Keith CouchCapital Rail Constructors
January 2016
Dulles Corridor Metrorail ProjectPhase 2, Package A
Capital Rail Constructors:Quarterly Update to MWAA Board of Directors
1. Safety
2. Schedule
3. Labor Statistics
4. DBE Subcontracting
5. Progress
Agenda
Scope
Current Program Focus:Decision Making/BehaviorHand Safety
Since Notice to Proceed:Man-Hours: 1,614,321(As of 11/28/2015)Recordable Rate: 0.86 (vs. National Average: 3.30) Lost Time Rate: 0.12(vs. National Average: 1.70)
SafetyCrane Training
Design Status
Design Status Overall: 98%* CompleteGeotechnical Work 100% Complete
Field Survey Work 100% Complete
Track Design 100% Complete
Systems Design 99% Complete
Civil Design 99% Complete
Utilities Design 100% Complete
Facilities Design (Stations) 95% Complete
Wayside Design 98% Complete
Structures Design (Aerial Guideway/3 Bridges) 100% Complete
*Percent Complete through November 2015 based on CRC Invoiced Value.
Construction Status: 12.2% Design Status: 98.5%
Overall Project StatusDesign and Construction: 28%
141 Drilled Shafts installed – 72% complete
Aerial Guideway: Drilled Shafts
Aerial Guideway: Drilled Shafts
141 Drilled Shafts installed – 72% complete
Aerial Guideway: Columns
123 Columns installed – 58% Complete
Aerial Guideway: Columns
123 Columns installed – 58% Complete
102 Caps poured – 58% complete
Aerial Guideway: Caps
Aerial Guideway: Caps
102 Caps poured – 58% complete
Aerial Guideway: Temporary BridgesCrossing Horsepen Run at Yard Leads
Status:• 12 Girders in Review with MWAA• 17 Girders in Review with CRC Engineering• 31 Girders to be Reviewed by January 2016
Goal:• Disposition of all Girders by the end of January 2016
Aerial Guideway: 96” Girders
GIRDERS FABRICATED
84” = 114 of 338
72” = 22 of 88
GIRDERS INSTALLED
84” = 60 of 338
72” = 12 of 88
Aerial Guideway: 84” and 72” Girders
*As of 9/28/20158 Decks poured – 5% complete
Aerial Guideway: Decks
Aerial Guideway: Straddle Bents
2 of 8 Straddle Bents installed
Enabling Work Nov 2014 – Jul 2015Excavation & Foundations Jul 2015 – Jun 2016Precast & Steel Jul 2016 – Apr 2017
Facilities: Dulles Airport Station
Facilities: Innovation Center Station
Enabling Work Nov 2014 – Apr 2015Excavation & Foundations May 2015 – Oct 2015Precast & Steel Dec 2015 – May 2016
Facilities: Herndon Station
Enabling Work Jan 2015 – Sep 2015Excavation & Foundations Oct 2015 – Mar 2016Precast & Steel Apr 2016 – Sep 2016
Facilities: Reston Town Center Station
Enabling Work Feb 2015 – Dec 2015Excavations & Foundations Dec 2015 – Aug 2016Precast & Steel Sep 2016 – Jan 2017
Facilities: Loudoun Gateway Station
Enabling Work Jan 2016 – May 2016Excavations & Foundations May 2016 – Nov 2016 Precast & Steel Dec 2016 – May 2017
Loudoun Gateway Station
Facilities: Ashburn Station
Ashburn Station
Enabling Work May 2016 – Sep 2016Excavations & Foundations Sep 2016 – Mar 2017 Precast & Steel Apr 2017 – Sep 2017
Support of Excavation & Foundations: Apr 2015 – Apr 2016Structural Steel & Bridge Deck: Oct 2015 – July 2016
Bridges: Broad Run
Broad Run Bridge
Support of Excavation & Foundations: CompleteStructural Steel & Bridge Deck: Spring 2016
Bridges: Centreville Road
Cargo 5 – Utility Relocation
Civil: Existing Utilities
Completed:• Gas and communication
utility relocations on airport property
• Electrical relocations to enable Dulles Station excavation
• Water line relocations on Autopilot Drive
Ongoing• Water and sanitary sewer
line relocation at Dulles Station
• Lighting relocations• Utility relocations at wayside
locations (TPSS 12, 13, 18)
Civil: 34.5 kV Ductbank
34.5 kV DuctbankInstallations:• N07 – EB DIAAH/DTR Median
between Herndon Station & Reston Pkwy
• N08 – North and East of Herndon Station
• N09 – East of Horsepen Bridge/ West of Centreville Rd/North of Innovation Station/TPSS 15
• N10 – Rt 28 between Dominion Virginia Power (DVP) tie-in manhole and TPSS 15 location, Rudder Rd, GSE-Cell Phone Lot
• N97 – TPSS 18
Civil: Wet Utilities & Utility Crossings
Storm Pipe/Wet Utilities:• N07 – West of Reston Station• N08 – East & West of Herndon
Station• N09 – East of Innovation
Station• N96 – Cargo 5 Parking Lot
Utility Crossings• Jack & bore – Reston Station,
Rt. 28, TPSS 15• Directional Drill – Water and
sewer at Herndon & Innovation Stations Complete
• Hand Mine – TPSS 13 and TPSS 14
Civil: Trackwall
Trackwall Installation• Footing and Wall installation west of Horsepen Run• Footing installation east of Horsepen Run• Footing and Wall installation east of Centreville Bridge
Civil: Grading/ExcavationGrading/Excavation:• N07 – Reston Station,
North and South of Reston Station in DIAAH/DTR median
• N08 – Herndon Station, East and West of Herndon Station
• N09 – East of HorsepenBridge, TPSS 14, TPSS 15
• N97, N11, N12 –Embankment for Greenway road widening, TPSS 18
Manpower HoursSeptember – November
*includes all other nationalities, for example: Pacific Islander, Native Hawaiian, Native American, Asian, etc.
Labor by Race/EthnicitySeptember – November
AfricanAmerican Caucasian Hispanic Other*
EMP % EMP % EMP % EMP %
September 2015 72 12 183 31 326 55 12 2October 2015 86 12 214 30 400 56 15 2November 2015 78 12 182 28 383 59 7 1
QTR AVG 79 12 193 30 370 57 11 1
African American Caucasian Hispanic Other
*includes all other states.
Labor by StateSeptember – November
VA MD DC PA WV OTHER*% % % % % %
September –November 2015
Average63% 19% 3% 5% 5% 5%
VA MD DC PA WV OTHER
DBE StatusAs of 12/10/15
$‐
$20,000,000.00
$40,000,000.00
$60,000,000.00
$80,000,000.00
$100,000,000.00
$120,000,000.00
$140,000,000.00
$160,000,000.00
$180,000,000.00
$200,000,000.00
DBE Project Goal DBE Committed Value Against Awarded Contracts
Remaining to Buy Projected Finish
DBE Status $164,888,780.00 $178,366,051.20 $‐ $182,249,501.82
Dollars Procured to DBE
Dulles Corridor Metrorail Project, Phase 2, Package A Disadvantaged Business Enterprise(DBE) Status
Local Outreach9/16/15 Greater Washington Urban
League9/16/15 Wharf-Washington DC9/28/15 Prince George’s County EDC10/2/15 Prince George’s County EDC10/3/15 Wharf-Washington DC 10/20/15 KRA Washington DC10/28/15 Wharf-Washington DC10/28/15 Greater Washington Urban
League11/02/15 Prince George’s County
Works: EDSI11/09/15 Loudoun County Workforce
Exchange
Dulles Days Plane Pull 2015 Dulles Corridor Metrorail Project Team
5K/10K on the Dulles RunwayCapital Rail Constructors Volunteers
Change OrdersDRB Establishment
Next Steps: