Canyon Road Bridge Replacement Project October 10, 2018 ... · 10/18/2010  · January Advertise...

20
Town of Moraga Canyon Road Bridge Replacement Project October 10, 2018 Town Council Presentation

Transcript of Canyon Road Bridge Replacement Project October 10, 2018 ... · 10/18/2010  · January Advertise...

Page 1: Canyon Road Bridge Replacement Project October 10, 2018 ... · 10/18/2010  · January Advertise For Construction February Bid Opening March Council Review and Award April Construction

Town of Moraga Canyon Road Bridge Replacement Project

October 10, 2018 Town Council Presentation

Page 2: Canyon Road Bridge Replacement Project October 10, 2018 ... · 10/18/2010  · January Advertise For Construction February Bid Opening March Council Review and Award April Construction

6/14/17

History of Events

2018 Bridge Redesign

Construction Schedule

OVERVIEW

2 10/10/2018

Page 3: Canyon Road Bridge Replacement Project October 10, 2018 ... · 10/18/2010  · January Advertise For Construction February Bid Opening March Council Review and Award April Construction

6/14/17

FHWA = Federal Highway Administration Caltrans = California Department of Transportation HBP = Highway Bridge Program ER = Emergency Relief Program PS = Preliminary Studies PE = Preliminary Engineering FD = Final Design ENV = Environmental RW = Right-of-Way APE = Areas of Potential Effects Map Budget vs. Allocation

ACRONYMS AND TERMINOLOGY

3 10/10/2018

Page 4: Canyon Road Bridge Replacement Project October 10, 2018 ... · 10/18/2010  · January Advertise For Construction February Bid Opening March Council Review and Award April Construction

6/14/17

LOCATION MAP

4 10/10/2018

Adjacent Hill and Residents

Joaquin Moraga Intermediate School

Pear Orchard

Adjacent Residents

Canyon Road Bridge

Lafayette-Moraga Regional Trail/Fire Trail

Moraga Creek and Larch

Creek

Canyon Road

Page 5: Canyon Road Bridge Replacement Project October 10, 2018 ... · 10/18/2010  · January Advertise For Construction February Bid Opening March Council Review and Award April Construction

6/14/17

Bi-Annual Caltrans Bridge Inspection Report finds Bridge Qualifies for Replacement

Town Awarded $3.2M Highway Bridge Program Grant

Town Begins Required Preliminary

Studies

2013- GRANT TO REPLACE BRIDGE

5 10/10/2018

BRIDGE STRUCTURALLY DEFICIENT

Page 6: Canyon Road Bridge Replacement Project October 10, 2018 ... · 10/18/2010  · January Advertise For Construction February Bid Opening March Council Review and Award April Construction

6/14/17

Caltrans Authorizes Phases: Preliminary Studies Environmental Right-of-Way Preliminary Engineering

Community Meeting #1 Speeding Funding Environment Pedestrians/Cyclists

2014 - STUDIES AND OUTREACH

6 10/10/2018

Page 7: Canyon Road Bridge Replacement Project October 10, 2018 ... · 10/18/2010  · January Advertise For Construction February Bid Opening March Council Review and Award April Construction

6/14/17

Environmental (ENV) Studies

Area of Potential Effects Map

Provides For Two Staging Areas

Pear Orchard

Town Staging Area

2014 - STUDIES AND OUTREACH

7 10/10/2018

Page 8: Canyon Road Bridge Replacement Project October 10, 2018 ... · 10/18/2010  · January Advertise For Construction February Bid Opening March Council Review and Award April Construction

6/14/17

Community Meeting #2

Speeding

Sight Visibility

Bridge Lighting

Pedestrian and Cyclist

Design Revised to Address Public Concerns

Caltrans Approves Revised $4.2 M Budget

2015 - OUTREACH AND PLANNING

8 10/10/2018

Page 9: Canyon Road Bridge Replacement Project October 10, 2018 ... · 10/18/2010  · January Advertise For Construction February Bid Opening March Council Review and Award April Construction

6/14/17

Partial Caltrans Submittals: National Environmental

Studies Noise Technical Memo Air Quality

Conformance Visual Technical Memo Traffic Study Bridge Type Selection

2016 - PROJECT STUDY SUBMITTALS

9 10/10/2018

Page 10: Canyon Road Bridge Replacement Project October 10, 2018 ... · 10/18/2010  · January Advertise For Construction February Bid Opening March Council Review and Award April Construction

6/14/17

Bridge Design On Schedule, construction scheduled to start in 2018

April 17 Town Closes Bridge Damaged by Landslide

November 22 Temporary One-Lane Signal Controlled Bridge Opened

2017 - LANDSLIDE

10 10/10/2018

Page 11: Canyon Road Bridge Replacement Project October 10, 2018 ... · 10/18/2010  · January Advertise For Construction February Bid Opening March Council Review and Award April Construction

6/14/17 11

Original Design 110.5’ Long x 48.5’ Wide

BRIDGE DESIGN CHANGES

10/10/2018

56% Bigger Bridge = Increases Concrete, Steel, Pilings,

and Labor

44% Longer Retaining Walls: 240 vs 318 ft. longer wall 40 vs. 71 more piles 1,200 vs. 2,000 ft. total length of pilings

Revised Design 165’ Long x 50.2’ Wide

Page 12: Canyon Road Bridge Replacement Project October 10, 2018 ... · 10/18/2010  · January Advertise For Construction February Bid Opening March Council Review and Award April Construction

6/14/17

Bridge Design to Address Landslide

New South Abutment w/24”” Diameter piles

Page 13: Canyon Road Bridge Replacement Project October 10, 2018 ... · 10/18/2010  · January Advertise For Construction February Bid Opening March Council Review and Award April Construction

6/14/17

KEY DESIGN ELEMENTS

13

Bike Lanes and Multi-Use Path across bridge Lighting for Motorist and Pedestrians Improved Sight Distance Improved Aesthetics Widen Bridge to Std. Guard Rails

Examples: Left – separated multi-use path Above - open guard rail

Page 14: Canyon Road Bridge Replacement Project October 10, 2018 ... · 10/18/2010  · January Advertise For Construction February Bid Opening March Council Review and Award April Construction

6/14/17

BRIDGE AND ROADWAY COORDINATION

Preliminary Moraga Way & Canyon - Camino Pablo Improvements

Page 15: Canyon Road Bridge Replacement Project October 10, 2018 ... · 10/18/2010  · January Advertise For Construction February Bid Opening March Council Review and Award April Construction

6/14/17

Town Requests $7.2M Budget HBP Freezes All Funding Town Appeals Funding Freeze Caltrans Releases Funds for PE, ENV, RW Caltrans Approves New Budget $6.5M $700k in Funding Shortfall Still To Be

Addressed Note: Bridge funding process is flexible to enable the incorporation of additional information discovered during the design process.

2018 – REDESIGN & FUNDING FREEZE

15 10/10/2018

Page 16: Canyon Road Bridge Replacement Project October 10, 2018 ... · 10/18/2010  · January Advertise For Construction February Bid Opening March Council Review and Award April Construction

6/14/17

Staff requests Caltrans funding in FY 18/19 as funding for temporary bridge lease expires in September 2019

Caltrans Sets November 1st Deadline to Accelerate Funds. Documents due include: Environmental Clearances RW Clearances Utility Clearance Final Design

FUNDING DEADLINE

16 10/10/2018

Page 17: Canyon Road Bridge Replacement Project October 10, 2018 ... · 10/18/2010  · January Advertise For Construction February Bid Opening March Council Review and Award April Construction

6/14/17

January Advertise For Construction

February Bid Opening

March Council Review and Award April Construction Commence

(2 Season Construction Phasing) Assumes Caltrans accelerates funding to FY 2018/19. If funding not accelerated, Town will need to evaluate options and determine course of action.

2019 - CONSTRUCTION SCHEDULE

17 10/10/2018

Page 18: Canyon Road Bridge Replacement Project October 10, 2018 ... · 10/18/2010  · January Advertise For Construction February Bid Opening March Council Review and Award April Construction

6/14/17

Construct bridge’s northbound lane and approaches Temporary bridge continues to handle traffic in both directions

2019 Construction – Phase I

18 10/10/2018

Page 19: Canyon Road Bridge Replacement Project October 10, 2018 ... · 10/18/2010  · January Advertise For Construction February Bid Opening March Council Review and Award April Construction

6/14/17

Construct bridge’s southbound lane and remove temporary bridge

New northbound lane handles traffic in both directions

2020 Construction - Phase 2

19 10/10/2018

Page 20: Canyon Road Bridge Replacement Project October 10, 2018 ... · 10/18/2010  · January Advertise For Construction February Bid Opening March Council Review and Award April Construction

6/14/17

Discussion

2020 Construction - Phase 2

20 10/10/2018