CANDLEWOOD elementary school Originally Built Years of Previous work (since 1988) Acreage Total Square Footage Number of Buildings on Campus Number of Classrooms Current Number of Portables 1988 2009 8.011 94,024 1 45 2 $279,780 $1,398,900 $61,250 $10,000 $348,000 $100,000 $60,000 $210,000 $27,000 $2,494,930 2016 Bond Proposal The above listed campus is programmed to receive the following items: Proposed Facility Improvements: Replace Panel, Upgrade Fire Alarm System, Upgrade Smoke & Duct Detectors - Complete Replace Sewer Lines under Building - Fall 2020 Modifications to Life Skills - Fall 2020 Add ADA/TAS Compliant Room Signage - Fall 2020 Minor Library Expansion - Fall 2020 Repair Roof Leaks ‐ Thru Wall Flashing - Spring 2019 (In progress) Refurbish Metal Roof - Spring 2019 (In progress) Clinic & Lounge Relocation - Fall 2020 Playground Shade Structure 30’x40’ - Complete

Transcript of CANDLEWOOD elementary school · 5.916 68,526 3 27 None campus assessment $1,537,500 $2,800 $65,520...

Page 1: CANDLEWOOD elementary school · 5.916 68,526 3 27 None campus assessment $1,537,500 $2,800 $65,520 $75,600 $80,000 $27,000 $1,788,420 2016 Bond Proposal The above listed campus is

campus needs

CANDLEWOOD elementary school Originally Built Years of Previous work (since 1988) AcreageTotal Square Footage Number of Buildings on Campus Number of Classrooms Current Number of Portables

1988 2009 8.011 94,024 1 45 2

$279,780 $1,398,900

$61,250 $10,000

$348,000 $100,000

$60,000 $210,000

$27,000 $2,494,930

2016 Bond ProposalThe above listed campus is programmed to receive the following items:

Proposed Facility Improvements:Replace Panel, Upgrade Fire Alarm System, Upgrade Smoke & Duct Detectors - Complete Replace Sewer Lines under Building - Fall 2020Modifications to Life Skills - Fall 2020Add ADA/TAS Compliant Room Signage - Fall 2020Minor Library Expansion - Fall 2020Repair Roof Leaks ‐ Thru Wall Flashing - Spring 2019 (In progress)Refurbish Metal Roof - Spring 2019 (In progress)Clinic & Lounge Relocation - Fall 2020Playground Shade Structure 30’x40’ - Complete

Page 2: CANDLEWOOD elementary school · 5.916 68,526 3 27 None campus assessment $1,537,500 $2,800 $65,520 $75,600 $80,000 $27,000 $1,788,420 2016 Bond Proposal The above listed campus is

campus needs

CONVERSE elementary school

Proposed Facility Improvements: Repair Amphitheater and Site Drainage Playground - On Hold Shade Structure 30’x40’ - Fall 2020

Originally Built Years of Previous work (since 2007) AcreageTotal Square Footage Number of Buildings on Campus Number of Classrooms Current Number of Portables

2007 None 22.14 115,880 1 38 2

campus assessment

$450,000 $27,000

$477,000

2016 Bond ProposalThe above listed campus is programmed to receive the following items:

Page 3: CANDLEWOOD elementary school · 5.916 68,526 3 27 None campus assessment $1,537,500 $2,800 $65,520 $75,600 $80,000 $27,000 $1,788,420 2016 Bond Proposal The above listed campus is

campus needs

CORONADO VILLAGE elementary school Originally Built Years of Previous work (since 1988) AcreageTotal Square Footage Number of Buildings on Campus Number of Classrooms Current Number of Portables

1970 2009 5.916 68,526 3 27 None

campus assessment

$1,537,500 $2,800

$65,520 $75,600 $80,000 $27,000

$1,788,420

2016 Bond ProposalThe above listed campus is programmed to receive the following items:

Proposed Facility Improvements: Replace Roof - Fall 2020ADA sidewalk to Playground Equipment - Fall 2020Replace Gym Flooring with Resilient Sports Floor - CompleteReplace Roof (Gym) - - Fall 2020Provide Covered Walkways between Classrooms & Gym - Fall 2020Playground Shade Structure 30’x40’ - Complete

Page 4: CANDLEWOOD elementary school · 5.916 68,526 3 27 None campus assessment $1,537,500 $2,800 $65,520 $75,600 $80,000 $27,000 $1,788,420 2016 Bond Proposal The above listed campus is

campus needs

CRESTVIEW elementary school

Proposed Facility Improvements: Add Secure Entry Vestibule - Fall 2020Provide Accessible Curb Ramps to Main Entrance - Fall 2020Replace Egress Doors - Fall 2020Add ADA/TAS Compliant Room Signage - Fall 2020Kitchen Addition, Stage Addition, and Minor Cafeteria Renovations - Fall 2020 Replace Gym Flooring With Resilient Sports Floor - CompleteReplace Roof (Gym) - Fall 2020Renovate Toilet Rooms - Fall 2020Playground Shade Structure 30’x40’ - Fall 2020

Originally Built Years of Previous work (since 1974) AcreageTotal Square Footage Number of Buildings on Campus Number of Classrooms Current Number of Portables

1974 1994 7 66,184 3 30 None

campus assessment

$60,000 $36,000 $82,500 $10,000

$3,444,000 $65,520 $75,600

$836,400 $27,000

$4,637,020

2016 Bond ProposalThe above listed campus is programmed to receive the following items:

Page 5: CANDLEWOOD elementary school · 5.916 68,526 3 27 None campus assessment $1,537,500 $2,800 $65,520 $75,600 $80,000 $27,000 $1,788,420 2016 Bond Proposal The above listed campus is

campus needs

ELOLF elementary school

Proposed Facility Improvements: Add Secure Entry Vestibule - CompleteReplace Chillers - CompleteReplace Corroded Galvanized Water Pipes Campus Wide - Fall 2020Replace Roof (Original Building) - CompleteLife Skill Modifications - Fall 2020Provide ADA/TAS Compliant Room Signage - Fall 2020Kitchen Addition and Minor Cafeteria Renovations - Fall 2020Minor Library Expansion - Fall 2020Playground Shade Structure 30’ x 40’ - Fall 2020Relocate Clinic & Lounge - Fall 2020

Originally Built Years of Previous work (since 1993) AcreageTotal Square Footage Number of Buildings on Campus Number of Classrooms Current Number of Portables

1993 None 10.302 92,847 1 47 None

campus assessment

$60,000 $250,000 $187,500

$1,391,955 $61,250 $8,000

$2,460,000 $348,000

$27,000 $210,000

$5,003,705

2016 Bond ProposalThe above listed campus is programmed to receive the following items:

Page 6: CANDLEWOOD elementary school · 5.916 68,526 3 27 None campus assessment $1,537,500 $2,800 $65,520 $75,600 $80,000 $27,000 $1,788,420 2016 Bond Proposal The above listed campus is

campus needs

FRANZ elementary school Originally Built Years of Previous work (since 1968) AcreageTotal Square Footage Number of Buildings on Campus Number of Classrooms Current Number of Portables

1968 2008 6.232 59,543 2 22 None

campus assessment

$250,000 $3,850

$65,520 $75,600

$760,515 $135,000

$85,000 $27,000

$1,402,485

2016 Bond ProposalThe above listed campus is programmed to receive the following items:

Proposed Facility Improvements: Add Outdoor Parking and Security Lighting - Fall 2019ADA Sidewalk to Playground Equipment - Fall 2019Replace Gym Flooring with Resilient Sports Floor - Complete Replace Roof (Gym) - Fall 2019Replace Roof - Fall 2019Upgrade Flooring to Match Throughout Campus - Summer 2019Playground Equipment Replacement - CompletePlayground Shade Structure 30'x40‘ - Complete

Page 7: CANDLEWOOD elementary school · 5.916 68,526 3 27 None campus assessment $1,537,500 $2,800 $65,520 $75,600 $80,000 $27,000 $1,788,420 2016 Bond Proposal The above listed campus is

campus needs

HARTMAN elementary school Originally Built Years of Previous work (since 2002) AcreageTotal Square Footage Number of Buildings on Campus Number of Classrooms Current Number of Portables

2002 2008 18.376 97,476 1 42 1

campus assessment

$60,000 $75,250 $37,500 $54,000

$226,750

2016 Bond ProposalThe above listed campus is programmed to receive the following items:

Proposed Facility Improvements: Add Secure Entry Vestibule - Fall 2019Replace Carpeting In Corridors With VCT - CompleteRemove Wall Covering In Corridor - CompletePlayground Shade Structure 30’x40’ - Complete

Page 8: CANDLEWOOD elementary school · 5.916 68,526 3 27 None campus assessment $1,537,500 $2,800 $65,520 $75,600 $80,000 $27,000 $1,788,420 2016 Bond Proposal The above listed campus is

campus needs

HOPKINS elementary school Originally Built Years of Previous work (since 1969 ) AcreageTotal Square Footage Number of Buildings on Campus Number of Classrooms Current Number of Portables

1969 2003 11.89 105,741 2 44 1

campus assessment

$60,000 $250,000

$61,500 $100,000

$8,050 $75,600

$555,150

2016 Bond ProposalThe above listed campus is programmed to receive the following items:

Proposed Facility Improvements: Add Secure Entry Vestibule - CompleteReplace Chillers - CompleteImprove Drainage Next to Gym - Spring 2019Mechanical Ductwork Modifications - Summer 2020ADA Sidewalk to Playground Equipment - CompleteReplace Roof (Gym) - Complete

Page 9: CANDLEWOOD elementary school · 5.916 68,526 3 27 None campus assessment $1,537,500 $2,800 $65,520 $75,600 $80,000 $27,000 $1,788,420 2016 Bond Proposal The above listed campus is

campus needs

MASTERS elementary school Originally Built Years of Previous work (since 2008) AcreageTotal Square Footage Number of Buildings on Campus Number of Classrooms Current Number of Portables

2008 2009 16.53 94,532 1 38 2

campus assessment

$12,450 $12,450

2016 Bond ProposalThe above listed campus is programmed to receive the following item:

Proposed Facility Improvements: Playground Swings- 1 bay 5" arch swing frame - Complete

Page 10: CANDLEWOOD elementary school · 5.916 68,526 3 27 None campus assessment $1,537,500 $2,800 $65,520 $75,600 $80,000 $27,000 $1,788,420 2016 Bond Proposal The above listed campus is

campus needs

MILLER’S POINT elementary school Originally Built Years of Previous work (since 1986) AcreageTotal Square Footage Number of Buildings on Campus Number of Classrooms Current Number of Portables

1986 1991 8.291 82,101 2 40 None

campus assessment

$1,065,000 $2,460,000

$64,800 $60,000

$125,000 $3,774,800

2016 Bond ProposalThe above listed campus is programmed to receive the following items:

Proposed Facility Improvements: Renovate Administration Area to Centralize; Add Secure Entry Vestibule - Fall 2020 Kitchen Addition; Minor Cafeteria Renovations - Fall 2020Remove Wall Covering in Corridor - CompleteRemodel PPCD Restroom - Fall 2020Add Kinder Playground Equipment and Shade Structure - Fall 2019 (In Progress)

Page 11: CANDLEWOOD elementary school · 5.916 68,526 3 27 None campus assessment $1,537,500 $2,800 $65,520 $75,600 $80,000 $27,000 $1,788,420 2016 Bond Proposal The above listed campus is

OLYMPIA elementary school Originally Built Years of Previous work (since 1978) AcreageTotal Square Footage Number of Buildings on Campus Number of Classrooms Current Number of Portables

1978 1985 7 64,767 3 30 None

$315,000 $2,400,000

$124,100 $40,000 $65,520 $75,600

$102,000 $3,122,220

2016 Bond ProposalThe above listed campus is programmed to receive the following items:

Proposed Facility Improvements: Renovate Administration Area to Centralize; Add Secure Entry Vestibule - Fall 2020Kitchen Addition; minor Cafeteria renovations - Fall 2020Remove Carpet in Classroom and Add VCT - CompleteRemove Carpet in Corridor and Add VCT - Complete Replace Gym Flooring with Resilient Sports Floor - CompleteReplace Roof (Gym) - Fall 2020Playground Shade Structure 30’ x 40’ and Kinder Playground Equip. Replacement - Fall 2020

Page 12: CANDLEWOOD elementary school · 5.916 68,526 3 27 None campus assessment $1,537,500 $2,800 $65,520 $75,600 $80,000 $27,000 $1,788,420 2016 Bond Proposal The above listed campus is

campus needs

PARK VILLAGE elementary school

Proposed Facility Improvements: Add Secure Entry Vestibule - Fall 2020Replace Roof (Annex) - CompleteKitchen Addition & Minor Cafeteria Renovations - Fall 2020 Replace Roof (Original) - CompleteReplace Roof (Gym) - CompleteAttach Gym and 12-classroom Wing to Building - Fall 2020Playground Shade Structure 30’ x 40‘ - Fall 20201 Playground Equipment Replacement - Fall 2020

Originally Built Years of Previous work (since 1999) AcreageTotal Square Footage Number of Buildings on Campus Number of Classrooms Current Number of Portables

1999 2009 22.52 77,770 2 34 1

campus assessment

$60,000 $258,375

$2,460,000 $373,500

$75,600 $4,250,000

$54,000 $125,000

$7,656,475

2016 Bond ProposalThe above listed campus is programmed to receive the following items:

Page 13: CANDLEWOOD elementary school · 5.916 68,526 3 27 None campus assessment $1,537,500 $2,800 $65,520 $75,600 $80,000 $27,000 $1,788,420 2016 Bond Proposal The above listed campus is

campus needs

PASCHALL elementary school Originally Built Years of Previous work (since 2000) AcreageTotal Square Footage Number of Buildings on Campus Number of Classrooms Current Number of Portables

2000 None 20 104,243 2 47 6

campus assessment

$60,000 $250,000

$1,200,000

$15,500 $27,000

$100,000 $2,460,000 $4,112,500

2016 Bond ProposalThe above listed campus is programmed to receive the following items:

Proposed Facility Improvements: Add Secure Entry Vestibule - Fall 2020Replace Chillers - CompleteRegrade and Excavate Under Floor - Fall 2020Add 6-ft Chainlink Fence at Bus Loop to Secure Campus (425 LF); Complete front 4-ft Chainlink Fence with 6-ft High Fence (350 LF) - CompletePlayground Shade Structure 30’x40’ - Fall 2020Repair Roof Drainage - CompleteKitchen Addition; Minor Cafeteria Renovations - Fall 2020

Page 14: CANDLEWOOD elementary school · 5.916 68,526 3 27 None campus assessment $1,537,500 $2,800 $65,520 $75,600 $80,000 $27,000 $1,788,420 2016 Bond Proposal The above listed campus is

campus needs

ROLLING MEADOWS elementary school

Proposed Facility Improvements: Install Portable Classrooms - Complete

Originally Built Years of Previous work (since 2009) AcreageTotal Square Footage Number of Buildings on Campus Number of Classrooms Current Number of Portables

2009 None 16.34 109,231 1 24 None

campus assessment

$150,000 $150,000

2016 Bond ProposalThe above listed campus is programmed to receive the following item:

Page 15: CANDLEWOOD elementary school · 5.916 68,526 3 27 None campus assessment $1,537,500 $2,800 $65,520 $75,600 $80,000 $27,000 $1,788,420 2016 Bond Proposal The above listed campus is

campus needs

SALINAS elementary school

Proposed Facility Improvements: Add 6-ft Chainlink Fence at Playground Area by Gym - CompletePlayground Shade Structure 30’x40’ - Complete

Originally Built Years of Previous work (since 2005) AcreageTotal Square Footage Number of Buildings on Campus Number of Classrooms Current Number of Portables

2005 None 19.38 101,105 1 39 None

campus assessment

$5,500 $54,000 $59,500

2016 Bond ProposalThe above listed campus is programmed to receive the following items:

Page 16: CANDLEWOOD elementary school · 5.916 68,526 3 27 None campus assessment $1,537,500 $2,800 $65,520 $75,600 $80,000 $27,000 $1,788,420 2016 Bond Proposal The above listed campus is

campus needs

SPRING MEADOWS elementary school

Proposed Facility Improvements: Renovate Administration Area to Centralize; Add Secure Entry Vestibule - Fall 2020 Replace Sewer System - Fall 2020Replace Roof (Classroom Annex) - Fall 2019 Add ADA/TAS Compliant Signage - Fall 2020 Remove Carpet in Classrooms; Install VCT - CompleteReplace Gym Flooring with Resilient Sports Floor - CompleteReplace Roof (Gym) - Fall 2020

Originally Built Years of Previous work (since 1984) AcreageTotal Square Footage Number of Buildings on Campus Number of Classrooms Current Number of Portables

1984 1991 8.906 79,606 2 36 None

campus assessment

$600,000 $750,000 $139,290

$8,000 $188,500

$65,520 $75,600

$1,826,910

2016 Bond ProposalThe above listed campus is programmed to receive the following items:

Page 17: CANDLEWOOD elementary school · 5.916 68,526 3 27 None campus assessment $1,537,500 $2,800 $65,520 $75,600 $80,000 $27,000 $1,788,420 2016 Bond Proposal The above listed campus is

campus needs

WOODLAKE elementary school Originally Built Years of Previous work (since 1978) AcreageTotal Square Footage Number of Buildings on Campus Number of Classrooms Current Number of Portables

1978 1992 9.327 73,489 3 44 2

campus assessment

$315,000 $360,000 $210,300

$8,000 $2,460,000

$1,430,000 $141,800

$65,520 $75,600

$100,000 $54,000

$5,220,220

2016 Bond ProposalThe above listed campus is programmed to receive the following items:

Proposed Facility Improvements: Renovate Administration Area to Centralize; Add Secure Entry Vestibule - Fall 2020 Upgrade Fire Alarm System, Smoke Detectors & Duct Detectors - Spring 2019 (In Progress)Replace Roof - Fall 2019Add ADA/TAS Compliant Signage - Fall 2020Kitchen Addition; Minor Cafeteria Renovations - Fall 2020Replace Library (4,850sf); Remodel old Library Space (2,300sf); Convert to New Classrooms and Staff Restrooms - Fall 2020VCT for Classrooms and Café - CompleteReplace Gym Flooring with Resilient Sports Floor - CompleteReplace Roof (Gym - Fall 20201 Playground Structure Replacement - CompletePlayground Shade Structure 30’ x 40’ - Complete

Page 18: CANDLEWOOD elementary school · 5.916 68,526 3 27 None campus assessment $1,537,500 $2,800 $65,520 $75,600 $80,000 $27,000 $1,788,420 2016 Bond Proposal The above listed campus is

campus needs

JUDSON middle school Originally Built Years of Previous work (since 1985) AcreageTotal Square Footage Number of Buildings on Campus Number of Classrooms Current Number of Portables

1985 1987 62.775 281,641 5 129 None

campus assessment

$23,000 $22,200 $31,000

$150,000 $700,406

$20,000 $1,039,805

$90,000 $2,076,411

2016 Bond ProposalThe above listed campus is programmed to receive the following items:

Proposed Facility Improvements: Secure Public Entrance (after hours near front office) - Spring 2021Upgrade Smoke Detector to Addressable Devices ADA - Spring 2020Upgrades based on TEA Audit - Spring 2021Upgrade Life Skills Room - Spring 2021Overlay Asphalt Parking and Drives - Spring 2021Add ADA/TAS Compliant Room Signage - Spring 2021Replace Flooring Campus Wide - Fall 2019 (In progress)Replace Gym Bleachers - Complete

Page 19: CANDLEWOOD elementary school · 5.916 68,526 3 27 None campus assessment $1,537,500 $2,800 $65,520 $75,600 $80,000 $27,000 $1,788,420 2016 Bond Proposal The above listed campus is

campus needs

KIRBY middle school Originally Built Years of Previous work (since 1964) AcreageTotal Square Footage Number of Buildings on Campus Number of Classrooms Current Number of Portables

1964 2014 19.015 193,999 7 51 None

campus assessment

$750,000 $409,500

$10,080,000 $10,000,000

$40,000 $50,000

$115,872 $120,000

$40,000 $21,605,372

2016 Bond ProposalThe above listed campus is programmed to receive the following items:

Proposed Facility Improvements: Replace Main Switchgear - Summer 2020Replace Roof (700 Buildings) - Summer 2020Raze & Replace 600 Building (Gym/Athletics) - Summer 2020 Raze 400 Building; Replace 100, 500 Buildings (Admin/Athletics) - Summer 2020 Upgrade Sound System at Fine Arts - PendingRepair Bus Loop - Summer 2020Retrofit Lighting at 100, 200, 700 Buildings (CPS Rebate) - Summer 2020Relocate and Replace Water Line Under Sidewalks - Summer 2020Replace Bleachers at Sports Field - Complete

Page 20: CANDLEWOOD elementary school · 5.916 68,526 3 27 None campus assessment $1,537,500 $2,800 $65,520 $75,600 $80,000 $27,000 $1,788,420 2016 Bond Proposal The above listed campus is

campus needs

KITTY HAWK middle school Originally Built Years of Previous work (since 1975) AcreageTotal Square Footage Number of Buildings on Campus Number of Classrooms Current Number of Portables

1975 2009 24 197,952 13 71 None

campus assessment

$1,125,000 $750,000 $519,580

$10,340,000 $7,980,000

$150,000 $247,173

$15,000 $21,126,753

2016 Bond ProposalThe above listed campus is programmed to receive the following items:

Proposed Facility Improvements: Replace Roofs (100, 400, 500, 600, 1000, and 1100 Buildings) - Summer 2020Replace Panel Boards, Switchgear, & Transformer - Summer 2020Replace Bus Loop - Summer 2020Raze & Replace 1300 Building (Gym) - Summer 2020Raze & Replace 200, 300, 1200 Buildings (Acad) - Summer 2020Replace Sewer Piping at 400 Building - Summer 2020Retrofit Lighting (CPS Rebate) - Summer 2020Add ADA/TAS Compliant Room Signage - Summer 2020

Page 21: CANDLEWOOD elementary school · 5.916 68,526 3 27 None campus assessment $1,537,500 $2,800 $65,520 $75,600 $80,000 $27,000 $1,788,420 2016 Bond Proposal The above listed campus is

campus needs

METZGER middle school Originally Built Years of Previous work (since 2002) AcreageTotal Square Footage Number of Buildings on Campus Number of Classrooms Current Number of Portables

2002 2005 51.739 221,892 1 51 None

campus assessment

$20,000 $25,000

$195,500 $35,520

$276,020

2016 Bond ProposalThe above listed campus is programmed to receive the following items:Proposed Facility Improvements: Secure Entry Vestibule - Spring 2020Repair Dilution Tanks and Chemical Drain Lines - Complete Remove Carpet in Classrooms; Replace with VCT - Fall 2019 (In Progress)Replace Carpet (Not in Classrooms) - Complete

Page 22: CANDLEWOOD elementary school · 5.916 68,526 3 27 None campus assessment $1,537,500 $2,800 $65,520 $75,600 $80,000 $27,000 $1,788,420 2016 Bond Proposal The above listed campus is

campus needs

WOODLAKE HILLS middle school

Proposed Facility Improvements: Repair/Replace Chiller - CompleteReplace Tennis Courts; Repair Soil Retainers; Repair Student Drop Off; Replace Roof - CompleteRetrofit Light Fixtures (CPS Rebate) - CompleteRepair/Replace Acid Dilution Tanks - CompleteReplace Stage Lighting - Fall 2020 & Sound System - CompleteRelocate Life Skills Restroom and Add Shower - Spring 2021Replace VCT Floor in Corridor - Complete

Originally Built Years of Previous work (since 1996) AcreageTotal Square Footage Number of Buildings on Campus Number of Classrooms Current Number of Portables

1996 None 37.717 169,145 1 62 None

campus assessment

$600,000 $4,548,400

$253,718 $25,000 $10,000

$160,000 $125,000

$5,722,118

2016 Bond ProposalThe above listed campus is programmed to receive the following items:

Page 23: CANDLEWOOD elementary school · 5.916 68,526 3 27 None campus assessment $1,537,500 $2,800 $65,520 $75,600 $80,000 $27,000 $1,788,420 2016 Bond Proposal The above listed campus is

campus needs

JUDSON high school Originally Built Years of Previous work (since 2008) AcreageTotal Square Footage Number of Buildings on Campus Number of Classrooms Current Number of Portables

2008 2014 54.77 439,273 2 131 3

campus assessment

$45,000 $350,000 $395,000

2016 Bond ProposalThe above listed campus is programmed to receive the following items:Proposed Facility Improvements: Motorized Shades - Commons Area J118 - CompleteRemodel Ag Farm Complex - Complete

Page 24: CANDLEWOOD elementary school · 5.916 68,526 3 27 None campus assessment $1,537,500 $2,800 $65,520 $75,600 $80,000 $27,000 $1,788,420 2016 Bond Proposal The above listed campus is
Page 25: CANDLEWOOD elementary school · 5.916 68,526 3 27 None campus assessment $1,537,500 $2,800 $65,520 $75,600 $80,000 $27,000 $1,788,420 2016 Bond Proposal The above listed campus is

campus needs

WAGNER high school Originally Built Years of Previous work (since 2003) AcreageTotal Square Footage Number of Buildings on Campus Number of Classrooms Current Number of Portables

2003 2011 100.00 419150 2 68 7

campus assessment

$220,000 $65,090 $20,000 $75,000

$150,000 $45,000

$150,000 $150,000 $150,000

$1,025,090

2016 Bond ProposalThe above listed campus is programmed to receive the following items:Proposed Facility Improvements: Lightning Protection - CompleteRetrofit Lighting - 46 Chandelier Fixtures at Main Corridor - CompleteRetrofit Lighting - Replace Canister Lights at Auditorium - CompleteLED Marquee 8’x 5’ - Fall 2021Remedy Heaving Piping on Main Water Line to Campus - Spring 2021ADA Room Sign Replacement & Graphics Package - Spring 2021Xeriscape Landscaping at All Building Entrances - Fall 2019 (In Progress)Repair Buckling Roof Drains - CompleteRe-direct Scuppers to Not Drain into Building - Complete

Page 26: CANDLEWOOD elementary school · 5.916 68,526 3 27 None campus assessment $1,537,500 $2,800 $65,520 $75,600 $80,000 $27,000 $1,788,420 2016 Bond Proposal The above listed campus is

campus needs

PERFORMING ARTS CENTER

Proposed Facility Improvements: Replace Chiller - CompleteReplace Low Slope Built-Up Roof - Fall 2019Replace Carpet - Complete

Originally Built Years of Previous work (since 1996) AcreageTotal Square Footage Number of Buildings on Campus Number of Classrooms Current Number of Portables

1996 None 18.612 66,899 1 1 None

campus assessment

$450,000 $1,305,000

$69,828 $1,824,828

2016 Bond ProposalThe above listed campus is programmed to receive the following items:

Page 27: CANDLEWOOD elementary school · 5.916 68,526 3 27 None campus assessment $1,537,500 $2,800 $65,520 $75,600 $80,000 $27,000 $1,788,420 2016 Bond Proposal The above listed campus is

campus needs

RUTLEDGE STADIUM

Proposed Facility Improvements: Replace Parking at Stadium (600 Spaces)- Complete

Originally Built Years of Previous work (since 2007) AcreageTotal Square Footage Number of Buildings on Campus Number of Classrooms Current Number of Portables

2007 None Included w/ Alt. 33,677 11 None None

campus assessment

$1,432,460 $1,432,460

2016 Bond ProposalThe above listed campus is programmed to receive the following item:

Page 28: CANDLEWOOD elementary school · 5.916 68,526 3 27 None campus assessment $1,537,500 $2,800 $65,520 $75,600 $80,000 $27,000 $1,788,420 2016 Bond Proposal The above listed campus is

campus needs

SECONDARY alternative school

Proposed Facility Improvements: Add Secure Entry Vestibule - Spring 2021ADA Upgrades based on TEA Audit - CompleteAdd Parking (68 Spaces) - Spring 2021Retrofit Lighting Throughout Campus – Replace all T12 Fixtures with LED - CompleteProvide ADA/TAS Compliant Room Signage - CompleteAdd Identifying Signage - CompleteReplace Gym Flooring with Resilient Sports Floor - CompleteReplace Roof (Gym) - Summer 2019

Originally Built Years of Previous work (since 1955) AcreageTotal Square Footage Number of Buildings on Campus Number of Classrooms Current Number of Portables

1955 1984 10 136,380 3 47 2

campus assessment

$80,000 $44,000 $89,760

$169,000 $8,000

$15,000 $65,520 $75,600

$546,880

2016 Bond ProposalThe above listed campus is programmed to receive the following items:

Page 29: CANDLEWOOD elementary school · 5.916 68,526 3 27 None campus assessment $1,537,500 $2,800 $65,520 $75,600 $80,000 $27,000 $1,788,420 2016 Bond Proposal The above listed campus is

campus needs

POLICE DEPARTMENT

Proposed Facility Improvements: ADA Upgrades based on TEA Audit - CompleteRetrofit Lighting - Replace all T12 Fixtures to LED - Complete

Originally Built Years of Previous work (since -) AcreageTotal Square Footage Number of Buildings on Campus Number of Classrooms Current Number of Portables

Included in JECC Included in JECC Included in JECC 1,928 Included in JECC None None

campus assessment

$46,000 $6,960

$52,960

2016 Bond ProposalThe above listed campus is programmed to receive the following items:

Page 30: CANDLEWOOD elementary school · 5.916 68,526 3 27 None campus assessment $1,537,500 $2,800 $65,520 $75,600 $80,000 $27,000 $1,788,420 2016 Bond Proposal The above listed campus is

campus needs

JISD TRANSPORTATION Originally Built Years of Previous work (since 1976) AcreageTotal Square Footage Number of Buildings on Campus Number of Classrooms Current Number of Portables

1976 2005 8.959 24,158 2 None 2

campus assessment

$148,500 $148,500

2016 Bond ProposalThe above listed campus is programmed to receive the following item:

Proposed Facility Improvements: Roof Replacement - Repair Garage on School Street - Fall 2020