Water cycle - All the steps to the water cycle with a video at the end
Capital Projects Life cycle Process (End to End) · PDF fileProjects Manual Page 1 Capital...
Transcript of Capital Projects Life cycle Process (End to End) · PDF fileProjects Manual Page 1 Capital...
Projects Manual
Page 1
Capital Projects Life cycle Process (End to End)
By Ritwik Kumar Mishra
Oracle Apps Functional Consultant
Table of Contents
1 Introduction ............................................................................................................. 4
2 Creation of Project .................................................................................................. 4
3 Set Up ...................................................................................................................... 9
3.1 Changing of Status ................................................................................................. 9
3.2 Project Structure ................................................................................................... 12
4 Work plan Setups ................................................................................................. 12
4.1 Work plan Information .......................................................................................... 13
4.1.1 Lifecycle .......................................................................................................... 14
4.1.2 Phase .............................................................................................................. 14
4.1.3 Default display outline level .......................................................................... 15
4.2 Progress ................................................................................................................ 16
4.2.1 Progress cycle ................................................................................................ 17
4.2.2 Physical percent complete method .............................................................. 17
5 Resource ............................................................................................................... 18
5.1 Assigning Resources ........................................................................................... 18
5.2 Update Duration .................................................................................................... 21
5.3 Update Hours per day .......................................................................................... 23
5.4 Update Work Pattern ............................................................................................ 25
5.5 Submit for apporval .............................................................................................. 26
6 Work plan .............................................................................................................. 28
6.1 Task Creation ........................................................................................................ 28
6.2 Updation of Work plan ......................................................................................... 33
Projects Manual
Page 2
7 Planning Resources to a Task ............................................................................. 35
7.1 Adding Resources ................................................................................................ 35
7.1.1 Adding People .................................................................................................... 36
7.1.2 Adding Equipment ......................................................................................... 39
8 Financials .............................................................................................................. 45
8.1 Financial Structure Information ........................................................................... 45
8.2 Creation of Budget ............................................................................................... 46
8.3 Edit Planning Options .......................................................................................... 47
8.3.1 Plan Settings .................................................................................................. 47
8.3.2 Currency Settings .......................................................................................... 49
8.3.3 Rate Schedules .............................................................................................. 50
8.3.4 Generation options ........................................................................................ 51
8.4 Enter Budget Amounts ......................................................................................... 52
8.4.1 Adding Resources ......................................................................................... 53
8.4.2 Adding Planning Element .............................................................................. 55
8.4.3 Entering Budget Amounts ............................................................................. 56
8.5 Submission of Budget .......................................................................................... 59
9 Creation of Forecast ............................................................................................. 60
9.1 Edit Planning Options .......................................................................................... 61
9.1.1 Plan Settings .................................................................................................. 61
9.1.2 Currency Settings .......................................................................................... 62
9.1.3 Rate Schedules .............................................................................................. 63
9.1.4 Generation Options ........................................................................................ 65
9.2 Enter Forecast Amount ........................................................................................ 67
9.2.1 Adding Resources ......................................................................................... 67
9.2.2 Adding as planning element ......................................................................... 71
9.3 Submission of the Forecast ................................................................................. 74
10 Payable Invoice ..................................................................................................... 76
10.1 Create an invoice with Project Details ......................................................... 76
10.2 Validate ........................................................................................................... 81
10.3 Create Accounting ......................................................................................... 82
10.4 View Accounting ............................................................................................ 83
Projects Manual
Page 3
10.5 Interface to project: ........................................................................................ 84
10.6 Checking of the interfaced expenditure in Oracle Projects ........................ 86
10.7 Expenditure in Project Form ......................................................................... 88
11 Creation of Assets ................................................................................................ 90
11.1 Capitalization details ..................................................................................... 91
11.2 Asset Details ................................................................................................... 91
11.3 Additional Asset details ................................................................................ 92
11.4 Location, Employee ....................................................................................... 92
11.5 Depreciation ................................................................................................... 94
11.6 Description ..................................................................................................... 95
12 Transactions for the asset ................................................................................... 95
12.1 Project Details ................................................................................................ 95
12.2 Line Items ....................................................................................................... 97
12.3 Distributions ................................................................................................... 97
12.4 Validate ........................................................................................................... 99
12.5 Create Accounting ....................................................................................... 100
12.6 View Accounting .......................................................................................... 101
12.7 Interface to project: PRC: Interface Supplier Costs .................................. 102
12.8 Check the interfaced expenditure ............................................................... 103
12.9 Generation of Asset Lines ........................................................................... 110
12.10 Interfacing Assets to Oracle Assets ........................................................... 118
12.11 Preapre Mass Additions .............................................................................. 120
13 Project Status...................................................................................................... 122
13.1 Reporting with Project Status Inquiry ........................................................ 122
14 Conclusion : ........................................................................................................ 123
Projects Manual
Page 4
1 Introduction
This manual gives us a detailed overview of the projects cycle with respect to capital projects.
The various steps involved in the process including the capitalization process is included in this
document.
This entire exercise has been performed in the vision instance with the following credentials
User Name: SERVICES
Password: welcome
2 Creation of Project
Responsibility: Projects Super user, Vision Services USA
Navigation: Projects > Delivery > Create Projects
The first step involved in the project cycle is regarding creation of a project with bare minimum
details. This process can be done by two ways
a) Creation of project from another existing project
This step is adopted when we want to create an exact replica of another project rather than
creating a project with the same characteristics and tasks from the fresh or for creating routine
type of projects which are very much recurring in nature.
b) Creation of project from template
This step is adopted when the user wants to create a project on the basis of a template which
contains all the necessary information that is required to run a project. So in many organizations
rather than creating projects from fresh they are interested to follow a template which contains
all the various information that is required to be there.
So the second option is more necessary and is mostly used in many organizations so we will be
using the second method that is creating a project from an existing template.
Step 1: Project from templates
Projects Manual
Page 5
As we know that we are creating a capital project so accordingly the template should also be
selected keeping in mind the fact that it should be suitable for capital project. Since we are
creating this project in Operating unit i.e Vision Services so we need to select a template
belonging to this particular operating unit.
So from the above discussion we can undesratand our requirement that is a template having the
two properties i.e
a) Suitabe for capital projects
b) Belonging to operating unit : Vision Services
So here we can see that we have selected a template for a capital project as shown in the
screenshot.
Projects Manual
Page 6
Click button for continuing the creation of project
Enter other project details like
Project Name
Project Number as shown below
Enter a project manager from the LOV
Here we need to keep one thing in mind while selecting the projrct manager which is that if we
are selecting am employee defined in the HRMS module which is not assigned to the user
name of the log in ID with which we have accesed the instance then we cannot see this project
in my projects list and while searching the project we need to enter the proejct manager as the
search criteria and then we can find it.
Projects Manual
Page 7
So since we are using log in credential as SERVICES so accordingly the employee attached to
this user name I,e Marlin Ms Amy has been selected as the project manager.
Enter the organisation : Services- East
This refers to a project organisation and this need to again fall under the operating unit i.e.
Select an organisation falling under the same operating unit.
Click button to complete the process of creation of project.
As soon as we do it the syaytem starts processing of the details entered by the user and
accordingly ceates a project with the template selected by the user.
Projects Manual
Page 8
Now the project is created with the required details as entered by the user.
Projects Manual
Page 9
3 Set Up
3.1 Changing of Status
After creation of the project we need to concentrate on the set ups before using the application
for tracking of the project tasks.
So for this purpose click on “Setup (T)” in the Projects, Main Tab as shown below
Click
Here we can see that currently the status of the project is “Unapproved”. So in order to
proceed with the further activities we need to change the status of the project.
Change the status
Projects Manual
Page 10
Click button
Change the status to Active by selecting the option from the LOV as shown below
Projects Manual
Page 11
Click for applying the changes done.
Projects Manual
Page 12
3.2 Project Structure
After chnaging the status of the project we need to look into the structure of the project. So in
order to change the structure related setups get into rhe section of project setups i.e
Click Link to see the set ups
In the above screen shot we can see that the various options relating to the project structure is
given.
So as per the requirement we need to select the the options.
If we need to track the financial and the workplan associated with the project then we need to
select these checkboxes.
Shared structure in Workplan and financials stuctures need to be selected as per requirement.
Click button for applying the chnages done to the structure and the chnages are
done.
4 Work plan Setups
After dealing of project related setups we need to work on the work plan related setups.
Projects Manual
Page 13
So Click TAB from the menu
Click and get into the setup section
4.1 Work plan Information
Get into workplan information in the setups menu in order to set the set ups fpr workplan
information.
Projects Manual
Page 14
Under workplan information various elements we will come across which are part of workplan
setups.
4.1.1 Lifecycle
In this process we need to enter the life cycle which the project is going to follw during its
operation. This lifecycle can be defined by the user as a setup in the projects module. While
defining the life cycle we need to specify the various phases the project is going ti go through in
its life cycle.
4.1.2 Phase
As mentioned earlier while defining the lifecycle we need to define the various phases of the
lifecycle. So during defining the project set ups with respect to workplan we need to specify the
phase in which the project is going on currently so that the tracking of the project takes place
acordingly.
Projects Manual
Page 15
4.1.3 Default display outline level
During the processs of workplan information set ups the user need to specify the default display
outline level. Under this section we specify the elements like workplan versioning etc. So if the
suer is interseted to have workplan versioning then we need to select the checkbox pertaining to
this.
Projects Manual
Page 16
Click to apply the changes done .
Since we are not following the standard lifecycle with which the template is going i.e. AIM so
upon applying the changes we will get an warning as we can see as hown below.
Click to proceed
4.2 Progress
Under setiups click the link for getting into the progress related setups.
Projects Manual
Page 17
4.2.1 Progress cycle
First we need to select the progress cycle that we are going to follw for tracking the progress of
the project. So accordingly we need to select the available options in the LOV.
4.2.2 Physical percent complete method
Physical percent complete method refers to the method to be adopted in order to track the
extent of physical work which has been completed in the project so far. So as per the
requirement we need to slect accprdingly.
Click to apply the chnages done so far.
Projects Manual
Page 18
5 Resource
Click TAB from the main menu and get into resources related information and
setups .
5.1 Assigning Resources
In order to assign resources to the project select the “Add Assignment” from the drop down list
as shown below.
Projects Manual
Page 19
Click for assigning the resources
Enter the details as shown as per the requirements
Role
Projects Manual
Page 20
Person
Click TAB to see the financial information related to this role
Select “Return to selected people” from the drop down list and click
Projects Manual
Page 21
5.2 Update Duration
If the user is interested to update the duration after assigning the resources then we can avail
this facility by use of update duration functionality.
In order to do it select update duration from the drop down list of the team role action after
selecting the resource whose duration has to be updated as shown below.
Projects Manual
Page 22
Click for updating the duration of the resource
Change the duration if required
Click to apply the changes and come back to the Schedules resources window .
So now we can see that after chnaging the duration the number of hours in comparison to
earlier has also changed which is obvious.
Projects Manual
Page 23
5.3 Update Hours per day
If the user is interested to change or update the hours per day then that also he can go for by
updating it. In order to achieve that select “Update Hours per day” from the drop down list of the
team role actions list and then can update the number of hours per day as shown below.
Here we can change the existing hours per day and enter the new hours if required as shown
below.
Projects Manual
Page 24
Click to apply the changes and come back to the Schedules resources window.
Projects Manual
Page 25
5.4 Update Work Pattern
If the user is interested to change or update the hours per day then that also he can go for by
updating it. In order to achieve that select “Update Work Pattern” from the drop down list of the
team role actions list and then can update the number of hours per day as shown below.
Apply
Projects Manual
Page 26
5.5 Submit for apporval
After assigning the resource and deciding on various elements like duration schedule etc. if the
user is very sure of no further change then they can go for submitting the work plan for
approval.
In order to submit the workplan for apporval we need to select “Submit for Apporval” from the
drop down list and then click “GO” as shown below.
Click on for submission form
Projects Manual
Page 27
Click for submission of the workplan for apporval.
As we submit the workplan we will receive this message as shown below and then click OK for
going forward.
Click
Projects Manual
Page 28
6 Work plan
6.1 Task Creation
Click TAB for gettting into workplan main window .
After setting the setups for workplan and assigning of the resources we need to create task for
the resources.
So in order to create task select the existing task from where we need to create a task and then
click button and proceed further
Projects Manual
Page 29
Select the outline level as 1 if the user wants to create a subtask of the task selected for
creation of task.
If we are selecting the outline level as 0 then it would create a peer task and not as a sub task.
Enter details like
Task name , type and planned effort as per our estimation and the task manager.
Enter all the various tasks that is required to be entered in the same manner as shown above
and the list will be as follows .
Projects Manual
Page 30
Click to apply the changes .
After applying the changes the system wlll start processing for the creation of tasks as per the
details entered in the above process.
After the completion of the process we wll get a confirmation message regarding the change of
work breakdown structure as shown below.
Projects Manual
Page 31
Here we can see that the work break down structure has been changed as per the details
entred by us above.
Click to view the workplan
Click button of we are interested to review it.
Projects Manual
Page 32
Click for publishing the workplan
Projects Manual
Page 33
6.2 Updation of Work plan
Here we can see that our workplan is now in the list as shown below.
But the name is in Copy so if we are intrested to update the workplan then click
button
Click to change the name and other details as required
Projects Manual
Page 34
Below we can see that the name has been changed by us as per requirement to
EDARANU_167_Capital Services
Select the change reason as Scope change
Click for applying the changes
Projects Manual
Page 35
In the above screenshot we can see that the name of the work breakdown structure has been
changed as we have changed the name of the workplan.
7 Planning Resources to a Task
7.1 Adding Resources
In general work breakdown structure refers to the structure which defines the various details pertaining to the work to be performed for accomplishing the task. So after entering the task details its very much necessary on our part to enter the various employees and resources that are going to be involved in the accomplishment of the task.
If the user is interested to update the work breakdown structure then they can do so by the functionality of update. For this we need to click the update button and then update the various details which we want to do.
First we need to select our task that we want to update let’s say task 1.1 as we can see
Click button for updating the task and entering the varios resources that are going to be involved in this process.
Click TAB for entering the rseources who or which are going to work for this task.
Projects Manual
Page 36
7.1.1 Adding People
Select the planning resource for which we want to add the resource as shown below
Click button for selecting the resource .
When we click go then we can see those resources in the list which are already added as an resource under this template which we have used for creation of the project.
Projects Manual
Page 37
If we want to add any other resource which is not in this list individually then we need to click the
button through which we can add one resource at a time.
Here we need to specify the resource class which can be anything among people , equipment , material item and financial elements as shown below.
Enter the details like
Resource format i.e Fianancial Category
Name
Projects Manual
Page 38
Financial Category : Labour
Enter the planning attributes
Spread curve : this will determine the distribution or apportionment of the cost time and effort among the resources.
click to apply the changes done by the suer.
If the user is interested to select multiple resources then they can do it by clicking
button .
Enter all the details like
Named person
Role
Team Role
After entering the details click and then we can see these resources in the list as
shown below.
Projects Manual
Page 39
Select these resources and then click
7.1.2 Adding Equipment
Similarily like we added “People” accordingly we can also do the same for Equipements from
the drop down list as we can see below.
Projects Manual
Page 40
Click
Projects Manual
Page 41
Click to see these in the list of resources like we did for “People”.
Select the required resource from here and click “GO”
After clicking “GO” we can see that he sreources selected by us are coming in the resources
field as shown below.
Click button for reviewing the workplan
Projects Manual
Page 42
Click button for publishing the work plan
So here we can see that all our resources with their respective ETC or Estmate to complete
effort are present here.
Projects Manual
Page 43
If we want to update the progress then click button
Click to calculate the estmate to complete effort
Click button to submit the workplan structure so designed.
Projects Manual
Page 44
After clicking the button the system throws an alert or warning. Click “Yes” and then
go ahead.
As soon as we click “Yes” button the system starts processing of the task related information
After completion of the process the updated task information is ready with the updated figures.
Projects Manual
Page 45
8 Financials
Click TAB in the main menu and enter the financials section of the project.
8.1 Financial Structure Information
Click to see the setups and change them if required
Get into the financial structure information under financial setups
We can observe that the values get defaulted form work break down structure definition.
Click
Projects Manual
Page 46
8.2 Creation of Budget
Budget is an essential part of the financial process in a project. So in order to create a budget
for our project we need to get into financials TAB under the main menu.
Click TAB
Select Approved cost budget
Click for creating a plan version for the budget
Enter various details like Name , Description as shown below
Projects Manual
Page 47
8.3 Edit Planning Options
Select “Edit Planning Options” from the drop down list as shown below and click
8.3.1 Plan Settings
Click TAB and enter the required options
Projects Manual
Page 48
Define the plan settings
Field Value
Approved Budget
Approved Cost Budget Yes (read only)
Approved Revenue Budget Yes (read only)
Amount Entry
Quantity Yes
Raw Cost Rate Yes
Burdened Cost Rate No
Raw Cost Yes
Burdened Cost No
Plan Amounts in Multiple Currencies No (read only)
Bill Rate No
Revenue No
Reporting and Display
Resource Breakdown Structure Standard RBS (view only)
Report Cost Using Burdened Cost
Display Factor 1
Cost And Revenue
Lowest Level Project
Planning Resource List Standard Planning List (no Central
Control)
Time Phase GL Period
Period Profile GL Period
Current Planning Period Accept Default Value
Projects Manual
Page 49
8.3.2 Currency Settings
Define the currency settings
Field Value
Project Functional Currency: USD
Cost Rate Type Corporate
Cost Rate Date Type Start Date of Plan Period
Cost Rate Date Leave Blank
Revenue Rate Type Corporate
Revenue Rate Date Type Start Date of Plan Period
Revenue Rate Date Leave Blank
Add Transaction Currencies
Currency USD - US Dollar (view only)
Cost Conversion Rate to: USD (first) Leave Blank
Revenue Conversion Rate to: USD
(second)
Leave Blank
Currency CAD - Canadian Dollar
Projects Manual
Page 50
Cost Conversion Rate to: USD (first) Leave Blank
Revenue Conversion Rate to: USD
(second)
Leave Blank
8.3.3 Rate Schedules
Enter rate schedule information
Field Value
Use Planning Rates Yes
Cost
Employee Leave Blank
Job Cost Rate by job
Non-Labor Resource Leave Blank
Resource Class Resource Class Rates
Burden Schedule Internal Costing
Revenue
Employee Bill Rate by Emp
Job Bill Rate by Job
Non-Labor Resource Non-Labor Bill Rate
Resource Class Res Class Bill Rates
Projects Manual
Page 51
8.3.4 Generation options
Specify Generation Options
Field Value
All Generation Options
Source Financial Plan
Plan Type Estimate
Version Leave Blank
Revenue Accrual Method WORK (read only)
Revenue Derivation Method Work
Include: Open Commitments Yes
Include: Billing Events Yes
Include: Retain Manually Added Plan
Lines
Yes
Projects Manual
Page 52
Click for applying the changes
8.4 Enter Budget Amounts
Click button to edit the budget amount
Projects Manual
Page 53
8.4.1 Adding Resources
Click for adding tasks and resources
Select the project
Click “Add Resources” from the drop down list for adding the rsources and then click on
as shown below
Select the resources as per requirement and then
Projects Manual
Page 54
After selecting all the required resources click button
After applying the selected resources we can see that the resources selected field has been
enabled and its checked.
Projects Manual
Page 55
8.4.2 Adding Planning Element
After adding the resources we need to add these resources as planning elements
Select “Add as Planning Element” from the drop down list. And then click
So here we can see that now the field for Planning Element has been enabled
Click “Apply” for applying the chages done
So here we can see the version of our budget so created by us
Projects Manual
Page 56
8.4.3 Entering Budget Amounts
Enter budget amounts for Contractor
Similarily enter the amounts for equipments , financial elemens and People as shown below
Projects Manual
Page 57
Click to save the chnages done by entering the amounts to resources
After saving the changes we can see that the budgeted amounts for the burdened cost gets calculated as shown in the next screenshot.
Click for editing the resource details pertaining to budgets and seeing the distribution of the total amounts under various periods.
Projects Manual
Page 58
Click for viewing the budget
Projects Manual
Page 59
8.5 Submission of Budget
Finally we need to submit the budget if we feel that everything is created as pe the requiremnt and so it can be send for approval.
Click for submission
Projects Manual
Page 60
9 Creation of Forecast
The functionality for forecasts is also there in Oracle projects. Budget is an essential part of the
financial process in a project. So in order to create a budget for our project we need to get into
financials TAB under the main menu.
In order to avail this functionality we need to get into financials menu as shown below
Click submenu and select Forecast
Click button for creation of a planned version of the project
Enter the details like forecast name and description as per our suitabality as shown below
Projects Manual
Page 61
9.1 Edit Planning Options
Select “Edit Planning Options” from the drill down list of box and then click
9.1.1 Plan Settings
Field Value
Primary Forecast
Primary Cost Forecast Yes (read only)
Primary Revenue Forecast Yes (read only)
Amount Entry
Quantity Yes
Raw Cost Rate Yes
Burdened Cost Rate No
Raw Cost Yes
Burdened Cost No
Plan Amounts in Multiple Currencies No
Projects Manual
Page 62
Bill Rate No
Revenue No
Reporting and Display
Resource Breakdown Structure Standard RBS (read only)
Report Cost Using Burdened Cost
Display Factor 1
Cost And Revenue
Lowest Level Project
Planning Resource List Standard Planning List (no Central
Control)
Time Phase GL Period
Period Profile GL Period
Current Planning Period Accept Default Value
9.1.2 Currency Settings
Define the currency settings
Field Value
Project Functional Currency: USD
Cost Rate Type Corporate
Cost Rate Date Type Start Date of Plan Period
Cost Rate Date Leave Blank
Revenue Rate Type Corporate
Revenue Rate Date Type Start Date of Plan Period
Projects Manual
Page 63
Revenue Rate Date Leave Blank
Add Transaction Currencies
Currency USD - US Dollar (view only)
Cost Conversion Rate to: USD (first) Leave Blank
Revenue Conversion Rate to: USD
(second)
Leave Blank
Currency CAD - Canadian Dollar
Cost Conversion Rate to: USD (first) Leave Blank
Revenue Conversion Rate to: USD
(second)
Leave Blank
9.1.3 Rate Schedules
Enter rate schedule information
Field Value
Use Planning Rates Yes
Cost
Employee Leave Blank
Job Cost Rate by job
Non-Labor Resource Leave Blank
Resource Class Resource Class Rates
Burden Schedule Internal Costing
Revenue
Employee Bill Rate by Emp
Job Bill Rate by Job
Projects Manual
Page 64
Non-Labor Resource Non-Labor Bill Rate
Resource Class Res Class Bill Rates
Projects Manual
Page 65
9.1.4 Generation Options
Specify Generation Options
Field Value
All Generation Options
Actuals Amounts Through Current Period
ETC Source Task Level Selection
Workplan XX Cost Plus Revised Workplan
Plan Type Forecast
Version Leave Blank
Revenue Accrual Method WORK (view only)
Revenue Derivation Method Work
Change Documents Yes
Open Commitments Yes
Billing Events Yes
Retain Manually Added Plan Lines Yes
Projects Manual
Page 66
Projects Manual
Page 67
9.2 Enter Forecast Amount
Click for entering the forecast amount
9.2.1 Adding Resources
Click for adding the tasks and resources
Select the project
Select “Add Resources” from the drop down list of the actions and click “Go” as shown below
Projects Manual
Page 68
Enter details like
Resource class , resource format and name as we did in case of budget.
Projects Manual
Page 69
Click for adding the resource
Like in case of budget in forecast also multiple resources can be added by clicking
button
Enter the necessary and the required details
Click
Projects Manual
Page 70
Like budgets we need to select our resouces and then add to the forecast
Click for adding the resource
In the above screenshot we can see that the field for “Resources Seelected” has been enabled hereby .
Projects Manual
Page 71
9.2.2 Adding as planning element
Select the project and select “Add as Planning Element” and click “Go”
Here we can see that after adding as a planning element the field for Planning Element has been enabled.
Click for applying the changes
Projects Manual
Page 72
Enter the forecast amount as shown below
Click for saving the forecast with the amounts so entered. After this we will get a message as hown below.
Projects Manual
Page 73
Projects Manual
Page 74
9.3 Submission of the Forecast
Approve the forecast by clikcing button
Projects Manual
Page 75
Projects Manual
Page 76
10 Payable Invoice
As part of the process flow we need to do a transaction and see its impact on the projects
module. So for this purpose we need to make a payables invoice and see its implication in
projects module by interfacing the transaction with projects through a programme.
10.1 Create an invoice with Project Details
Responsibility: Payables Manager
Navigation: Invoices > Entry > Invoices
Enter the basic information
Enter the project details
Select the project
Select the task
Projects Manual
Page 77
Select the expenditure type
Here we can see all the project informations
Projects Manual
Page 78
Here we can see that the acount is defaulting because of autoaccounting
Projects Manual
Page 79
Since we need to capitalise the asset as part of the requirement so we need to take an asset
clearing a/c as shown below
Projects Manual
Page 80
Save it
Projects Manual
Page 81
10.2 Validate
Projects Manual
Page 82
10.3 Create Accounting
Projects Manual
Page 83
10.4 View Accounting
As we can see that the accouting entry is a follows
Item Expense (Asset Clearing ) A/c 01-720-1570-000 Dr. 2000 USD
To Liability A/c 01-000-2210-000 2000 USD
Projects Manual
Page 84
10.5 Interface to project:
After performing of the transaction we need to interface the transaction with projects module.
This can be achieved through a programme or request i.e. PRC: Interface Supplier Costs
Responsibility: Project Costing Super User
Navigation: View > Request > Submit a new request
Run Program “PRC: Interface Supplier Costs” to interface Payable Invoices related to
concerned projects
Select the project as one of the parameter
Enter a batch name for easy identification: DIPL_ER_PA
Projects Manual
Page 85
Submit the request
Refersh till completion of the request
Click for seeing the output of the request.
From the output we can see that the transaction has been interfaced that is the invoice number
has come as higlighted over here and is hereby attached
Projects Manual
Page 86
10.6 Checking of the interfaced expenditure in Oracle Projects
To crosscheck the fact that the transaction has reached the projects module lets query for the
transaction in projects costing module.
Responsibility: Project Costing Super User
Navigation: Expenditures > Expenditure Enquiry > Projects
Enter the project
Enter the task
Expenditure Organisation
Click
Projects Manual
Page 87
Click
Projects Manual
Page 88
Note the transaction ID and query for the same in the projects form : 102041
10.7 Expenditure in Project Form
Search for your projects in the project list
Responsibility : Projects Superuser
Navigation : Projects > Delivery > Projects List
Search for your project and click it for seeing the present status
Projects Manual
Page 89
Click
So as we know the transaction ID so let’s query with the transaction ID
Projects Manual
Page 90
11 Creation of Assets
Since we are creating a capital project process flow so we need to create a CIP asset as part of
the process flow which will be later interfaced to oracle assets and then capitalized over there.
Responsibility: Projects Vision Services
Navigation: Capitalization > Capital Projects
Enter the project
Click for creation of assets
Projects Manual
Page 91
11.1 Capitalization details
Since the asset is still on a planning phase so we need to set the status of the asset as
“Estimated” as we can see.
Once all the details are created and the transactions are performed then only we will change the
status from “Estimated” to “As Built” when it is to be capitalized by the user.
11.2 Asset Details
Enter the following
Book Name
Category
And other required details
Enter the asset book
Enter the asset category
Projects Manual
Page 92
Enter details like Asset number and actual units
11.3 Additional Asset details
11.4 Location, Employee
Enter the following
Projects Manual
Page 93
Location
Employee Name
Number
Projects Manual
Page 94
11.5 Depreciation
Enter the depreciation expense account
Projects Manual
Page 95
11.6 Description
Save it and close the window
12 Transactions for the asset
Responsibility: Payables
Navigation: Invoices > Entry > Invoices
12.1 Project Details
Enter the project information
Projects Manual
Page 96
Project Name and number
Task Name and Number
Expenditure organisation
All the project details will be as follows
Projects Manual
Page 97
12.2 Line Items
Click
12.3 Distributions
Click TAB
As we can see that the account is defaulted
But we need to have asset clearing a/c as the account so let’s change the a/c
Projects Manual
Page 98
Save
Projects Manual
Page 99
12.4 Validate
Projects Manual
Page 100
12.5 Create Accounting
Projects Manual
Page 101
12.6 View Accounting
Go to Menu > Tools > View Accounting Events
Accounting Entry
As we can see that the accouting entry is a follows
Item Expense (Asset Clearing ) A/c 01-720-1570-000 Dr. 20000 USD
To Liability A/c 01-000-2210-000 20000 USD
Projects Manual
Page 102
12.7 Interface to project: PRC: Interface Supplier Costs
In order to interface the transaction from payables to projects we need to run the programme :
PRC: Interface Supplier Costs
Responsibility: Project Costing Super User
Navigation: View > Request > Submit a new request
Run Program “PRC: Interface Supplier Costs” to interface Payable Invoices related to
concerned projects
Submit the request and refersh till completion
Click for seeing the output
Projects Manual
Page 103
12.8 Check the interfaced expenditure
Responsibility: Project Costing Super User
Navigation: Expenditures > Expenditure Enquiry > Projects
Projects Manual
Page 104
Note the transaction ID and query for the same in the projects form : 102042
Projects Manual
Page 105
Query for the same in Respective Projects Form,
Search for ypur projects in the project list
Responsibility : Projects Superuser
Navigation : Projects > Delivery > Projects List
Search for your project and click it for seeing the present status
So as we know the transaction ID so let’s query with the transaction ID
Projects Manual
Page 106
Run the following programmes
PRC: Distribute Labor Costs
Projects Manual
Page 107
PRC: Distribute Usage and Miscellaneous Costs
PRC: Update Project Summary Amounts for a Single Project
PRC: Distribute Total Burdened Cost
Projects Manual
Page 108
PRC: Generate Cost Accounting Events
Projects Manual
Page 109
PRC: Update Project Summary Amounts for a Single Project
Projects Manual
Page 110
PRC: Create Accounting
12.9 Generation of Asset Lines
Get back to “Capitalize” window
Capitalization > Capital Projects
Projects Manual
Page 111
Projects Manual
Page 112
Projects Manual
Page 113
Click
Click
Projects Manual
Page 114
Change the current status of the project to As-Build as we want to capitalise the asset
Projects Manual
Page 115
Enter an actual date of service as shown below
Save
Click “Assets” TAB to see the posotion of the assets of the project
Projects Manual
Page 116
Click
Here we can see that the lines are generated for this asset as we generated lines in the
previous step but the names are the same so lets change the asset from the asset lines .
Select our asset as created by us and the change the asset as shown below
Projects Manual
Page 117
Now the asset has been changed
Click and enter the assets window
Projects Manual
Page 118
Click the Tab to see the asset lines of this partcular asset
12.10 Interfacing Assets to Oracle Assets
In this step we interface the assets so created by us in oracle projects to oracle assets and this
is the final step which is done regrading the asset in oracle projects. After this interfacing we
cannot do any sort of change to the asset created in oracle projects.
The programme is PRC: Interface Assets to Oracle Assets
Submit the request and refrsh till completion
Projects Manual
Page 119
Click “View Output” to see the output of the request
Here we can see that our asset has been interfaced to Oracle assets
Projects Manual
Page 120
12.11 Preapre Mass Additions
After creation of capital asset in oracle projects and then interfacing the asset to Oracle assets
we need to prepae mass additions in fixed assets module.
Responsibity : Assets
Navigation : Mass Additions > Prepare Mass Addtions
Enter the asset book : GOK ERN
Click
Here we can see that our asset is present over here with the status of Post and next we need to
post it which means to capitalise it by posting mass addition .
Projects Manual
Page 121
Here we can post the asset by setting the parameter as the asset book name and then the
status of the asset changes to POSTED as we can see below.
Projects Manual
Page 122
13 Project Status
13.1 Reporting with Project Status Inquiry
Responsibility = Projects, Vision Services (USA)
2. Navigate to the Find Project Status window
(N) Project Status Inquiry > Project Status Inquiry
Search for the project created
Projects Manual
Page 123
Click
14 Conclusion :
Thus this manual on capital gives a detailed explanation of the process involved in capital projects and the various steps and functionality involved in it.