Capital Budgeting

41

Transcript of Capital Budgeting

Page 1: Capital Budgeting
Page 2: Capital Budgeting

Meaning

Capital Budgeting is the process of identifying, analyzing, and selecting investment projects whose returns (cash flows) are expected to extend beyond one year.

Page 3: Capital Budgeting

Specifically, CB involves:• Generating investment project proposals

consistent with the firm’s strategic objectives;

• Estimating after-tax incremental operating cash flows for the investment projects;

• Evaluating project incremental cash flows;• Selecting projects based on a value-

maximizing acceptance criterion; and• Continually reevaluating implemented

investment projects.

Page 4: Capital Budgeting

• Since CASH is central to all decisions of the firm, the expected benefits to be received from the project is expressed in terms of Cash Flows and not income flows.

• Cash flows should be measured on an incremental, after-tax basis. In addition, the stress is on operating, not financing flows.

• It is helpful to place project CFs into 3 categories based on timing: (1) the initial CF, (2) interim incremental net CFs, and (3) the terminal-year incremental net CF.

Page 5: Capital Budgeting

Capital Budgeting: The process of planning for purchases of long-term assets.

• Example: Suppose our firm must decide whether to

purchase a new plastic molding machine for $125,000. How do we decide?

• Will the machine be profitable?• Will our firm earn a high rate of return

on the investment?

Page 6: Capital Budgeting

Decision-making Criteria in Capital Budgeting

How do we decide if a capital investment

project should be accepted or

rejected?

Page 7: Capital Budgeting

• The Ideal Evaluation Method should:

a) include all cash flows that occur during the life of the project,

b) consider the time value of money,c) incorporate the required rate of

return on the project.

Decision-making Criteria in Capital Budgeting

Page 8: Capital Budgeting

Payback Period

• How long will it take for the project to generate enough cash to pay for itself?

Page 9: Capital Budgeting

Payback Period

• How long will it take for the project to generate enough cash to pay for itself?

0 1 2 3 4 5 86 7

(500) 150 150 150 150 150 150 150 150

Page 10: Capital Budgeting

Payback Period

• How long will it take for the project to generate enough cash to pay for itself?

0 1 2 3 4 5 86 7

(500) 150 150 150 150 150 150 150 150

Payback period = 3.33 years.

Page 11: Capital Budgeting

• Is a 3.33 year payback period good?• Is it acceptable?• Firms that use this method will compare

the payback calculation to some standard (maximum acceptable PB period) set by the firm.

• If our senior management had set a cut-off of 5 years for projects like ours, what would be our decision?

• Accept the project.

Payback Period (Acceptance Criterion)

Page 12: Capital Budgeting

Drawbacks of Payback Period

• Firm cutoffs are subjective.• Does not consider time value of

money.• Does not consider any required

rate of return.• Does not consider all of the

project’s cash flows.

Page 13: Capital Budgeting

Drawbacks of Payback Period

• Does not consider all of the project’s cash flows.

• Consider this cash flow stream!

0 1 2 3 4 5 86 7

(500) 150 150 150 150 150 (300) 0 0

Page 14: Capital Budgeting

Drawbacks of Payback Period

• Does not consider all of the project’s cash flows.

• This project is clearly unprofitable, but we would accept it based on a 4-year payback criterion!

0 1 2 3 4 5 86 7

(500) 150 150 150 150 150 (300) 0 0

Page 15: Capital Budgeting

Other Methods

1) Net Present Value (NPV)2) Profitability Index (PI)3) Internal Rate of Return (IRR)

Each of these decision-making criteria:• Examines all net cash flows,• Considers the time value of money, and• Considers the required rate of return.

Page 16: Capital Budgeting

Net Present Value

NPV = the total PV of the annual net cash flows - the initial outlay (or cash outflows).

NPVNPV = - ICO = - ICO CFCFtt(1 + k)(1 + k) tt

nn

t=1t=1

Page 17: Capital Budgeting

Net Present Value

Decision Rule:

If NPV is positive, accept. If NPV is negative, reject.

Page 18: Capital Budgeting

NPV ExampleNPV Example

• Suppose we are considering a capital investment that costs $250,000 and provides annual net cash flows of $100,000 for five years. The firm’s required rate of return is 15%.

Page 19: Capital Budgeting

NPV ExampleNPV Example

0 1 2 3 4 5

(250,000) 100,000 100,000 100,000 100,000 100,000

• Suppose we are considering a capital investment that costs $250,000 and provides annual net cash flows of $100,000 for five years. The firm’s required rate of return is 15%.

Page 20: Capital Budgeting

Net Present Value (NPV)

NPV is just the PV of the annual cash flows minus the initial outflow.

PV of cash flows = $335,216 - Initial outflow: ($250,000) = Net PV $85,216

Page 21: Capital Budgeting

Profitability Index

Page 22: Capital Budgeting

Profitability Index

NPV = - ICO CFt(1 + k) t

n

t=1

Page 23: Capital Budgeting

Profitability Index

PI = ICO CFt(1 + k)

n

t=1 t

NPV = - ICO CFt(1 + k) t

n

t=1

Page 24: Capital Budgeting

Decision Rule:

If PI is greater than or equal to 1, accept.

If PI is less than 1, reject.

Profitability Index

Page 25: Capital Budgeting

PI Example

We know that from the previous example PV of cash flows is $335,216 and the Initial cash outflow is $250,000.

Therefore, PI = 335,216 / 250,000 = 1.34 You should accept as PI = 1.34, which is more

than 1.

Page 26: Capital Budgeting

Internal Rate of Return (IRR)

• IRR: The return on the firm’s invested capital. IRR is simply the rate of return that the firm earns on its capital budgeting projects.

Page 27: Capital Budgeting

Internal Rate of Return (IRR)

Page 28: Capital Budgeting

Internal Rate of Return (IRR)

NPV = - ICO CFt(1 + k) t

n

t=1

Page 29: Capital Budgeting

Internal Rate of Return (IRR)

NPV = - ICO CFt(1 + k) t

n

t=1

n

t=1IRR: = ICO CFt

(1 + IRR) t

Page 30: Capital Budgeting

Internal Rate of Return (IRR)

• IRR is the rate of return that makes the PV of the cash flows equal to the initial outlay.

• This looks very similar to our Yield to Maturity formula for bonds. In fact, YTM is the IRR of a bond.

n

t=1IRR: = ICO CFt

(1 + IRR) t

Page 31: Capital Budgeting

Calculating IRR

• Looking again at our problem:• The IRR is the discount rate that

makes the PV of the projected cash flows equal to the initial outlay.

0 1 2 3 4 5

(250,000) 100,000 100,000 100,000 100,000 100,000

Page 32: Capital Budgeting

IRR Decision Rule

• If IRR is greater than or equal to the required rate of return, accept.

The acceptance criterion related to the IRR method is to compare it to the required r.o.r., known as the cutoff or hurdle rate. Hurdle rate is the rate at which a project is acceptable.

If IRR is less than the required rate of return, reject.

Page 33: Capital Budgeting

• IRR is a good decision-making tool as long as cash flows are conventional. (- + + + + +)

• Problem: If there are multiple sign changes in the cash flow stream, we could get multiple IRRs. (- + + - + +)

Page 34: Capital Budgeting

• IRR is a good decision-making tool as long as cash flows are conventional. (- + + + + +)

• Problem: If there are multiple sign changes in the cash flow stream, we could get multiple IRRs. (- + + - + +)

0 1 2 3 4 5

(500) 200 100 (200) 400 300

Page 35: Capital Budgeting

• IRR is a good decision-making tool as long as cash flows are conventional. (- + + + + +)

• Problem: If there are multiple sign changes in the cash flow stream, we could get multiple IRRs. (- + + - + +)

0 1 2 3 4 5

(500) 200 100 (200) 400 300

1 1

Page 36: Capital Budgeting

• IRR is a good decision-making tool as long as cash flows are conventional. (- + + + + +)

• Problem: If there are multiple sign changes in the cash flow stream, we could get multiple IRRs. (- + + - + +)

0 1 2 3 4 5

(500) 200 100 (200) 400 300

1 2

Page 37: Capital Budgeting

• IRR is a good decision-making tool as long as cash flows are conventional. (- + + + + +)

• Problem: If there are multiple sign changes in the cash flow stream, we could get multiple IRRs. (- + + - + +)

0 1 2 3 4 5

(500) 200 100 (200) 400 300

1 2 3

Page 38: Capital Budgeting

Summary Problem

• Enter the cash flows only once.• Find the IRR.• Using a discount rate of 15%, find NPV.• Add back IO and divide by IO to get PI.

0 1 2 3 4 5

(900) 300 400 400 500 600

Page 39: Capital Budgeting

Summary Problem

• IRR = 34.37%.• Using a discount rate of 15%, NPV = $510.52.• PI = 1.57.

0 1 2 3 4 5

(900) 300 400 400 500 600

Page 40: Capital Budgeting

Capital Rationing

• A final potential difficulty related to implementing the alternative methods of project evaluation and selection.

• Refers to a situation where a constraint (or budget ceiling) is placed on the total size of capital expenditures during a particular period.

• Constraints come when there is a policy of financing all capital expenditures.

Page 41: Capital Budgeting

• CR also occurs when a division of a large company is allowed to make capital expenditure only upto a specified budget ceiling, over which the division usually has no control.

• With such a constraint, the firm attempts to select the combination of investment proposals that will provide the greatest increase in the value of the firm subject to not exceeding the budget ceiling constraint.