CARBON PARTNERSHIP FACILITY 1 CARBON PARTNERSHIP FACILITY APRIL 2014 SELLER PARTICIPANT TRAINING OVERVIEW OF PROGRAM AND CPA LEVEL MONITORING, PREPARATION OF MONITORING REPORTS AND VERIFICATION

description

Carbon Partnership Facility April 2014 Seller Participant Training Overview of Program and CPA Level Monitoring, Preparation of Monitoring Reports and Verification. Training on CDM Operations Plans and Sub-ERPA Contracting. presented by Dr. Balasankari. 02 April 2014. - PowerPoint PPT Presentation

Transcript of Carbon Partnership Facility April 2014 Seller Participant Training

Page 1: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 1

CARBON PARTNERSHIP FACILITY APRIL 2014 SELLER PARTICIPANT TRAINING

OVERVIEW OF PROGRAM AND CPA LEVEL MONITORING, PREPARATION OF MONITORING REPORTS AND VERIFICATION

Page 2: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 2

Training on CDM Operations Plans and Sub-ERPA Contracting

presented by

Dr. Balasankari

02 April 2014

Page 3: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 3

Training on CDM Operations Plans and Sub-ERPA Contracting

Basic Programme of Activities (PoA) structure

PoA

Coordinating / Managing Entity (CME)

CPA 1Project Owner

CPA 2Project Owner CPA 3

Project Owner

CPA 4Project Owner

CPA 5Project Owner

In some cases, CME itself may be the CPA implementer

Page 4: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 4

Training on CDM Operations Plans and Sub-ERPA Contracting

Basic needs of PoA monitoring

Implementation in line with registered PoA and CPA DD

Measurement of monitoring parameters at the required frequency

Maintenance of hard copy documents / records

Creation and maintenance of electronic database

Page 5: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 5

Training on CDM Operations Plans and Sub-ERPA Contracting

General monitoring data flow diagram

Meter Operator Officer CPA database

ManagerPoA database

CPA level

PoA level

Page 6: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 6

Training on CDM Operations Plans and Sub-ERPA Contracting

Components of effective PoA monitoring

Effective verification of generated project data

Deployment of trained monitoring staff

Creation / maintenance of up-to-date database

“ Both at PoA and CPA level ”

Page 7: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 7

Training on CDM Operations Plans and Sub-ERPA Contracting

Importance of data management systems

An effective data management system must be implemented at PoA and CPA level to:

Provide evidence for CERs generated

Collect and store the monitored data for verification

Avoid duplicate / discrepant records

Ensure quality of data generated

Page 8: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 8

Training on CDM Operations Plans and Sub-ERPA Contracting

Basic requirements of data management system

» Standard format / template across all CPAs

» Generation of unique ID for each record

» Completeness of data collected

» Correctness of data recorded

» Effective conversion from hard copy to electronic copy

» Centralized storage and update

Page 9: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 9

Training on CDM Operations Plans and Sub-ERPA Contracting

PoA level monitoring

A Project manager must be assigned at CME level to carry out the following tasks:

Monitor overall programme execution

Set up project management team

Arrange training for CPA implementers and other stakeholders

Support DOE during verification

Deployment of trained monitoring staff

Page 10: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 10

Training on CDM Operations Plans and Sub-ERPA Contracting

PoA level monitoring

Creation / maintenance of up-to-date database

“ A strong central database is needed for effective PoA implementation”

Must be up to date

Accurate and error free

Easy to retrieve details of CPAs

Page 11: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 11

Training on CDM Operations Plans and Sub-ERPA Contracting

PoA level monitoring

A Database administrator must be assigned at CME level to carry out following tasks:

Prepare templates for data collection / reporting

Collect data from CPAs

Maintain hard copy /soft copy documents collected from CPAs

Create a programme level central electronic database

Creation / maintenance of up-to-date database

Page 12: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 12

Training on CDM Operations Plans and Sub-ERPA Contracting

PoA level monitoring

A Verification officer must be assigned at CME level to carry out following tasks:

Provide CDM training to CPAs

Carry out site inspection to project locations

Inspect monitoring procedures implemented at CPA level

Cross-check data reported and data at project locations

Effective verification of generated project data

Page 13: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 13

Training on CDM Operations Plans and Sub-ERPA Contracting

PoA level monitoring

Documentations required at PoA level

Legal / contract agreement with all stakeholders

MOM of various co-ordination meetings

Operations manuals & training materials

Monitoring data from each CPAs

Monitoring survey reports

CPA inspection reports

Page 14: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 14

Training on CDM Operations Plans and Sub-ERPA Contracting

Best practices in PoA level monitoring

Decide all templates/formats and procedure to be followed before start of crediting period

Setup regional offices and distribute responsibilities

Have frequent meeting with all stakeholders

Make occasional site visit to project locations

Prepare quality operations manual / training materials on CDM monitoring

Page 15: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 15

Training on CDM Operations Plans and Sub-ERPA Contracting

CPA level monitoring

A Monitoring officer must be assigned at CPA level to carry out following tasks:

Install monitoring equipments as per monitoring plan

Train plant operators on data recording

Prepare reports based on monitored data

Support DOE during verification

Deployment of trained monitoring staff

Page 16: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 16

Training on CDM Operations Plans and Sub-ERPA Contracting

CPA level monitoring

Creation / maintenance of up-to-date database

• Primary records: One record book / register for each monitoring parameter

• Second records: Necessary support documents for each of the monitoring parameter

• Electronic database : Electronic conversion from hard copy records

Page 17: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 17

Training on CDM Operations Plans and Sub-ERPA Contracting

CPA level monitoring

A database administrator must be assigned at CPA level to carry out following tasks:

Create CPA level database

Maintain the hard copy records of data monitoring

Conversion of hard copy data to electronic copy

Submission of monitored data to CME

Creation / maintenance of up-to-date database

Page 18: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 18

Training on CDM Operations Plans and Sub-ERPA Contracting

CPA level monitoring

Best practices in documentationo Mention the date of recording/measurement clearly

o All records must be approved by supervisor/next level authority

o Do not correct / over write documents

o Any corrections made must be approved

o Store all documents/records in one single location

o Do an internal review of documents

Page 19: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 19

Training on CDM Operations Plans and Sub-ERPA Contracting

CPA level monitoring

Other documentations:

• Calibration records for meters

• Lab reports for any tests

• Monitoring sample survey records

• Legal / contract / loan agreements

• Technical specifications

• Operations manual

• Training materials

Page 20: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 20

Training on CDM Operations Plans and Sub-ERPA Contracting

CPA level monitoring

Verification of monitored data can be carried out by Monitoring officer itself

Check for duplicate data

Cross check hard copy data and electronic data

Check for consistency

Effective verification of generated project data

Page 21: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 21

Training on CDM Operations Plans and Sub-ERPA Contracting

Best practices in CPA level monitoring

Use only templates / formats given by CME for data recording

Install equipments only as per type / accuracy stated in PoA and CPA DD

Carry out calibration of equipments at required frequency

Communicate immediately on any issues identified in monitoring to CME

Maintain all project related documents / files in one central location

Page 22: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 22

Training on CDM Operations Plans and Sub-ERPA Contracting

Monitoring Surveys

Calculate sample size as per confidence level and error margin

Study and select suitable sampling method

Design standard template to record survey data

Carry out surveys at PoA level or CPA level as required

Finish the survey in stated time period

Page 23: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 23

Training on CDM Operations Plans and Sub-ERPA Contracting

Monitoring Surveys

Always have 20% additional samples for non-responses

Properly document survey results

Prepare a consolidated report

File all filled in survey template in order

Page 24: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 24

Training on CDM Operations Plans and Sub-ERPA Contracting

Quality control & quality assurance

• Two step quality verification of data to be done

• First quality check by monitoring officer at CPA level

• Second quality check by database administrator / inspection team at PoA level

• CPA level data can also be checked through field inspections by CME

Page 25: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 25

Training on CDM Operations Plans and Sub-ERPA Contracting

Quality control & quality assurance

CPA level check

PoA level check

Monitoring officerCPA database Plant records

ReportsDatabase administratorPoA database

Page 26: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 26

Training on CDM Operations Plans and Sub-ERPA Contracting

Monitoring - Verification - Issuance

Page 27: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 27

Training on CDM Operations Plans and Sub-ERPA Contracting

Stakeholders in monitoring to issuance

Collect data and submit

to CME

CPA implementer

Prepare monitoring

report

CME

Publish MR and site

verification

DOE

Issuance of CERs

UNFCCCReceive &

Pay for CERS

WB

1

2

3

4

5

6

Page 28: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 28

Training on CDM Operations Plans and Sub-ERPA Contracting

Step by step process in monitoring to issuance

Preparation of monitoring report (MR)

Hiring a DOE

Publishing of MR in UNFCCC site by DOE

Site visit and verification by DOE

Preparation of Draft Verification Report (DVR) by DOE along with • Corrective Action Required (CARs)• Clarifications (CLs)• Future Actions Required (FARs)

Page 29: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 29

Training on CDM Operations Plans and Sub-ERPA Contracting

Step by step process in monitoring to issuance

Response to DOE comments by CME

Review of CME responses by DOE

Finalizing Verification Report by DOE

Submission of issuance request to UNFCCC

Final review by UNFCCC and issuance of CERs

Page 30: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 30

Training on CDM Operations Plans and Sub-ERPA Contracting

Preparation of monitoring reportsStep 1:Consolidate the monitored data for the monitoring period

Step 2:List the documents/proofs for the monitored data

Step 3 :Calculate the CERs for the monitoring period

Step 4:Get the latest monitoring report format from CDM website

Step 5:Update the details in monitoring report

Step 6 :Cross check details/process stated in monitoring report with registered PoA and CPA DD

Page 31: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 31

Training on CDM Operations Plans and Sub-ERPA Contracting

Monitoring report - DOs & DONTs Confirm the first and last date of the reported

monitoring period

Provide detailed timeline of activities carried out

Add foot notes wherever required to provide supporting information

Mention any deviations from monitoring plan clearly with explanations

Explain in detail the CME level and CPA level monitoring done

Page 32: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 32

Training on CDM Operations Plans and Sub-ERPA Contracting

Monitoring report - DOs & DONTs

x Change the start date of crediting period

x Alter the format of CDM monitoring report

x Provide data without support documents

x Revise tools or methodologies referred

Page 33: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 33

Training on CDM Operations Plans and Sub-ERPA Contracting

What if deviations happen during implementation ?

Case 1:

• Minor changes like temporary deviation from monitoring plan, different accuracy levels of equipments, measurement locations, etc.

o DOE conducting the verification may assess the impact of changes.

o CERs may be deducted if there is significant impact in ER calculation

Page 34: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 34

Training on CDM Operations Plans and Sub-ERPA Contracting

What if deviations happen during implementation ?

Case 2:

• Major changes like project design or capacity or technology, crediting period, permanent change in monitoring plan, etc...

o PDD must be revised and Prior approval must be obtained from UNFCCC before issuance

o CER issuance will be very much delayed (minimum of another 6 months)

Page 35: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 35

Training on CDM Operations Plans and Sub-ERPA Contracting

Preparation for site verification

Arrange training on verification to all stakeholders

Prepare of list of documents for verification

Check for all database at CME and CPA level

Keep all support documents ready

Page 36: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 36

Training on CDM Operations Plans and Sub-ERPA Contracting

DOE Site verification process

• Kick-off meeting at CME office• Audit of documents at CME office• Site visit to CPA project locations• Inspection of equipments• Inspection of meters installed• Audit of documents at the CPA

implementer office• Check of monitoring practices• Other CDM requirements• Closure meeting at CME office

Page 37: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 37

Training on CDM Operations Plans and Sub-ERPA Contracting

Verification to Issuance - Time frame

• DOE uploads documents in UNFCCC website

• Request for Issuance kept in waiting queue (4 weeks)

• Completeness Check (1 week)

• Information and Reporting Check (3 weeks)

• Issuance kept for public review (4 weeks)

• Issuance of CERs

Page 38: Carbon Partnership Facility  April  2014  Seller  Participant  Training

CARBON PARTNERSHIP FACILITY 38

Training on CDM Operations Plans and Sub-ERPA Contracting

Questions & Discussions