“Capture the Spending” Measure Presentation Phase.

10
“Capture the Spending” Measure Presentation Phase

Transcript of “Capture the Spending” Measure Presentation Phase.

  • Slide 1
  • Slide 2
  • Capture the Spending Measure Presentation Phase
  • Slide 3
  • Project Premise Reiterated The Facilities Department has had issues with proper tracking of materials. Simply capturing materials purchases and applying them in the work order system will eliminate the wasteful spending that has been evident in this area and help to reduce costs. The initial spend for the project will be negligible because a CMMS is already in place that is capable of the tracking. The system users will just be asked to add a few steps in their work order processing.
  • Slide 4
  • SuppliersInputsProcessOutputsCustomers CFOImprovement points Transition the CMMS to capture materials. Verifies improvementCFO CEOAdvisesAlignmentCEO Purchasing ManagerProvides dataVerifies informationPurchasing Manager Facilities ManagerCoordinates effortVerifies completionFacilities Manager CMMS Super userProcesses dataVerifies progressCMMS Super user UsersProcesses dataVerifies processUsers
  • Slide 5
  • Slide 6
  • Process Map
  • Slide 7
  • Step Description Observations 1 Enable CMMS for Data One 8 hour day for super user to enable, then complete 2 Bulk Stock Item? Time data N/A 3 No Time data N/A 4 W/O #s Reqd Each generated work order takes approx. 2 minutes 5 Listing material data Depending on the materials approx. 15 minutes 6 Acct auto-correlates Verification is no extra time 7 Yes Bulk material will require a 2 minute W/O Process Observation Worksheet
  • Slide 8
  • Check sheet DateUserCompliantNon-compliant/ReasonNotes 10-22-13Tech AYes 10-22-13Tech BNoBulk stock orderReview Process 10-23-13Tech CYes Project Name: Capture the Spending Output Metric: Material Tracking
  • Slide 9
  • Spaghetti Diagram
  • Slide 10
  • Data Collection The users will enter the materials data each time they use supplies/parts The superuser will track the materials data real-time through CMMS auto required fields. Accounting will report variances and materials budget improvements monthly.
  • Slide 11
  • Charted Projection