CAPITAL PROGRAMS – O’HARE 21 PRESENTATION TO CMAA CHICAGO CHAPTER NOVEMBER 17, 2016

Transcript of Capital Programs - O'Hare 21

Page 1: Capital Programs - O'Hare 21

CAPITAL PROGRAMS – O’HARE 21PRESENTATION TO CMAA CHICAGO CHAPTER

NOVEMBER 17, 2016

Page 2: Capital Programs - O'Hare 21

OVERALL PLAN & STATUSORD PROJECTSMDW MODERNIZATION

Page 3: Capital Programs - O'Hare 21

3CONNECTING THE WORLD TO CHICAGO

Mayor’s GoalsCustomer Service Facilities, Technology, Preclearance, Amenities and Service Culture

Connectivity Air Service, Express Rail, Western access

Benefit to Chicago Direct development on airport; Indirect, business & job growth

CDA Programs to Achieve

O’Hare 211. Airfield package 2. New lease negotiations & capital plan

Domestic Terminals Gates, technology, concessions – ability to expand for future needs

OHare Express Rail (OER) Optimize customer access / cost to maximize private viability

Latin America/ InternationalAir service development, increase international gates, increase proximity to domestic gates

Hotels 2 new hotels; refurbish and expand existing Hilton

2015-2019 Plan

Page 4: Capital Programs - O'Hare 21

STATUS – O’HARE KEY PROJECTS

4CONFIDENTIAL – DRAFT – PREDECISIONAL

Approved/Underway

UnderNegotiation/Review

Airfield uDomestic Gates

L “Stinger” 5-RJ Gate Expansion uNew Concourses u

International Gates

T5 M-Concourse 9 WB gate expansion uNew T2 International/domestic terminal u

RFP for Hotel Operator uO’Hare Express Rail

Conceptual Engineering uRFP for Hotel Developer u

Page 5: Capital Programs - O'Hare 21

STATUS – O’HARE PROJECTS

• Innovation Lanes, T1 and T3 November 2016

• Northeast Cargo Phase II December 2016

• L Stinger completion February 2018

• Multi Modal Facility December 2018

• Concessions– Goose Island B concourse – food service in hold rooms started last week– Food cart delivers food to hold room area– ARN Award

• New Flights in November– EVA to Taipei and on to Bangkok – ANA to Tokyo Haneda and on to Asia– Interjet to Mexico City– Frontier to Cancun, Cabo and PV

5CONFIDENTIAL – DRAFT – PREDECISIONAL

Page 6: Capital Programs - O'Hare 21

STATUS – MIDWAY MODERNIZATION

• Concessions Proposal Completed– City Council December

• Ground breaking dates for Midway Modernization– Security Checkpoint (new bridge) March 2017– Parking Expansion/ CTA connection upgrade June 2017

• Completion dates for Midway Modernization– Security Bridges & Parking Structure June 2019

6CONFIDENTIAL – DRAFT – PREDECISIONAL

Page 7: Capital Programs - O'Hare 21

OVERVIEW – O ’HARE TERMINAL AREA PROGRAM (TAP)

Page 8: Capital Programs - O'Hare 21

8

POTENTIAL CONFIGURATIONS FOR NEW CONCOURSES

8

Page 9: Capital Programs - O'Hare 21

CONFIDENTIAL – DRAFT – PREDECISIONAL 9

O’HARE 21 – TERMINAL AREA PROGRAM

• The Modernization of O’Hare has completed approximately $5.8B of improvements, including:– Two New Airport Traffic Control Towers– Extension of Runway 10L/28R– New Runway 9L/27R– New Runway 10C/28C– New Runway 10R/28L– Multiple Taxiway Improvements (K&L, LL, others)– On-going Runway 9C/27C– On-going Centralized Deicing Facility and Cross Field Taxiway– On-going Consolidated Rental Car/Parking Multimodal Facility– On-going ATS Modernization and Extension

• Next goal – Terminal Expansion and remaining airfield improvements

Page 10: Capital Programs - O'Hare 21

CONFIDENTIAL – DRAFT – PREDECISIONAL 10

O’HARE 21 – TERMINAL AREA PROGRAM (CONTINUED)

• Consistent with the approved Airport Layout Plan, the next step in the process is to build terminals and concourses to increase gate capacity

– Additional domestic and international gates– Increased concession space– Enhanced Passenger Experience– Increase efficiency– Reduce Operating Costs– State-of-the-art building systems – Enhanced transit connections (intra-terminal/downtown)– Replacement of aged facilities

Page 11: Capital Programs - O'Hare 21

CONFIDENTIAL – DRAFT – PREDECISIONAL 11

PROGRAM MANAGER FOR O’HARE 21

• Owner’s Representative Services for Terminal Area Plan and ultimately ORD’s Capital Improvement Program

• Manage multiple construction managers

• Design and engineering management

• Project control services– Master Program Plan– Schedule Development

• Anticipated term: 8 years

• Anticipated Advertisement Date: 4th Quarter 2016

Page 12: Capital Programs - O'Hare 21

CONFIDENTIAL – DRAFT – PREDECISIONAL 12

LEAD DESIGN SERVICES FOR TERMINAL DEVELOPMENT

• One lead A/E firm will be chosen for the design of new terminal development at O’Hare

• Primary focus will be on the anticipated O’Hare Central Facility

• The O’Hare Central Facility is the centerpiece of the terminal area plan for O’Hare 21 and the design should reflect the significance of this component of the project

• Design team will be expected to include industry leading experts on security technology, as well as new technology for passenger amenities

• Anticipated project delivery method is Construction Manager at Risk (CM@R). Accordingly, design team will work closely with CM@R firm during preconstruction services and throughout the life of the project

• Anticipated Advertisement Date: 1st Quarter 2017

Page 13: Capital Programs - O'Hare 21

13

TARGET MARKET DESIGN CONTRACTS

• Non-federal engineering task order contracts will be bid target market

• Contracts designated for competition limited to MBEs or WBEs

• The Target Market Program reserves a percentage of the City’s non-construction contracts and limits participation to M/WBEs

• Contracts are not eligible for the program unless there are at least three qualified MBEs or WBEs interested in participating in that type of contract

• The prime contractor on a Target Market Contract must perform at least 50 percent of the dollar value

Page 14: Capital Programs - O'Hare 21

14

• Multiple target market Construction Manager contracts will be awarded to oversee various segments of O’Hare 21 Terminal Area Plan and the upcoming Capital Improvement program

• Projects will include airside work, landside projects, terminal projects, site preparation and security packages

TARGET MARKET CONSTRUCTION MANAGEMENT SERVICES

Anticipated Term: 5 Years

Anticipated Advertisement Date:

4th Quarter 2016

Anticipated Award Date:

3rd Quarter 2017

The procurement method has aspects of professional services procurement. For the construction planning phase, the City can require the successful proposers to implement subcontractor mentoring, use of hiring and training for citizens in socioeconomic disadvantaged neighborhoods, and targeted outreach.

Page 15: Capital Programs - O'Hare 21

15

CM@RISK HIGHLIGHTS

Contractor DBE Goal

DBEActual

DFW International Terminal “D” 26% 33%

Nashville Airport (CONRAC) 10% 22%

Atlanta Airport (CONRAC) 34% 36%

Phoenix Airport (CONRAC) 10% 24%

Miami Airport 20% 28%

Sacramento Airport Terminal B 0% 10%

LAX World Airport West Gates 14% 21%

LAX World Airport TBIT Core 14% 14%

DART Transit Expansion 42% 54%

Texas Instruments RFAB 35% 50%

Toyota World Headquarters 20% 30%

A project delivery method in which the Construction Manager acts as a consultant to the Owner in the development and design phases, but assumes the risk for construction performance as the equivalent of a general contractor holding all the trade subcontracts during the construction phase

• CMAR delivers the project within Guaranteed Maximum Price (GMP)

• Used for projects where the Owner gains the benefit of having the Contractors input during planning and design

• Provides the ability to start construction on portions of the work even if the overall design is not finalized

The procurement method has aspects of professional services procurement. For the construction planning phase, the City can require the successful proposers to implement subcontractor mentoring, use of hiring and training for citizens in socioeconomic disadvantaged neighborhoods, and targeted outreach.

Page 16: Capital Programs - O'Hare 21

16

• CM-at-Risk contracts to construct the Terminal 5 M Extension projects as well as additional O’Hare 21 Projects

• Projects will include airside work, landside projects, terminal projects, site preparation and security packages

CM@RISK FOR T5 EXTENSION AND ADDITIONAL O’HARE 21 PROJECTS (ANTICIPATED TO BE TWO CONTRACTS)

Anticipated Term: TBD

Anticipated Advertisement Date:

4th Quarter 2016

Anticipated Award Date:

2nd Quarter 2017

Page 17: Capital Programs - O'Hare 21

17

EXPANSION OF TERMINAL 5 SUPPORTING INCREASED DEMAND

Terminal expansion includes 9 new wide-body gates Provides for a second A380 capable gate at O’Hare Addresses near-term demand and capacity of International Terminal gates and facilities Provides additional capacity for domestic flights Includes expanded security screening and Federal Inspection Services (FIS) facilities

Page 18: Capital Programs - O'Hare 21

STATUS – TERMINAL 5 EXTENSION

Design NTP (Sitework) 4th Quarter 2016 Design NTP (Facility) 4th Quarter 2016 Advertise Sitework Construction 2nd Quarter 2017 NTP Sitework Construction 3rd Quarter 2017 Advertise Facility Construction 1st Quarter 2018 NTP Facility Construction 1st Quarter 2018 Operational Facility 4th Quarter 2019

18CONFIDENTIAL – DRAFT – PREDECISIONAL

Page 19: Capital Programs - O'Hare 21

CAPITAL IMPROVEMENT PROGRAM (CIP) PROJECTS

Page 20: Capital Programs - O'Hare 21

UPCOMING CONSTRUCTION – CIP UNDER $30MProject Description Anticipated

Ad DateEstimated

Contract ValueDBE/MBE/WBE/

SBE Goals:United Airlines Employee Parking Lot Reconstruction

Remove existing asphalt pavement and reconstruct the parking lot with latex concrete.

Bids Due: 11/15/16 $1 – 1.5 Million SBE 51%

MDW Taxiway A Extension Construction of a new Taxiway A extension, including pavement, associated drainage, and lighting installation.

1st Quarter 2017 $3 – 5 Million DBE 30%

Building 521 Renovation 16,500sf of conditioned space for police use and 2,770sf of garage space.

1st Quarter 2017 $3 – 4 Million MBE 26% / WBE 6%

Trunk Radio System Replacement Replace trunking systems, backup systems, core controllers, repeaters, dispatch consoles, recorders, and fiber infrastructure.

1st Quarter 2017 $5 – 7 Million MBE 26% / WBE 6%

Restroom Modernization – Phase 5 Renovation of nine restrooms throughout Terminals 1 & 3. 1st Quarter 2017 $10 – 15 Million MBE 26% / WBE 6%

Bessie Coleman Water Main Replace 5,000LF of water main along Bessie Coleman Drive. 1st Quarter 2017 $2 – 3 Million MBE 26% / WBE 6%

MDW Airfield Lighting Infrastructure Improvements

Installation of a new duct bank system for Airfield lighting. 1st Quarter 2017 $10 – 15 Million DBE 30%

MDW Airport Maintenance Complex Improvements

Replacement of HVAC, roof, overhead doors, and emergency egress doors for the MDW AMC facility.

1st Quarter 2017 $10 – 15 Million MBE 26% / WBE 6%

Page 21: Capital Programs - O'Hare 21

UPCOMING CONSTRUCTION – CIP PROJECTS OVER $30MProject Description Anticipated

Ad DateEstimated

Contract ValueDBE/MBE/WBE/

SBE Goals:Replace High Temperature Water Generators

Replace all eight (8) 75,000 MBH High Temperature Water (HTW) Generators along with their associated equipment.

4th Quarter 2016 $55 – 60 Million MBE 26% / WBE 6%

MDW Security Checkpoint Expansion

Widening of the existing passenger bridge as a means to accommodate current and future pedestrian traffic flow.

4th Quarter 2016 $80 – 85 Million DBE 30%

MDW Terminal Parking Garage Extension

Expansion of existing Terminal Parking Garage, adding approximately 1,500 parking spaces.

1st Quarter 2017 $115 – 125 Million MBE 26% / WBE 6%

Page 22: Capital Programs - O'Hare 21

RUNWAY 9C/27C AND ADDIT IONAL A IRFIELD IMPROVEMENT PROJECTS

Page 23: Capital Programs - O'Hare 21

CONFIDENTIAL – DRAFT – PREDECISIONAL 23

RUNWAY 9C/27C AND OTHER AIRFIELD PROJECTS• Overall Program is

estimated at roughly $1.3B

• Graphic depicts the projects CDA is leading

• Other associated projects, such as relocation of Airline Support Facilities relocation and fuel line relocations are not reflected herein

Page 24: Capital Programs - O'Hare 21

RWY 9C PROJECTS AND TIMELINESProject Description Anticipated

Ad DateEstimated

Contract ValueDBE/MBE/WBE/

SBE Goals:

Centralized Deicing Facility – Mass Grading Project

Mass grading (earthwork) including sorting, transport, cut and embankment, and other incidental work to prepare the site for the paving of these improvements. Project extends and prepared a portion of the Elgin-O’Hare Bypass. Project site is located in the Aircraft Operations Area (AOA)

4th Quarter 2016 $55-75 Million MBE 26% / WBE 6%

Rwy 9C/27C Package 1 Construction of temporary and permanent airfield pavements (PCC & AC Shoulders), airfield lighting, signage, grading drainage, site restoration, utility infrastructure (power & communications) and other incidental work. Project site is located in the Aircraft Operations Area (AOA). Work will be phased to accommodate aircraft operations and may require off peak construction. Key work items include approximately 201,000 SY of PCC pavement and 85,000 SY of AC pavement.

4th Quarter 2016 $80 – 120 Million DBE 30%

Twy ZJ and TFR – Package A Construction of an on-airport two lane road and two taxiways. The project includes earthwork, utility construction, lighting, signage, PCC and AC pavements, site restoration, drainage and other incidental work.Project site is located in the Aircraft Operations Area (AOA).

4th Quarter 2016 $48 – 57 Million DBE 30%

10R Safety and Security Package 2 Miscellaneous improvements including grading, roadway signage, fencing and utility work.

1st Quarter 2017 $5 – 7 Million DBE 30%

Centralized Deicing Facility – Paving/Electrical Project

Construction of a new pavement area dedicated to deice aircraft during winter operations and to stage aircraft during the balance of the year. This project also includes the construction of two parallel taxiways. Scope includes PCC Pavement, airfield lighting and signage, flood lighting, deicing fluid collection systems, drainage, and other incidental work. Project site is located in the Aircraft Operations Area (AOA).

2nd Quarter 2017 $75 – 85 Million MBE 26% / WBE 6%

Page 25: Capital Programs - O'Hare 21

RWY 9C PROJECTS AND TIMELINES (CONTINUED)Project Description Anticipated

Ad DateEstimated

Contract ValueDBE/MBE/WBE/

SBE Goals:Relocation of ARFF#2 Construction of a replacement on-airport aircraft rescue and fire fighting

station (ARFF) on the north east side of the airfield. Construction will be located airside. Structure will be single story with a mechanical mezzanine, with 6-high bay apparatus bays. Project site is located in the Aircraft Operations Area (AOA).

2nd Quarter 2017 $15 – 25 Million DBE 30%

East Lighting Control Vault Construction of a new airfield lighting vault (similar to the south vault) housing the switchgear, ALSC and regulators needed to power the airfield lighting and signage for Runway 9C/27C, Runway 9R/27L and associated taxiways. Site for this facility will be adjacent to the ARFF #2 on the north east of the airfield. Project site is located in the Aircraft Operations Area (AOA).

2nd Quarter 2017 $15 – 25 Million DBE 30%

Rwy 9C/27C Package 2 Construction of airfield pavements, PCC and AC, airfield lighting and signage, demolitions of existing structures and underground utilities and other improvements, site preparation, grading and drainage, site restoration, utilities and other appurtenances and incidental work. Project site is located in the Aircraft Operations Area (AOA). Key work items include approximately 510,000 SY of PCC pavement and 270,000 SY of asphalt pavement.

1st Quarter 2018 $120 – 160 Million DBE 30%

Rwy 9C/27C Package 3 Phased construction of airfield pavements, PCC and AC, airfield lighting and signage, site preparation, grading and drainage, site restoration, utilities and other appurtenances and incidental work. Project site is located in the Aircraft Operations Area (AOA). Key work items include approximately 150,000 SY of PCC pavement and 82,000 SY of asphalt pavement.

3rd Quarter 2018 $40 – 60 Million DBE 30%

Page 26: Capital Programs - O'Hare 21

RWY 9C PROJECTS AND TIMELINES (CONTINUED)Project Description Anticipated

Ad DateEstimated

Contract ValueDBE/MBE/WBE/

SBE Goals:

Relocation of Taxiways A and B Phased construction of airfield pavements, PCC and AC, airfield lighting and signage, pavement removal, PCCP crushing, and underground utilities and other improvements, site preparation, grading and drainage, site restoration, utilities and other appurtenances and incidental work. Project site is located in the Aircraft Operations Area (AOA).

2nd Quarter 2018 $100 – 140 Million MBE 26% / WBE 6%

ATS Lot E Station Demolition Demolition of the structure and platform of this station, modification of wayside systems, power systems and track work as required and site restoration. Construction will require coordination with and limited interruption of services of the Airport’s Transit System Project site is in the current Public Parking Lot E.

4th Quarter 2019 $10 – 20 Million DBE 30%