Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building Committee HMFH ARCHITECTS 130 Bishop Allen Drive, Cambridge, MA 02139 617 492 2200 hmfh.com

Transcript of Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School...

Page 1: Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building

Brookline High SchoolCampus Expansion Update

Feasibility StudyA P R I L 13, 2017

Brookline High SchoolBuilding Committee

H M F H A R C H I T E C T S130 Bishop Allen Drive, Cambridge, MA 02139 617 492 2200 hmfh.com

Page 2: Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building

H M F H A R C H I T E C T SBHS Campus Expansion

Existing

MB

TA G

REE

N L

INE

Massing

Page 3: Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building

H M F H A R C H I T E C T SBHS Campus Expansion

OPTION 4A9th Grade Academy at Cypress St. with BHS-Greenough Renovate Existing Science & New 5-Classroom Addition

Massing

MB

TA G

REE

N L

INE

Renovate Existing Science35,500 sf

New Construction at BHS7,500 sf

New Construction at 9th Grade Academy109,810 sf

Page 4: Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building

H M F H A R C H I T E C T SBHS Campus Expansion

Massing

OPTION 4B9th Grade Academy at Cypress St. with BHS-Greenough New Science at Roberts Wing & Renovate 3rd Floor as Core Academics

MB

TA G

REE

N L

INE

Renovate Existing ScienceInto Classrooms36,500 sf

New Construction at BHS44,100 sf

New Construction at 9th Grade Academy109,810 sf

Page 5: Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building

H M F H A R C H I T E C T SBHS Campus Expansion

OPTION 4C9th Grade Academy at Cypress St. and MBTA with BHS-Greenough Renovate Existing Science & New 5-Classroom Addition

Massing

MB

TA G

REE

N L

INE

Renovate Existing Science35,500 sf

New Construction at BHS7,500 sf

New Construction at 9th Grade Academy112,700 sf

Page 6: Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building

H M F H A R C H I T E C T SBHS Campus Expansion

OPTION 4D9th Grade Academy at Cypress St. and MBTA with BHS-Greenough New Science at Roberts Wing & Renovate 3rd Floor as Core Academics

Massing

MB

TA G

REE

N L

INE

Renovate Existing Scienceinto Classrooms36,500 sf

New Construction at BHS50,400 sf

New Construction at 9th Grade Academy112,700 sf

Page 7: Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building

H M F H A R C H I T E C T SBHS Campus Expansion

OPTION 4A & 4B9th Grade Academy at Cypress St. with BHS-Greenough

MBTA

DINNINGCOMMONS

LIBRARYCOLLAB

CORE ACADEMIC

Massing4A & 4B

Section 4A & 4B

Page 8: Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building

H M F H A R C H I T E C T SBHS Campus Expansion 50’ 100’

OPTION 4A & 4B9th Grade Academy at Cypress plus see BHS-Greenough Options

Lower Level Plan 1st Floor Plan

TAPPAN ST

BRINGTON RD

CYPR

ESS

ST

DIN

NIN

GC

OM

MO

NS

MBTAGREEN LINE

TAPPAN ST

BRINGTON RD

CYPR

ESS

STLIBRARY

COLLAB

MBTAGREEN LINE Plaza

Page 9: Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building

H M F H A R C H I T E C T SBHS Campus Expansion 50’ 100’

OPTION 4A & 4B 9th Grade Academy at Cypress plus see BHS-Greenough Options

2nd Floor Plan 3rd Floor Plan 4th Floor Plan

SCI

SCI

COLLAB

SCI

SCI

MAKER SPACE

COLLAB

SCI

SCI

COLLAB

Page 10: Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building

H M F H A R C H I T E C T SBHS Campus Expansion

LIBRARY

DINNINGCOMMONS

MBTA

CORE ACADEMIC

Massing 4C & 4D

Section 4C & 4D

OPTION 4C & 4D: 9th Grade Academy at Cypress & MBTA plus see BHS-Greenough Options

Page 11: Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building

H M F H A R C H I T E C T SBHS Campus Expansion 50’ 100’

OPTION 4C & 4D: 9th Grade Academy at Cypress & MBTA plus see BHS-Greenough Options

Ground Floor Plan 1st Floor Plan

TAPPAN ST

CYPR

ESS

ST

BRINGTON RD

COLLAB

MBTAGREEN LINE

TAPPAN ST

CYPR

ESS

ST

DIN

NING

COM

MO

NS

MBTAGREEN LINE

BRINGTON RD

MAKERSPACE

Page 12: Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building

H M F H A R C H I T E C T SBHS Campus Expansion 50’ 100’

2nd Floor Plan 3rd Floor Plan 4th Floor Plan

SCICR

SCICR

COLLAB

SCICR

SCICR

COLLAB

LIBRARY

SCICR

SCICR

COLLAB

OPTION 4C & 4D9th Grade Academy at Cypress & MBTA plus see BHS-Greenough Options

Page 13: Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building

H M F H A R C H I T E C T SBHS Campus Expansion

CR

SCI CRSCI CR

Massing 4A & 4C

Section 4A & 4C

OPTION 4A & 4CBHS New 5-Classroom Addition & Renovate Existing Science

RENOVATION

EXISTING - NO WORK

EXTENT OF DEMOLITION

Page 14: Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building

H M F H A R C H I T E C T SBHS Campus Expansion 50’ 100’

OPTION 4A & 4CBHS New 5-Classroom Addition & Renovate Existing Science

CR

CR

CR

CR

CR

1st Floor Plan

RENOVATION

EXISTING - NO WORK

EXTENT OF DEMOLITION

Page 15: Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building

H M F H A R C H I T E C T SBHS Campus Expansion 50’ 100’

OPTION 4A & 4CBHS New 5-Classroom Addition & Renovate Existing Science

2nd Floor Plan

RENOVATION

EXISTING - NO WORK

EXTENT OF DEMOLITION

Page 16: Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building

H M F H A R C H I T E C T SBHS Campus Expansion 50’ 100’

OPTION 4A & 4CBHS New 5-Classroom Addition & Renovate Existing Science

SCI SCICR

SCICR

SCICR

SCICR

SCICR

SCICR

SCI CR

SCICR

SCICR

SCICR

SCI CR

SCI CR

SCI CR

SCI CR

SCI CR

SCI CRSCI CR

SCI CR

3rd Floor Plan

RENOVATION

EXISTING - NO WORK

EXTENT OF DEMOLITION

Page 17: Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building

H M F H A R C H I T E C T SBHS Campus Expansion

SCISCISCI CR

SCISCISCI CR

COLLAB

Massing 4B & 4D

Section 4B & 4D

OPTION 4B & 4DBHS New Science at Roberts Wing & Renovate 3rd Floor as Core Academics

RENOVATION

EXISTING - NO WORK

EXTENT OF DEMOLITION

Page 18: Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building

H M F H A R C H I T E C T SBHS Campus Expansion

SCICR

CULINARY

KITCHENCAFE

CAFE

SCICR

SCICR

SCICR

SCICR

SCICR

50’ 100’

1st Floor Plan

RENOVATION

EXISTING - NO WORK

EXTENT OF DEMOLITION

OPTION 4B & 4DBHS New Science at Roberts Wing & Renovate 3rd Floor as Core Academics

Page 19: Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building

H M F H A R C H I T E C T SBHS Campus Expansion 50’ 100’

OPTION 4B & 4DBHS New Science at Roberts Wing & Renovate 3rd Floor as Core Academics

SCICR

MAK

ER S

PACE

COLL

AB

SCICR

SCICR

SCICR

SCICR

SCICR

2nd Floor Plan

RENOVATION

EXISTING - NO WORK

EXTENT OF DEMOLITION

Page 20: Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building

H M F H A R C H I T E C T SBHS Campus Expansion 50’ 100’

OPTION 4B & 4DBHS New Science at Roberts Wing & Renovate 3rd Floor as Core Academics

SCICR

MAK

ER S

PACE

COLL

AB

SCICR

SCICR

SCICR

SCICR

SCICR

RENO

VATE

INTO

CO

REA

CADE

MIC

SPA

CE

3rd Floor Plan

RENOVATION

EXISTING - NO WORK

EXTENT OF DEMOLITION

Page 21: Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building

H M F H A R C H I T E C T SBHS Campus Expansion

Option 4 Program ComparisonImproving Classroom Spaces

Brookline High School Expansion Feasibility Study HMFH Architects Inc.

Design Alternate Comparisons April 13, 2017

Improving Classroom Spaces

New 9th Grade Academy

BHS - Greenough Renovated Science

Classrooms

BHS - Greenough New Science Wing

Classrooms

Existing to Remain 65 Classrooms 56 Classrooms

Renovated Classrooms 12 Classrooms

New Classrooms 26 Classrooms 5 Classrooms 2 Classrooms

Science Classrooms/Labs

New Science Classrooms/Labs 6 Classrooms/Labs 18 Classrooms/Labs

Renovated Science Classrooms/Labs

18 Classrooms/Labs

Special Education

Self-Contained Classrooms, Learning Centers, Resource Rooms

6 New Existing to Remain Existing to Remain

OT/PT 1 New Existing to Remain Existing to Remain

Page 22: Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building

H M F H A R C H I T E C T SBHS Campus Expansion

Brookline High School Expansion Feasibility Study HMFH Architects Inc.

Design Alternate Comparisons April 13, 2017

Program Expansion

New 9th Grade Academy

BHS - Greenough Renovated Science

Classrooms

BHS - Greenough New Science Wing

Cafeteria New Existing to Remain Existing to Remain

Library / Media Center New Existing to Remain Existing to Remain

Collaborative Learning

Small Group Rooms 1 New 6 New

Maker Space 1 New 1 Existing to Remain2 New/

1 Existing to Remain

Learning Commons 5 New MLK Room to Remain2 New/

MLK Room to Remain

Language/ Computer Labs In New Classrooms 3 Existing to Remain 3 Existing to Remain

Teacher Planning 3 New Existing to Remain6 New/

Existing to Remain

Administration / Guidance Medical / Nurse

New Existing to Remain Existing to Remain

Option 4 Program ComparisonProgram Expansion

Page 23: Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building

H M F H A R C H I T E C T SBHS Campus Expansion

Brookline High School Expansion Feasibility Study HMFH Architects Inc.

Design Alternate Comparisons April 13, 2017

Program Expansion

New 9th Grade Academy

BHS - Greenough Renovated Science

Classrooms

BHS - Greenough New Science Wing

Career Education & Technology At UAB & BHS Existing to RemainNew Culinary Arts Café/

Existing to Remain

Performing Arts

Music/ Performance Space 1 New Existing to Remain Existing to Remain

Ensemble and Music Practice 3 New Existing to Remain Existing to Remain

Visual Arts : Studios 1 New/ and at UAB Existing to Remain at UAB Existing to Remain at UAB

Physical Education

Health Classroom 2 NewExisting to Remain for

OT/PTExisting to Remain for

OT/PT

Schluntz Gym Keep Existing Keep Existing Keep Existing

Tappan Facility Refer to Tappan Options Refer to Tappan Options Refer to Tappan Options

Option 4 Program Comparison

Page 24: Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building

H M F H A R C H I T E C T SBHS Campus Expansion

Option 4 Summary and Cost

$105,342,903 $131,117,378 $110,838,332 $136,612,807

Renovate Existing Science35,500 sf

New Construction at BHS7,500 sf

New Construction at 9th Grade Academy109,810 sf

Renovate Existing Scienceinto Classrooms36,500 sf

New Construction at BHS44,100 sf

New Construction at 9th Grade Academy109,810 sf

Renovate Existing Science35,500 sf

New Construction at BHS7,500 sf

New Construction at 9th Grade Academy112,700 sf

Renovate Existing Scienceinto Classrooms36,500 sf

New Construction at BHS50,400 sf

New Construction at 9th Grade Academy112,700 sf

Option 4A Option 4B Option 4C Option 4D

Page 25: Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building
Page 26: Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building

H M F H A R C H I T E C T SBHS Campus Expansion

TRAINMULTI-PURPOSE

WRSTL

DANCESTUDIO LKRM

LKRM

LKRM

OFF

OFF

TRAIN

SHWR

KIRRANEPOOL

MECH ACCESS

LKRM LKRMLKRM

DANCESTUDIO

FITNESSCENTER

OFF

OFF

OFF

OFF

OFF KIRRANEPOOL

GYMNASIUM

GYMNASIUM

POOLOPEN TOBELOW M

ULT

I-PU

RPO

SE

INDOORPLAYINGFIELD

POOLROOF

ExistingTappan Gym

Basement Plan First Floor Plan

Second Floor Plan Third Floor Plan

Mezzanine Plan

50’ 100’

Page 27: Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building

H M F H A R C H I T E C T SBHS Campus Expansion

DANCE

LKRM

LKRM

TEAM LKRM

TT

STOR

WRSTL

TEAMKIRRANE

POOL

MECH ACCESS

DANCEBELOW

TRAI

NER

&A

DMIN

WEL

L-N

ESS

DANCE

FITNESSTT

NEW CANOPY AND ENTRY PLAZA

LOBBY

KIRRANEPOOL

TT

LARGE GYM

SMALL GYM

POOLOPEN TOBELOW M

ULT

I-PU

RPO

SE

PAVILION

POOLROOF

Option 1Tappan Gym Renovation

Basement Plan First Floor Plan

Second Floor Plan Third Floor Plan

Mezzanine Plan

50’ 100’

Page 28: Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building

H M F H A R C H I T E C T SBHS Campus Expansion

POOLLOCKERROOMS

DANCE

FITNESSLOBBY

KIRRANEPOOL

HEALTH

Vest.

ADMIN

OPENTO

BELOW

A

A

BBLKRMS

DANCE

KIRRANEPOOLWREST.

TRAING

MECH ACCESSLOBBY

A

A

BB

POO

LM

ECH

Basement Plan First Floor Plan

Second Floor Plan Third Floor Plan

PRACTICEGYM

GYM

LKRM

GYM

POOLOPEN TOBELOW

T

LOBBYA

A

BB

T

PAVILION

POOLROOF

GYMROOF

LKRMT

Mech

LOBBYA

A

BB

T

Option 2.1Tappan Gym Renovation & Addition

50’ 100’

WELL-NESST

LOBBY

GYMOpen toBelow

Mech

Mezzanine Plan

Page 29: Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building

H M F H A R C H I T E C T SBHS Campus Expansion

Option 2.1Tappan Gym Renovation & Addition

PRACTICE GYMWELLNESS

LKRM

LKRMLKRMLKRM

LOBBY

B

B

PRACTICEGYM POOLLKRMLKRM

A

A

32’ 64’

Page 30: Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building

H M F H A R C H I T E C T SBHS Campus Expansion | Cypress Playground

Cypress Field Open Space : Renovation Project Goals and Features

• Synthetic Turf Field with Organic Infill for Soccer, Football

Practice only, and Softball

• New Perimeter Fencing and Lighting

• Improve Pedestrian Circulation

• Improve/New Basketball Court

• New Stadium Bleacher Seating

• New Playground and Splash Pad

• New Picnic Area and Shelter

• Improve/New Utilities and Drainage

• New Site Furniture, Accessories such as Trash Recycling, Water

Fountains Bottle Refill

• Plantings, Lawn Area

Other: Below Grade Storm-water Retention

Optional: Below Grade Parking Structure

Page 31: Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building

H M F H A R C H I T E C T SBHS Campus Expansion

ExistingCypress Field and Playground

100’ 200’

Page 32: Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building

H M F H A R C H I T E C T SBHS Campus Expansion

Option 1Cypress Field and Playground Renovation

100’ 200’

Page 33: Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building

H M F H A R C H I T E C T SBHS Campus Expansion

Option 2Pedestrian Raised Crossing and Vehicle Access at Plaza

100’ 200’

Page 34: Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building
Page 35: Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building

H M F H A R C H I T E C T SBHS Campus Expansion

Option 1 Below Grade Plan Diagram

Below Cypress Park Turf Field - Storm-Water Retention System & Parking Structure @ +/- 100 Cars per Level

Page 36: Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building

H M F H A R C H I T E C T SBHS Campus Expansion

Existing Conditions

Greenough St & BHSCypress St

Site Section & Underground Parking

MWRA Easement

MWRA Easement

Parking - Level 1

Cypress St Greenough St & BHS

Parking Structure Below Cypress Park - Field @ +/- 100 Cars per Level

RAMPParking - Level 2

Parking - Level 3

MWRA & EASEMENT LAYOUT VARIES SEE PLAN

MWRA & EASEMENT LAYOUT VARIES SEE PLAN

Storm-water Retention System

Page 37: Campus Expansion Update - Public Schools of Brookline · 2017-04-13 · Brookline High School Campus Expansion Update Feasibility Study APRIL 13, 2017 Brookline High School Building