Cargill, Inc., Docket No. 90-3191 - OSHRC · Title: Cargill, Inc., Docket No. 90-3191
cargill
-
Upload
bc-petrochemical -
Category
Documents
-
view
51 -
download
2
Transcript of cargill
© T O U C H B R I E F I N G S 2 0 0 8
For over 35 years Pipeline Engineering (PE) has provided pigging solutions
for the oil and gas and related pipeline industries. PE was a forerunner in
the development of a reliable dual-diameter pigging solution, and
continues to advance this technology into multidiameter lines. With a
track record of engineered design solutions to dual-diameter and related
pigging problems, the application of proven techniques together with
new and innovative concepts has allowed the development of
multidiameter pigs capable of negotiating multiple pipeline diameter
changes and geometry conditions, together with specific launch and
operational parameters.
Historically, pipeline inspection companies required a pipeline to be
of single-diameter construction with a constant bore and bend radii
five times the internal diameter. This was to enable the necessary
clearance between their tools and the pipe wall to allow collection of
the required data. If a pipeline followed this configuration, it was
deemed to be piggable.
The drive for cost-effective design highlighted potential savings in space,
weight, fabrication and installation costs. It was found that if topside pipe
work, risers and subsea manifolds were of a smaller diameter than the
main pipeline, a considerable reduction in cost could be realised. The
reduction in bore necessitated smaller valve configurations, branches and
welded fittings such as tees and bends, which naturally led to reduced
costs. The weight savings in these assemblies also reduced fabrication and
installation outlay, which also contributed to the overall reduction in cost.
The joining of lines within a field from a main transmission line to a
central processing location provides a source of dual and multiple
diameters. It is more cost-efficient to tie into an available existing line
than to lay a new line, with benefits being shared in terms of
maintenance and reduced overall installation lead time. A branch line can
be smaller than the main line, and the former’s size is determined by the
production output of the joining location.
The continuing development of deepwater fields has emphasised the
requirement for economical design. The greater water depths dictate
higher pressure ratings and therefore thicker-walled pipe systems, valves
and fittings. With increasing field water depths come exponentially
escalating construction costs, and as such any potential area for saving
must be explored. With this in mind, connectors, valves and features
have been scrutinised, with the result being that rather than reducing the
overall diameter of the component, it is acceptable to reduce the internal
diameter to achieve the thicknesses and cavities needed for form and
function. This then creates the opportunity for a vast quantity of internal
diameters due to the array of manufacturers producing components to
be included in assemblies.
A prime design consideration is that the line to be installed has to be
piggable. This factor is generally never discounted when applying varying
diameters, as flow assurance is a mandatory aspect to be addressed. A
flow assurance programme ensures line condition is maintained at a pre-
determined level, optimum flow conditions are achieved and product
quality is retained. With the aforementioned factors taken into account,
the drive for savings is still pressing and a direct approach can be
achieved by pushing the boundaries of the term ‘piggable’. A balance
must therefore be struck between economy and functional viability.
The Process of Pig Selection
Suitable pig selection is crucial to ensure that the desired task is
carried out to the standard specified, within the project timescale
and to the allocated budget. Here, the drive for an engineered
solution that has been proved to be successful, the need for accurate
information and provision of operating conditions are essential.
Foam and conical cup construction pigs can negotiate reductions in
diameter, but are not specifically designed to cope with changes
in diameter for considerable lengths of run. To fulfil the requirement
of functioning within a dual- or multidiameter line, the pig needs to
be suitably designed to negotiate the pre-defined diameters and to
pass through the diameter-specific features.
Step-by-step Design Guide
To design a pig capable of negotiating a multidiameter pipeline, the
parameters must first be clearly defined. Within the term ‘parameter’,
the following factors need to be considered:
Multidiameter Pigging – Factors Affecting the Design and Selection ofPigging Tools for Multidiameter Pipelines
a report by
Andrew Cargi l l
Pipeline Engineering
74
Pip
eli
ne
s
A flow assurance programmeensures line condition is
maintained at a pre-determinedlevel, optimum flow conditions
are achieved and product qualityis retained.
Suitable pig selection is crucial to ensure that the
desired task is carried out to thestandard specified, within
the project timescale and to the allocated budget.
Cargill.qxp 17/12/08 3:07 pm Page 74
2 5 – 2 8 M AY 2 0 0 9Abu Dhabi National Exhibition Centre • UAE
W H E R E T H E C O M M E R C I A L A N D T E C H N I C A L G A S W O R L D S M E E T
GAS: A TIME OF CHANGEChallenges, Solutions and Alternatives
CONFERENCE REGISTRATION NOW OPEN
Book your place before 31 January 2009 and save over £200
www.gastech.co.uk/hydrocarbon
LAST EXHIBITION SPACE BEING SOLD
Contact us now to book your space
Watch highlights from 2008
www.gastv.tv
H O S T E D B Y
O R G A N I S E D B Y
DMG_ad.qxp 17/12/08 12:38 pm Page 75
H Y D R O C A R B O N W O R L D V O L U M E 3 I S S U E 276
• internal diameters;
• bend radii;
• feature definition and configuration;
• length of each section;
• transitions between diameters;
• location of features;
• flow and pressure conditions;
• medium and environment;
• expected debris and internal line conditions;
• pig launcher and receiver; and
• interaction of pig characteristics to negotiate features.
Internal Diameters
The diameters present in a line need to be defined as accurately as
possible, as all variations of the stated diameters can have an effect on
the boundary conditions. The range of diameters needs to be broken
down into a range for each core diameter. This could involve grouping
schedules for each major diameter or, more likely, similar sizes to allow
a number of defined ranges to be identified. The pig seal and support
elements would then be sized to suit the ranges. If the ranges are
found to be too great for the elements to accommodate, the ranges
could be broken down further to identify additional elements for
cover. The type of seal and support element and configuration will be
selected based on the range step changes, together with the length of
run in each diameter and transitional conditions. The seal element
could be a range of specially sized sealing discs (see ‘Case Study’,
below) or an overlapping petal-style disc (see Figure 1). The support
element could be a modified traditional style support disc (see ‘Case
Study’, below) or a hybrid paddle support (patent held by PE; see
Figure 2). For larger diameters it may be necessary to employ a
wheeled spring suspension arrangement to maintain alignment to the
pipe centre-line due to the increased weight of the pigging tool (see
Figure 3).
Bend Radii
The bend radii need to be defined together with the specific diameter
in which the bend is formed. The portion of bend in angular terms and
the method in which the bend is formed, such as induction bending
or lobster-back field fabrication, are also key factors for consideration.
The pig length is of major consideration here, as a longer body is less
likely to be able to traverse the bend, but a short pig would be
unstable through straight length runs. The pig length is also
influenced by the combination of features within the pipeline system.
Feature Definition and Configuration
Definition of the feature and its particular configuration in the
application require detailing. An example would be a tee, which
could have a barred branch for pigging, or it could be a flow tee with
through-bore flow-matched pipeline. The pig design needs to provide
a positive seal across the feature to allow an efficient passage with no
loss of drive, which would lead to stalling. A wye piece is another
example of branch that requires careful design consideration.
Length of Each Section
The length of each section in relation to its diameter needs to be
clearly defined to assist the review of the main diameters. This also
provides a basis for the selection of materials resistant to wear for
the stated length.
Transitions Between Diameters
The transitions between different diameters and features need to be
investigated and simulated to ensure that they are not too abrupt,
which could cause loss of a positive seal and therefore drive, and
could also prevent the switch between the two sealing elements, as
required in the transition between major diameters. The length of
run to each feature needs defining so that a map of the pig run can
be built up for analysis purposes to enable the optimum pig design
to be generated. The distance to each feature and the order in which
they occur in the line are key pieces of information, without which a
suitable design cannot be produced.
Flow and Pressure Conditions
The stipulated flow and pressure conditions need to be taken into
account, and recommendations should be made to ensure pig
speeds are kept at the optimum level to prevent unnecessary wear
Figure 1: Petal-style Pig
Figure 2: Paddle Support Pig
Figure 3: Wheeled Suspension Pig
Multidiameter Pigging – Design and Selection of Pigging Tools for Multidiameter Pipelines
To design a pig capable ofnegotiating a multidiameter
pipeline, the parameters mustfirst be clearly defined.
Cargill.qxp 17/12/08 3:07 pm Page 76
H Y D R O C A R B O N W O R L D V O L U M E 3 I S S U E 2 77
and damage, but also to ensure an optimum cleaning speed, as
required. Bypass can be introduced to maintain flow but reduce pig
speed, while introducing an efficient cleaning mechanism.
Medium and Environment
The medium and environment in which the pig is to transit can be
corrosive, and as such the materials and design need to be resistant
to corrosion. A medium that is not self-lubricating, such as a dry gas
line, can present a particular challenge as the seal and support
elements can wear at a faster rate than they would in a lubricated
line. Careful material selection for the affected elements will ensure
that a suitable pig is designed for the task.
Expected Debris and Internal Line Conditions
Depending on the internal condition of a line and the medium
transmitted, varying types and quantities of debris can be present.
The array of types and quantities of debris dictate a specific
approach, for example a bypass pig to allow through-flow to
suspend black powder in front of the pig in order to prevent a
blockage and overloading of the pig receiver facilities.
Pig Launcher and Receiver
The onsite launching and receiving facilities can restrict the overall
length of the pig and hence prevent the pig being designed to best
suit the line geometry of any feature combinations. An example of
this is an ITAG pigging valve, which has a strict maximum length to
allow a pig to be inserted and rotated into the main flow of the line
to be launched.
Interaction of Line Features
The interaction of individual line features may not at first appear to
have a large bearing on pig design, but in fact can never be
sufficiently stressed as an underestimated design premise. The
interaction of pig characteristics designed to negotiate and traverse
separate line features can potentially have an impact on passage
through a feature in which they are not required to be active. An
example of this is when a pig is designed to seal across a wye piece,
where the body is considerably longer than that of a standard pig.
The pig could also be required to traverse a bend, but due to the
revised length the pig may not be able to do this as the increase in
length could have lowered its position in the bend, causing a clash
between the inside of the bend and the body material. Figure 4
shows the layout of such a scenario.
The severity of the clash would be dependent on the radius of the bend
and may result in a loss of seal rather than a clash; this may be able to
be rectified with a modification to the disc pack configuration. If the
disc pack cannot be modified, the tool could be split into two modules
with an articulated joint between two pig bodies. This would allow
passage around the bend and sealing across the wye.
Pipeline Data Are Critical
Line diametrical information and feature details are fundamental
inputs into the design process. As previously stated, in order to
achieve an optimum design all available line data are required, and
where information is found to be missing, measurements need to be
taken – where viable – to allow the full picture to be obtained. If the
aforementioned data are not obtained, the process of design will be
extremely difficult – or, depending on the missing information,
impossible – to complete. The objective is to provide a pig to suit the
application; this must kept in mind when engineering a suitable
solution, and therefore assumptions and estimations must not take
the place of fact: if information is found to be lacking, a halt must be
called to the design process until the information can be provided.
Prototype Development and the Importance of
Testing and Validation
When a design has been developed to suit a particular application, it
is trialled using computer-aided design (CAD) modelling through the
diameters and features to be negotiated. The design basis and
previous trial data are utilised to refine the design to achieve the most
suitable solution. The true test and therefore validation of the design
is to manufacture a prototype of the design solution and test the pig
in a purpose-made test rig. The test rig should be designed to simulate
the worst-case scenario features and diameters to which the pig will
be subjected when running through the field line. When testing, the
conditions under which the pig will operate in the field – such as flow
and pressure – are simulated to ensure the test is as true a
representation of the operational conditions as possible. This will
therefore validate the pig for use in its intended application in the
field. Data collected from testing can be used as a benchmark for flow
and pressure readings in the simulated features; these can be
compared with operational data to review performance. It must be
noted that testing is generally under ideal conditions with no pipe wall
deposits, such as wax, and no corrosion. However, it is possible to
apply such build-ups and replicate corrosion pits and scours to enable
a true assessment of pig performance.
When testing, it may be necessary to amend disc diameters and disc pack
configurations to allow a smoother, more efficient passage through the
features. A particular parameter to be noted when developing a dual- or
multidiameter pig is bypass; where possible, modifications can be made
to keep this to a minimum. Bypass can be reduced when the pig is
traversing a straight pipe section or is in a bend, but it is at the transition
to a larger diameter where it can not be reduced as the sealing elements
respond to the variations and effect a positive seal.
Figure 4: Layout of Pig in Wye and Bend
Multidiameter Pigging – Design and Selection of Pigging Tools for Multidiameter Pipelines
Line diametrical information andfeature details are fundamentalinputs into the design process.
Cargill.qxp 17/12/08 3:07 pm Page 77
H Y D R O C A R B O N W O R L D V O L U M E 3 I S S U E 278
Multidiameter Pigging – Design and Selection of Pigging Tools for Multidiameter Pipelines
Together with the validation of pig performance, testing is imperative
to validate the functionality of a new or special pig design. Gaining
data that can be used for operational purposes is a useful exercise,
but testing the pig through the simulated field geometry and
conditions is invaluable as, should a design feature not perform as
intended or an unexpected clash occur between the body and pipe
wall, leading to the pig becoming stuck, it can easily be removed
from the test rig and the design rectified. The number of
modifications and re-tests is unlimited, but when the operation
requiring the pig takes place only a single opportunity exists for
success. The cost of recovering a stuck pig from a subsea manifold
would be substantial and would undoubtedly delay a project, with
further financial impacts. The cost incurred in performing test loop
trials is minimal in comparison, and could prevent a series of events
detrimental to the success of a project.
Case Study – 8x10-inch Pipeline Offshore India
PE was approached to supply a pigging solution to negotiate 8–10-
inch major diameters for commissioning activities and production
pigging. For dewatering on the line the pig was to be propelled with
nitrogen to remove the water. The pig was to be back-loaded into
an 8-inch vertical subsea launcher, which was then to be connected
to a pipeline end termination through a reduced-bore mechanical
connector and into a 90° 5D bend. The pig was to perform a
mandrel body roll flip and pass though the connector and 5D bend,
then pass into a 10-inch pipeline section, in which it was to travel
3.2km before negotiating a reduction into an 8-inch pipe via a 90°
5D bend and a reduced bore connector before being received at the
subsea manifold (see Figure 5).
Pig Operational Requirement
The operations were to be carried out subsea with both launch and
receipt at 600m water depth. The pig was extensively tested and
developed to ensure functionality was maintained under the
parameters. The pig was required to negotiate the following:
• 8-inch launcher and pipe work (internal diameter 190.5mm);
• connector (internal diameter 179.8mm);
• 5D bend (internal diameter 190.5mm);
• 10-inch line (internal diameter 241.3mm);
• tapered 1 in 6 transition; and
• length fixed at 400mm due to laydown head design.
Figure 5: Test Rig Layout
Figure 6: Initial 8x10-inch Pig Design
Launcher spoolID 189.0
ConnectorID 180.0
10”NS pipework241.25
10”NS pipework241.25
8“NS pipeworkID 189.0
8“NS pipeworkID 189.0
8“NS pipeworkID 189.0
5D bendID 189.0
ConnectorID 180.0
8“NS pipeworkID 189.0
6 in 1 transitionID 202.74 x ID 254.46
6 in 1 transitionID 202.74 x ID 254.46
ID = internal diameter.
When a design has beendeveloped to suit a particularapplication, it is trialled using
computer-aided designmodelling through thediameters and features
to be negotiated.
When testing, it may benecessary to amend discdiameters and disc packconfigurations to allow asmoother, more efficient
passage through the features.
Cargill.qxp 17/12/08 3:09 pm Page 78
The Pigging Products andServices AssociationAn international trade associationserving the pipeline industry
The Pigging Products andServices AssociationAn international trade associationserving the pipeline industry
Pigging seminars – next one18th November 2009 Aberdeen
PPSA newsletter:“Pigging Industry News”
PPSA’s book:“An Introduction to Pipeline Pigging”
Training coursesPPSA website
www.ppsa-online.com
Services include:Free technical information service
available to allComplimentary Buyers Guide and
Directory of MembersSourcing of pigs and
pigging services
Want to join?Full members: piggingmanufacturers and serviceprovidersAssociate members: pipelineoperators, suppliers and alliedindustriesIndividual members: anyone with aninterest in pigging
To find out more visit our websitewww.ppsa-online.com
or contact the Secretary [email protected]
Pigging Products andServices Association
PO Box 2, Stroud, Glos GL6 8YB, UKTelephone: +44 1285 760597Facsimile: +44 1285 760470Email: [email protected]
www.ppsa-online.com
Our aims are to promote the knowledge of pigging and itsrelated products and services by providing a channel ofcommunication between the members themselves, and
with users and other interested parties
background image © iStockphoto.com/P Wei
PPSA_ad.qxp 17/12/08 12:39 pm Page 79
Pig Functional Requirements
The pig functional requirements were as follows:
• remove construction debris;
• flood line for hydrotest; and
• dewater line.
Pig Design Development and Validation Testing
The pig design could not incorporate a suspension system or a
paddle support system due to the bi-directional and back-loading
requirements and the restriction on length. A segmented support
system was employed for pliability through the reduced-diameter
connector and to provide support in both the minor and major
diameters. Dual seals were utilised for the 10-inch section and single
seals for the 8-inch section (see Figure 6).
When the trials commenced, the design was found to be unsuccessful
at negotiating the features due to the reduced bore connector
damaging the disc packs, preventing formation of an effective seal in
the 10-inch pipe work. It was found that the annular clearance in the
8-inch pipe work was too small to allow the compression of the 10-inch
seal discs and the required proportion of the support discs. The pig was
subsequently re-designed and the prototype modified for further trials.
A combination of radially grooved supports arranged in a petal
formation was applied to support the pig in both diameters. Two 10-
inch seal discs were removed and the disc pack spacing and body
flange positions were revised for compression in the 8-inch pipe work
(see Figure 7). The pig was run through the test rig to fine-tune the disc
diameters, with the pig found to be successful.
The 8x10-inch pig will be used to flood and dewater lines in the
field. It was therefore a requirement to test the pig using gas as a
pigging medium to dewater the test rig. The main criterion for the
dewatering test was that the pig was able to be received into the 8-
inch pipe section with gas as the pigging medium. This test was
carried out and the design was again found to be successful.
Testing Results
As stated in the previous section, the final pig design was found to be
successful in the trials and was therefore validated as fit for purpose.
The following information details the differential pressures in each
feature for water to water pigging:
• flip launch: 8.0 bar;
• 8-inch pipe work: 7.5 bar;
• connector: 15.6 bar;
• 5D 90° bend: 13.6 bar;
• 10-inch pipe work: 0.9 bar; and
• pass through reducer: 17.4 bar.
The differential pressures were quite high in the 8-inch diameter
pipe work due to the compression of the 10-inch elements, with
the main length of run having a differential as would be expected in
this diameter. The above results were mirrored with the air water
test exercises. The pig design was successfully launched and received
in a number of field operations, and performed as required during
these operations.
Summary
The process of pig design can be eased by the interaction between client
and vendor where a free flow of information is present. It is only under
these circumstances that a true appreciation of the impact of line
geometry on the final pig design and operational capabilities can be
gained. When developing a pigging tool suitable for a specific task, it is
essential that knowledge of the operations to be carried out is held by
both parties. Dual- and multidiameter pigs have long been proved to be
successful during validation testing and field usage. Each design diameter
difference has to be approached and appraised on a case-by-case basis,
with minor individual changes being considered together with the overall
major change. The interaction of the changes with the features must also
be considered in order for a suitable design solution to be engineered.
With the cost of pipeline recovery and deepwater operations,
validation testing is a necessary step to ensure that a successful
design solution has been supplied and that the risk to the project has
been reduced to as low as reasonably practicable. ■
About Pipeline Engineering
Pipeline Engineering provides products and services for pipelinepigging and flow assurance. Products include utility pigs, pigsignallers, rapid opening closures, pig launchers and receivers,bend restrictors, polyurethane products and other pipelineproducts, including AMPL, an automatic multiple pig launchingsystem. Support services include project management,engineering consultancy and operational support. This includesproduction cleaning services, design, development testing andproduction of special cleaning pigs, product deployment andretrieval, pipeline modifications, caliper surveys and piggingcampaign management.
Figure 7: Successful Final 8x10-inch Pig Design
Multidiameter Pigging – Design and Selection of Pigging Tools for Multidiameter Pipelines
80 H Y D R O C A R B O N W O R L D V O L U M E 3 I S S U E 2
Together with the validation ofpig performance, testing isimperative to validate thefunctionality of a new or
special pig design.
Cargill.qxp 17/12/08 3:09 pm Page 80
2009 National Safety Conference
The National Safety Conference takes place on Tuesday 12 May to
Wednesday 13 May 2009 and features an overview of safety challenges
and issues affecting refineries and petrochemical plants. The exhibition,
held as part of the conference, gives attendees the opportunity to meet
and talk with representatives of companies offering a variety of safety-
related services to the refining and petrochemical industries.
The culmination of the meeting will be the Safety Awards Reception and
Banquet from 6pm to 9:30pm on 13 May. The event celebrates and
honours the industry’s excellent safety achievements. Be sure to purchase
your tickets for this event when you register.
The Board of Certified Safety Professionals will grant CSP Continuance of
Certification (COC) points for attendance at the National Safety Conference
without pre-approval. The American Board of Industrial Hygiene (ABIH)
grants certification maintenance (CM) points.
Who Should Attend
Over 300 industry safety managers, engineers and experts are expected to
attend the conference. ■
For further information please visit the National Petrochemical & Refiners
Association’s website at www.npradc.org
Research and Development Center Garners International Recognition
The Research and Development Center (R&DC) is a leading research
facility, but what is the proof? To reach a level of excellence that is well-
defined and recognised worldwide demands precise measurement by an
independent and respected international standards organisation.
Reaching a high level of excellence does not happen overnight. It is a
long journey – a journey overseen by Dr Abdulrahman Vogel, R&DC’s
Quality Co-ordinator. Vogel, a mountaineer, compares striving for
excellence to climbing Mount Everest. “You climb a difficult mountain in
stages, taking time to make yourself safe and rested before continuing
up the cliff.” These stages are vital because testing occurs every year and
it is possible that your organisation could lose ground. As Vogel says, the
true key to excellence is sustainability. Meeting quality milestones is
valueless if you reach a high point only to slide back down the mountain.
When it came to selecting a standard to follow in the pursuit of
excellence, R&DC faced several choices. In the end, the European
Foundation for Quality Management (EFQM) was selected. “EFQM is a
well-respected international standard that fits well with our quality
philosophy at R&DC,” Vogel said. “We can progress in stages and earn
points as long as we are well focused on meeting the EFQM
requirements. In fact, the highest level of EFQM, the tip of the peak,
which equates to a maximum of 1,000 points, can take companies 15
years or more to reach.” Quality is just one aspect of R&DC’s drive for
excellence. “Excellence in everything we do, is the true objective,” Vogel
said. That encompasses more than doing good work.
The approach is QSE plus E, which stands for quality, safety and
environment plus excellence. To measure success, ISO and OHSAS
systems are applied to specific R&D-relevant areas. ISO stands for the
International Organization for Standardization, which sets standards in
several fields. OHSAS is an internationally recognised standard for
occupational health and safety management.
R&DC earned ISO 17025 accreditation in 2006 and recently obtained, as
a first in the Middle East, an accredited ISO 29001 certification for its
core R&D activities. ISO 29001 is the latest oil and gas industry sector-
specific quality management system, a result of intensive co-operation
between the American Petroleum Institute (API) and ISO. Next month,
the R&DC will be certified for its ISO 14001 environment-management
systems. These are important milestones. Take, for instance, the ISO
17025 accreditation, which is for competence of testing and calibration
laboratories. By earning that accreditation, R&DC’s analytical data are
respected around the world and can even be presented as part of legal
procedures or specification product sheets for international trade. That
is what a research institute requires – respect.
OHSAS 18001 certification, in addition to corporate safety standards, is
also vital, according to Vogel. This international health and safety
standard was developed to:
• reduce risk to employees, customers and suppliers;
• reduce or eliminate the damage associated with accidents at work;
• enhance staff morale and motivation;
• demonstrate legal and international compliance;
• ensure competitive advantage;
• build trust and confidence;
• achieve external recognition for safety excellence; and
• guarantee sustainability.
R&DC’s approach to excellence is leading the way not only for Saudi
Aramco, but also for the entire Middle East. This has not come easily.
Training staff to focus on excellence is a journey in itself, but the result
is worth the effort as professionals around the world are taking notice
of Saudi Aramco and its research and management capabilities. For
more information, visit www.saudiaramco.com ■
H Y D R O C A R B O N W O R L D V O L U M E 3 I S S U E 2 81
HSE.qxp 17/12/08 9:44 am Page 81