Capital Budgeting Analyses
-
Upload
imran-ahmad -
Category
Documents
-
view
11 -
download
3
description
Transcript of Capital Budgeting Analyses
Lead WorksheetCapital Budgeting Analysis forSupplemental Material for Short Course 3: Capital Budgeting Analysis, located on the internet at www.exinfm.com/training. Prepared by: Matt H. Evans, CPA, CMA, CFMMedical Services USA
Purpose of Spreadsheet Lead WksIllustrate concepts related to capital budgeting analysis of projects. Certain aspects of a capitalProject Aproject may have not been included in order to help highlight basic concepts, such asProject BNet Present Value. The spreadsheet is setup to evaluate six different projects and summarizeProject Call projects based on both economic analysis and risk factors assigned.Project DNote: The Solver feature of Excel is used in an example at the end. Please make sure that youProject Ehave installed Solver:Solver add-on feature (Tools => Add-Ins => Solver).Project FSummaryEconomic AnalysisThree economic criteria are applied to projects: Net Present Value, Modified Internal Rate ofReturn and Discounted Payback Period. If your project(s) have non-periodic payments(payments are not equal over the life of the project), then you should use these Excel Functions:=XNPV for Net Present Value by entering specific dates of cash flows=XIRR for Internal Rate of Return by entering specific dates of cash flows
Cell IndicatorsCertain cells are highlighted as follows:Selected
input cells (not all input cells are highlighted since each project
is unique)
Matt H. Evans: Cells with a red triangle in the upper right corner
have commentsCell includes a comment - move mouse and point over
cell for commentIndication of an error in calculation or a red flag
that a criteria has not been metOrganization of SpreadsheetLead
WorksheetProject A Analysis - Example with Annual Cash Flow
CalculationsProject B Analysis - Example with Sunk Costs &
Projected FinancialsProject C Analysis - Example of Upgrade
InvestmentProject D Analysis - Example of Project FinancingProject
E Analysis - Example of Foreign InvestmentProject F Analysis -
Example of Monthly Inflows / OutflowsSummary and Example of Using
Excel SolverAnswer Report 1 - Output from Using Excel Solver in
Summary ExampleGeneral InputThe following general inputs have been
used on different worksheets:ADiesel Generation SystemF Priority
>2Preliminary ReviewAssign points from 0 to 5 for each of the
following project attributes. 0 indicates that the attribute does
not apply to the project. 5 is the highest rating, indicating that
the project strongly meets this project attribute.Financial
Attributes:F1Project improves overall profitability of the
company2F2Project lowers cost structure3F3Project will generate a
rate of return3F4Project improves asset utilization1F5Other
Financial Attribute __________________________________0F6Other
Financial Attribute __________________________________0
Operating Attributes:O1Improves operating efficiencies4O2Increases the customer base0O3Improves overall customer service0O4Improves competitive position of company0O5Other Operating Attribute _________________________________0O6Other Operating Attribute _________________________________0
Contingency Attributes:C1Project has options that allow for change during life2C2Project will positively impact company even if value is negative4C3Project can be abandoned easily with some positive value1C4Project permits several options to maximize value2C5Other Cont Attribute _____________________________________0
Miscellaneous Attributes:M1Expands Human Resource Capital0M2Enhances workforce productivity0M3Project meets a critical regulatory, security or specific need0M4Project fits with company strategy and goals1M5Probability of project success is very high / low risk4M6Other Misc Attribute _____________________________________0M7Other Misc Attribute _____________________________________0M8Other Misc Attribute _____________________________________0
Total Preliminary Points27
Projects with point totals less than 15 may represent poor investments and require additionalapproval before further analysis and processing. Projects with point totals between 15 and 20require caution and careful analysis. Projects with point totals greater than 20 may proceedwith analysis and submission.
Financial Analysis Proposed Project Expenditure:*Equipment &
Facilities (purchase price)
Matt H. Evans: Quote from vendor selected in bidding
process.165,000*Installation Cost650*Labor
Matt H. Evans: In house personnel to assist with installation and
testing during first week.4,500*Materials
Matt H. Evans: Initially, purchase of diesel fuel for storage and
testing.250*Shipping1,280*Taxes11,550Other Costs
(expensed)350Intial Cash Outlay for Project183,580Tax Breaks for
Investment
Matt H. Evans: Not recovered until three months after project is
complete.(1,500)Sale of Existing Assets0Tax Benefit on Loss - Sale
of Assets0Total Project Investment182,080Project Analysis
Required?Yes
*capitalized costs subject to depreciation using double declining method over 8 years with $ 8,000 salvage valueNOTE: Depreciation for tax purposes is considered the same for accounting purposes. If tax depreciation isdifferent than accounting depreciation, deduct tax depreciation in calculating taxes.Cash Flows associated with Project:Year 1:Reductions in annual operating costs28,900New revenues from higher output volumes6,200Eliminate third party vendor service35,000Annual service and maintenance(4,600)Annual fuel costs(1,500)Depreciation:Cost183,230Salvage Value8,000Useful Life8Depreciation in Yr1(45,808)Operating Cash Flow in Year 118,193Less Taxes(5,003)Net Income - Year 113,190Add Back Non Cash Depreciation45,808Change to Net Working Capital(3,500)Net Cash Flow - Year 155,497
Year 2:Reductions in annual operating costs32,100New revenues from higher output volumes6,900Eliminate third party vendor service35,000Annual service and maintenance(5,000)Annual fuel costs(1,800)Depreciation:Cost183,230Salvage Value8,000Useful Life8Depreciation in Yr2(34,356)Operating Cash Flow in Year 232,844Less Taxes(9,032)Net Income - Year 223,812Add Back Non Cash Depreciation34,356Change to Net Working Capital(650)Net Cash Flow - Year 257,518Year 3:Reductions in annual operating costs34,800New revenues from higher output volumes7,100Eliminate third party vendor service35,000Annual service and maintenance(5,000)Annual fuel costs(2,000)Depreciation:Cost183,230Salvage Value8,000Useful Life8Depreciation in Yr3(25,767)Operating Cash Flow in Year 344,133Less Taxes(12,137)Net Income - Year 331,997Add Back Non Cash Depreciation25,767Change to Net Working Capital(550)Net Cash Flow - Year 357,213Year 4:Reductions in annual operating costs37,200New revenues from higher output volumes7,900Eliminate third party vendor service0Annual service and maintenance(5,200)Annual fuel costs(2,100)Depreciation:Cost183,230Salvage Value8,000Useful Life8Depreciation in Yr4(19,325)Operating Cash Flow in Year 418,475Less Taxes(5,081)Net Income - Year 413,394Add Back Non Cash Depreciation19,325Change to Net Working Capital(250)Net Cash Flow - Year 432,469Year 5:Reductions in annual operating costs40,900New revenues from higher output volumes8,900Eliminate third party vendor service0Annual service and maintenance(5,300)Annual fuel costs(2,200)Depreciation:Cost183,230Salvage Value8,000Useful Life8Depreciation in Yr5(14,494)Operating Cash Flow in Year 527,806Less Taxes(7,647)Net Income - Year 520,160Add Back Non Cash Depreciation14,494Change to Net Working Capital(350)Net Cash Flow - Year 534,303Year 6:Reductions in annual operating costs44,200New revenues from higher output volumes9,700Eliminate third party vendor service0Annual service and maintenance(5,400)Annual fuel costs(2,300)Depreciation:Cost183,230Salvage Value8,000Useful Life8Depreciation in Yr6(10,870)Operating Cash Flow in Year 635,330Less Taxes(9,716)Net Income - Year 625,614Add Back Non Cash Depreciation10,870Change to Net Working Capital(150)Net Cash Flow - Year 636,334Year 7:Reductions in annual operating costs50,100New revenues from higher output volumes10,200Eliminate third party vendor service0Annual service and maintenance(5,500)Annual fuel costs(2,400)Depreciation:Cost183,230Salvage Value8,000Useful Life8Depreciation in Yr7(8,153)Operating Cash Flow in Year 744,247Less Taxes(12,168)Net Income - Year 732,079Add Back Non Cash Depreciation8,153Change to Net Working Capital(150)Net Cash Flow - Year 740,082Year 8:Reductions in annual operating costs55,500New revenues from higher output volumes11,000Rebuild / Repair Unit Option(25,000)Annual service and maintenance(4,600)Annual fuel costs(2,600)Depreciation:Cost183,230Salvage Value8,000Useful Life8Depreciation in Yr8(6,115)Operating Cash Flow in Year 828,185Less Taxes(7,751)Net Income - Year 820,434Add Back Non Cash Depreciation6,115Change to Net Working Capital(50)Net Cash Flow - Year 826,499
Terminal Year 9Salvage Value of Asset5,000Working Capital Reversed2,500Terminal Value7,500
At the end of Year 8, a decision will be made to either rebuild
the asset or outsource to third party.Economic Analysis Summarize
Cash Outflows and Inflows for Project:CashPresent
RecoveryYearFlowsValuePayback0(182,080)(182,080)155,49749,997(132,083)
257,51846,683(85,400) 357,21341,834(43,566) 432,46921,389(22,177)
534,30320,357(1,820)636,33419,42617,60611.00%Reinvestment Rate for
Project =>6.00% Net Present Value$51,342 Modified
IRR11.03%Discounted Payback (years)6.1Economic AssessmentProject
has positive Net Present Value?YesProject has IRR in excess of
cost?YesProject has a positive payback?YesProject must meet at
least two of the three Economic Criteria, otherwise specialapproval
is required.Risk AnalysisRisk Premium Applied to Project
1.50%Compare Risk Factor with Government Treasury Bond (lowest
risk) to Project Risk Factor:Risk Ranking = 1 for lowest possible
risk up to 10 for highest possible riskProbability of Accurate and
Reliable Information - Gov't T Bond
Matt H. Evans: There are usually very few unknowns concerning a
Government Treasury Bond; yields, payments, and other attributes
are usually very certain and thus, the probability of reliable
information is extremely high for such an investment.1.00(a)Risk
Ranking assigned to Gov't Treasury Bond ( 1 to 10)1(b)Exponential
power to apply to Risk Ranking is 2 - (a)1(c)Risk Factor = (b)
raised to the power (c)1Probability of Accurate and Reliable
Information for Project0.6Risk Ranking assigned to project (1 to
10)5 Exponential power to apply to Project1.4Risk Factor for
Project 10 Assign probabilities to three possible outcomes for
project:PPesimistic outlook, declining growth, slower volumes,
etc.25.00%NNormal expected outlook as applied in
analysis60.00%OOptomistic outlook, better than expected
growth15.00%Total should equal100.00%100.00%Enter Expected Cash
Flows for different outcomes:
StandardCoeff ofNet Cash FlowsExpectedDeviationVariationYearPesimistNormalOptomistValue(Abs Risk)(Rel Risk)141,80055,49764,90053,48317,7580.332239,75057,51867,30054,54321,5840.396337,40057,21366,10053,59322,8540.426426,20032,46941,05032,18910,6990.332521,05034,30340,90031,97915,6790.490613,20036,33439,80031,07122,5310.725711,80040,08240,80033,11925,4300.76888,10026,49935,70023,27921,7930.936Terminal1,0007,5008,5006,0256,3461.053Totals200,300347,416405,050319,282164,6740.516Absolute Risk of Project (Std Deviation)164,674Relative Risk of Project (Coeff of Variation)0.516
Revised Economic Analysis using Expected ValuesExpectedPresentRecoveryYearValueValuePayback0(182,080)(182,080)153,48348,183(133,897)254,54344,268(89,628)353,59339,187(50,442)432,18921,204(29,238)531,97918,978(10,259)631,07116,6126,352payback733,11915,95222,304823,27910,10232,40696,0252,35534,761Totals 34,761 Net Present Value$34,761 Modified IRR10.07%Discounted Payback (years)6.6
Project BCapital Budgeting Analysis forMedical Services USABNew Clinic in Kansas CityProject InformationProject Description >New Walk In Clinic - Kansas CityProject Benefits >Toehold market position, profit center, business expansionProject Location >Kansas CityResponsible Division >Mid WestResponsible Department >Business DevelopmentContact Person Name >Bill Watson, Operations DirectorEstimated Project Start Date >04/01/92Classification >2 Justification >CPriority >3 Preliminary ReviewAssign points from 0 to 5 for each of the following project attributes. 0 indicates that the attribute does not apply to the project. 5 is the highest rating, indicating that the project strongly meets this project attribute.Financial Attributes:F1Project improves overall profitability of the company3F2Project lowers cost structure2F3Project will generate a rate of return4F4Project improves asset utilization2F5Other Financial Attribute __________________________________0F6Other Financial Attribute __________________________________0
Operating Attributes:O1Improves operating efficiencies2O2Increases the customer base3O3Improves overall customer service3O4Improves competitive position of company2O5Other Operating Attribute _________________________________0O6Other Operating Attribute _________________________________0
Contingency Attributes:C1Project has options that allow for change during life0C2Project will positively impact company even if value is negative0C3Project can be abandoned easily with some positive value0C4Project permits several options to maximize value0C5Other Cont Attribute _____________________________________0
Miscellaneous Attributes:M1Expands Human Resource Capital0M2Enhances workforce productivity0M3Project meets a critical regulatory, security or specific need0M4Project fits with company strategy and goals3M5Probability of project success is very high / low risk0M6Other Misc Attribute _____________________________________0M7Other Misc Attribute _____________________________________0M8Other Misc Attribute _____________________________________0
Total Preliminary Points24
Projects with point totals less than 15 may represent poor investments and require additionalapproval before further analysis and processing. Projects with point totals between 15 and 20require caution and careful analysis. Projects with point totals greater than 20 may proceedwith analysis and submission.
Financial Analysis
Proposed Project Expenditure: Rework / Upgrade Existing
Building85,000(1)Equipment and Fabrication45,000(2)Marketing and
Promotion of Clinic7,500Contingency Costs
Matt H. Evans: A contingency provision for unexpected costs is
added into the investment estimate.3,500Market Study /
Research
Matt H. Evans: A market study was conducted to ascertain if a new
clinic would be profitable in Kansas City. The study is made
regardless of the investment decision and therefore, it is not a
relevant cost associated with the investment; it is sunk regardless
if the project goes ahead or
not.2,500302,8332,8332,8332,8332,8332,8332,8332,8332,8332,8332,500Equipment
126,9236,3465,7695,1924,6154,0383,4622,8852,3081,7310Operating Cash
Flow22,49420,77931,22343,69644,13448,19748,34549,94351,90452,41447,450Net
Working
Capital(6,500)(7,500)(10,000)(12,500)(13,500)(14,000)(14,500)(14,900)(15,300)(15,500)(16,000)Planned
Critical Cash Outlays(1,500)(2,500)(3,500)(500)0000000Total Cash
Flow14,49410,77917,72330,69630,63434,19733,84535,04336,60436,91431,450
Economic Analysis Summarize Cash Outflows and Inflows for
Project: CashPresent
YearFlowsValuePayback0(141,000)(141,000)114,49412,883(128,117)210,7798,517(119,599)317,72312,447(107,152)430,69619,163(87,989)530,63417,000(70,990)634,19716,868(54,121)733,84514,840(39,282)835,04313,658(25,624)936,60412,681(12,943)1036,91411,368(1,575)1131,4508,6097,033payback1231,4507,65214,6861331,4506,80221,4881431,4506,04627,534
1531,4505,37432,9081631,4504,77737,6861731,4504,24641,9321831,4503,77545,7071931,4503,35549,0622031,4502,98252,044Net
Present Value52,044Required Rate of Return for Project
=>12.50%Reinvestment Rate for Project =>7.50%Net Present
Value $52,044 Modified IRR11.36% Discounted Payback
(years)11.18Economic AssessmentProject has positive Net Present
Value?YesProject has IRR in excess of cost?NoProject has a positive
payback?YesProject must meet at least two of the three Economic
Criteria, otherwise specialapproval is required.Risk AnalysisRisk
Premium Applied to Project 3.00%Compare Risk Factor with Government
Treasury Bond (lowest risk) to Project Risk Factor:Risk Ranking = 1
for lowest possible risk up to 10 for highest possible
riskProbability of Accurate and Reliable Information - Gov't T
Bond
Matt H. Evans: There are usually very few unknowns concerning a
Government Treasury Bond; yields, payments, and other attributes
are usually very certain and thus, the probability of reliable
information is extremely high for such an investment.1.00(a)Risk
Ranking assigned to Gov't Treasury Bond ( 1 to 10)1(b)Exponential
power to apply to Risk Ranking is 2 - (a)1(c)Risk Factor = (b)
raised to the power (c)1Probability of Accurate and Reliable
Information for Project0.5Risk Ranking assigned to project (1 to
10)7 Exponential power to apply to Project1.5 Risk Factor for
Project 19Assign probabilities to three possible outcomes for
project:PPesimistic outlook, declining growth, slower volumes,
etc.35.00%NNormal expected outlook as applied in
analysis60.00%OOptomistic outlook, better than expected
growth5.00%Total should equal100.00%100.00%Enter Expected Cash
Flows for different outcomes:
StandardCoeff ofNet Cash FlowsExpectedDeviationVariationYearPesimistNormalOptomistValue(Abs Risk)(Rel Risk)18,65014,49426,80013,06413,8451.06026,80010,77927,50010,22315,0311.47037,90017,72333,20015,05919,7741.31348,60030,69637,80023,31725,8651.10958,10030,63443,90023,41030,4221.30067,50034,19742,10025,24830,7941.22077,10033,84541,85024,88430,9081.24286,20035,04340,95025,24331,5011.24896,00036,60440,20026,07231,6301.213105,50036,91439,90026,06831,9931.227115,10031,45037,75022,54329,3861.304124,90031,45035,95022,38328,3671.267134,25031,45034,15022,06527,7791.259143,70531,45032,99021,81627,5201.261153,25031,45031,65021,59027,0541.253162,68031,45031,28021,37227,3491.280172,00531,45031,00021,12227,8061.316181,49031,45030,85020,93428,1971.347191,10531,45029,99020,75627,9861.3482079031,45028,75020,58427,4541.334Totals101,625595,428698,560427,753540,6601.264
Absolute Risk of Project (Std Deviation)540,660Relative Risk of Project (Coeff of Variation)1.264
Revised Economic Analysis using Expected ValuesExpectedPresentRecoveryYearValuesValuePayback0(141,000)(141,000)113,06411,612(129,388)210,2238,077(121,311)315,05910,576(110,734)423,31714,557(96,177)523,41012,991(83,186)625,24812,454(70,732)724,88410,911(59,821)825,2439,838(49,983)926,0729,032(40,951)1026,0688,028(32,923)1122,5436,171(26,752)1222,3835,446(21,306)1322,0654,772(16,534)1421,8164,194(12,340)1521,5903,689(8,651)1621,3723,246(5,404)1721,1222,852(2,552) 1820,9342,513(40)1920,7562,2142,175payback2020,5841,9524,127Net Present Value4,127 Net Present Value$4,127Modified IRR9.68%Discounted Payback (years)19.02
Project CCapital Budgeting Analysis forMedical Services USACUpgrade to DuBois CenterProject InformationProject Description >Upgrade DuBois for unused capacityProject Benefits >Better use of facility, more incomeProject Location >IowaResponsible Division >Mid WestResponsible Department >FinanceContact Person Name >Cheryl Strickland, ControllerEstimated Project Start Date >03/15/92Classification >4 Justification >CPriority >3 Preliminary ReviewAssign points from 0 to 5 for each of the following project attributes. 0 indicates that the attribute does not apply to the project. 5 is the highest rating, indicating that the project strongly meets this project attribute.Financial Attributes:F1Project improves overall profitability of the company3F2Project lowers cost structure3F3Project will generate a rate of return4F4Project improves asset utilization4F5Other Financial Attribute __________________________________0F6Other Financial Attribute __________________________________0
Operating Attributes:O1Improves operating efficiencies4O2Increases the customer base3O3Improves overall customer service3O4Improves competitive position of company2O5Other Operating Attribute _________________________________0O6Other Operating Attribute _________________________________0
Contingency Attributes:C1Project has options that allow for change during life0C2Project will positively impact company even if value is negative0C3Project can be abandoned easily with some positive value0C4Project permits several options to maximize value0C5Other Cont Attribute _____________________________________0
Miscellaneous Attributes:M1Expands Human Resource Capital0M2Enhances workforce productivity0M3Project meets a critical regulatory, security or specific need0M4Project fits with company strategy and goals2M5Probability of project success is very high / low risk3M6Other Misc Attribute _____________________________________0M7Other Misc Attribute _____________________________________0M8Other Misc Attribute _____________________________________0
Total Preliminary Points31
Projects with point totals less than 15 may represent poor investments and require additionalapproval before further analysis and processing. Projects with point totals between 15 and 20require caution and careful analysis. Projects with point totals greater than 20 may proceedwith analysis and submission.
Cost Volume Profile of DuBois Facility
Personnel & Labor37.50Supplies and Inventory2.65Variable Adm Overhead3.60Fixed Overhead Costs10.50Total Unit Costs per Billable Hour54.25
Current Operating Capacity =>60%Maximum Capacity per month15,000billable hoursSales growth rates over the next ten years are estimated at 4% per year with increases to costs 1.03estimated at 1.5% per year for each variable component.1.015
Estimated Changes from Upgrade Investment
Upgrade Investment will result in additional 5,000 billable hours per monthNew Services from Upgrade Investment are billable to customers at $ 50.00 per hourCapacity after upgrade =>14,000Does upgrade project exceed max?No
Financial Analysis
Proposed Project Expenditure:Upgrade Systems &
Facilities
Matt H. Evans: Modifications to technical equipment and processes
to expand and introduce new services to existing customer base.
These costs are not considered capitalized related
expenditures.1,150,000Executive Management Time
Matt H. Evans: Senior Management from other locations will
temporarily oversee upgrade project for successful implementation.
405,000Training and Promotion135,000Contingency Costs90,000Total
Investment1,780,000Project Analysis Required?Yes
Annual< - - relevant annual costs to project - -
>IncrementalPersonnelSuppliesVar AdmProfitsLessProjectAdj
toCashYearRevenues& Labor& InventoryOverheadbefore
TaxTaxesIncomeIncome
Matt H. Evans: The project is expected to tie up some minor amounts
of working
capial.Flow13,000,000(2,250,000)(159,000)(216,000)375,000(103,125)271,875(15,000)256,87523,090,000(2,283,750)(161,385)(219,240)425,625(117,047)308,578(13,000)295,57833,182,700(2,318,006)(163,806)(222,529)478,359(131,549)346,811(12,000)334,81143,278,181(2,352,776)(166,263)(225,867)533,275(146,651)386,625(12,000)374,62553,376,526(2,388,068)(168,757)(229,255)590,447(162,373)428,074(12,000)416,07463,477,822(2,423,889)(171,288)(232,693)649,952(178,737)471,215(12,000)459,21573,582,157(2,460,247)(173,857)(236,184)711,868(195,764)516,105(12,000)504,10583,689,622(2,497,151)(176,465)(239,727)776,279(213,477)562,802(12,000)550,80293,800,310(2,534,608)(179,112)(243,322)843,267(231,898)611,369(12,000)599,369103,914,320(2,572,627)(181,799)(246,972)912,921(251,053)661,868(12,000)649,868
Due to the rapid changes in services provided by this upgrade
investment project, no terminal value was calculated for the
periods beyond year 10. Economic Analysis Summarize Cash Outflows
and Inflows for Project: CashPresent YearFlowsValuePayback
0(1,780,000)(1,780,000) 1256,875233,523(1,546,477)
2295,578244,279(1,302,198) 3334,811251,548(1,050,650)
4374,625255,874(794,776) 5416,074258,349(536,427)
6459,215259,215(277,212)
7504,105258,685(18,527)8550,802256,953238,427payback9599,369254,191492,618
10649,868250,552743,170Net Present Value743,170Required Rate of
Return for Project =>10.00%Reinvestment Rate for Project
=>4.00%Net Present Value $743,170 Modified IRR11.24%Discounted
Payback (years)8.07Economic AssessmentProject has positive Net
Present Value?YesProject has IRR in excess of cost?YesProject has a
positive payback?YesProject must meet at least two of the three
Economic Criteria, otherwise specialapproval is required.Risk
AnalysisRisk Premium Applied to Project 0.50%Compare Risk Factor
with Government Treasury Bond (lowest risk) to Project Risk
Factor:Risk Ranking = 1 for lowest possible risk up to 10 for
highest possible riskProbability of Accurate and Reliable
Information - Gov't T Bond
Matt H. Evans: There are usually very few unknowns concerning a
Government Treasury Bond; yields, payments, and other attributes
are usually very certain and thus, the probability of reliable
information is extremely high for such an investment.1.00(a)Risk
Ranking assigned to Gov't Treasury Bond ( 1 to 10)1(b)Exponential
power to apply to Risk Ranking is 2 - (a)1(c)Risk Factor = (b)
raised to the power (c)1Probability of Accurate and Reliable
Information for Project0.7Risk Ranking assigned to project (1 to
10)4 Exponential power to apply to Project1.3 Risk Factor for
Project 6Assign probabilities to three possible outcomes for
project:PPesimistic outlook, declining growth, slower volumes,
etc.20.00%NNormal expected outlook as applied in
analysis65.00%OOptomistic outlook, better than expected
growth15.00%Total should equal100.00%100.00%Enter Expected Cash
Flows for different outcomes:
StandardCoeff ofNet Cash FlowsExpectedDeviationVariationYearPesimistNormalOptomistValue(Abs Risk)(Rel Risk)1212,500256,875285,700252,32454,9780.2182242,500295,578324,300289,27162,3010.2153301,200334,811362,050332,17444,8920.1354326,700374,625401,200369,02656,6380.1535370,900416,074441,300410,82353,4930.1306411,800459,215483,700453,40554,9490.1217461,900504,105533,100500,01353,2390.1068510,200550,802582,200547,39153,3230.0979561,300599,369631,100596,51551,3740.08610615,100649,868677,700647,08946,2300.0714,014,1004,441,3204,722,3504,398,031531,4190.121Absolute Risk of Project (Std Deviation)531,419Relative Risk of Project (Coeff of Variation)0.121
Revised Economic Analysis using Expected ValuesExpectedPresentRecoveryYearValuesValuePayback0(1,780,000)(1,780,000)1252,324229,385(1,550,615)2289,271239,067(1,311,548)3332,174249,568(1,061,981)4369,026252,050(809,931)5410,823255,089(554,842)6453,405255,935(298,907)7500,013256,586(42,321)8547,391255,362213,041payback9596,515252,980466,021 10647,089249,481715,502Net Present Value715,502Net Present Value$715,502 Modified IRR11.12%Discounted Payback (years)8.17
Project DCapital Budgeting Analysis forMedical Services USADSoutheastern UpgradesProject InformationProject Description >Upgrade to various Southeastern facilitiesProject Benefits >Better use of facility, more incomeProject Location >AtlantaResponsible Division >SoutheastResponsible Department >EngineeringContact Person Name >Bob FerrellEstimated Project Start Date >02/05/92Classification >4 Justification >CPriority >3 Preliminary ReviewAssign points from 0 to 5 for each of the following project attributes. 0 indicates that the attribute does not apply to the project. 5 is the highest rating, indicating that the project strongly meets this project attribute.Financial Attributes:F1Project improves overall profitability of the company2F2Project lowers cost structure2F3Project will generate a rate of return4F4Project improves asset utilization5F5Other Financial Attribute __________________________________0F6Other Financial Attribute __________________________________0
Operating Attributes:O1Improves operating efficiencies5O2Increases the customer base1O3Improves overall customer service2O4Improves competitive position of company3O5Other Operating Attribute _________________________________0O6Other Operating Attribute _________________________________0
Contingency Attributes:C1Project has options that allow for change during life0C2Project will positively impact company even if value is negative1C3Project can be abandoned easily with some positive value1C4Project permits several options to maximize value0C5Other Cont Attribute _____________________________________0
Miscellaneous Attributes:M1Expands Human Resource Capital0M2Enhances workforce productivity2M3Project meets a critical regulatory, security or specific need0M4Project fits with company strategy and goals2M5Probability of project success is very high / low risk2M6Other Misc Attribute _____________________________________0M7Other Misc Attribute _____________________________________0M8Other Misc Attribute _____________________________________0
Total Preliminary Points32
Projects with point totals less than 15 may represent poor investments and require additionalapproval before further analysis and processing. Projects with point totals between 15 and 20require caution and careful analysis. Projects with point totals greater than 20 may proceedwith analysis and submission.
Project Summary
Several facilities in the Southeast area need to upgrade existing scanner equipment to better serve customersand produce higher quality analysis / treatments. The Atlanta Bank has agreed to finance $ 500,000 towardsthe investment at 9% over a five year period. The loan repayment schedule is as follows:
InterestNumber of LoanInterestPrincipalTotalTax BenefitRateInstallmentsYearBalancePaymentPaymentPaymentof Interest0.0951500,000(45,000)(83,546)(128,546)12,3752416,454(37,481)(91,065)(128,546)10,3073325,388(29,285)(99,261)(128,546)8,0534226,127(20,351)(108,195)(128,546)5,5975117,932(10,614)(117,932)(128,546)2,919
Financial Analysis
Proposed Project Expenditure:Total Upgrade Acquisition Price1,650,000(1)Installation / Training / Other Costs65,000Total Investment1,715,000Financed through Bank(500,000)Net Cash Outlay1,215,000Project Analysis Required?Yes
(1): $ 650,000 of this price is subject to capitalization.
Depreciation deducted on the tax returndiffers from depreciation
for accounting purposes:Tax ReturnAccountingTax
BenefitYearDepreciationDepreciationDepreciation1325,00065,00089,3752162,50065,00044,688381,25065,00022,344440,62565,00011,172540,62565,00011,1726
65,000765,000865,000965,0001065,000Total650,000650,000Cash Flow
Analysis #1 - Only Project Cash Flows
Matt H. Evans: When a project is financed, we can either include
the cash flows associated with financing (principal and interest)
or we can exclude the financing cash flows and focus on only the
project related cash flows. Since the discount rate accounts for
the cost of financing, the preferred approach is to analyze only
project cash flows and ignore financing flows since they are
accounted for within the discount rate. If you decide to include
financing cash flows, then make sure you use a discount rate that
matches the cost of financing the project. ServiceOther
DepreciationTaxableLessNetAdd
BackWorkingCashYearRevenuesCostsCostsDeductionIncomeTaxesIncomeDepreciationCapitalFlow1535,800(112,000)(38,000)(325,000)60,800(16,720)44,080325,000(29,500)339,5802585,900(155,100)(46,500)(162,500)221,800(60,995)160,805162,500(33,100)290,2053612,600(188,600)(54,100)(81,250)288,650(79,379)209,27181,250(35,600)254,9214636,050(202,900)(63,200)(40,625)329,325(90,564)238,76140,625(37,900)241,4865644,112(224,200)(68,900)(40,625)310,387(85,356)225,03140,625(38,400)227,2566653,500(241,600)(72,110)339,790(93,442)246,348
(39,200)207,1487668,200(258,800)(77,800)331,600(91,190)240,410
(40,400)200,0108677,400(272,100)(83,100)322,200(88,605)233,595
(41,200)192,3959689,800(287,800)(88,900)313,100(86,103)226,998(41,900)185,09810705,300(298,400)(94,200)312,700(85,993)226,708(42,300)184,40811712,900(309,100)(97,800)306,000(84,150)221,850(42,800)179,05012719,600(319,400)(101,050)299,150(82,266)216,884(43,600)173,28413722,800(325,400)(104,900)292,500(80,438)212,063(44,100)167,96314729,100(329,900)(107,800)291,400(80,135)211,265(44,600)166,66515734,300(334,100)(110,100)290,100(79,778)210,323(45,100)165,223
Economic Analysis #1PresentYearCash FlowValuePayback0(1,215,000)(1,215,000)1339,580303,875(911,125)2290,205232,386(678,739)3254,921182,668(496,071)4241,486154,846(341,225)5227,256130,400(210,825)6207,148106,364(104,461)7200,01091,901(12,560)8192,39579,10766,547payback9185,09868,104134,65110184,40860,716195,36711179,05052,754248,12012173,28445,686293,80713167,96339,627333,43414166,66535,187368,62115165,22331,214399,835Net Present Value399,835
Required Rate of Return for Project =>11.75%Reinvestment Rate for Project =>4.50% Net Present Value$399,835 Modified IRR9.25%Discounted Payback (years)8.16
Cash Flow Analysis #2 - Include Financing Flows / Discount Rate
= Cost of Borrowing:
Matt H. Evans: The preferred approach to cash flow analysis for
projects with financing is to exclude financing flows and evaluate
only project related cash flows. This way, we can use the
appropriate discount rate adjusted for risk. This is how we did it
in Cash Flow Analysis #1. However, we can combine both project and
financing cash flows. Additionally, instead of adjusting cash flows
for interest expense, principal payments on the loan, and
depreciation, we will simply use "net" tax amounts to illustrate
cash flows for our project. We still come up with the same answer.
Example for Year 1 using gross amounts:
Revenues . . . . . $ 535,800Serv Costs . . . . (112,000)Other Costs . . . ( 38,000)Interest Exp . . . ( 45,000)Depreciation . . . (325,000)Taxable Income 15,800Less Taxes . . . . . ( 4,345)Net Income . . . . 11,455Depreciation 325,000Loan Principal ( 83,546)Working Capital ( 29,500)Cash Flow 223,409
NOTE: Don't forget to use only the financing cost rate as your
discount rate when combining project and financing cash flows in
your cash flow analysis. ServiceOtherTaxableLessNetTax BenefitTax
BenefitLoan
WorkingCashYearRevenuesCostsCostsIncomeTaxesIncomeDepreciation
Matt H. Evans: We could just deduct depreciation before tax and
then add it back to Net Income. Another approach is to simply add
back the "tax benefit" of depreciation. You can do it either
way!Interest
Matt H. Evans: Interest Expense is a tax deduction. We could have
simply deducted the entire interest amount in arriving at Taxable
Income. Instead, we added the tax benefit and then deducted the
entire loan payment.Payment
Matt H. Evans: Since we did not deduct Interest Expense in arriving
at Taxable Income, we show the entire financing cash outflow, but
we offset it with the "tax benefit" of interest expense in the
previous column. Capital
Matt H. Evans: Net Working Capital does not include interest
bearing items, such as Short Term Loan Payable since our discount
rate accounts for financing
costs.Flow1535,800(112,000)(38,000)385,800(106,095)279,70589,37512,375(128,546)(29,500)223,4092585,900(155,100)(46,500)384,300(105,683)278,61844,68810,307(128,546)(33,100)171,9663612,600(188,600)(54,100)369,900(101,723)268,17822,3448,053(128,546)(35,600)134,4284636,050(202,900)(63,200)369,950(101,736)268,21411,1725,597(128,546)(37,900)118,5365644,112(224,200)(68,900)351,012(96,528)254,48411,1722,919(128,546)(38,400)101,6286653,500(241,600)(72,110)339,790(93,442)246,348
(39,200)207,1487668,200(258,800)(77,800)331,600(91,190)240,410(40,400)200,0108677,400(272,100)(83,100)322,200(88,605)233,595(41,200)192,3959689,800(287,800)(88,900)313,100(86,103)226,998(41,900)185,09810705,300(298,400)(94,200)312,700(85,993)226,708(42,300)184,40811712,900(309,100)(97,800)306,000(84,150)221,850(42,800)179,05012719,600(319,400)(101,050)299,150(82,266)216,884(43,600)173,28413722,800(325,400)(104,900)292,500(80,438)212,063(44,100)167,96314729,100(329,900)(107,800)291,400(80,135)211,265(44,600)166,66515734,300(334,100)(110,100)290,100(79,778)210,323(45,100)165,223
Economic Analysis #2PresentYearCash
FlowValuePayback0(1,215,000)(1,215,000) 1223,409209,724(1,005,276)
2171,966151,544(853,731)3134,428111,208(742,523)4118,53692,054(650,469)5101,62874,089(576,380)6207,148141,766(434,614)7200,010128,496(306,118)8192,395116,033(190,085)9185,098104,794(85,291)10184,40898,00812,718payback11179,05089,332102,05012173,28481,159183,20913167,96373,849257,05814166,66568,790325,84815165,22364,017389,865Net
Present Value389,865After Tax Cost of Borrowing =>
6.53%Reinvestment Rate for Project =>2.50% Net Present
Value$389,865 Modified IRR6.38%Discounted Payback
(years)10.87Economic Assessment (based on Analysis #1)Project has
positive Net Present Value?YesProject has IRR in excess of
cost?NoProject has a positive payback?YesProject must meet at least
two of the three Economic Criteria, otherwise specialapproval is
required.Risk Analysis (based on analysis #1)Risk Premium Applied
to Project 2.25%Compare Risk Factor with Government Treasury Bond
(lowest risk) to Project Risk Factor:Risk Ranking = 1 for lowest
possible risk up to 10 for highest possible riskProbability of
Accurate and Reliable Information - Gov't T Bond
Matt H. Evans: There are usually very few unknowns concerning a
Government Treasury Bond; yields, payments, and other attributes
are usually very certain and thus, the probability of reliable
information is extremely high for such an investment.1.00(a)Risk
Ranking assigned to Gov't Treasury Bond ( 1 to 10)1(b)Exponential
power to apply to Risk Ranking is 2 - (a)1(c)Risk Factor = (b)
raised to the power (c)1Probability of Accurate and Reliable
Information for Project0.65Risk Ranking assigned to project (1 to
10)6 Exponential power to apply to Project1.35 Risk Factor for
Project 11Assign probabilities to three possible outcomes for
project:PPesimistic outlook, declining growth, slower volumes,
etc.10.00%NNormal expected outlook as applied in
analysis70.00%OOptomistic outlook, better than expected
growth20.00%Total should equal100.00%100.00%Enter Expected Cash
Flows for different outcomes:
StandardCoeff ofNet Cash FlowsExpectedDeviationVariationYearPesimistNormalOptomistValue(Abs Risk)(Rel Risk)1321,100339,580361,200342,05630,1060.0882271,600290,205311,950292,69430,2910.1033237,200254,921276,705257,50629,7620.1164224,850241,486261,890243,90327,9010.1145211,800227,256248,605229,98027,9510.1226190,450207,148227,690209,58628,0570.1347184,100200,010220,280202,47327,3250.1358176,350192,395211,650194,64226,5490.1369169,150185,098204,880187,45926,9350.14410168,340184,408203,090186,53726,0780.14011163,100179,050197,450181,13525,7630.14212158,350173,284192,770175,68826,0380.14813153,300167,963185,200169,94423,9580.14114152,820166,665183,990168,74623,5120.13915152,650165,223183,690167,65923,6710.141Totals2,935,1603,174,6893,471,0403,210,006403,8970.126 Absolute Risk of Project (Std Deviation)403,897Relative Risk of Project (Coeff of Variation)0.126
Revised Economic Analysis using Expected ValuesExpectedPresentRecoveryYearValuesValuePayback0(1,215,000)(1,215,000)1342,056306,090(908,910)2292,694234,379(674,531)3257,506184,520(490,011)4243,903156,396(333,614)5229,980131,963(201,651)6209,586107,616(94,035)7202,47393,032(1,002)8194,64280,03079,028payback9187,45968,973148,00110186,53761,417209,41811181,13553,368262,78612175,68846,320309,10613169,94440,095349,20114168,74635,626384,82715167,65931,675416,502Net Present Value416,502 Net Present Value$416,502 Modified IRR9.33%Discounted Payback (years)8.01
Project ECapital Budgeting Analysis forMedical Services USAECanadian PartnershipProject InformationProject Description >Expand Toronto Urban CentersProject Benefits >Market expansion, new source of revenues, leverage of assetsProject Location >TorontoResponsible Division >Canadian DivisionResponsible Department >MarketingContact Person Name >Allen J. HerbertEstimated Project Start Date >04/01/92Classification >8 Justification >CPriority >3 Preliminary ReviewAssign points from 0 to 5 for each of the following project attributes. 0 indicates that the attribute does not apply to the project. 5 is the highest rating, indicating that the project strongly meets this project attribute.Financial Attributes:F1Project improves overall profitability of the company3F2Project lowers cost structure2F3Project will generate a rate of return4F4Project improves asset utilization4F5Other Financial Attribute __________________________________0F6Other Financial Attribute __________________________________0
Operating Attributes:O1Improves operating efficiencies1O2Increases the customer base4O3Improves overall customer service4O4Improves competitive position of company3O5Other Operating Attribute _________________________________0O6Other Operating Attribute _________________________________0
Contingency Attributes:C1Project has options that allow for change during life0C2Project will positively impact company even if value is negative2C3Project can be abandoned easily with some positive value0C4Project permits several options to maximize value0C5Other Cont Attribute _____________________________________0
Miscellaneous Attributes:M1Expands Human Resource Capital0M2Enhances workforce productivity0M3Project meets a critical regulatory, security or specific need0M4Project fits with company strategy and goals3M5Probability of project success is very high / low risk2M6Other Misc Attribute _____________________________________0M7Other Misc Attribute _____________________________________0M8Other Misc Attribute _____________________________________0
Total Preliminary Points32
Projects with point totals less than 15 may represent poor investments and require additionalapproval before further analysis and processing. Projects with point totals between 15 and 20require caution and careful analysis. Projects with point totals greater than 20 may proceedwith analysis and submission.
Project Summary
In order to establish a toehold position in the Toronto area, a joint venture investment will be made since the current major provider in Toronto needs improved child care services for theurban areas of Toronto. Medical Services USA will provide personnel and overall managementfor urban child care. In return, Medical Services USA will share in the profits 50% / 50%. The JointVenture Agreement has a ten year term period.
Financial Analysis (all amounts are expressed in Canadian Dollars)Convert to U.S.$ * Initial Relocation / Setup Costs$750,0001.12$840,000 Ten Year Projected Income Statement Adj toEstimatedYearSalesCost ofIncomeLessNetCashCash50%Convert (100%)Servicebefore TaxTaxesIncomeFlowFlowShareto U.S.$ *1 **637,500270,000367,50079,500288,00042,000330,000165,0001.15189,7502895,000366,000529,000119,000410,00082,000492,000246,0001.18290,2803912,000377,000535,000101,000434,00055,000489,000244,5001.21295,8454942,000378,000564,000104,000460,00068,000528,000264,0001.20316,8005977,000370,000607,000112,000495,00088,000583,000291,5001.17341,05561,015,000368,000647,000129,000518,00090,000608,000304,0001.17355,68071,045,000362,000683,000140,000543,000110,000653,000326,5001.17382,00581,088,000355,000733,000138,000595,000115,000710,000355,0001.17415,35091,135,000350,000785,000151,000634,000122,000756,000378,0001.17442,260101,180,000348,000832,000157,000675,000135,000810,000405,0001.17473,850
* convert from Canadian Dollars to U.S. Dollars** partial year
in 1992Economic Analysis (U.S. Dollars) Summarize Cash Outflows and
Inflows for Project: CashPresent YearFlowsValuePayback
0(840,000)(840,000) 1189,750167,181(672,819)
2290,280225,333(447,486) 3295,845202,338(245,148)
4316,800190,898(54,250) 5341,055181,069126,819
6355,680166,374293,193
7382,005157,434450,6268415,350150,816601,4429442,260141,486742,92910473,850133,562876,491Net
Present Value876,491Required Rate of Return for Project
=>13.50%Reinvestment Rate for Project =>3.50%Net Present
Value $876,491 Modified IRR16.95%Discounted Payback
(years)5.30Economic AssessmentProject has positive Net Present
Value?YesProject has IRR in excess of cost?YesProject has a
positive payback?YesProject must meet at least two of the three
Economic Criteria, otherwise specialapproval is required.Risk
AnalysisRisk Premium Applied to Project 4.00%Compare Risk Factor
with Government Treasury Bond (lowest risk) to Project Risk
Factor:Risk Ranking = 1 for lowest possible risk up to 10 for
highest possible riskProbability of Accurate and Reliable
Information - Gov't T Bond
Matt H. Evans: There are usually very few unknowns concerning a
Government Treasury Bond; yields, payments, and other attributes
are usually very certain and thus, the probability of reliable
information is extremely high for such an investment.1.00(a)Risk
Ranking assigned to Gov't Treasury Bond ( 1 to 10)1(b)Exponential
power to apply to Risk Ranking is 2 - (a)1(c)Risk Factor = (b)
raised to the power (c)1Probability of Accurate and Reliable
Information for Project0.6Risk Ranking assigned to project (1 to
10)6 Exponential power to apply to Project1.4 Risk Factor for
Project 12Assign probabilities to three possible outcomes for
project:PPesimistic outlook, declining growth, slower volumes,
etc.25.00%NNormal expected outlook as applied in
analysis50.00%OOptomistic outlook, better than expected
growth25.00%Total should equal100.00%100.00%Enter Expected Cash
Flows for different outcomes:
StandardCoeff ofNet Cash FlowsExpectedDeviationVariationYearPesimistNormalOptomistValue(Abs Risk)(Rel Risk)1132,000189,750198,500177,50055,6850.3142227,300290,280311,100279,74066,7080.2383239,100295,845315,200286,49860,4210.2114244,050316,800340,500304,53876,8710.2525267,800341,055368,500329,60379,3040.2416285,200355,680387,500346,01579,1710.2297307,900382,005416,900372,20384,0060.2268329,100415,350460,900405,175100,3910.2489363,300442,260484,800433,15592,3520.21310380,050473,850517,100461,213105,8450.2292,775,8003,502,8753,801,0003,395,638800,7540.236Absolute Risk of Project (Std Deviation)800,754Relative Risk of Project (Coeff of Variation)0.236
Revised Economic Analysis using Expected ValuesExpectedPresentRecoveryYearValuesValuePayback0(840,000)(840,000)1177,500156,388(683,612)2279,740217,152(466,461)3286,498195,945(270,516)4304,538183,509(87,007)5329,603174,98987,9826346,015161,853249,8357372,203153,394403,2288405,175147,121550,3509433,155138,574688,92310461,213130,000818,923Net Present Value818,923Net Present Value$818,923 Modified IRR16.58%Discounted Payback (years)5.50
Project FCapital Budgeting Analysis forMedical Services USAFRegulatory Compliance NEProject InformationProject Description >Regulatory Compliance in NEProject Benefits >ComplianceProject Location >Northeast Regional Office - Boston, MAResponsible Division >FinanceResponsible Department >FinanceContact Person Name >Carl Jackson, V.P. FinanceEstimated Project Start Date >01/01/92Classification >9 Justification >EPriority >2
Preliminary ReviewAssign points from 0 to 5 for each of the following project attributes. 0 indicates that the attribute does not apply to the project. 5 is the highest rating, indicating that the project strongly meets this project attribute.Financial Attributes:F1Project improves overall profitability of the company2F2Project lowers cost structure3F3Project will generate a rate of return4F4Project improves asset utilization3F5Other Financial Attribute __________________________________0F6Other Financial Attribute __________________________________0
Operating Attributes:O1Improves operating efficiencies2O2Increases the customer base3O3Improves overall customer service3O4Improves competitive position of company2O5Other Operating Attribute _________________________________0O6Other Operating Attribute _________________________________0
Contingency Attributes:C1Project has options that allow for change during life3C2Project will positively impact company even if value is negative1C3Project can be abandoned easily with some positive value0C4Project permits several options to maximize value0C5Other Cont Attribute _____________________________________0
Miscellaneous Attributes:M1Expands Human Resource Capital0M2Enhances workforce productivity0M3Project meets a critical regulatory, security or specific need5M4Project fits with company strategy and goals2M5Probability of project success is very high / low risk1M6Other Misc Attribute _____________________________________0M7Other Misc Attribute _____________________________________0M8Other Misc Attribute _____________________________________0
Total Preliminary Points34
Projects with point totals less than 15 may represent poor investments and require additionalapproval before further analysis and processing. Projects with point totals between 15 and 20require caution and careful analysis. Projects with point totals greater than 20 may proceedwith analysis and submission.
Project Summary
A major regulatory change is expected to change certain services
in the Northeastern United States.In order to meet this new
mandate, an investment is required in field personnel, training,
andequipment. Revenues from the new services are also forecasted
based on demand in Californiawhich adopted this regulatory change
two years ago. The regulatory change is subject to
futuremodification and therefore, the project is only projected
over two years on a month to month basis.There is no initial
investment required for this project.Economic Analysis (Cash Flows
by Month) MonthlyPeriodSetupServiceMisc / TotalNet
CashPresentPresentDateRevenuesCostsCostsTaxesOutflowsFlowValueValue
(simple
calc)(functional)131-Jan-9235,200-16,000-3,500-2,500-22,00013,20013,12913,129228-Feb-9239,400-5,000-3,500-2,000-10,50028,90028,58928,590331-Mar-9241,000-3,500-3,500-2,000-9,00032,00031,48631,488430-Apr-9242,550-1,500-4,000-1,750-7,25035,30034,54534,551531-May-9243,990-1,500-4,000-1,750-7,25036,74035,76135,771630-Jun-9244,550-2,000-4,000-1,750-7,75036,80035,62635,642731-Jul-9245,100-4,500-1,650-6,15038,95037,50537,527831-Aug-9246,990-4,500-1,650-6,15040,84039,11339,144930-Sep-9247,800-4,500-1,650-6,15041,65039,67339,7141031-Oct-9248,650-5,100-1,500-6,60042,05039,83939,8891130-Nov-9249,280-5,100-1,500-6,60042,68040,21840,2801231-Dec-9248,300-5,100-1,500-6,60041,70039,08339,155
1992
Total532,810-102,0001331-Jan-9347,100-10,000-5,800-1,350-17,15029,95027,91927,9801428-Feb-9345,500-2,000-5,800-1,350-9,15036,35033,70233,7881531-Mar-9344,100-5,800-1,350-7,15036,95034,07434,1731630-Apr-9342,400-6,200-1,275-7,47534,92532,03332,1401731-May-9341,000-6,200-1,275-7,47533,52530,58330,6981830-Jun-9339,100-6,200-1,275-7,47531,62528,69528,8151931-Jul-9338,500-6,750-1,205-7,95530,54527,56527,6952031-Aug-9337,900-6,750-1,205-7,95529,94526,87827,0182130-Sep-9337,100-6,750-1,205-7,95529,14526,01926,1682231-Oct-9336,800-7,000-1,170-8,17028,63025,42225,5822330-Nov-9336,400-7,000-1,170-8,17028,23024,93225,1032431-Dec-9336,000-5,000-7,000-1,170-13,17022,83020,05420,204
1993 Total481,900-109,250Total1,014,710 -211,250 752,443754,244
AnnualMonthlyRequired Rate of Return for Project
=>6.50%0.54%Calculate IRR (annual basis):Net Present Value
752,443AnnualAnnualRate of Return (IRR Annual Basis)419%
JFI: Since we have monthly cash flows, we would use the XIRR
Function. However, Microsoft Excel does not accept an "array" for
input values for the XIRR Function; but the IRR Financial Function
doesl accept a "mix" or array of values. Since we have both
positive and negative cash flows for each period, we have a mix or
arrary of values and only the IRR Function will work. In order to
use the IRR function, we will summarize cash flows on an annual
basis. We could also use the Solver Function to solve for finding
the rate where the discounted inflows = discounted outflows.
NOTE: Negative values need to come first in the array or range
that Excel uses to calculate the IRR. OutflowInflowDiscounted
Payback Immediate0-102,000532,810-109,250481,900Economic
AssessmentProject has positive Net Present Value?YesProject has IRR
in excess of cost?YesProject has a positive payback?YesProject must
meet at least two of the three Economic Criteria, otherwise
specialapproval is required.Risk AnalysisRisk Premium Applied to
Project 0.00%(Required for Compliance)Compare Risk Factor with
Government Treasury Bond (lowest risk) to Project Risk Factor:Risk
Ranking = 1 for lowest possible risk up to 10 for highest possible
riskProbability of Accurate and Reliable Information - Gov't T
Bond
Matt H. Evans: There are usually very few unknowns concerning a
Government Treasury Bond; yields, payments, and other attributes
are usually very certain and thus, the probability of reliable
information is extremely high for such an investment.1.00(a)Risk
Ranking assigned to Gov't Treasury Bond ( 1 to 10)1(b)Exponential
power to apply to Risk Ranking is 2 - (a)1(c)Risk Factor = (b)
raised to the power (c)1Probability of Accurate and Reliable
Information for Project0.75Risk Ranking assigned to project (1 to
10)4 Exponential power to apply to Project1.25 Risk Factor for
Project 6Assign probabilities to three possible outcomes for
project:PPesimistic outlook, declining growth, slower volumes,
etc.15.00%NNormal expected outlook as applied in
analysis65.00%OOptomistic outlook, better than expected
growth20.00%Total should equal100.00%100.00%Enter Expected Cash
Flows for different outcomes:
StandardCoeff ofAdjustedAdjustedNet Cash FlowsExpectedDeviationVariationInflowsOutflowsMonthPesimistNormalOptomistValue(Abs Risk)(Rel Risk)112,05013,12913,70013,0811,2000.092226,20028,58929,90028,4932,6840.094328,83031,48632,92031,3742,9710.095431,39034,54536,05034,3733,4170.099532,71035,76137,43035,6373,4250.096632,60035,62637,25035,4973,3790.095734,17037,50539,25037,3543,6990.099835,87039,11340,90038,9843,6480.094936,27539,67341,47039,5233,7800.0961036,51039,83941,68039,7083,7480.0941136,81040,21842,05040,0733,8080.0951235,86039,08340,92038,9673,6600.094Annual Sub Total413,0631325,62027,91929,20027,8302,5940.0931430,85033,70235,24033,5823,1890.0951531,17034,07435,63033,9503,2420.0951629,35032,03333,51031,9263,0170.0951727,96030,58331,92030,4572,8890.0951826,30028,69530,01028,5992,6910.0941925,12027,56528,85027,4562,7150.0992024,47026,87828,14026,7692,6720.1002123,69026,01927,30025,9262,6190.1012223,15025,42226,70025,3372,5700.1012322,66024,93226,20024,8452,5650.1032418,23020,05421,10019,9902,0750.104Annual Sub Total336,665687,845752,443787,320749,72972,2590.096Absolute Risk of Project (Std Deviation)72,259Relative Risk of Project (Coeff of Variation)0.096
Revised Economic Analysis using Expected ValuesExpectedPresent DatesValuesValue 113,12913,058228,58928,282331,48630,979434,54533,807535,76134,808635,62634,490737,50536,113839,11337,458939,67337,7911039,83937,7441140,21837,8981239,08336,6291327,91926,0251433,70231,2471534,07431,4221632,03329,3811730,58327,9001828,69526,0361927,56524,8762026,87824,1262126,01923,2292225,42222,5732324,93222,0192420,05417,615Calculate IRR (annual basis):Net Present Value705,507AnnualAnnualNet Present Value $705,507OutflowInflowRate of Return (IRR Annual Basis)298.86%Discounted Payback Immediate0-102,000413,063-109,250336,665
SummaryCapital Budgeting Analysis forMedical Services USA9.50% Solver. We will solve for a Target Cell, asking Solver to find the maximum or minimum values by changing a set of variables (cells) given a set of constraints.
Financial Modeling Textbooks provide useful examples of how
Excel Solver can be used to solve for capital budgeting program
decisions given a set of constraints. The following example will
illustrate how we could apply Solver for finding the right set of
projects given a set of contraints:Example:Objective: Maximize Net
Present Value of Projects Contraints:Year 1: Only $ 200,000 can be
spent on all capital projects Year 2: Only $ 150,000 can be spent
on all capital projectsYear 3: Only $ 120,000 can be spent on all
capital projectsYear 4: Only $ 100,000 can be spent on all capital
projectsYear 5: Only $ 75,000 can be spent on all capital
projectsFive Projects require investments over five years and have
the following Net Present Values:Select?Project0 = No< - - - - -
Five Year Capital Budgets for Each Project - - - - - >Ref1 =
YesProject NameNPVYear 1Year 2Year 3Year 4Year 5 A1
JFI: Solver will change these values since these are the
"variables" in our problem. Solver will also produce a report -
Answer Report 1.Annual Marketing
Program650,00045,00040,00038,00035,00035,000B0IT Infrastructure
Development820,00055,00060,00060,00058,00055,000C1Executive
Leadership540,00025,00020,00020,00018,00017,000D1HR Capital
Improvement701,00035,00030,00030,00028,00027,000E0Product
Research490,00050,00045,00042,00040,00040,000 Total
(SumProduct)1,806,385
JFI: This is the "set" cell we will use with Solver.99,051
JFI: Constraints used with Solver start with this cell. We need to
make sure we compare an equal set of arrays; I.e. compare the
arrary or range E43:I43 against the range E44:I44.
85,28283,67277,15475,000Maximum Allowed
Budget200,000150,000120,000100,00075,000We will enter the following
constraints into Solver:$ 45,000 A + $ 55,000 B + $ 25,000 C + $
35,000 D + $ 50,000 E .LE. $ 200,000LE: Less than or Equal to$
40,000 A + $ 60,000 B + $ 20,000 C + $ 30,000 D + $ 45,000 E .LE. $
150,000$ 38,000 A + $ 60,000 B + $ 20,000 C + $ 30,000 D + $ 42,000
E .LE. $ 120,000$ 35,000 A + $ 58,000 B + $ 18,000 C + $ 28,000 D +
$ 40,000 E .LE. $ 100,000$ 35,000 A + $ 55,000 B + $ 17,000 C + $
27,000 D + $ 40,000 E .LE. $ 75,000Each of the above constraints
recognizes that we can spend no more than what is budgeted each
year. We alsohave the equation we are trying to solve for: Maximize
NPV = $ 650,000 A + $ 820,000 B + $ 540,000 C + $ 701,000 D + $
490,000 EWe will also use as our variables "0" for No and "1" for
Yes as to which projects we should select given the
aboveconstraints and equation. The "maximum" NPV will show up in
our "set" cell which is cell D43.Now go to the main toolbar, select
Tools -> Solver and enter the following:1. Target Cell is D432.
Equal to: Select the Max button since we are solving for maximum
values.3. By Changing Cells: Select the range B38:B42 as our
variables.4. Subject to Constraints: Add two contraints as
follows:B38:B42 .EQ. Binary
JFI: Constraints in Solver consists of three components:
1. Cell Reference (such as $B$38:$B$42)2. Operator (such as bin for binary)3. Constraint (default is binary when bin is operator)EQ or = (equal)E43:I43 .LE. E44:I44LE or