CanSat 2020 Preliminary Design Review (PDR) Outline Version 1
Transcript of CanSat 2020 Preliminary Design Review (PDR) Outline Version 1
CanSat 2020 PDR: Team 4920 Manchester CanSat Project 1
CanSat 2020
Preliminary Design Review (PDR)
Outline
Version 1.0
Team 4920
Manchester CanSat Project
2
Presentation Outline
Presenter: May Ling Har CanSat 2020 PDR: Team 4920 Manchester CanSat Project
This review follows the sub-sections listed below:
Section Presenter Page Number
Systems Overview May Ling Har (MLH) 5
Sensors Sub-System Overview May Ling Har (MLH) 21
Descent Control Design May Ling Har (MLH) 34
Mechanical Sub-System Design May Ling Har (MLH) 55
Communications and Data Handling Sub-System Design
May Ling Har (MLH) 93
Electrical Power Sub-System Conor Shore (CS) 109
Flight Software Design Conor Shore (CS) 122
Ground Control System Design Conor Shore (CS) 130
CanSat Integration and Testing Conor Shore (CS) 141
Mission Operations and Analysis Conor Shore (CS) 152
Requirements Compliance Conor Shore (CS) 157
Management Conor Shore (CS) 164
3
Team Organization
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
May Ling Har
Chief Engineer
Mechanical Subsystem
May Ling Har
2nd Year
Claudio Rapisarda
2nd Year
Min Woo Ryu
2nd Year
Gaurav Jalan
4th Year
Timos Chronis
4th Year
Electronics Subsystem
Conor Shore
2nd Year
Mihnea Romanovschi
2nd Year
Marin Dimitrov
3rd Year
Teja Potocnik
3rd Year
George Amies
4th Year
Integration and Testing
Teja Potocnik
Ground Control Station
Teja Potocnik
Conor Shore
Project Manager
Kate SmithAcademic Advisor
Team Member Responsibility
May Ling Har (MLH) CE, ME
Conor Shore (CS) PM, CDH, EPS
Teja Potocnik (TP) I&T, GCS
Claudio Rapisarda (CR) DC
Min Woo Ryu (MWR) ME
Gaurav Jalan (GJ) ME
Timos Chronis (TC) DC
Mihnea Romanovschi (MR) FSW
Marin Dimitrov (MD) EPS, CDH
George Amies (GA) SE, CDH
Presenter: May Ling Har
4
Acronyms
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
CDH Communications and Data Handling
EPS Electrical Power Sub-System
FSW Flight Software
GCS Ground Control Station
ME Mechanical Sub-System
SE Sensors Sub-System
DC Descent Control Sub-System
CE Chief Engineer
PM Project Manager
I&T Integration and Testing
CONOPS Concept of Operations
A Analysis
I Inspection
T Testing
D Demonstration
TBC To be confirmed
TBD To be determined
RE# Top Level Requirement
SL System Level
SSL Sub-system Level
GUI Graphical User Interface
IDE Integrated Development Environment
RTC Real Time Clock
I2C Inter-Integrated Circuit
SPI Serial Peripheral Interface
ADC Analog to Digital Converter
DAC Digital to Analog Converter
EEPROM Electrically Erasable Programmable Read-only memory
MCU Microcontroller
ADU Analog Digital Unit
IMU Inertial Measurement Unit
CCU Central Control Unit
CG Centre of Gravity
NP Neutral Point
Presenter: May Ling Har
5
Systems Overview
May Ling Har
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
6
Mission Summary
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Objectives:1. Build a CanSat with an atmospheric-sampling Science Payload, a delta-wing glider, that shall descend in a
circular pattern and a Parachute, and a separate Container and Parachute.2. The CanSat shall be launched in a sounding rocket to an altitude of 675-725 meters.3. Once the CanSat is deployed from the rocket, the CanSat shall descend using a Parachute at a descent rate of 20
m/s.4. The CanSat Container must protect the Science Payload from damage during the launch and deployment.5. At 450 meters, the Container shall release the Science Payload. The Science Payload shall then descend in a
circle for a minute and remain above 100 meters. After that, the Science Payload shall deploy a Parachute to descend at 10 m/s.
6. The Science Payload shall collect and transmit atmospheric data to a Ground Control Station in real-time, throughout its operation phase.
7. When the Science Payload lands, all telemetry transmission shall stop and a located audio beacon shall activate.8. The Ground Control Station shall receive and display CanSat data.
Selectable Bonus and Rationale:• Camera Bonus selected because of abundant team members experience.
External Objectives:• Continue to deliver Manchester CanSat Project weekly, educational, space-related Workshops towards University
of Manchester STEM Students. • Continue to develop a UK University CanSat Competition for UK universities. • Inspire other UK Universities and Academic Institutions to adopt the Manchester CanSat Project model to create
a network of CanSat societies across the UK.
Presenter: May Ling Har
System Requirement Summary
7CanSat 2020 PDR: Team 4920 Manchester CanSat Project
RE# RequirementVerification
A I T D
1 Total mass of the CanSat (science payload and container) shall be 600 grams +/- 10 grams. X X
2 CanSat shall fit in a cylindrical envelope of 125 mm diameter x 310 mm length. Tolerances are to be included to facilitate container deployment from the rocket fairing.
X X
3 The container shall not have any sharp edges to cause it to get stuck in the rocket payload section which is made of cardboard.
X X X
4 The container shall be a fluorescent color; pink, red or orange. X X
5 The container shall be solid and fully enclose the science payload. Small holes to allow access to turn on the science payload is allowed. The end of the container where the payload deploys may be open.
X X
6 The rocket airframe shall not be used to restrain any deployable parts of the CanSat. X X
7 The rocket airframe shall not be used as part of the CanSat operations. X X
8 The container parachute shall not be enclosed in the container structure. It shall be external and attached to the container so that it opens immediately when deployed from the rocket.
X X X
9 The descent rate of the CanSat (container and science payload) shall be 20 meters/second +/- 5m/s. X X
10 The container shall release the payload at 450 meters +/- 10 meters. X X X
11 The science payload shall glide in a circular pattern with a 250 m radius for one minute and stay above 100 meters after release from the container.
X X X
12 The science payload shall be a delta wing glider. X X X
13 After one minute of gliding, the science payload shall release a parachute to drop the science payload to the ground at 10 meters/second, +/- 5 m/s
X X X
14 All descent control device attachment components shall survive 30 Gs of shock. X X
Presenter: May Ling Har
System Requirement Summary
8CanSat 2020 PDR: Team 4920 Manchester CanSat Project
RE# RequirementVerification
A I T D
15 All electronic components shall be enclosed and shielded from the environment with the exception of sensors. X
16 All structures shall be built to survive 15 Gs of launch acceleration. X X
17 All structures shall be built to survive 30 Gs of shock. X X
18 All electronics shall be hard mounted using proper mounts such as standoffs, screws, or high performance adhesives. X
19 All mechanisms shall be capable of maintaining their configuration or states under all forces. X
20 Mechanisms shall not use pyrotechnics or chemicals. X
21 Mechanisms that use heat (e.g., nichrome wire) shall not be exposed to the outside environment to reduce potential risk of setting vegetation on fire.
X X X
22 The science payload shall measure altitude using an air pressure sensor. X X X X
23 The science payload shall provide position using GPS. X X X X
24 The science payload shall measure its battery voltage. X X X X
25 The science payload shall measure outside temperature. X X X X
26 The science payload shall measure particulates in the air as it glides. X X X X
27 The science payload shall measure air speed. X X X X
28 The science payload shall transmit all sensor data in the telemetry. X X X X
29 Telemetry shall be updated once per second. X X X
30 The Parachutes shall be fluorescent Pink or Orange . X X
31 The ground system shall command the science vehicle to start transmitting telemetry prior to launch. X X X
Presenter: May Ling Har
System Requirement Summary
9CanSat 2020 PDR: Team 4920 Manchester CanSat Project
RE# RequirementVerification
A I T D
32 The ground station shall generate a csv file of all sensor data as specified in the telemetry section. X X
33 Telemetry shall include mission time with one second or better resolution. Mission time shall be maintained in the event of a processor reset during the launch and mission.
X X X
34 Configuration states such as if commanded to transmit telemetry shall be maintained in the event of a processor reset during launch and mission.
X X X
35 XBEE radios shall be used for telemetry. 2.4 GHz Series radios are allowed. 900 MHz XBEE Pro radios are also allowed. X
36 XBEE radios shall have their NETID/PANID set to their team number. X X X
37 XBEE radios shall not use broadcast mode. X X
38 Cost of the CanSat shall be under $1000. Ground support and analysis tools are not included in the cost. X X
39 Each team shall develop their own ground station. X
40 All telemetry shall be displayed in real time during descent. X X
41 All telemetry shall be displayed in engineering units (meters, meters/sec, Celsius, etc.) X X
42 Teams shall plot each telemetry data field in real time during flight. X X
44 The ground station shall include one laptop computer with a minimum of two hours of battery operation, XBEE radio and a hand-held antenna.
X
45 The ground station must be portable so the team can be positioned at the ground station operation site along the flight line. AC power will not be available at the ground station operation site.
X
46 Both the container and probe shall be labelled with team contact information including email address. X
47 The flight software shall maintain a count of packets transmitted, which shall increment with each packet transmission throughout the mission. The value shall be maintained through processor resets.
X X
Presenter: May Ling Har
System Requirement Summary
10CanSat 2020 PDR: Team 4920 Manchester CanSat Project
RE# RequirementVerification
A I T D
48 No lasers allowed. X X
49 The probe must include an easily accessible power switch that can be accessed without disassembling the CanSat and in the stowed configuration.
X X X
50 The probe must include a power indicator such as an LED or sound generating device that can be easily seen without disassembling the CanSat and in the stowed state.
X X X
51 An audio beacon is required for the probe. It may be powered after landing or operate continuously. X X X
52 The audio beacon must have a minimum sound pressure level of 92 dB, unobstructed. X X
53 Battery source may be alkaline, Ni-Cad, Ni-MH or Lithium. Lithium polymer batteries are not allowed. Lithium cells must be manufactured with a metal package similar to 18650 cells.
X X X
54 An easily accessible battery compartment must be included allowing batteries to be installed or removed in less than a minute and not require a total disassembly of the CanSat.
X X X
55 Spring contacts shall not be used for making electrical connections to batteries. Shock forces can cause momentary disconnects.
X
56 The CANSAT must operate during the environmental tests laid out in Section 3.5. X X
57 Payload/Container shall operate for a minimum of two hours when integrated into rocket. X
B1 Bonus: A video camera shall be integrated into the science payload and point toward the coordinates provided for the duration of the glide time. Video shall be in color with a minimum resolution of 640x480 pixels and 30 frames per second. The video shall be recorded and retrieved when the science payload is retrieved. Points will be awarded only if the camera can maintain pointing at the provided coordinates for 30 seconds uninterrupted.
X X X
Presenter: May Ling Har
11
System Level CanSat Configuration
Trade & Selection
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Concept 1 Concept 2
Central Control Unit (CCU) for Payload release, Wings deployment, and Payload Parachute release.
Enclosed Nichrome wire mechanism for Payload release, and Payload Parachute release.
Airfoil-shaped fuselage. Cuboid-shaped fuselage with a rounded nose.
‘X’ wing structure to fold wings Wings folded using torsion springs.
Container made of carbon fibre rods, and ABS ‘ribs’ and plates.
Container made of fiberglass.
Deflected elevon on T-tail to ensure circular descent. Deflected rudder on tail to ensure circular descent.
Concept Chosen Rationale
CONCEPT 1
Improved stability and predictabilityMore reliable release mechanismHigher wing structural integrity
Larger wingspan achieved
Both designs are compliant with the mission requirements. Hence, the most important factor is theaerodynamic stability of the glider, and the release and deployment mechanism. While Concept 1 isindeed harder to integrate and heavier, the the CCU has been tested in last year’s Competition along withvarious test launches, and has shown to be effective and reliable.
Presenter: May Ling Har
12
System Level CanSat Configuration
Trade & Selection
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Concept One (Chosen):
Payload stowed in fluorescent pink Container
Payload with delta wing deployed
Payload with fluorescent pink parachute deployed
T-tail with slightly deflected elevon.
Camera with 360° continuous rotation and 90° pitch, with bevel gears.‘X’ structure to fold wings.
Central Control Unit for Payload release, Wings Deployment and Payload Parachute Deployment.
Presenter: May Ling Har
13
System Level CanSat Configuration
Trade & Selection
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Concept Two:
Torsion springs to fold wings.Nichrome wire mechanism for Payload release
and Payload Parachute deployment.
Camera with 360° continuous rotation and 90° pitch, with
3D printed ABS gears.
Payload stowed in fluorescent pink Container
Payload with delta wing deployed
Tail with slightly deflected rudder.
Payload with fluorescent pink parachute deployed
Presenter: May Ling Har
System Level Configuration Selection
14CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Concept Chosen: CONCEPT 1
Configuration Rationale
Central Control Unit (CCU) for Payload release, Wings deployment, and Payload Parachute release.
A CCU was used in last year’s design and consists of arotational servo with various rods attached,converting motion from rotational to linear. It hasbeen a thoroughly tested mechanism and is known tobe both effective and reliable.
Airfoil-shaped fuselage.An airfoil-shaped fuselage allows the team to predictand simulate the glider. It also improves theaerodynamic stability of the glider.
‘X’ wing structure to fold wingsAn ‘X’ wing structure not only improves the structuralintegrity of the wing, it can also achieve a largerwingspan.
Deflected T-tail to ensure circular descent.The deflection needed to ensure a circular descent islarger and easier to incorporate on a T-tail elevoncompared to a rudder.
Container made of carbon fibre rods, and PLA ‘ribs’ and plates.
This configuration allows for better access to the payload.
Presenter: May Ling Har
15
Physical Layout
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
321 4 5
1) Launch Configuration (In Rocket)2) Deployed Configuration (Rocket Deployment – 450 m)3) Payload released Configuration (450 m)4) Payload deployed Configuration (450m – 100m)5) Payload parachute deployed Configuration (100m – Landfall)
Presenter: May Ling Har
Physical Layout
16
Red – Container Parachute BayBlue – Central Control Unit (CCU) subassemblyYellow – PCB and Mounted ElectronicsGreen – Camera Mechanism subassembly
3
12 4
5
A
B
C
D
E F G H
I
J
Basic Dimensions1 – 305 mm2 – 300 mm3 – 125 mm4 – 400 mm5 – 280 mm6 – 120 mm
Major componentsA – BatteryB – GPS moduleC – Pitot tubeD – CameraE – Camera pitch/yaw mechanismF – PCB + TeensyG – PM sensorH – Parachute bayI – Central Control Unit (CCU)J – Tail
Presenter: May Ling Har CanSat 2020 PDR: Team 4920 Manchester CanSat Project
6
17
System Concept of Operations
•
•
•
•
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
0. Pre-Launch
1. Launch
2. Container Parachute
Deployment
3. CanSatDescent
4.1 Payload Release
4.2 Payload Wings
Deployment
5.1 Container Descent
5.2 Payload Descent
6. Payload Parachute
Deployment
7. Landfall 8. Recovery9. Data
Handover
Presenter: May Ling Har
18
System Concept of Operations
•
•
•
•
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
0. Pre -Launch
• CanSatswitched on
• Telemetry transmitting start
1. Launch
• CanSatinsertion in Rocket Payload Bay
• Rocket ignition and ascension
• Apogee reached
2. Parachute Deployment
• Rocket and nose cone separation
• CanSatdeployed from rocket Payload Bay
• Container Parachute deploys
• Rocket and nose cone descend separately
3. CanSatDescent
• CanSat descent at 20 m/s with Parachute deployed
4. Payload Release
• 450 m altitude sensed by Payload
• Payload released from Container
• Payload wings deploy
• Camera begins recording
Presenter: May Ling Har
19
System Concept of Operations
•
•
•
•
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
5.1. Container Descent
• Container descends separately under deployed Parachute
5.2. Payload Descent (Glide)
• Payload descends by gliding in a circular motion of radius 250 m for a minute, remaining above 100 meters in altitude
5.3. Payload Descent
(Parachute)
• Payload releases Parachute, and descends at 10 m/s
6. Landing
• Telemetry transmitting stop
• Audio beacon activation
7. Recovery
• Audio beacon operational
• All systems recovered (including Container)
• CanSatswitched off
8. Data Handover
• Data formatted and saved to USB
• USB handed over to officials
Presenter: May Ling Har
Dimensional constraints (as per Competition Requirements):• Diameter - 125 mm• Height - 310 mm
Dimensional constraints of current design:• Diameter – 120 mm• Height – 305 mm• Diameter clearance – 2.5 mm each side• Height clearance – 2.5 mm each side• No sharp protrusions (bolts will be sanded down if necessary)
Dimensions account for ease of fit and deployment.The team will endeavor to increase the clearance size to 5 mm.
Multiple test launches will be performed at the University of Manchesterto verify Launch Vehicle Compatibility.
2.5 x 2.5clearance
20
Launch Vehicle Compatibility
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
2.5 x 2.5clearance
Presenter: May Ling Har
21
Sensor Subsystem Design
May Ling Har
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Sensor Subsystem Overview
22
Selected Component Function
ICM-20948 9-axis IMUMeasures angular velocity, angular acceleration, and magnetic heading. All measurements contain readings in 3-axis.
BMP 388 Barometric Pressure SensorMeasures the air pressure to provide temperature compensated altitude information. Also provides temperature information.
u-blox NEO-M8N GPS ModuleTracks the position of the Payload. Also provides ground speed readings.
MS4525DO Differential Pressure Sensor
Measures differential pressure to provide airspeed readings.
GP2Y1010AU0F Particulate Sensor Measures the concentration of particulates in the air.
RunCam Nano 2 CMOS Camera Used for camera bonus objective to record position of target location.
HMDVR Digital Video Recorder Used to record video from the camera.
CanSat 2020 PDR: Team 4920 Manchester CanSat ProjectPresenter: May Ling Har
23
Sensor Subsystem Requirements
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
RE# RequirementVerification
A I T D
1 Total mass of the CanSat (science payload and container) shall be 600 grams +/- 10 grams. X X
2 CanSat shall fit in a cylindrical envelope of 125 mm diameter x 310 mm length. Tolerances are to be included to facilitate container deployment from the rocket fairing. X X
9 The descent rate of the CanSat (container and science payload) shall be 20 meters/second +/- 5m/s. X X
10 The container shall release the payload at 450 meters +/- 10 meters. X X X
11 The science payload shall glide in a circular pattern with a 250 m radius for one minute and stay above 100 meters after release from the container. X X X
13 After one minute of gliding, the science payload shall release a parachute to drop the science payload to the ground at 10 meters/second, +/- 5 m/s X X X
14 All descent control device attachment components shall survive 30 Gs of shock. X X
15 All electronic components shall be enclosed and shielded from the environment with the exception of sensors. X
16 All structures shall be built to survive 15 Gs of launch acceleration. X X
17 All structures shall be built to survive 30 Gs of shock. X X
Presenter: May Ling Har
24
Sensor Subsystem Requirements
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
RE# RequirementVerification
A I T D
18 All electronics shall be hard mounted using proper mounts such as standoffs, screws, or high performance adhesives. X
22 The science payload shall measure altitude using an air pressure sensor. X X X X
23 The science payload shall provide position using GPS. X X X X
24 The science payload shall measure its battery voltage. X X X X
25 The science payload shall measure outside temperature. X X X X
26 The science payload shall measure particulates in the air as it glides. X X X X
27 The science payload shall measure air speed. X X X X
28 The science payload shall transmit all sensor data in the telemetry. X X X X
29 Telemetry shall be updated once per second. X X X
41 All telemetry shall be displayed in engineering units (meters, meters/sec, Celsius, etc.) X X
56 The CANSAT must operate during the environmental tests laid out in Section 3.5. X X
57 Payload/Container shall operate for a minimum of two hours when integrated into rocket. X
Presenter: May Ling Har
25
Sensor Subsystem Requirements
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
RE# RequirementVerification
A I T D
B1 Bonus: A video camera shall be integrated into the science payload and point toward the coordinates provided for the duration of the glide time. Video shall be in color with a minimum resolution of 640x480 pixels and 30 frames per second. The video shall be recorded and retrieved when the science payload is retrieved. Points will be awarded only if the camera can maintain pointing at the provided coordinates for 30 seconds uninterrupted.
X X X
Presenter: May Ling Har
Payload Air Pressure Sensor
Trade & Selection
26
Component InterfaceResolution
(Pa)
Accuracy (hPa) Size (mm)L x W x H
Mass (g) Cost (£)Error (m)*
BMP180 I2C 0.01-4.0 / +2.0 2.5 x 2 x
0.950.04 3.19
-0.28 / -0.14
BMP388 I2C / SPI 0.016+/- 0.4 2.0 x 2.0 x
0.750.06 2.62
+/- 0.03
MS5607 I2C / SPI 2.4+/- 1.5 5.0 x 3.0 x
1.00.12 2.42
+/- 0.11
*At altitude of 300m
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Selected Component Rationale
BMP388
• Best specifications• Small footprint• Direct upgrade from last year’s solution (BMP180). Familiar with
interface.
Presenter: May Ling Har
27
Payload Air Temperature Sensor
Trade & Selection
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Selected Component Rationale
BMP388• Module already integrated in the system• Highest resolution and accuracy
Component InterfaceResolution
(oC)Accuracy (oC)
Size (mm)L x W x H
Mass (g) Cost (£)
BMP180 I2C 0.1 ± 0.52.5 x 2 x
0.950.04 3.19
BMP388 I2C / SPI 0.005 ± 0.32.0 x 2.0 x
0.750.06 2.62
MS5607 I2C / SPI 0.008 ± 2.05.0 x 3.0 x
1.00.12 2.42
Presenter: May Ling Har
28
GPS Sensor
Trade & Selection
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Component InterfaceHorizontal
Position Accuracy (m)
Velocity Accuracy
(m/s)
Time-To-First-Fix (s) Size (mm)L x W x H
Mass (g)Cost (£)Cold Hot
uBlox NEO M8N
I2C/ SPI/ UART
2.5 0.05 29 116 x 12 x
2.23.00 6.78
MTK MT3339I2C/ SPI/
UART3.0 0.1 35 1 16 x 16 x 5 4.00 23.15
Titan X1I2C/ SPI/
UART3.0 0.1 35 1
13 x 13 x 6.9
5.30 38.54
Selected Component Rationale
uBlox NEO M8• Most accurate position tracking• Fastest operation• Previous experience
Presenter: May Ling Har
29
Payload Power Voltage Sensor
Trade & Selection
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Component Interface Resolution (mV)Size (mm)L x W x H
Mass (g) Cost (£)
Onboard ADC + Voltage Divider
Analog 1.6 Negligible Negligible Negligible
INA219 I2C 41.63 x 2.90 x
1.450.08 20
Selected Component Rationale
Onboard ADC + Voltage Divider
• Simplicity• Previous experience
Note: the voltage divider is needed as the inbuilt Teensy
ADC measures voltage values up to 3.3 V.
Presenter: May Ling Har
30
Air Speed Sensor
Trade & Selection
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Component InterfacePressure
Range (kPa)Accuracy (%
span)Size (mm)L x W x H
Mass (g) Cost (£)
MPXV7002 I2C ± 2 ± 2.517.8 x 18.4 x
9.44.5 17.4
MS4525DO I2C / SPI ± 6.89 ± 0.2512.4 x 17.4 x
7.23.0 31.57
MS5525DSO I2C / SPI ± 6.89 ± 0.25 12.5 x 7.9 x 9.7 3.0 17.75
Selected Component Rationale
MS4525DO
• Low Mass• Accuracy• Availability• Previous experience
Presenter: May Ling Har
31
Particulate/Dust Sensor
Trade & Selection
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Selected Component Rationale
GP2Y1010AU0F• Smallest size• Lightest
Component InterfaceResolution
(µm/m3)Size (mm)L x W x H
Mass (g) Cost (£)
GP2Y1010AU0F Analog 1.6 46 x 34 x 17.6 15 7.43
PPD42NS SPI 1 59 x 45 x 22 24 8.89
Presenter: May Ling Har
32
Bonus Camera Trade & Selection
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Component Interface ResolutionField of View
(deg)Size (mm)L x W x H
Mass (g) Cost (£)
RunCam Nano 2
Serial 976 x 582 155 14 x 14 x 16 3.2 12.58
Foxeer XAT520 Mini FPV Camera
Serial 786 x 576 10011.8 x 11.8 x
24.54.5 19.58
SQ11 Pawaca Camera
SelfContained
640 x 480 140 20 x 28 x 105
(disassembled)12
Selected Component Rationale
RunCam Nano 2• Lowest Mass• High field of view
Presenter: May Ling Har
33
Container Air Pressure Sensor
Trade & Selection
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Note:From previous experience, there is no need for an air pressure sensor in the container. The sensor available in the payload is sufficient to determine the exact altitude.
Component InterfaceResolution
(Pa)
Accuracy (hPa) Size (mm)L x W x H
Mass (g) Cost (£)Error (m)*
BMP180 I2C 0.01-4.0 / +2.0 2.5 x 2 x
0.950.04 3.19
-0.28 / +0.14
BMP388 I2C / SPI 0.016+/- 0.4 2.0 x 2.0 x
0.750.06 2.62
+/- 0.03
MS5607 I2C / SPI 2.4+/- 1.5 5.0 x 3.0 x
1.00.12 2.42
+/- 0.11
Presenter: May Ling Har
*At altitude of 300m
34
Descent Control Design
May Ling Har
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
35
Descent Control Overview
•
•
•
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Stage 1: apogee → 450m
Container is released from the rocket at apogee. The Container parachute is deployed with the payload stowed inside the container.
Stage 2A: 450m → ≥100m
The payload is released from the container and glides in a circular pattern for 60 seconds while data acquisition takes place and the camera tracks its target.
Stage 3: ≥100m → landfall
The payload parachute is deployed.
Stage 2B: 450m → landfall
After the payload is released, the container continues to descend under its parachute.
1
2A
2B
3
Container and container parachute will be fluorescent pinkPayload parachute will be fluorescent pink
Presenter: May Ling Har
36
Descent Control Requirements
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
RE# RequirementVerification
A I T D
1 Total mass of the CanSat (science payload and container) shall be 600 grams +/- 10 grams. X X
2 CanSat shall fit in a cylindrical envelope of 125 mm diameter x 310 mm length. Tolerances are to be included to facilitate container deployment from the rocket fairing.
X X
3 The container shall not have any sharp edges to cause it to get stuck in the rocket payload section which is made of cardboard.
X X X
4 The container shall be a fluorescent color; pink, red or orange. X X
5 The container shall be solid and fully enclose the science payload. Small holes to allow access to turn on the science payload is allowed. The end of the container where the payload deploys may be open.
X X
6 The rocket airframe shall not be used to restrain any deployable parts of the CanSat. X X
7 The rocket airframe shall not be used as part of the CanSat operations. X X
8 The container parachute shall not be enclosed in the container structure. It shall be external and attached to the container so that it opens immediately when deployed from the rocket.
X X X
9 The descent rate of the CanSat (container and science payload) shall be 20 meters/second +/- 5m/s. X X
10 The container shall release the payload at 450 meters +/- 10 meters. X X X
11 The science payload shall glide in a circular pattern with a 250 m radius for one minute and stay above 100 meters after release from the container.
X X X
12 The science payload shall be a delta wing glider. X X X
13 After one minute of gliding, the science payload shall release a parachute to drop the science payload to the ground at 10 meters/second, +/- 5 m/s
X X X
14 All descent control device attachment components shall survive 30 Gs of shock. X X
Presenter: May Ling Har
37
Descent Control Requirements
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
RE# RequirementVerification
A I T D
16 All structures shall be built to survive 15 Gs of launch acceleration. X X
17 All structures shall be built to survive 30 Gs of shock. X X
18 All electronics shall be hard mounted using proper mounts such as standoffs, screws, or high performance adhesives. X
19 All mechanisms shall be capable of maintaining their configuration or states under all forces. X
30 The Parachutes shall be fluorescent Pink or Orange X X
38 Cost of the CanSat shall be under $1000. Ground support and analysis tools are not included in the cost. X X
48 No lasers allowed. X X
B1 Bonus: A video camera shall be integrated into the science payload and point toward the coordinates provided for the duration of the glide time. Video shall be in color with a minimum resolution of 640x480 pixels and 30 frames per second. The video shall be recorded and retrieved when the science payload is retrieved. Points will be awarded only if the camera can maintain pointing at the provided coordinates for 30 seconds uninterrupted.
X X X
Note: Regarding RE B1, an outer structure will be required in order to accommodatethe camera. This will create extra drag and lower the net Lift over Drag ratio.
Presenter: May Ling Har
38
Payload Descent Control Strategy
Selection and Trade
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
STAGE 1 & 2B - Container Parachute design Selection & Trade off:
Shape Advantages Disadvantages
CircleHigher drag, short deployment time,
high durabilityDifficult to fabricate
Cross Easy to manufacture, easy to stack Lower drag
Square Easy to manufacture, ease of integration Longer deployment time, lower drag
Material Advantages Disadvantages
Ripstop NylonLightweight, high strength-to-weight ratio, resistant to tear, low moisture
absorbencyHeat sensitive, not eco-friendly
Terylene High strength, heat resistant Not eco-friendly, not easily procurable
KevlarHigh tensile strength, thermal stability
and resilienceLow compressive strength, absorbs
moisture, expensive
Therefore, a fluorescent pink circular Ripstop Nylon parachute has been chosen to control stowed descent rate. This is thefirst parachute and it will be deployed at rocket separation for both the container and payload and, once the payload hasbeen released, only for the container. The parachute will be purchased off-the shelf to compensate for the disadvantage.
Used from apogee (670-725 m) until landing (0 m)
Presenter: May Ling Har
39
Payload Descent Control Strategy
Selection and Trade
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Configuration B: Folding wingsConfiguration A: Extending blended wing
Deployed payload descent control strategy
Payload descent control will be achieved by means of the lifting force generated by wings in a delta configuration. The rate of descent is depended on the ratio of the lifting force to the aerodynamic drag force. Two configurations were conceived to provide the required lift-to-drag ratio:
Configuration Advantages Disadvantages
A: Extending blended wing• Allows the use of more efficient airfoils• Larger wing surface area achievable
• Complex to design and assemble
B: Folding wings• Easy to manufacture• Simpler mechanism• More flexible allocation of fuselage space
• Smaller wing area• Poorer wing structural integrity
Presenter: May Ling Har
40
Payload Descent Control Strategy
Selection and Trade
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Configuration A was chosen with the following details:
Component Construction Reasons for selection
Fuselage compartment Rib frame with fabric skin• Lightweight• More aerodynamic
Wings Extending X-frame spar with stretched fabric skin• Space-efficient stowage• Rigid construction• Smooth wing blending
Collapsed configuration Extended configuration
Presenter: May Ling Har
41
Payload Descent Control Strategy
Selection and Trade•
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Option B: Nichrome wireOption A: Central Control Unit (CCU)
Payload parachute deployment method
CCU in parachute release position
Option Advantages Disadvantages
A: CCUIntegrates with other mechanisms of the
design, reusable, previous experienceHeavier, occupies more space
B: Nichrome wire Lightweight, simple operation Single use, requires insulating
Parachute bay lid release controlled by Nichrome wire heating
Presenter: May Ling Har
Option A was chosen as the CCU has shown to be reliable and has been tested thoroughly in previous competitions and test launches.
42
Payload Descent Control Strategy
Selection and Trade
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
STAGE 3 - Payload Parachute design Selection & Trade off:
Shape Advantages Disadvantages
CircularHigher drag, short deployment time,
high durabilityDifficult to fabricate
Cross Easy to manufacture, easy to stack Lower drag
Square Easy to manufacture, ease of integration Longer deployment time, lower drag
Material Advantages Disadvantages
Ripstop NylonLightweight, high strength-to-weight ratio, resistant to tear, low moisture
absorbencyHeat sensitive, not eco-friendly
Terylene High strength, heat resistant Not eco-friendly, not easily procurable
KevlarHigh tensile strength, thermal stability
and resilienceLow compressive strength, absorbs
moisture, expensive
Therefore, a circular fluorescent pink Ripstop Nylon parachute has been chosen to control stowed descent rate.This is the second parachute and it will be deployed after one minute of gliding, or at 100 metres, only for the payload.The parachute will be purchased off-the shelf to compensate for the disadvantage.
Used after one minute of gliding until landing (0 m)
Presenter: May Ling Har
Payload Descent Stability Control
Strategy Selection and Trade
•
43CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Active or Passive control Selection & Trade off:
Design Advantages Disadvantages
Passive
The design is inherently positively stable and does not need any active
corrections, ease of integration, no dependence on sensors and software
Challenging to manufacture and assemble, less predictable in case of
strong wind or air currents
Active
The turn would be achieved with greater accuracy, stability could be controlled actively, reducing the risk of tumbling
due to air currents
Extra weight and volume required for servo,
complexity of integration and coding
A passive control system has been chosen for the mission as it isless complex to integrate, allowing the team to focus on othertasks for the mission to be successful. Static stability control willbe achieved by generating enough lift to balance the drag and acomponent of the weight. Longitudinal stability is attained as theCG is forward of the NP, whereas lateral stability is obtained usinga vertical fin and a dihedral angle. The glider will then descend ina circular pattern due to a fixed elevon deflection.
CGNP
Vertical fin
Presenter: May Ling Har
44
Payload Descent Stability Control
Strategy Selection and Trade
•
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Option B: Section twistOption A: Reflex cambered airfoil
Longitudinal stability
XFLR5 was initially used to iterate through combinations of airfoil sections. With the planform area constrained by the payload container and deployment mechanism, the main requirements for airfoil selection were the descent rate, positive longitudinal stability and internal volume.
Two options for balancing the pitching moment were identified:
Option A (reflex airfoil) was chosen as it was easier to incorporate into the design and to manufacture.
Option Advantages Disadvantages
A: Reflex cambered airfoil Simpler to incorporate into design Performance reliant on accurate manufacturing
B: Section twist More effective in balancing pitching momentLess compatible with selected wing skinning method
Presenter: May Ling Har
45
Payload Descent Stability Control
Strategy Selection and Trade
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
For the inboard panels (1, 2):the GOE735 airfoil was chosen for its internal volume. Data was obtained from XFLR5 airfoilanalysis.
For the outboard panels (3):The ESA40 was chosen as a reflex airfoil with high L/D. Data was obtained from Selig Low Speed Airfoil Data Vol.3.
A static margin of 30% of the wing mean aero chord was selected based on the XFLR5 analysis of the longitudinal stability modes.
CG
NP
11
22
3 3
Horizontal stabiliser
Wing span 400 mm
Total wing area 0.0788 m2
Presenter: May Ling Har
46
Payload Descent Stability Control
Strategy Selection and Trade
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Based on Prandtl’s lifting line theory, the aerodynamic coefficients of the glider were calculated from the 2D airfoil data and used to validate the chosen configuration. Longitudinal stability was determined using the total pitching moment coefficient, evaluated using moment contributions from each wing panel for a given airfoil section.
A negative rate of change of Cm with angle of attack confirmed positive longitudinal stability.
Ӗ𝑐 Mean aero chord of wingന𝑐𝑖 Mean aero chord of panel 𝑖ℎ CG position, in % of Ӗ𝑐ℎ0𝑖 AC of panel 𝑖, in % of Ӗ𝑐𝑆𝑖 Surface area of panel 𝑖𝑆 Total wing surface area𝐶𝑀, 0𝑖
Moment coefficient of panel 𝑖𝐶𝐿, 𝑖 Lift coefficient of panel 𝑖
(function of AoA and lift slope)
𝑉𝑇 Horizontal stabiliser volume coefficient
𝐶𝐿, 𝑇 Horizontal stabiliser lift coefficient
Presenter: May Ling Har
47
Payload Descent Stability Control
Strategy Selection and Trade
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Lateral Stability
A simulated approach to evaluating dynamic stability was chosen given the complexity of the system to be solved. XFLR5 was used to predict the lateral stability in all dynamic modes when determining the appropriate size for the vertical fin and degree of dihedral.
Damping of the dutch roll mode is predicted, however the spiral mode diverges slightly over the
descent time.
Presenter: May Ling Har
48
Payload Descent Stability Control
Strategy Selection and Trade
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Option B: Fixed elevon deflection angle
Asymmetric deflection of the elevons on the horizontal stabiliser will induce a rolling moment, leading to a banked turn.
Option A: Fixed rudder deflection angle
A rudder deflection will induce a yawing moment, leading to a change of direction.
Methods to induce the turn
Based on flight dynamic theory, it was determined that two options were available to induce the turn without active control. The vertical fin is required in both cases for directional stability.
Option Advantages Disadvantages
A: Fixed rudder deflection angle • Rate of turn is more constant• A very small deflection angle is needed for the
required 250m radius turn, which would be difficult to set accurately
B: Fixed elevon deflection angle• A much larger deflection angle can be
used to achieve the required 250m radius turn
• The addition of a horizontal stabiliser upon which to mount the elevons is required
• Rate of turn slow at first, before converging to required radius
Presenter: May Ling Har
Option B was selected as the larger deflection angle would be easier to manufacture and adjust during testing.
49
Payload Descent Stability Control
Strategy Selection and Trade
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
The glider’s descent was simulated in the University of Manchester’s Merlin flight simulator to obtain an estimate of the required elevon deflection angle for the turn (approximately 3 degrees).
Further testing will be performed to ensure actual performance matches these results.
Deflected elevon
Presenter: May Ling Har
50
Payload Descent Stability Control
Strategy Selection and Trade
•
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Design Advantages Disadvantages
Spill holeDrifting is decreased and
stability increasedReduce effective size of
parachute
No spill hole Ease of manufacture Reduced stability
A spill hole will be integrated in both parachutes to improve stability. This will be accountedfor in the descent rate calculations.
Spill hole
Presenter: May Ling Har
51
Descent Rate Estimates
Parachute Calculations:
Assumptions made:
1. Weight of falling object is equal to drag when it travels at terminal velocity.
2. Density of air is assumed to be 1.225 kg/m3
3. No wind or air currents.
Using the Drag Equation
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Note that the assumptions and the valuesin this slide will be used in the followingslide throughout the calculations
Presenter: May Ling Har
52
Descent Rate Estimates
Container + Payload Parachute Calculation:
For V=15 m/s For V=25 m/sThe area of the spill hole is chosen tobe equal to 3% of the totalparachute projected area (A⋅103%)
Container Parachute Calculation (After Payload is released):
Science Payload Parachute Calculation (After separation from Container):
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
A diameter of 0.229 m has been chosen as it can easily be purchased (9'')
For V=5 m/s For V=15 m/s
A diameter of 0.457 m has been chosen as it can easily be purchased (18'')
Mass is reduced by 378g (as payload is released from container.Hence only the mass of the container is accounted for
The area of the spill hole is chosen tobe equal to 3% of the totalparachute projected area (A⋅103%)
Presenter: May Ling Har
53
Descent Rate Estimates
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Payload descent
Assumptions made:
• Descent rate is assumed constant
• The turn has a negligible effect on the descent rate
• The initial deployment is not considered
• Small-angle approximations for γGlide ratio γ = atan
1L
D
= 8.7°
Total lift L = mgcos(γ) = 3.5 𝑁
𝐿 =1
2𝜌𝑉2𝑆𝐶𝐿 ⇒ 𝑉 =
2𝐿
𝜌𝑆𝐶𝐿= 28.8 𝑚/𝑠
𝑉𝑠𝑖𝑛𝑘 =𝑉
𝐿𝐷
= 4.4 m/s
Maximum allowed descent speed (Vsink): 350 𝑚𝑒𝑡𝑟𝑒𝑠
60 𝑠𝑒𝑐𝑜𝑛𝑑𝑠= 5.8 𝑚/𝑠
L/D taken at 𝛼Τ = 1.5°(from stability analysis)
L
mgγ
Vsink
D
Presenter: May Ling Har
54
Descent Rate Estimates
Summary
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Container mass 222 g
Payload mass 378 g
Total mass 600 g
Stage 1 Container + Payload
Parachute diameter is 0.229 m
Estimated descent rate is 17.6 m/s
Stage 2A Payload while gliding
Glider wing area is 0.0788 m2
Lift-to-drag ratio is 6.50
Estimated descent rate is 4.4 m/s
Stage 2B Container after Payload release
Estimated descent rate is 10.7 m/s
Stage 3 Payload with parachute deployed
Parachute diameter is 0.457 m
Estimated descent rate is 7.0 m/s
Stage 1 Stage 2A
Stage 2B Stage 3
Presenter: May Ling Har
55
Mechanical Subsystem Design
May Ling Har
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
56
Mechanical Subsystem Overview
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Structural Rods (Carbon fibre)
Container ‘Ribs’(ABS)
Fluorescent pink cover to aid CanSat location
and recovery(PE)
Central Control Unit (CCU) Mechanism
Spool (ABS)
180° Servo
Steel rodsCCU mounting structure (ABS)
305 mm
120 mm
180 mm
Electronic components placement mounts (ABS)
Key Aspects and Materials
Payload with Fluorescent Pink Parachute Deployed
Deflected elevon on tail (ABS)
Container with Fluorescent Pink
Parachute Deployed
Wing ribs (Balsa wood)
Wing structure
(ABS)
PCB
Payload ParachuteBay
Structural Fuselage plates (Foam cored carbon fibre)
Presenter: May Ling Har
String connecting Payload and
Container
57
Mechanical Sub-System
Requirements
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
RE# RequirementVerification
A I T D
1 Total mass of the CanSat (science payload and container) shall be 600 grams +/- 10 grams. X X
2 CanSat shall fit in a cylindrical envelope of 125 mm diameter x 310 mm length. Tolerances are to be included to facilitate container deployment from the rocket fairing.
X X
3 The container shall not have any sharp edges to cause it to get stuck in the rocket payload section which is made of cardboard.
X X X
4 The container shall be a fluorescent color; pink, red or orange. X X
5 The container shall be solid and fully enclose the science payload. Small holes to allow access to turn on the science payload is allowed. The end of the container where the payload deploys may be open.
X X
6 The rocket airframe shall not be used to restrain any deployable parts of the CanSat. X X
7 The rocket airframe shall not be used as part of the CanSat operations. X X
8 The container parachute shall not be enclosed in the container structure. It shall be external and attached to the container so that it opens immediately when deployed from the rocket.
X X X
12 The science payload shall be a delta wing glider. X X X
13 After one minute of gliding, the science payload shall release a parachute to drop the science payload to the ground at 10 meters/second, +/- 5 m/s
X X X
14 All descent control device attachment components shall survive 30 Gs of shock. X X
15 All electronic components shall be enclosed and shielded from the environment with the exception of sensors. X
16 All structures shall be built to survive 15 Gs of launch acceleration. X X
17 All structures shall be built to survive 30 Gs of shock. X X
Presenter: May Ling Har
58
Mechanical Sub-System
Requirements
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
RE# RequirementVerification
A I T D
18 All electronics shall be hard mounted using proper mounts such as standoffs, screws, or high performance adhesives. X
19 All mechanisms shall be capable of maintaining their configuration or states under all forces. X
20 Mechanisms shall not use pyrotechnics or chemicals. X
21 Mechanisms that use heat (e.g., nichrome wire) shall not be exposed to the outside environment to reduce potential risk of setting vegetation on fire.
X X X
30 The Parachutes shall be fluorescent Pink or Orange . X X
38 Cost of the CanSat shall be under $1000. Ground support and analysis tools are not included in the cost. X X
46 Both the container and probe shall be labeled with team contact information including email address. X
48 No lasers allowed. X X
49 The probe must include an easily accessible power switch that can be accessed without disassembling the CanSat and in the stowed configuration.
X X X
54 An easily accessible battery compartment must be included allowing batteries to be installed or removed in less than a minute and not require a total disassembly of the CanSat.
X X X
56 The CANSAT must operate during the environmental tests laid out in Section 3.5. X X
B1 Bonus: A video camera shall be integrated into the science payload and point toward the coordinates provided for the duration of the glide time. Video shall be in color with a minimum resolution of 640x480 pixels and 30 frames per second. The video shall be recorded and retrieved when the science payload is retrieved. Points will be awarded only if the camera can maintain pointing at the provided coordinates for 30 seconds uninterrupted.
X X X
Presenter: May Ling Har
59
Payload Mechanical Layout of
Components Trade & Selection
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
The following page discusses the structure materials for the payload.
Structure Materials
Material Density (kg/m3) Manufacturing Advantages Disadvantages
FuselageStructural
Plates
ABS (3D Printed) 1052 3D Printer Very strongToxic fumes released in manufacture
Foam Cored Carbon Fibre
1280/32 CNC Lightweight, very strongExpensive, difficult to manufacture
Pine Plywood 575 Laser Cutter Very lightweight Low strength
Mounts for electronic
components
PLA (3D Printed) 1430 3D Printer Very strong Heavy
ABS (3D Printed) 1052 3D Printer Very strongToxic fumes released in manufacture
Pine Plywood 575 Laser Cutter Very lightweight Low strength
Wing structure
PLA (3D Printed) 1430 3D Printer Very strong Heavy
ABS (3D Printed) 1052 3D Printer Very strongToxic fumes released in manufacture
Pine Plywood 575 Laser Cutter Very lightweight Low strength
Balsa Wood 170 Laser Cutter Extremely lightweight Low strength
Presenter: May Ling Har
60
Payload Mechanical Layout of
Components Trade & Selection
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
The following page discusses the mechanisms for the payload.
Mechanisms
Material Mass (g) Manufacturing Advantages Disadvantages
PayloadRelease
Solenoid 12.6 Off the shelf Reliable, high performance Short travel range, heavy
Servo with string 9 Off the shelfReliable, able to control in small steps
Large space required, larger battery required
Nichrome wire with string TBD Off the shelfReduces need for actuating, lightweight
Needs to be insulated, not as reliable as mechanical methods
Wing Deployment
Solenoid 12.6 Off the shelf Reliable, high performance Short travel range, heavy
Servo with string 9 Off the shelfReliable, able to control in small steps
Large space required, larger battery required
Nichrome wire with string TBD Off the shelfReduces need for actuating, lightweight
Needs to be insulated, not as reliable as mechanical methods
Torsion springs 2 Off the shelf Reliable, space efficientNeeds to be replaced after a number of test iterations due to fatigue
PayloadParachute
Deployment
Solenoid 12.6 Off the shelf Reliable, high performance Short travel range, heavy
Servo with string 9 Off the shelfReliable, able to control in small steps
Large space required, larger battery required
Nichrome wire with string TBD Off the shelfReduces need for actuating, lightweight
Needs to be insulated, not as reliable as mechanical methods
Presenter: May Ling Har
61
Payload Mechanical Layout of
Components Trade & Selection
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Chosen Structure Materials
Material Rationale
Fuselage structural
platesFoam Cored Carbon Fibre High strength and lightweight. Team members have experience in the manufacture.
Mounts for electronic
componentsABS (3D Printed) High strength and stiffness. Easy to remodel and manufacture.
Wing Structure
ABS (3D Printed) High strength and stiffness. Easy to remodel and manufacture.
Balsa Wood Extremely lightweight, sufficient strength for its purpose. Fast and easy to manufacture.
The following page summarizes the chosen materials and mechanisms to be used in the Payload.
Chosen Structure Materials
Method Rationale
Payload Release
Servo with string (CCU) High reliability of servo. Thoroughly tested in previous Competitions and test launches.
WingDeployment
Servo with string (CCU) High reliability of servo. Thoroughly tested in previous Competitions and test launches.
Torsion springs High reliability and space efficiency.
Payload Parachute
DeploymentServo with string (CCU) High reliability of servo. Thoroughly tested in previous Competitions and test launches.
Presenter: May Ling Har
62
Payload Mechanical Layout of
Components Trade & Selection
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
The four following pages discuss the first method conceptualized for the mechanical layout of the payload.
CONCEPT 1 (Chosen)
Rocket bodytube
Fluorescent Pink Container
Cover (PE)
Transparent payload cover
(PE)
Structural Fuselage plates (Foam cored carbon fibre)
Electronic components placement mounts (ABS)
String attaching Payload to Container String attaching Wing rib to
Fuselage
Presenter: May Ling Har
63
Payload Mechanical Layout of
Components Trade & Selection
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
CONCEPT 1 (Chosen)
‘X’ wing structure (ABS)
Balsa Ribs
Spool (ABS)
Central Control Unit (CCU) Mechanism
180° Servo
Steel rods
CCU mounting structure (ABS)
Slightly deflected elevon (ABS)
Tail (ABS)
Torsion springs Fluorescent Pink wing skin (ripstop nylon)
Presenter: May Ling Har
64
Payload Mechanical Layout of
Components Trade & Selection
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
CONCEPT 1 (Chosen)
Stacked PCBs for mounted electronics
Pitot tube
GPS
Particulate sensor
Battery
SwitchPCBsCamera
Buzzer
FPVDVR Hinged Parachute Bay
Lid (ABS)
Teensy 4.0
IMU (underneath Teensy 4.0)
BMP388
ADUXBEE
Transparent vacuum formed
PE structureHeaders
Folded Fluorescent Pink Parachute (Ripstop nylon)
Presenter: May Ling Har
65
Payload Mechanical Layout of
Components Trade & Selection
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
CONCEPT 1 (Chosen)Key Features:• ‘X’ wing structure for folding, aided by
torsion springs and string connected to a spool
• Camera with 360° continuous rotation and 90° pitch.
• Central Control Unit (CCU) mechanism for Payload Release, Payload Wings Deployment, and Payload Parachute Deployment.
• Deflected elevon on T-tail.• Airfoil-shaped fuselage with transparent
dome for camera mechanism.
Advantages:• Larger wingspan achieved.• Higher wing structural integrity.
Disadvantages:• Difficult to manufacture and integrate.• Less space efficient.
Camera
Slip ring to avoid wire entanglement
Motor for 360°
continuous rotationBevel gears (off the shelf)
Servo for 90° pitch
Mounts (ABS)Structural plate (plywood)
Presenter: May Ling Har
66
Payload Mechanical Layout of
Components Trade & Selection
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
The four following slides discuss the second method conceptualized for the mechanical layout of the payload.
CONCEPT 2
Rocket bodytube
Fluorescent Pink Container
Cover(Fibreglass)
Parachute Bay Lid (Plywood)
Structural Plates (Plywood)
Structural Plate (Acrylic) Nylon Spacers for
structural purposes
Parachute Bay Lid Hinge
Transparent payload cover
(PE) 153 mm
Presenter: May Ling Har
67
Payload Mechanical Layout of
Components Trade & Selection
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Carbon Fibre plates
Plywood guide for rudder deflection
Carbon Fibre rods
Fluorescent Pink wing skin (ripstop nylon)
Carbon Fibre ribs
Wing spar (Plywood)
Torsion spring for wing
deployment
Boxes (ABS) to contain NichromeWire Deployment Mechanism
NichromeWires
CONCEPT 2
Presenter: May Ling Har
68
Payload Mechanical Layout of
Components Trade & Selection
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Pitot tubeFolded Fluorescent Pink
Parachute (Ripstop nylon)GPS
Particulate sensor
Battery Switch PCBCamera
CONCEPT 2
ADU
Stacked PCBs for mounted electronics
XBEE
Buzzer
FPVDVR
Teensy 4.0
IMU (underneath Teensy 4.0)
BMP388
Headers
Presenter: May Ling Har
69
Payload Mechanical Layout of
Components Trade & Selection
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
CONCEPT 2
Slip ring to avoid wire entanglement Stepper motor for 360°
continuous rotation
3D printed gears (ABS)
Servo for 90° pitch
Camera
Key Features:• Wings folded and deployed using
torsion springs.• Camera with 360° continuous rotation
and 90° pitch.• Nichrome wire mechanism for Payload
Release and Payload Parachute Deployment.
• Deflected rudder on tail.
Advantages:• Easier manufacture and integration.• Space efficient.
Disadvantages:• Difficult prediction of glider
performance.• Lower wing structural integrity.
Presenter: May Ling Har
70
Payload Mechanical Layout of
Components Trade & Selection
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Concept 1 Concept 2
Difficult manufacture and assembly Shorter manufacture and assembly times
Higher predictability of performance, more aerodynamic
Low predictability of performance, less aerodynamic
Deflected elevon on T-tail to ensure circular descent pattern
Deflected rudder on tail to ensure circular descent
Off the shelf gears used for camera mechanism 3D printed ABS gears used for camera mechanism
Higher wing structural integrity due to ‘X’ wing spar Less wing structural integrity
CHOSEN CONCEPT RATIONALE
Concept 1While Concept 1 is more difficult to manufacture and assembly, it has higher predictability and stability. A larger wingspan can also be achieved with Concept 1.
Presenter: May Ling Har
71
Payload Pre Deployment
Configuration Trade & Selection
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
The following three slides discuss the two methods conceptualized for the Payload pre-deployment configuration.
Design 1:
Stowed Payload in Container: Servo + String (CCU)• The Payload is held inside the
Container with string, secured to the Payload by the CCU servo. The Payload will not be released from the Container until the first rod in the CCU is retracted so that the Payload is free to fall from the Container.
Stowed Wings: Torsion springs + Spool + String (CCU)How it works:• Payload wings are kept in stowed
configuration using torsion springs that connect the wing spar to the Fuselage structure, and string connecting to the first wing rib is wound around the spool which is held stationary by a servo arm attachment on the CCU servo. This enables the wings to remain stowed until the Payload is fully released from the Container.
String attaching Payload to Container
Payload-Container String is connected to
this slot
Servo
CCU Mechanism: Before Payload is released
Rod
Torsion spring CCU Mechanism
Spool
String from Wing rib
Wing rib string connecting to Spool
Presenter: May Ling Har
72
Payload Pre Deployment
Configuration Trade & Selection
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Stowed Payload in Container: Nichrome wire + String• Payload is held inside the
Container through the use of string. When the Payload is ready to be released, the Nichrome wire is heated to the string’s melting point. The string will melt and the Payload will be free to fall from the container. The Payload will not be released until the wire is heated and the string melts, which is controlled by the FSW.
Nichrome wires
ABS Casing
Stowed Wings: Torsion springs• Payload wings are kept in stowed
configuration using torsion springs that connect the wing spar to the Fuselage structure. This enables the wings to stay stowed until the Payload is fully released from the Container. Torsion spring connecting wing
spar to fuselage structure
Design 2:String attaching Payload
to Container
Stowed Wing
Presenter: May Ling Har
73
Payload Pre Deployment
Configuration Trade & Selection
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Design 1 was chosen because of its higher reliability with the CCU, as it has been tested thoroughly in previous Competitions and test launches. Furthermore, the additional string connecting to the first rib and
wound around a spool ensures that the wings will remain in stowed configuration.
Design 1: Servo and String (CCU) Design 2: Nichrome wire and String
Can be controlled in small steps Relies on strength of both Nichrome wire and string
Difficult to set up Difficult to set up
Reusable Needs to be replaced for every test
Larger space and more powerful battery required Extra wiring may be needed to keep payload in Container
Method to keep Payload Stowed in Container: Key Trade Issues
Design 1: Torsion springs, Spool and String (CCU) Design 2: Torsion springs
Wings kept in stowed configuration with torsion springs and with string connecting spool and wing rib
Wings kept in stowed configuration with only torsion springs
Difficult to set up Wing tips in contact with Container walls
Method to keep Wings Stowed: Key Trade Issues
Presenter: May Ling Har
74
Payload Deployment
Configuration Trade & Selection
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
The following three slides discuss the two methods conceptualized for the Payload’s transition from stowed to deployed configuration.
Design 1:
Releasing Payload from Container: Servo + String (CCU)• The Payload is held inside the Container with
string, secured to the Payload by the CCU servo. Once the CanSat reaches 450 m altitude, the servo is actuated by the FSW and rotates, moving the first rod in the CCU. The string is no longer secured by the pin, and the Payload is no longer held inside the Container by the string, allowing it to fall from the Container.
Deploying Payload Wings: Torsion springs + Spool + String (CCU)• Payload wings are kept in stowed configuration
using torsion springs that connect the wing spar to the Fuselage structure, and string connecting to the first wing rib is wound around the Spool which is held stationary by the servo arm attachment on the CCU servo. After the Payload is fully released from the Container, the servo is actuated and moves the arm, allowing the spool to spin freely due to tension release in the torsion springs. The string is then unwound by the rotation of the spool and the wings unfold with the aid of torsion springs.
CCU Mechanism: Releasing Payload and Deploying Payload Wings
CCU Rod no longer holding string to Container
Spool allowed to spin, unwinds string to Wing rib
Torsion springs unfolds wings
Presenter: May Ling Har
Nichrome wires
ABS Casing
75
Payload Deployment
Configuration Trade & Selection
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Design 2:
Releasing Payload from Container: Nichrome Wire• Payload is held inside the Container through
the use of string. When the Payload is ready to be released, the Nichrome wire is heated to the string’s melting point. The string will melt and the Payload will be free to fall from the container. The Payload will not be released until the wire is heated and the string melts, which is controlled by the FSW.
Deploying Payload Wings: Torsion springs• Payload wings are kept in stowed configuration
using torsion springs that connect the wing spar to the Container structure. This enables the wings to transition into deployed configuration when the Payload is fully released from the Container.
Torsion springs connecting wing spar to fuselage structure
Wings in deployed configuration via torsion springs
Presenter: May Ling Har
76
Payload Deployment
Configuration Trade & Selection
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Design 1: Servo and String (CCU) Design 2: Nichrome wire and String
Difficult to set up Difficult to set up
Reusable Needs to be replaced for every test
Can be used to perform other operations Multiple modules needed for multiple operations
Larger space and more powerful battery required Extra wiring may be needed to keep payload in Container
Method to release Payload from Container: Key Trade Issues
Design 1: Torsion springs, Spool and String (CCU) Design 2: Torsion springs
Wings allowed to transition from stowed to deploy state only when spool is allowed to rotate, and torsion springs unfold wings
Wings kept in stowed configuration with only torsion springs
Difficult to set upWing tips in contact with Container walls may lead to additional friction
Method to deploy Payload Wings: Key Trade Issues
Design 1 was chosen because of its higher reliability with the CCU, as it has been tested thoroughly in previous Competitions and test launches. Furthermore, the additional string connecting to the first rib and wound around a spool ensures that the wing tips are not in contact with the Container walls, allowing the
Payload to slide out of the Container with ease.
Presenter: May Ling Har
77
Container Mechanical Layout of
Components Trade & Selection
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Structure Materials
Material Density (kg/m3) Manufacturing Advantages Disadvantages
Parachute attachment
plate
ABS (3D Printed) 1052 3D Printer Very strongToxic fumes released in manufacture
Carbon Fibre (Plate) 1280 CNC Lightweight, very strong Expensive
Pine Plywood 575 Laser Cutter Extremely lightweight Low strength
Main Structural
Parts
PLA (3D Printed) 1430 3D Printer Very strong Heavy
ABS (3D Printed) 1052 3D Printer Very strongToxic fumes released in manufacture
Fiberglass 1522 CNC Very strongHard to machine, heavy
Carbon Fibre (Rods) 1280Cutting to Size
(Dremel)Lightweight, very strong
Brittle, weak under compression
The following page discusses the structure materials for the Container.
Presenter: May Ling Har
78
Container Mechanical Layout of
Components Trade & Selection
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Chosen Structure Materials
Method Rationale
Parachute attachment
plateABS (3D Printed)
High strength, tested in 2019 Competition and various drop tests, has shown to be capable of withstanding very high loads. Easy to remodel and manufacture.
Main Structural
Parts
ABS (3D Printed)High strength, stiff enough for its purpose of ensuring structural integrity of the Container. Easy to remodel and manufacture.
Carbon Fibre (Rods) High strength and stiffness with very little weight. Easy to acquire and manufacture.
The following page summarizes the chosen materials to be used in the Container.
Presenter: May Ling Har
The following page discusses the first conceptual design for the mechanical layout of the Container.
CONCEPT 1 (chosen)
79
Container Mechanical Layout of
Components Trade & Selection
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Parachute plate (ABS)
Structural Rods (Carbon fibre)
Container ‘Ribs’(ABS)
Holes for Parachute string
Holes for string connecting
Payload and Container
Fluorescent pink cover to aid CanSat
location and recovery(PE)
300 mm
5 mm
120 mm
Parachute Bay
Payload Bay (ABS, carbon
fibre rods)
Fluorescent Pink Parachute (Ripstop Nylon)
Presenter: May Ling Har
80
Container Mechanical Layout of
Components Trade & Selection
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
The following page discusses the second conceptual design for the mechanical layout of the Container.
CONCEPT 2
Holes for Parachute string
Fluorescent pink Container Body to aid CanSat location and recovery (Fiberglass)
Holes for string connecting
Payload and Container
Parachute Bay
Fluorescent Pink Parachute (Ripstop Nylon)
Payload Bay (Fibreglass) 290 mm
5 mm
120 mm
Presenter: May Ling Har
81
Container Mechanical Layout of
Components Trade & Selection
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Concept 1 Concept 2
Longer manufacture and assembly timesShorter manufacture times (can be provided by sponsor)
Combination of Carbon Fibre rods and 3D printed ABS for Container structure
Fiberglass for Container body
Lightweight Heavy
CHOSEN CONCEPT RATIONALE
Concept 1While Concept 1 takes longer to manufacture, it consists of less mass and allows for easier access to the Payload.
Presenter: May Ling Har
82
Payload Release Mechanism
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
The following page discusses the mechanism conceptualized for the release of the Payload from the Container.
Central Control Unit (CCU)
The Central Control Unit (CCU) is designed such that Payload Release, Wing Deployment, and Payload Parachute Deployment can be actuated from a single location with a servo. The first operation performed by the CCU servo will be to release the Payload from the Container.
Sequence of Events:1. The CCU Servo is sent a signal determined by altitude to actuate Payload Release.2. The CCU Servo rotates, and retracts the rod by a specific margin and releases the string from
the CCU. 3. Once the string is no longer attached to the CCU, the Payload is free to fall from the Container.4. When the Payload is fully separated from the Container, the CCU Servo rotates again, and
raises the CCU arm.5. The spool spins and unwinds the string connecting to the wing ribs, allowing the wings to
deploy.
String connecting
Payload and
Container
Presenter: May Ling Har
String connecting Wings and
CCU
Container Parachute Attachment
Mechanism
83CanSat 2020 PDR: Team 4920 Manchester CanSat Project
The following page discusses the Container Parachute Attachment mechanism.
The Container Parachute is attached to the Container via string and a swivel pin. It will not be enclosed by the Container structure to ensure deployment after the CanSat is released from the rocket.
In Launch Configuration, the Parachute will be folded such that it will deploy effectively after CanSat release from the rocket, and that it will not cause the CanSatdimensions to exceed the given dimensional constraints.
After the CanSat is released from the rocket, air flow will cause the Parachute to deploy and slow the descent rate of the CanSat to 20 m/s. The swivel pin will prevent the Parachute strings from tangling, thus preventing Parachute collapse as this was found to be an issue in the 2019 Competition.
After the Payload is released from the Container, the Container will continue to descend separately with its Parachute.
Fluorescent pink Parachute
Fluorescent pink Container
Container Parachute
attachment point
Presenter: May Ling Har
Electronics Structural Integrity
84CanSat 2020 PDR: Team 4920 Manchester CanSat Project
The following two slides discuss the electronics structural integrity of the CanSat.
Selection of the method for hard-mounting the electronics was constrained by RE18, which states that:
‘All electronics shall be hard mounted using proper mounts such as standoffs, screws, or high performance adhesives.’
Payload Electronics Mounting Methods
Method Advantages Disadvantages
Screws Very secure, strong Non-reusable, additional mass
Standoffs Variable in sizes Additional mass
Bolts & Nuts Variable in sizes, can detach if needed Additional mass
High performance adhesives Lightweight, very secure Permanent
Gorilla Tape Lightweight, easy to apply Can become easily detached
Velcro Easy to apply/remove, lightweight Can become easily detached
PCBAll-in-one, ease of integration, less likelihood of
short-circuitingRequires manufacture
Electronic Equipment Enclosure Methods
Method Advantages Disadvantages
EPS Foam Good shock absorption Difficult to mould and allow access to electronics.
Carbon Fibre Very strong Difficult to manufacture
Plastic Cover Very light, easily shapedDifficult to secure, would require unscrewing for
access
3D Printed ABS Strong, easy to produce Heavy if high infill
Presenter: May Ling Har
Electronics Structural Integrity
85CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Descent Control Attachment Methods
Part Method Justification
Parachutes Swivel & StringSwivel used to secure parachute strings to container such that the parachute strings do not twist, leading to parachute collapse.
CCU
3D Printed ABS Housing Holds servo and rods in place.
3D Printed ABS Spool systemStrings connecting to the first wing ribs are wound around the spool. When the servo moves, the spool is allowed to spin and the wings deploy.
Adhesive Secures rod to servo head.
Washer & String Rod secures the washer until the servo moves and releases the strings.
Securing Electrical Connections Selection
Method Justification
Cable ties Cheap, ease of use, non-permanent.
Epoxy High dielectric strength, very good thermal conduction.
The CCU will be made out of an ABS casing that will hold the servo in place. The servo controls the linear movement of a metal rod thatwill release the load on the spool, allowing the spool to spin due to tension release in the torsion springs, and thus the glider’s wingsunfold and deploy.
A PCB and high performance adhesives will be used for the attachment methods as it provides a strong bond against extreme vibrations.
A plastic cover was chosen to cover the electronics in the payload as it is lightweight and does not need to be structurally supporting anycomponents/parts. It is also easy to remove and replace when replacing the battery.
Epoxy is to be used for securing electrical attachments. Epoxy would be used for cases where the wires are better suited to beingsecured permanently. Otherwise, they will be left to be loose to make remedial actions easier.
Presenter: May Ling Har
86
Mass Budget
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Container Mass Breakdown
Subsystem Component Mass (g) Justification
ME/DCS
Structural Carbon Fibre Rods (x6) 10.03 Datasheet
Container Cover (PE) 5.00 Estimated
Parachute (Ripstop Nylon) 3.45 Datasheet
3D Printed Parts (ABS)
Container ‘Ribs’ (x3) 28.50 Datasheet
Container top plate 90.32 Datasheet
Container bottom rib 15.10 Datasheet
String 3.00 Estimated
M3x10 bolt (x12) 5.52 Datasheet
Total 160.92 g
Presenter: May Ling Har
87
Mass Budget
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Payload – Electronics Mass Breakdown (1/2)
Subsystem Component Mass (g) Justification
EPS PCB Core (no headers) 3.27 Measured
SE GPS 4.30 Measured
EPS Battery 15.45 Measured
CDH Buzzer 1.40 Measured
SE Camera 3.20 Measured
ME Motor 11.61 Measured
ME Servo 10.48 Measured
SE Pitot tube 7.78 Measured
SE PM sensor 15.17 Measured
EPS Switch 2.70 Measured
ME Slip Ring 10.00 Measured
CDH/SE/FSW Teensy 4.80 Measured
Presenter: May Ling Har
88
Mass Budget
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Payload – Electronics Mass Breakdown (2/2)
Subsystem Component Mass (g) Justification
CDH XBee 3.68 Measured
EPS PCB add on 4.43 Measured
SE/CDH FPVDVR 8.70 Measured
EPS Headers 6.00 Measured
EPS Wiring 5.00 Measured
Total 117.97 g
Presenter: May Ling Har
89
Mass Budget
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Payload – Structure Mass Breakdown (1/3)
Subsystem Component Mass (g) Justification
ME/DCS
3D printed ABS
X frame arms 48.00 Datasheet
Fuselage – X frame attachment 22.70 Datasheet
GPS mount 3.21 Datasheet
Roof scoop 3.42 Datasheet
Buzzer mount 6.49 Datasheet
PCB mount 3.48 Datasheet
CCU housing + spool 12.30 Datasheet
Camera mechanism mount 7.70 Datasheet
Tail 21.70 Datasheet
Parachute bay 17.10 Datasheet
1mm CFRP Fuselage airfoil (x4) 22.70 Datasheet
3mm Rohacell foam Fuselage airfoil (x2) 0.55 Datasheet
Laser cut BalsaWing ribs (x4) 3.00 Datasheet
Camera mechanism mount 0.63 Datasheet
Presenter: May Ling Har
90
Mass Budget
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Payload – Structure Mass Breakdown (2/3)
Subsystem Component Mass (g) Justification
ME/DCS
Torsion spring (x2) 2.05 Datasheet
Motor bevel gear 1.87 Datasheet
Servo bevel gear 6.26 Datasheet
Kevlar string 0.50 Estimated
Ripstop nylon (glider cover) 5.90 Estimated
PETG sheet (camera bubble) 7.10 Estimated
M3x10 bolt (x4) 1.84 Datasheet
M3 nut (x4) 1.27 Datasheet
M2.5x6 bolt (x3) 1.23 Datasheet
M2.5 nut (x3) 0.97 Datasheet
M2x12 bolt (x12) 6.48 Datasheet
Presenter: May Ling Har
91
Mass Budget
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Payload – Structure Mass Breakdown (3/3)
Subsystem Component Mass (g) Justification
ME/DCS
M2 nuts (x12) 4.10 Datasheet
M1.6x10 bolts (x8) 6.11 Datasheet
M1.6 nuts (x8) 5.21 Datasheet
2mm dia. Steel shaft (CCU, Ribs)
3.00 Estimated
3mm dia. Steel shaft (fuselage attachment, parachute bay)
5.26 Estimated
Glue 8.00 Estimated
Parachute 20.00 Datasheet
Total 260.13 g
Presenter: May Ling Har
92
Mass Budget
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
TOTAL BUDGET
System Mass (g)
Container 160.92
Payload (Electronics + Structure)
378.10
Payload + Container 539.02
Mass Margin
Mass (g) Available mass (g) Margin (g)
539.02 600 ±10 60.98 ± 10
Currently, the mass is below the mass budget requirement at 539.02 g. Once the first prototype has been fully assembled, the team will assess where mass can be added so that it will meet the required mass budget.
A source of uncertainty is that each prototype assembled by the team will have varied masses due to different lengths of wires and strings. Another source of uncertainty is the use of high performance adhesives in the assembly of prototypes. As the CanSat will be assembled by hand, the amount of adhesive used will vary between prototypes, and thus the mass of the prototypes will vary.
To increase the mass of the CanSat, ballast will be added to the Payload to ensure that the Payload is aerodynamically stable. Ballast can also be added to the Container to ensure that the design is compliant with the mass budget requirement. The team will also replace certain structural materials with materials that are heavier yet stronger (such as replacing balsa wood with plywood). The thickness of structural elements and infill percentages of 3D printed components can also be increased. Furthermore, additional adhesive can be applied. This will increase the structural strength and integrity of the CanSat.
Presenter: May Ling Har
93
Communication and Data Handling
(CDH) Subsystem Design
May Ling Har
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
CanSat 2019 PDR: Team 4999 Manchester CanSat Project 94
Payload CDH Overview
Presenter: May Ling Har
MCU
EEPROMFlash
RTC
Analogue input
IMU, Barometer,
ADU
I2C
GPSSerial
Particle sensor
Analog input
SD card
RadioSerial
AntennaCoax
GCS
Serial
CameraVideo
recorder
Buzzer,Motor,Servos
Digital output
Digital output
Component FunctionTeensy 4.0 internal RTC
RTC
Teensy 4.0 Microcontroller (MCU)ICM-20948 9 –axis IMU8 GB SD card For local data storageXBee Pro 900HP RadioTaoglas FXP290 915 MHz
Antenna
NEO M8N GPS Radio And Antenna
BMP 388Pressure and temperature measure
GP2Y1014AU0FParticles in air measurement
4525DOADU – for differential pressure
95
Payload CDH Requirements
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
RE# DescriptionVerification
A I T D
1 Total mass of the CanSat (science payload and Container) shall be 600 grams +/- 10 grams. X X
2CanSat shall fit in a cylindrical envelope of 125 mm diameter x 310 mm length. Tolerances are to be included therocket fairing.
X X
15 All electronic components shall be enclosed and shielded from the environment with the exception of sensors. X
18All electronics shall be hard mounted using proper mounts such as standoffs, screws, or high performanceadhesives.
X
22 The science payload shall measure altitude using an air pressure sensor. X X X X23 The science payload shall provide position using GPS. X X X X24 The science payload shall measure its battery voltage. X X X X25 The science payload shall measure outside temperature. X X X X26 The science payload shall measure particulates in the air as it glides. X X X X27 The science payload shall measure air speed. X X X X28 The Science Probe shall transmit all sensor data in the telemetry X X X X
29 Telemetry shall be updated once per second. X X X
31 The ground system shall command the science vehicle to start transmitting telemetry prior to launch. X X X
33Telemetry shall include mission time with one second or better resolution. Mission time shall be maintained in theevent of a processor reset during the launch and mission
X X X
34Configuration states such as if commanded to transmit telemetry shall be maintained in the event of a processorreset during launch and mission.
X X X
35XBEE radios shall be used for telemetry. 2.4 GHz Series radios are allowed. 900 MHz XBEE Pro radios are alsoallowed.
X
36 XBEE radios shall have their NETID/PANID set to their team number. X X X
37 XBEE radios shall not use broadcast mode. X X
38 Cost of the CanSat shall be under $1000. Ground support and analysis tools are not included in the cost. X X
39 Each team shall develop their own ground station X
Presenter: May Ling Har
96
Payload CDH Requirements
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
RE# DescriptionVerification
A I T D
42 Teams shall plot each telemetry data field in real time during flight. X X
44The ground station shall include one laptop computer with a minimum of two hours of battery operation, XBEEradio and a hand-held antenna.
X
Presenter: May Ling Har
Payload Processor & Memory
Trade & Selection
97
Memory Storage Requirements:
• 1 kB of non-volatile memory is needed at least- For maintaining mission time and packet count In case of a processor restart
• 32 kB of program storage (flash) memory is needed at least. From previous years’ experience 32kB is the minimum required. The chosen microcontroller has 64 times thatamount. Additional program storage capacity allows for greater flexibility.
• An additional 8 GB non-volatile memory for telemetry data needed- External SD card reader
• A non-volatile memory solution for video storage is required- A video recorder with a SD card
Presenter: May Ling Har CanSat 2020 PDR: Team 4920 Manchester CanSat Project
98
Payload Processor & Memory
Trade & Selection
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Micro-controller
Processor Speed (MHz)
Data Interfaces
Non-Volatile Memory (kB)
Volatile Memory
(kB)
Current (mA)
Size (mm)Mass
(g)Cost (£)
Flash EEPROM
ArduinoNano
161x UART1x SPI1x I2C
32 12
SRAM19
@ 5 V43 x 19 7 16.87
Teensy 4.0 6007x UART3x I2C3x SPI
2048 641024RAM
100@ 5 V
36 x 18 4.8 15.26
Teensy 3.2 24-96 (OC)3x UART2x I2C1x SPI
256 264
RAM
32@ 5 V
(72MHz)36 x 18 4.8 15.14
Microcontroller Boot Time (s)
Arduino Nano 1.46
Teensy 3.2 1.09
Teensy 4.0 1
• Boot time information is not obtainable online, that is why itwas measured experimentally. The table on the right showsthe boot time of the three compared microcontrollers.
• This was achieved by having a program that sets a port highas soon as the device turns on. The device was then reset andthe time from the reset pin going high to the output goinghigh is the result. This was repeated 20 times for an averagemeasurement.
Presenter: May Ling Har
Payload Processor & Memory
Trade & Selection
99
Chosen Microcontroller Board
Rationale
Teensy 4.0 Microcontroller
• The fastest processing speed. Power consumption changes if device is underclocked or overclocked
• It is as light as Teensy 3.2 and lighter than most microcontrollers• Smallest form factor• Outstanding flash storage for complex programs• High RAM value• Previous team experience will accelerate integration• High number of Data interfaces• Compatible with Arduino IDE, speeding up the software development process• Cheap
Teensy 4.0 MC GPIO Pins Digital IO PWM Pins Analog Inputs Analog Output
Pin Number 40 40 ( All interrupt capable ) 31 14 0
Note: Teensy 4.0 not having a DAC is not a problem as it will not be needed for the given project.
Presenter: May Ling Har CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Payload Real-Time Clock
100CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Name AccuracyActive Supply Current (µA)
InterfaceOperating
voltageHardware/Software Cost (£)
Teensy 4.0internal lowspeed clock
50 ppm 26 Internal to CPU 3.3 V Hardware
Free ( It comes
with the Teensy)
DS3231 3.5 ppm 300 I2C 3.3 V Hardware 1.84
Chosen RTC Rationale
Teensy 4.0 RTC
• Lower supply current• Does not require additional circuitry• Comes as part of the MCU• Does not add extra weight or occupy extra are since its already on the board
A hardware RTC will be used. At mission start, the time will be recorded and saved to the EEPROM on the MCU. Inthe event of a processor reset, the mission start time in EEPROM will be used as a reference. The Teensy 4.0 RTCwill have an additional battery, so whenever the microcontroller resets or stops working, it will continue to operate.On the other hand, when the Teensy is on, the RTC will be powered by it.
Presenter: May Ling Har
101
Payload Antenna Trade & Selection
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Chosen Antenna Rationale
Taoglas FXP290 915 MHz
• Can be placed near the outside of the payload• Best gain pattern• No extra circuitry needed• Lighter when extra PCB area is accounted for
Antenna Connector Gain (dBi) VSWR Range (m) Mass (g) Size (mm) Polarization Cost (£)
Taoglas FXP290 915 MHz
MHFII (U.FL compatible)
1.5 < 2:1 11646* 1.5 75 x 45 Linear 14.29
Abracon ACAG1204-915-T 915 MHz
Surface Mount 3.42 <2:1 5202** 0.452* 12 x 4 x 1.6 Linear 1.22
* Needs PCB based circuit of 50mm x 90mm adding an additional 12 grams. ** Range estimated based on the Friis transmission equation with a -20 dBm link margin and non-optimal projection angle.
Presenter: May Ling Har
Payload Antenna Trade & Selection
102
On this slide, the antenna patterns are shown. The plots were taken from the antenna datasheet. Patterns provided in the top row are for Taoglas FXP290 915 MHz (chosen). Patterns provided in the bottom row are for Abracon ACAG1204-915-T 915 MHz.
Radiation pattern XZ planeRadiation pattern YZ plane Radiation pattern XY plane
Presenter: May Ling Har CanSat 2020 PDR: Team 4920 Manchester CanSat Project
103
Payload Radio Configuration
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Chosen Radio Rationale
Xbee-Pro 900HP
• High Range• High Transmit power• Best RX sensitivity• Previous Experience
NETID/PANID will be 4920.
Tranmission is going to be handled by the FSW. GCS to payload transmission will start on power on and stop on touchdown. Data will be transmitted every 1 s ( frequency of 1 Hz) back to the GCS. Additionally, it will be saved locally to non-volatile memory. This will be burst transmission. The XBEE will use direct addressing, not broadcasting.
NameOperating Frequency (MHz)
Ant. Conn. Type
TX Current
(mA)
RX Current
(mA)
Tx Power (dBm)
Rx Sensitivity (dBm)
LOS Range (km)
Mass (g)Dimensions (mm)
Cost (£)
Xbee-Pro 900HP
915U.FL or
RPSMSA215
@3.3V29
@3.3V+24 -101 15.5 42 32 x 22 41.66
Xbee-Pro S2C
2400U.FL or
RPSMSA120
@3.3V31
@3.3V+18 -101 3.2 40 24 x 33 30.46
Xbee -S2C
2400U.FL or
RPSMSA33
@3.3V28
@3.3V+5 -100 1.2 40 24 x 28 20.24
Presenter: May Ling Har
104
Payload Telemetry Format
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Frame ID Description Example Value
<TEAM ID> Unique assigned Team ID 4920
<MISSION TIME> Time since power up of the payload in seconds 280
<PACKET COUNT> number of transmitted packets which will be maintained even in the event of processor reset 59
<ALTITUDE> altitude relative to ground level. Resolution 0.1m 103.3
<PRESSURE> Atmospheric pressure in pascals. Resolution 0.1Pa 101358.5
<TEMP> Measured temperature in degrees C. Resolution 0.1 degrees C 26.6
<VOLTAGE> Voltage of CanSat power bus. Resolution 0.01V 5.02
<GPS TIME> Time reported by GPS receiver, UTC time zone in seconds 12:38:47
<GPS LATITUDE> Latitude reported by GPS receiver in decimal degrees. Resolution 0.0001 degrees 53.4851
<GPS LONGITUDE> Longitude reported by GPS receiver in decimal degrees. Resolution 0.0001 degrees -2.2748
<GPS ALTITUDE> Altitude reported by GPS receiver in meters above mean sea level. Resolution 0.1m 103.3
<GPS SATS> Number of GPS satellites being tracked, as reported by the GPS receiver. Integer number 5
<AIR SPEED> The airspeed relative to the payload in meters/second 20.4
<SOFTWARE STATE> Operating state of software. States include boot, idle, launch detection, deployed, landed 0 (idle)
<PARTICLE COUNT> Decimal value showing the measured particle count in mg/m^3 0.025
• Full Packet Makeup = <TEAM ID>,<MISSION TIME>,<PACKET COUNT>,<ALTITUDE>, <PRESSURE>,<TEMP>,<VOLTAGE>,<GPS TIME>,<GPS LATITUDE>,<GPS LONGITUDE>,<GPS ALTITUDE>,<GPS SATS>,<AIR SPEED>,<SOFTWARE STATE>,<PARTICLE COUNT>
• Packet will be ASCII comma delimited format• Transmission will be burst and occur every 1 sec• Example packet:
4920,280,59,103.3,101358.5,26.6,5.02,12:38:47,53.4851,-2.2748,103.3,5,20.4,IDLE,0.025
Transmission format
Presenter: May Ling Har
105
Payload Telemetry Format
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Frame ID Description Example Value
<TEAM ID> Unique assigned team ID 4920
<TX START> Transmission trigger 1
Receiving format
• Full Packet Makeup = <TEAM ID>,<TX START>
• Packet will be ASCII comma delimited format.
• When its idle,The Payload will be waiting for these commands from the GCS. Afterwards, it will no longer be listening.
• Example packet:4920, 1
• Transmission of the TX start packet will only occur once.
Presenter: May Ling Har
106
Container CDH Overview
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
There will be no electronics in the Container.
The Payload will contain all electronics associated with Payloaddeployment and Payload parachute deployment
Presenter: May Ling Har
107
Container CDH Requirements
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
RE# DescriptionVerification
A I T D
1 Total mass of the CanSat (science payload and Container) shall be 600 grams +/- 10 grams. X X
2CanSat shall fit in a cylindrical envelope of 125 mm diameter x 310 mm length. Tolerances are to beincluded the rocket fairing. to facilitate Container deployment from
X X
3The Container shall not have any sharp edges to cause it to get stuck in the rocket payload section whichis made of cardboard.
X X X
4 The Container shall be a fluorescent color; pink, red or orange. X X
10 The Container shall release the payload at 450 meters +/- 10 meters. X X X
15All electronic components shall be enclosed and shielded from the environment with the exception ofsensors.
X
18All electronics shall be hard mounted using proper mounts such as standoffs, screws, or highperformance adhesives.
X
38 Cost of the CanSat shall be under $1000. Ground support and analysis tools are not included in the cost. X X
Presenter: May Ling Har
Container Processor & Memory
Trade & Selection
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Micro-controller
Processor Speed (MHz)
Data Interface
Non-Volatile Memory (kB) Volatile Memory
(kB)
Boot Time (s)
Current (mA)
Size (mm)
Mass (g) Cost (£)Flash EEPROM
None N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A
Teensy 4.0 6007x UART
3x I2C3x SPI
2048 64 1024 (RAM) 1100
@ 5V36 x18
4.8 15.26
Chosen Solution Rationale
No microcontroller for Container• All functionality can be contained in in payload• Cheaper and lighter• Reduced complexity for same functionality
Related to the Container electronics must ensure safe and correct payload deployment.
It is not a necessity for the electronics/hardware to be located in the Container in order to perform this function.
Therefore, there will be no processor in the Container.
108Presenter: May Ling Har
109
Electrical Power Subsystem (EPS)
Design
Conor Shore
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
110
EPS Overview
Presenter: Conor Shore CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Component Function
RS PRO 6V dc Buzzer
NEO M8N GPS
BMP 388 Barometer
Qulit Fire 16340 3.7 Li-ion Battery
GP2Y1014AU0F Particle sensor
Runcam Nano 2 Camera (for the bonus)
ICM-20948 9-Axis IMU
HMDVR Camera video recorder
Motor encoder Camera bonus
Servo 1 4.8 g 180 degrees Camera bonus
Servo 2 4.8 g 180 degrees CCU mechanism
Teensy 4.0 MCU
XBEE 3 PRO Radio
SD card breakout boardInterfacing SD card – for additional memory
The CanSat will be powered using only one Lithium-ion battery. The rationale for thischoice is presented in the following slides.Teensy 4.0 will act as the only MCU in the Payload. 5 V are required to power thecomponent.The system RTC will be powered by the MCU when MCU is on, when it is off orreseting it will be powered by an external battery.The IMU requires 1.8 V, which will be supplied by another voltage regulator.All the electronic components will be in the Payload, enclosed by the Payload cover.The Container will not have its own electronic components or enclose any of its own.
111
EPS Requirements
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
RE# RequirementVerification
A I T D
1 Total mass of the CanSat (science payload and Container) shall be 600 grams +/- 10 grams. X X
2CanSat shall fit in a cylindrical envelope of 125 mm diameter x 310 mm length. Tolerances are to be included tofacilitate Container deployment from the rocket fairing.
X X
15 All electronic components shall be enclosed and shielded from the environment with the exception of sensors. X
18 All electronics shall be hard mounted using proper mounts such as standoffs, screws, or high performance adhesives. X
22 The science payload shall measure altitude using an air pressure sensor. X X X
23 The science payload shall provide position using GPS. X X X
24 The science payload shall measure its battery voltage. X X X
25 The science payload shall measure outside temperature. X X X
26 The science payload shall measure particulates in the air as it glides. X X X
27 The science payload shall measure air speed. X X X
35 XBEE radios shall be used for telemetry. 2.4 GHz Series radios are allowed. 900 MHz XBEE Pro radios are also allowed. X X
38 Cost of the CanSat shall be under $1000. Ground support and analysis tools are not included in the cost. X X
44The ground station shall include one laptop computer with a minimum of two hours of battery operation, XBEE radioand a hand-held antenna.
X X X
Presenter: Conor Shore
EPS Requirements
112
RE# RequirementVerification
A I T D
45The ground station must be portable so the team can be positioned at the ground station operation site along theflight line. AC power will not be available at the ground station operation site.
X X
48 No lasers allowed. X
49The probe must include an easily accessible power switch that can be accessed without disassembling the cansatand in the stowed configuration.
X X X
50The probe must include a power indicator such as an LED or sound generating device that can be easily seenwithout disassembling the cansat and in the stowed state.
X
51 An audio beacon is required for the probe. It may be powered after landing or operate continuously. X X X
53Battery source may be alkaline, Ni-Cad, Ni-MH or Lithium. Lithium polymer batteries are not allowed. Lithium cellsmust be manufactured with a metal package similar to 18650 cells.
X
54An easily accessible battery compartment must be included allowing batteries to be installed or removed in lessthan a minute and not require a total disassembly of the CanSat.
X X
55Spring contacts shall not be used for making electrical connections to batteries. Shock forces can cause momentarydisconnects.
X X
56 The CANSAT must operate during the environmental tests laid out in Section 3.5. X
57 Payload/Container shall operate for a minimum of two hours when integrated into rocket. X X
B1
Bonus : A video camera shall be integrated into the science payload and point toward the coordinates provided forthe duration of the glide time. Video shall be in color with a minimum resolution of 640x480 pixels and 30 framesper second. The video shall be recorded and retrieved when the science payload is retrieved. Points will beawarded only if the camera can maintain pointing at the provided coordinates for 30 seconds uninterrupted.
X X X
Presenter: Conor Shore CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Payload Electrical Block Diagram
113
•
•
•
Presenter: Conor Shore CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Payload Electrical Block Diagram
114Presenter: Conor Shore CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Payload Electrical Block Diagram
115
The current slide discusses the electrical block diagram.Notes:• The SD card will be powered by the Teensy 4.0 as it will be interfaced to its 4 bit SDIO, which is located under
the real board.
• A battery header will be used to connect the battery to the PCB. It ensures easy replacement.
• Two PCBs will be used for the circuit connection. One containing core CanSat components and one with components that are necessary for this year.
• Umbilical cord will be used to access the Teensy. This will be a USB cable which will connect to the Teensy. This will provide power to the Payload and allow for data transmission.
• An easily accessible external switch will be used to turn on and off the power.
• Two voltage regulators are used to provide stable 3.3 V and 1.8 V and one synchronous boost converter is used to provide 5 V.
• The Buzzer will be beeping every second to show that the system is turned on
•
•
•
Presenter: Conor Shore CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Payload Power Trade & Selection
116CanSat 2020 PDR: Team 4920 Manchester CanSat Project
• The team has decided to choose the Qulit fire 16340 Lithium-ion battery, because the team has hadsuccessful experience using this component. A single battery will be used. Two voltage regulators will beused to maintain a steady voltage. One will be 3.3 V and the other 1.8 V. In addition, a synchronous boostregulator will be used for components, which require 5 V.
• The chosen battery source is Lithium-ion. The battery size is 16340, it is small and quite light. The chosenbattery does not represent a fire hazard.
• The battery will be secured with velcro and cable ties. A header will be used to connect it to the core PCB.
Battery Name SizeMass
(g)Type
Voltage (V)
Capacity (mAh)
Price (£) Advantages Disadvantages Energy (Wh)
Qulit fire 16340 Li-ion Rechargeable
34 X 16 mm (L x Dia)
16 Li-ion 3.7 1400 4.99Light, small size, cheap and
rechargeable.Medium capacity 5.18
Sony VTC664.9 X 18.2 mm
(L x Dia)46.8 Li-ion 3.6 3000 5.99
Outstanding capacity, large amount of power, cheap.
Heavy and large 10.8
KeepPower ICR14500
52 X 14 mm (L x Dia)
21.44Li-ion
3.7 800 4.13 Cheap, relatively light.Small amount of
capacity2.96
Presenter: Conor Shore
117
Payload Power Budget
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Component Name Current (A) Voltage (V) Power (W)Duty Cycle
(%)Duty Cycle (Hrs) Duty hour (sec)
Required Energy
(W·h)
9-axis IMU 3.11 x 10-3 1.8 5.6 x 10-3 100 01:00:00 3600 11.2 x 10-3
Barometer 3.4 x 10-6 3.3 11.2 x 10-6 100 01:00:00 3600 22.4 x 10-6
GPS 0.023 5 0.115 100 01:00:00 3600 0.23
3.3 V Voltageregulator
18 x 10-6 3.7 66.6 x 10-6 100 01:00:00 3600 133.2 x 10-6
1.8 V Voltageregulator
23 x 10-6 5 115 x 10-6 100 01:00:00 3600 230 x 10-6
Synchronous boostregulator
109 x 10-6 3.7 403 x 10-6 100 01:00:00 3600 806 x 10-6
2 x Servo 4.8g 180º 0.0612 5 0.306 100 01:00:00 3600 0.612
Buzzer 0.03 5 0.15 25 00:15:00 900 0.075
Teensy 4.0 0.1 5 0.5 100 01:00:00 3600 1
XBEE 0.229 3.3 0.7557 10 00:06:00 360 0.15114
ADU 0.003 3.3 0.01 100 01:00:00 3600 0.02
Presenter: Conor Shore
Payload Power Budget
118
Component Name Current (A) Voltage (V) Power (W)Duty Cycle
(%)Duty Cycle (Hrs) Duty hour (sec)
Required Capacity
(W·h)
Particle sensor 0.02 5 0.1 100 01:00:00 3600 0.2
Camera 0.11 5 0.55 10 00:06:00 360 0.11
Motor driver 0.85 x 10-3 5 4.25 x 10-3 100 01:00:00 3600 8.5 x 10-3
Motor 0.07 5 0.35 10 00:06:00 360 0.07
Voltage level shifter 20 x 10-6 3.3 6.6 x 10-5 100 01:00:00 3600 13.2 x 10-5
Video recorder 0.05 5 0.25 100 01:00:00 3600 0.5
Teensy 4.0 RTC 26 x 10-6 3.3 85.8 x 10-6 100 01:00:00 3600 171.6 x 10-6
SD card breakout board 2 x 10-3 3.3 6.6 x 10-3 100 01:00:00 3600 0.0132
• The main source of uncertainty is that the data was taken from component datasheets. Data will be confirmed experimentally when CanSat is built.
• Note : Servo current consumption was estimated combining servo being idle and servo operating.• The only power source for the system is the selected battery. For the RTC an additional battery will be used when
the Teensy is turned off.• The total power consumption is expected to be 3.00 Wh, while the battery can supply 5.18 Wh. The margin is
2.18 Wh, which is 42.1 % of the battery supply. There will be enough power to supply the operation of the CanSat for more than 2 hours.
CanSat 2020 PDR: Team 4920 Manchester CanSat ProjectPresenter: Conor Shore
119
Container Electrical Block Diagram
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Container will not contain any electronics, therefore no block diagram is required.
Presenter: Conor Shore
Container Power Trade & Selection
120CanSat 2020 PDR: Team 4920 Manchester CanSat Project
The team has chosen to not use any battery for the Container as there will not beany electronic components that require power in the Container.
Battery Name SizeMass
(g)Type
Voltage (V)
Capacity (mAh)
Price (£) Advantages Disadvantages Energy (Wh)
Qulit fire 16340 Li-ion Rechargeable
34 X 16 mm (L x Dia)
16 Li-ion 3.7 1400 4.99Light, small size, cheap and
rechargeable.Medium capacity 5.18
Sony VTC664.9 X 18.2 mm
(L x Dia)46.8 NMC 3.6 3000 5.99
Outstanding capacity, large amount of power, cheap.
Heavy and large 10.8
KeepPower ICR14500
52 X 14 mm (L x Dia)
21.44Li-ion
3.7 800 4.13 Cheap, relatively light.Small amount of
capacity2.96
Presenter: Conor Shore
121
Container Power Budget
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
The total required capacity for the Container will be 0 Wh, because there are no electronics in the container.
Component NameCurrent
(A)Voltage
(V)Power
(W)Duty
Cycle (%)Duty Cycle
(Hrs)Duty hour
(sec)
Required Capacity
(W·h)
N/A N/A N/A N/A N/A N/A N/A N/A
Presenter: Conor Shore
122
Flight Software (FSW) Design
Conor Shore
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
123
FSW Overview
CanSat 2020 PDR: Team 4920 Manchester CanSat ProjectPresenter: Conor Shore
Brief summary of the FSW tasks:
• Throughout: Collect data from sensors, GPS and camera, form data packets for transmission and save backup to
SD card, ensure recovery in case of failure or reboot.
• Launch Pad: Calibrating sensors, setting up SP, ensuring working condition, detecting launch, starting the
telemetry collection and transmission loop
• Before Apogee: Transmit telemetry
• At Apogee: Detect apogee and release of CanSat from rocket (and parachute release)
• Above 450 metres: Detect reaching 450 metres above ground
• Below 450 metres: Deploy SP from Container
• Landed: Detect landing, turn on buzzer and switch off other components
Bonus objective:• A video camera will be integrated into the science payload and point toward the coordinates
provided by the GPS for the duration of the glide time.
FSW Overview
124CanSat 2020 PDR: Team 4920 Manchester CanSat ProjectPresenter: Conor Shore
C++ is the main language of development
• Encapsulation: The ability to store different
functions into specific structs or classes.
Thus the code will be easier to be
understood by all team member.
• Low level: It gives us the ability to
manipulate variables and function via
pointers to the memory address.
• Light weight: C++ follows a philosophy
where only the important metadata is stored.
Language: Development environment:
Arduino IDE for Teensy 4.0
• Community support: The Arduino project
has a lot of community backing, making it
easy to troubleshoot common problems.
• Library friendly: It allows for easy
implementation of pre-existing libraries or
even custom ones.
FSW Overview
125CanSat 2020 PDR: Team 4920 Manchester CanSat ProjectPresenter: Conor Shore
Basic FSW architecture:
126
FSW Requirements
•
•
•
•
•
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
RE# RequirementVerification
A I T D
23 The science payload shall provide position using GPS. X X X X
24 The science payload shall measure its battery voltage. X X X X
28 The science payload shall transmit all sensor data in the telemetry. X X X
29 The science payload shall transmit all sensor data in the telemetry. X X X
33Telemetry shall include mission time with one second or better resolution. Mission time shall be maintained in the event of a processor reset during the launch and mission.
X X X X
34Configuration states such as if commanded to transmit telemetry shall be maintained in the event of a processor reset during launch and mission.
X X X
47The flight software shall maintain a count of packets transmitted, which shall increment with each packet transmission throughout the mission. The value shall be maintained through processor resets.
X X X X
48 No lasers allowed. X X
50The probe must include a power indicator such as an LED or sound generating device that can be easily seen without disassembling the cansat and in the stowed state.
X X X
51 An audio beacon is required for the probe. It may be powered after landing or operate continuously. X X X
25 The science payload shall measure outside temperature. X X X X
22 The science payload shall measure altitude using an air pressure sensor X X X X
26 The science payload shall measure particulates in the air as it glides. X X X X
27 The science payload shall measure air speed. X X X X
B1
Bonus : A video camera shall be integrated into the science payload and point toward the coordinates provided for theduration of the glide time. Video shall be in color with a minimum resolution of 640x480 pixels and 30 frames per second.The video shall be recorded and retrieved when the science payload is retrieved. Points will be awarded only if the cameracan maintain pointing at the provided coordinates for 30 seconds uninterrupted.
X X X
Presenter: Conor Shore
127
Payload FSW State Diagram
•
•
•
CanSat 2020 PDR: Team 4920 Manchester CanSat ProjectPresenter: Conor Shore
RECOVERY: During the
operation of the CanSat a
proccesor reset might be
caused by a short circuit or one
of the electrical motors
temporarily drawing too much
power.
In the case of reset data will be
saved in the EEPROM after
every measurment and state
transition, thus in case of
processor reset the state of the
FSW can be broght back
128
Container FSW State Diagram
CanSat 2020 PDR: Team 4920 Manchester CanSat ProjectPresenter: Conor Shore
There are no electronics in the Container. There is no processor, hence no flight software, in the Container. Thus a Container FSW state diagram
is unnecessary.
129
Software Development Plan
•
•
•
CanSat 2020 PDR: Team 4920 Manchester CanSat ProjectPresenter: Conor Shore
GITLAB will be the platform used to keep track of the development cycle.The Software development will be divided into the:• Flight Software branch• Ground Control Station branchOnce the Software has been completed for each branch the two will be merged on themaster branch creating a deployable FSW/GCS package.
Prototyping: will be done when ever possible using the components in isolation or in combination with others.Divide work: work is divided into the two main branches. For further subdivisions different branches will be made with appropriate name of their main branch and given task. Example: FSW-StateMachineDevelopment team: SE – GA, FSW – MR, CDH –CS, EPS – MD, Integration and Test – MR with support from rest of the teamIn the case of problems arising: It will be possible to revert to a previous version from Gitlab. Thus we avoid breaking dependent systems.
Software testing cycle
Hardware testing cycle
Revert cycle
130
Ground Control System (GCS) Design
Presenter Name(s) Go Here
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
131
GCS Overview
Payload XBee-Pro900HP
900 MHz Yagi Antenna
GCSXBee-Pro 900HP
Laptop (GUI)
N-Female to SMA Male Adapter
.csv files and graphs
CanSat 2020 PDR: Team 4920 Manchester CanSat ProjectPresenter: Conor Shore
132
GCS Requirements
RE# DescriptionVerification
A I T D
29 Telemetry shall be updated once per second. x x x
31The ground system shall command the science vehicle to start transmittingtelemetry prior to launch.
x x x
32The ground station shall generate a csv file of all sensor data as specified inthe telemetry section.
x x
33Telemetry shall include mission time with one second or better resolution.Mission time shall be maintained in the event of a processor reset during thelaunch and mission.
x x x
34Configuration states such as if commanded to transmit telemetry shall bemaintained in the event of a processor reset during launch and mission.
x x x
35XBEE radios shall be used for telemetry. 2.4 GHz Series radios areallowed. 900 MHz XBEE Pro radios are also allowed.
x
36 XBEE radios shall have their NETID/PANID set to their team number x x x
37 XBEE radios shall not use broadcast mode. x x
38Cost of the CanSat shall be under $1000. Ground support and analysistools are not included in the cost.
x x
39 Each team shall develop their own ground station. x
CanSat 2020 PDR: Team 4920 Manchester CanSat ProjectPresenter: Conor Shore
GCS Requirements
133
RE# DescriptionVerification
A I T D
40 All telemetry shall be displayed in real time during descent. x x
41All telemetry shall be displayed in engineering units (meters, meters/sec,Celsius, etc.)
x x
42 Teams shall plot each telemetry data field in real time during flight. x x
44The ground station shall include one laptop computer with a minimum of twohours of battery operation, XBEE radio and a hand-held antenna.
x
45The ground station must be portable so the team can be positioned at theground station operation site along the flight line. AC power will not beavailable at the ground station operation site.
x
46Both the container and probe shall be labeled with team contact informationincluding email address.
x
56The CANSAT must operate during the environmental tests laid out inSection 3.5.
x x
57The CANSAT must operate during the environmental tests laid out inSection 3.5.
x
CanSat 2020 PDR: Team 4920 Manchester CanSat ProjectPresenter: Conor Shore
GCS Design
134
Specifications
Laptop Battery 3 hours from fully charged
Overheating mitigationSun shielding umbrella
Laptop cooling pad
Auto update mitigationDisable auto-update
Disable Internet Connection
GCS Antenna GCS XBee-Pro 900 HS
GCS LaptopN-Female toSMA Male Adapter
USB Cable
CanSat 2020 PDR: Team 4920 Manchester CanSat ProjectPresenter: Conor Shore
135
GCS Antenna Trade & Selection
Antenna Gain VSWR ConnectorBeam width
horizontal/verticalPolarization Cost (£)
TerraWave Yagi Antenna
15dBi ≤1.5 N-female 28˚/28˚Vertical/
horizontal47.95
900 MHz 9 dBi SS Yagi Antenna SMA
Male Connector9dBi ≤1.5 SMA Male 54˚/48˚
Vertical/horizontal
65.24
Hyperlink Wireless Yagi Antenna
14dBi ≤1.5 N-female 30˚/30˚Vertical/
horizontal179.50
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
All antennas are handheld.
GCS antenna will have a 900 MHz operating frequency, because of XBee Pro 900 HS. It will be handled and directed by a team member.
Presenter: Conor Shore
136
GCS Antenna Trade & Selection
Selected Antenna Rationale
900 MHz 9 dBi SS Yagi
Antenna SMA
Male Connector
The largest horizontal
beam width.
Antenna radiation and gain patterns.
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
TerraWave Yagi Antenna900 MHz 9 dBi SS
Yagi Antenna SMA Male Connector
Hyperlink Wireless Yagi Antenna
Selected antenna radiation and gain patterns.
Presenter: Conor Shore
137
GCS Antenna Trade & Selection
Antenna mounting design:
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Antenna will be mounted on a wooden pole, as shown in the image above. This method was used in previous years and was found to be appropriate.
Presenter: Conor Shore
GCS Software
138
Software Packages:
• Python 2.7.15 - Computational environment of choice
• XCTU – XBee Program Software
• XBEE Python Library – real time access to XBEE via USB interface
• Matplotlib Python Library – real time plotting and data manipulation
• SKlearn Python Library – simple data filtering and post-processing features
Command Software and Interface:• Commands can be sent from the Ground Control Station to the CanSat via command.• The GCS uses the XBEE Python Library to access the XBEE receiver through the USB interface.
Telemetry Data Recording:• Telemetry will be recorded in a .csv file without processing after being read via USB interface.• .csv data will be analyzed in python to present in PFR.
CSV File Generation:• .csv file will be generated in GCS Python software and data will be continuously appended to the
file as it arrives in packets to GCS.
CanSat 2020 PDR: Team 4920 Manchester CanSat ProjectPresenter: Conor Shore
GCS Software
139CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Payload transmission procedure flowchart:
Presenter: Conor Shore
GCS Software
GCS Architecture
140
All x-axis units are in seconds.
Telemetry display prototype.
Wait for dataRead data from
USB portCheck data not
corrupt
Convert data from string to float
Save data .csv file
Plot data
Presenter: Conor Shore CanSat 2020 PDR: Team 4920 Manchester CanSat Project
141
CanSat Integration and Test
Conor Shore
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
142
CanSat Integration and Test
Overview
•
•
•
•
• 31/57 requirements + Bonus requirement can be tested, the other are satisfied in design stage
• If problems arise during integration, it is likely that retroactive design iterations will occur, and these will maintain compliance with the requirements at all times.
• CanSat will be tested:
Component level
Subsystem level
• Then as grouped subsystems, such as the embedded subsystems Sensors, EPS and CDH, are ready, they can be integrated together and tested:
System level
• Then when grouped subsystems are ready, whole system tests can be performed
CanSat 2020 PDR: Team 4920 Manchester CanSat ProjectPresenter: Conor Shore
Overview of Integration and Testing
• All of these 31 requirements would benefit from an integrated level test
• Launch test(s) will be performed at the University of Manchester with the assistance of the University’s Space Systems Engineering Group
• These launch tests will assess:
– How the components and subsystems perform when fully integrated
– How the entire design performs at integrated level
• Environmental testing will be carried out to verify physical mission conditions - for exampletemperature, shock acceleration, vibration, wind - will not affect system performance
– These should be performed at the component, subsystem and system levels
143Presenter: Conor Shore CanSat 2020 PDR: Team 4920 Manchester CanSat Project
CanSat Integration and Test
Overview
Subsystem Level Testing Plan
144
CanSat: Payload
Presenter: Conor Shore CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Subsystem Level Testing Plan
145
SubsystemTesting plan
Component Level Subsystem Level System Level
Sensors
• Test if sensor readings are accurate: Altimeter, Adu, IMU, GPS, Particle sensor.
• Test both servos mechanism.• Ensure video being stored on SD
card on FPVDVR on command.• Verify the motor spinning and
changing on command• Test motor response time.• Test encoder.
• Test camera response to changes from GPS
• Test multiple sensor data can be measured at the same time
• Ensure live data collected by sensors can be transmitted and stored
• Verify software can control wing, glider and parachute deployment
• Ensure data transmission starts on command
• Verify live data plotting
CDH
• Verify the buzzer sounds at 92 db• Check is RTC keeps time in case of
power disconnection• Test if data can be received with
XBee• Test if data is stored on SD
• Ensure microcontroller keeps its function in case of power disconnection
• Ensure live data transmission packets can be controlled by FSW
• Verify data packets are sent in appropriate time intervals
CanSat 2020 PDR: Team 4920 Manchester CanSat ProjectPresenter: Conor Shore
Subsystem Level Testing Plan
146
SubsystemTesting plan
Component Level Subsystem Level System Level
EPS
• Test if voltage is maintained under expected load for 5V, 3.3V and 1.8V regulator.
• Ensure battery can run for 3 hours at expected load level.
• Test if reading are accurate from the voltage divider.
• Ensure all power rails behave in combination
• Ensure power requirements are satisfied
• Test the system in different external conditions
Radio Communications
• Ensure XBee sends data by testing with randomly generated data
• Test live graph generation with randomly generated data
• Verify communication occurs at and above the required range
• Test data transmission can be stored by generating random data every second
• Verify live data transmission is not affected by external conditions
• Ensure data transmission can be actuated by command
CanSat 2020 PDR: Team 4920 Manchester CanSat ProjectPresenter: Conor Shore
Subsystem Level Testing Plan
147
SubsystemTesting plan
Component Level Subsystem Level System Level
Mechanical
• Ensure any changes in component design allow for compatibility and easy integration with requirements
• Test mechanical stresses/strains on all components
• Ensure the CCU works when manually initiated
• Ensure the camera mechanism works manually actuated
• Test wing mechanism works when manually initiated
• Ensure functions (camera mechanism, parachutes deployment) is not affected by external conditions
• Ensure camera is not obstructed in any situation
• Test CCU mechanism with wing and parachute deployment
• Ensure the system operation is not affected by external conditions
• Ensure the system does not fail in different external conditions
• Test if the system withholds stresses/strains of the integrated system
Descent Control
• Ensure easy container parachutedeployment
• Ensure easy glider parachutedeployment
• Flight Simulation Testing• Ensure wing deployment
is not affected by external conditions
• Ensure the payload is aerodynamically stable
• Ensure the payload descends in a circular pattern
CanSat 2020 PDR: Team 4920 Manchester CanSat ProjectPresenter: Conor Shore
Subsystem Level Testing Plan
148
SubsystemTesting plan
Component Level Subsystem Level System Level
FSW
• Ensure software maintains packet count in case of processor reset
• Ensure software maintains mission time in case of processor reset
• Ensure software state is correct at each point in the sequence of events
• Test the microcontroller memory after sensor, CDH and GCS subsystem integration
• Verify software operation with randomly generated data
• Ensure software runs without errors
• Verify software works in the case of different external conditions
• Ensure compatibility and integration with all subsystems
CanSat 2020 PDR: Team 4920 Manchester CanSat ProjectPresenter: Conor Shore
Integrated Level Functional Test Plan
Important considerations:• Each system requires sequenced testing to guarantee its required integrated
functions• One or two subsystems in each system acts as a critical subsystem and it is identified
to guarantee the start of the sequence• Table below shows the critical subsystem of both systems:
149
•
System Critical Subsystem Description
CanSat EPSAll mechanisms depend on correct power distribution and supply from the power source to sensors and servos.
CanSat DC, METest launch to validate descent control design concept including stability, descent rate. Also to validate mechanisms.
Comms GCS, CDHAll transmission of mission data and telemetry depends on the correct operation and function of the microcontroller and communication system.
CanSat 2020 PDR: Team 4920 Manchester CanSat ProjectPresenter: Conor Shore
Integrated Level Functional Test Plan
150CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Payload
Presenter: Conor Shore
Environmental Test Plan
The following table gives the environmental tests for the subsystems:
151
Subsystem Critical Subsystem Description
ProbeFlight Simulation Testing
Wind Tunnel Testing
• Performance of the glider will be tested in a Flight Simulator to assess the behaviour and descent velocity in initial stages of the design.
• Glider will be examined in the wind tunnel using different air flow velocites.
CanSat
Vibration TestThermal Test
Drop TestFit Test
• CanSat will be tested under specified conditions to ensure compatibility with specified requirements.
• Vibration test will be performed to evaluate the mounting integrity of the components and entire CanSat.
• Thermal test will be performed in an insulating chamber to evaluate performance at higher temperatures.
• Drop test will be performed to test survival of 30Gs of shock on descent control device attachment component and structures as stated in mission requirements.
• Container compatibility will be tested by measuring the dimensions of the final CanSat.
• Ensure fit of CanSat using jigs, such as diameter jig to ensure CanSar passes through laser cut 125 mm circular hole and height jig, ensuring CanSat passes through 125 x 310 mm rectangle.
CanSat 2020 PDR: Team 4920 Manchester CanSat ProjectPresenter: Conor Shore
152
Mission Operations & Analysis
Conor Shore
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
153
Overview of Mission Sequence of
Events
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Roles and Responsibilities:Mission Control Officer: TCGround Station Crew: MLH, CS, TP, MR, GA, CRRecovery Crew: GJ, MD, MWRCanSat Crew: MLH, CS, TP, CR, MWR, GJ, MR, MD, GA
Final Integration and Testing:• Between 08:00 and 12:00• Full team involved, excluding TC• Various CanSat I&T procedures are carried out prior to the competition to ensure that everything is in order.
This is led by TP and performed by the CanSat Crew.• Antenna and GCS set-up will be carried out by the Ground Station Crew. Simple plug-and-play philosophy stands
behind the design of the GCS and Antenna systems.• An I&T plan will be followed throughout this process to ensure that all procedures have been carried out
sufficiently – see Mission Operations Manual.
Presenter: Conor Shore
154
Overview of Mission Sequence of
Events
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Arrival
•08:00 – Full Team
Final Integration and Testing
•CanSat Crew
Official Inspection
•12:00 - TC
Collect CanSat
•TC
CanSat integration with rocket
•MLH, CR
Check Communications
•CS, TP
GCS & Antenna Set-Up
•CS, TP
Rocket with CanSattaken to Launchpad
•MLH, CR
Rocket Installation
•Officials
GCS operational
•GCS Crew
Launch Procedures Execution
•TC
Flight + GCS Operational
•GCS Crew
CanSat Launched
Recovery
•Recovery Team
Handover CanSatfor Final Judging
•MD
Terminate GCS Operation
•TP
Submit USB with collected and received data
•MLH
Begin PFR work and data analysis
Presenter: Conor Shore
155
Mission Operations Manual
Development Plan
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
The Mission Operations Manual will contain instructions for the following procedures:
1. CanSat Integration and Testing TP, MLH, CS1.1. Integration Procedure1.2. Testing Procedure1.3. Operational Checks
2. GCS & Antenna Setup and Operation Ground Station Crew2.1. Setup Procedure2.2. Operational Checks
3. CanSat-Rocket Integration CanSat Crew4. Launch TC, Officials
4.1. Preparation Procedure4.2. Launch Procedure
5. Other Procedures TC
The Mission Operations Manual will be compiled at individual- and team-level to ensure suitable accuracy and detail of tests and procedures.
The Mission Operations Manual shall be completed by early February in time for the first test launch.
The Mission Operations Manual will be reviewed and approved by the full team. Multiple copies will be distributed to the team on test launch days and at the competition.
Presenter: Conor Shore
156
CanSat Location and Recovery
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
The following measures will ensure that both the Container and the Payload will be recovered.
1. Audio BeaconContinuously beeping on the Payload at 92 dB unobstructed.
2. TelemetryPayload GPS position plotted on the GCS. Subject to errors and degree of accuracy.
3. ColourThe Container and the Payload will be fluorescent pink to make the CanSat easier to identify and locate.
4. VisuallyRecovery Crew will track the Container and Payload as they descend.
In the event that the CanSat is not recovered, both the Container and the Payload will have Manchester CanSatProject’s address and email address clearly labelled, along with any other relevant contact details.
Presenter: Conor Shore
157
Requirements Compliance
Conor Shore
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Requirements Compliance Overview
158CanSat 2020 PDR: Team 4920 Manchester CanSat Project
The current design complies with all requirements.
The design shall be tested to ensure Requirement Compliance, following the procedure explained in the Integration and Testing section of this document.
The design can be altered by the CDR, in case the testing outcome is negative, to ensure the revised design also complies with requirements.
The following five slides trace and demonstrate compliance with all requirements. Comments have been included where necessary.
The legend provides an explanation as to the colour coding used throughout this section, with the goal of demonstrating if a requirement has been met.
Full Compliance
Partial Compliance
No Compliance
Presenter: Conor Shore
Requirements Compliance
(Slide 1 of 5)
159CanSat 2020 PDR: Team 4920 Manchester CanSat Project
RE#
Requirement ComplianceReference
SlidesComments
1 Total mass of the CanSat (science payload and container) shall be 600 grams +/- 10 grams. 92
539.02 g. Will add Ballast to
Payload. See ref slide.
2CanSat shall fit in a cylindrical envelope of 125 mm diameter x 310 mm length. Tolerances are to be included to facilitate container deployment from the rocket fairing.
20, 151 120 x 305
3The container shall not have any sharp edges to cause it to get stuck in the rocket payload section which is made of cardboard.
20, 79Bolts will be
sanded if needed
4 The container shall be a fluorescent color; pink, red or orange. 35, 62, 79
5The container shall be solid and fully enclose the science payload. Small holes to allow access to turn on the science payload is allowed. The end of the container where the payload deploys may be open.
20, 62, 79
6 The rocket airframe shall not be used to restrain any deployable parts of the CanSat. 20, 62, 66
7 The rocket airframe shall not be used as part of the CanSat operations. 20, 62, 66
8The container parachute shall not be enclosed in the container structure. It shall be external and attached to the container so that it opens immediately when deployed from the rocket.
20, 79, 83
9 The descent rate of the CanSat (container and science payload) shall be 20 meters/second +/- 5m/s. 54 17.6 m/s
10 The container shall release the payload at 450 meters +/- 10 meters. 82, 123, 127
11The science payload shall glide in a circular pattern with a 250 m radius for one minute and stay above 100 meters after release from the container.
49, 54
12 The science payload shall be a delta wing glider. 12, 13, 39
Presenter: Conor Shore
Requirements Compliance
(Slide 2 of 5)
160CanSat 2020 PDR: Team 4920 Manchester CanSat Project
RE#
Requirement ComplianceReference
SlidesComments
13After one minute of gliding, the science payload shall release a parachute to drop the science payload to the ground at 10 meters/second, +/- 5 m/s
65, 69, 127
14 All descent control device attachment components shall survive 30 Gs of shock. 82, 83, 151
15All electronic components shall be enclosed and shielded from the environment with the exception of sensors.
62, 84
16 All structures shall be built to survive 15 Gs of launch acceleration. 61, 78, 151
17 All structures shall be built to survive 30 Gs of shock. 61, 78, 151
18All electronics shall be hard mounted using proper mounts such as standoffs, screws, or high performance adhesives.
84, 85
19 All mechanisms shall be capable of maintaining their configuration or states under all forces. 82, 83, 151
20 Mechanisms shall not use pyrotechnics or chemicals. 60, 61, 78
21Mechanisms that use heat (e.g., nichrome wire) shall not be exposed to the outside environment to reduce potential risk of setting vegetation on fire.
61, 78Not using nichrome
wire
22 The science payload shall measure altitude using an air pressure sensor. 26
23 The science payload shall provide position using GPS. 28
24 The science payload shall measure its battery voltage. 29, 114
25 The science payload shall measure outside temperature. 27
26 The science payload shall measure particulates in the air as it glides. 31
27 The science payload shall measure air speed. 30
Presenter: Conor Shore
Requirements Compliance
(Slide 3 of 5)
161CanSat 2020 PDR: Team 4920 Manchester CanSat Project
RE#
Requirement ComplianceReference
SlidesComments
28 The science payload shall transmit all sensor data in the telemetry. 101-105, 127
29 Telemetry shall be updated once per second. 126
30 The Parachutes shall be fluorescent Pink or Orange . 35, 56, 79, 83
31 The ground system shall command the science vehicle to start transmitting telemetry prior to launch. 138, 139
32 The ground station shall generate a csv file of all sensor data as specified in the telemetry section. 137
33Telemetry shall include mission time with one second or better resolution. Mission time shall be maintained in the event of a processor reset during the launch and mission.
100, 104, 127
34Configuration states such as if commanded to transmit telemetry shall be maintained in the event of a processor reset during launch and mission.
127
35XBEE radios shall be used for telemetry. 2.4 GHz Series radios are allowed. 900 MHz XBEE Pro radios are also allowed.
102, 103
36 XBEE radios shall have their NETID/PANID set to their team number. 102, 103
37 XBEE radios shall not use broadcast mode. 102, 103
38Cost of the CanSat shall be under $1000. Ground support and analysis tools are not included in the cost.
171
39 Each team shall develop their own ground station. 131-140
40 All telemetry shall be displayed in real time during descent. 140
41 All telemetry shall be displayed in engineering units (meters, meters/sec, Celsius, etc.) 140
42 Teams shall plot each telemetry data field in real time during flight. 140
Presenter: Conor Shore
Requirements Compliance
(Slide 4 of 5)
162CanSat 2020 PDR: Team 4920 Manchester CanSat Project
RE#
Requirement ComplianceReference
SlidesComments
44The ground station shall include one laptop computer with a minimum of two hours of battery operation, XBEE radio and a hand-held antenna.
134
45The ground station must be portable so the team can be positioned at the ground station operation site along the flight line. AC power will not be available at the ground station operation site.
134
Using laptop. Thus,
portable.
46 Both the container and probe shall be labeled with team contact information including email address. 156
47The flight software shall maintain a count of packets transmitted, which shall increment with each packet transmission throughout the mission. The value shall be maintained through processor resets.
104, 105, 127
48 No lasers allowed. 12, 13No lasers
used.
49The probe must include an easily accessible power switch that can be accessed without disassembling the CanSat and in the stowed configuration.
64, 114
50The probe must include a power indicator such as an LED or sound generating device that can be easily seen without disassembling the CanSat and in the stowed state.
114, 127, 156
51 An audio beacon is required for the probe. It may be powered after landing or operate continuously. 114, 127, 156
52 The audio beacon must have a minimum sound pressure level of 92 dB, unobstructed. 156
53Battery source may be alkaline, Ni-Cad, Ni-MH or Lithium. Lithium polymer batteries are not allowed. Lithium cells must be manufactured with a metal package similar to 18650 cells.
116
Presenter: Conor Shore
Requirements Compliance
(Slide 5 of 5)
163CanSat 2020 PDR: Team 4920 Manchester CanSat Project
RE#
Requirement ComplianceReference
SlidesComments
54An easily accessible battery compartment must be included allowing batteries to be installed or removed in less than a minute and not require a total disassembly of the CanSat.
62, 64
55Spring contacts shall not be used for making electrical connections to batteries. Shock forces can cause momentary disconnects.
84, 85, 115
56 The CANSAT must operate during the environmental tests laid out in Section 3.5. 151
57 Payload/Container shall operate for a minimum of two hours when integrated into rocket. 118
B1
Bonus: A video camera shall be integrated into the science payload and point toward the coordinates provided for the duration of the glide time. Video shall be in color with a minimum resolution of 640x480 pixels and 30 frames per second. The video shall be recorded and retrieved when the science payload is retrieved. Points will be awarded only if the camera can maintain pointing at the provided coordinates for 30 seconds uninterrupted.
32, 69, 123, 125
Presenter: Conor Shore
164
Management
Conor Shore
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
165
CanSat Budget – Hardware
•
•
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
The following table shows the budget for hardware in terms of CanSat subsystems:
Subsystem Cost (£)
Structures 157.36
Electronics 164.70
Tools 0
Total: £322.06
Legend
Estimated XX Actual XX
Presenter: Conor Shore
166
CanSat Budget – Hardware
•
•
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Legend
Estimated XX Actual XX
3D Printed Components*
Part Name Function Reuse Quantity Total Cost (£) Total Cost ($)
Container top plate Attachment for Container Parachute
No
1 2.12 2.77
Container ribs Structural integrity 3 0.67 0.88
Container bottom rib Structural integrity 1 0.35 0.46
X frame arms Wing spar structure 2 1.13 1.48
Fuselage-X frame attachment Attach wings to fuselage 1 0.53 0.69
GPS mount To mount GPS 1 0.08 0.10
Roof scoop To aid airflow for particulate sensor 1 0.08 0.10
Buzzer mount To mount buzzer 1 1.53 2.00
PCB mount To mount stacked PCBs 1 0.08 0.10
CCU housing (inc. spool) To mount Servo for Payload release, wings and Payload Parachute deployment mechanism
10.29 0.38
Total Cost: £6.86 $8.97
Presenter: Conor Shore
167
CanSat Budget – Hardware
•
•
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Legend
Estimated XX Actual XX
3D Printed Components
Part Name Function Reuse Quantity Total Cost (£) Total Cost ($)
Camera mechanism mount To mount camera mechanism components
No
10.18 0.24
Tail To ensure circular descent pattern 3 0.51 0.67
Payload parachute bay To enclose payload parachute 1 0.40 0.52
Total Cost: £1.09 $1.42
Presenter: Conor Shore
168
CanSat Budget – Hardware
•
•
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Electronic Components
Part Name Function Reuse Quantity Total Cost (£) Total Cost ($)
ICM-20948 9-axis IMU Tilt
No
1 4.58 5.99
BMP 388 Barometer 1 2.48 3.24
u-blox NEO-M8N GPS Module GPS 1 5.50 7.19
MS4525DO ADU Measures differential pressure 1 30.43 39.77
2.6 Arduplane Airspeed Sensor Pitot tube 1 3.37 4.40
GP2Y1010AU0F Particle Sensor Particulate count 1 2.87 3.75
Runcam Nano 2 Camera 1 10.21 13.35
HMDVR Records video from camera 1 20.02 26.17
Hitec HS-40 180° Servo CCU and camera pitch 2 17.58 22.98
Aslong JG-12 Stepper motor (camera rotation) 1 6.56 8.57
XBEE Pro 900HP u.fl Communications 1 32.82 42.90
Switch On/Off Switch 1 0.61 0.80
Total Cost: £137.03 $179.11
Legend
Estimated XX Actual XX
Presenter: Conor Shore
169
CanSat Budget – Hardware
•
•
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Legend
Estimated XX Actual XX
Electronic Components
Part Name Function Reuse Quantity Total Cost (£) Total Cost ($)
Slip Ring Camera Mechanism
No
1 5.02 6.56
Buzzer Payload Recovery 1 1.17 1.53
Headers N/A N/A 6.00 7.84
Capacitors N/A 25 11.00 14.37
Inductors N/A 1 0.30 0.39
Resistors N/A 14 2.00 2.61
Digital transistor N/A 1 0.40 0.52
PCB Component Mounting 2 0.78 1.02
Wiring N/A N/A 1.00 1.3
Total Cost: £27.67 $36.16
Presenter: Conor Shore
170
CanSat Budget – Hardware
•
•
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Legend
Estimated XX Actual XX
Off-the-Shelf Components
Part Name Function Reuse Quantity Total Cost (£) Total Cost ($)
Carbon fibre rods Container structural support
No
3 7.20 9.41
Plastic file folder Container cover 1 1.50 1.96
String CCU mechanism 1 1.50 1.96
Nuts/Bolts Box Various nuts and bolts Assorted 11.00 14.38
1 mm CFRP Fuselage airfoils 4 21.50 28.10
3 mm Rohacell foam Fuselage airfoils 2 30.68 40.10
Balsa Wing ribs, camera mechanism mount plate 1 6.45 8.43
Parachutes N/A 2 17.23 22.52
PETG sheet Camera bubble 1 4.75 6.21
Torsion springs Wing deployment mechanism 2 6.00 7.84
Ripstop Nylon Payload wing skin 1 19.99 26.13
Total Cost: £127.80 $167.03
Presenter: Conor Shore
171
CanSat Budget – Hardware
•
•
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Legend
Estimated XX Actual XX
Off-the-Shelf Components
Part Name Function Reuse Quantity Total Cost (£) Total Cost ($)
Steel shaft CCU rods, wing ribs, fuselage attachment, parachute bay
No
25.89 7.70
Gorilla epoxy High performance adhesive 2 11.00 14.38
Bevel gears Camera mechanism rotation 2 4.72 6.17
Total Cost: £21.61 $28.24
Presenter: Conor Shore
172
CanSat Budget – Hardware
•
•
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Total Spent (£) 322.06
Total Spent ($) 420.93
Budget Left ($) 579.06
Exchange Rate (£1 = ) $1.307
Exchange Rate Date 28/01/2020 14:30 GMT
Presenter: Conor Shore
173
CanSat Budget – Other Costs
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Source Amount (£) Additional Information
Department of MACE 6500
Department of EEE 2000
Department of Computer Science 500
Aerospace Research Institute 1000
MANSEDS 620
BAE Systems 2,500 TBC
Airbus 6,000 TBC
Total Income Confirmed (£) 10,620
Legend
Estimated XX Actual XX
Presenter: Conor Shore
174
CanSat Budget – Other Costs
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Detail Description Unit Cost Quantity Total Cost
Travel, Accommodation and Sustenance
Costs
Travel Flights, rental car, train £758 10 people £7,580
VisasTourist Visa £122.42 4 people £489.67
ESTA £10.71 6 people £64.27
HousingBased on a stay from
13/06/2019 to 17/06/2019£325 10 people £3250
Food Assuming £15/person/day £60 10 people £600
GCS Hardware Cost
DisplayLaptop (provided by team
member)N/A 1 N/A
Telemetry900 MHz 9 dBi SS Yagi Antenna
SMA Male Connector£65.24 1 £65.24
Emergency CanSat All CanSat parts N/A £322.06 1 £322.06
Competition Entry Fee
N/A N/A £159.19 1 £159.19
Total Mission Cost: $16377.27
Legend
Estimated XX Actual XX
Presenter: Conor Shore
175
Program Schedule Overview
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
• The Gantt chart on the left shows MCP’s Program Schedule Overview
• OpenProject is used as MCP’s primary project management tool
•Milestone
Isolated Task
Parent Task
Exam/Holiday
Presenter: Conor Shore
Detailed Program Schedule
176CanSat 2020 PDR: Team 4920 Manchester CanSat Project
ID Subject Category Relation ID Subject Start date Finish date Category Assignee
143 Initial Design Concept 18.10.2019 23.10.2019 Mechanical Claudio Rapisarda
93 Component Selection Electrical parent of 94 CDH Selection 16.10.2019 26.10.2019 Electrical Conor Shore
93 Component Selection Electrical parent of 96 EPS Selection 15.10.2019 26.10.2019 Electrical Marin Dimitrov
93 Component Selection Electrical parent of 95 Sensor Selection 15.10.2019 26.10.2019 Electrical Khalid Ibrahim
94 CDH Selection Electrical parent of 126 Other components 16.10.2019 26.10.2019 Electrical Conor Shore
94 CDH Selection Electrical parent of 125 Teensy 3.2 vs 4.0 16.10.2019 19.10.2019 Electrical Marin Dimitrov
95 Sensor Selection Electrical parent of 110 Select Pitot Tube/Pressure Sensors 15.10.2019 26.10.2019 Electrical Khalid Ibrahim
96 EPS Selection Electrical parent of 113 Battery Selection 15.10.2019 26.10.2019 Electrical Marin Dimitrov
96 EPS Selection Electrical parent of 114 Power System Design/Boost Converter 15.10.2019 26.10.2019 Electrical Marin Dimitrov
89 Electrical Schematic Finalised Electrical parent of 93 Component Selection 15.10.2019 26.10.2019 Electrical Conor Shore
89 Electrical Schematic Finalised Electrical parent of 97 Schematic Design 27.10.2019 02.11.2019 Electrical Conor Shore
97 Schematic Design Electrical parent of 148 CanSat Addon Schmatic 27.10.2019 02.11.2019 Electrical Marin Dimitrov
97 Schematic Design Electrical parent of 147 CanSat Core Schmatic 27.10.2019 02.11.2019 Electrical Conor Shore
117 Container Mechanical parent of 163 Additional 04.11.2019 23.11.2019 Mechanical May Ling Har
117 Container Mechanical parent of 162 Basic 04.11.2019 04.11.2019 Mechanical May Ling Har
117 Container Mechanical parent of 208 Parachute 13.11.2019 17.11.2019 Decent Control Tim Chronis
120 Container Mechanical parent of 165 Additional 04.11.2019 23.11.2019 Mechanical May Ling Har
120 Container Mechanical parent of 164 Basic 04.11.2019 23.11.2019 Mechanical May Ling Har
120 Container Mechanical parent of 202 Parachute 13.11.2019 17.11.2019 Decent Control Tim Chronis
166 PCB Mechanical parent of 168 Add-on 04.11.2019 24.11.2019 Mechanical May Ling Har
166 PCB Mechanical parent of 167 Core 04.11.2019 09.11.2019 Mechanical May Ling Har
81 Build PCB Electrical parent of 109 Build CanSat Addon PCB 24.11.2019 07.12.2019 Electrical Conor Shore
81 Build PCB Electrical parent of 108 Build CanSat Core PCB 24.11.2019 07.12.2019 Electrical Marin Dimitrov
81 Build PCB Electrical parent of 103 Design CanSat Addon 2020 03.11.2019 09.11.2019 Electrical Marin Dimitrov
81 Build PCB Electrical parent of 102 Design CanSat Core PCB 03.11.2019 09.11.2019 Electrical
The following five slides show the Program Schedule in detail, including Competition Milestones, Academic Milestones and Holidays, Major Development Activities, Component/Hardware Deliveries, and Major I&T Activities and Milestones. Team members have been assigned to each task.
Presenter: Conor Shore
Detailed Program Schedule
177CanSat 2020 PDR: Team 4920 Manchester CanSat Project
ID Subject Category Relation ID Subject Start date Finish date Category Assignee
81 Build PCB Electrical parent of 107 Order Parts For CanSat Addon 2020 10.11.2019 16.11.2019 Electrical Conor Shore
81 Build PCB Electrical parent of 106 Order Parts for CanSat Core PCB 10.11.2019 16.11.2019 Electrical Conor Shore
81 Build PCB Electrical parent of 104 Order PCBs 10.11.2019 23.11.2019 Electrical Conor Shore
81 Build PCB Electrical parent of 105 Order Stencil From UoM PCB Lab 10.11.2019 23.11.2019 Electrical Marin Dimitrov
112 GCS Modular Design Electrical parent of 145 Data CSV to graphs 23.10.2019 15.12.2019 Electrical Teja Potocnik
112 GCS Modular Design Electrical parent of 159 Data to Google Earth workflow 08.12.2019 14.12.2019 Electrical Teja Potocnik
112 GCS Modular Design Electrical parent of 158 Graph Generation Script 01.12.2019 07.12.2019 Electrical Teja Potocnik
112 GCS Modular Design Electrical parent of 160 Modify current GCS to work this year 26.10.2019 30.11.2019 Electrical Teja Potocnik
112 GCS Modular Design Electrical parent of 157 Serial Spitter 26.10.2019 09.11.2019 Electrical Teja Potocnik
115 Sponsorship Updates 16.12.2019 16.12.2019 Admin May Ling Har
119 Concept 2 Mechanical parent of 120 Container 04.11.2019 23.11.2019 Mechanical May Ling Har
119 Concept 2 Mechanical parent of 121 Payload 28.11.2019 20.12.2019 Mechanical Richard Ryu
121 Payload Mechanical parent of 211 Camera Mechanism 18.12.2019 18.12.2019 Mechanical May Ling Har
121 Payload Mechanical parent of 199 Elevator Design 28.11.2019 07.12.2019 Decent Control Tim Chronis
121 Payload Mechanical parent of 196 Fuselage Structure 28.11.2019 04.12.2019 Mechanical Gaurav Jalan
121 Payload Mechanical parent of 198 Integration 08.12.2019 08.12.2019 Mechanical Richard Ryu
121 Payload Mechanical parent of 197 Parachute Bay 05.12.2019 07.12.2019 Mechanical Gaurav Jalan
121 Payload Mechanical parent of 200 Parachute Size 28.11.2019 07.12.2019 Decent Control Tim Chronis
121 Payload Mechanical parent of 195 Payload Deployment Mech 28.11.2019 07.12.2019 Mechanical Richard Ryu
121 Payload Mechanical parent of 201 Rudder Design 28.11.2019 07.12.2019 Decent Control Tim Chronis
121 Payload Mechanical parent of 212 Tail 20.12.2019 20.12.2019 Mechanical May Ling Har
121 Payload Mechanical parent of 194 Wing Structure 28.11.2019 07.12.2019 Mechanical Gaurav Jalan
90 CAD for Concept 1 and Concept 2 Mechanical parent of 187 Auxiliary Electronics 13.11.2019 23.11.2019 Mechanical May Ling Har
90 CAD for Concept 1 and Concept 2 Mechanical parent of 116 Concept 1 04.11.2019 22.12.2019 Mechanical Gaurav Jalan
90 CAD for Concept 1 and Concept 2 Mechanical parent of 119 Concept 2 04.11.2019 20.12.2019 Mechanical Richard Ryu
Presenter: Conor Shore
Detailed Program Schedule
178CanSat 2020 PDR: Team 4920 Manchester CanSat Project
ID Subject Category Relation ID Subject Start date Finish date Category Assignee
90 CAD for Concept 1 and Concept 2 Mechanical parent of 166 PCB 04.11.2019 24.11.2019 Mechanical May Ling Har
116 Concept 1 Mechanical parent of 117 Container 04.11.2019 23.11.2019 Mechanical May Ling Har
116 Concept 1 Mechanical parent of 118 Payload 13.11.2019 22.12.2019 Mechanical Gaurav Jalan
118 Payload Mechanical parent of 189 Camera Mechanism 13.11.2019 17.11.2019 Mechanical Richard Ryu
118 Payload Mechanical parent of 188 CCU 13.11.2019 14.11.2019 Mechanical Richard Ryu
118 Payload Mechanical parent of 205 Elevator Design 13.11.2019 23.11.2019 Decent Control Tim Chronis
118 Payload Mechanical parent of 191 Fuselage Structure 13.11.2019 24.11.2019 Mechanical Richard Ryu
118 Payload Mechanical parent of 193 Integration 26.11.2019 27.11.2019 Mechanical Gaurav Jalan
118 Payload Mechanical parent of 206 Parachute 13.11.2019 17.11.2019 Decent Control Tim Chronis
118 Payload Mechanical parent of 190 Parachute Bay 25.11.2019 25.11.2019 Mechanical Richard Ryu
118 Payload Mechanical parent of 204 Rudder Design 13.11.2019 23.11.2019 Decent Control Tim Chronis
118 Payload Mechanical parent of 213 Tail 20.12.2019 22.12.2019 Mechanical Gaurav Jalan
118 Payload Mechanical parent of 207 Winglet 24.11.2019 25.11.2019 Decent Control Tim Chronis
118 Payload Mechanical parent of 192 Wing Structure 13.11.2019 24.11.2019 Mechanical Gaurav Jalan
228 Christmas Break 13.12.2019 13.01.2020 Admin
229 Semester 1 Exams 13.01.2020 24.01.2020 Admin
132 First Draft Admin parent of 134 CDH 27.10.2019 26.01.2020 Electrical Conor Shore
132 First Draft Admin parent of 140 DC 23.12.2019 29.01.2020 Decent Control Tim Chronis
132 First Draft Admin parent of 137 EPS 27.10.2019 26.01.2020 Electrical Marin Dimitrov
132 First Draft Admin parent of 135 FSW 17.10.2019 26.01.2020 Electrical Mihnea Romanovschi
132 First Draft Admin parent of 136 GCS 17.10.2019 26.01.2020 Electrical Teja Potocnik
132 First Draft Admin parent of 141 I&T 17.10.2019 26.01.2020 Admin Teja Potocnik
132 First Draft Admin parent of 139 Mech 23.12.2019 29.01.2020 Mechanical Gaurav Jalan
132 First Draft Admin parent of 142 PM 17.10.2019 26.01.2020 Admin Conor Shore
132 First Draft Admin parent of 138 Sensor 27.10.2019 26.01.2020 Electrical Khalid Ibrahim
Presenter: Conor Shore
Detailed Program Schedule
179CanSat 2020 PDR: Team 4920 Manchester CanSat Project
ID Subject Category Relation ID Subject Start date Finish date Category Assignee
132 First Draft Admin parent of 214 Systems 26.12.2019 27.01.2020 Mechanical May Ling Har
131 PDR Admin parent of 132 First Draft 17.10.2019 29.01.2020 Admin May Ling Har
131 PDR Admin parent of 133 First Review 30.01.2020 30.01.2020 Admin May Ling Har
82 PDR Submission 31.01.2020 31.01.2020 Admin May Ling Har
123 Prototype 1 Manufacture 07.12.2019 01.02.2020 Mechanical Richard Ryu
111 Modular Code Framework Electrical parent of 149 Create all sensor class for FSW 26.10.2019 02.11.2019 Electrical Mihnea Romanovschi
111 Modular Code Framework Electrical parent of 153 Flowchart for FSW operation 26.10.2019 13.11.2019 Electrical Mihnea Romanovschi
111 Modular Code Framework Electrical parent of 155 FSW logic state machine 14.11.2019 21.11.2019 Electrical Mihnea Romanovschi
111 Modular Code Framework Electrical parent of 154 PID functionality 26.10.2019 23.11.2019 Electrical Khalid Ibrahim
111 Modular Code Framework Electrical parent of 156 Software intergration and test 02.12.2019 02.02.2020 Electrical Mihnea Romanovschi
111 Modular Code Framework Electrical parent of 150 Template for iteration framework 26.10.2019 16.11.2019 Electrical Mihnea Romanovschi
111 Modular Code Framework Electrical parent of 152 Unit test for iteration framework and sensor 17.11.2019 01.12.2019 Electrical Mihnea Romanovschi
85 Test Launch 2 08.03.2020 08.03.2020 Admin May Ling Har
210 Component Level Testing 30.11.2019 08.03.2020 Admin Teja Potocnik
215 Overall Design Revision 2 Admin parent of 219 Descent Control 10.02.2020 09.03.2020 Decent Control Tim Chronis
215 Overall Design Revision 2 Admin parent of 217 Electrical 10.02.2020 09.03.2020 Electrical Marin Dimitrov
215 Overall Design Revision 2 Admin parent of 218 Mechanical 10.02.2020 09.03.2020 Mechanical May Ling Har
86 University CanSat Competition 01.04.2020 01.04.2020 Admin May Ling Har
88 Test Launch 3 01.04.2020 01.04.2020 Admin May Ling Har
87 CDR Submission 03.04.2020 03.04.2020 Admin May Ling Har
216 Overall Design Revision 3 Admin parent of 222 Descent Control 10.03.2020 03.04.2020 Decent Control Tim Chronis
216 Overall Design Revision 3 Admin parent of 220 Electrical 10.03.2020 03.04.2020 Electrical Marin Dimitrov
216 Overall Design Revision 3 Admin parent of 221 Mechanical 10.03.2020 03.04.2020 Mechanical May Ling Har
230 Easter Break 27.03.2020 20.04.2020 Admin
231 Semester 2 Exams 13.05.2020 03.06.2020 Admin
Presenter: Conor Shore
Detailed Program Schedule
180CanSat 2020 PDR: Team 4920 Manchester CanSat Project
ID Subject Category Relation ID Subject Start date Finish date Category Assignee
223 Design/Manufacturing Buffer Admin parent of 226 Descent Control 04.04.2020 10.06.2020 Decent Control Tim Chronis
223 Design/Manufacturing Buffer Admin parent of 224 Electrical 04.04.2020 10.06.2020 Electrical Marin Dimitrov
223 Design/Manufacturing Buffer Admin parent of 225 Mechanical 04.04.2020 10.06.2020 Mechanical May Ling Har
227 AAS CanSat Competition 11.06.2020 11.06.2020 Admin May Ling Har
Presenter: Conor Shore
181
Conclusions
•
•
CanSat 2020 PDR: Team 4920 Manchester CanSat Project
Major Accomplishments
• Significant funding secured for this year of the project, with the addition of four new sponsors
• First revision on standardised PCB design manufactured and assembled• Majority of components obtained• Design of Container and Payload finished, prototyping work started
Major Unfinished Work
• First full prototype of CanSat• Testing of new electronic components for this year• Full systems test launch, scheduled for early February
Justification for Progress to the Next Stage
• Significant funding for project obtained• At present, all major goals have been completed on time (on track)
Presenter: Conor Shore