Cape and Vineyard Electric Cooperative

June 13, 2012

Joe Soares, Cape Light Compact Senior Power Supply Planner

Rebecca Zachas, BCK LawLiz Argo, Consultant, Argo Consulting

DG Interconnection Experiences from CVEC’s PV Initiative Round 1

Page 2: Cape and Vineyard Electric Cooperative

Background on CVEC

The Cape & Vineyard Electric Cooperative, Inc. (CVEC) was formed out of a strategic planning process commissioned and undertaken by the Cape Light Compact (CLC)

Neither CLC, nor its member towns, could develop electric generation projects and enter into long-term power purchase and other agreements

Desire to stabilize electric rates for all ratepayers with renewable energy projects

Develop renewable energy projects

Public policy

Currently twenty members

Page 3: Cape and Vineyard Electric Cooperative

CVEC PV Initiatives- ROUNDS 1 & 2

Two RFP Processes for Municipal projects through the Cooperative: Fall of 2010 Fall of 2011

American Capital Energy selected for Round 1 in April 2011 ~ 14MW

Broadway Electric selected for Round 2 in April 2012 ~ 25MW

Round 1: 8 projects ranging from .627 – 4.6MW (Average 2.03MW) Hard copy applications & fee in to NStar from 9/15/11 to

11/17/11

Page 4: Cape and Vineyard Electric Cooperative

CVEC PV Initiatives - ROUND 1

Page 5: Cape and Vineyard Electric Cooperative

Timeframe chart from Tariff with steps added