1 [Type the document title] Capital Works Monthly Review February 2019

Transcript of Capital Works Monthly Review - City of Mackay · 2019-03-21 · Shade Sail Replacement - Community...

Page 1: Capital Works Monthly Review - City of Mackay · 2019-03-21 · Shade Sail Replacement - Community Areas 2019AMD $11,019 Blacks Beach Park 2018 $209,102 W4Q2 - Roadwork/parking upgrades

1 [Type the document title]

Capital Works

Monthly Review

February 2019

Page 2: Capital Works Monthly Review - City of Mackay · 2019-03-21 · Shade Sail Replacement - Community Areas 2019AMD $11,019 Blacks Beach Park 2018 $209,102 W4Q2 - Roadwork/parking upgrades

Page 2

Capital Works Monthly Review > February 2019

OVERVIEW .......................................................................................................................... 3

SAFETY .............................................................................................................................. 4

1.1. Incidents and Injuries ................................................................................................. 4 1.2. Lost time Injuries & Days Lost ................................................................................... 5

CAPITAL PROJECT UPDATES ................................................................................... 6

2.1. Capital Summary Report ........................................................................................... 6 2.2. Financial Performance ............................................................................................... 6 2.3. Capital Projects Status .............................................................................................. 8 2.4. Key Contracts Approved for February ........................................................................ 9

MAJOR PROJECT UPDATES..................................................................................... 10

3.1 Resource Centre of Excellence ............................................................................... 10 3.2 Mackay Regional Sports Precinct ............................................................................ 11

ROADS & TRANSPORT PROJECT UPDATES ...................................................... 13

4.1 Camilleris Road Causeway Reconstruction ............................................................. 13 4.2 Bakers Creek Ferris Gully Ch 3350-4200 Landscaping Works ................................ 15

WATER & SEWERAGE PROJECT UPDATES ........................................................ 17

5.1 60080-rwi-New Eton Bore ........................................................................................ 17 5.2 Sewer Renewals - Replacement: Mackay and Sarina ............................................. 19 5.3 Mirani STP Effluent Storage Expansion ................................................................... 20

Page 3: Capital Works Monthly Review - City of Mackay · 2019-03-21 · Shade Sail Replacement - Community Areas 2019AMD $11,019 Blacks Beach Park 2018 $209,102 W4Q2 - Roadwork/parking upgrades

Page 3

Capital Works Monthly Review > February 2019

OVERVIEW

This report is for Capital Works Department activities during the month of February 2019. Significant

items in this period include:

• The safety of our staff, contractors and the public continue to be our top priority. In February the

Department recorded four incidents, one (1) relating to the injury of Mackay Regional Council (MRC) employee and three (3) relating to asset damage. Given the high potential of MCR injury incident the Safety Department in conduction with the Capital Directorate has initiated an internal investigation to assess the root cause and look at ways to ensure adequate controls are in place to mitigate the risk for future works.

• For the month of February $6.1M of work was completed. YTD expenditure is $76.2M against a YTD forecast of $79.2M representing a 96.2% completion rate.

• Continued wet weather has again impacted progress on several projects with measures being put in place where possible to recover lost time.

• Eton water supply improvements are operational delivering softer water to Eton residents.

• Mackay Regional Sports Precinct works are substantially completed for forecast opening of the 9th

March 2019.

• Lamberts Beach NDRRA works has commenced and Midge Point works continues on schedule.

Stewart Furness Director Capital Works

Page 4: Capital Works Monthly Review - City of Mackay · 2019-03-21 · Shade Sail Replacement - Community Areas 2019AMD $11,019 Blacks Beach Park 2018 $209,102 W4Q2 - Roadwork/parking upgrades

Page 4

Capital Works Monthly Review > February 2019

SAFETY

1.1. Incidents and Injuries

The incident statistic details a summary of the Capital Works safety incident performance. Capital Works

aspires to achieve zero harm with a stretch target of zero injuries

February 2019 Summary:

One (1) injury to a MRC employee was reported in February:

• A worker who was undertaking work on the edge of an excavation that was barricaded with plastic fencing sustained minor bruising and grazing when they came into contact with a close passing MRC truck.

➢ Recommendations from the investigation into this incident are being implemented in order to

improve safety on worksites involving excavations and heavy plant.

Three (3) asset damage incidents were reported in February:

• A truck and trailer parked near a gate entrance to fill a water pod hit and damaged the gate, when the gate sensors didn't detect the trailer was still within the closing area.

• A truck being reversed into a driveway hit and ran over a letterbox.

• A passing non-staff member vehicle flicked up a rock, hitting and damaging the windscreen of a MRC truck.

Page 5: Capital Works Monthly Review - City of Mackay · 2019-03-21 · Shade Sail Replacement - Community Areas 2019AMD $11,019 Blacks Beach Park 2018 $209,102 W4Q2 - Roadwork/parking upgrades

Page 5

Capital Works Monthly Review > February 2019

1.2. Lost time Injuries & Days Lost

Capital Works aspires to achieve zero Lost Time Injuries by improving safety performance by developing

a proactive safety culture and implementing best practice safety management across all business areas.

00 0

1

2

3

4

5

0

1

2

3

4

5

2018-19

CW Total Days Lost CW Total LTIs

Department 2018-19

Contract Management

Major Projects

Project Management Office

Transport & Infrastructure Projects

Water & Sewerage Projects

Design Services

Capital Works Total 0 0

Page 6: Capital Works Monthly Review - City of Mackay · 2019-03-21 · Shade Sail Replacement - Community Areas 2019AMD $11,019 Blacks Beach Park 2018 $209,102 W4Q2 - Roadwork/parking upgrades

Page 6

Capital Works Monthly Review > February 2019

CAPITAL PROJECT UPDATES

2.1. Capital Summary Report

The delivery of the 2018/19 capital program remains a significant focus of Council. The following capital

information provides a financial summary of the status of delivery against our baselined budget position

and includes the outcomes, of the recent December budget review.

The original budget was adopted by Council in July. This was amended in August to take into account

carryovers and other adjustments. Further adjustment to the capital program has occurred as part of

budget reviews carried out in September and December. To date, an amount of $13M has been deferred

to future financial years. Overall the approved budget has decreased by $10.4M comparatively to the

original budget (including carryover).

The 2018/19 capital works program is made up of a total of 506 projects with a current approved budget

of $135.6M. Delivery for the capital program is on track with 96% of the forecast YTD spend being

incurred.

2.2. Financial Performance

The table below summarises the year to date financial summary for the 2018/19 Capital program.

The ~$1.8M variance between the approved budget and the current forecast is mainly attributable to the

following:

• Reporting timelines - $1.7M of new projects approved as part of the December Quarterly Review are

not reflected in the current forecast as the forecasting process was completed prior to the December

quarterly approvals. (Major Contributors – BSIP Mackay Stage 2 Construction, Stormwater Relining

Design and the Mackay Tourism Kiosk). This will be rectified as part next month’s reporting.

Department

Original Budget (inc

Carryover) Approved Budget Current Forecast YTD Forecast YTD Actuals

% Spent of

YTD

Forecast

% Spent of

Approved

Budget

Major Projects 51,812,995 47,253,294 46,441,916 32,099,339 30,641,878 95.46% 65%

Waste 410,653 649,359 416,400 250,754 312,645 124.68% 48%

Water 12,320,613 12,831,834 14,479,020 5,454,162 5,221,899 95.74% 41%

Sewerage 15,967,464 15,137,699 14,039,816 6,520,833 6,232,990 95.59% 41%

Corporate Revenues and Expenses 2,000,000 2,000,000 2,000,000 0 0 0.00% 0%

Works For Queensland Round 2 Funding Project 7,126,380 6,957,380 7,193,120 5,543,319 5,471,420 98.70% 79%

NDRRA 9,339,749 9,843,544 9,856,429 2,397,756 2,940,355 122.63% 30%

Transport and Infrastructure Projects 47,090,654 40,950,045 39,385,398 26,934,537 25,395,526 94.29% 62%

Total 146,068,508$ 135,623,154$ 133,812,098$ 79,200,699$ 76,216,713$ 96.23% 56.20%

Capital Expenditure 137,309,142 126,009,385 124,386,264 76,804,812 73,562,761 95.78% 58.38%

Operational Expenditure 8,759,366 9,613,770 9,425,834 2,395,888 2,653,952 110.77% 27.61%

Capital Projects Expenditure 2018/19February 2019

Page 7: Capital Works Monthly Review - City of Mackay · 2019-03-21 · Shade Sail Replacement - Community Areas 2019AMD $11,019 Blacks Beach Park 2018 $209,102 W4Q2 - Roadwork/parking upgrades

Page 7

Capital Works Monthly Review > February 2019

Capital Expenditure Forecast 2018/19

As at 28 February 2019, $76.2M of work has been completed.

The main variances between actuals and forecast for the month are identified in the below table.

Project Description Comments Variance

10390 Plant & Equipment - Replacement Program

Delays to several plant replacement items. These include larger plant such as a several trucks and a forklift where supply and weather issues have caused delays. Also, several light vehicles have been delayed and are expected to be delivered in early March. -$685,039

56006 Baxter Dr Extension to Tamron St

Contractors onsite works disrupted due to wet weather. Claim significantly less than anticipated. Forecast will be amended to reflected new works program. -$416,395

73040 Mirani Liquid Stream Upgrade

Contractor delayed commencing while contractual issues were addressed so have not progressed as anticipated. Revised program and cashflow have now been provided and will be reflected in future forecast. -$313,382

56059 Milton St/Boundary Rd Intersection - Signalisation & 4 Lanes

Project expenditure adjusted as a result of an over accrual in the prior month for service relocation costs. Project expenditure is now realigned.

-$283,711

60080 RWI-New Eton Bore Project expenditure adjusted as a result of an over accrual in a previous month. Project expenditure is now realigned with program of works. -$255,388

Improvement initiatives / focus areas

Several safety incidents occurred during the month and this has initiated a re-focus for the department on

safety, particularly the link between heat and fatigue. Crews are trialling cooling head scarfs as well as

increased small breaks during periods of excessive heat. This, combined with additional safety focus during

tool box talks, has raised the awareness and is a good example of our staff pro-actively managing safety

risks. At the department Workplace Health and Safety committee meeting an initiative to invite a different

field crew to each meeting was agreed with the aim of providing all staff a further opportunity to provide

safety input.

Page 8: Capital Works Monthly Review - City of Mackay · 2019-03-21 · Shade Sail Replacement - Community Areas 2019AMD $11,019 Blacks Beach Park 2018 $209,102 W4Q2 - Roadwork/parking upgrades

Page 8

Capital Works Monthly Review > February 2019

2.3. Capital Projects Status

The above graph shows the status of capital projects as at the end of February 2019. Please note the

completed projects can include projects commenced in prior years which were finalised in July and includes

projects with carryover expenditure. The following list identifies the projects marked complete in during the

month.

Description

Budget Approval

Year

Total Project

Costs

SES Building Upgrade - Ness Street 2016 $1,976,441

Botanic Gardens Shade Sail Replacement 2019 $15,457

Beach Outlet Creation at Cod Hole 2015 $3,112,474

Horse and Jockey Rd - Lansdowne Rd HEADAD $65,532

W4Q2 - Drainage upgrades - Hampden Court W4Q2 $129,403

Lucas Paddock Rd, Pinnacle - Culvert replacement 2018 $254,866

Land Acquisition - Ferris Gully - 3350 to 4200 2015 $6,137,569

Nebo Rd WTP - light pole repairs HEADWT $12,369

Marian WTP Chemical Dosing Hose Replacement HEADWT $5,827

Nebo Rd WTP Washwater Pump Replacement HEADWT $8,934

Main PRV valve replacement - Alligator Ck 2019AMD $8,037

SWRF Chemical Dosing Pipework Replacement (Alum/Caustic) HEADST $23,949

Shade Sail Replacement - Community Areas 2019AMD $11,019

Blacks Beach Park 2018 $209,102

W4Q2 - Roadwork/parking upgrades - Casey Avenue W4Q2 $1,207,675

Land held for resale YEARLY $11,517

SPS - Schmidtkes Rd Pump Station 2010 $3,214,127

Page 9: Capital Works Monthly Review - City of Mackay · 2019-03-21 · Shade Sail Replacement - Community Areas 2019AMD $11,019 Blacks Beach Park 2018 $209,102 W4Q2 - Roadwork/parking upgrades

Page 9

Capital Works Monthly Review > February 2019

2.4. Key Contracts Approved for February

A list of key contracts that have been finalised and approved for the month is given below. In total these

contracts are valued at ~ $1,218,653 for February 2019. There are smaller packages of works (not included

below) and ancillary contracts that have also been awarded for the month of February linked to capital.

Contract Design /

Construction

Amount

Award

(ex GST)

Contractor

MRC 2019-049 Construction of Sarina

Wash Bay

Construction $ 53,912.00 Dowdens Pumping and

Water Treatment

Quote 2019-050 Shakespeare Street

Drainage

Design $ 53,510.00 AECOM Australia Pty Ltd

Quote 2019-052 Northern Beaches

Community Hub

Design $169,700.00 Ethos Urban

Quote 2019-054 Rocky Waterholes

Culvert Replacement

Construction $175,281.00 Seaforth Civil Pty Ltd

Quote 2019-059 Mackay Waterfront

PDA - Electrical, Lighting,

Telecommunications

Design $ 61,815.00 SPA Consulting Engineers (QLD) Pty Ltd

Quote 2019-064 North Mackay Rotary

Lookout

Design $ 63,450.00 Bold Architecture and Interior Design Pty Ltd

Quote 2019-066 River and Rain Alert

Stations

Design $50,320.00 AECOM Australia Pty Ltd

SQ 2019-024A Pratt Street WMR Works

– Concrete restoration works

Construction $42,419.00 Beagle Boys Constructions

SQ 2019-026 Louise Street, Mirani –

concrete restoration works

Construction $48,246.00 Beagle Boys Constructions

Total $1,218,653.00

Page 10: Capital Works Monthly Review - City of Mackay · 2019-03-21 · Shade Sail Replacement - Community Areas 2019AMD $11,019 Blacks Beach Park 2018 $209,102 W4Q2 - Roadwork/parking upgrades

Page 10

Capital Works Monthly Review > February 2019

MAJOR PROJECT UPDATES

3.1 Resource Centre of Excellence

Project Overview

Activity Delivery Start

Date

Completion Date

% Complete

Detailed Design External March 2019 May 2019 0

Construction Procurement

Contracts May 2019 June 2019 0

Construction External July 2019 January 2020 0

Finalisation External January 2020 0

The objective of The Resource Centre of Excellence (RCoE) is to provide a world class training centre of

excellence for the resource sector to be located at 65 Crichtons Road Paget. The project will involve the

construction of a large industrial shed, extending to a covered hardstand area at the rear of the building.

The industrial shed will have adjoining building housing office space, training rooms and laboratories. A

carpark, site service infrastructure and landscaping will also be included. The industrial shed will house

an Underground Mining Simulated Training Facility (UMSTF) for use by the resources sector.

Recent Project Activities

✓ The project currently has an estimated budget of $7.5M, awaiting costings from Detailed Design

package

✓ Tenders are currently being assessed for the Detailed Design

✓ Consultant has been engaged for Geotechnical Survey

✓ Council continues to liaise with the Resource Industry Network (RIN) to scope the end user

requirements

1600m2 hardstand under

cover (secured/enclosed

by fencing)

Photo 1 – Conceptual Site Layout for the RCoE

Page 11: Capital Works Monthly Review - City of Mackay · 2019-03-21 · Shade Sail Replacement - Community Areas 2019AMD $11,019 Blacks Beach Park 2018 $209,102 W4Q2 - Roadwork/parking upgrades

Page 11

Capital Works Monthly Review > February 2019

3.2 Mackay Regional Sports Precinct

Project Overview

Activity Delivery Start

Date

Completion Date

Budget Actual

to date

% Complete

Preliminary Design External 01/03/17 30/09/17

$23,798k $23,349k*

100

Detailed Design External 13/11/17 01/06/18 100

Construct External 19/12/17 16/01/19 98

Commissioning External 04/12/18 Feb 19 98

Projected Facility Opening

Mar 19 0

*includes projected February claim Recent Project Activities

✓ Pool Plant Building complete & staff training has been undertaken;

✓ LTS Pool complete, pool covers installed;

✓ 25m Pool complete, lane ropes & pool covers installed;

✓ 50m Pool complete, lane ropes & pool covers installed

✓ Aquatic Change Room complete;

✓ Aquatic Café/Reception complete and principal supplied equipment installed;

✓ Athletic Café complete and principal supplied equipment installed;

✓ Additional Shelving throughout the complex installed;

✓ Grandstands assembled & installed;

✓ Shade Pods assembled & installed;

✓ Commonwealth Games Legacy equipment relocated to Athletic Storage Shed;

✓ Athletics clubs relocated their equipment to Athletic Storage Shed;

✓ Carpark line marking complete;

✓ Event Lighting installed & tested;

✓ Concreting of all pathways complete;

✓ Landscape furniture installed

✓ Soft Landscaping & irrigation underway.

Page 12: Capital Works Monthly Review - City of Mackay · 2019-03-21 · Shade Sail Replacement - Community Areas 2019AMD $11,019 Blacks Beach Park 2018 $209,102 W4Q2 - Roadwork/parking upgrades

Page 12

Capital Works Monthly Review > February 2019

Photo 1 – Drone shot of Complete MARC Site

Photo 2 - Overhead view of Athletic Track

Page 13: Capital Works Monthly Review - City of Mackay · 2019-03-21 · Shade Sail Replacement - Community Areas 2019AMD $11,019 Blacks Beach Park 2018 $209,102 W4Q2 - Roadwork/parking upgrades

Page 13

Capital Works Monthly Review > February 2019

Photo 3 - 25m Pool under lights

ROADS & TRANSPORT PROJECT UPDATES

4.1 Camilleris Road Causeway Reconstruction

Overview

Camilleris Road Causeways Reconstruction project is funded by Queensland Government’s Works for

Queensland (Round 2) program. Major project works includes upgrade of two causeways to improve flood

immunity and accessibility for the residents living along Camilleris Road.

The driver for the project was direct representations from the residents to Councillors highlighting risk and

access restriction during rainfall especially for medical reasons and for picking up their children after

schools.

Project Overview

Activity Delivery Start Date End Date Budget Actual % Complete

Design Internal 01/10/2017 01/03/2018 $67,000 $67,000 100%

Construction External 09/07/2018 01/02/2019 $1,177,800 $1,065,000 100%

Page 14: Capital Works Monthly Review - City of Mackay · 2019-03-21 · Shade Sail Replacement - Community Areas 2019AMD $11,019 Blacks Beach Park 2018 $209,102 W4Q2 - Roadwork/parking upgrades

Page 14

Capital Works Monthly Review > February 2019

Recent Project Activities ✓ All site works completed.

✓ Side tracks on both causeways removed.

✓ Landscape establishment ongoing.

✓ Practical completion granted on 1 February 2019 after the submission of as-constructed and

finalisation documents.

Figure 1 – Causeway 1 after early January rain.

Figure 2 – Causeway 2 after mid-January 2019 rain

Page 15: Capital Works Monthly Review - City of Mackay · 2019-03-21 · Shade Sail Replacement - Community Areas 2019AMD $11,019 Blacks Beach Park 2018 $209,102 W4Q2 - Roadwork/parking upgrades

Page 15

Capital Works Monthly Review > February 2019

4.2 Bakers Creek Ferris Gully Ch 3350-4200 Landscaping Works

Overview

Bakers Creek Ferris Gully Ch 3350-4200 Landscaping Works (North of Schmidtkes Road and south of

Sports Precinct) project is part of the “Bakers Creek Stockroute Road East” (BCSRE) Catchment

Stormwater Trunk Infrastructure. It consists of a low flow open channel stormwater drain designed using

the principles of water sensitive urban design (WSUD). Initial works involved the channel excavation and

these works are for the landscape/revegetation works as part of the water quality management system.

The project aligns with Council’s strategy to address trunk drainage requirements for the ultimate

development of the Bakers One Catchment providing an appropriate level of service and flood immunity

for land and property during weather events (up to 100-year ARI event).

Project Overview

Activity Delivery Start Date End Date Budget Actual % Complete

Design External 01/03/2016 01/02/2017 $300,000 $300,000 100%

Construction (land acquisition, earthworks and drain)

External 09/07/2018 30/12/2018 $4,049,000 $4,049,000 100%

Landscaping External 15/02/2018 28/02/2019 $2,305,900 $2,332,100 98%

Recent Project Activities

✓ All amelioration and topsoil work complete.

✓ Coir matting installed and planting complete.

✓ Turf 95% complete. Wet weather delay in turf laying. The remainder of the turf to be laid by the end

of Feb 2019.

✓ Irrigation system installed and operational.

✓ Project Revised Practical Completion due 28 Feb 2019, due to pending items as remainder of the

turf placement and time required for re-review of the plant numbers design vs. as-planted.

✓ Maintenance period of 18 months to commence after the Practical Completion. Maintenance

Management plan to be submitted by the contractor for review and approval by MRC.

Page 16: Capital Works Monthly Review - City of Mackay · 2019-03-21 · Shade Sail Replacement - Community Areas 2019AMD $11,019 Blacks Beach Park 2018 $209,102 W4Q2 - Roadwork/parking upgrades

Page 16

Capital Works Monthly Review > February 2019

Figure 1 – Control line B- After rain end of Jan 19.

Figure 2 – Ferris Drain control line A-looking north from Schmidtkes Rd.PDATE E

Page 17: Capital Works Monthly Review - City of Mackay · 2019-03-21 · Shade Sail Replacement - Community Areas 2019AMD $11,019 Blacks Beach Park 2018 $209,102 W4Q2 - Roadwork/parking upgrades

Page 17

Capital Works Monthly Review > February 2019

TER & SEWERAGE PROJECT UPD ATES TER & SEWERAGE PROJECT UPDATES

WATER & SEWERAGE PROJECT UPDATES

5.1 60080-rwi-New Eton Bore

Overview

Mackay Regional Council (Council) manages water supply schemes for several small townships within the

region including Eton. These water supply schemes generally consist of raw water drawn from bores, a

water pump station, chlorination system, treated water storage and reticulation network.

Following engagement with the Eton community in late 2016 the aesthetic water hardness was identified

as a key concern to which Council made a commitment to find a solution. The proposed project works

includes a new production bore drilled to access better quality water from a shallow aquifer and direct

treatment with raw water being softened with the use of an ion exchange softening process. In addition to

this, chemical dosing equipment to bring about PH correction/adjustment will also be installed.

The geotechnical investigations, trial bores and construction of a new production bore were completed in

May 2018.

Project Overview

Activity Delivery

Start

Date

Completion

Date Budget Actual %

Complete

Project Management & Supervision

Internal 1/07/2017 31/06/2019 $43,615 $37,043 90%

Internal Design - Bore and Treatment Plant

Internal 1/07/2017 31/07/2018 $68,809 $63,709 100%

External Design - Bore and Treatment Plant

External 1/10/2017 21/11/2018 $132,768 $132,768 100%

Bore Construction External 12/02/2018 15/05/2018 $169,550 $169,950 100%

Treatment Plant Design and Construct and Commission

External 18/06/2018 01/12/2018 $875,850 $822,736 95%

Additional funds have been obtained from 55277- W4Q2 Koumala Water Upgrades W4Q2, increasing the

Construction Contract Budget to $875,850.

Contractor claims are milestone linked and not progressive, with the 90% milestone reached in late mid-

February. The Contractor will be eligible to claim outstanding milestone once proof of performance testing

results is submitted and any defect rectification is complete.

Page 18: Capital Works Monthly Review - City of Mackay · 2019-03-21 · Shade Sail Replacement - Community Areas 2019AMD $11,019 Blacks Beach Park 2018 $209,102 W4Q2 - Roadwork/parking upgrades

Page 18

Capital Works Monthly Review > February 2019

Recent Project Activities

✓ Works on some minor Civil works within the site enclosure delayed by wet weather but all complete

by end of February including gravel surfacing.

✓ All electrical supply works are complete, and all electrical equipment and instrumentation installed,

commissioned and connection to the Council telemetry network complete.

✓ From the end of January, the new softening plant was operated continuously, with Network operators

continuing to optimise plant operating parameters to achieve the best possible water hardness

values. Eton’s water is now within the Australian Drinking Water Guideline values. ✓ Driveway access improvements details being finalised with TMR. This work expected to be

completed by internal resources before end of the FY.

Figure 1 – Bulk Salt unloading crane

Page 19: Capital Works Monthly Review - City of Mackay · 2019-03-21 · Shade Sail Replacement - Community Areas 2019AMD $11,019 Blacks Beach Park 2018 $209,102 W4Q2 - Roadwork/parking upgrades

Page 19

Capital Works Monthly Review > February 2019

Figure 2 – Containerised treatment plant and salt unloading crane in position.

5.2 Sewer Renewals - Replacement: Mackay and Sarina

Overview

As a part of maintaining the condition of the sewer reticulation network, Mackay Regional Council has a program to inspect its gravity sewer mains through Closed Circuit Television (CCTV) works. CCTV work undertaken has identified several sewer mains that require repair works. The most cost- effective approach to sewer renewals is to insert a structural liner into the existing sewers which restores the sewer to as new condition. Relining has the added benefit of sealing all pipe joints reducing the ingress of groundwater which is a major component of inflow and infiltration that leads to surcharging within the sewerage networks. The intent of the Contract is to rehabilitate assets by “no dig” methods via in-situ lining of deteriorated sections of gravity sewer to restore the structural integrity, hydraulic capacity and efficiency of the network. This rehabilitation constitutes a key part of the efficient and systematic management of the sewer system by minimising replacement costs and minimising the risk of emergency repair costs, damage to property and the receiving environment and related service disruptions. The sewer repair sites are located at various sites within the Mackay and Sarina regions. The methods of repair include junction sealing and both point patching and full relining. The works include all necessary customer consultation, CCTV inspections, relining, clean up, removal of all construction items, and the restoration of property and other related work where required.

• 21.3 km of CCTV inspection in Mackay

• 3.4 km of sewer relining in Sarina (part funded by W4Q2)

• 8.9 km of sewer relining in Mackay

Page 20: Capital Works Monthly Review - City of Mackay · 2019-03-21 · Shade Sail Replacement - Community Areas 2019AMD $11,019 Blacks Beach Park 2018 $209,102 W4Q2 - Roadwork/parking upgrades

Page 20

Capital Works Monthly Review > February 2019

The works have been Contracted to Interflow Pty Ltd for relining commencement in November 2018. Project Overview

Activity Delivery Start

Date

Completion Date

Budget Actual % Complete

Project Management incl, Supervision and internal Design

Internal 01/07/2017 31/07/2019 $167,555 $109,039 65%

Sarina (W4Q2) Construction

External 24/10/2018 28/02/2019 $493,664 $487,000 98%

Mackay Construction incl. Sarina works cross subsidy

External 24/10/2018 28/06/2018 $2,308,298 $1,052,315 45%

Construction Internal 01/07/2017 28/06/2019 $22,240 $2,440 10%

Recent Project Activities

✓ Relining pipe installation is 100% complete in Sarina (Package A) with the remaining works – only 1

Junction Seal is outstanding.

✓ Sewer pre-cleaning and CCTV inspections commenced in Mackay in the 3rd week of November 2018

and pipe relining commenced on 3 December 2018. Some days lost to rain delay through December,

January and February, however works generally progressing well with majority of large diameter

main relining complete by end of February. An extension of time claim for Package A & B is currently

being assessed (due to wet weather and an increased numbers of Junction Seals) for a revised date

for Practical Completion of 24 March 2019.

✓ The Contractor is planning to commence the 3rd and final package of works (C) earlier than was

expected and may be finished earlier than what was previously scheduled – late May versus by 30th

June 2019.

5.3 Mirani STP Effluent Storage Expansion

Overview

License conditions for the Mirani Sewerage Treatment Plant only allow for wet weather discharges from

the existing 60ML effluent storage dam when a dilution rate of 5:1 is achieved in the adjacent cane drain –

this is generally only when there is a significant rain event. Under current inflow conditions, the 60ML dam

frequently reaches capacity due to the restrictions on discharging and the existing recycled water users

(the adjacent cane farm and the Pioneer Valley Golf Course) having limited capacity for use. A water

balance assessment concluded that, to limit the risk of out of license discharges, storage capacity needed

to be increased from 60ML to 360ML.

This project is being partly funded by the State Government through the Local Government Grants and

Subsidies Program and incudes construction of a new 300ML effluent storage dam as well as a transfer

pump station at the existing 60ML dam and a pipeline between the two dams.

Page 21: Capital Works Monthly Review - City of Mackay · 2019-03-21 · Shade Sail Replacement - Community Areas 2019AMD $11,019 Blacks Beach Park 2018 $209,102 W4Q2 - Roadwork/parking upgrades

Page 21

Capital Works Monthly Review > February 2019

Project Overview

Activity Delivery Start

Date

Completion Date

(Target)

Budget Actual % Complete

Project Management

Internal 01/07/2015 (01/12/2019) $221,000 $171,466 97%

Land Acquisition Internal 11/10/2016 22/12/2017 $400,000 $359,500 100%

Design External 16/10/2017 19/03/2018 $115,000 $146,250 100%

Construction External 20/06/2018 (22/11/2018) $3,206,000 $2,978,056 98%

Recent Project Activities

✓ Commissioning of pump station with mains power completed early February. Contractor addressing

a few minor defects identified at the commissioning. Transfer pump station and new dam now

available for operations.

✓ Energisation of the switchboard adjacent to the farmer’s outlet at the Dam still outstanding. Ergon

has now promised this for mid-March 2019. This not impacting use of dam.

✓ Contractor addressing Council feedback on submitted “as constructed” documentation.

✓ Several minor issues identified at “On maintenance” inspection being attended to.