, or other acquisition, of any item of either ( 1 ) severable industrial facilities hav-

ing a value in excess of J 1,000 or the amount, if any, specified in the Schedule or

Task Order, whichever is the lesser, or (2) special test equipment having a value in

excess of $ 1 ,000. ( 1 967 APR)

In (iii)(B)(I) thereof, the $1,000 limit may, in the discretion of the contracting

officer, be decreased where it is determined to be in the interest of the Govern-

ment, in view of the circumstances of each particular contract, as, for example,

the nature of the Contractor's operations, previous experience with the contrac-

tor on comparable procurements, the contractor's accounting and procurement

systems, accounting and supply systems of the procurement activity, and the

capability of the procuring activity to effect close surveillance of the contractor's

procurement and accounting practices. Also, in the discretion of the contracting

officer, the cumulative total of acquisitions of severable industrial facilities maybe limited to a stated dollar amount or an amount equal to a stated percentage of

the estimated cost, beyond which amount the contractor will be required to ob-

tain written consent of the contracting officer for any additional acquisitions of

such facilities.

(d) In accordance with 23-201.4, insert the Equal Opportunity Pre-Award

Clearance of Subcontracts clause set forth in 7-104.22.

61

Page 126: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 127: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

C. TEACHING COMMENTARY

This case has been developed to illustrate several

aspects of subcontracting. The principal aspects include

what are the contractor's responsibilities in subcontracts

and what are the ACO's responsibilities and options in

subcontract consent procedures. Secondary aspects include

a review of ASPR make or buy considerations. In addition

it was endeavored to provide an entire consent package,

adapted from an actual package, to familiarize the student

with its make up and review.

The consent package and its circumstances in the case

have been constructed to be grossly deficient and heavily

slanted toward non-consent by the ACO. The errors written

into the consent package range from transposition errors

to major omissions in the package and nonadherence to the

ASPR provisions concerning consent requirements and changes

to a contract make or buy list. Also it was attempted to

show that the procurement was hurried and granted very

favorable conditions to the subcontractor. This will be

explained further as the considerations raised in the case

are discussed.

1 . Contractor Responsibilities in Subcontracting

The responsibilities placed on a prime contractor

are not unlike the responsibilities placed on the government

Both groups are expected to manage their programs, obtain

competition in necessary procurements, control risk, keep

interested parties informed, comply with the provisions of

62

Page 128: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 129: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

ASPR, deal fairly with contractors, etc., etc. A primary-

contractor responsibility is to manage his portion of the

program or contract. This is repeatedly reinforced in ASPR,

paragraphs 23-203(a), 1-906, 3-902.1. It is expected that

the prime contractor will manage the development in house

and also manage subcontractor efforts in support of the

prime contractor and the program. The government does not

desire to manage the subcontractor; it is the prime con-

tractor's responsibility to do so.

The prime contractor is also required to insure

that all the necessary ASPR provisions and prime contract

provisions are included in a subcontract. These include

socio-economic considerations such as utilization of small

business (ASPR para 1-707.3) and utilization of labor

surplus areas (ASPR para 1-805.3). However, in this flowdown

of requirements both from ASPR and the prime contract the

prime contractor should not place excessive flowdown require-

ments on the subcontractor. The prime contractor should

have, no need for excessive proprietary information from the

subcontractor. Such information could put the subcontractor

in a degraded position should the prime and the sub become

competitors in the future. The prime contractor should not

put disproportionate risk on the subcontractor. If a prime

contractor is performing under a development cost type con-

tract, for example, a subcontractor should not be placed on

a fixed price type subcontract for supportive development.

63

Page 130: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 131: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

Further the prime should not seek all patent rights from

the subcontractor's work if the government is not seeking

such rights from the prime contractor.

The requirement that the prime contractor conduct

his procurements as competitively as possible to gain the

cost, performance and other benefits therein is very impor-

tant, especially when the prime contractor is performing

under a cost type contract. There is a real possibility

that under a cost type prime contract the prime contractor

will turn to a favored supplier and incur excessive costs

for excessive quality or other desired benefits or con-

cessions. An approved prime contractor procurement system

as evidenced by a successful Contractor Procurement System

Review (CPSR) does show that the prime contractor's past

procurements were, on the average, competitive and accept-

able; but it in no way certifies that all past procurements

were conducted correctly or guarantee that all future pro-

curements will be conducted correctly.

There are many other considerations and responsi-

bilities that guide a prime contractor when dealing with

subcontracting but the above are among the most important.

2 . ACQ'S Subcontract Consent Responsibilities § Options

The ACO's primary responsibility is to consider the

12 concerns listed in ASPR paragraph 23-202 (exhibit 2)

which range from technical justification to small business

concerns. He should also insure that the proposed subcontract

is consistent with the objectives and provisions of the prime

contract.

64

Page 132: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 133: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

There are three reasonable options available to an

ACO when reviewing a subcontract for consent.

a. Do Nothing

The ACO could do nothing. Since his consent is

required before the subcontract can be effected the prime

contractor is stopped from obtaining the item from Raysonream.

However, if it can be shown that the government's non-action

constitutes delay then the government can be required to

reimburse the contractor for expenses incurred due to the

delay. The ASBCA decision on the ALGERNON BLAIR CASE dated

11 Nov. 1971 pertains.

The McDonnell-Douglas decision of the ASBCA

dated 7 Oct. 1968 provided further interpretation when it

held that the government does not acquiesce to a subcontract

when it returns the subcontract to the prime contractor

without action. A fair explanation of this would be that

for the government to grant consent it must do so by positive,

affirmative action.

b. Consent to the Subcontract

The ACO could consent to the subcontract and

effect the interpretation of consent as contained in ASPR

paragraph 23-202, 203. He would also be agreeing to the

use of the particular subcontract type employed, to the

proper make up of the consent package, to the proper inclu-

sion in the subcontract of all required clauses for sub-

contracts as stipulated in the prime contract, to the degree

65

Page 134: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 135: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

of competition obtained, to the fairness of any patent and

technical data clauses imposed on the subcontractor and

other flowdown clauses.

However, as ASPR paragraph 23-202 (c) points out

consent does not constitute that the ACO approves of the

acceptability of the contract price or the allowability of

costs

.

c. Do Not Consent to Subcontract

The ACO could specifically not consent to the

subcontract and return it stating its shortcomings. His

reasons for not consenting to the subcontract are the same

concerns as stated under consenting to the subcontract. If

sufficient competition was lacking, etc., it is in the best

interests of the government to stop the procurement and con-

duct it correctly.

2 . Make or Buy Considerations

The make or buy requirements of ASPR are one more

attempt on the government's part to insure that procurements

are thought out as completely as possible. Make or buy pro-

posals of the potential contractors are studied before

contract award to determine that the contractor has adequately

thought through the task at hand and that he has the capabil-

ity to manage the program. Costs and risks associated with

make or buy proposals are reviewed to determine what is in

the best interests of the government, to make or to buy.

For more detail concerning make or buy see Appendix 1.

66

Page 136: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 137: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

4. Review of the Consent Package

It should first be noted that Lieutenant Sliden's

consent is required by ASPR paragraph 23-201.2 as the prime

contract is a cost type contract and the proposed subcontract

is for research and development.

In this particular case Lieutenant Sliden should

question IAC's management of the development program. There

was no expected subcontract for the antenna subassembly. It

was not on the buy portion of the make or buy list of the

prime contract as the entire original buy list only amounted

to $100,000. With the prime contract already one-third

complete it appears that IAC has encountered some difficul-

ties and Sliden should discuss the circumstances with the

procuring hardware command and IAC. Further, IAC is in non-

compliance with the make or buy changes clause (ASPR 3-902.4,

Appendix 1) of the prime contract which states that proposed

changes to the make or buy list of a contract must be sub-

mitted to the ACO with justification. No such justification

was provided Sliden.

The hurried nature of the subcontract and the need

for Raysonream's expertise is evidenced by the way the sub-

contracting procedure and negotiations were handled. Very

little time was permitted the respective subcontractors to

draw up a proposal. Only Raysonream who had essentially

already drawn up the proposal when it had worked on the ori-

ginal prime contract proposal had a chance to be responsive

67

Page 138: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 139: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

on the request for proposals for the subcontract. The pro-

curement was directed to Raysonream under the guise of

competition.

The very favorable procurement for Raysonream is

further evidenced by manner in which the negotiations were

conducted. There was very little real negotiation present

with Raysonream* s data being accepted without question in

most cases. Whatever advantage IAC received was in areas

of little cost, the $190.00 tool, or government intervention,

the DCAA estimate for manufacturing overhead. Very generous

profit terms were granted without negotiation. There is no

evidence that IAC is protecting the interests of the govern-

ment in these negotiations. IAC because of its cost type

contract with the government appears ready in all instances

to pay a high price for the Raysonream procurement and pass

the cost to the government.

The consent package content is grossly deficient.

It lacks a price analysis by IAC, substantiation/breakdown

of cost or pricing data as required by the DD 633 and justi-

fication of the "other costs" noted in the memorandum of

negotiations. There are extension and carry over errors

wherein the price of $3226 in the manufacturing overhead

paragraph of the Memorandum of Negotiations appears as $3262

in the summary paragraph. The profit paragraph of the

memorandum states $11,214 whereas in the summary paragraph

it appears as $11,241. The extension of the quality control

hours should be 571x3.25=1855.75 vice the 1890 shown in the

68

Page 140: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 141: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

paragraph. Also the Memorandum of Negotiations uses the

term "they" extensively meaning the Raysonream representa-

tives. The individual concerned should be mentioned by name

to be more meaningful.

In summation, unless it can be shown not to be in

the government's best interests, consent should be denied

and IAC directed to conduct a truly competitive procurement

with meaningful requests for proposal and negotiations.

69

Page 142: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 143: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

IV. SUBCONTRACTOR SOURCE SELECTION: A CASE STUDY

A. INTRODUCTION

1. Case Brief and Objective

The purpose of this case is to introduce the student

to the source selection process used by a major defense con-

tractor in awarding subcontracts. The case will review some

of the issues which have challenged government in its practice

of negotiation and source selection. From this baseline the

case will illustrate the mechanics of source selection used

by one defense contractor under circumstances which caused

these same basic issues to be raised. The student should

also gain an appreciation for the role of the Government's

Administrative Contracting Officer in subcontractor source

selection.

2

.

Negotiation and Source Selection Within DoD

The Department of Defense (DoD) procures material

from private industry by two basic methods: formal advertis-

ing and negotiation. By statute, formal advertising is the

preferred method. However, as the Government's need for

increased use of the negotiation method evolved, so too did

the Government's need to satisfy itself that negotiated

procurements could withstand public scrutiny. To this end,

the legislative process, decisions of courts and boards,

and procurement regulations have defined and elaborated the

negotiation method in terms both broad and narrow.

70

Page 144: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 145: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

Congress began in the "broad" form in passage of

the Armed Services Procurement Act of 1947. A section of

that Act, later codified in Title 10, 2304 (g) , U.S. Code,

stated:

"In all negotiated procurements .. .writtenor oral discussions shall be conducted with allresponsible offerors who submit proposals withina competitive range, price, and other factorsconsidered."

This general theme is reiterated in the Armed

Services Procurement Regulations (ASPR) . Section 3-805

identifies four special cases in which discussions need not

be held following receipt of initial proposals. A fifth

and broader class of exceptions to the general requirement

for holding discussions speaks of (3-805.1 (a) (v)):

"Procurements in which it can be clearlydemonstrated from the existence of adequate com-petition or accurate prior cost experience withthe product or service that acceptance of themost favorable initial proposal without discus-sion would result in a fair and reasonableprice."

Circumstances which would appear to permit this

latter exception to be invoked raise the question of whether

the procurement should have been formally advertised in the

first place. At any rate, the overall thrust of ASPR 3-805.1

is that discussions with all offerors in the competitive

range is the general rule in negotiated procurement. No

proposal from a responsible source offering an acceptable

technical proposal is permitted to be rejected unless such

proposal includes a price proposal.

71

Page 146: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 147: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

The Comptroller General stated it perhaps more

plainly when he said (47 Comp. Gen. 336, 342 (1967)):

"...for competitive negotiation to bemeaningful and effective, negotiations shouldinform offerors within a competitive range asto the areas in which their proposals arebelieved deficient, to the end that competitiveofferors are given an opportunity to supportor revise their proposals to satisfy theGovernment's requirements."

Further clarification of important details of the

negotiation method have been the subject of General Account-

ing Office (GAO) interpretation. For example, the "competi-

tive range" has been broadly defined to include any offeror

whose proposal stands a reasonable chance of being selected

for final award. A more difficult question deals with the

extent to which a procuring agency is required to avoid or

minimize advantages afforded to one of the competitors.

This may arise when an offeror is the incumbent contractor

in a developing project, or when an offeror gains the bene-

fit of information through his other government contracts.

To decide this issue GAO has posed two questions:

1.) was there independent justification for the actions

which resulted in the competitive advantage, and 2.) did

the agency make a good faith effort to avoid affording

exclusive advantage to one offeror?. If either question is

answered in the negative, an award to the advantaged offeror

can be overturned.

Source selection can be broadly defined as the

process used to select a winner in a negotiated procurement.

72

Page 148: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 149: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

The process may be simple or elaborate, according to the

stakes involved and the amount of uncertainty in the cost,

schedule, and performance factors. In its more elaborate

form, source selection involves evaluation and ranking of

proposals by an evaluation board according to predetermined

criteria. Actual selection is usually made by a second

committee at a higher organizational echelon. Variations

in the mechanics of the source selection process are nearly

infinite. Even fundamental principles of source selection

are fraught with controversy.

The question of discussions with all offerors in

the competitive range is one aspect of source selection

already discussed. Compliance with this provision, while

observing the prohibition against technical transfusion

among proposals, is another important issue. There is no

disagreement that the criteria by which proposals will be

evaluated should be made known in the Request for Proposals

(RFP) . But the question of informing prospective offerors

of the relative importance or weights of the technical

proposal, management plan, cost proposal, etc., is indeed

controversial.

The GAO position has been that offerors should be

informed of the broad scheme of scoring, to be employed and

reasonably definite information as to the degree of impor-

tance to be accorded to particular factors in relation to

each other. However, in situations where the sufficiency

of information concerning the relative importance of the

73

Page 150: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 151: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

evaluation criteria is not questioned prior to submission

of proposals, and the record does not establish that any

offeror was placed at a competitive advantage or disadvan-

tage by the inadequacy of such information, the deficiency

is not sufficient to disturb the award.

At least one industry view is less certain on

this issue than is GAO. Mr. W. Gregor Macfarlan, in an

address at Washington Chapter of the National Contract

Managers Association on March 21, 1973 put it this way:

"How much should contractors be told aboutthe basis for evaluation? A little bit? That'strouble right from the start. Everything? Ifthat's the case, they may sit down and bid theevaluation criteria and lose any sense of biddingthe job."

The usual result of the first phase of the source

selection process is to assign a numerical grade to the

various categories of each responsive proposal. These

grades are then multiplied by the weight assigned to that

category. For example, in a research and development

procurement, the technical category would usually be

assigned a relatively high weight and the cost category

a relatively low one. These products are then totalled to

arrive at an overall score for each offeror. Presumably,

the selection committee makes the award to the high scorer.

Difficulties arise because in the period between

preparation of the RFP and evaluation of proposals, the

procurement agency's understanding of how its requirement

can best be satisfied becomes less uncertain. Armed with

74

Page 152: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 153: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

the new and better information, a source selection committee

may well wish to stress different criteria and rearrange

the relative weights assigned the various categories. Such

a tactic can hardly be regarded as equitable by offerors

who structured their proposals according to the initial

evaluation plan. On top of this the procurement agency

must negotiate with all offerors in the competitive range

and, as previously noted, avoid technical transfusion.

For those unconvinced that the source selection

process is fraught with potential controversy, two final

points can be made. One is whether competition is served

when the management plans of a major prime contractor and

of a relative newcomer are evaluated by the same criteria.

Lastly, GAO has ruled that evaluation board scoring is

advisory only and is not binding. This is premised on the

view that no RFP can adequately express all of the judge-

mental factors which must be brought to bear in making a

source selection for a major project. The source selection

authority must retain the discretion to award to other than

the high scorer if this is considered in the best interests

of the Government.

3. Contractor Procurement

The procurement practice of major defense contractors

lies somewhere in between Government and commercial practice.

Defense contractors are strongly encouraged and in some

details directed to adopt Government principles in their

own procurement operations. Contractor purchasing personnel

75

Page 154: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 155: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

are every bit as familiar with ASPR and GAO decisions as

their Government counterparts. Even the forms used by a

major defense contractor in his purchasing department dupli-

cate ASPR provisions almost without exception.

Negotiation is virtually the only procurement

method employed in the commercial arena. There is no

statutory requirement that formal advertising be used as

a preferred method. This fact points out a fundamental

difference between Government and commercial practice --

the source, scope, and number of procurement rules and

regulations

.

Unlike a Government procuring activity, a contractor

is relatively free to establish his own procurement procedures,

unencumbered by detailed statutory requirements and regula-

tions from "higher authority". As a condition of doing

business with the Government, a contractor relinquishes

some of his freedom and agrees to incorporate certain Govern-

ment imposed requirements in his own procurement practice.

Despite this limitation however, the contrast between a

contractor and a Government procurement agency, from the

standpoint of inflexible procurement regulations, is

significant

.

A second difference between contractor and Govern-

ment procurement concerns the number of sources of supply

solicited for a given procurement transaction. Contractors

are not compelled to widely publicize a forthcoming procure-

ment nor to place heavy emphasis on award to the low bidder.

76

Page 156: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 157: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

Contractors solicit fewer sources of supply, insuring only

that minimum required competition is obtained rather than

maximum possible. Contractors are relatively free to

place more emphasis on quality, delivery, and continuing

relationships with an adequate circle of suppliers.

As to source selection procedures for major

procurements, the differences between Government and con-

tractor practice are much less. Each entity utilizes

rather similar procedures intended to accomplish the same

purpose. Some procedural differences do exist. They arise

not only from the Government practice of developing elaborate

written regulations, but also from the Government's desire

to demonstrate the presence of maximum possible competition.

4. Subcontracts and the Role of the ACQ

The procurement operations of major defense contrac-

tors are continually supervised by a Government Contract

Administration Office (CAO) at or near the contractor's

plant. In performing this function, the CAO personnel are

inevitably guided by the Government view of the negotiation

method. This view is the baseline of their training and

experience. Annually, the procurement operation of the

defense contractor is reviewed by the terms of the Contractor

Procurement System Review Program (CPSR) . If the review

shows that the contractor's procurement system meets certain

standards of efficiency, ethics, contractual compliance, and

competitiveness, his procurement system is approved. Such

approval significantly reduces the number of contractor

77

Page 158: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 159: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

procurement transactions which the CAO must review. By sheer

number of transactions alone, no CAO is equipped to do more

than monitor high dollar value procurements. Of neces-

sity, great reliance is placed on the contractor's possession

of an approved procurement system.

Under certain circumstances -- type of contract,

nature of the work, dollar thresholds, etc. -- a defense

contractor must obtain the consent of an Administrative

Contracting Officer (ACO) prior to awarding a particular

subcontract. Section 23-202 of ASPR lists the considera-

tions to be observed by an ACO prior to granting consent.

Among these is that the ACO consider the basis for select-

ing the proposed subcontractor, including the price compe-

tition obtained. However, by no means does the consent

procedure make the Government a party to the arrangement

between contractor and subcontractor. The Government is

not in privity with the subcontractor. The prime contractor

is paid to manage the subcontracts and is expected to resolve

any disputes which may arise out of them. Any three-party

arrangement would be highly unworkable.

Thus while the CAO is charged with insuring that

competitive procurement is practiced in connection with con-

tracts under its administration, resources and lack of

privity limit the CAO's prerogatives. The relationship

between the CAO and the prime contractor is important to

progress of the contract work. Issues which would disturb

78

Page 160: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 161: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

this relationship tend to be resolved in favor of preserving

the relationship. Customer relations tends to be a two-way-

street.

B. CASE BACKGROUND

1. The Pluto Program

Pluto I is a two stage, solid propellant medium

range missile, armed with a nuclear warhead, and deployed

on Guided Missile Cruisers of the U. S. Navy. This system

was developed and produced for the Naval Ordnance Systems

Command by the Rocket and Space Division of Consolidated

Industries. Since its introduction to the fleet in 1967,

Pluto I had made a significant contribution to the strategic

deterrence of the United States.

Responsibility for management of the Pluto program

within the Navy was assigned to the Pluto Project Manager,

NORD-053, at the Naval Ordnance Systems Command (NAVORD) in

Washington, D. C. The Project Manager, a Captain, was

responsible for both business and technical aspects of the

Pluto Program. Some 100 civilian and military personnel were

assigned to the immediate staff of the Project Manager. In

addition, numerous field activities of the Defense Department

provided support. Foremost among these was the Naval

Plant Representative Office located in Prunedale, New York.

Prunedale was the site of the Pluto prime contractor's

principal facility.

The mission and functions assigned to the Naval Plant

Representative Office (NAVPRO) , Prunedale were delineated in

79

Page 162: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 163: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

NAVORD Instruction 5450. 37B. Generally stated, the NAVPRO

was to act as technical representative and contracting

officer of the appropriate Systems Command in all matters

relating to administration of contracts to the extent

authorized by appropriate authority. In performing his

duties the NAVPRO was guided extensively by the Armed

Service Procurement Regulations (ASPR)

.

NAVPRO Prunedale was responsible for supporting all

Navy procurement activities doing business with the Rocket

and Space Division. In this regard specific contract

administration tasks were often agreed upon by letter between

NAVPRO and the procurement agency. The Rocket and Space

Division was, in turn, directed by contract clause to look

to the NAVPRO for Government contract administration. Be-

cause of the magnitude of the Pluto Program, NAVPRO Prune-

dale's major effort was in support of the Pluto Project

Office. The relationship between the NAVPRO and NORD-053

was extremely close, emphasizing the team effort needed for

the success of the Pluto Program.

In March of 1972, the Navy announced award of a

cost plus incentive fee contract to the Rocket Systems Div-

ision for development and production of ten prototype

missiles to be designated Pluto II. Extensive research and

development in rocket motor and guidance system design had

indicated significant improvements in Pluto missile

80

Page 164: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 165: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

performance could be achieved. At the time of contract

award, NAVPRO Prunedale consisted of one hundred and seventy-

three personnel. Of this number, seventeen were military-

personnel and the remainder Civil Service. The organization

of NAVPRO Prunedale is shown in Exhibit One.

81

Page 166: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 167: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

NAVAL PLANT REPRESENTATIVE OFFICE - PRUNEDALE

_ REPRESENTATIVE _EXECUTIVE OFFICER

NAVAL PLANT BRANCHREPRESENTATIVESWEETWATER, FLORIDA

fPOLICY & PLANS

DIVISION

ENGINEERINGDIVISION QA

DIVISION

OFFICE OFSECURITY & COMMUNICATION

OFFICE OFCIVILIAN PERSONNEL

ADMINISTRATIVE DIVISION

CONTRACTS DIVISIOIDIVISION HEADDEPUTY

PROPERTYADMINISTRATION i

PLANT CLEARANCE

ADMINISTRATIONSUPPORT BRANCH

CONTRACTADMINISTRATIONBRANCH "A"

CONTRACTADMINISTRATIONBRANCH "B"

COST & PRICEANALYSIS BRANCH

INDUSTRIALDIVISION

EXHIBIT ONE

82

Page 168: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 169: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

2. The Prime Contractor

Consolidated Industries employs approximately 60,000

people distributed throughout seven major operating divisions

and subsidiaries. In addition to the design, development

and production of aircraft, missiles, and satellite systems,

Consolidated is at work in such fields as rocket propulsion

systems, aircraft service, ship building, bridge, highway,

dam and tunnel construction, ocean systems, communications,

airport operation and maintenance, electronics, and military

ground vehicles.

The Rocket and Space Division builds the Pluto

missile system for the U. S. Navy and the Pollux space

system for NASA. The corporation's ocean systems programs

are also managed by this division.

The Rocket and Space Division employs approximately

24,000 people and is located in Prunedale, New York. Its

nearly 7 million square feet of floor space, in addition to

the Prunedale plant, include a missile test facility and

aerospace research center at Sweetwater, Florida.

As of September 1973, the Consolidated Industries'

backlog of unfilled orders stood at $849,000,000 under U.S.

Government contracts and $1,372,000,000 under commercial and

export programs. Rocket and Space Division sales for 1972

totalled $306,000,000 under U. S. Government contracts and

$36,000,000 in commercial and foreign business.

The procurement function and certain related

material activities were assigned to the Material Branch,

83

Page 170: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 171: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

headed by the Director of Material, who reports to the

President of the Rocket and Space Division.

Management provide guidance and control over the

Material Branch and was made aware of Branch policies and

practices by written statements of policy and procedure

maintained and distributed through a system of manuals as

required by Management Directive, negotiation and assign-

ment of operating budgets, President's staff meeting, etc.

Authority to commit the Company was delegated to the

Director of Material. Level of authority to approve procure-

ment documents was established at fixed dollar levels in

accordance with position and may include the review and

approval of the cognizant Vice-President.

Management was directly involved in the award of

key subcontracts through the media of go ahead approvals

and/or Procurement Review Committee approval action. Pro-

curement Review committees were convened by the Director of

Material, and comprised of the responsible Project Vice

President, the Directors of Engineering, Financial Operations,

Product Assurance and such other executives as the nature of

the procurement dictated. The organizational structure of

RSD is shown in Exhibit Two.

84

Page 172: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 173: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

CO2:

H- «a

z: QiLU OQ Oi—

i

<X.

OO Q.LUo: _iQ- «C

>-H

LU OC_> Cd»—

*

LU> 2:

2:

CD

cc ocO LU LU\— C_> LUo *z s:LU LU >—

1

a: •—1 o

>—1 o rrO OO LU

LU0; CJ

1— sr»

h— O <13 0;

LU O rjOT O OO1—

i

a; on^ a_ <

LUO

h- OH 1—2:(_> LU <_> <C

"-D <c 1— q zd

ct < _id: wa. 2: a. q_ «=c

0;

1— 1—;et

LU _j LUq; <c 2:1—

1

d: LULU ct:

2; rs1— LU t_>

0000 a;<: CL

OHOh-CJLUcc1—

1 OQ I—

OO Q-OO<C

CO CD< I—

a; q_

00LU>•

1— 1—|

z: CD OO c_xLU LU 7^* Ql <Q—_1 2: *—

H

LU r->^~

1—1 LU to f— H-LUOO CC <coo OO 1—1 SI/}CO ZD lin- d; o-u1—1 O os: LU LU (-TT2: ttTLU >- Q- mn,

oh IDCD rD x :dujD_ D-eC m lu 000;

_la: «a

t—

t

h- DiO LULU H-Qi =ck—

i

2:Qi—

1— siOO <C00 _i=t Q.

1—2:

LU LUC_> 2152 LU=^T CL2: :r>

Q CD0;O C£

Q..

2:1— <c2: or

orLUOO

LU CD Q- 21 CDO O > <C <C•—1 cc CH 2:00 Q_ 1— CD <cLU 2: 2;c£ t- — <C OH 1—Q- rr h- Q_ 2> 1—

LU OO _l c_>

lu s: >—<>- a. lu

rr OO > "D—< 0^ oo <: O> LU> <c 2: oh

OCD

0;O LUh- CDCD s:LU <Ccc 2:t—( 1

i

Q U_

00z:

1—

1

I—=COH

CC LUlu a.CD O=CZZ CD< s:2: >—

,

C£ f—hHDC_> 1— —

1

UUD.n <O Ll_

o; ^>d. 2:

<c

85

Page 174: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 175: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

RSD had been included in the Contractor Procurement

System Review Program since 1961 and had maintained an

approved status throughout this period. The Annual Review

completed by NAVPRO in April 1973 revealed no significant

discrepancies or unfavorable trends in the RSD procurement

system. The scope of the RSD procurement operation during

the last review period was as follows:

Summary

Purchases $162,800,000Number of transactions 159,070Ratio: purchases to sales 53.3%

Distribution of Purchases

Category Number Value

$25,500,00016,100,0009,700,000

29,400,00082,100,000

159,070 $162,800,000

The CPSR report noted that a sample consisting of

(50) procurements on the Pluto program revealed the follow-

ing statistics pertaining to subcontractor source selection:

Number Reason Percentage of Sample

44 Lowest bidder 88.03 Other than lowest bidder 6.03 Single responsive bidder 6.0

Of the (50) sampled procurements, a total of (325)

suppliers received RFP's. Of this total, (229) were respon-

sive (70.51) and the remaining (96) declined to bid. Of the

(3) awards to other than the lowest bidder, (2) were customer

(Navy) directed and (1) was more technically qualified. All

three of the awards to a single responsive bidder were for

86

0-$2,500 154,800$2,500-$10,000 2,865$10,000-$25,000 616$25,000-$100,000 592over $100,000 197

Page 176: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 177: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

items which had interface with other equipments on which

the bidder was the supplier.

3. The Case Problem

LCDR Fred Brown had served as Head of the Contracts

Division at NAVPRO Prunedale since mid-1972. Some thirty

five civilian personnel were assigned in this division,

ranging in grade up to GS-13. LCDR Brown was both manager

of the division and one of five duly authorized Administra-

tive Contracting Officers (ACO's). A sixth ACO in the

NAVPRO was the Representative himself, Captain Smiley.

LCDR Brown was a Supply Corps officer with experience

aboard ship, at a Navy Regional Purchasing Office, and most

recently at a major project office in NAVSHIPS. In the

Navy's view this background was well suited to his present

assignment. Fred, however, still felt pretty much like a

novice in trying to understand the inner workings and

hidden mechanisms of a major defense contractor like RSD.

Most of the work of the Contracts Division of NAVPRO

involved two RSD suborganizations -- the Pluto Project

Manager Group and the Material Division. Relations between

NAVPRO and RSD personnel were good. The NAVPRO was operating

under the DOD policy of engagement with the contractor. RSD,

in turn, accepted this approach since it was consistent

with the Navy-industry team concept so successfully used

throughout the Pluto Program.

LCDR Brown frequently felt himself adrift in a sea

of paper. In all contract administration organizations

87

Page 178: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 179: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

paperwork was the dominant medium and NAVPRO Prunedale was

no exception. Fortunately, however, there were the occa-

sional documents which interrupted the routine -- for better

or for worse. The following letter was in this latter

category:

88

Page 180: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 181: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

15 November 1973

From: Chief of Naval Material

To: Naval Plant Representative Prunedale

Subj : Award of Rocket and Space Division Subcontract;

request for information concerning

1. An unofficial Congressional inquiry has been

made on behalf of Connectronix Corporation of Wilmington,

New Jersey, concerning the award of the Rocket and Space

Division Contract R-739F821A to Pyramid Products, Inc. of

Freemont, New York. The RSD subcontract is for components

in support of the Pluto II prime contract, N-0682B7193.

2. Connectronix alleges that during the post-award

debriefing by RSD, they were advised that their low bid,

while technically satisfactory, was judged to be inferior

to that of Pyramid Products. Connectronix maintains that

their proposal was in every respect responsive to the RSD

Request for Proposal (RFP) . Specifically, Connectronix

maintains that the basis for evaluating proposals was not

fully expressed in the RFP, but that this information was

known to the winning offeror because of his continuing

business relationship with RSD. As a result, a critical

element needed to make this award on a competitive basis,

equality of information, was not present.

89

Page 182: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 183: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

3. You are requested to review the aforementioned

RSD procurement and provide this office with sufficient

information to answer this allegation. A reply by 30

November is requested.

\NW. T. Door

by direction

Copy to: NAVORD (NORD-0 53)

90

Page 184: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 185: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

After studying the letter for some moments, LCDR

Brown recalled an RSD subcontract with Pyramid Products

but could not remember much more about it. If the sub-

contract had been approved by the NAVPRO (which it had)

,

then the Contract Division must have been involved.

Attached to the CNM letter was a NAVPRO form assigning

LCDR Brown the task of preparing a reply.

Fred's first impulse was to call George Bloom, the

RSD General Purchasing Agent responsible for Pluto pur-

chases. George could quickly fill him in on the nature

of this subcontract and send over the purchase file for

Fred to review. Instead he decided to read the letter

once more.

Fred knew that RSD had elaborate written procedures

covering source selection for major subcontracts. These

procedures were, in essence, approved by NAVPRO during the

annual Contractor Procurement System Review of RSD.

Although subcontracting was a major part of the Pluto

Program, Fred could not recall a prior bid protest by a

subcontractor.

But there was a bid protest now and one with

Congressional interest. A perfunctory reply to CNM

might come back to haunt him. Fred decided to outline the

fundamental questions raised by the CNM letter -- competi-

tion, source selection, ACO consent, and the NAVPRO'

s

alternatives should the Connectronix protest prove to have

91

Page 186: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 187: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

some merit. He then quickly sketched his plan for getting

the necessary information and answers.

C. REVIEWING THE SOURCE SELECTION

1. General

LCDR Brown was fairly familiar with the process by

which procurement requirements were satisfied at RSD.

Generally, requirements were generated by Engineering and

forwarded to Subcontracts together with technical evaluation

criteria and a list of recommended suppliers. An RSD manual

known as Material Procedures described in great detail the

procedures to be followed by Subcontracts personnel. These

procedures were occasionally supplemented by ad hoc RSD

procedures, similar in form to Navy Instructions and Notices.

For significant material requirements, a Subcontracts

Manager convened a source selection evaluation team with

members from all affected RSD departments. The team met to

develop the information needed to draft an RFP and to

establish source evaluation criteria in five broad categories.

The 'categories were Technical Approach, Management, Product

Quality and Reliability, Manufacturing, and Cost Considerations

Subcontracts was responsible for issuing the RFP

and distributing the proposals received, broken down by

category, to members of the evaluation team. Proposals were

then graded according to the predetermined criteria and a

resultant grade assigned to each of the five major categories.

After receiving the graded proposals, the Subcon-

tracts Manager next convened a source selection board.

92

Page 188: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 189: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

Membership from Engineering, Product Assurance, Material,

and Manufacturing was customary. The source selection

board met to determine the relative weights to be assigned

to each of the five categories by which proposals were

evaluated. Having assigned the weights, determining a

total score for each proposal was a simple matter. Normal

procedure was to select for award the proposal having the

highest score. If any member disagreed with this choice,

the matter was brought to a higher organizational level

for consideration.

After being notified of the results of the source

selection process, Subcontracts proceeded to negotiate the

contract. If required, a "consent package" was prepared

and submitted to the ACO for his approval.

2 . Supporting Documents

The material included in the remainder of section C,

of the case was gathered by LCDR Brown to assist him in

resolving the questions raised by the CNM letter. The

student should review this material in preparation for the

case requirements contained in section D. The following

material is included:

Exhibit One - NAVPRO Prunedale memorandum of 23November 1973 with vendor profiles andselected financial information

Exhibit Two - RSD memorandum of 22 November 1973with the following attachments:

1.) Procurement Summary2.) ACO Consent Form dtd 12 October 19733.) RSD Material Procedure #752 (Source

Selection)

93

Page 190: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 191: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

4.) Enclosure CI) to RSD RFP of 17 April1973 with attachments (9), (10), and(11).

5.) RSD Interoffice memorandum of 25August 1973 with attachment (1)

.

6.) RSD Interoffice memorandum of 18August 1973 with attachments (1)through (6)

.

94

Page 192: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 193: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

NAVAL PLANT REPRESENTATIVE OFFICEPRUNEDALE, NEW YORK

23 Nov 1973MEMORANDUM

From: A. Sloan, Contract Administration Branch 'A'

To: LCDR Brown

Subject: Vendor Profiles

1. The attached vendor profiles were obtained by telephoneinquiry to the DCASO's concerned and from Moody'sIndustrials

.

Very respectfully,

A. Sloan

EXHIBIT (1) - 1

95

Page 194: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 195: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

Connectronix Corporation

Headquarters: Wilmington, New Jersey.

Production Facilities: Wilmington, New Jersey.

Contract Administration: DCASO, Connectronix, Wilmington

Sales to the Government (1972): DOD prime contracts $22,174,000DOD subcontracts $7,824,000

CPSR Status: approved (since 1970).

RSD Subcontracts: no current or prior contracts with RSD.

DCASO Comment: good R 5 D capability; limited productionfacilities; placed on Navy ContractorExperience List for delivery delinquenciesin 1968 and removed from the list in thesame year; facility was idle during Julyand August due to labor dispute.

Income Statement- -1972

Net sales $34,87Cost of sales 24,58Sell, etc. exp. 6,84Other deduct., net 12Oper. income 3,31Other income 5

Total income 3,36Income Tax 1,64Inc. cont. oper. 1,72Inc. discont. oper. 3

Extraord. creditNet Income 1,76

Prev. ret. earn. 1,95Cm. divs. (cash) 65Cm. divs. (stk) 1,95Retained earnings 1,10Earn. cm. shareNo. of cm. shares 1,86

1437,7706,6206,059

694703397084313

4,2579,0419,6113,3379,1977,4326,319$.95

5,785

EXHIBIT (1) - 2

96

Page 196: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 197: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

Connectronix Corporation (cont.)

Combined Balance Sheet--1972

Ac S G t S

Cash $881,050Rec. net 3,394,169Inventory 5,873,666Prepay. 162,831

Total current $10,311,716Net prop. etc. 7,401,484Other assets 718,945Intang. 265 , 555Total $18,697,700

LiabilitiesNotes Pay. $1,532,229Accts. pay. 2,197,966Inc. tax

'

709,001Total current $4,439,196

Long term debt 1,747,606Def. inc. tax 30,696Cm. stk ($5) 9,427,310Capital surplus 2,089,678Retained earn. 1,106,319Stockholders equity 12,623,307Reacquired stock 143,105Net stockholders equity 12, 430, 202

Total $18,697,700Net current assets 5,872,520Net tg. cm. share $6.54

1972 stock price range - high, $15-1/2; low, $9.

EXHIBIT (1) - 3

97

Page 198: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 199: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

Pyramid Products Inc.

Headquarters: Freemont, New York.

Production Facilities: three locations including Freemont,where Pluto connectors are beingproduced.

Contract Administration: DCASO, Pyramid Products, Freemont.

Sales to the Government (1972): DOD prime contracts $37,423,000DOD subcontracts $44,861,000

CPSR Status: approved (since 1966).

RSD Subcontracts: awarded subcontract for design/productionPluto I connectors in 1962; three follow-on contracts subsequently awarded forproduction including one still outstanding.

DCASO Comment: strong development capability and productioncapacity; good quality assurance record; minordelivery delinquencies.

Income Statement--1972

Net sales $153,437,000Other income 1,480,000

Total 154,917,000Cost of sales 128,747,000Sell. etc. exp. 10,315,000Interest 561,000Fed. inc. tax 7,233,000Net profits 8,061,000Prev. ret. earn. 26,734,000Common divs. 1,844,000Retained earn. 32,951,000Earn. cm. share $2.62No. of cm. shares 3,082,000

EXHIBIT (1) - 4

98

Page 200: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 201: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

Pyramid Products Inc. (cont.)

Combined Balance Sheet- -1972

AssetsCash § equiv. $7,740,000Rec. net 18,789,000Inventory 25,920,000Prepay. 214,000

Total current $52,663,000Net prop. etc. 17,514,000Other assets 1,708,000

Total $71,885,000

LiabilitiesAccts. Pay. $16,410,000Notes pay 1,515,000Accruals etc. 3,627,000Fed. inc. tax 2,914,000

Total current $24,466,000Long term debt 5,296,000Cm. stk. ($1) 3,085,000Capital surplus 6,230,000Retained earn. 32,951,000Stockholder equity 42,266,000Reacquired stk. 143,000

Net stockholder equity 42,123,000Total $71,885,000

Net current assets $28,197,000Net tg. cm. share $13.70

1972 stock price range - high, $76; low, $73.

EXHIBIT (1)

99

Page 202: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 203: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

Wafburg Industries

Headquarters: Lyme, New York

Production Facility: Lyme, New York

Contract Administration: DCASO, Wafburg, Lyme

Sales to the Government (1972): DOD prime contracts $17,152,000DOD subcontracts 11,469,000

CPSR Status: approved (since 1969)

RSD Subcontracts: Three R 5 D subcontracts during pastthree years; one production contract,Pluto I connectors, 1971.

DCASO Comment: none (DCASO policy is to respond only towritten requests for evaluative information)

.

Income Statement- -1972

Sales 44,087,740Equity earnings 390,444Other income 313, 290

Total $44,791,474Cost of sales 30,090,131Selling, etc. exp. 10,861,872Depr. $ amort. 1,793,924Profit share. 134,500Interest 1,045,273Inc. tax 320,500Inc. contin. oper. 545,274Loss discont. oper. 56,551Extraord. credit 588,674Net income 1,077,397Earn cm. share $0.39No. of cm. shares 2,766,911

1972 stock price range: high, $16-l/4;low, $6-1/2

EXHIBIT (1) - 6

100

Page 204: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 205: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

Wafburg Industries Ccont.)

COMBINED BALANCE SHEET - 1972

As setsCash $1,533,064Mkt. sec. cost 194,287Rec. net 8,648,821Inventories 9,728,521Real estate for sale 429,730Prepayments 400,449

Total current $20,934,872Net prop. etc. 9,579,230Invest, a adv. 3,649,025Patents, etc. 1,229,960

Total $35,393,087

LiabilitiesAccts. etc. pay. $6,577,607Notes pay. 2,712,730Inc. taxes 135 , 503Total $9,425,840

Notes pay. 12,043,126Def. inc. tax 193,503Common stk 2,768,911Capital surplus 7,395,505Retained earn. 3, 566 , 202

Total $35,393,087Net current assets 11,509,032

EXHIBIT (1) - 7

101

Page 206: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 207: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

ROCKET AND SPACE DIVISION

CONSOLIDATED INDUSTRIES

November 22, 1973MEMORANDUM

From: Assistant Director of Material (Pluto Program)

To: LCDR Brown, Contracts Division, NAVPRO(Prunedale)

Subj : RSD Subcontract R-739F821A

Attach: 1. Procurement Summary

2. ACO Consent Form dated 12 Oct 1973

3. RSD Material Procedure # 752

4. Enclosure (1) to RSD RFP of 17 April 1973 withattachments (9), (10), and (11).

5. RSD Interoffice MEMO of 25 AUG 1973 withattach. (1)

.

6. RSD Interoffice MEMO of 18 AUG 1973 withattachments (1) through (6)

.

1. George Bloom informed me of your interest in obtaining

a recap of the recent Pluto II connectors procurement. The

attached material is provided for this purpose.

2. Source selection for the connectors was carefully under-

taken to. insure the high reliability requirements of the

prime contract would be fully satisfied for these critical

components. A heavy emphasis was placed on technical worth

of the various proposals for this reason.

3. Should you require further information concerning this

procurement, I will be happy to make the necessary

arrangements

.

Avery H. Hill

EXHIBIT (2)

102

Page 208: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 209: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

PROCUREMENT SUMMARY

Request for Proposals Issued

Number of Sources Solicited

Proposal due Date

Number of Sources Declining to Bid

Responsive Offerors and Price Proposals

A. Wafburg Industries

B. Pyramid Products

C. Connectronix

Source Selection Procedure

Pre-Award Negotiations

Evaluation Completed

Selection Made

Source Selected

ACO Consent (R§D type prime contract)

Requested

Granted

Letter Contract Awarded

Notification of Unsuccessful Offerorsand Invitation to be Debriefed

17 April 1973

9

4 June 1973

6

$675,000

$767,000

$510,000

none

18 August 1973

25 August 1973

Pyramid Products

1 October 1973

12 October 1973

12 October 1973

20 October 1973

Firm-Fixed Price Contract Definitized 29 October 1973

Attachment 1

103

Page 210: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 211: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

PROCUREMENT

TRANSACTIONPrior Consent

date p . o . /subcontract no. amendment/chg notice' 1 Oct 73" ~ R-739F821A ^ ' x

To: Naval Plant Representative OfficeAttn: CodePrunedale, New York

Re:

1. Advance notification is hereby given that the Contractorproposes to make an award under prime contract N-0682B7193which is a CPIF (R$D) type of prime contract.

a. Name of Subcontractor: Pyramid Products Inc.Freemont, New York

b. Description of Supplies or Services:

Pluto II connectors (see item 3901 of primecontract - statement of work)

.

c. Type of Subcontract:

_CPFF _CPIF _C0ST _C0ST SHARING _T$M

_LAB0R HOUR X_FFP _FPI _FPR X_LETTER

_CHANGE NOTICE

d. Proposed price of this procurement transaction is:

$767,000.00

2. The Administrative Contracting Officer's prior consentto the placement of this procurement transaction is

X Requested Not Required

Submitted by

(X^VlSK^Attachment 2

104

Page 212: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 213: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

Consent is hereby given to the placement of subject proposedsubcontract or purchase order, subject to the conditions ofthe clause entitled "Subcontracts" of the prime contract andconditioned upon the information furnished by the contractorin support thereof. This consent shall in no way relieve theprime contractor of any obligations or responsibilities itmay otherwise have under the contract or under law, shallnot create any obligation of the Government to, or privitywith, the subcontractor or vendor, and shall be withoutprejudice to any right or claim of the Government under theprime contract. This consent does not constitute a determi-nation as to the allowability of costs.

byAdministrative Contracting Officer

Date 12 Oct. 1973

105

Page 214: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 215: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

MATERIAL

PROCEDURE

#752

9 Nov 72

SOURCE SELECTION PROCEDURE - PLUTO PROGRAM

PURPOSE

To establish a systematic method and define respon-sibilities regarding the evaluation of supplierproposals or information, the selection of sources,and proper documentation thereof.

ATTACHMENTS

A.

B.

C.D.

Basic Procedures for Source Evaluation andSelectionSample, Source Selection and Evaluation SheetSample, Selection Summary ReportGuidelines for Evaluation

BACKGROUND AND GENERAL PLAN :

is to define responsation and source selRSD Policies and Proand ASPR requirementto be used as a geneand is not intendedand requirements fornegotiation, approvasupplier proprietaryformat described hermined beneficial, toprocurement/programsProgram.

The purpose of this procedureibilities and a method of evalu-ection for items consistent withcedures, Pluto Program Objectivess. This procedure is intendedral guide to source selectionto circumvent existing proceduresgovernment audit, analyses,

Is, handling of classified ordata, etc. The techniques and

ein may be modified, as deter-suit the wide variety ofto be expected during the Pluto

SCOPE : This procedure shall apply to all procured materialand support requirements with a total estimated valueof $100,000 or more per program phase or sensitive

Attachment 3

106

Page 216: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 217: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

programs as recommended by the responsible organiza-tions with the approval of the cognizant subcontractmanager.

OBJECTIVES :

A. To establish a uniform method for impartial andcomprehensive evaluation of two or more potentialsuppliers

.

B. To select the supplier(s) who offer(s) the maxi-mum potential for achieving Program objectivesand, based on the combination of Technical,Product Assurance, Management, and cost effec-tiveness will provide the best ultimate programto RSD and our customer.

C. Small Businesses and Minority Businesses shallbe considered.

PRINCIPLE ACTION ORGANIZATIONS:

77-XX76-XX75-XX

RSDRSDRSD

MaterialEngineeringProduct Assurance

It is incumbent on evaluation personnel to utilizethe support services as necessary of any otherorganization deemed necessary to insure the bestanalyses possible.

CONCURRENCE:

This Directive has been coordinated with all Actionorganizations

.

TERMINATION:

This Directive will remain in effect until specifically terminated.

Attach: (A) Basic Procedures For Source Evaluation andSelection

(B) Source Selection Evaluation Sheets(C) Source Evaluation 5 Selection Summary Report(D) Guidelines for Evaluation

107

Page 218: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 219: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

BASIC PROCEDURES FOR SOURCE EVALUATION AND SELECTION

PURPOSE

To establish a systematic method and define responsibilitiesregarding the evaluation of supplier proposals or information,the selection of sources, and proper documentation thereof.

GENERAL

A. The selection of a sufficient number of competent,reliable and financially sound sources prior to solicit-ing proposals will ultimately result in the selectionof a supplier offering the best combination of capabil-ity and cost effectiveness.

B. The ultimate selection of a supplier will be enhancedif the combined skills of Technical and Administrativepersonnel are fully utilized to assure a balancedappraisal of all factors and if the appraisal is con-ducted using systematic methods.

C. Impartial evaluation can best be assured by segregationof the cost and technical portions in order that oneset of criteria cannot influence the appraisal of theother criteria of a proposal.

D. The final selection of a source can best be accomplishedby a board of Technical and Administrative Managementor Supervisory personnel acting independently on thefindings of the evaluation team.

PROCEDURE

A. After completing the data defining a new technicalrequirement, the Engineering Organization will generatetechnical evaluation criteria generally in accordancewith Attachment "B" and with particular emphasis onCompliance to Design Criteria (I.D.).

B. The Engineering Organization will then forward thetechnical data and evaluation criteria to RSD Sub-contracts together with their request for action anda list of recommended suppliers.

C. RSD Subcontracts will organize an evaluation team con-sisting of Engineering, Product Assurance, Material,Program Office, and other personnel as deemed necessaryto assure a comprehensive evaluation.

108

Page 220: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 221: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

D. The evaluation team shall meet for the purpose of review-ing the requirement and mutually establishing the totalevaluation criteria (generally in accordance withAttachment "B") and will prepare instructions to thesupplier that will assure replies totally responsive tothe established criteria. The team shall also reviewprospective suppliers and reach agreement on thesuppliers to be solicited.

E. RSD Subcontracts shall prepare and submit requests tothe selected suppliers in accordance with establishedprocedures together with the response instructionsgenerated by the team.

F. Upon receipt of the supplier responses, RSD Subcontractsshall convene the evaluation team. The members shallestablish action dates for completing the evaluationand reach an agreement on which factors each member willevaluate. RSD Subcontracts will then distribute theapplicable portions of the responses to the team memberstogether with rating sheets and instructions for rating.The rating sheets will contain the criteria mutuallyestablished for evaluation. In order to insure thatvarious considerations are not overlooked and to obtainthe greatest possible objectivity in the evaluation,Attachment "D" should be used as a Guideline forEvaluation. The following rating system shall be useduniformly by each evaluator.

(1) Point ratings from to 10

(a) Excellent - 10 points - meets all requirements -

is beyond what would normally be expected.

(b) Good - 8 points - Unconditionally meets require-ment. Above average.

(c) Fair - 6 points - Not having marked merit ordefect. Generally meets requirements; minimalguidance may be required. Average.

(d) Satisfactory - 4 points - Apparent weaknessesthat nominal assistance can correct. Belowaverage

.

(e) Poor - 2 points - Does not present the desirablequality" Would require maximum assistance.

(f) Unacceptable - points - Supplier apparentlydoes not understand or appears incapable ofmeeting the requirement.

109

Page 222: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 223: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

When more than one member from each Organization partici-pates in the evaluation or when a member calls uponanother person outside the team to assist in all or partof the evaluation, that organization is responsible fordetermining the average score of all participants foreach subfactor and a composite score for each factor.One rating sheet per supplier shall be completed fromeach participating organization and submitted to the RSDSubcontracts representative together with back-up evalu-ation data and justification when deemed appropriate.Each participating organization will assure that allmembers of that organization consent in the final scoressubmitted.

The weighting of each factor will not be determined bythe evaluation members.

G. RSD Subcontracts upon receipt of all evaluation sheetsshall compile the data using Attachment "C" or similar -

Selection Summary Report and submit the report and alldata to the Subcontracts Manager.

H. The RSD Subcontracts Manager will organize and convene aSource Selection Board (SSB) to be established asfollows

:

The level of the Source Selection Board is dependent on(1) the total expected dollar over program life and/or(2) the expected criticality of the evaluated item.

Supervisors - up to $5,000,000 - Modifications of exist-ing conceptsNew techniques/concepts

Dept. Managers - $5,000,000 to $15,000,000 - AdvancedConcepts

Div. Managers - $15,000,000 and over - Extreme advance-ment in state of thearts

.

One member from each of the participating organizations(RSD Engineering, Material, and Product Assurance) willbe selected. Other members may be selected from Finance,Legal, Manufacturing, or other organizations as deemednecessary.

The SSB will be responsible for establishing weightsfor each factor evaluated. These weights will be deter-mined based on the relative importance of each individualfactor. The weights will be determined after allevaluations are complete but before the evaluation scores

110

Page 224: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 225: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

are divulged to the board members. Weighing rangesshould generally be in accordance with the followingbut may vary with a majority agreement of the boardmembers.

Factors Weight Range

1. Technical Approach 8-122. Management 3 or 4

3. Product Quality § Reliability 3 or 4

4. Manufacturing 3 or 4

5. Cost Considerations 1 or 2

After the weights are assigned, the evaluation sheetfrom each participating organization shall be completedby multiplying the weight times the point average foreach factor to arrive at the subtotal score. The sub-total scores for each factor shall be added for thefinal weighted score.

The final weighted scores from each organization shallthen be totalled. The supplier receiving the highesttotal score will be selected. In the event any memberof the board disagrees with the selection, the mattershall be referred to higher management for resolution.

The RSD Subcontract representative shall assure thatall data, justifications, score sheets, and SourceSelection Summaries are maintained and included with anyresultant subcontract.

After approval of the Source Selection, arrange for de-briefing meetings as requested by the unsuccessfulrespondees in accordance with established procedures.

Ill

Page 226: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 227: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

ATTACHMENT B to MP 752

SOURCE SELECTION EVALUATION SHEETS

Item Orgn.

RFQ No. Date

Supplier

Rating Range- 5

I. TECHNICAL APPROACH

a) Grasp of Problem

b) Logic of Approach'

c) Producibility and Economy of Design

d) Compliance to Design Criteria (Attachschedule of analysis)

e) Experience in Similar or Related Fields

f) Qualification of Key TechnicalPersonnel

Total Points

Point Average

Weight X Point Average

Sub Total Score

Rating Range- 5

II. MANAGEMENT

a) Evidence of Good Organization $

Management Practices

b) Qualification of Key Personnel

c) Cost Control Methods

d) Material Management

112

Page 228: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 229: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

e) Program Management _f) EOC Compliance _

Total Points

Point Average

Weight X Point Average

Sub Total Score

Rating Range- 5

III. PRODUCT QUALITY $ RELIABILITY

a) System of Quality Control _b) Configuration Management _c) Reliability Analysis, Planning,

§ Control _d) Quality and Reliability Organization _

Total Points

Point Average

Weight X Point Average =

Sub Total Score

Rating Range- 5

IV. MANUFACTURING

a) Research $ Development Facilities _

b) Production Facilities _c) Production Planning $ Control _d) Rate Capability _

Total Points

Point Average

Weight X Point Average =

Sub Total Score

113

Page 230: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 231: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

Rating Range- 5

V. COST

a) Approved Accounting System

b) Cost vs. Effort

c) History

d) Willingness to Submit Cost Data

Total Points

Point Average

Weight X Point Average

Sub Total Score

FINAL WEIGHTED SCORE

Back-Up Sheets Attached

Evaluators

Narrative Justification Attached

Orgn.

Mgr. Approval Date

114

Page 232: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 233: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

J<HOE-

<E-OE->

ATTACHMENT C TO MP 7 52

<HOE-

ftQi

Pi

+J

OCO

*-i

+J

GOO.O

CO

Oi—

i

E-<S3

<>WWu

oCO

GO•HMft

•i-l

O10

oOE(1)

CJ3

5

-J<HOH

PiWacE-O

J<i—

i

WE-

<ft

o Pio o(h E-3 UO <W ft

>

w

>

<HOH

w33HO

<PiWH<

ft

o

3o

> >

w

><

J<HOH

PiWE-O

.-J

<t—

i

Piw

ft

(J

u3oCD

>

115

Page 234: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 235: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

<HOH

4->

co

Hoa,w

>~

oy—i

HUWw

zoI—

I

H<

wwu

oto

o

PJ>

J<oE-

wa:Ho

I—

I

w

zw

oHU<

>

116

Page 236: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 237: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

ATTACHMENT D to MP 752

GUIDELINES FOR EVALUATION

Prospective sources will almost always initially be evaluatedon the basis of five primary factors:

1) The technical approach2) Management3) Product quality and reliability4) Manufacturing5) Cost

In the majority of cases, all five factors will be involvedin the selection; however, the relative importance of thefactors, and therefore their assigned weights, will vary fromone request to another.

In order to obtain the greatest possible objectivity in theevaluation, these primary evaluation factors are not rateddirectly, but in terms of detailed supporting subfactors.For example, rather than evaluate directly on the basis ofthe technical approach, the evaluation will list such sub-factors as grasp of the problem, logic of approach, etc.Similarly, rather than to attempt to evaluate "Management"as a single factor, the evaluator will develop a detailedevaluation plan which would include such subfactors asevidence of good organizational and management practices,qualifications of personnel, etc. If the procurement con-templates a second phase which will not be contracted forimmediately, and separate information is required on thesecond or succeeding phases from the bidders, a separateevaluation plan will be developed for each of the phasesinvolved, which will take into consideration the effect ofthe various phases on each other.

Selection of Subfactors

The selection of supporting subfactors for each of the fiveprimary evaluation factors will vary depending upon thenature of the work required. The following tables comprisea guide to the selection of appropriate subfactors. It isthe responsibility of the evaluating personnel responsiblefor the procurement to determine the specific subfactorsrequired.

Only such subfactors shall be included as are necessary anddesirable for adequate evaluation. While the more subfactorsthat are included the more objective will be the evaluation,no factors should be included which are not necessary toevaluate the specific procurement in question. Neither

117

Page 238: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 239: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

should subfactors be included covering the mandatory aspectsof the procurement. For example, the compliance of bidderswith proprietary rights requirements or with mandatorydelivery schedules, since proposals are normally eitherresponsive or non-responsive to these requirements and thereis usually no permissible graduation of compliance.

The inclusion of a large number of subfactors to which allbidders must comply if their proposal will be consideredhas the effect of leveling the final technical rating so thatthe point spread between the best and worst proposal willbe deceptively small. To be of greatest possible value, theevaluation plan should be designed to result in the greatestpossible point spread between good and poor proposals.

CONSIDERATION FOR EVALUATION

I. Technical Approach

a. Grasp of ProblemConsiderations

:

1. Does the proposal recognize and differentiatebetween the simpler and more difficult perfor-mance requirements?

2. Does it evidence recognition of inherent main-tenance and supply problems?

3. Does it demonstrate an awareness of human andenvironmental factors affecting the scope ofwork?

4. Does it evidence a recognition of relationshipswith other contractors and agencies, and thecoordination and liaison problems involved?

5. Is the estimate of professional, technical, andadministrative manpower requirements in conso-nance with the project requirements? Is therea reasonable balance between professionalpersonnel and technicians?

6. Is there evidence of appropriate utilization ofscientific and professional personnel; or con-versely are technicians offered where highlyqualified professional specialists are required?

b. Logic of Approach

1. Does the proposal convincingly show a depth ofunderstanding of the problem?

118

Page 240: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 241: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

2. Is there a brief discussion of alternate solu-tions which were explored and rejected and thereason for their rejections?

3. Is there a discussion of technical approaches tobe explored and why the company's approach maybe expected to yield the desired results?

4. Does the Proposal respond to the RFP requirementswithout unnecessary additional or differentproblems?

5. If the Proposal contemplates more effort thanrequested in the RFP, has the additional effortbeen justified on the basis that it is technic-ally and economically desirable?

6. Does the Proposal commit the company to require-ments that can be accomplished, or are therepotential cost or technical problem areas?

7. Have unrealistic and unreasonable performancerequirements been identified and alternativessuggested?

8. In event of deviations or alternates is thedetailed logic for these recommendations given?Especially in terms of benefits, such asenhanced performance, lower costs, greaterproducibility, earlier delivery and simplermaintenance?

9. In the event that certain problem objectivesare to some extent incompatible with otherproblem goals, (e.g. simplicity vs. accuracy)does the proposal unequivocally show that theoptimum solution, all factors considered, hasbeen attained?

10. Have the more difficult areas been identifiedand detail provided showing how performancerequirements never before achieved will be met?

Producibility § Economy of Design

1. Have self -checking features been considered inthe proposal?

2. Are high mortality components intended to beeasily accessible and fully interchangeable?

119

Page 242: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 243: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

3. Are requirements for special tools, fixtures andtest equipment expected to be minimal?

4. Has consideration been given to simplicity,degree of risk, logistics, compatibility,environmental factors, reliability, vulnerability,maintainability, operability, test and evaluation,training or other manpower factors?

d. Compliance to Design Criteria

1. If originality has been spelled out as a require-ment, does the Proposal represent a unique,imaginative approach?

2. Is there a description of novel ideas or technicalapproaches?

3. Is there a statement of major technical problemswhich must be solved with an indication as tothe amount of effort budgeted to each?

4. Is the relation of proposed solution to thebroader over-all system with which it willoperate shown?

5. Is there a clear, concise statement of thetechnical requirements which the proposalfulfills?

e. Experience in Similar/Related Fields

Simply listing the programs that the firm has workedon is not sufficient. The examples provided shouldexplain specifically how the experience gained in theprevious contracts is related to the work calledfor by the Proposal.

1. Does the proposal give specific examples ofsimilar projects successfully completed?

2. Is information provided as to the relation ofthe proposed hardware to existing or previousprograms which the company has done for othercustomers, indicating the customer, project, andfunds already spent?

3. Do the biographies relate specific experienceof personnel to the specific needs of thisproject? Has extraneous biographical informationbeen eliminated?

120

Page 244: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 245: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

4. Is the normal commercial or Government businessof the offeror closely related to the proposedwork?

5. Is the offeror experienced with practices andprocedures of the contracting agency to an extentwhich would increase the effectiveness of hisperformance?

6. Does the company enjoy a respected reputationin the field to which the proposal relates?

7. Does the company have Hi-Rel and ControlledLine experience?

II. Management

a. Evidence of Good Organization § Management Practices

1. Does the Supplier have an approved Equal Oppor-tunity Program (Certificate)?

2. Does the proposal outline the type of managementto be provided for the project, viz: whether aspecial management group will be formed orwhether there will be company-wide participation?

3. Does the proposal demonstrate that top-levelmanagement will continue a high level of interestand assume responsibility for successful accom-plishment of the program?

4. Does the proposal provide convincing evidencethat the company is properly oriented and organi-zationally structured to meet the specificmanagement needs of this project? Especially interms of providing the requisite functions ofcommunication (internal and external) and ofintegration of all project phases and pieces?

5. Is evidence given of management's understandingof how the specific project fits into thecustomer's over-all needs?

6. Does the proposal indicate that management firsthas taken a completely objective and detachedlook at the entire problem prior to thinking interms of specific solutions?

7. Is it clear that management has honestlyexamined its own areas of competence andincompetence?

121

Page 246: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 247: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

8. Are details provided on management objectives,policies, participation, and reliability concepts?

9. Does the proposal show the capabilities of themanagement to handle a project of the sizecontemplated?

10. Is evidence given that top-level management hasfull control of its organization?

11. Does the proposal show the position of the pro-gram manager or group in the over-all companyorganization and the limits of authority andresponsibility?

12. If no over-all group is to be formed, does theproposal show the method of operation within theover-all company structure?

13. Does the proposal delineate the requisitenumbers (neither over-or-under managed) of theright types of management people?

14. Where organizational charts are presented, isit clearly shown how the project management willoperate effectively on a day-to-day basis?

15. Is information furnished as to the type, frequency,and effectiveness of management controls andmethods for corrective action?

16. Do the manpower buildup charts clearly explainthe methods of manpower acquisition, particularlyskilled manpower requirements?

17. Is a total manpower plan and individual plansfor engineering, manufacturing and qualitycontrol furnished?

18. Is information furnished showing how the presentproject will phase in with current and futurebusiness?

19. Does the proposal evidence the breadth and depthof management capability appropriate to theproject? Is there evidence of stability of jobtenure in upper management echelons?

Qualification of Key Personnel

1. Does the proposal include definite plans for theassignment of specific key personnel?

122

Page 248: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 249: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

2. Do assigned key personnel possess the experi-ence, educational background and record of pastaccomplishment appropriate to the scope of work?

3. Is the quality of personnel as set forth in theproposal generally supported by the salary scales?

4. Is the proposal dependent upon any substantialrecruitment of key personnel? If so, would suchrecruitment result in high cost of performance,or might it adversely affect other vital con-tracts in the geographical areas of the offeror?

5. Is the success of the project excessivelydependent upon subcontract or temporary consul-tants? If so, to what extent are subcontractplans firm and reasonably irrevocable?

6. Are details provided on corporate experience,facilities and personnel?

Cost Control Methods

1. Does supplier have an approved system(s) forcost reimbursement contracts?

2. Have excessive costs or time delays required tomeet certain specific requirements been clearlypointed out?

3. Are overhead and burden rates and fees com-pletely reasonable for this type of project?

4. Has consideration been given to the dollar valueplaced on the project by the customer and thefunds available for it?

5. If there were significant cost over-runs, werethey due to an incompetently low initial costestimate, or to valid problems which could nothave been anticipated?

6. Does the company have adequate financialresources?

Material Management

1. Does offeror have an approved procurement system?

2. Is a Make or Buy Program provided?

3. Is evidence given that supports the selection ofsubcontractors - not only from the standpoint

123

Page 250: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 251: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

of their technical and manufacturing capabili-ties, but also their management philosophy andtalents?

4. If the proposal involves systems management, doesthe proposal show how the subcontractor'smanagment will be integrated into the program?

5. Are organization charts furnished of first andsecond tier subcontractors which show clearlytheir relationship to the prime and to othersubcontractors?

6. Is evidence given of the complete support of thesubcontract management for an arrangement whereinthe company would be the system manager?

7. If subcontractors will be used for major partsor subsystems, is a copy of their proposal fur-nished or evidence to show their proposal hasbeen properly developed and evaluated?

8. Has provision been made for horizontal consul-tation between subcontractors?

e. Program Management

1. Does the proposal clearly demonstrate an under-standing of the customer's concern with themanagement of this project?

2. Does the proposal provide convincing assurancethat the customer's delivery dates will be metor bettered?

3. Is sufficient detail regarding master scheduling,programming, follow-up, and other like functionsgiven to reinforce the foregoing assurance?

4. Where subcontractors and major suppliers areinvolved, are sufficient safeguards built intoproposed scheduling system to insure sub-schedule compliance with master program?

5. Is it a certainty that manhour, space, facilityand other cost factors have not been over-estimated?

6. How does the proposed task organization integrateinto the overall organization in terms ofeffective lines of authority and communication,

124

Page 252: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 253: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

and in terms of effective integration of re-search, development, design, drafting, technicalwriting, reliability and test functions.

7. Does the proposal demonstrate detailed andrealistic scheduling of the various technicalphases of the project?

8. Does the proposal demonstrate effective review,evaluation and control at specific check-points?

9. Are proposed schedules in line with availablepersonnel resources?

10. Are parallel investigations proposed on criticalproblems, and avoided on more routine problems?

11. Are breadboard tests planned early in the programin vital design areas?

f. EOC Compliance

1. Does the supplier have an approved Equal Oppor-tunity Program (Certificate)?

III. Product Quality $ Reliability

a. System of Quality Control

1. Does the proposal describe the company'squality control plan including organization,policies, facilities, operational system, tech-nical capabilities, and records systems levelof Government approval?

2. Is it clear that the customer's quality controlrequirements will be achieved by the company'squality control system, organization, conceptand approach?

3. Are deviations from customer requirements satis-factorily explained?

4. Does the proposal show that customer reliabilityrequirements can be achieved by the company'sconcept and approach, including a specific pro-gram for meeting or surpassing these requirements?

5. Is it clearly shown how the reliability organi-zation and project responsibility fit into theproposed program?

125

Page 254: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 255: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

6. Are reliability monitoring points (breadboard,experimental development, service test, prototypeand production) clearly delineated so thatcustomer surveillance may be effectivelyexercised?

7. Does the proposal show an understanding ofreliability prediction techniques and spell outin detail how predicted goals will be met?

8. Is creative ingenuity reflected in the proposalby pointing out reliability approaches to parti-cular development phases?

9. Does the proposal discuss the company's facili-ties and measuring equipment?

10. Are sub-tier supplier controls satisfactorilyexplained?

11. Does the proposal reflect the process controltechnique (s) used by the Quality and Reliabilityorganization?

12. Does the proposal indicate an awareness ofrequirement for special test/measuring equipment?

13. Certification of personnel (special proceses,NOT, functional test, etc.).

14. Control of materials.

15. Quality review of designs and design changes.

16. Control and segregation of discrepant material -

MRB.

17. Metrology System and Calibration Control.

18. System for selection and control of sub-tiers.

19. Does Manufacturing or Quality have control overfunctional testing?

20. Does the company have a corrective action program?

21. Does the company permit RSD and GovernmentSource Inspection?

Configuration Management

1. Does the supplier have a configuration managementprogram?

126

Page 256: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 257: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

c. Reliability

Considerations

:

1. Is proposal based on proven components andtechniques?

2. Is redundancy provided in critical functionalfeatures?

3. Will design be based upon "worst case" analysis?

4. How are theoretical reliability analyses andreliability testing integrated into the designprogram?

d. Quality and Reliability Organization Structure

1. Does the organization chart provide for aQuality and Reliability management reportingstructure?

2. Does the proposal reflect awareness of allrequired Quality functions (Tool Inspection;Testing Organization; Metrology; NDT; SpecialTraining, etc.)?

IV. Manufacturing

a. Research and Development Facilities

1. Are the proposed laboratory pilot manufacturingand test facilities adequate for the require-ments of the Technical Scope of Work?

2. Are the proposed facilities conveniently avail-able to engineering personnel?

3. Is the proposal contingent upon Governmentfurnished capital equipment beyond that set outin the RFP?

b. Production Facilities

1. Does the proposal present adequate evidence ofthe existence of physical plant, personnel, andfinancial resources to permit transition fromdevelopment to production?

2. Do other mobilization planning commitments ofthe offeror preclude proposed production of theitem under mobilization conditions?

127

Page 258: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 259: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

3. Does the close proximity of a production facil-ity reflect in valuable feed-back to developmentengineers? If so, is the production orientationof development engineers of significance to thesuccessful completion of the proposed work?

c. Production Planning d, Control/Rate Capability

1. Does the proposal describe the company'smanufacturing organization responsibilities,tool policy and plan, fabrication and assemblyplan?

2. Does the proposal explain the system and pro-cedures used for schedule planning and operationalcontrols?

3. Does the proposal provide convincing assuranceof specific manufacturing competence in termsof this project? Does the biographical datarelate to the specific experience of the manufac-turing people to the specific work areas of thisproject?

4. Does the proposal clearly indicate the varyingavailabilities of these manufacturing people tothe project? If subcontractors and/or consul-tants are involved, does the proposal provideassurance of their availability?

5. Does the proposal clearly indicate that thecompany has adequate manufacturing space andfacilities, both general and special, to per-form the work efficiently and on schedule?

6. Are specialized equipment and processes requiredfor the project given sufficient prominence inthe proposal?

7. Does the proposal clearly delineate the workflow paths from the time the engineering is

released to the time that items are shipped?

8. Does the proposal show evidence of an effectivemanufacturing control system?

9. Does the proposal indicate a clearly definedprocedure under which the company can movequickly to meet any emergency with a minimum ofprogram disruption?

10. Does the proposal specifically state that allrequired facilities are available for the project

at this time?

128

Page 260: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 261: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

11. Does the proposal provide evidence that the companyutilizes the most advanced methods in its manufac-turing and manufacturing support areas?

V. Cost

a. Approved Accounting System

1. Does the Supplier have an approved accountingsystem for cost reimbursement type subcontracts?

b. Cost vs. Effort

1. Is this the lowest possible price? Considering(a) long-range potential vs. immediate return;(b) probable competitive price range?

2. Is the extent of pricing detail given consistentwith the importance of these details?

3. Is there complete satisfaction that subcontractorsand vendors have submitted their lowest realisticcost estimate?

c. Willingness to Submit Cost § Pricing Data to RSD

1. Does the Supplier conform to Public Law 87-653?

129

Page 262: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 263: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

ENCLOSURE NO. 1 to RFP Dated 17 April 1973

RSD's responsibility to cognizant Government agencies requiressubmission of data sufficient and complete enough to substan-tiate the subcontractor's proposals in relation to effortrequired based on the proposed Work Statement or items listedon Request for Proposal (RFP) and to permit evaluation of theelements within the overall intended price.

1. REQUIREMENTS

RSD rquests your (FFP) proposal to accomplish the effortand objectives set forth in the following documents:

1.1 Statement of Work Number R398XL2 dated 26 March1973 (Attachment No. 1) including provisions, spe-cifications, and requirements contained orreferenced therein.

1.2 Inspection and Quality Assurance Requirements(Attachment No. 2).

1.3 Materials Handling and Packaging Standards (Attach-ment No. 3)

.

1.4 Subcontractor/Supplier Special Tooling Requirements,RSD D054159, dated 18 May 1972 (Attachment No. 4).

1.5 Subcontractor/Supplier Special Test EquipmentRequirements, RSD DO54160, dated 18 May 1972(Attachment No. 5).

1.6 Reports Requirements Exhibit (Attachment No. 6).

1.6.1 Proposal Information Instructions forContract Budget System (Attachment No. 7).

1.7 Design Disclosure Data and Configuration Management(Attachment No. 8).

2. PROPOSAL

The proposal shall be submitted in separate volumes asfollows

:

2.1 Technj cal The Technical Proposal shall contain,but not be limited to, the information delineatedand requested in Attachment No. 9, TECHNICAL PROPOSALREQUIREMENTS.

2.2 Management. The Management Proposal shall contain,but not be limited to, the information delineated

Attachment 4

130

Page 264: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 265: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

and requested in Attachment No. 10, MANAGEMENTPROPOSAL REQUIREMENTS. Information furnished pur-

. suant to this requirement may either be submittedas a separate volume, or may be included as a partof 2.1 above.

2.3 Cost A detailed Cost Proposal responsive to therequirements of Attachment No. 1 and prepared inaccordance with the instructions set forth inAttachment No. 11, COST PROPOSAL INFORMATIONINSTRUCTIONS, shall be submitted on the appropriateContract Pricing Proposal (DD 633) (Attachment No.12) . Failure to use this Contract Pricing ProposalForm may result in the rejection of the proposal.Cost proposals submitted pursuant hereto must beseparated from technical proposals.

2.3.1 In the event of an award resulting from this

proposal, the successful bidder shall berequired to execute a Certificate of CurrentCost or Pricing Data on Form 8525C(Attachment No. 13), prior to the issuanceof a definitive subcontract.

2.3.2 The proposal shall include a standardContingency Fee Statement in accordance withASPR 1-506.1.

2.3.3 The mandatory prime contract flowdownprovisions for compliance with the CostAccount Standards applies to all non-exemptprocurements under Government contract.Attachment No. 14 is included for yourexecution and return with your proposalpursuant to the provisions of ASPR SectionIII, Part 12.

2.4 General Proposal shall include the followinginformation:

2.4.1 Corporate legal name, state in which incor-porated, and complete address.

2.4.2 Name, address and telephone extension of:The individual empowered to negotiate the

proposal

;

The individual having technical responsi-bility for the project; and

The individual having contract administra-tion responsibility for the subcontract.

131

Page 266: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 267: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

2.4.3 Name and address of Government office havingcognizance of:

Contract Administration Services (ACO)Property AdministrationSecurityAudit.

2.4.4 Level of Security clearance in effect withrespect to the plant and the names andaddress of the Government office whichissued such clearance.

2.4.5 Date of approval of your accounting andproperty control system and name of Govern-ment office providing such approval.

3. TERMS § CONDITIONS/SPECIAL PROVISIONS

3.1 Terms and Conditions (FP-D2) dated 15 December 1971(Attachment No. 19) applicable to Firm Fixed Pricesubcontracts shall apply to any subcontract issuedas a result of the proposal required. Should youtake any exception to any article in the Terms andConditions, such exceptions shall be clearly statedin the proposal.

3.2 If applicable, the appropriate Clause Group(s)in Attachment No. 15, Additional Terms and Conditionsof Purchase, (Form 966EE April 1972) will be includedin any subcontract award pursuant to this proposalrequest.

3.3 All procurements for an estimated or actual valueof $1,000,000 or more require the execution ofSection I and the return of one (1) copy of Form1588X-3, EQUAL OPPORTUNITY COMPLIANCE REVIEW §

CLEARANCE, (Attachment No. 16) with your proposalas a condition of award.

3.4 Restricted or Proprietary Data Proposal shallclearly indicate areas and extent of restricted dataor proprietary information contained therein. Theappearance of any statement on any material or datasubmitted hereunder will not establish a confiden-tial relationship between the submitter and Rocketand Space Division, Inc. unless a specific writtenagreement to this effect is negotiated prior to thesubmission of the data or the statement appearingon the data is in the form of the Rocket and SpaceDivision Inc. standard legend as follows:

132

Page 268: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 269: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

"This proprietary information, furnished inresponse to R-364A61 shall not be disclosedoutside Rocket and Space Division Inc. or beduplicated or used in whole or in part exceptCI) to evaluate offeror's proposal or (2) toinclude the information in an RSD proposal toa customer provided the information is includedwith an appropriate restrictive legend. If asubcontract or a purchase order requiring useof this information is awarded to this offeror,RSD shall have the right to duplicate, use ordisclose this information except to the extentprovided otherwise in the subcontract onpurchase order. This restriction shall notapply to information which is already in RSDor Consolidated Industries' possession at thetime of submission, is or later falls withinthe public domain, is obtained by RSD fromanother source, or has been or later is dis-closed by offeror to others on an unrestrictedbasis."

3.5 Acquisition of Data Rights In the placement ofcertain specified subcontracts, RSD is required byprime contract provisions to inform bidders thatany limitations on the use of technical data willbe considered as one element in the evaluation ofproposals along with other factors such as qualityof design, experience, cost, etc. If technicaldata is specified to be delivered pursuant to theproposed procurement and Attachment 17 is specifiedas being applicable, the proposal must be incompliance with that Attachment.

3.

6

Rent-Free Use of Government Production and ResearchProperty

-

3.6.1 No facilities, special test equipment,special tooling or standard componentsthereof will be furnished by RSD for theperformance of the proposed procurementother than those set forth in AttachmentNo. 1.

3.6.2 If your proposal is based upon rent-freenoninterference use of Government produc-tion and research property in your plant,the following information is required:

Accountable prime contract(s)Date of contract (s) and expiration date

133

Page 270: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 271: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

Cognizant Administrative Contracting Agency(Name and Address)

Specific item(s) of property requiredidentified as follows:

Gov't/Sub-Contractor Year of Acquisition

Contract Description ID/Tag Number Manufacture Cost

Additional costs for use of property ifnot provided on a rent free basis.

3.7 Government-Furnished Material List Government-Furnished Material Requirements, if any, in yourproposal.

3.8 Security If this RFP involves classified defenseinformation or material, such information ormaterial and all subsequent classified data ormaterial forwarded for use or generated in theperformance of the subcontract shall be safeguardedin accordance with the Industrial Security Manual(DD 411) and specific instruction contained in theContract Security Classification Specification(DD 254) (Attachment No. 18).

3.9 Inspection and Quality Assurance Inspection andacceptance of the products to be fabricated anddelivered under the proposed procurement will beat RSD's Prunedale plant unless otherwise stated.The Quality Assurance and Inspection Requirementsare annotated on Attachment No. 2 and will be madea requirement of any subcontract or purchase ordercommitment made as a result of this RFP, and anyprice associated with the implementation thereofshall be included in your quotation.

3.10 Utilization of Small Business Indicate in yourproposal whether you are a Small Business concernand include a statement in regard to your policyon utilization of small business.

3.11 Labor Surplus Area Indicate in your proposalwhether the plant (or Plants) in which the pro-posed work will be performed is in a labor surplusarea and provide the category classificationthereof.

3.12 FOB Point Unless otherwise stated, articles shallbe delivered FOB, Rocket and Space Div., Inc.,Prunedale, New York.

134

Page 272: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 273: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

3.13 Royalty When the response to this Request forProposal contains costs or charges for Royaltiestotaling more than $250.00, include in yourproposal the information required by ASPR,Paragraph 9-110(2) (3).

3.14 Submittal In order to be properly considered,twenty ["20) copies of your proposal shall besubmitted to the following address on or before4 June 1973 .

Rocket and Space Division, Inc.Post Office Box 309Prunedale, New York

Attention: Mr. J. GreenBuilding: 802A

3.15 All bidder requests for information in regard tothis RFP must be directed in writing to theresponsible Material representative indicated inParagraph 3.14 above. Direct contact with RSDpersonnel other than the responsible RSD Materialrepresentative may result in disqualification ofyour proposal. The question(s) and RSD's answer(s)will be made available simultaneously in writingto all bidders solicited under this RFP.

ACCEPTANCE/VALIDITY

4.1 While a Firm Fixed Price (FFP) proposal is requestedand anticipated, RSD reserves the right to negotiatea multiple incentive Fixed Price Incentive (FPI)subcontract prior to award.

4.2 RSD reserves the right to accept other than thelowest quotation and/or to reject any or all pro-posals. RSD may accept any item, or group ofitems, contained in your proposal unless qualifiedby your specific limitation. This RFP is not a

commitment by RSD.

4.3 RSD requests that you certify your proposal to bevalid for a period of not less than 180 days.

135

Page 274: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 275: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

Enclosure (1) to RFP

ATTACHMENTS

1. Work Statement Number R398XL2 RevDated 26 March 1973

2. Inspection and Quality Assurance Requirements

3. Materials Handling and Packaging Standard

4.

5.

Subcontractor/Supplier Special ToolingRequirements (D054159)

Subcontractor/Supplier Special TestRequirements (DO54160)

6. Reports Requirements

7. Contract Budget System (CBS) InformationInstructions

8. Design Disclosure Data and ConfigurationManagement

9. Technical Proposal Requirements

10. Management Proposal Requirements

11. Cost Proposal Information Instruction

12. Contract Pricing Proposal (DD Form 633)

13. Certificate of Current Cost or PricingData (Form 8525C)

14. Cost Accounting Standards Clause

15. Cost or Pricing Data and Audit Clauses

16. Equal Opportunity Compliance Review andClearance

17. Request for Information on Acquisitionand Price of Data

18. Contract Security Classification Specifica-tion (DD 254) dated

19. Terms and Conditions

APPLICABLE

136

Page 276: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 277: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

Attachment No. 9

TECHNICAL PROPOSAL REQUIREMENTS

The Technical Proposal shall contain, but not be limited to,

the following sections:

1. INTRODUCTION

A summary stating the reasons for the selections of the

design, materials, components, etc., for the desired

item.

2. SPECIFICATION REVIEW

Discuss, in detail, all specifications considered and

particularly note any specifications which cannot be met

or require exceptions.

3. TECHNICAL MILESTONE CHART

Provide a detailed Technical Milestone Chart for each

Phase of the program, including starting and completion

date.

4. TEST PROGRAM DEFINITION

Describe the test program to be utilized, which will

proof the design of the item.

5. DESIGN DISCLOSURE

Provide necessary information and/or design disclosure

plan, including list of documents to be utilized for the

design disclosure, i.e., drawings, specifications, test

procedures, test plans, data lists, etc.

137

Page 278: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 279: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

6. RATE CAPABILITY

The proposal shall indicate tooling requirements (both

soft and hard) and additionally the bidder shall indicate

his maximum monthly rate capability to support a produc-

tion program based on an 8 hour day, one shift, five days

per week utilizing hard tooling.

138

Page 280: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 281: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

Attachment No. 10

MANAGEMENT PROPOSAL REQUIREMENTS

1.0 PERSONNEL, ORGANIZATION, MANAGEMENT

1.1 Indicate the names of key management, scientific,

and engineering personnel who will be assigned to

this program. Indicate how all personnel assigned

to this program will be organized and how this

group will be related to the present organization.

1.2 Discuss manufacturing, producibility, quality §

reliability, and cost control, as related to this

program.

1.3 Discuss system for complying with PRODUCT

ASSURANCE REQUIREMENTS of Attachment 2 to

Enclosure I.

1.4 Provide general information relative to union

labor agreement, i.e., with whom, duration, and

dates, etc.

2.0 SUBCONTRACTING

2.1 Describe company policy as it pertains to sub-

contracting including basis for policy, provisions

for management review, and control of subcon-

tractors, furnish description of purchasing

system. Provide a list of major subcontract

activity as applicable to this program, indicat-

ing your supplier's input to your proposal.

139

Page 282: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 283: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

2.2 Develop and provide a "make or buy" plan supported

by policies and procedures for such development in

general accordance with ASPR 3-902.

3.0 PROGRAM PLAN

3.1 Provide a simplified PERT Program Plan Event

Chart. This chart, as a minimum will indicate all

significant events in the design, documentation,

fabrication and test phases. Such a chart will

also include a proposed work order structure.

3.2 In support of this chart a narrative program

plan shall be provided, which shall describe in

detail how you propose to accomplish each event.

4.0 FACILITIES

Each response will be evaluated on the basis of

responder's inclusion of data and plans which

outline equipment that is in his possession, is

applicable, available and in sufficient quantities

to meet the requirements of the program on a non

interference basis. Additional consideration

factors include: outline of new equipment

required in support of task definition,

anticipated subcontract effort, and essential

requirements in support of potential production

effort.

140

Page 284: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 285: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

Attachment No. 11

COST PROPOSAL INFORMATION INSTRUCTIONS

(Accurate, Complete, and Current Cost or Pricing Data)

1. The Cost Proposal must include a completed, signed, anddated Contract Pricing Proposal (DD Form 633) - or otherappropriate form in the DD Form 633 series - which bearsthe printed "Instructions to Offerors" on the reverseside. Each Cost Proposal and each supporting documentmust be identified to the Request for Quotation (RFQ)or Request for Proposal (RFP) and to your proposal.

2. The following signed statement must accompany the CostProposal. "A Certificate of Current Cost or PricingData, in the exact format prescribed by RSD, will besigned and submitted to RSD at the conclusion of negoti-ations". A copy of the certificate is included withthe RFQ or RFP.

3. If you propose to use government -owned property (facili-ties, special tooling, special test equipment), preparethe Cost Proposal upon the assumption that rent-freeuse of the government-owned property will be granted.In your transmittal furnish an estimate of the amountyour proposed price would be increased if rent-free usewere not approved.

4. If you propose to request the inclusion of a provisionrelieving you from liability for loss or destructionof or damage to Government property, you should prepareyour proposal on the assumption that approval willnot be granted. In your transmittal, indicate the'amount by which the subcontract price may be reduced ifsuch approval were to be granted. Also, indicatewhether the proposed cost for insurance to coverGovernment property will be a direct subcontract costor an overhead cost. You should also indicate whetheryou obtain relief from liability for Government propertyfrom the Government under prime contracts and underother subcontracts.

5a. In addition to the total cost proposal, furnish costbreakdowns for each task, priceable item, or workpackage, as specifically called for by the Request forProposal. (See Attached Addendum Sheet.)

141

Page 286: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 287: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

6a. The REFERENCE column of DD Form 633 must specify anattachment by line item in order to identify andestablish traceability to the supporting data actuallysubmitted with the proposal or specifically identifiedin writing. Refer to DD Form 633, Footnotes, NOTE 3.

6b. Your proposal must provide the rationale and basesfor your proposal. Such bases, for example are: (i)existing or verifiable data, (ii) judgmental factorsapplies to projecting from known data to the estimate,or (iii) contingencies used in the proposed price.Data submitted or identified must be verifiable. Theactual data for a like or similar effort from whichestimates are projected must be submitted or identified;methods used in cost projections (such as improvementcurves, elimination of task, etc.) explained; and themethod used to develop the estimate revealed. Contin-gencies must be explained, and the method of pricingdetailed. When physical submission is impractical, thedocumentation, data, or information must be describedin your proposal, adequately identified, includingphysical location and made available for inspection byRSD or the government upon request. Necessary devi-ations from these instructions which result from youraccounting system should be detailed and explained asan integral part of your cost proposal. All cost orpricing data submissions must be updated with the mostcurrent, accurate, and complete data prior to finalagreement on price. In all instances, be prepared tomake the records upon which your proposal is basedavailable to authorized RSD or government personnel inaccordance with Instruction 5 on the reverse side ofthe DD Form 633.

6c. In the event that one or more subcontracts or purchaseorders in excess of $100,000 will be placed with lower-tier suppliers, certified accurate, complete, and current'cost or pricing data and a Contract Pricing Proposal(DD Form 633) must be obtained from the lower-tiersupplier for each such procurement. If the award willbe exempt from the provisions of ASPR 3-807 because theprice will be based on established catalog or marketprices of commercial items sold in substantial quanti-ties to the general public, or prices set by law orregulation, a "Claim for Exemption from Submission ofCertified Cost or Pricing Data", DD Form 633-7 will berequired. You must perform an evaluation and analysisof the submitted DD 633s or 633-7s as may be appropriatein the particular circumstances and you will be requiredto make such data, including your analysis thereof,available to RSD in order to permit an evaluation ofthe proposed lower-tier price. If a DD 633-7 is receivedfrom a lower-tier supplier in support of a claimedstatutory exemption, it will be your responsibility to

142

Page 288: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 289: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

review and evaluate the claim, obtain additional dataif required, verify sales information as necessary,and perform that price analysis necessary to concur withthe exemption claim and the reasonableness of price.When a supplier submits a DD Form 633-7 exemption claimfor an offer in excess of $100,000. and when more thanone catalog item for which an exemption is claimed isincluded in such offer, an additional DD Form 633-7 shallbe submitted for each catalog item for which the pro-posed price is $10,000 or more. All DD Forms 633-7submitted to you by your suppliers must be submitted toRSD with your proposal.

7. Cost breakdowns and backup information required hereinmust be provided in detail as follows: (Parentheticalreferences are to the DD Form 633 cost elements)

.

a. Purchased Parts and Raw Material (l.a. and I.e. (1))

Submit a bill of materials or itemized listingfor each category, showing:

(1) Known or anticipated sources.

(2) Quantity and the basis for determining thequantity, exclusive of load factors (see (5)below)

.

(3) Description and Part Number, with manufacturer'snumber, if available.

(4) Unit price and basis for determining it. Describecompetition obtained and the basis of establish-ing the source and reasonableness of cost.Reference supporting documents such as purchaseorders, supplier quotations, or invoices.Indicate quantities for each purchase orderor quotation as well as the reference number.Be prepared to furnish copies of such documentsupon request.

(5) Load factors such as scrap rates, attrition,manufacturing spares, shrinkage, materialburden, etc., together with their bases ofcomputation. Show each such factor and support-ing basis as a separate item.

(6) Indicate parts which are purchased in largelots or under corporate agreements and othervolume discounts.

143

Page 290: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 291: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

(7) In the event materials estimates are not basedupon a bill of materials or itemized list,present the statistical data forming the basisof estimate. This is to be in comprehensiveform and should support the estimated cost.

7b. Subcontracted Items (l.b.)

List all lower-tier subcontracts, showing:

(1) The names of the potential or actual subcontractors.

(2) Description of items of work to be subcontracted.

(3) Quantities of deliverable units.

(4) Unit price, and basis for determining it, withreference to supporting documentation such asprevious purchase or quotation (identify) , astatement indicating whether or not negotiated,and type of subcontract contemplated. Be preparedto provide copies of documentation upon request.

(5) Target price, ceiling price, sharing plans, incen-tives, etc., of lower-tier subcontracts used inestimates

.

7c. Standards Commercial Items (I.e. (2))

These are items normally fabricated and stocked by youand priced at catalog or commercial market prices.Provide or identify catalog or price lists and suffici-ent sales information (commercial customers' names andquantities purchased, sales in dollars, or percent oftotal sales) to establish the commercial identity ofthe item. Submit an executed "Claim for Exemption fromSubmission of Certified Cost or Pricing Data" (DD Form-633-7) if the price quoted or catalog price exceeds$100,000. If the quotation is based on a catalog price,provide cost data covering the difference. When a DDForm 633-7 exemption claim for an offer is in excess of$100,000, and when more than one catalog item for whichan exemption is claimed is included in such offer, anadditional DD Form 633-7 must be submitted for eachcatalog item for which the proposed price is $10,000 ormore.

7d. Interdivisional Transfers (3. and I.e. (3))

Support proposed charges for in-house effort by furnish-ing the basis of estimate in the same detail as requiredby these instructions.

144

Page 292: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 293: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

(1) At Cost (3)

Intercompany or interdivisional sales or transfersordinarily should be handled on a cost, no-profitbasis to the transferor. Support proposed chargesby furnishing cost data in the same detail asrequired for in-house effort.

(2) At Other Than Cost (I.e. (3))

This is a special catgory which permits specificidentification of certain transfers of parts orservices between separate segments of the supplier'sorganization. Generally these transfers will begoverned by an approved pricing agreement. Thecriteria governing such prices are set forth inASPR 15-205.22 (2) .

7e. Overhead and G § A (2, 5, 7, and 10)

The basis for the overhead and G § A rates proposedmust be provided in one of the following ways:

(1) When forward pricing rates applicable to the periodof performance have been approved by the contract-ing officer, furnish your letter requesting rateapproval and the letter or agreement from the con-tracting officer granting such approval. Identifyin your proposal the cost data submitted to thecontracting officer in support of the forwardpricing rates (unless already identified in yourletter to the contracting officer requesting rateapproval)

.

(2) When you have furnished or will furnish overheadand G 5 A cost data to the DCAA in support of theproposed rates, you must submit such data withyour Cost Proposal or identify it on the DD Form633 and its attachments by listing the detailedjournals or cost accounts where the overhead andG ^ A costs are recorded. It is important tonote that the use of contracting officer approvedor DCAA recommended rates does not relieve you ofthe responsibility to disclose and identify currentcost or pricing data (including significant changesin the cost base which would result from award ofthe procurement being negotiated) which differsmaterially from the data furnished in connectionwith the relied-upon rate agreement.

(3) When no government approvals or recommendationsexist or are not available, provide by submittal

145

Page 294: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 295: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

or identification the itemized cost elements,methods of computation and allocation, forecastedtrends and sales, and budgetary data as necessaryto provide a basis for evaluation of the reason-ableness of the proposed rates.

7f. Direct Labor (4 and 6)

Provide a separate breakdown of labor by appropriatelabor category, and furnish the basis for cost estimates,for each task specified by this RFQ or RFP:

(1) The number of labor hours by functional laborcategories, the rate applied to each category, andthe extended cost.

(2) As with other elements of the Cost Proposal, thebasis of the proposed hours and rates must be sub-mitted either actually or by specific identifica-tion in writing. The basis should reveal thethought processes by which the hours and ratesproposed were determined, and must include thefollowing for each functional labor category:

(a) A short description of the type of effort tobe performed by each labor class.

(b) Historical data from like or similar programsprojected to the proposed hours by applicationof identified complexity factors, learningcurves, and other forecasted variations on thehistorical data. When submitting actualincurred hours from a previous or currentprogram, start-up and nonrecurring hours mustbe segregated from the recurring hours(ASPR 3-807. 3(e)).

(c) A copy of your request for approval of forwardpricing rates and the approval letter oragreement negotiated with the government. Inthe absence of such agreement, historical datamust be submitted or identified showingcurrent rates and trends to support the reason-ableness of the rates proposed. Identify inyour proposal the cost data submitted to thecontracting officer in support of your forwardpricing rates (unless already identified inyour letter to the contracting officer request-ing rate approval)

.

(3) In addition, submit a manloading chart showingtime and talent for each task and subtask (job

146

Page 296: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 297: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

package, work package, etc.) identified in thestatement of work. An example is included asAttachment 1. Summarize the chart to total proposedlabor hours.

(4) Segregate any overtime premium proposed if it is adirect charge.

7g. Other Costs (8)

Lease or Rental Equipment

Furnish details concerning equipment you anticipateleasing or renting in conjunction with this program.Include item description, proposed sources and financialarrangements

.

Special Tooling (ST) and Special Test Equipment (STE)

Furnish a list of your requirements, showing:

CI) Quantity.

(2) Description of the ST and STE, and description ofpurpose for which it is required.

(3) If the ST or STE is a standard commercial product,state the extent of modification.

(4) If ST or STE is to be supplied by a lower-tiersource, furnish the following information:

(a) Name of source.

(b) Whether procured to your drawings and specifi-cations or to a lower-tier subcontractor'sspecial purpose design.

(c) Unit price and the basis for determining it,with supporting documentation such as purchaseorder, subcontract, or supplier quotation; a

cost breakdown by element must be submittedif available.

(5) If ST or STE is to be manufactured by you, furnishcost and pricing information, and backup data, tothe same level as required for other priceableitems

.

Consultants

Submit the following concerning each consultant you planto employ on this program:

147

Page 298: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 299: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

(1) Specific nature of the consulting service proposed.

(2) Name of individual or firm, with a description oftheir specialized field of proficiency.

(3) Hourly/daily rate or firm fee for the engagement,with supporting documentation.

(4) Proposed duration of the services required.

Travel

Furnish a list of proposed trips, with the followinginformation:

(1) Point of departure and destination.

(2) Number of trips and duration of each.

(3) Reason for each trip proposed.

(4) Type of transportation contemplated and fare.

(5) Per diem and other allowances, with the purposeand amount of each.

Other Direct Charges

Indicate and explain any additional items treated asother direct charges in your accounting system. Pro-vide pricing details and backup data for each item,including historical data and the pricing methods usedto arrive at the amounts proposed. Identify and explainany items proposed as direct charges which are normallyconsidered indirect or allocated items in your account-ing or estimating system.

7h. - Royalties (11)

Refer to DD Form 633, Footnotes, Note 14.

7i. Excise Taxes (12)

Refer to DD Form 633, Footnotes, Note 15.

7j. Profit or Fee (14)

Provide a statement of facts justifying the amountquoted for profit or fee. The facts may include qualityof talent proposed, complexity and state-of-the-artfeatures, risk, past performance, use of resources and

148

Page 300: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 301: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

any other factors supporting your profit or feeposition. In evaluating your proposal the weightedguidelines criteria in ASPR 3-808.2 may be applied.

8. Furnish a separate "Recurring-Nonrecurring Task Breakdown"at the selling price level, listing the recurring and non-recurring price for each task. A sample format is includedas Attachment 2.

9. Furnish a separate "Manloading Chart" for recurring andnonrecurring costs. A sample format is included asAttachment 1.

10. Submit a Gantt chart schedule depicting the significantmilestones (discrete events) on a time-phased basis,indicating scheduled start and completion dates. Thischart may be a reproduction of the milestone chartappearing elsewhere in your proposal.

11. Provide a forecast of funds required, by month for thefirst ten to twelve months and by calendar quarterthereafter, segregating expenditures and open commit-ments. (If accounting months are other than calendar,please stipulate; e.g., 4-4-5 etc.)

NOTE: More detailed instructions for completing yourproposal and DD Form 633 and illustrations ofthe type of backup information required are con-tained in Department of Defense publication ASPMNo. 1, Armed Services Procurement Regulation ManualFor Contract Pricing~ dated 14 February 1969, andAppendix A, thereto, available from the Govern-ment Printing Office.

149

Page 302: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 303: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

RSD INTEROFFICE MEMORANDUM 25 August 1973

FROM'- Murray, RSD Subcontracts Manager

TO- Green, RSD Subcontracts Representative

SUBJ; Results of Source Selection for Proposed ContractR-739F821A

ATTACH: CI) Results of Source Selection

1. The SSB has met, determined the weights for the respec-

tive evaluation categories and selected a source, Pyramid

Products. Notify the selectee and debrief the unsuccessful

respondees

.

R. Murray

Attachment 5

150

Page 304: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 305: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

SOURCE SELECTION SUMMARY REPORT

25 August 1973

CATEGORY § WEIGHT A (WAFBURG) B (PYRAMID C (CONNECTRONIX)FINAL PRODUCTS)

FINALAVE SCORE AVE SCORE AVE FINAL SCORE

I - 10 8 80 9 90 8 80

II - 4 8 32 9 36 8 32

III - 4 8 32 9 36 8 32

IV - 4 8 32 9 36 8 32

V - 2 9.4 18.8 9.2 18.4 10 20194.8 216.4 196.0

SUBMITTED

R. BROWN T\ BURKE R. ROBIN R. TiURRAY J. AMESENGINEERING MATERIAL PRODUCT ASSURANCE MATERIAL MANUFACTUR-

ING

ATTACHMENT (1)

151

Page 306: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 307: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

RSD INTEROFFICE MEMORANDUM 18 August 1973

FROM: Green, RSD Subcontract Representative

TO: Murray, RSD Subcontract Manager

SUBJ: Results of Subcontractor Evaluation

Ref: (A) RSD Source Selective Procedure 752

ATTACH: 1. Evaluation Summary Report

2. Technical Approach Evaluation Summary Sheet

3. Management Evaluation Summary Sheet

4. QA § Reliability Evaluation Summary Sheet

5. Manufacturing Evaluation Summary Sheet

6. Cost Evaluation Summary Sheet

1. 'In accordance with reference (A) attachments 1 through6 are

Green

Attachment 6

152

Page 308: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 309: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

EVALUATION SUMMARY REPORT18 August 1973

ITEM connectors ORGANIZATION RSD

DATE

SUI(CONTRACTS

RFQ/ R-739F821AContract

RATING RANGE 0-10

A (WAFBURG) B (PYRAMIDPRODUCTS)

c (CONNECTRONIX)

I TECHNICAL APPROACH. POINT AVERAGE 8 9 8

II MANAGEMENTPOINT AVERAGE 8 9 8

III PRODUCT QA a RELI-ABILITY

POINT AVERAGE 8 9 8

IV MANUFACTURINGPOINT AVERAGE 8 9 8

COST

A. TOTAL PROPOSEDPRICE 7.5

B. COMPLETENESSOF PACKAGE 10

C. TYPE OF ACCOUNT-ING SYSTEM 10

D. AUDIT INFORMA-TION 10

POINT AVERAGE 9.4

6.7

10

10

109.2

10

10

10

1010

EVALUATORS

B. SMITH, ENGINEERING

R. GUNN, PRODUCT ASSURANCE

D. DIRK, MATERIAL

Q. BRISBANE, PROGRAM OFFICEATTACHMENT (1)

153

Page 310: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 311: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

u <?>> 00 00 cr r- h-CO CO

rn Noimt—i

PIPh PQ <A 00 cr or cr <r 00

CO N

< CD r- 00 CO cr od oO h-

e~ *3 42If) P Op cd i •H

H p P P 1 42m O 0) o 42 P ^ }-> Sw 0) 6 O rH P O rH Sh

ffi £ 0) P •H •H -H cu 1 TJ T3 tO -Hto P P cd > S P o c to P P

0) •H P P cd C o P -H 3 042CJ 43 3 O o r>- co p id cd CO T) 4-1 4H •H P,2; cr p 4*5 Ph-H p P cd P O > -H <4-l Pt—

1

O o C T3 P •H-d cd o o cd P rH O 3 PPS P p •H p O 42 P to P P O Cd rH Oo Cd cd ct) £ CO O • P .H o O 3 . 42 O Mhu •H E P O rH O cd tu •H cr P CO

CO P o P 0) O O cd CJ c P p Ph Pc p +J cd 42 •H O o c cd o >> o

K 0) cd P E p 4-> 0) •H P P o N t—

i

T3 p to

u p 6 o 3 cd42 P-H tu to •H •-42 o- cd cd

< s- (h 42 4- rH P 42 42 J^ rH rH MTJ cd Po m o 0) o (J CO P o •H -H P U<* m m 42 4-1 P ^3 <D P Ph P P 42 p 5D-. •H p P O P P P IT, 3 P •H o p oPh TJ o •H Ph 4-1 cd CU (—

1

rH O 3 42 rH42< Ph CO O O • E CU CO p O* CO cd P

X) m co O Wk rH 0) C +-> pJ p P o CD CO P CO cd Jh C^- o cd 42 P ^ <P -3

< cd <-t p o o c^- P -H to •H •H Ph 5 rH O Pu " 3 c o O •H -H X) O 3 M t/j P DO cd1—

1

to <J o P .p P O CU •h cr p tfl PnrH T3 P P c"Z a N •H •H cd P •H P > CO CD tu o cd cd •H 0^SC o •h m p £ P <U rH co P E Mh p P in u •H ^u •H p m •H rt bO MMO CU tu o Ph O CO p o-

to+J

w +-> b0-H P P o cd > <-M p S^ u Ph-H M-i +-> H E to uH cd O T3 bO P •H o P o o H Ph cd CO t|H CO > 3 "

. P o O cd P D-d-H p £ 3 CO O •H P rH o ••-»

0) 0) O o o P P Ph O cr p U-i rH O 43 to <"*3 p p O CD cd co Ph CD tu O Uh to cd U o •H »»

•H o }-i P 4-1 cd E M-l P p tu o p •H p 1310 rH E Cd 4-1 CO CD O cd s P 'co o rH Ph -3p cd 4) (>• p. Cd d> p rH E +-> p u Ph-H cd 4H po CO T3 U CO p O O 43 tu o 0) p (J Ph CO cd

u O p P e CO CO P P O P 0) <D 43 DflH to O 42 •HPh cd a) p rH OOP cd > r—> 13 P P 42 PhP P -3

E o X) rH o O T3 cd Ph E -h O o- •H cd 42 rH U O 43o P p •H 43 E P •H U •H p p u to > o cd cd in 4H p 0-r-l Ph 0) > O u > P P p cd Ph P P U P O Ph O Cd O CO

43 rH <L) ^H T3 cd tu p o co P cu cd •H P o P rH PO 0) Ph Ph 4-1 O CO tu P O i—

t

H m •H Ph 00 Ph OP 42 E P P p o cd co 42 cd o p •H CO Ph r* P in X -HPh P H •H X •H rH •H -H tU >H P 43 H P 42 to < P •H p

CO r-l cd P rH 42 P P 42 P P T3 42 Om to CO Ph CO P CO CD P -H 42 42 P <+-! MH CO P Po 0) O Ph O P <D 42 T3 E P rH u •H O o cd P -n

o rH o 3 O o O P P CO 'O H 43 to O *H p o p to

Phto

cd

Q P Q CO Q E Q O cd rH Cd £ cU p H CO cd Ph o•H

Q CO rH 5 P

P • • • • • • o • •

o 03 43 O n3 tu m PI cd 43

CSl

154

Page 312: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 313: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

COOSw•—

i

xa.Ohpoto

cr h oo 00 00 CO

eq 00 cr cr <7>> &\ CO c?s O

N

< r- cr cr 00 03 !- CD cr

xt I t3 Tj 1X O P! i <D P •Hp +-» P O P o rH P o 3o •H to to to p H •H 5 cr toV o £ O T) P o •H cd o o to pX p. pi o p o 3 P XrHrrJ P •> C P pX to c-- ctp x o crc- o rH P to 3 O TJo p to 0> tO rH 6 rH o X) T3 rH •> cd rH P c Ep C 6 rH 3 rH o cd P o Cd O P Cd rH U cd

0) o •r-» cd rH -H p O •H U >N cd o cd cd PV) X> 6 rH Px) O •H P o to X O P P GO 10 4h d •H0) X cd cd -h 3 P o o P o cd to o 3X X rH O x e cr a) P GO Ph E > E P-rH •H cro cd •H P P P O O P cd to to to P •H > O rH 4hcd E 3 Ph O P rH O E 3 •H w o rH •H rH P Cd •H po cr POO PL, y* to 4-1 O •P XI PL, PPX i . P rH X U O o * P T3 O o P oPh O p p O (1) P o tp to to e- a) POP oP- cd o 4H P rH P o o P PL, rH •r-i PhX O T3 pcd o Ph f-c 4h p Tj X O o > > u o X P -H •H cdp Ph O OOP P X Ph-H •H > TJ •H O p -p E

rH &, cdm 4H CO cd p p P •h a> rH to 3 C p o-cd p, 4-1 o m PL, o cd cd GO O rH E -c O PO cd <1) -H POX E o rH p C p cd POO 4-10•H X '3 O rH o P X U P. to cd rH O TJ to X P Ep to P E rH rH o cd cd (1) o P X X e-x - c- P. cd cd P P p O P •> OXrNE'd to Phu x V) o o to p O O P O rH 1—t •H <D X P p x a cd Xo p p p o o -h X O c- to cd cd P p Ph-H U i P 5p cd rH rH +-> -H C p to cd cd to H 5 cd -H •H P O rH

PL, 3 T3 03 cd p X A cd O h3 rH TJ H P p p cd cd X r-i

mh e t/> PI P! rH -H (J P h3 (Si p p O P •H •H 3 P-P •Ho o o O O P,TJ •H 0) rH P cd O X X Cd rH O O p p GO So p P.-H 6 T3 P B X cd 3 to E O •H *-> X^ u cd rH PPi to P O cd E to T3 P E 3 u p •H Cd 3 •H T3O TJ -H p to O -H E TJ O O o to 3 o- P X P O S•HX rH T3 P -H O rH o P -H •H o T) o cd to p •H o >tO 4-> P n3 OX PUrH Cd <4H P <u ~ O o Ph > 4h Xto H rH C(J O +-> P rH E X •H cd P to P p p E P X 4-1 tO -H3 X to as •H cd O o O P •H p Ph Cd cd O X cd •H XOX 0) to X rH tO to O u •H P > -H p X O P X to ra t1/5 £ T3 O P cd cd +-> o o Ph P <D a> to 4H P p P -H P cd o cd•H Pu cd to X cd Ph Cd to T3 u p •H U X TJXt 13 o to O X o rH •H -H X P P p p •H ^ p r-tPX P to Ph ~-P P o cd rH m P cd •H p P rH O m o > Pcd cd 4-> PL, O O Ph >• Pux O cd P O X o cd P PhX Tj E o o

o p Ph to o •H o o p p E > E to o p 4H<U T3 TJ O 0) PmDh -H rH <D P p: Pi O p O 4h to P >H p PhP O rH X p to JO X cd X P X P 4-1 O P X to X X X)P O P p o o cd cd P o O 3 a> r\ HT3 p rHX O H 3 XXX P a to > O 10 to rH X • rH •H •H PP rH X to p p H to P p a> p o •H E p P- P CO Cd to Cdp. O -P o to o cd > P GO P tfl E E • O P > P >

to X O o 3 <P P X o X P cd o p O o H P O O o cdH P Ph o HH |JTJ Q P O X E r-l rH P u to r-l tow > o K T3 P

4-1 GO

155

Page 314: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 315: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

o 00 or <r r oo 00 oo 00 r-

OT «S

wnJa. pq cT cr r cr cr <r cr cr

co

< ' CO cr 00 cr 00 CP oo OO 00

pM|•Hin

QMho

.NeoP!OuwT3PaS

XIP•HrH•H4=1

•HO

"POPcm

X X Pi-i P

45 •H 'd -H 45+> W P p rH rH P

aS as Mnj.ri Op P 43•H ft T3 P as P

in P OtJ 4=) •> E-h

P X P aS bou o 3 p O P p

P P •H P p -HT=> X O >H -H p•H t3 •H e- •H > aS -HV) e- MH rH rH P E as

P i3 as P, Po P ^ - E E ~Po X) t/1 tH •H •> >s

P as rH P </> XP •p P O -H P -H C

•H DO o E O -H rH Op p P rH t-1 -H

x> in as •H 43 PP 45 rH43 PIJ3 ni rt

tn P (J aS -h p po P •H O > P rHP P U P •H aj p aj

P o +-> 60 (3,1-1 >P p, p PhTS E 3as e-H w P O >« o P O n3m u X P U X P

t-H O 43 -P aS

bo XH MH p< W tHp P 3 x P U rH P C-•H •H Mh M O 'H -H in U1

r* rH p •H P 43 Po as 13 P P P in aS P O

P P p ns -H -H P45 P as E p bOrH - uO O E O X aS

i E P P- T3 rH p P MHMh »>• <—i •H -H •H tHi-l rH 45 43 3 3 t/) •> »rH p

a! do-h cr cr CAi in -H(0 w •H t/1 O in P 43 IS

O X m rH U -H O aS OP. P P P P P,

> o O W V) U {5

as P P O P aS Mh aS (3, aS

K p. < as < P X O <P O E

as

aS

•HP

PUPM

• tH

01

QOP

opas

PEOU

45•1 O Mhp •h O rHc 45 P a)

tH % P uE as P •P C- •rH

> U in p aS P PP -H •H E o O £ 45•H P P E P OP as 45 i-h aj 43 4:

cr p U 43 in p-H O

P bO P P 45 45as P,P P p 45 e-

as E P as p in

•H O rH O O P r-t

W d P P Mh rHrt •> in O P- O -H

as •h in P O MhP P P as O P rH

P cr t3 45 •H rH P PO -H •H O P P r-i Mh

p O P •H E•p p rH P -H rH £ <-{

P O p aS

>-i as > P aS in P p in

rH o O O •H P Op p •r->-H -P in cu

Ou P a! -P 45to Mh E P in U P

V) O •H c^- •H in pup MH 45 P-45 •H

p P O P U £ Op. o as aS p P 45

43 •H p P<45 O Pp P P45 P U

V) P. p O p •H 4503 rH •H E-h P £ > O45 as P 5 P -H

in U p 'P p E OS 45X o in a! 'P 5p P. p p •H p rH•H O P in > P in u in

rH P >• rH DO aS X p<^i P, as in as o 'p ,—{ in as PP C^' in P•H 45 45 43 P rH E6045 u P u P i-H P•H P as as 43 P as PP o 45 O 45 P 45 1 45 -HO in P P P +-> P O P P P P

P, P. in Mh crMh O P. in P, in 'p Mh in > in

i-A T3 a >—i aS >-< E H O t-i P

as O -P

to

156

Page 316: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 317: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

u

CO

wN>

i-3

ft «ft:=>

co

oo r- o- r~ 00 oo oo

<r (T or <r !i <r

cr oo p- oo

o-

OD oO OO

c

cd

V)

oC -H ft Jh X 1,

o cd to O cd to 13 •H m I 1

iH 3 Jh iH E cd E O P- O Jh

T) P.O O. •H X cd CD t+H C- .H *i Jh n uO X •H 6 P Jh •> Jh O P iH tO Jh ft ft •H c o,X <D > CD •H 60 to rH O CD to O P •H <Jh CD X CO <P O Jh cd CD CD 3 T3 C to c rH X.OT3 Jh P o Jh CD o •-. C C C -h o w£|H ft m ft g to COO •HT) cd p X. •H 13 >

3 X o c O T3 CD Jh 10 X P <to O CD X o to P G •H ChJD 3 to tO MH cd rHcd^cc CO •H 3 to 3 Jh XI O o 4-> C^- rH H-J

rC M) P Jh CD p o =3 m to C ft u c 3 to o hJO rH cd •H CJ ft-H O P O •H cd to ft Jh <

£-d cm ft iH > 13 XX'H C Jh P to p P ciJh •H e CD CD Jh £ P P ft O O Jh Cd c w•Hl3 13 cd Jh Jh CD cd cd E cd p c rH o >m -h t3 <u X fXX U«H E C Jh T3 u o

> Q> rH CD CD p •v •H O Jh Jh X ft X > Jh

10 O C iH o- X Jh O p <P O p O -H 4-> 13 a:13 Xi Jh •H cd o id P o o •H CO MH > j: c p <J rH c uiH P ft cd O •H CD Jh CD U 13 C o o P u Cd cd <

60 Mh p O 60 O n -H CJ +J •H t0 ft to o•H P 10 r* •H CD P C <H O ft S cd <H to O J ccPL, cd <L> CD Jh O iH •H Jh to C iH Jh 13 m ft m ft

Xi r-H O O ft to P CD ft cd O X) 60 Jh O Di ft13 P P.C ^ ft E cd to C o u p c Jh <(I) 6 CD to O •H O Ik P -H -H rH cd (J -H cd ft HHP to cd •H CD o -a X 13 Jh cd Mh X. Cd rH C P X rc -Jcd a x JhX CD CD CD H-H ft H U P >N <r-t cd 0) CD P > X Tj to E o cd O Jh •H Cd o X u'0 Jh ft •H rH •H o cd o Jh Jh Jh Jh Jh •1-,-M > HPi t>0 CD X o 60 rH > p x p ft 60 >> P to c cd z\ O X P 3 O to CO to o E -H ft C cd X. X rnJh Jh H iH IH Jh 0X3 -H E X O o ucd P. 13 cd to ft Jh o •h u^a O to O Jh X-H X wrH X CD to to cd rt .cc o o O C X c H•H <D . P P o C 3: ft CD ftp to iH Jh C cd S cd

E X P cd ft u o-dE£ cd 3 H O O X -H ft ft•H P £ £ -H o o •H Jh O p Jh O O cd Jh 4-> E O ECO CD O CD Jh 3 P Cd U OOP E Jh 13 O P O P-

60-H ,C Jh ft to cd X 60 o c Jh O iHtHH (J uc C O £ C •H iH Cd O Jh Uh O 3 C^- 13 U•H •H •<-< >s 10 to Jh 13 X •H X> Jh C o o rH C

p m i—1 -H X p O CD P P C P 4h to £ O X XIw m rH P o m to cd cv- C X c-- Mh c P -H p H

o •H 3 Cd CO CD C O X U P jd o x) X O X Jh X cd >-H Jh

c i-i en V P to t-> •H ft o •H C p to P P 3 O E to to

•H (J CD O OHT) O Jh to P 13 -H Jh ft•H XP <+ O Jh to Jh X C ft o cd cd to XI to X O O X o X(-1 rH O •H Jh Q ft H ft £ •H 10 q ftn: c IH P ih o £ m Q P Q o

P. Pi O PQ> e CD fiK •H 10 ft O • • • • • • •

w co -h V) O cd ,0 o TJ t+H 60

to

157

Page 318: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 319: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

CJ O CO CO CD r- or

co

U4t—I

a,ft:oCO

PQ i O

Vfc_

D cr oo <r

oo oo oo r- oo

p3 o

E- n3 i 4H X ••

W E-h 3 i <D O +J V) 3 AW o £ +-> o O +-> X) S to

X O CO < 3 ft<>- D H'O S oCO X rt X a) t/> E X P </> c O •H

X 3 3 E <u rt P +J -H 03 X c to Uw •P O 03 03 p P to to 3 4-1 •Has •H P E ft CO CO +-> -H CT^^ MH rH •H t-{

o PI E o3 O 03 XX <-i O rH ou 3 P rH O 3 E P X rH P P 03 03 T3 ftCO P 3 rt U o3 3 ft +-> rH C CO i

P 0) -H E W 03 MH O p C P C m

z O E O 0) 10 <L) C O X C-- •n a; •iH wo ft O X i-h o3 X O O P P to T3 > E o1—1 ft CO ft O +-> C -h to X C O 03 >H o oj to i—

i

>T3 4-> T3 CO U 03 X •H< o 3 rH O 3 'W TJ U J) C +J to 4->

!=> I-H I-l 3 o3 -H rH rt O •H M -H 13 H to - O P-J rt E > I > -H C TJ C ft p p

P03

<D

3

X

V)

< o 3 p ft+J +J C -H 03 O •r-,4->

> H cr moo owe 03 P > 'd -3 E C^- X ftw w OX P +J O CO CO C O rH C c o Oo p in E C P P 03 03 3 P U uH TJ o o x 4-> X •H O E ft C to 3 4-> 32 S o ftX P aj +-> V) O Sh to to 3 3 Ow o > X£ X G-H C TJ COMh - U P Us oS o p p +J tH t—

1

•H C 03 O +-> to +-> to Ew ft p .. a> ft > 03 C C oi C rt ft O Xu p. n x M-l E C 03 V) -H X X j^ E COP< cq ft X -H 4-> POO Ot)EE^ ft E *-> O 03 -H2 Pi 3 P > 03 O O >H +j u C rH<^ O X ^H U p O 0) c p CO o 3 3 03 -H2 CJ 3 ~ £ P 03 C -H +-> O u 03 -> •H E X

CO ct3 3 P w > "3 Mh -h 3 3 E 03

•HUP C rH •H >H -H d +J •r-> aj -H *^i 3 -H< (1) 0" H o o O r-l 3 > P O -H 03 O E CO 3 O rH

> +J -.-> E "+H O O O P to 3 03

3G 3 O 5 o-d X V) P ft X-H ft <4H 4-) 3 T3 PH x +-> P T3 tO 10 (O, X (/) rH C O -H 03n 3 ft E •H rH j-i 3 <-^ MH E u •3 TJS= p o rH P rH X O rH P CO E i—

1

3 3 •H C0) H 3 O O 03 O 03 X -H E 03 P P > 03

2 •h m to X <4-t w nJ 3 to CX+J o O > O 03 P Om rH •H O P c- o in O O O MH •H X P •>

H ftp ft 0) 3 ft ft P P ft O CO-r-, 4-> ft ft ct—

<

ft P O P X O O 3 P O ft V) <4H o S o3 <u p o H P £ O P w o 3 p P o V) -H

I H CO u ftMH rH 4-> ft-H <4-( ft to E O O ft 03 o i-H +->

CJ Z i—

i

rt +-> •H tO •H 3 •H 03

< w CJ-d-H ft OCX O^ C +J o r-i t4H 03 ftw S X E X o 3: H X O P X XP P o 03 TJ -H V O P -H

PJ 4-> rt P TJ O P O -H PC O -H S-. •H MH Uw u P •H ft •H t—

1

03 n3 +-> CO > -rH p to t3 -HQ < to CO t/1 > 3 +-> V) r-t -H W ft -r-» O U •H 03 4->

a2 a> o o o o S-< rH X E P o 3. +J P*a* o P Ok^ 03 O -H -H O O 3 P 3 3 to ft to P P 03

C-3 2 Q ft a ft t>o ft Q 3 v) Q O P ft«4H •H 1—1 10 I-H 03 < ft

CS) to LO *o

158

Page 320: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 321: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

CJ

CO

w(—

I

p. m:=>

co

GO <*\ OS 1/? CD Do Oo 00 I/]

cr 0^ ^ CO 0^ Cr o CT> C-

00 00 00 -300 r 0^ oo r~

CO

c^

CO

P P CO

1

P i

4-» 0) 0) >N TJ CD CD

p! bO X X XrH O CD P bou cd rH P P P rH 0) X P CJ cd

e P! cd cd •H p P > p p •H CD Pcd cd a) tO p, CD CD c3 •H CD CD bo •r-i to cd

bO EX o E C E a> P E S P O rH Ecd P PU O w a) rH U o o P CHp E o o bo U CD CD P« P. O pcd cdTj p. to 03 m X P P C-- O- CD

6 P Pi P<rH P P 4-> M-l P 03 O TJ P X p pbo o3 rH CD OS •H o E CH CD P c- p CJ p.

o O CD cd X E P X <D to P O 3x\ e» P P X i E to o H TJ CO CO CO 10 CD •1—1

P X) P o P Pi 3 4-i •H +-> 03 CD P •H CD CD TJ O PCD •H CD P O «J rH rH cd c P P U -H

cp +-> CD +-> co > n p PH rH p P.-H TJ P.O cd X cd <d o CD CO 13 o X -H P. 3 10 P o

rH P N o P CD CD P, CD AS m CD 3 03 CD PV) p< •H CN- TJ CD •H Pc P o to rH X X X 3cd 6 4H P >. X to X P ^N cd rH P r* P P•H 0) O Cd P •>P •H P CD rH rH X 3 O CD P CD+J P bO-H 13 3 to H P rH TJ P 5 P TJ O P•h p P P rH 0) P CP CD •H o3 P •H P O 3 cd 4->

rH O O O -H e -h CD .P P 5 CD o3 > P X P CD X•H O •H J3 p. x P bO PL, i-i rH H o 3 p CD OX 4-> X'H O P H +-> O 3 TJ CJ b04-i X P T-»cd cd •H p to CM -H CD P CD P CJ P a cd

P< N W 0) C £ Xi P o (0 -H •H X •H TJ CD •H CHcd -H O P.O P CD oS E P P p 5 p X P oO co asa X Pi X CD P P TJ •H o cd P p.

O to O <D P VI CO 03 0$ c rH X O XCD CD CD CJ CD O -H P p cd X P. cd cd CO P CD p p.cc X\ P P P OS tH p c CJ 3 P CJ P.-Hp p P rH Cd CD O o3 rt ~ P cr TJ O P PrH

rHTj CO Pi P X E p. p cd CD P CD OS -H£ 4h £ cd p •H 0) •H /—

v

CJ >• 3 O rH TJ X P TJ .oo o O i cd P. rH T3 M to TJ -H P,P co 3 •H X 03X X !-< PL, O CD CD rH U •H rH P cd •H O > p pV) 4-> w (D N 3 Tj bO ci o to •H -H P p CD •iH C/)

o > P o m 03 p •r-i 03 3 to CD bo p -p rHrH CD iH O -H P o rH P o O X X -H £ P 3 P rH H IHcd t-> cd P bO o3 03 •H p 3 O •H M-l -H cd x oto o V) <u o TJ w E P p,^ p cr P P 5 to cd

O P O XX rH O O 03 03 CD U P 3 P o CU CD IN-

p. p. P.P P rH X, PUP M CD T3 £ co e- OS p o p P. cd cj to Wo O 3 03 P O CD r-tX i o to E u •H -H o V P P Cip cd h c ra i CD P T3 P P O p p p cd P p CD O oP. P.-H P E c^- Pw p OS P P CD p rH CH OS CD p,p u

o «P CD 3 bO 5 i 03 ^ cd 3 E to P -H CD COCD rH cd p o > cd P CD i P o >^ E O E +-> P P cd CD CD > XX Tj ,P ^ O X 3 X P c-. O X 03 P CD o cd ox X E CD U wP Pi •POM P P +-> O CD Tj CD P P p E CH P P CD CD CJ

rt p p o u l rH CD p x a H p bO CD <to X (rt bO-H p £ 3 to P P, P :s 03 P E 3 03 It •H rH co 03 P P cicd <D E o P CD CD O CD O cr bo rH CD POP UJo o O P -H <p ,p p O > CD X X p O <P CD to P CO -H O cd X o >Q P Q O rH 1—I to CO a o a, 3= if) O Q O P t—i •H M £ Q E (-> E <

oo a> CM to vO

159

Page 322: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 323: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

o

COOSw»—

i

PI

CO

*> fc—

00 CO 00 -5 o 00 o o V) CD

<3~

^ -<f~

cr COO cr

|

o r* cr

CO GO CO r* o- loo o V^ 00

e^CD ip rH

c 1 P p X i-H

CD o P-H cd cd 4->

E 1 p CD p u to I o PP cd ex, 6 P o o CD P-H CDbO o p. P i-H P CU Pu > •H O P E•H 3 cd •n{ ^ O rC 3 P o P O X CD10 T3 3 CO CD 4J cd p •H X o boV) <L) P P CD IP P X i-H 3 O cd0} P

•>. cd

O P «P <4H

CD CCj OcCD

S-H •HU e^-

to P Pcd

tt) O e P P T3 o X cd E ch P EX ox P X co a •M <-t <H CD O -hPCD -H

h a)H ni

rt 6 cd <D

CD

PL,

Xcd ^

Pco

CD

P X*H

•HP •H i-H •H 4-> CO p o O P CD >» O P CDo P Pu +-> -H H cd T3 <A O O en •H Xm CD E C 3 cd CO c +J Ch +J

P. O CtJ Sh > rH >sCH CD P O OCO X o p O id cd rH t—1 CD •H P CD op CD o co cd cd O O p i- (D r-i -M tocd cd X P -H > CD E O P 1—

1

i-i 3 PX •H cv "O a CD CO -H cd

Pu X P tO X -H pL, to to p X P O+-> CO o cd to p cd CD 3 CD PuP

CD cO X 3 p H O p O x-o 3P to Pu C to X bo O cd E CD O CN- P P -Q•H V) cd bO O X P P P u T3 cd

G o m TJ "H CD CD i-H -H c3 PC CD to P m•H CO o CHEM 3 ch (h T3 P co tom 10 O 3 +-> to O TJ •H P oo ,d^• PL, O Sh CD o P CO Ph CD > O CD •HtJ Pu P M 3 3: OX o o c !h > O PuX M

cs. O Sh P r-> O CO O O (h PuP •H<d iH rH O O +->•>•> o rH O u PL, 3 i-H

T3 V <u a> £ POOP P X PL, PU to E •H3 P P p CD CO O -H PL, ^ P Pu E O X)1-1 P P <P T3 P rt +-> O cd cd P Sh CO C^-

a O O -O o p ch cd to CD S-, o P CO CH PL.PP c/> tfi p r-H g 4-> X O cd T3 P bo X CO P•H Si p co <u PL, P O P Pu P CD f- cd O P X O CD

cd O p. cu o cd E P T3 2: P r-H .—

1

!-< Pu Pu'O o X) 0- CH Jh CH o p •H w 0) cx, P P CO COas p a H C,p o P o > s > CD O p pC/> X X 3 10 r-t cd o a o o cq cd X > •HO a) CD O tscao CO P X p C-- CJ3 X 3 •H +J Sh 'O

-J Pu^ rM P CD to p O CO O 3 p.,,-1 UJ < PQ bO O 3 P PJw o box O O ch o to CD OS •z p P +-) cO cc2 u u 'O ^ P an oh o +J to p o <^ o P CD U o2 Pu H cu cj OP cO O u o >—

1

p u ^ u O O i cO X uO m p co O >h CD P P 3 cd P •H O CO CD

Mrd

P CH ,C COCO <D H cox P Pu PL, 10 -H >• to P cd CO CO X <H CD CO 3 PuaS X o •H o > ^ +-> 4-> p w < CH T3 ^-, P O UJw P 0) 10 rH 0) CD X O o CD P P CD CD CJ I-H o •H O CO CO u(X. Pu 10 CtJ P X CD H in X O P -o Pu <l a: > p E O <

to to cd C CO M ^ X CD CD +-> o o ex w CO CO CD U r-H CXX 0) o H bOX ch X> P CD T3 w E- CD CO T3 -rH ww O 4-1 O -H I-. v) m -H +J CH to 3 X 1h P > O co CO P C X >US' Q o Q P PL, i-H o x o o 1—

1

to CD < cd < s Q >—

(

-H +J CO Pu <

pq to LO CJ to

160

Page 324: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 325: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

u

coOSw

p<^>CO

vf» 1

00

*1 » - .

00 00 00 0000 CO 00 00 CO

CT" 00 <rfr- 0-

or cr cr cr °~

00_

r 000- CO 00 00 oO CO r

b0 -

Pe^- •H4-> e <u

CH O exO O crj +-i

•t—

>

CD rH rHW> O X b0 CD CD

P M M O pH p, i-< h pn3 +-> Ph OP to as c^. 4-1 to

rt -h x-o A P (-<P£ +J CD b0-H CD

tO 4-> Jh p CJ Ph^l CD CD •H S-

(1) M-i O 4-> rH CD

T3 O P 4-> p rHP rt CD T3 •«-> £>3 -P ..J-..0. CD as

P p . X c rH

P 0) tO r-l u CD •Hco e to (O > a)

0) a$ •H >CD bO t-> u bO a$

+-> a! b0 CD CD

a) P P 6 4-> CO XJh oS •H to P +->

p e O CD cd O •Hto P X> E • H £a a) •H Mox > rH bo CD

f= 4-> P rH P p. Pa> O -H •H =3 •HTj X O £ T3 4h rH

+-> rH

X-H CD CO as CD PrH £ •Xi CD bO^i •H^ •H +-> CD •Haj P > aS U rH to

CD !-i O Tj CD

rH CD r-c rH rH C- rHO U Ph X •H CD CD PH P r-l as X u Tj

Z r-l O rH <D +-> 4-> p CD

W as as > CD O as XS to tO -H T) rH O Jw O co O rH t3 p to <u Ph- Ph CD +-> p. to w H< u O T3 P <M to T3 a: O

u rH CD a( CD O H<c Ph e P-, to •H •. to C^- u^ •- U P. bO O (0 CO W

+-> CD U •H P P Ph CD Di2 ,p co X CD 4-1 1 •H O w O2 4-> 3 +j e m s O U ^ e) C_)

a P bo Ph PSi

COto 10 4-> to r-l CD

CD CD CD lO ,—

1

i-< CD to w UJCC O X O 3 to O O rH CD > uex, Q 4-> Q O l-H m 4-1 < rn <

• • • • • >Q rH C^l to »* < m u

HWw<2

>o

161

Page 326: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 327: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

u

COoJwI—

<

P)ex,

ex,

CO

PQ

<r cr CO 00 h oO

<T 00 l^ (T 0-

CTv cr I- h- CP OD

WWECCO

ot—

osouco

>-Hn.J<

UH3QOOSCM

4->

Cd rH

C Ocd

10 4-1

pcd

PXEOo

cd

Xp(1)

XI•Hpoto

13

o

oPn

Pi

o•r-l

P c~-

cd to

CD

•HP

rH

Pcd

bOrHrH »HO XI

cd

bO p,.P cd

o

orH

PPOupPCD

£CD

bfl

cd

Pcd

Cd

CO

o

orH

Ph

CD

ip

T3

rHO

cd

U

PX•> OP CD

cd Pi—

(

PTJG

rH Cd

CO

CD

•HP

X

CO

cd

Pcd

E

p, to

o CD

orPto

CD

rH

3PO P3 UrH CD

P rH

10 'H13

po cd

•HP Pi

cd Otsl

•H bOP P!

Cd -HbOPrH rH

O OP.

tO CD- rH

UCD

•H

cd

CO

CD MPi p•H -HiH rH

CD

P CD

o p

bOPCD

PI

O-I -HPXPP, O3 pCO 3

4-1

CD

bO

6

CD

OPCD

3rH4-1

C•H /—

>

+-> p

pXP•H

10 rHCD cd

oo

pCD

ECD

rH

3uorH

P

U C~CD PE CD

O 6P10 CD

3 XO

CD

X

£ co

O PX P

CD

ECD

rH

CD

cd

Jco 3

a"X CD

rH rH

rH

cd eCD CD

rH PU (O

rH tO

cd

tO r-i

o oP. rH

O PrH CP O

UCD

IP XP P

cd

cd

3Ol

bop•Hppc3

rHOh

to

>> CD cd

O 3a cr

P•HrH Pcd bo3-Hc_y to

CD

4-1 Tjo

P Pcd

Pb0

PCD

PXCD

to

CD CD

X T3P

CD

CD XC P•H4-1 pCD 'H*P

PX OrH -HrH -Pcd cd

CD CX

o u

cd

+->

rH

to cd

O P,o-p >O Pu oPh-H

cd cd

X MP -H

Pabo

to cd pCD bo cd

rn Xo o

OO

cd

CO

pO•H+->

cd

i-

CD

Ph!opco

CD

HPO

uCD

P^to

P

1

cou >•

CL. tO

U-t E co id op •H

e cr, PCD cd

P T3 rH

to CX cd exen

Pc

CO O T3» •H cXP cd

p cd

a u c£PX•H PE4H •HO •H CU P C

c cd

CD eo HP-OfxP •H

P e^OJ cr, O mp Z. •rH TJcd 4-J P hp cd u oin P CD u

m P CD

x to PdrH c PrH o 1

Xcd •H +j

CD P T3 •HrH O PJ «—

1

u CD cd ns

cx 3r-i in p Ccd p to

to •rH CD Po H oex /—

\

3o rH /—

>

TJu v

*N OP.

, .

v-' rH

cxo rn . ~

x: O H /—

\

P 4-1 O rOP »—

'

CO rH PCD o p -dO rH o CQ P u cd

<CD

>

uCD

rH

rH

OU

o>•HPuCD

P C-P ASO uO cd

Sito T3

•- CD

X CD

P 4hcd

Ph >nE uO cCJ 0)

•HCD orj •HP 4-

oCD T4=1 »x.H CD

P. P'J 3CO r-K

O HTJ cd

4h>xr-l cj:'

P ccd •HCD T3rH 3U H

urH Ccd •Hto

o w\

P Eo Orn PPh W

>^o m

*J po

to •HCD Po oa cd

CM rO

162

Page 328: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 329: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

u r- 00 00 oo

CO vexwi—i

•Jo- O O <>>

3,*•• **

3CO s

< r*~ Q~- QD 00

1 i-H Vh

" 3T3 i—

1

o 1

fi O 3 3 4-1 OO rH m P Jh

CJ ••>/—> to O V) E 3 t- P,WtO P C i-H P CD rt Om fn ^ 3 -h O 3 p P, <+-! rH

o a> <l> H CD 10 CD US

•h --Eh P g >-n H E -hEHfiOJtJ 3 P, to O rt U0) p, O i-t -H O -H to ^i CD

P PVH -H h O 3 t/> -H bO pi.

10 3 P 3 CD cr - TJ O to

>% to rt C+J 3 <D X >H

V) 4-> CD us O 344 P, to

M C *m S •H P rt O US

CO CD CD P CO 3, to

- -H 6 ^ w> US CD E rH - X>>P 3 p 3 r, +-> o o X o3 < CJ >H -H X O H 3 3oJ^OHg •HTj p rt to

3, 3 t3 rt o r-l 3 CD 3 3,6 to 3 uS uS X O E to

o p cr 3 CJ P O O US

o m pi -H 3 U CD

O CD <-n -3 o • • CD T3 Ho e ^^ 3 -H i—

1

P 3 CD rt• • 43 3 CD v-'i/i rt p uS rt us XIH +-> O H ">—

'

CJ •H p P 3o •H 3 •- X CD >H to 3 • • •HM CD +-> CJ CO TJ bO P, CD O 3 CD

p ,£3 U o bo 3 O to +-> X-H O XI CNp •h <D u n rt rH 3 uS iH P •H •HOPo H r-l PVH O -H S >- rt P H -H CO

<_} O <D P • we- H us DO rt CJ P Oll) lAM-l CO 10 CO P •> +-> CD CD u to rt p

p CD O-H 4J <D . • CD CO 3 rH H •H CD U3 tj /—> h c i/i .—

1

6 -H rt O MN Ch T)'H C(Li r-l £ CD t/> O o 3 cd pq •H m o6 H^O tn E ID H to o CD rH CO CX P i-H -H -HCD uS -H CD 3 U P - p >-. ^ s f-i rt p pSh 1/1 M > >H O O 3 X CJ to •• to f-, CJ

3 O 3 CD rH O H O 3 3 to O 3 • CJ O CD 3u PVH H PV~3 p. U rt O •H a o cd P, U 3o o-d pi, PVH Q O -H . nd o chu H W >^Z5 4-> •-! 3 E P H P -H 3 U T3ex, acup w c d O O UN 4-1 p, rt rt P. 3 «

W)-H CD -H •H O 3 T3 O (J •> rt HfH O DHTl E U P Td CD CD -H rH to CD O0) X H rt CD CD uS CD O 3 r—

1

XJ'+H Cl! 3 X H 2•H p 3 > >- 3, H JZ i~< -< O P -H -H •H P CD

H m CO 3 w XI P PL rt H P M 3 3 -

P. CO rH H CJ •H iH P to 3 CD •H to -H to

3, CD O /—n P, O 00 i—

1

CD H p. 3 CD CD P ui CD US to

3 O >,N ftM C uS Jh O X o o t3 rt M O H CD

CO QfJ^H PVH U < "4-1 CD u a -h e H Q P U

vO OO

163

Page 330: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 331: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

u

co

w»—

i

~jOh

co

m

<r 00 J> 00 ^S oo

<r <r 00 0" <r <r tr

00 00 r- o- oo_5 00

HPJWco

nPiOCJco

>-

<h-3WPi

HUJ3QOI*a.

-a1 C crH £ o cd

•H rt HX TJ P P rHcd P to cd <u t/>

•h cd o E "3 00 p -3rH tH P O p c C

00 ft o E C CJ cd

P CO 4-1 o E•H 0) P X c c>- o CO

00 O X H •M o p ^ c- -H -M •H Pi ft o •H^H X rH c CO pp o r< P H o u p cd

cd ft O •H X u c c Pft 4-1 rH cd o cd

e p •H •H c u — -3o o X X rH o cO -H U cd O > £ 3 PP CCJ •H u o CO -d rH

cd on rH f-* •H CJ cd

-C! N oo a £^ oo' p P

P -H v P O- CJ

P u E U-t m -3 Ip <Pas 0) cd cj o o o o

X co C p CJ

•H P (U V) o o rH oP o 00 C X 00 00 p Lr. 00

o P •H 00 3 3 E 3 300 CO as 4-( •H

p H 0) C Q) e>-- o 00 a>*3 -H P H3 O X oo * X X

13 •H P t3 M as p P>s 3 0) >s+-> orH rH id rH OS CJ X oP U C- 3 rH C c p c p P Ca p V) r-l as -h •H tu •H •H •H •H

-H O u <u E IH E ^M l+H IH IPr-l •H CO G r-l O o CJ CJ o

00

rHu p P

•H •H•H O 00

00

-o oo

•H oTj X) 13

o-13 c—

oo

O rH rH i—

(

G rH rH -H 00 rH 00 •H H X rH i—

1

<D rH rHP cd ft •i-l c as aj T3 rH as X P cd P cd cd P as+-> oo XI cd t/1 !>• p 00 (D 00 rH o 00 o- •H 00 00 a) 00 >C o p cd i—

i

O C o O T3 •n O cd 0) O 00 o o o •H Oo P P P. Oh a o •rH a, a o a. c rH P CJ •H p. P rH 00 PrHu o cd o •H P O as 2 o ^ o o 3 rH o O p rH o

p e u X p P O !-. rH to ,^ cr ft u P o S-c 00

+-> P P P< as a, c o P c ft •H E p. >v CX P > P 00

c COr-

(

•i-C P rH o •H o p c •H u P<u Cd cd rH CD C rH a> -h +-> a> •H c cj x CO CJ c a P X O iH

6 x p o •H X o x; +-> a! X P a> X u X a H as X Ptu 4-> aS •H XI +-> E u +-> u E 4-> o c M o c •t-l ^ •M 00 P 00

&o 6 p CO OJ CJ •H o +J CO c CJ 00

as oo x •H to r-

1

as 00 rH X oo t3 p. 00 •H 00 3 00 S-. 00

c X U rH CJ P P <D rH •!-> <U 0) E O T3 00 CJ X) CJ CJ rH mOS O P o E as o o -2 O rH o O c CJ o CJ O X p o as

2 Q -H +-> as a •H Q Q U s a P U a as a Q Di Q £ CO Q oo

CM rO LO \0 00

164

Page 332: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 333: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

in

do•H4->

rt

U0)

t3•Hin

P!

OO

>>+J

0)mt/>

oC•Hm<u

»o

rHn3

in

OPUoueu

a>

03 CD 03

or (r cr

co eft CD

0)

wu3w><JJ

*

>o

•HrH•HXI

•HrHd>

pi

W t3C3 C

a03

W w X> es •(->

<2!

•HrH

>^ w 03

+-> > 3•H < cyrHn) X +j

3 4-> uC •H 3rH i3

•P •H oo X> r-l

3 03 euT3 •HO rH or-i <D COeu e! p!

J<HOH

t/)

ooIQ

o>

165

Page 334: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 335: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

u r- cr (r O V) 00 00

03 nJ

w

Oh «Oh3 *> a—— .

cr cr GO cr cr 00

CO

< 00 00 00 r~ <5~ 00 00 00

1

1 cd U <+4 -HO ft O •H O J2 rH•M O O -H T3 1+-1 to •(-> cd CD 1

10 4-> ft CD •H CD CD tO rH X O•H box (O O O O MH cd CD 4-> cd T3 O-X v> G cd pi CD Q C O rC PI «H CD CD(1) CD •H 44 PL, <D CD (-. o- PI rH EO ft 10 10 -H t/) X bo PI O rH C •H -Ha> ft 3 « CD c- ^i cd P! O 4-1 cd cd Pi 4->X 3n 4-> C ft 4-1 4-> CD CD cd x to E cr

CJ5

+-> O C O cd 3 O O PL, rH PL, 4-> T3 TJ O CD 1010 O Cd rH T3 e- cd X cd E O p| CD PL, CD ft -H2 *n a> «h 44 Ph CD 10 CD 'n CD O xi cd ft O > XrH

a:PO

O ft 4-> 3 O rH U O M O •H S-, •H rH 4->O G T3 O O c u u • X P3 PL, 4-> rHOH 3 cd C ft ft cd pu-h CD tO rH cr (J Cd 4->H u rt -r) E aj Pu4-> in I4-I ^ X <D 4-> CD CD CD cd

< C «H Pl PS V) -H 4-> -H C ft X 4-1 4-1d) u ^ to X T3 O tO -H U O 4-> CD 4-> 4-1 cd 4-<

PO•oca - pi l> (O JT; CD -H +-> -H -H to CD X O•h cd X-H cd Cd +-> Pl,<+-I Cd rH O CD C 4-> CD2: > c C rH 1—1 to -H X -H -H 10 -H p; •r—

t

5 CD -H 4-> cd O E cd t0<41 (j 4-> (J M-l to cd CD O2 4-1 PU PL, <D p; P! O CD CD cd <+-i a> cd 4-> ftO 4-> e +-> •H X PL, <D "4-1 CD 4-1 cd pu4-1

4JT) C O rH to -H u to +-> to 4-> ccd a cd O O X4-> p; e rtTJA! ft CD tO CD3 rt g O to cd •H h O CO O PI rH PL, C CD Xcr pu 4-> ft > CD 4-) x: •H cd O •H U X4Ja> •> X CD CD PJ 4-> 4-> Xl £ TJ E G rHrC) rH rH 4-> •> X PL, O <D PI CD PI CD rH ftcd cd cd to 4-> O O Pi 4-> O •H U CD cd ft TJ cd Oc > CD CD • rt Cd 4-J cd X PU •H O 4-1

- •M Pl CD X -H Pl X) <D rH X PL, 4-> 4-> > •HCox) H 4-> H C T3 CD CD (D rH tO C 4-> CD 44 CDCD 10 ft -H 0- cd cd •H O J-l rH rH E <D C •H rHW ft E O r-l C rH > p: PL, Cd bO rH E CD s o- O XCD CD O 10 -H cd PL, bo O cd CD p| O PU-H E CD cd>H Pu ft CD X rH X C r-i 4-» 4-> CD rH -H M-l •H O X CD PUrHPu 4-1 T3 -H PL, CD -H PL, CD Cd PL, O U rl Pi -H to 4-> tO -Ht tO p; PL,TJ Pi CD crm to cd•H +-> P! rH a X rH pi rH E t30 H P ft (D Mh rH X rH >cd pl Cd O rH cd cd cd rH p; cd pi cd to cd cdto cd -h tO puX tO r-l 10 O Cd -H to cd TJ (0 to toO rH 4-> O CO E O PL, u m +-> o O rH O CDp, cl,.h PU CD CD PL, PL, Wl-H D Cu D N Pl pu PU >-iO 10 O ft 10 O (D O C X 4-> PI - •H CD ft cdJhhC ft to !h rH r-l -H PL, U rH Cd rH rH > ft 4-1 ftpu cd cd PL, C cd PL, 3 PL, rH cd cd Pl, E cd cd -H Pu c Pu toU ft O ra P! r-t MH •H CN. •H DO O CDD-H P CD -H 13 CD CD CD 4-> W) P! o- CD CD U CD u CD O CD "HX 10 X 4-> C X jr; X U O C 4-1 X 4-> CD rH CD 4-J X X 4->4-> X+-> 4-> OS cd +-> u 4-> cd -H cd u 4-> Cd PL, pi Pu L) 4-) bo 4J -HX -H M to <4-l XI E Pi tO TJ tO CD c rH</> a. e (/) -H C to tO P3 -r-, 10 CT CD •r"» to •H 10 -HCD ft cd pi CD li CD C <D CD O CD <D X) X CD O CD ft CD UO 44 CD O CO •H O O O Cd X X rH one U ft ft O pi O cdC3 O Pu O D0 4-> Q m Q E 4-> 4J PL, Q cd cd to < PU a 4-> Q t4H

CS) to LO VO 00

166

Page 336: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 337: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

OSwI—

CO

00

<r

< cx>

°\

c•H

rt 4->

P« o£3 cd

O M-t

O da

a) rt

pto

p P

p p:•H

0)

O to

PS t3 *•<D O c/)

•HP 0)

> d) pa> g rt

o>o

PL.T3

J-i

op<

> 3

a p10 to

o opuso

•H

Pu <u u

p m3a)

p6

to

0)

N

o n ps

O 3 rt

wOSou

w<OSw

cr>

167

Page 338: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 339: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

Ph

w

cj o 3. 2. oooooq o £ £l£O O

pq

1^ o o ooooolo o o 01 oCO

E-WpqXCO

CJ2I—

I

piocjCO

e-cooCJ

V) OQOOoOOQ O ^ Ocr

E-2PJ2 QPJ COH Pi< 1—

,

H <CO <

< CJ

< s QQ Q

W aXCO

OHW Oh m oH < E- E- < J <

sa, CO a; CJ E- cj E-pj Q Pi o X < CO <X pi PJ 3 CO Ph a Q (—1 Q

CJ Ph H O pj Ph • • o QCJ Pi X H 3 2 pi H Ph

• • < >- O « CO PJ Ph CO CO OPJ J Ph Pi E- O Qo * Pi n Ph o CO CO o CJ Pi PJ

s H PJ pj 3 pq pi H >* H < CO PJw 2 Ph H CO < o CO CO o Q < CJCJ CJ PJ O Pi -q PQ o H H 2 PJ

i1—1 < Pi Pi O CO < CJ CJ CO < • • -Jf* Ph ej Ph Ph pj Pi J 2 o >H H 2 PJ wPh X Ph H O H PJ 1—1 CJ H CO PJ O Pi >

Ph u K) X rf Ph Pi cj CJ H i—

i

CJ i—

i

<Q o to CO ps O PJ < 2 CO J CJ <£ H Q hJw Wk v£> PJ Ph Pi Pi X PJ i—

i

2 re < PJ < HCO CO pj J H -J 1—

<

PJ O H-

H

cq i—

i

pj 2 tsi H COo CO H 2 < CJ < H Q > CJ Ph >—

i

H > 2 i—

i

O OPh w pj 2 y-t pj 2 Pi < CJ 1—i CO 2 < o Pi H CJo 2 J o Pi Pi O O Pi < H CO X re OPi pj Ph Ph PJ t—

<

t—

i

Ph PJ 2 PJ O 2 XPh H S H Q E- re X Ph PJ CJ CJ t—

i

E-PJ o Q <a^ 2 <£ X H o Q CJ CJ XJ J CJ n 2 »—i K CO O >—

(

< < H << Oh PJ i—i

E- 2 Ph QO o >- • • • X •

E- CJ < PQ CJ X PJ Ph CJ H < pq CJ < <

168

Page 340: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 341: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

D. CASE REQUIREMENTS

1 . The Source Selection Process

a. Consider the RSD Material Procedure #752. Iden-

tify aspects of this procedure which tend to be counter to

the best interests of the Government.

b. Review the RSD Request for Proposals.

(1) Does the RFP adequately convey to the

offerors an understanding of the criteria by which proposals

are to be evaluated? Comment.

(2) Is an offeror who has not been debriefed in

a prior RSD source selection significantly handicapped?

If so, does this matter in the long run? Comment.

(3) How could the RFP be improved?

c. With regard to the details of the source selec-

tion process:

(1) Did RSD comply with its own written proce-

dures in all essential areas? Comment.

(2) Evaluation criteria must be carefully chosen

to avoid an "averaging out" effect that inhibits selection

based on the really significant discriminators among the

offerors. Were the criteria in the RSD source selection so

chosen? Comment.

(3) By which criteria did Connectronix lose the

award?

(4) Would the outcome have been different if

Pyramid had proposed $900,000? Comment.

169

Page 342: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 343: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

2. NAVPRO/ACO Role

a. RSD made nearly two hundred procurements in the

past year of about the same dollar magnitude as the connectors,

In view of this:

(1) In what level of detail should the NAVPRO/ACO

review such a procurement before granting consent?

(2) What safeguards exist to insure that the

contractor conducts a "proper" procurement operation, in

addition to the consent procedure?

3. Role Reversal

a. Consider the case problem as having arisen one

level higher in the contracting hierarchy. Assume NAVORD is

the procuring agency and that the same source selection pro-

cedure was used to award a prime contract.

(1) Is such a procedure consistent with Govern-

ment procurement practice? Defend the procedure from the

view of a PCO. Attack it from the view of Connectronix.

(2) If the Government had negotiated with each

offeror, would you expect the outcome to have been different?

How?

(3) If the offerors knew that negotiations would

precede award, what proposal strategies would they be forced

to employ?

4. The CNM Letter

a. What response should LCDR Brown make to the

CNM letter?

170

Page 344: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 345: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

E. TEACHING COMMENTARY

1. Introduction

As stated in section one, the purpose of the case is

to introduce the student to the source selection process used

by a major defense contractor. RSD Material Procedure #752,

the RFP, and the evaluation sheets contained in section three

are Navy contractor documents. They have been altered only

to disguise authorship.

In writing the case, a concerted effort was made to

limit the number of side issues brought into focus. Sub-

contractor source selection involves not only the mechanics

of the process, but also all the issues of negotiated pro-

curement and the role of a third party, the contract admin-

istration organization.

By no means does the case describe or even mention

the process used by the Contracting Officer to insure that

the subcontract was made at a fair and reasonable price.

Such information would have increased the scope of the case

beyond the stated objectives. It may be assumed that the

ACO did correctly make such a determination during the con-

sent process. However, an astute student will question this

aspect of the case.

The case requirements were intended to limit the

issues to a manageable range. Classroom discussion of the

case may lead far afield of the specified case requirements.

For example, had the NAVPRO decided that the bid protest was

substantiated, determining the liability of the Government,

in view of ACO consent, would make a case unto itself.

171

Page 346: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 347: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

The RFP's failure to describe just how proposals would

be evaluated is certainly a serious and valid criticism of

the contractor. The illogic of omitting such information

was well stated in a past issue of Defense Management Journal

"Firm criteria for proposal evaluation should begiven (in the RFP) , as well as the actual or approxi-mate weighting factor for each of the criteria orgroups of criteria. Since the purpose of the RFP isto elicit the best possible responses from all biddersreflecting the system program office desires, what canbe gained by making the evaluation process mysterious?The bidders ought to know the rules of the game. Ifthey don't, the evaluation board runs into evaluationproblems because the various proposals will reflectdifferent degrees of emphasis in various areas. Thebidder who comes nearest to guessing the right answersgets a higher score. Yet, he may not be the bestqualified contractor for the program.'

2 . Discussion Questions

a. Consider the RSD Material Procedure #752. Iden-

tify aspects of this procedure which tend to be counter to

the best interests of the Government.

RSD Material Procedure #752 was approved during

the last CPSR and is entirely sound. The procedure is broad

enough to cover every conceivable procurement necessary in

the Pluto Program. The same basic principles are applied

to both major and minor procurements. Yet flexibility in

applying specific details and levels of organizational

involvement, according to the nature of each procurement --

dollar threshhold, technical risk, etc. -- is provided for.

STEELE, Morris, "Communications Effectiveness Neededin RFP-Proposal-Contract Award Cycle", Defense ManagementJournal

,

v. 9, p. 22, January 1973.

172

Page 348: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 349: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

Furthermore, the procedure permits evaluation criteria for a

specific procurement to be chosen according to the nature of

that procurement.

No RSD department can entirely dominate the

source selection process. The high weight assigned to the

technical worth of proposals is consistent with the require-

ments imposed on RSD by its customer, the Navy. The relativ-

ely low weight suggested for cost considerations bears watch-

ing. Not all RSD Pluto procurements are of a nature which

would justify such a minor role for cost factors. The RSD

procedure permits the source selection board to vary from the

suggested weight ranges of the various categories. There

should be an understanding between RSD and the NAVPRO that

cost will be given greater emphasis when circumstances

permit.

b. Review the RSD Request for Proposals.

(1) Does the RFP adequately convey to the

offerors an understanding of the criteria by which proposals

are to be evaluated? Comment.

Clearly, the RFP does no such thing. Broad

requirements as to format and content of the technical,

management, and cost proposals are included in the RFP. But

criteria by which the three proposals will be evaluated are

not stated. The RFP offers no indication of the relative

importance of technical, management, and cost aspects of an

offeror's proposal. Offerors are advised that RSD reserves

the right to accept other than the lowest quotation. And

that is the extent of the guidance provided.

173

Page 350: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 351: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

(2) Is an offeror who has not been debriefed in

a prior RSD source selection significantly handicapped? If

so, does this matter in the long run? Comment.

Such an offeror is operating under a severe

handicap. He needs more than a statement of work to prepare

a proposal likely to satisfy an RFP and result in an award.

An astute supplier, without prior business experience with

RSD, would be expected to find some means of gaining a gen-

eral idea of how RSD evaluates proposals. Nevertheless, such

a supplier is hardly on equal footing with other offerors who

have a current or recent business relationship with RSD.

(3) How could the RFP be improved?

By now the answer is obvious. Because the

RFP is deficient in informing offerors of evaluation criteria

and the relative weighting of categories, RSD is less likely

to be in a position to select the supplier best suited to

this procurement. If offerors have to guess in preparing

proposals, then in a subtle way, a proposal selection process

has been substituted for a source selection process.

c. With regard to the details of the source selection

process

:

(1) Did RSD comply with its own written pro-

cedures in all essential areas? Comment.

RSD did comply with its own Procedure #752.

The answer to this question is important since an informal

bid protest is involved. Had RSD deviated from this proce-

dure, the procurement file would be expected to contain

documentary justification for such action.

174

Page 352: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 353: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

C2) Evaluation criteria must be carefully chosen

to avoid an "averaging out" effect that inhibits selection

based on the really significant discriminators among the

offerors. Were the criteria in the RSD source selection so

chosen? Comment.

In attempting to answer this question one

begins to develop an appreciation for the challenge which

devising evaluation criteria can present. Several of the

criteria are redundant. These tend to reinforce the better

proposal. By several other criteria, each proposal received

a maximum of ten points. Such criteria have a place in

screening proposals for responsiveness and responsibility

of the offeror. They are more in the nature of a "go, no-go"

test than a measure of the degree to which a particular

quality is present in a proposal. When used in the evaluation

process, the "averaging out" effect creeps in. This was

most apparent in the cost category where the significance

of total price was negated by the remaining "boilerplate"

criteria.

The quality of the source selection process

can be judged to some extent by examining the range of total

scores from high to low. If the range is broad, the process

probably did a good job of differentiating between proposals.

In the case at hand, the range is narrow -- a high of 216 and

a low of 194 -- so we must look further.

The winning proposal received a grade as

high or higher than either of the other proposals for all but

175

Page 354: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 355: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

three criteria. This increases the confidence that the

process produced the best choice. Still, a wider range in

total scores would have been more reassuring.

(3) By which criteria did Connectronix lose

the award?

The Connectronix proposal received high

marks in every category and for nearly every criteria. But

closer examination shows that Connectronix was graded at

least two points lower than the winning offeror for about

seventeen criteria. Of this number, thirteen of the

criteria have cost growth implications. Relatively low

grades here tend to explain why Connectronix was able to

make its proposal so low.

(4) Would the outcome have been different if

Pyramid had proposed $900,000?

With the arithmetic procedure by which grades

were assigned for "total proposed price", a proposal of

$900,000 would have made no difference in the outcome.

However, there exists some ceiling price beyond which a

proposal would be declared non-responsive before evaluation

or else rejected later by the source selection board. A

ceiling price would not have to be specified beforehand.

But if needed it would be based on RSD's cost estimate of

the work and the company's confidence in this figure based

on all cost proposals received.

176

Page 356: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 357: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

The question does illustrate the apparent

insignificance of total proposed price (within limits) in the

RSD source selection plan. However, as noted earlier,

criteria in other evaluation categories also have cost

implications

.

d. RSD made nearly two hundred procurements in the

past year of about the same dollar magnitude as the connec-

tors. In view of this:

(1) In what level of detail should the NAVPRO/ACO

review such a procurement before granting consent?

The NAVPRO/ACO is limited by time and

resources in reviewing an RSD procurement for consent.

Naturally, the detail in which a procurement is reviewed

varies according to the nature of the contract, the dollar

value, and the criticality or technical complexity of the

end item. As a minimum, the NAVPRO/ACO must insure that

certain administrative and contractual requirements are met.

The proposed price may be confirmed by separate analysis. A

NAVPRO will categorize prime contractor procurements and

develop internal review procedures for each category. Detail

of review will vary according to category.

(2) What safeguards exist to insure that the

contractor conducts a "proper" procurement operation, in

addition to the consent procedure?

Over a period of time, the NAVPRO will

develop a working relationship with the contractor and exten-

sive familiarity with his procurement procedures. NAVPRO

177

Page 358: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 359: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

procedures are guided in part by his judgement of the

efficiency and integrity of the contractor's procurement

methods. The contractor's procurement system must meet the

requirements of annual reviews in the CPSR program. Finally,

as noted in ASPR 23-302 (c) , ACO consent to a subcontract

"does not constitute a determination as to the acceptability

of the subcontract price or the allowability of costs". ~

e. Consider the case problem as having arisen one

level higher in the contracting hierarchy. Assume NAVORD

is the procuring agency and that the same source selection

procedure was used to award a prime contract.

(1) Is such a procedure consistent with Govern-

ment procurement practice? Defend the procedure from the

view of a PCO. Attack it from the view of Connectronix.

A PCO would experience great difficulty in

defending a negotiated procurement in which no negotiations

took place, unless he could demonstrate 1) adequate competi-

tion or accurate prior cost experience and, 2) insufficient

time to utilize formal advertising. A government RFP

would be required to appraise offerors of the criteria by

which proposals would be evaluated. Without such informa-

tion, an unsuccessful low offeror would very likely protest

prior knowledge of the criteria by a winning offeror, if

such appeared to be the case.

(2) If the Government had negotiated with each

offeror, would you expect the outcome to have been different?

How?

178

Page 360: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 361: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

The opportunity for a different outcome

would obviously be increased. Either unsuccessful proposal

might have been modified through negotiation to the point

where, after best and final offers, one of them best satis-

fied the Government's requirements.

(3) If the offerors knew that negotiations would

precede award, what proposal strategies would they be forced

to employ?

The question is open-ended, serving only

to make the point that proposal strategy becomes a signifi-

cant factor when negotiations can be anticipated.

f. What response should LCDR Brown make to the CNM

letter?

Pyramid Products was awarded a subcontract by

RSD on the basis of a source selection process which met

all contractual requirements. RSD's judgement that the

Connectronix proposal was unlikely to satisfy its require-

ments at the price quoted was within RSD's prerogatives.

Indeed, the Government is paying for RSD's management services

in decisions of this sort.

Upon analysis, the proposal of Wafburg Industries

and that of the winning offeror were reasonably close from a

price standpoint. Cost analysis performed by the NAVPRO sub-

stantiated the reasonableness of the price. Thus minimum

requirements for competition were satisfied.

The RSD Request for Proposals reserved the right

of the company to accept other than the lowest quotation. If

179

Page 362: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 363: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

this statement aroused the curiosity of Connectronix as to

how an award decision would be made, the RFP provided a means

of making necessary inquiries. However, no such inquiries

were made. It cannot be shown that RSD would not have

adequately responded to such an inquiry. Indeed, the RSD

source selection procedure was willingly explained during

post-award debriefing. The RSD procedure was not particularly

unique for this industry and was common knowledge among

RSD suppliers.

The NAVPRO reply to CNM should "sustain" the

award to Pyramid Products for the foregoing reasons. Some

mention could be made of RSD's procurement performance as

evidenced by past CPSR's.

This bid protest could have been avoided if RSD

had been more explicit in describing evaluation criteria in

its RFP. Such action might improve the quality of proposals

and should be discussed with the contractor.

180

Page 364: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 365: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

BIBLIOGRAPHY

1. Federal Contracts Report, The Bumpy Road to SourceSelection , v. 457, p. K-l through K-8, 27 November 1972.

2. Department of Defense Instruction 5000.1, Subject:Acquisition of Major Defense Systems , 13 July 1971.

3. Department of Defense Manual for Contractor ProcurementSystem Reviews , January 1973.

4. Morris, Steele, "Communications Effectiveness Needed inRFP-Proposal-Contract Award Cycle", Defense ManagementJournal , v. 9 no. 1, p. 17-25, January 1973.

5. Chief of Naval Material Procurement Policy Memorandum(PPM) Number 16, Source Selection Procedures for MajorWeapon System Acquisition , 21 December 1973.

6. Armed Services Procurement Regulations 1973 Edition,

Issued by direction of the Assistant Secretary ofDefense (Installation § Logistics)

.

7. Navy Guide for Contract Managers . Department of the Navy,Headquarters Naval Material Command, March 26, 1973.

8. Government Contract Law - Third Edition , Air University,The Air Force Institute of Technology School of Systems §

Logistics, Wright-Patterson AFB, Ohio, Dr. James 0.

Mahoy, Editor, November 1972.

9. Defense Procurement Management for Technical Personnel,

prepared under direction of Headquarters Naval MaterialCommand, by Harbridge House, Inc., copywrite 1972 byHarbridge House, Inc., Boston, Massachusetts.

181

Page 366: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 367: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

INITIAL DISTRIBUTION LIST

Defense Documentation CenterCameron StationAlexandria, Virginia 22314

No. Copies

2

2. Library, Code 0212 2

Naval Postgraduate SchoolMonterey, California 93940

3. Commander Peter DeMayo , SC, USN, Code 55Dm 3

Department of Operations Researchand Administrative Sciences

Naval Postgraduate SchoolMonterey, California 93940

4. Lieutenant Commander David A. Donovan, USN 1

Norfolk Naval ShipyardPortsmouth, Virginia 23709

5. Lieutenant Commander Charles R. Privateer, SC, 2

USNc/o 7932 Wellington RoadAlexandria, Virginia 22308

6. Chairman, Department of Operations 1

Researchand Administrative SciencesNaval Postgraduate SchoolMonterey, California 93940

7. Lieutenant Commander Edward A. Zabrycki, SC, USN 2

Code 55ZxDepartment of Operations Research

and Administrative SciencesNaval Postgraduate SchoolMonterey, California 93940

182

Page 368: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 369: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

UNn.ASSTFTF.nSECURITY CLASSIFICATION OF THIS PAGE fWh»n Data 1•ntered}

REPORT DOCUMENTATION PAGE READ INSTRUCTIONSBEFORE COMPLETING FORM

1. REPORT NUMBER 2. GOVT ACCESSION NO. 3 RECIPIENT'S CATALOG NUMBER

4. TITLE (and Submit)

Case Studies in Subcontracting

5. TYPE OF REPORT 6 PERIOD COVERED

Master's Thesis:March 1974

6. PERFORMING ORG. REPORT NUMBER

7. AUTHORrV)

David Anthony DonovanCharles Russell Privateer

8. CONTRACT OR GRANT NUMBER<"«;

9. PERFORMING ORGANIZATION NAME AND ADDRESS

Naval Postgraduate SchoolMonterey, California 93940

10. PROGRAM ELEMENT. PROJECT. TASKAREA 4 WORK UNIT NUMBERS

11. CONTROLLING OFFICE NAME AND ADDRESS

Naval Postgraduate SchoolMonterey, California 93940

12. REPORT DATE

March 197413. NUMBER OF PAGES

184U. MONITORING AGENCY NAME a ADDRESSf// dlHor.nl from Controlling Office)

Naval Postgraduate SchoolMonterey, California 93940

IS. SECURITY CLASS, (ol thle riport)

Unclassified

15a. DECLASSIFICATION DOWNGRADINGSCHEDULE

16. DISTRIBUTION STATEMENT (ol Ihl a Report)

Approved for public release; distribution unlimited

17. DISTRIBUTION STATEMENT (ol the abatract entered In Block 30, II dltlarant from Report;

18. SUPPLEMENTARY NOTES

19. KEY WORDS (Contlnua on reverse alda If nacaaaary and identify by block number)

Subcontracting Source SelectionCPSR Program Make-or-Buy PolicyConsent

20. ABSTRACT (Continue on reverie aide If neceeeary and Identity by block number)

Subcontractors play a significant role in governmentprocurement and are essential to an effective procurement process.Current estimates of D0D procurement show that at least 50 per-cent of prime contract funds are subcontracted. A series ofthree case studies has been developed to illustrate major concernsin subcontracting. The cases are designed to introduce thestudent to subcontracting and to the specific procedures and

DD | j°nM73 1473 EDITION OF I NOV 6» IS OBSOLETE

(Page 1) S/N 0102-014-6601I

183

UNCLASSIFIEDSECURITY CLASSIFICATION OF THIS PAGE ftOien Data Entered)

Page 370: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 371: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

UNLLaaairicijCkCUMITY CLASSIFICATION OF THIS PAGEr»T-»n D.r« EnKf.d)

20. ABSTRACT

sub-requirements of Contractor Procurement System Reviews, :

contract review and consent by the government, and sub-

contractor source selection. Particular attention has been

paid to an examination of subcontracting from the point of

view of both the prime contractor and the government as well

Teaching commentaries are included to assist the instructor.

L

DD Form, 1 Jan 73

rt , „

S/N 0102-014

1473 (BACK) UNCLASSIFIED6601 SECURITY CLASSIFICATION OF THIS PAGEP»..n D... H»«««0

184

Page 372: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 373: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 374: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting
Page 375: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

anD°nov,

50494

m sub.

3 5

j

ThesisD6475 Donovanc ' 1 Case studies in sub-

contracting.

Page 376: Case studies in subcontracting - CORE · topurchasingandsubcontracting.Relianceuponacontrac- tor's approvedprocurementsystem will usuallyobviate the need for reviewing and consenting

thesD6475

Case studies in subcontracting /

3 2768 002 00595 1

DUDLEY KNOX LIBRARY