Capacity Management 2

download Capacity Management 2

of 34

Transcript of Capacity Management 2

  • 8/18/2019 Capacity Management 2

    1/34

    Capacity Management

  • 8/18/2019 Capacity Management 2

    2/34

    11/12/2015 Capacities Management 2

    Definisi

    The “throughput,” or number of units a facility canhold, receive, store, or produce in a period of time.

    Output, atau jumlah unit yang dapat

    dihasilkan/disimpan/diterima oleh suatu fasilitas.

  • 8/18/2019 Capacity Management 2

    3/34

    11/12/2015 Capacities Management 3

     An Overview of

    Capacities

    Management inManufacture

    Facility

    PRODUCTIONPLANNING

    PRODUCTION

    ACTIVITY

    CONTROL

    MATERIAL

    REQUIREMENT

    PLANNING

    MASTER

    PRODUCTION

    SCHEDULE

    Resource

    RequirementsPlanning

    Operation

    Sequencing

    Input/Output

    Control

    Capacity

    Requirement

    Planning

    Rough Cut

    Capacity

    Planning

    CAPACITY

    MANAGEMENT

    TECHNIQUES

    Long Range

    Short Range

    Medium Range

  • 8/18/2019 Capacity Management 2

    4/34

    11/12/2015 Capacities Management 4

    Design and Effective Capacity

    Design

    capacity: 

    The theoretical maximum output of a

    system in a given period.

    Utilization:   Actual output / Design capacity.

    Effectivecapacity: Capacity a firm can expect to achieve givenits product mix, methods of scheduling,maintenance, and standards of quality.

    Efficiency:  Actual output / Effective capacity.

  • 8/18/2019 Capacity Management 2

    5/34

    11/12/2015 Capacities Management 5

    Lamp Assemble

    Oven

    Base Forming

    Plastic Molding

    Socket Assemble

    Teknik RCCP akan digunakan untuk me-verifikasi

    MPS dengan ketersediaan resource yaitu kapasitas

    workstation. Workstation yang digunakan untukmembuat Lamp LAXX yaitu :

  • 8/18/2019 Capacity Management 2

    6/34

    11/12/2015 Capacities Management 6

    Rough Cut Capacity Planning

    Lamps

    LAXX

    Shades  Socket

     Assembly

    Base

     Assembly

    15W14 B 15C8"7" One-Way Three-Way

    Contoh : Akan dibuat lampu dengan struktur produk sebagai berikut :

  • 8/18/2019 Capacity Management 2

    7/34

    11/12/2015 Capacities Management 7

     Available Capacities vs Required Capacities

     Available Capacities = Available Time x Utilization x Efficiency

     Available Time = M x S x H x W

    M : Jumlah Mesin

    S : Jumlah Shift per Hari

    H : Jumlah Jam per Shift

    W : Jumlah hari kerja per bulan

    Keputusan dalam RCCP

  • 8/18/2019 Capacity Management 2

    8/34

    11/12/2015 Capacities Management 8

    MPS untuk Lamp LAXX

    Bulan  Forecast  Produksi

    Reguler  

    Produksi

    Overtime 

    Total

    Produksi 

    Inventory

    Tersedia 

    15000 

    Januari  22000  15000  0  15000  8000 

    Februari  8000  15000  0  15000  15000 

    Maret  10000  15000  0  15000  20000 

    April  10000  15000  0  15000  25000 

    Mei  20000  15000  0  15000  20000 

    Juni  14000  15000  0  15000  21000 

    Juli  8000  15000  0  15000  28000 

    Agustus  8000  15000  1000  16000  36000 September   12000  15000  4000  19000  43000 

    Oktober   15000  15000  4000  19000  47000 

    Nopember   30000  15000  4000  19000  36000 

    Desember   40000  15000  4000  19000  15000 

    197000  180000  17000  197000 

  • 8/18/2019 Capacity Management 2

    9/34

    11/12/2015 Capacities Management 9

    Data Waktu Baku

    Work Station  Waktu Baku (jam) 

    Lamp Assembly  0,1 

    Oven  0,01 

    Base Forming  0,05 

    Plastic Molding  0,02 

    Socket Assembly  0,04 

    0,22 

  • 8/18/2019 Capacity Management 2

    10/34

    11/12/2015 Capacities Management 10

     Available Capacities

    Sebagai contoh untuk Workstation Plastic Moldingterdapat 3 mesin dengan utilitas 0,756 dan efisiensi1,05.

    Dalam 1 bulan terdapat 21 hari kerja dengan 1 shift

    per harinya selama 8 jam.

     Available Time = 3x1x8x21 = 504 jam/bulan

     Available Capacities = 504x0,756x1,05=400 jam

  • 8/18/2019 Capacity Management 2

    11/34

    11/12/2015 Capacities Management 11

    RCCP … 

    Work Station 

    Bulan  Lamp Assembly  Oven  Base

    Forming 

    Plastic

    Molding 

    Socket

    Assembly 

    Januari  1500  150  750  300  600 

    Februari  1500  150  750  300  600 

    Maret  1500  150  750  300  600 

    April  1500  150  750  300  600 

    Mei  1500  150  750  300  600 

    Juni  1500  150  750  300  600 

    Juli  1500  150  750  300  600 

    Agustus  1600  160  800  320  640 

    September   1900  190  950  380  760 

    Oktober   1900  190  950  380  760 

    Nopember   1900  190  950  380  760 

    Desember   1900  190  950  380  760 

    Total 19700  1970  9850  3940  7880 

  • 8/18/2019 Capacity Management 2

    12/34

    11/12/2015 Capacities Management 12

    Plastic Molding Load Report

    0

    50

    100

    150

    200

    250

    300

    350

    400450

      J  a  n  u  a  r   i

      F  e   b  r  u  a  r   i

       M  a  r  e  t

      A  p

      r   i   l

       M  e   i

      J  u

      n   i

      J  u   l   i

      A  g   u  s  t

      u  s

      S  e  p  t  e  m   b

      e  r

      O   k  t  o   b  e  r

       N  o  p  e  m   b

      e  r

      D  e  s  e  m   b

      e  r

    Bulan

         J    a    m

         /     B    u     l    a    n

    Required Capacities

     Available Capacities

  • 8/18/2019 Capacity Management 2

    13/34

    11/12/2015 Capacities Management 13

    Capacity Requirement Planning

    PRODUCTION

    PLANNING

    PRODUCTION

    ACTIVITY

    CONTROL

    MATERIAL

    REQUIREMENT

    PLANNING

    MASTER

    PRODUCTION

    SCHEDULE

    Resource

    Requirements

    Planning

    Operation

    Sequencing

    Input/Output

    Control

    Capacity

    Requirement

    Planning

    Rough Cut

    Capacity

    Planning

    CAPACITY

    MANAGEMENT

    TECHNIQUES

    Long Range

    Short Range

    Medium Range

    Dipergunakan untukmemeriksa apakahrencana MRP dapat

    dilakukan dengankapasitas yang tersediaatau tidak

    Pada prinsipnya sama

    dengan RCCP, tetapiyang diuji bukan MPSmelainkan MRP atauPlanned Order Release

  • 8/18/2019 Capacity Management 2

    14/34

    11/12/2015 Capacities Management 14

    CRP … 

    INPUT

    OUTPUT

    Planned Order Released

    Routing Sheet

    Work Station / Machined Data

    Work station / Machine Load Report

  • 8/18/2019 Capacity Management 2

    15/34

    11/12/2015 Capacities Management 15

    Contoh :

    Level Part Qty/Parent Description

    0-- 100 1 Finished Widget

    -1- 110 2 Subassembly

    --2 121 6 Component A--2 122 10 Component B

    Misalkan diketahui produk dengan struktur seperti

    berikut :

  • 8/18/2019 Capacity Management 2

    16/34

    11/12/2015 Capacities Management 16

    Contoh … 

    Week  1  2  3  4  5  6  7 

    Quantity  250 200 250 150 200 300 150

     Adapun MPS untuk Finished Widget untuk periode 7 minggu

    ke depan yaitu :

    Data-data lain untuk masing-masing part yaitu :Part Lot

    Size

    Lead

    Time

    On Order Scheduled

    Receipt

    On-Hand

    Stock

    100 LFL 1 week 250 Week #1 0

    110 400 2 week 400 Week #2 500

    121 2400 2 week 2400 Week #2 1500

    122 6000 2 week 6000 Week #2 2500

  • 8/18/2019 Capacity Management 2

    17/34

    11/12/2015 Capacities Management 17

    Item : 100 

    Lot Size :

    LFL 

    LLC : 0  Lead Time : 1 week 

    Period 

    PD  1  2  3  4  5  6  7 

    Gross Requirements  250  200  250  150  200  300  150 

    Scheduled Receipt  250 

    Projected On Hand  0  0  0  0  0  0  0  0 

    Net Requirements  0  200  250  150  200  300 

    Planned Order Receipts  0  200  250  150  200  300 

    Planned Order Releases  200  250  150  200  300  150 

  • 8/18/2019 Capacity Management 2

    18/34

    11/12/2015 Capacities Management 18

    Item : 110 

    Lot Size :

    400 

    LLC : 1  Lead Time : 2 week 

    Period 

    PD  1  2  3  4  5  6  7 

    Gross Requirements  400  500  300  400  600  300 

    Scheduled Receipt  400 

    Projected On Hand  500  100  0  100  100  300  0 

    Net Requirements  0  0  300  300  500  0 

    Planned Order Receipts  400  400  800 

    Planned Order Releases  0  400  400  800  0  800  0  0 

  • 8/18/2019 Capacity Management 2

    19/34

    11/12/2015 Capacities Management 19

    Item : 121  Lot Size : 2400 

    LLC : 2  Lead Time : 2week 

    Period 

    PD  1  2  3  4  5  6  7 

    Gross Requirements  1200  1200  2400  0  2400  0  0 

    Scheduled Receipt  2400 

    Projected On Hand  1500  300  1500  1500  1500  1500  1500  1500 

    Net Requirements  0  0  900  0  900  0  0 

    Planned Order Receipts  2400  2400 Planned Order Releases  0  2400  0  2400  0  0  0  0 

  • 8/18/2019 Capacity Management 2

    20/34

    11/12/2015 Capacities Management 20

    Item : 122  Lot Size : 6000 

    LLC : 2  Lead Time : 2week 

    Period 

    PD  1  2  3  4  5  6  7 

    Gross Requirements  2000  2000  4000  0  4000  0  0 

    Scheduled Receipt  6000 

    Projected On Hand  2500  500  4500  500  500  2500 

    Net Requirements  0  0  0  0  3500  0  0 

    Planned Order Receipts  6000 Planned Order Releases  0  0  0  6000  0  0  0  0 

  • 8/18/2019 Capacity Management 2

    21/34

    11/12/2015 Capacities Management 21

    Summary PORel

    Period 

    PD  1  2  3  4  5  6  7 

    Item : 100 

    Gross Requirements 250 200 250 150 200 300 150

    Planned Order Releases 200 250 150 200 300 150

    Item : 110 

    Planned Order Releases 0 400 400 800 0 800 0 0

    Item : 121 

    Planned Order Releases 0 2400 0 2400 0 0 0 0

    Item : 122 

    Planned Order Releases 0 0 0 6000 0 0 0 0

  • 8/18/2019 Capacity Management 2

    22/34

    11/12/2015 Capacities Management 22

    Data Waktu Setup dan Waktu Proses

    Part  Work Station  Setup Time/Lot (minutes)  Run Time/Piece (minutes) 

    100  1  30  2,50 

    110 2  10  0,75 

    1  15  0,50 

    121 

    3  15  0,30 

    1  25  0,25 

    2  15  0,25 

    122 

    2  25  0,75 

    3  30  0,15 

    1  75  0,50 

    3  30  0,75 

  • 8/18/2019 Capacity Management 2

    23/34

    11/12/2015 Capacities Management 23

    Perhitungan Kebutuhan KapasitasSETUP 

    Work Station  Part 

    Period 

    1  2  3  4  5  6  7 

    Work Station

    1

    100 30 30 30 30 30 30 30

    110 15 15 30 0 30 0 0

    121 25 0 25 0 0 0 0

    122 0 0 75 0 0 0 0

    TOTAL  70  45  160  30  60  30  30 

    Work Station

    2

    100 0 1 2 3 4 5 6

    110 10 10 20 0 20 0 0

    121 15 0 15 0 0 0 0

    122 0 0 25 0 0 0 0

    TOTAL  25  11  62  3  24  5  6 

    Work Station

    3

    100 0 0 0 0 0 0 0

    110 0 0 0 0 0 0 0

    121 15 0 15 0 0 0 0

    122 0 0 60 0 0 0 0

    TOTAL  15  0  75  0  0  0  0 

  • 8/18/2019 Capacity Management 2

    24/34

    11/12/2015 Capacities Management 24

    Perhitungan Kebutuhan Kapasitas (2)RUN 

    Work Station  Part 

    Period 

    1  2  3  4  5  6  7 

    Work Station 1

    100 625 500 625 375 500 750 375

    110 200 200 400 0 400 0 0

    121 600 0 600 0 0 0 0

    122 0 0 3000 0 0 0 0

    TOTAL  1425  700  4625  375  900  750  375 

    Work Station 2

    100 0 0 0 0 0 0 0

    110 300 300 600 0 600 0 0

    121 600 0 600 0 0 0 0

    122 0 0 4500 0 0 0 0

    TOTAL  900  300  5700  0  600  0  0 

    Work Station 3

    100 0 0 0 0 0 0 0

    110 0 0 0 0 0 0 0

    121 720 0 720 0 0 0 0

    122 0 0 5400 0 0 0 0

    TOTAL  720  0  6120  0  0  0  0 

  • 8/18/2019 Capacity Management 2

    25/34

    11/12/2015 Capacities Management 25

    Perhitungan Kebutuhan Kapasitas (3)

    Required Capacities 

    Work Station Period 

    1  2  3  4  5  6  7 

    1 1495 745 4785 405 960 780 405

    2 925 311 5762 3 624 5 6

    3 735 0 6195 0 0 0 0

    Available Capacities 

    Work

    Station 

    Available Time

    (Minutes) Utilization (%)  Efficiency (%) 

    Available

    Capacities 

    1 2400 100% 100% 2400

    2 2400 100% 100% 2400

    3 2400 100% 100% 2400

  • 8/18/2019 Capacity Management 2

    26/34

    11/12/2015 Capacities Management 26

    Work Station Load Report

    0

    1000

    2000

    3000

    4000

    5000

    6000

    7000

    1 2 3 4 5 6 7

    Period

         M     i    n    u     t    e    s

    WS1

    WS2

    WS3

    available Capacities

  • 8/18/2019 Capacity Management 2

    27/34

    11/12/2015 Capacities Management 27

     Available Capacities vs Required Capacities

    Over Time (Extra shift)

    Menambah personnel, mesin,peralatan dll.

    Subcontracting

    Mengubah MPS (jika RCCP ataupun CRP

    tidak valid) dan MRP (jika CRP tidak valid)

  • 8/18/2019 Capacity Management 2

    28/34

    11/12/2015 Capacities Management 28

    Input/Output Control Teknik yang efektif untuk

    mengendalikan antrianpekerjaan di depan mesindan mengendalikan leadtime manufaktur.

    Meliputi :

    PRODUCTION

    PLANNING

    PRODUCTION

    ACTIVITY

    CONTROL

    MATERIAL

    REQUIREMENT

    PLANNING

    MASTER

    PRODUCTION

    SCHEDULE

    Resource

    Requirements

    Planning

    Operation

    Sequencing

    Input/Output

    Control

    Capacity

    Requirement

    Planning

    Rough Cut

    Capacity

    Planning

    CAPACITY

    MANAGEMENT

    TECHNIQUES

    Long Range

    Short Range

    Medium Range

    Merencanakan besar input danoutput per periode waktutertentu pada setiap work station

    Mengukur dan melaporkan input

    dan output aktual Memperbaiki atau merevisi

    situasi yang diluar batas kendaliyang telah ditetapkan

  • 8/18/2019 Capacity Management 2

    29/34

    11/12/2015 Capacities Management 29

    I/O pada Work Station Tunggal

    I/O dilakukan untuk mengendalikan kegiatan hari per hari

    Konsep dasar dari I/O pada work station tunggal adalah besar

    antrian pada akhir proses sama dengan besar antrian pada awal

    proses ditambah input dikurangi output I/O harus seimbang jika diinginkan jumlah antrian yang sama

     Antrian

    ProsesINPUT  OUTPUT

  • 8/18/2019 Capacity Management 2

    30/34

    11/12/2015 Capacities Management 30

    I/O pada Work Station Tunggal (2)

    i : Periode waktu

    PI : Planned Input

     AI : Actual Input

    PO : Planned Output

     AO : Actual Output ICD : Input Cumulative Deviation

    OCD : Output Cumulative Deviation

    PWIP : Planned Work-In-Process

     AWIP : Actual Work-In-Process

    ICDi = ICDi-1-PIi+AIi

    OCDi = OCDi-1-PO+AOi PWIPi= PWIPi-1+PIi-Poi  AWIPi= AWIPi-1+AIi-Aoi Lead Time =

    (WIP) / Output

    Perhitungan I/O dapat dijelaskan sebagai berikut :

  • 8/18/2019 Capacity Management 2

    31/34

    11/12/2015 Capacities Management 31

    Ilustrasi 1 : Kondisi TerkendaliDAY 

    25  26  27  28  29  30 

    INPUT 

    Planned Input (PI) 16 16 16 16 16

     Actual Input (AI) 12 19 22 10 15

    Input Deviation -4 3 6 -6 -1

    Input Cumulative Deviation (ICD) 0 -4 -1 5 -1 -2

    OUTPUT 

    Planned Output (PO) 16 16 16 16 16

     Actual Output (AO) 17 15 17 18 15

    Output Deviation 1 -1 1 2 -1

    Output Cumulative Deviation (OCD) 0 1 0 1 3 2

    WIP (ending) 

    Planned WIP 32 32 32 32 32

     Actual WIP 32 27 31 36 28 28

    WIP Deviation 15,63% 3,13% 12,50% 12,50% 12,50%

  • 8/18/2019 Capacity Management 2

    32/34

    11/12/2015 Capacities Management 32

    Ilustrasi 1 : Kondisi Terkendali

     Actual Input dan Actual Output tidak terlalu

    bervariasi dibandingkan Planned Input dan

    Planned Output

     Actual WIP tidak bervariasi melebihi 5 jamdibandingkan Planned WIP

  • 8/18/2019 Capacity Management 2

    33/34

    11/12/2015 Capacities Management 33

    Ilustrasi 2 : Mereduksi WIPDAY 

    25  26  27  28  29  30 

    INPUT 

    Planned Input (PI) 14 14 14 13 13

     Actual Input (AI) 12 17 16 9 14

    Input Deviation -2 3 2 -4 1

    Input Cumulative Deviation (ICD) 0 -2 1 3 -1 0

    OUTPUT 

    Planned Output (PO) 16 16 16 16 16

     Actual Output (AO) 17 15 15 14 18

    Output Deviation 1 -1 -1 -2 2

    Output Cumulative Deviation (OCD) 0 1 0 -1 -3 -1

    WIP (ending) 

    Planned WIP 30 28 26 23 20

     Actual WIP 32 27 29 30 25 21

    WIP Deviation 10,00% 3,57% 15,38% 8,70% 5,00%

  • 8/18/2019 Capacity Management 2

    34/34

    11/12/2015 Capacities Management 34

    Ilustrasi 2 : Mereduksi WIP

    Mulai Day #26 tingkat input dikurangi pada

    tingkat output yang tetap

    Hal tersebut bertujuan untuk mengurangi

    tingkat WIP yang sebesar 32 standard hoursmenjadi 20 standard hours pada Day #30.

    Pengurangan WIP ini memperkecil lead time.