Caltrans 23 USC 326 Categorial Exclusions and Programmatic … · 2020. 8. 4. · 23 USC 326...
Transcript of Caltrans 23 USC 326 Categorial Exclusions and Programmatic … · 2020. 8. 4. · 23 USC 326...
Caltrans 23 USC 326 Categorical Exclusions and Programmatic
Categorical Exclusions 12-month Report to FHWA
January 1, 2018 – December 31, 2018
Summary
This report has been prepared pursuant to the Caltrans/FHWA Memorandum of
Understanding (MOU) regarding State assumption of responsibilities under Section 326
of amended Chapter 3 of title 23, United States Code (23 U.S.C. 326). Section IV, State
Performance Requirement E.1 of the May 2016 MOU, requires Caltrans to provide a list
of Categorical Exclusion (CE) determinations that it approves annually.
During the January 1, 2018 – December 31, 2018 period (Quarter 43 through Quarter 46),
Caltrans is reporting the following approvals:
876 23 USC 326 Categorical Exclusions (359 State Highway System Projects and
517 Local Assistance Projects)
17 Section 4(f) approvals (5 State Highway System Projects and 12 Local
Assistance Projects)
Newly identified approvals from previous quarters and other corrections are also included
in this report.
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
District-EA County Route Post MileDate
Signed
01-0C450_ MEN 101 58.9/82.5 3/16/2018
01-0C660_ DN 101 25.8/27.3 06/21/18
01-0E030_ HUM 299 16.1/26.6 1/23/2018
01-0E040_ HUM 101 78/79.8 05/17/18
01-0E650_ HUM 101 88.2/88.3 05/16/18
01-0E680_ HUM 101 78.1/79.6 05/17/18
01-0E730_ LAK 029 17.74/20.73 8/16/2018
01-0E770_ HUM 101 17.89/87.84 8/23/2018
01-0E850_ VAR VAR 0/0 06/27/18
01-0E860_ MEN 020 16.94/17.15 9/6/2018
01-0F080_ HUM 096 22.9/22.9 9/17/2018
01-0F360_ HUM 101R39.2/R48.
305/15/18
01-0F440_ MEN 001 0/15 12/12/2018
01-0F490_ LAK 020 5.84/5.84 04/04/18
01-0F490_ LAK 020 5.800/5.800 12/12/2018
01-0F690 HUM 299 14.7/15.7 8/31/2018
01-0F960_ HUM 101 124.49/124. 05/31/18
01-0G130_ DN 199 10.24/10.7 11/30/2018
01-0G330_ LAK 020 5.100/5.700 05/23/18
01-0G480_ MEN 162 17.49/17.72 05/29/18
01-0G650_ MEN 101 104.7/105.3 05/09/18
01-0G790_ MEN 101 43.2/43.2 8/29/2018
01-0G810_ HUM 101 24/26.5 8/7/2018
01-0G820_ HUM 101 28.4/32 06/27/18
01-0G850 HUM 036 29/30 02/05/18
01-0G900_ MEN 162 0/16.2 9/27/2018
01-0G930_ HUM 169 29.7/29.7 7/17/2018
01-0G950_ HUM 299 30.6/30.6 7/25/2018
01-0H020_ HUM 169 15/30 7/18/2018
01-0H050_ DN 101 20/28 1/29/2018
01-0H060_ LAK 029 12/15 3/22/2018
01-0H100_ HUM 101 T0/R16 8/14/2018
01-0H710_ MEN 128 39.7/39.7 06/19/18
01-0J160_ MEN 101 9/20/2018
01-46630_ MEN 101 0/9.6 8/16/2018
02-0H410_ TRI 299 10.9/11.2 06/29/18
02-0H540_ TRI 00330.51/T57.7
910/31/2018
02-0H550_ PLU 070 .47/30.68 8/31/2018
02-0H560_ BUT 070 29.7/48.01 8/31/2018
02-0H690_ TRI 299 43.1/43.3 06/27/18
LAKE 20 shoulders
Widen Shoulders & Install Rumble
Little Lost Man Fish Passage
DN-199 Safety Improvements
MEN-162 Super El Improvement
Piercy slide
Slope Repair CCA 3-19-18
Storm repairs near Myers Flats
Myers Flat & Weott storm repairs
HUM 36 Repair slipouts
MEN-162 Storm repairs
Hopland CAPM
Burnt Ranch Curtains
Cedar Creek storm repairs
Repair slipouts
Repair slope & repair culvert
Repair Culvert / Stabilize Slope
Eureka CAPM
HUM-299 Off ramp improvement
4th Street Safety
Lake 29 Shoulder widening and truck lane
Martins Ferry Storm Repairs
State Highway System 326 CE Projects
Project Description
Moss Cove, Irvine Lodge & Empire Camp SRRA's
Crescent City ADA SHOPP
Slope Repair and Drainage Improvements
HUM-101 Strengthen 3 Bridges
LaDicino Guardrail
Storm Repairs near Richardson Grove
MEN-128 Slide repair
MEN-101 Storm Damage
CAMP 20 Safety project
Pectah Wall
Redcrest CAPM
Point Arena CAPM
Bachelor Creek Bridge
Bachelor Creek Bridge
Trinity 3 Drainage
Plumas 70 Drainage rehab
Butte 70 Drainage rehab
Junction City Drapery
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
1
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
02-1H390_ SHA 005R32.16/R32
.1611/14/2018
02-1H970_ TEH 036 R12.6/13.1 04/16/18
02-2H630_ TEH 036 26.6/27.6 11/01/18
02-2H990_ SHA 044 51.6/52.2 12/12/18
02-4E46U_ LAS 036 6.1/14.3 05/14/18
02-4F220_ TRI 003 58.7/61.9 12/11/18
02-4F590_ TEH 005R25.4/R25.
405/21/18
02-4F600_ VAR VAR 0.000/0.000 09/17/18
02-4G400_ SHA 005 57.41/57.41 01/30/18
02-4G410_ SHA 005 66.8/66.8 01/30/18
02-4G41U_ SHA 5 01/30/18
02-4G500_ TRI 299 1.9/2.1 02/21/18
02-4G560_ TEH 036 0/100 07/11/18
02-4H200_ SHA 89 26.30/29.2 06/21/18
02-4H230_ PLU 89 30.2/35.3 07/12/18
02-4H870_ VAR 299 0.000/0.000 08/14/18
03-0F030 PLA 089 17.2/18.3 07/26/18
03-0F250 YOL 080R11.300/R1
1.30008/16/18
03-0F290_ BUT 099 013.1/45.9 03/07/18
03-0H330_ BUT 099 13.25/45.92 01/29/18
03-0H530_ SAC 080 15.0/17.2 02/28/18
03-0H540_ VAR 080 0/0 05/11/18
03-0H570 SAC 050 10.84/10.99 05/16/18
03-1F170_ PLA 065 6/12.8 03/27/18
03-1H190 SAC 080 9.6/12.9 07/13/18
03-2F570_ PLA 080 28.7/R63.52 04/05/18
03-2H570_ VAR VAR VAR 03/01/18
03-2H640_ SAC 012 0.57/0.57 07/23/18
03-2H700_ VAR VAR VAR 02/12/18
03-3F250 NEV 080 29.1/29.4 03/29/18
03-3H570_ SAC 5 10.82/11.6 03/12/18
03-4F100_ SAC VAR 0/0 04/27/18
03-4F420_ GLE 005 14.6/14.6 10/01/18
03-4F810_ GLE 032 0/0.7 02/28/18
03-4H030_ VAR VAR 06/14/18
04-0C930 SM 1 0/10.6 09/26/18
04-0J100_ SON 101 9/9 06/29/18
04-0J530_ ALA 880 11.3/12.3 12/20/18
04-0J560_ SCL 101 0.01/4.2 08/27/18
Mesh Drapery
Sac River BOH (Bryte Bend)
Ward Curves
CARR Fire Reconstruction
Sacramento River Bridge Seismic DES Broker
Sis Tri Deck Rehab
Sims Road UC Replacement
Lake Britton Overlay
Lower Almanor Mill & Fill
Crag View Dr Undercrossing Replacement
Sims Crag Combine
South Fork Mine CRZ
Red Bluff Drainage restoration
Diamond Star Curve
Eskimo Hill Superelevation Improvement
Good Fred
Swift Creek Bridge Replacement
O Brien Deck and Rail Rehab
Cottonwood Creek Bridge Replacement
But 99 Bridge Rail Replacement
0312000133 - Slope Stabilization near Truckee
Elk Grove Aux Lane
Seismic Retrofit
Willows SRRA
Orland ADA Infrastructure
Rumble Strips
SM-1 CAPM
SON-101 N of Pepper Rd - regrade slope
Patterson Slough Creek Bridge Deck Replacement
Antelope truck scales
SAC/PLACER 80 fiber optics
0315000210 - Zinfandel Complex - PEER
PLA-65 - C&O In Roseville
SAC 80 R&R RHMA
PLA 80 Bridge Rehab
Repair loop Detectors, (198 Field Elements) various
counties, various routes
Hwy 12/160 Intersection Improvements
Repair Field Elements
SCL 101 Br. Rail Replacement/Upgrade
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
2
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
04-0J642_ SON 101 29.3/R54.3 04/17/18
04-0J710_ SOL 080 1.8/4.4 05/29/18
04-0J720_ SM 280 7/7.7 08/01/18
04-0p370_ ALA 980 09/11/18
04-1A210_ SON 37 2.6/0 03/29/18
04-1J360 SON 012 34.2/41 03/29/18
04-1J970_ SCL 017 2.8/9.4 09/18/18
04-1J990_ ALA/CC VAR Var 06/08/18
04-2G460_ ALA 13 10.8/12.10 04/16/18
04-2G460_ ALA 13 10.8/12.10 11/05/18
04-2J720_ CC 580 1.17/1.17 10/08/18
04-2J750_ SCL 280 2.87/17.8 01/02/18
04-2J810_ ALA 880 4.8/11.3 05/24/18
04-2j830_ ALA 080 1.9/4 10/16/18
04-2J88U_ NAP 02938.900/42.9
0008/22/18
04-2J890_ SCL 017 0/6.55 05/07/18
04-2K750_ SCL 152 7.6/10.3 02/28/18
04-2K840_ SOL 080 1.1/1.1 05/10/18
04-3J050_ ALA 580 30.81/46.46 06/13/18
04-3j190_ ALA VAR 0/0 01/10/18
04-3J700_ ALA 080 4.5/7.6 10/26/18
04-4J390_ SF 101 0/4.24 11/21/18
04-4J750_ ALA 084 0.73/3.06 10/12/18
05-0L721_ SLO 001 32.61/32.61 06/22/18
05-0L722 SLO 001 34.46/34.46 05/10/18
05-0N200_ MON 101 82.0 / 101.3 06/28/18
05-0N220_ SLO 101 30.5 / 59.8 09/20/18
05-0Q500_ MON 001 20.4/20.4 08/27/18
05-1C420_ SB 154 22.9/23.2 07/09/18
05-1F100_ SB 101 85.18 02/05/18
05-1F490_ SLO 101 0/0 07/09/18
05-1F680_ MON 001 39.8/74.6 04/18/18
05-1F790_ SB 101 56/56 06/18/18
05-1F820_ MON 101 R6.6/6.6 08/06/18
05-1F830_ SB 135 R7.2/R7.2 08/16/18
05-1G130_ SB 001R36.400/49.
20006/12/18
05-1G260_ SCR 017 9.4/9.6 04/30/18
05-1G300_ VAR 101 0/0 05/23/18
sol 80 Raise overcrossing
Erosion Control Measures - various locations
TMC Hardware Replacement
Install traffic census station with weign-in-motion
0414000202 Pavement preservation (CAPM)
SCL 17 CAPM - pavement rehab
Ala 13/CC 24 Enhance Lighting
Upgrade curb ramps/sidewalks Claremont Ave to
Shattuck Ave (ASHBY)
Upgrade curb ramps/sidewalks Claremont Ave. to
Shattuck Ave (ASHBY)
CC-580 Stege Drain super-structure
Seismic Restoration, Arasteradero Rd, undercrossing
and Bird Ave. overcrossing
Pave areas from shoulder to soundwall
TMS Replace & Upgrade at Maze
SR 29 3 bridges, scour measures
SCL 101 Rumble Strips.
Wildlife Habitat
SB/SLO Horizontal Curve Signs
Big Pave segment 2
Pavement Preservation (CAPM)
Sol-80/29 Separation
TMS on ALA-580 & ALA/SJ-205
ALA Install 241 APSs
Ala 80 Median Barrier & Lighting
Mitigate wet pavement
Install Outer Separation Barriers
Toro Creek Bridge replacement
0515000098 - Old Creek Bridge
Mon 101 TMS
SLO 101 N Cnty TMS
Replace culvert near Limekiln Creek
Infrastructure maintenance
Route 101 Northboung Ramp - Clark Ave
Route 101 and Route 41 Barrier Improvements
Big Sur CAPM
Nojoqui Creek Bridge (51-0018) Railing Upgrade
San Antonio River bridge-seismic retrofit
San Antonio Cr Seismic Retrofit
Solomon Canyon CAPM
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
3
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
05-1G310_ VAR 101 0/0 05/23/18
05-1G980_ SLO 001 10/16.77 07/31/18
05-1H010_ SB VAR 19.3/20.6 01/09/18
05-1H020_ MON 101 2.9/5.3 08/21/18
05-1H060_ SCR VAR 0/0 01/09/18
05-1H930_ SLO 046 R17.4/17.4 08/21/18
05-1H960_ SB 135 10.6/17.6 09/17/18
05-1H990_ VAR VAR 0/0 07/30/18
05-1J470_ SB 135 0/0 09/13/18
05-1J480_ SBT 025 54.05/54.05 08/23/18
05-1J660_ SB 192 8.0/12.50 07/12/18
05-1J670_ SB 192 15.4/15.6 06/01/18
05-1K140_ SCR 009 15.00/15.00 12/20/18
05-1K330_ SB 101 57.5/65.0 10/18/18
06-0H140_ TUL 190 34.7/39.4 10/11/18
06-0Q820_ KER 005 8.53/8.87 02/05/18
06-0Q910_ TUL 099 19.46/19.46 01/08/18
06-0S830_ FRE 005 44.4/45.4 08/02/18
06-0U100 KER VAR 0/0 06/22/18
06-0U170_ MAD 099 9.74/9.74 04/27/18
06-0U420_ FRE 099 R5.7/11.1 11/20/18
06-0U450_ FRE 168 18.9/T24.7 07/23/18
06-0U450_ FRE 168 18.9/T24.7 08/15/18
06-0U470_ KER 005 82/87 10/22/18
06-0U480_ KER 046 49/50.9 03/15/18
06-0U490_ KER 204 5.1/6.7 08/20/18
06-0U760_ FRE 168 R0/R11.7 12/18/18
06-0V280_ KER 184 L.9/L1 07/17/18
06-0V320_ FRE 168 11.67/39.36 08/08/18
06-0V780_ FRE VAR 0/0 10/30/18
06-0V910_ VAR 099 0/0 04/30/18
06-0V930_ VAR VAR 0/0 07/03/18
06-0W410_ KER 046 26.8/47.02 06/21/18
06-0W430_ KER 00515.82/R15.8
203/28/18
06-0W460_ KER 005 12.47/12.47 03/28/18
06-0W950_ FRE 041 24.5/24.5 12/19/18
06-0X390_ KIN 43 0.0/3.2 12/27/18
06-0X830_ KER 33 44.2/54.0 08/14/18
06-0Y310 TUL VAR Various 07/06/18
06-0Y630_ TUL 190 40 11/21/18
Warning Sign Upgrades
Pismo Beach pavement restoration
Lompoc CAPM
Camp Roberts SRRA Infrastructure Upgrade
Pasatiempo II
Vineyard Roundabout
Route 135 Signal Modifications
Tipton Bridge Deck Rehab
Tumey Gulch bridge replacement
0615000211 - Roadway preservation
South Gateway Drive Overcrossing deck rehab
Selma to Fowler Rehab
Morgan Canyon CAPM
Morgan Canyon CAPM
Lost Hills Rehab
Wasco Route 46 CAPM
TMS Detection Repair
Bunny Avenue and North Broadway Ped
Improvements
SR 25/156 Roundabout
Replace three bridges, repair bridge rails
Arroyo Paredon EFA
Spring Cr. PM 15 Soldier Pile Wall
RHMA Overlay
Tulare culvert replacement
Grapevine Channel Repair
I-5 Freight Corridor California Aqueduct
180 Connector guard rail
Kings 43 CAPM
Pavement repair
ADA Ramps (Directors ORDER)
Camp Nelson Slide Repair
Golden Empire CAPM
Fre-168 Recycled Water Irrigation UpgradE
Kern 184/Sunset Roundabout
Shepherd to Top o' the 4-Lane Rumble Strip
Fre-41;99;168 & 180 Fiber Optic
Zero Emissions Vehicle Charging Stations
TMS Element Upgrade/Repair
Lost Hills to Wasco Rumble Strip
I-5 Fast Freight Corridor I-5/Rte 99 Separation
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
4
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
07-1XG50_ VEN 101 Various 07/05/18
07-1XG70_ VEN 033 13.2/30.5 07/05/18
07-21060_ LA 071 0.500/4.700 09/20/18
07-25310_ LA 213 3.80 09/28/18
07-25940_ LA 210R0.000/R9.
70008/28/18
07-26080_ LA 010 16.57/30.1 03/30/18
07-27610_ LA 110 3.800/6.500 04/18/18
07-29510_ LA 005 38./39.2 02/23/18
07-29540_ VEN 101 30.2/31.4 05/08/18
07-30110_ LA 060R 2.80/ R
11.806/19/18
07-30170_ LA 210R33.75/R39
.806/05/18
07-30240_ VEN 101 36.3/40.6 05/02/18
07-30250_ VEN 023 R3.29/11.26 03/23/18
07-30330_ VEN 001 0.0/4.4 02/06/18
07-30450_ LA 057 R0/R4.45 04/25/18
07-30490_ LA 001 Various 05/10/18
07-30970_ LA 005 39.200/R43. 09/24/18
07-31100_ LA 210R24.600/R2
5.30003/27/18
07-31380_ LA 110 10/11 05/23/18
07-31380_ LA 110 11.000 10/01/18
07-31730_ LA 060 0/0 06/28/18
07-31960_ VEN 001 02/12/18
07-32300_ VEN 033 16.13/16.13 05/10/18
07-32530_ LA 118R1.500/R10
.20012/17/18
07-32550_ LA 605 20.19/26 06/22/18
07-32660_ LA 110 28.65/29.35 05/10/18
07-33230_ VEN 03318.880/19.0
4011/14/18
07-33760_ LA 014 29/29 05/30/18
07-33800_ LA 005 20.77/20.77 06/20/18
07-34060_ LA 00214.940/R22.
62006/27/18
07-34170_ LA 001 2.75/2.75 04/03/18
07-34220_ VEN 150 16.577/18.5 08/16/18
07-34240_ LA VAR 0/0 05/29/18
07-34280_ LA 014 R27.00/R28 12/12/18
07-34760_ LA 210 R 0.850/R 11/13/18
Roadside Safety Improvements
Drainage Improvement & Replace Culvert System
Drainage Improvement & Replace Culvert System
Ven 101 Padre Juan Rehab
VEN-23 Rehab
SR 1 Cnty Ln Pavement Rehab
Lane Replacement
TMDL- 18/19
Route 5 Rehab
overhead sign panels
Geo-technical Boring for Site Exploration
TMDL stormwater mitigation
Slab Replacement and Shoulder Resurfacing
High Friction Surface Treatment
Rock block barrier
Rte 14 Drainage Culvert
0717000053 - LA-005 Culvert Repair
ITS Restoration Work in Hassan Manaa's area
PCH @ Anaheim St.
City of Ojai Complete Streets
District Building Roof Replacement
Storm Damage
Replace fire-damaged MBGR and crash cushions on
VEN 33, 101 and 150.
Replace fire-damaged MBGR and crash cushions on
VEN 33
SR 71 Freeway Conversion
Storm Drain Repair
Storm water mitigation
Stormwater Mitigation TMDL
TMDL- 18/19
5 @118 Maintenance safety
101 @ Rte 33
Pavement Rehab
Stormwater
Soundwall
Bridge Structure Painting
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
5
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
07-3W680_ LA 001 21.9/29.084 10/03/18
07-3W970_ LA 105 7.98/15.53 02/12/18
07-4P590_ LA 405 37.5/38.6 05/24/18
07-4P630_ LA 405 32.9/34.9 02/26/18
07-4P640_ LA 405 28/39 02/22/18
07-4T950_ LA 405 33/34.7 05/24/18
07-4U050_ LA 405 38.590/45.7 05/04/18
07-4V060_ LA 210 34.9/35.5 10/22/18
07-4W140_ LA 057 R 2.5/R 05/07/18
07-4W270_ VEN 1018.900/11.50
007/19/18
07-4W280_ VEN 033 6.330/11.09 05/21/18
07-4W290_ VEN 1180.516/10.97
005/15/18
07-4W310_ LA 210 11.180/14.1 10/24/18
07-4W400_ LA 2100.0/16.1 &
25.8/62.106/13/18
07-4W420_ LA 405 0.000/48.64 11/02/18
07-95212_ LA 101 11.85/11.85 03/27/18
07-95212_ LA 105 05/03/18
07-95212_ LA 005 07/17/18
08-0E33U_ SBD 060 R7.3/R10 12/03/18
08-0G790_ SBD 071 R0.000/R8. 11/28/18
08-0G800_ SBD 038 47.5/59.4 07/20/18
08-0G800_ SBD 038 47.5/59.4 10/26/18
08-0G860_ SBD 040R105.3/R10
5.609/24/18
08-0K122_ SBD 015 30.8/42.5 04/23/18
08-0K293_ SBD 010R36.9/R39.
101/08/18
08-0M900_ RIV 111 18.0/19.0 04/26/18
08-0P390 SBD 018 101.5/115.9 06/06/18
08-0Q75U_ VAR VAR 0/0 05/01/18
08-0R142_ SBD 040R125/R154.
611/29/18
08-0R150_ SBD 040 R75/R100 08/29/18
08-0R301_ RIV 11147.250/55.2
6006/04/18
08-0R781_ RIV 074 82.3/83.2 07/18/18
08-1C29U_ SBD 010 26.8/34.2 02/01/18
08-1C300_ SBD 010 34.2/39.16 02/26/18
08-1C300_ SBD 010 34.2/39.16 07/18/18
08-1C38U_ RIV 010 6.700/R25.1 06/07/18
08-1C590_ RIV 074 7/R14.4 08/02/18
08-1C590_ RIV 074 7/R14.4 11/28/18
08-1C660_ RIV 215 R9/R16 11/16/18
08-1E060_ SBD 018 98.08/99.45 10/31/18
SBD 10 Redlands Rehab
Riv 111 Grade Separation
SBD 18 Adelanto shoulder widening
SBD 60 Replace Lanes and Slabs - (G-13)
SBD 40 Needles regrade median
SBD 40 Regrade median cross slope (near Arizona)
RIV 111 Construct & Reconstruct Curb Ramps Phase
I
RIV 74 Install midwest guardrail system-Palm Desert
0817000219 - Install gore/slope paving, pave under
SBd 10 Remove and Replace Diseased Plants
SBd 10 Remove and Replace Diseased Plants
RIV 10 Pavement replacement
RIV 74 Source control in Lake Elsinore
RIV 74 Source control in Lake Elsinore
RIV 215 Sediment stabilization, erosion control
SBD 18 Construct raise median in Victorville
VEN 118 FY 1819 PM
Line and repair culverts
0718000154 - LA-210 Replace 4 in striping with 6 in
striping
Replace pavement delineation
Air Space Lease project - Wireless Cell Site
Air Space Lease Project - Wireless Cell Site
Air Space Lease project - Wireless Cell Site
SBD 60 Add westbound AUX lane, add eastbound
Install CCTV, CMS, VDS & fiber optic communication
SBd 38 Replace Culverts
SBd 38 Replace Culverts
SBD 40 UPGRADE SRRA
SBD 15 Rehab (G-13)
210 Traffic Signal
HM3-115 Bridge Preservation
VEN 101 RBWC-G
VEN 33 FY 1819 PM
LA 1 Digouts slurry seal
LA-105, Repair and replace culverts
405 Wildlife Fence
Minor B project fr Getty Center Drive to Sunset Blvd
0718000243 - LA405 Signing
LA 405 wildlife Fencing
LA 405 Slab replacement
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
6
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
08-1E570_ RIV 010 27.69/27.69 05/31/18
08-1E611_ RIV 062 81.600/82.2 10/23/18
08-1E780_ SBD 330 37.1/41.1 01/16/18
08-1F131_ SBD 095 9.700/33.60 05/04/18
08-1F132_ SBD 095 64.5/80.5 04/30/18
08-1F133_ SBD 062 122/142.7 05/04/18
08-1F141_ RIV 015 R0/3 03/15/18
08-1F143_ RIV 01538.200/51.5
0004/09/18
08-1F361_ SBD 060 R0/R9.9 07/23/18
08-1F371_ RIV 060 R0/22.3 04/12/18
08-1F410_ RIV 010R110.47/11
0.4701/31/18
08-1F590_ RIV 074 36.93/43.59 06/07/18
08-1F600_ RIV 079 25.65/26.4 04/04/18
08-1F690_ RIV 0790.000/15.60
006/27/18
08-1F730_ SBD 215 2.4/3 03/14/18
08-1F780_ SBD 095 9.6/56.5 02/27/18
08-1H271_ SBD 015 40.2/40.8 04/03/18
08-1H340_ SBD 210 21.1/33.2 05/07/18
08-1H530_ VAR VAR / 02/02/18
08-1H640_ SBD 210 R26.5/26.5 01/23/18
08-1H660_ VAR VAR 0/0 05/29/18
08-1H760_ SBD 015R18.5/R21.
403/01/18
08-1H770_ SBD 215 4.800/5.800 05/07/18
08-1H770_ SBD 215 4.8/5.8 12/27/18
08-1H880 RIV 60 0/0 01/31/18
08-1H931_ SBD 71 0/8.5 04/25/18
08-1K210_ SBD 38 12.4/27.10 12/20/18
08-38423_ SBd 1029.24/R39.1
605/31/18
09-36690_ MNO 203 5.1/5.7 04/16/18
09-37640_ MNO 395 12.6/25.8 11/02/18
10-0L870_ STA 99 13.4 / 13.8 01/25/18
10-0S120_ MER 152 0/0 04/10/18
10-0S680_ ALP 004 19.48/31.11 07/19/18
10-0S740_ ALP 088 .3/2.6 10/29/18
10-0S750 ALP 088 0/4.75 04/23/18
10-0X730 AMA 049 3.7/4 01/26/18
10-0X750_ ALP 004 26.15/26.15 12/28/18
10-0Y600_ MPA 140 21.2/22.8 04/04/18
Temecula Lane Replacement
RIV 10 Rehab substructure
HM1 122 FY 18/19
Repair damanged embankment and culvert
RIV 62 Widen shoulders
SBD 330 Construct rockfall barrier
SBD 95 Roadway Rehabilitation
SBD 95 Roadway Rehabilitation
SBD 62 Roadway Rehabilitation
Installing TMS field elements
Lower Main Street Sidewalk
SB Long Valley thin blanket
Stanislaus auxiliary lane
Drainage restoration
Alpine Culvert Rehab
SJ/ALP 88 Drainage system
Culvert rehabilitation
1014000111 - Jackson Bridge replacement
Mountain counties bridge rails
Mariposa crosswalks
RIV 015 Bridge Maintenance
SBD 60 Replace existing guide signs (Phase 1)
RIV 60 Replace existing guide signs (Phase 1)
RIV 10 Palen Ditch bridge rail upgrade
RIV 74 Hemet Upgrade ADA
RIV 79 Hemet Upgrade ADA
RIV-79 Near Temecula Mill & Overlay
Washington Br. - Replace overcrossing
SBD 95 Shoulder rumble strips
SBD 15 Permanent restoration of irrigation and plant
material
HM1 18/19
RIV/SBD Repair detection sites
SBD 210 Ramp widening
SBD 15 Install electric ZEV charging stations
SBD 15 Repair damaged road
SBD 215 Modify striping detail
SBD 215 Modify striping detail
RIV 60 install pilot CCTV surveillance system
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
7
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
10-1C040_ MPA 049 0/18.5 10/16/18
10-1C170_ MER 099 12.7/17.6 02/08/18
10-1C170_ MER 099 12.7/17.6 05/11/18
10-1C200_ SJ 004 0/5 08/28/18
10-1C280_ SJ 099 30.8/31.5 06/12/18
10-1C330_ SJ 205 0/13.4 08/13/18
10-1C500_ SJ VAR 15.5/16.5 02/23/18
10-1C690_ TUO VAR 0/0 01/08/18
10-1C800_ SJ 004 0/0 07/18/18
10-1C810_ MER 099 0/0 07/18/18
10-1C940_ SJ 005 26.47/26.47 02/15/18
10-1C960_ SJ-Var Var 0/0 05/16/18
10-1E531_ SJ 08822.093/22.0
9306/12/18
10-1F400 SJ VAR 0/0 06/21/18
10-1F460_ SJ 004 4.1/4.9 10/12/18
10-1H470_ STA,SJ108,120,
165Various 08/20/18
10-1H820_ MPA 49/14029.0/42.3 &
11.3/18.702/02/18
10-1J300_ MER 152 21.0 05/15/18
10-1J420_ CAL 049 7.60/8.70 12/19/18
11-2E009_ SD 005 0/0 02/28/18
11-41133 SD 008 6/12 06/27/18
11-41750_ SD 005 34.6/35.1 10/03/18
11-41810_ SD5,15,75,16
3VAR 05/03/18
11-41820_ SD 078 0/0 05/04/18
11-42030_ SD 052 0/14.8 01/24/18
11-42050_ IMP 078 62.3/R73.8 06/04/18
11-42060_ IMP 115 10.4/19.8 01/03/18
11-42211 SD 8R25.1/R40.
106/05/18
11-42750_ SD 005 0.3/15.2 08/24/18
11-42810_ SD 008 L0.7/R23 08/21/18
11-42970_ SD VAR VAR 06/25/18
11-42980_ SD 015 11.5/31.2 05/07/18
11-43042 SD 076 11.0/17.0 03/19/18
12-0M990_ ORA 001 9.31/9.39 11/28/18
12-0N520_ 12 405 7.3/11.8 10/08/18
12-0N530_ ORA 55 13.2/17.8 12/06/18
12-0N860_ ORA 073 23.96/24.16 02/28/18
12-0P42U_ ORA VAR 0/0 04/25/18
12-0P520_ ORA 022 12.03/12.64 06/04/18
SD-008-L0.7/R23.0 - drainage system restoration
Repair existing loop detectors
Install radar detection systems
SJ culverts rehab
Victor onramp
SR205 Smart corridor - Phase 2
SJ SR 5 Bridge Deck Rehabilitation
Pavement Resurfacing and Restoration
Tuolumne Drainage restoration
SJ bridge maintenance
D10 bridge substructure repairs
Repair damage from Lilac Fire
Modifying the Existing Lane
12-0M990 PCH/Broadway Culvert Bridge
12-0N520 Rt 405 Roadside Worker Safety Project
12-0N530 Rt 55 Roadside Worker Safety Project
Mariposa SR 49 CAPM
SR99 Merced rehab
SR99 Merced Rehab
I-5, SR57, & SR 91 ICM123 Project combined with
ICM 1,2, & 3
SR22 & SR 57 Install Safety Lighting
11-SD-8 Roadside safety improvements
I-5 Detention basins
Construct ADA curb ramps
1114000063 - Culvert Rehabilitation
Rumble strips, upgrade end treatments
1115000052 - Culvert Rehabilitation
Culvert rehabilitation
Culvert Rehabilitation
Intelligent transportation system technology
SR 120 TMC Upgrade
Liberty Safety Improvement
1016000053 - SJ changeable message signs
SJ Middle River Bridge Roadway Realignment
RHMA Overlay
Detwiler Fire
152 Intersection Control
Angels Camp oversight
Mitigation I-5 Batoqiotos bluffs
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
8
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
12-0P680_ ORA 001 13.0/33.6 12/21/18
12-0P700_ ORA 5 3.29 05/31/18
12-0Q280_ ORA 001 27.04/29.89 12/06/18
12-0Q290_ ORA 039 19.36/19.36 05/11/18
12-0Q580_ ORA VAR 2.700/17.10 12/07/18
12-0Q850_ ORA 005 34.5/37.4 12/21/18
12-0R260_ ORA 090 5.5/8.1 & 11/08/18
District-EA County Route Post MileDate
Signed
01-0C440 HUM 101 102.9/105.2 09/28/17
01-0G840 HUM 096 4/8 10/02/17
01-0G970 MEN 101 86/87.5 06/02/17
01-0H090 MEN 101 97.14/97.14 11/29/2017
01-0H120 MEN VAR 0/0 06/02/17
02-4F360 LAS 036 26.2/26.6 12/6/2017
03-0H400 VAR VAR 0/0 12/8/2017
03-1G010 YUB 020 1.9/3.5 8/22/2017
03-2H750 BUT 070 41.5/41.5 10/12/2017
03-2H760 PLA 174 2.32/2.32 10/12/2017
03-2H770 YOL 016 20.75/20.75 10/12/2017
03-2H800 SIE 049 20.48/27.14 10/12/2017
03-2H860 SAC 160 4.54/9.24 10/12/2017
03-2H920 NEV 049R14.05/R14
.0510/12/2017
03-2H950 YUB 049 6.73/6.73 10/12/2017
03-2H960 NEV 049 22.7/22.7 10/12/2017
03-2H970 PLA 193 9.83/9.83 10/12/2017
03-3f540 SAC VAR 0.000/0.000 10/19/2017
04-0J140 SM 92 6.0 11/16/2017
04-2J540 SON 001 24.3/24.4 12/28/2017
04-3J300 SF 001 6.3/6.3 12/15/2017
04-3K310 ALA VAR 0/0 10/26/2017
04-3k320 CC VAR 10/25/2017
04-3K330 SCL VAR 0/0 10/27/2017
04-3K340 VAR VAR 0/0 10/27/2017
04-3K350 VAR VAR 0/0 10/27/2017
04-4K680 SCL 130 9.3/9.3 6/27/2017
06-0Q920 KER 099 19.54/21.08 12/20/2017
06-0U300 VAR VAR 0/0 9/25/2017
07-12030 LA 405 32.17/32.25 12/14/2017
07-29360 LA 405 14.4/15.6 12/26/2017Crenshaw 405 interchange
12-0Q850 I-5 Polyester concrete on 3 bridges
0417000135 - Detection restoration service contract
Construct tie-back wall and sheet pile wall
Correct Vertical Clearance
0616000027 - Tulare & Kings Co wire theft restoration
Drainage Culverts
0415000147 - 3J300 Lighting rehabilitation
Detection Restoration Service Contract
Detection Restoration Service Contract
Detection Restoration Service Contract
Detection Restoration Service Contract
326 CE Approvals from previous reporting periods (prior to January 1, 2018) -- State Highway
System Projects1
Project Description
Repair slide & rock fall fence
0112000284 - Rehab Safety Roadside Rest Area
(SRRA)
HUM-96 Slide Repair
Storm repairs near Cummings
Storm Repairs - MEN-101 & 271
South Susanville Gateway
Upgrade EMS Sign
RHMA Overlay/DIKE/PCC Island Removal
BUT 70 Pulga Soldier Pile Wall
PLA 174 Slipout Repair
Yolo 16 Culvert Repair
SIE 49 Culvert & Slope Repair
Sac 160 Levee Rdwy Repair
Nev 49 GV Culvert Liner
YUB 49 Slipout
Nev 49 Slipout
West of Old Canada Rd
SON-1 soldier pile wall and RSP
Pla 193 Sinkhole Repair
Scour Repair-Geotech Lagoon Creek
12-0P680 Upgrade Traffic Signal
Drainage Restoration
Signal Modification
12-0Q280 PCH Install Outer Seperation Barrier
12-0Q580 2nd Meter On Minor A
Resurface mainline with RHMA
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
9
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
08-0R310 RIV 074 12.09/14.28 11/3/2017
08-1H350 SBD 015 R20.000/R2 12/5/2017
10-0L870_ STA 99 13.4 / 13.8 10/2/2017
10-1F740 CAL 004 0/0 11/14/2017
10-1H440 CAL 49 20.5/25.0, 8/31/2017
10-1H460 STA 132 0.0/13.3 10/19/2017
10-1H480 TUO 108 45.5/67.0 9/6/2017
11-41132 SD 008 5/6.3 10/30/2017
11-41134 SD 008 12/13 10/30/2017
11-42000 SD 094 10.4/14.9 6/21/2017
12-0M820 ORA 001 10/10.53 10/13/2017
12-0N660 ORA 133 3.42/13.64 12/5/2017
12-0N930 ORA 001 20.5/20.9 10/2/2017
Footnotes1
Includes approvals omitted in error from previous reporting period(s) and other corrections, shown in italics. Notes on project-specific
corrections are as follows:
- 10-0L870 Stanislaus AUX lane - CE originally reported in error in the 23 USC 326 2017 Annual Report (dated January 22, 2018) with an
approval date of 10/2/17; CE was approved on 1/25/18.
SR 4 and SR 26 in Calaveras, Amador, and Alpine
Reconstruct sidewalks and curb ramps & driveways
SBD 15 Pave invert culverts
Calaveras overlay
Stanislaus overlay
Stanislaus auxiliary lane
Tuolumne overlay
11-SD-8 & 15 Roadside safety improvements
11-SD-8 & 125 Roadside safety improvements
SR-94 Pavement rehab
1214000041 - 12-0M820 RTE1 Mandated ADA
Rte 133 Replace Damaged and Outdated MBGR
1215000009 - 12-0N930 1 Clean & rehab 2000 ft
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
10
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
District-EA County Route Post Mile Project Description TypeDate
Signed
01-0G130_ DN 199 10.24/10.7 Widen Shoulders De minimis 11/30/2018
02-0H560_ BUT 070 29.7/48.01 Drainage Rehabiliation De minimis 8/31/2018
05-1C960_ MON 101 R41.4/41.8Salinas River bridge seismic
retrofitDe minimis 2/7/2018
10-0Y600_ MPA 140 21.2/22.8Install crosswalks & In-
roadway warning lights
De minimis &
Programmatic4/4/2018
10-1C800_ SJ 004 0/0 SJ bridge maintenance Programmatic 7/18/2018
District-EA County Route Post Mile Project Description TypeDate
Signed
NONE
Approvals from previous reporting periods (prior to January 1, 2018) -- State Highway System
Projects - Section 4(f)
State Highway System Projects - Section 4(f)
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
11
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
Federal Aid Project
NumberDistrict
Date
Signed
BRLO-5904(138) 01 HUM 10/12/2018
BRLO-5904(147) 01 HUM 10/12/2018
BRLO-5914(077) 01 LAK 8/7/2018
BRLO-5914(079) 01 LAK 06/29/18
BRLO-5914(092) 01 LAK 06/26/18
ER-30R0(012) 01 MEN 7/31/2018
ER-32D0(007) 01 MEN 1/9/2018
ER-32L0(076) 01 MEN 9/4/2018
ER-32L0(137) 01 HUM 05/02/18
ER-32L0(175) 01 HUM 12/12/2018
ER-32L0(267) 01 HUM 2/6/2018
ER-38F0(001) 01 MEN 2/22/2018
ER-38F0(010) 01 MEN 8/27/2018
HSIPL-5017(044) 01 HUM 3/16/2018
HSIPL-5017(046) 01 HUM 06/12/18
HSIPL-5076(012) 01 LAK 1/9/2018
RPSTPL-5904(143) 01 HUM 7/13/2018
ATPL-5068(055) 02 SHA 12/28/2018
BRLO-5068(032) 02 SHA 05/04/18
BRLO-5907(061) 02 LAS 06/05/18
BRLO-5907(065) 02 LAS 06/05/18
Permanent Restoration under Emergency Opening
Procedures - Alderpoint Road PM 18.25
Emergency Opening - East Read, CR 230, Redwood
Valley
Restoration-Main Street CR 407E MP 0.04
Bridge Replacement-Sharon Avenue at A.C.I.D. canal
Bridge Replacement-Muddy Slough on Punkin Center
Road (Bridge 7C-88)
Bridge Replacement-Replace Bridge 07C0089 over
Muddy Slough No. 2 on Punkin Center Road in
Lassen County.
Bike Path - Diestelhorst to Downtown - various streets
and trails in the City of Redding
Restoration-North State Street PM 6.59/7.27
Install High Visibility Crosswalk Markings - Thirty-eight
(38) non-signalized crosswalk locations throughout
Eureka.
Upgrade Signals-Signalized Intersections: H Street at
6th, 7th, 14th, Buhne, Henderson, and Harris; and I
Street at 6th, 7th 14th, and Henderson.
Local Assistance 326 CE Projects
Bridge Replacement - Holmes Flat Rd Over Larabee
Low Level Eel River. Bridge #04C0171
County Project Description
Restoration - Mountain View Road, CR 510 PM 22.02
Restoration-Bell Springs Road CR 324 PM 3.50
Install Pavement Markings - Arterial and Collector
Streets within the City of Lakeport
Class I Multi-Use Path-Adjacent to, & west of, HUM-
101 between Eureka and Bracut.
Restoration - Alderpoint Road PM 1.67/1.68
Bridge Replacement-Clayton Creek at Clayton Creek
Road in Lake County
Bridge Replacement-Clover Creek Bridge at First
Street (Br. No. 14C-0015)
Bridge Preventative Maintenance-Cache Creek Bridge
on Bartlett Springs Road
Emergency Opening-Alderpoint Road PM 34.79
Bridge Replacement - Bridge No. 04C0172, McCann
Road over Eel River, E Dyerville Loop Rd.
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
12
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
BRLS-5068(036) 02 SHA 3/1/2018
BRLS-5906(088) 02 SHA 05/01/18
ER-32D0(015) 02 SIS 9/17/2018
ER-32L0(428) 02 MOD 1/12/2018
ER-32L0(433) 02 SHA 12/6/2018
ER-32L0(536) 02 LAS 12/12/2018
ER-32L0(537) 02 LAS 12/17/2018
HSIPL-5068(057) 02 SHA 11/5/2018
HSIPL-5906(120) 02 SHA 3/15/2018
HSIPL-5906(122) 02 SHA 05/18/18
SRTSL-5908(092) 02 TEH 3/16/2018
ATP03-5924(243) 03 SAC 11/19/2018
ATP-5398(011) 03 ED 8/2/2018
ATPCML-5015(027) 03 ED 04/16/18
ATPCML-5398(012) 03 ED 05/16/18
Bridge Replacement-Cassel-Fall River Road at Pit
River - Bridge 6C-39
Emergency Opening and Restoration-Salmon River
Rd
Bridge Replacement - Eastside Road at Olney Creek
Roadway Widening-Deschutes Rd bewteen Beatie Rd
and Brundage Rd (Phase 2)
Pedestrian Walkway - Los Molinos, Stanford Ave
between Palm St and Grant St.
Pedestrian and Bike Path - 47th Avenue Pedestrian
and Bicycle Improvement Project.
Emergency Opening - Herlong Access Road at Long
Valley Creek / Bridge 07C0007
Bike Lane - Churn Creek Rd betw Hartnell and
Cypress Aves, and Margalia St betw Churn Cr Rd and
Hilltop Dr
Roadway Widening - Deschutes Rd Between Balls
Ferry Rd and Beatie Rd (Phase 1)
Road Related - Other - Modoc County Road 87,
various locations
Emergency Opening - Reconstruct pavement and
shoulders on Big Bend Road. - Big Bend Road - 2
locations were repaired in 2017 / 2018 - Roaring
Creek MP 7.65 shoulder & guardrail, & MP 14
shoulder washouts.
Emergency Opening - Along Wendel Road north and
south of, and including, bridge 07C0055 at Skedaddle
Creek, about 19 to 20 miles southeast of US395.
bicycle/pedestrian safety improvements-from the
existing Class I Path at the Al Tahoe Blvd/Johnson
Blvd Intersection east to the Route 50/Al Tahoe Blvd
Intersection
Project to widen shoulders to add Class II bike lanes-
on Broadway from Schnell School Road to Jacquier
Road/Point View Drive
Bike lanes, paths, pedestrian sidewalks, lighting,
hardscape and landscape improvements project-on
Sierra Blvd from Palmira Avenue to Barbara Avenue
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
13
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
ATPCML-5925(129) 03 ED 12/7/2018
ATPCML-6506(001) 03 ED 2/21/2018
ATPL-5002(179) 03 SAC 04/23/18
ATPSB1L-5002(173) 03 SAC 2/6/2018
ATPSB1L-5924(242) 03 SAC 12/6/2018
BRLO-5925(108) 03 ED 7/18/2018
BRLS-5018(012) 03 NEV 2/21/2018
BRLS-5924(190) 03 SAC 7/10/2018
CML-5002(192) 03 SAC 8/3/2018
CML-5023(022) 03 NEV 9/28/2018
CML-5163(037) 03 SUT 12/7/2018
CML-5425(038) 03 BUT 3/19/2018
CML-5447(044) 03 YOL 8/30/2018
CML-5919(128) 03 PLA 2/22/2018
CML-5925(132) 03 ED 12/17/2018
Meadowview Rd Streetscape Project
Road Rehabilitation - Folsom Blvd btwn Mayhem and
Bradshaw.
Bridge Replacement-Hanks Exchange Road at
Squaw Hollow Creek ~0.4 miles South of Pleasant
Valley Road
Construct Class I multi-use bike/ped path,
approximately 2.54 miles. - El Dorado Trail from
Missouri Flat Rd to El Dorado Rd
Pedestrian and Bike Path - South Tahoe Greenway
Shared Use Trail, Phases 1b & 2
Cycle track project-on North 12th Street from
American River to H Street
Bike Path - Martis Valley Trail Project. Complete a 10'
wide paved Class 1 multipurpose trail connecting
Northstar Village roundabout to the southerly border
of Army Corps property.
Construct a multi-use ped/bike over-crossing w/ a 12'-
14' wide concrete deck - POC on El Dorado Trail over
Missouri Flat Rd
Pedestrian and Bike Path - Along Franklin Rd., east of
State Route 99 between South Palora Ave. and Gray
Ave
Construct new sidewalks, curbs and gutters, Class II
Bicycle Lanes - Fir St (Skyway to Black Olive), Birch
St (Skyway to Black Olive)
Pedestrian and Bike Overpass-1500' overpass:
Sycamore Park from Westmore Oaks School over US
50 connecting Joey Lopes Park
Pedestrian and Bike Path-From access road entrance
to Condon Park on Scotia Pines Circle and connect to
the existing roadway along the main park entrance on
Minnie Street.
Bridge Replacement - Nevada Street at Deer Creek
bridge, near Broad Street - Br. No. 17C-02
Bridge Replacement-New Hope Road over Grizzly
Slough 0.5 miles North of the San Joaquin County
Line
Construct sidewalks, install a signalized intersection
with accessibility compliant crosswalks-Woolley Way
from Albatross to DW Babcock School
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
14
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
CML-5925(145) 03 ED 05/31/18
CML-5925(166) 03 ED 9/6/2018
CMLNI-6085(076) 03 SAC 8/9/2018
CMLNI-6158(084) 03 PLA 3/2/2018
CMLNI-6236(018) 03 SAC 06/20/18
CMSTPL-5046(044) 03 YOL 2/22/2018
ER-32L0(484) 03 SIE 06/14/18
ER-32L0(485) 03 SIE 06/14/18
ER-32L0(486) 03 SIE 06/14/18
ER-32L0(487) 03 SIE 06/14/18
ER-32L0(489) 03 SIE 06/12/18
ER-32L0(490) 03 SIE 8/31/2018
ER-32L0(491) 03 SIE 05/21/18
ER-32L0(495) 03 YUB 3/9/2018
ER-32L0(496) 03 YUB 3/9/2018
ER-32L0(510) 03 BUT 7/18/2018
ER-32L0(515) 03 YUB 04/02/18
ER-36P0(003) 03 YUB 3/9/2018Restoration of failed AC pavement sections -
Woodrullf Lane from SR-70 to Jack Slough Road
Upgrade and install pedestrian and bicycle
infrastructure-Various locations on Merrychase and
Country Club Dr in Cameron Park
Emergency Opening and Restoration-Mountain House
Road 2
Emergency Opening and Restoration-Mountain House
Road 3
Emergency Opening and Restoration-Mountain house
Road 4 a and b
Spare the Air, Phase 2, 17/18 FY; Voluntary driving
curtailment program (public outreach)-Throughout the
Sacramento region.
Construct full road vehicle, bicycle, and sidewalk
safety improvements. - West Main St., between West
St. and CR 98
Emergency Opening and Restoration-Mountain House
Road 1
Miscellaneous - Other - NI reduce traffic congestion in
the Apple Hill Area during tourist season-El Dorado
County Apple Hill area
Transportation Demand Management Phase 3, 2018-
TDM Phase 3, 2018
Planning,Programming and Monitoring - Congestion
Management Program 2018
Restoration of 2 culverts and shoulder erosion.-La
Porte Road from 0.69 miles west of Aero Way to 1.1
miles west of Aero Way.
Emergency Opening and Restoration of pavement
failure due to flood waters - Ramirez Road from
Tanabe Road to Butte County Line.
Restoration of AB shoulder - Simpson Lane from 400'
east of Bridge over Yuba River to 600' east of
Babbington Road
Emergency Opening and Restoration of Roadway
Slipout at three locations-Oroville Quincy Hwy
Emergency Opening and Restoration-Smithneck
Road
Emergency Opening and Restoration-Henness Pass
Road
Restoration-Westside Rd A23
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
15
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
ER-36P0(004) 03 YUB 2/6/2018
ER-38F0(011) 03 BUT 06/14/18
FSPCMLNI-
6158(088)03 PLA 10/25/2018
HRRRL-5917(093) 03 NEV 05/14/18
HSIPL-5002(184) 03 SAC 11/19/2018
HSIPL-5002(186) 03 SAC 2/20/2018
HSIPL-5037(034) 03 BUT 2/8/2018
HSIPL-5089(026) 03 PLA 7/12/2018
HSIPL-5475(041) 03 SAC 9/25/2018
HSIPL-5917(098) 03 NEV 1/8/2018
HSIPL-5919(127) 03 PLA 2/22/2018
HSIPL-5922(110) 03 YOL 8/21/2018
HSIPL-5924(235) 03 SAC 10/30/2018
NHCBPL-6081(043) 03 NEV 3/6/2018
RPSTPL-5924(241) 03 SAC 9/25/2018
STPL-5046(039) 03 YOL 2/22/2018
Restoration of pavement failure - Ramirez Road from
SR-70 to Tanabe Road
Emergency Opening-0.35 miles west of the
intersection of Skyway Crossroads and Skyway.
Various signalized intersections throughout the City of
Citrus Heights.
Thermoplastic striping and pavement markers along
approx. 30 miles - Various road segments: Garden
Bar Rd, Lime Kiln Rd, McCourtney Rd, N. Bloomfield-
Graniteville Rd, Ridge Rd, Rough & Ready Hwy, Tyler-
Foote Crossing, Wolf Rd, and You Bet Rd.
Street Lighting, pavement markers, flashing beacons
at non-signalized intersections - 19 intersections
throughout southwest Placer County
Street Lighting - Three Corridors
Upgrade existing pedestrian signals to include
countdown heads. - Fifty (50) intersections throughout
the City limits.
Install crosswalk enhancements at unsignalized
locations.-Various locations throughout the City.
Traffic Related - Other - Freeway Service Patrol
Road Safety Sign Audit and sign modification
accordingly-130 Miles of Various County Roads Major
and Minor Collectors
Install advanced dilemma zone loops for the high
speed approaches - 6 Locations
Road Rehabilitation-Complete Streets Rehab: Florin
Rd, Martin Luther King Jr, Micron Ave.
Sidewalks, class 2 bike lanes, bus turnouts, & safety
improvements - East Main St
Guardrail-Old River Road (south of County Road 124)
and South River Road (south of Freeport Bridge).
Traffic Related - Other See Comments - Florin Rd
between Franklin Blvd and Power Inn Rd (excluding
the segment at the SR-99 interchange).
Bridge Rehabilitation - Bridgeport Historic Covered
Bridge, South Yuba River State Park, south Fork of
the Yuba River, French Corral
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
16
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
STPL-5095(025) 03 PLA 2/6/2018
STPL-5187(011) 03 PLA 3/19/2018
STPL-5482(032) 03 SAC 05/10/18
STPL-5924(212) 03 SAC 1/3/2018
STPL-5925(164) 03 ED 2/13/2018
STPLNI-6085(075) 03 SAC 7/12/2018
STPLNI-6478(007) 03 ED 06/11/18
ATCMTDL-
6480(017)04 ALA 8/31/2018
ATPL-5303(017) 04 CC 3/14/2018
ATPL-5333(018) 04 SM 04/11/18
ATPL-6480(010) 04 ALA 11/16/2018
ATPSB1NI-
6429(022)04 NAP 2/28/2018
BHLO-5934(168) 04 SF 2/13/2018
Pedestrian and Bike Path-Construct a separated, 6-
foot-wide pathway for students and pave the road
shoulder for cyclists.
15-mile active transportation corridor consisting
mainly of Class I trail facilities. - East Bay Greenway;
15-miles under elevated BART tracks in Oakland, San
Leandro, Hayward, Ashland, and Cherryland from
north of Fruitvale BART Station to South Hayward
BART Station
SRTS project Non-infrastructure - 38 Napa County
Schools
Bridge Rehabilitation - Islais Creek Bridge on Third
Street over Islais Creek Channel
Road Rehabilitation - Rising Sun Road from Ben
Taylor to W. Grass Valley Street
Road Reconstruction-On Zinfandel Blvd., modify US
50 ramp intersections, lengthen turn pockets, add
additional overhead signage, and build ped refuge
islands.
New Signals - Fair Oaks Blvd. btw Howe Ave. and
Munroe St.
Road Rehabilitation - Granite Dr, Lonetree Blvd, Blue
Oaks Blvd, Wildcat Blvd, Park Dr, Sunset Blvd, Sierra
College Blvd, and West Oaks Blvd.
Pedestrian Safety Program - intersection of Francisco
Dr/Schooner Dr and Francisco Dr/Kensington Dr
Planning,Programming and Monitoring, Phase 3, 2019-
PPM (RSTP) Phase 3, 2019
Miscellaneous - Other-Develop a project plan with
options for a revenue assessment and collection
system related to vehicle use at Lake Tahoe.
ITS Improve, Signal Sys & Other Technologies to
Manage Truck Arrivals and Improve Incident
Response-Oakland: In the Port of Oakland and
Surrounding Area
Complete Streets Improvement and Road Diet - Along
Rumrill Boulevard between San Pablo Avenue to the
north and Costa Avenue (City Limits) to the south
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
17
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
BPMP-5012(137) 04 ALA 8/7/2018
BPMP-5101(029) 04 ALA 7/10/2018
BPMP-5375(033) 04 CC 04/10/18
BRLO-5043(038) 04 MRN 2/8/2018
BRLO-5937(182) 04 SCL 3/12/2018
BRLS-5094(066) 04 SOL 11/16/2018
CML-5005(142) 04 SCL 1/29/2018
CML-5267(022) 04 SM 9/13/2018
CML-5306(029) 04 SCL 05/29/18
CML-5309(018) 04 SCL 05/29/18
CML-6249(046) 04 SOL 05/14/18
CML-6297(008) 04 SF 05/23/18
CML-6297(009) 04 SF 05/23/18
CMLNI-6072(020) 04 CC 1/25/2018
CMLNI-6084(219) 04 MULT 3/28/2018Transportation Demand Management - West Grand
Ave Corridor in Oakland
Electric Vehicle Programs and Outreach-Bay Area
Counties
Comprehensive Car Share Expansion and Outreach
Program - West Contra Costa Communities of
Richmond, El Cerrito, and San Pablo.
Bridge Preventative Maintenance-On 98TH Ave
(Bridge No 33C0148) and on 23RD Ave (Bridge No.
33C0218)
Convert one-way couplets to two-way streets, reduce
lanes and add bike lanes - 5005(142) Almaden
Avenue and Vine Street only.
Sidewalk-San Carlos: At the intersections of Arroyo
Ave and Cedar St and Hemlock St and Orange Ave
and the Postman Walkway: Implement safety
improvements.
Pedestrian Walkway-On Eden Ave Bet. Hamilton Ave
& north city limits:
Install new sidewalk and buffered Class II bike lanes,
along with improving crosswalks and rechannel-In Los
Altos; Miramonte Ave from Foothill Expwy to northern
City limit.
Bridge Preventative Maintenance-City of Pleasanton:
5 Bridges, 33C0454, 33C0099, 33C0453, 33C0461,
and 33C0462.
Cleaning, patching, apply Methacrylate-Bridge 28C-
0454, Cottonwood Dr @ Grayson Crk; Br. 28C-0410,
Norse Dr @ Contra Costa Canal; Br 28C-0411, Viking
Dr @ Grayson Crk; Br 28C-0349, Elinora Dr @
Grayson Crk;...
Bridge Replacement, Br No. 27C0148 - Southern
Heights Blvd over Hillside, junction Meyer Road
Bridge Replacement - Bridge NO. 37C0172, New Ave,
over Red Fox Crk,1.6 MI N Leavesly Rd.
Bridge Replacement - Buck Avenue Bridge over
Alamo Creek
Operate Call Center Featuring In-Person Assistance
for Transit, Commuting, and Mobility Services-Solano
County: Countywide
Miscellaneous - Other-San Francisco Bay Area,
Region - wide.
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
18
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
DEM05L-5933(123) 04 ALA 2/5/2018
ER-26E0(001) 04 NAP 11/2/2018
ER-32L0(204) 04 SF 2/28/2018
ER-32L0(511) 04 CC 04/05/18
ER-38H0(002) 04 NAP 05/31/18
ER-5277(030) 04 MRN 2/12/2018
HPLUL-5933(116) 04 ALA 12/20/2018
HSIPL-5005(150) 04 SCL 12/31/2018
HSIPL-5012(149) 04 ALA 8/9/2018
HSIPL-5032(030) 04 SOL 1/5/2018
HSIPL-5127(031) 04 CC 10/30/2018
HSIPL-5354(039) 04 ALA 2/9/2018
HSIPL-5920(156) 04 SON 05/30/18
HSIPL-5923(118) 04 SOL 3/26/2018
Upgrade Traffic Signals; Install Lighting - Whipple
Road/Central Avenue and Decoto Road/Perry Road
New Center Line, Edge Line Rumble Strips, Upgrade
Existing Striping to Enhance Night Visibility-Lakeville
Road between State Route 116 and SR 37
Install New Guardrail and Upgrade Existing Guardrail -
Various Locations in Unincorporated Solano County.
Total 22 locations.
Construct Curb and Gutter, Sidewalk, ramp and High
visibility Crosswalk and pavement rehb. - Haviland
Ave. from Grove Way to Blossom Way
Restoration - 04/06/17 - DAF RAC-NAP-011-0 & 015-
0 are not ER eligible because of off Fed-aid system
Pavement restoration at various locations
Rock bolting, wire mesh with scaling and catchment
system. - O'Shaughnessy Blvd Southbound lane
Install New Class II Bicycle Lanes, Enhanced Safety
Features at Ped Crossings, ...-Fruitvale Avenue from
Ashbrook Court to East 10th Street
Improve Traffic Signals - 1. Sunset Ave b/w SR12 and
Railroad Ave East. 2. Walters Rd. b/w SR12 & E.
Tabor Ave.
Warning signs, centerline rumble strips, protected left
turn, high friction surface treatment - West Leland
Road from Bailey Road to Rail Road Avenue including
intersection approaches.
Install Buffered Bike Lanes, Enhanced Crosswalks,
Flashing Beacons, Lighting - White Road between
Penitencia Creek Road and Rose Avenue
Emergency Opening and Restoration-St. Mary's Road
700' South of Diftwood Drive
Emergency Opening and Restoration-Petrified Forest
Road @ MPM 0.5/1.8
Restoration: approx. 4ft section of roadway from edge
of road 110 linear ft collasped due to storm - approx.
345 Forrest Ave in City of FairFax
Roadway reconstruction, realignment,truck climbing
lane,median barrier signing and striping. - Vasco
Road- Livermore City limit to Mile Post 3.00
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
19
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
HSIPL-5923(119) 04 SOL 3/26/2018
HSIPL-5927(114) 04 MRN 1/16/2018
HSIPL-5928(130) 04 CC 05/14/18
HSIPL-5928(140) 04 CC 10/26/2018
HSIPL-5928(144) 04 CC 05/16/18
HSIPL-5933(142) 04 ALA 04/03/18
LPPSB1L-6480(015) 04 ALA 10/25/2018
RSTP-6084(224) 04 MULT 1/3/2018
STPCML-5415(014) 04 CC 10/31/2018
STPL-5034(027) 04 SCL 12/13/2018
STPL-5094(068) 04 SOL 9/13/2018
STPL-5135(054) 04 CC 2/26/2018
Upgrade Existing Painted Edge and Center Lines to
Thermoplastic with raised Pavement Markers -
Various locations within unincorporated area of
Solano County
Road Related - Other - Sir Francis Drake Blvd from
MP 8.60 to 9.53
Complete Street Improvement including Traffic Circle -
Danville Boulevard between Stone Valley Road and
Jackson Way in unincorporated Alamo
Construct ADA Curb Ramp, Curb, Gutter, and
Sidewalk; Install Rectangular Rapid Flashing
Beacons-Intersections of Olympic Boulevard at
Bridgefield Road and Walden Road at Westcliffe
Lane.
Install Guardrails-Fairmont Drive between Lake
Chabot Road and 2700 Fairmont Drive
Signage, install centerline rumble strip/stripe; Install
intersection ahead flashers & street light.-Marsh
Creek Road between City Limits of both Clayton and
Brentwood
Monterey Road between 1st Street and 8th Street:
Pavement preservation including rehabilitation,
resurfacing, roadway reconstruction, and/or spot
reconstruction
Road Rehabilitation-Various streets in City of
Vacaville including: Arcadia Drive, Tulare Drive,
Lawrence Drve, Gibson Canyon Road, Dobbins
Street, Hickory Lane, Mason Street, California Drive.
Road Rehabilitation and paving, adjust utilities to
grade, ADA upgrades, Class 3 bike route,... -
Commerce Avenue from Concord Avenue to end of
cul-de-sac at southern end.
7th Street Grade Separation East. - Port of Oakland,
sea port area along the following roadway segments:
7th street b/n Maritime and Bay Street Circle.
Planning,Programming and Monitoring - SF Bay Area:
Regionwide: Planning and implementation of various
multi-modal operational policies.
Bicycle Related - Other - Moraga Way and
Canyon/Camino Pablo
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
20
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
STPL-5225(029) 04 CC 9/7/2018
STPL-5267(023) 04 SM 9/13/2018
STPL-5306(031) 04 SCL 9/4/2018
STPL-5322(059) 04 ALA 10/9/2018
STPL-5350(021) 04 SM 7/2/2018
STPL-5350(022) 04 SM 10/9/2018
STPL-5361(028) 04 MRN 06/25/18
STPL-5376(014) 04 SM 10/24/2018
STPL-5383(012) 04 SON 8/2/2018
STPL-5928(148) 04 CC 7/17/2018
STPL-5935(078) 04 SM 8/2/2018
Resurface Pavement, Pavement Repair, Pavement
Markings,Shoulder Backing-San Mateo County
Edgewood Rd between 0.17 mi west of Crestview Dr
to Cervantes Rd and Canada Rd between the NB and
SB 280 off- and on-ramps.
Road Rehabilitation-3 Locations: San Pablo Dam
Road, El Portal Drive, and Vasco Road
Road Rehabilitation-Nave Dr. from Alameda Del
Prado to Bel Marin Keys Blvd., Bel Marin Keys Blvd.
from Nave Dr. to 200 ft North of Digital Dr., Bolling Dr.
from Nave Dr. to Marin Valley Dr.
Road Rehabilitation - Brisbane: Tunnel Ave from
northern city limits (N/O Beatty Ave) to 1500 ft. south:
Rehabilitate pavement
Road Rehabilitation new ADA accessible curb ramps,
sidewalks, curb and gutter, electrical conduit-Within
the City of Cotati in the County of Sonoma. 680ft long
and 70ft wide segment of East Cotati Ave between
SMART railroad tracks to the west and Sunflower Dr.
to the east.
Rehabilitate Pavement and Implement Bike/Ped
Improvements - Carrillo Drive, Grimmer Blvd, Mission
Blvd, Carol Ave, Las Palmas Ave, Mission View Dr,
Fremont Blvd, Deep Creek Rd, Farwell Dr, Olive Ave,
Warm Springs Blvd and Palm Ave.
Asphalt Concrete Overlay-Linda Mar Blvd from Adobe
Drive to Alicante Drive and on Oceana Blvd from
Milagra Drive to Monterey Road
Sidewalk - At various locations throughout the city:
Install 100 new curb ramps.
Road Rehabilitation-North Main Street between the
Interstate 680 Overpass and California Boulevard
Road Rehabilitation-San Carlos: On Cedar Street,
between San Carlos Ave and the City of Belmont, and
Brittan Ave, between Elm Street and El Camino Real
Winchester Blvd from northern city limit near
Rosemary Ln to southern city limit at Knowles Dr and
Campbell Ave from Jeffers Way to Winchester Blvd:
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
21
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
STPL-5937(218) 04 SCL 11/2/2018
STPL-6084(239) 04 MULT 11/29/2018
STPL-6169(013) 04 SF 10/22/2018
STPLNI-5100(025) 04 SCL 7/5/2018
STPLNI-6084(222) 04 MULT 1/3/2018
STPLNI-6084(225) 04 MULT 1/3/2018
STPLNI-6084(226) 04 MULT 3/12/2018
STPLNI-6084(230) 04 MULT 3/30/2018
STPLNI-6084(231) 04 MULT 3/14/2018
STPLNI-6084(232) 04 MULT 3/1/2018
ATPSB1L-5944(135) 05 MON 12/31/2018
BHLO-5944(099) 05 MON 6/29/2018
BHLO-5944(100) 05 MON 8/21/2018
BHLO-5951(152) 05 SB 2/22/2018
BRLO-5423(029) 05 SLO 9/5/2018
BRLO-5949(156) 05 SLO 9/21/2018
BRLS-5423(032) 05 SLO 9/5/2018
BRLS-5949(131) 05 SLO 9/13/2018
CASB-5949(092) 05 SLO 1/31/2018
ER-32D0(002) 05 SCR 9/5/2018
Las Lomas Drive Bicycle Lane
Bridge Rehabilitation-Robinson Canyon Road
Bridge Rehabilitation-Bradley Road Bridge
Bridge Scour Repair and Counter-Measure - Alamo
Pintado Bridge 51C0081 Los Olivos
Bridge Replacement-Santa Lucia Road @ Graves
Creek - Br. No. 49C-0164
Planning,Programming and Monitoring - SF Bay
Area: Regionwide
Planning and implementation of various multi-modal
operational policies - SF Bay Area: Regionwide
Parking management technologies, to encourage
carpool and express bus ridership. - Albany and
Oakland: I-80/Buchanan Ave, I-880/High St, I-
880/Fruitvale
System/Travel Demand Management - Alameda &
Santa Clara Counties
SF Bay Area: Regionwide: Planning Assistance to
support transportation investments and improve their
performance in priority development areas.
Road Rehabilitation - Capitol Exwy (Capitol Auto Mall
Pkwy to McLaughlin Ave)
Shared Use Mobility - Bay Area
Pedestrian and Bike Path - San Francisco: 19th St
from Illinois St to approximately 600' east
Develop a Comprehensive Planning Document
Similar to a Specific Plan for a Mixed-Use
Neighborhood-In proximity to the California Ave
Caltrain station, the California Ave Business District,
El Camino Real and the Stanford Research Park.
Incident Management program - San Francisco Bay
Area Region
Bridge Replacement-Jack Creek Road over Paso
Robles Creek; Br. No. 49C-0342
Bridge Replacement-Via Ave @ Atascadero Creek -
Br. No. 49C-0158
Bridge Replacement - Replace 2-lane bridge with 2-
lane plus left-turn lane-El Camino Real at Santa
Margarita Creek Bridge - Br. No. 49C0310
Construct Bikeway - Morro Bay - Cayucos Bikeway
Connector
Emergency Opening-Soquel-San Jose Rd PM 5.36
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
22
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
ER-32D0(003) 05 SCR 12/27/2018
ER-32D0(014) 05 SCR 7/5/2018
ER-32L0(009) 05 SCR 9/5/2018
ER-32L0(011) 05 SCR 7/23/2018
ER-32L0(012) 05 SCR 9/5/2018
ER-32L0(021) 05 SCR 4/9/2018
ER-32L0(025) 05 SB 12/21/2018
ER-32L0(031) 05 SB 6/4/2018
ER-32L0(110) 05 SLO 7/5/2018
ER-32L0(203) 05 SB 3/20/2018
ER-32L0(222) 05 SCR 9/11/2018
ER-32L0(435) 05 MON 10/1/2018
ER-32L0(435) 05 MON 5/4/2018
ER-32L0(436) 05 MON 2/2/2018
ER-32L0(437) 05 MON 7/11/2018
ER-32L0(438) 05 MON 10/1/2018
ER-32L0(438) 05 MON 5/4/2018
ER-32L0(439) 05 MON 10/1/2018
ER-32L0(439) 05 MON 5/4/2018
ER-32L0(440) 05 MON 7/11/2018
ER-32L0(440) 05 MON 10/1/2018
ER-32L0(456) 05 MON 7/11/2018
ER-32L0(457) 05 MON 2/6/2018
Emergency Opening - Cabrillo College Drive PM 0.50
Emergency Opening and Restoration-Glen Haven
Drive PM 0.81
Emergency Opening-Bear Creek Road PM 0.2
Emergency Opening-Bear Creek PM8.02
Emergency Opening-Soquel-San Jose Rd PM 5.91
Emergency Opening and Restoration-Paulsen Road
PM 0.43
Emergency Opening and Restoration - Hall Road at
Sill Road
Emergency Opening and Restoration - Hall Road at
Sill Road
Emergency Opening and Restoration - Corral de
Tierra Road
Emergency Opening and Restoration-Hall Road at
Johnson Road
Emergency Opening and Restoration-Soquel Dr Aptos
Street/Valencia Creek Rd PM 5.56
Emergency Opening and Restoration - Tepusquet
Road PM 11.0
Emergency Opening-Cathedral Oaks Road 0.1 mi
north of Calle Real
Emergency Opening and Restoration-Burton Drive
PM 2.0(120' north of village ln)
Emergency Opening and Restoration - Lompoc-
Casmalia Road 600' S of Bishop Rd
Emergency Opening and Restoration - Hall Road at
Pini Road
Emergency Opening-Metz Road
Emergency Opening and Restoration - San Juan
Grade Road
Emergency Opening and Restoration - Aromas Road
MP .5
Emergency Opening and Restoration -Aromas Road
MP .5
Emergency Opening and Restoration - Hall Road at
Las Lomas
Emergency Opening and Restoration - Hall Road at
Las Lomas
Emergency Opening and Restoration-Hall Road at
Pini Road
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
23
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
ER-32L0(458) 05 MON 7/10/2018
ER-32L0(458) 05 MON 10/1/2018
ER-32L0(462) 05 SB 12/21/2018
ER-32L0(465) 05 SB 12/21/2018
ER-38M0(001) 05 SB 7/18/2018
ER-38M0(002) 05 SB 10/29/2018
ER-38M0(003) 05 SB 10/29/2018
ER-38M0(004) 05 SB 6/26/2018
ER-38M0(005) 05 SB 7/18/2018
ER-38M0(006) 05 SB 7/26/2018
ER-38MO(001) 05 SB 7/18/2018
HPLU-5949(132) 05 SLO 1/18/2018
HPPLU-5025(061) 05 SCR 7/9/2018
HSIPL-5007(078) 05 SB 6/26/2018
HSIPL-5025(068) 05 SCR 9/7/2018
HSIPL-5045(033) 05 MON 2/6/2018
HSIPL-5138(052) 05 SB 12/4/2018
HSIPL-5138(053) 05 SB 11/30/2018
HSIPL-5944(130) 05 MON 8/2/2018
Emergency Opening and Restoration-San Juan Road
at Aromas Road
Emergency Opening and Restoration - San Juan
Road at Aromas Road
Road Reconstruction-Ortega Ridge Road
Road Rehabilitation-On Hot Springs Road from Oak
Road to East Mountain Drive
Road Reconstruction and bridge railing-Sheffield
Drive and Bridge 51C-0048
Bridge Rail-Hot Springs Road at Montecito Creek
Pedestrian and Bike Path - Multi-Use Bob Jones Trail -
Construct Class 1 Bike & Ped Path from San Luis
Obispo to Avila Beach
Restoration - San Marcos Road PM 1.6 from
Cathedral Oaks
Restoration - Stowell Road East of SR101
Emergency Opening and Restoration-Hot Springs
Road Bridge 51C-0041
Road Reconstruction - North Jameson Lane between
Olive Mill and Sheffield Dr
Restoration - Olive Mill Road btw Hill Rd and Hot
Springs
Median and Left Turn Lane and Striping Work - In the
City of Santa Maria on N. Broadway (Rte 135)
between Main St. (Rte 166) and Mill St.
Upgrade existing Guard Rails-Various locations along
Carmel Valley Rd, Carpenteria Rd, Outlook Dr,
Laureles Grade, Old Stage Rd, Reservation Rd, and
San Juan Road
Pedestrian and Bike Path-Santa Cruz Branch Rail
Line from Pacific Ave to Natural Bridges Dr
Install PED timers, enhanced pvmt markings, access
ramps, warning signs, improve sight lines-Various
intersections ( 22) within the City of Santa Barbara
Pedestrian and Bike Path-various roads in the City of
Santa Cruz
New Signals - North Main between Chaparral and
Navajo Streets
Construct a Median Barrier and Road Diet Feature - In
the City of Santa Maria on N. Blosser Road (from W.
Taylor St. to Atlantic Ave)
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
24
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
HSIPL-5949(167) 05 SLO 12/14/2018
HSIPL-5949(169) 05 SLO 9/27/2018
-5950(452) 06 KER 5/14/2018
ATPCML-5157(100) 06 MAD 6/27/2018
ATPL-5060(333) 06 FRE 1/3/2018
ATPL-5122(088) 06 TUL 4/13/2018
ATPL-5946(167) 06 TUL 4/5/2018
BPMP-5197(024) 06 FRE 4/26/2018
BRLO-5941(089) 06 MAD 9/25/2018
BRLO-5942(234) 06 FRE 3/29/2018
BRLO-5942(247) 06 FRE 7/18/2018
BRLO-5946(106) 06 TUL 8/24/2018
BRLO-5946(108) 06 TUL 8/6/2018
CMAQ-5950(460) 06 KER 9/25/2018
CML-5044(122) 06 TUL 9/19/2018
CML-5060(341) 06 FRE 10/8/2018
CML-5109(241) 06 KER 2/28/2018
CML-5115(035) 06 KIN 1/31/2018
CML-5157(108) 06 MAD 4/25/2018
CML-5157(109) 06 MAD 4/26/2018
Segment Lighting at Intersections - Segment Lighting
at Intersections.
Install RRFBs and Overhead Flashing Beacons-Bob
Jones Trail (Ontario Rd), North Ocean Ave (between
Cayucos Dr and E St), Dana Elementary Schol in
Nipomo (Tefft St)
Universe Ave : Mcray Street to North Chester Ave in
Oildale
Bridge Replacement-Bridge 41C0149 on Avenue 16
1/2 over Dry Creek
Replace 2 Lane Bridge with 2 Lane Bridge - Bridge
42C0078 on Lost Hills Ave. over Jacalitos Creek
Replace Two Lane Bridge with Two Lane Bridge-
Bridge 42C0289 on North Frankwood Avenue over
Alta Main Canal
Replace Two Lane Bridge with Two Lane Bridge-
Bridge 46C0196 on M375A Mineral King Road over
East Fork Kaweah River
Replace 1 lane with 2 Lane Bridge-Bridge 46C0208
on Avenue 364 over Cottonwood Creek
Bike Path-Fresno River Trail and UPRR
Undercrossing.
Install traffic signals - Cedar Ave. and Woodward Ave.
Pedestrian Walkway-Olive Avenue Corridor
Crosswalk Warning Lights Installation Project
Pedestrian Walkway-Earlimart Safe Routes to School
Community Projects
Bridge Preventative Maintenance-Citywide
Pedestrian Walkway-Sidewalk Construction Around
Schools and Commercial areas.
Asphalt Concrete Overlay-Alley Paving on Various
Locations.
Road Related - Other: install AC shoulders and class
II bike lane-Fruitvale Ave: Norris Road to Snow Road
Roundabout-Intersection of Tulare Avenue and Santa
Fe Street
New Signals - Divisadero and Mariposa Streets
Intersection
New Signals - Stine Rd at McKee Rd
CNG Station Expansion - CNG SITE AT 857 IONA
AVE.
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
25
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
CML-5157(110) 06 MAD 4/25/2018
CML-5170(058) 06 FRE 6/13/2018
CML-5252(025) 06 FRE 9/20/2018
CML-5252(026) 06 FRE 9/20/2018
CML-5258(035) 06 MAD 8/14/2018
CML-5305(018) 06 FRE 4/6/2018
CML-5941(114) 06 MAD 3/15/2018
CML-5942(283) 06 FRE 6/22/2018
CML-5950(454) 06 KER 6/28/2018
CML-5950(455) 06 KER 7/6/2018
CML-5950(456) 06 KER 7/18/2018
CML-5950(457) 06 KER 7/18/2018
CML-5950(458) 06 KER 9/26/2018
CMLNI-5044(119) 06 TUL 1/18/2018
CMLNI-5072(061) 06 TUL 7/24/2018
CMLNI-5096(035) 06 FRE 9/27/2018
CMLNI-5115(033) 06 KIN 7/18/2018
CMLNI-5122(086) 06 TUL 3/20/2018
CMLNI-5157(105) 06 MAD 6/19/2018
CMLNI-6087(059) 06 KER 1/22/2018
CMLNI-6087(062) 06 KER 12/17/2018
CMLNI-6326(004) 06 FRE 5/15/2018
Shoulder Paving-Golden State Blvd from Pecan to
Madera Community Hospital Entrance.
Bike Path-Madsen Ave Bike Trail - From Stroud to
Kamm
Road Related - Other- Paving and valley gutter
installation-Merced/Tuolumne St Alley Paving from K
to Zediker
Interconnect Signals-Oildale Drive from Merele
Hanggard Drive to Airport Drive and Norrris Road.
Bike Path-Renfro Rd between Rosedale HWY to
Hageman Rd.
Road Reconstruction:surface unpaved shoulders and
install class II bike lane-Breckenridge Rd: Monica
Street to Commanche Dr.
Interconnect Signals-Union Ave: Casa Loma Dr./ Ming
Ave to Fairview Road.
Road Related - Other- Costruct AC shulders and
class II bike lane-Nord Ave: Stockdale highway to
Reina Road
Pedestrian and Bike Path-Manning Ave Sidewalk and
Bike Lane from Academy to Mendocino
Pedestrian Walkway-Various Locations near Wilson
School, Chowchilla, CA
Road Related - Other-Alleys btwn. Railroad & Lassen
Aves., Huron Ave. & 5th St., and Azteca Blvd. & O St.
Road Reconstruction - Road 30 from Ave 12 to 500ft
north
Road Related - Other-Jensen Ave. from Dickensen
Ave. to Madera Ave.
Rideshare - 17/18 Rideshare Program
Rideshare - Throughout Kern County
Bus Purchase: Purchase (1) clean Diesel School Bus-
clovis unified school district corporation yard Clovis
Ca
Equipment Purchase - City of Visalia
Equipment Purchase-City of Tulare
Purchase street sweeper-Selma
Equipment Purchase-Purchase CNG Refuse Truck
Purchase 5 CNG-powered municipal solid waste
trucks. - City of Porterville Corporation yard
Street Sweeper-Purchase One Diesel PM Certified
Street Sweeper.
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
26
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
CMLNI-6326(005) 06 FRE 5/15/2018
CMLNI-6336(006) 06 FRE 7/16/2018
CMLNI-6338(010) 06 FRE 6/11/2018
CMLNI-6423(008) 06 FRE 6/27/2018
HSIPL-5060(349) 06 FRE 12/20/2018
HSIPL-5060(350) 06 FRE 12/20/2018
HSIPL-5109(247) 06 KER 8/23/2018
HSIPL-5109(248) 06 KER 8/23/2018
HSIPL-5122(085) 06 TUL 10/31/2018
HSIPL-5157(111) 06 MAD 4/30/2018
HSIPL-5281(027) 06 KER 4/6/2018
HSIPL-5343(012) 06 KER 3/27/2018
HSIPL-5946(161) 06 TUL 1/11/2018
HSIPL-5946(174) 06 TUL 3/22/2018
HSIPL-5950(440) 06 KER 8/17/2018
Bus Purchase-clovis unified school district corporation
yard
Upgrade signing with new LED stop signs, solar
speed limits signs, striping, & ADA improvement
Install guardrails and centerline rumble strips/stripes,
improve signs and striping. - Worth Drive (M 146)
between Road 278 and Road 284.
Rumble strips and flashing beacons. - Drive 134
(Spare Drive) between Road 134 and Road 124.
Guardrail placement at various locations in Kern
County (9 locations)
Remove existing pedestrian walk/dont walk signal
head and install new ped. countdown time modules-
Fifty-Seven (57) location within north west portion of
the City of Bakersfield.
Remove existing pedestrian walk/dont walk signal
head and install new ped. countdown time modules.-
Eighty-eight (88) signalized intersections within south
west portion of the Cit of Bakersfield.
Replace existing traffic signal, add NB/SB protected
LT phasing, add mast arm mounted LT heads -
Intersection of Olive Ave. and Newcomb St.
Install Pedestrian medians and ADA compliant
sidewalks.-Sunset Ave from Granada Ave to Foster
Ave.
Median Barrier-Lerdo Hwy between Cherry Ave and
Zerker Rd
Bus Purchase: Purchase three (3) CNG school buses
to replace 3 old diesel school buses.-Fresno Unified
School District Corporation yard
Bus Purchase: Purchase one (1) clean diesel bus-
Southwest Transportation Agency Maintanance Yard
Bus Purchase: Purchase two (2) CNG school buses-
Kings Canyon Unified School Dist. maintenance yard
Pedestrian Walkway - Herndon Ave. from Golden
State Blvd. to Willow Ave.
Pedestrian Walkway - Shaw Ave. from West to
Chestnut Avenues
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
27
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
STPL-5044(128) 06 TUL 8/14/2018
STPL-5060(318) 06 FRE 2/28/2018
STPL-5060(320) 06 FRE 1/29/2018
STPL-5060(325) 06 FRE 3/5/2018
STPL-5060(342) 06 FRE 4/26/2018
STPL-5109(249) 06 KER 10/10/2018
STPL-5109(250) 06 KER 10/10/2018
STPL-5170(055) 06 FRE 5/17/2018
STPL-5197(032) 06 FRE 2/14/2018
STPL-5208(156) 06 FRE 8/29/2018
STPL-5252(027) 06 FRE 9/20/2018
STPL-5281(025) 06 KER 1/3/2018
STPL-5285(019) 06 FRE 7/16/2018
STPL-5305(016) 06 FRE 10/29/2018
STPL-5343(010) 06 KER 2/28/2018
STPL-5942(292) 06 FRE 6/20/2018
STPL-5950(442) 06 KER 1/2/2018
STPL-5950(443) 06 KER 1/2/2018
STPL-5950(451) 06 KER 5/14/2018
Asphalt Concrete Overlay - SB Friant Road from
Champlain to Shepherd Avenues
Asphalt Concrete Overlay - Inyo Street from Fulton to
'O' Streets
Street Lighting-Various Locations
Road Reconstruction - District Blvd; Between Gosford
Rd to Stine Rd (2.0 miles)
Road Reconstruction - Wible Rd; Between White Ln.
to Planz Rd. AND South H St. between Pacheco Rd.
to White Ln.
Road Reconstruction-Bethel Ave. from SR99 SB
Ramps to Golden State
Pavement Rehabilitation, widening, bike lanes,
replace damaged curb, gutter, SW, ADA ramps -
Bethel Ave. between Annadale Ave. and Jensen Ave.
Road Rehabilitation-Various location
New Road-Owens Mountain Parkway, East of
Temperance Past Enterprise Canal
Road Reconstruction-Zediker Ave Reconstruction
from Fresno St to Merced St
Road Rehabilitation - Beech Ave: State Ave to E.
Tulare Ave.
Road Reconstruction-5th Street from Oller to Quince
St, and Black Ave from Rowe Ave to Sorensen Ave,
Lassen Avenue (SR269) between 9th and 10th
Streets
Pedestrian Walkway and landscape improvements -
W. Kern Ave (Southside):3rd Street to 4th Street.
Furnishing and placing hot mix asphalt concrete
(HMA) overlay and shoulder backing-Nees Ave -
From Millux Alignment to Russell Avenue
Road Rehabilitation - Gibson Avenue: Gilmore Ave to
Rosedale Highway
Road Rehabilitation: AC overlay - Degiorgio Rd.
between SR 184 to Tejon Hwy.
Road Reconstruction-Stockton Ave : China Grade
Loop to Universe Ave in Oildale
Asphalt Concrete Overlay - Blackstone Avenue from
Dakota to Ashlan Avenues
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
28
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
STPL-5950(453) 06 KER 6/27/2018
STPLNI-6087(061) 06 KER 10/31/2018
ATPL-5006(855) 07 LA 11/2/2018
ATPL-5107(044) 07 LA 2/15/2018
ATPL-5108(182) 07 LA 11/9/2018
ATPL-5108(187) 07 LA 10/4/2018
ATPL-5131(021) 07 LA 11/7/2018
ATPL-5369(011) 07 LA 4/24/2018
ATPL-5419(050) 07 LA 11/2/2018
ATPL-5953(710) 07 LA 8/3/2018
ATPL-5953(737) 07 LA 4/30/2018
ATPL-5953(738) 07 LA 4/27/2018
ATPL-5953(739) 07 LA 4/27/2018
ATPL-5953(741) 07 LA 7/17/2018
Road Rehabilitation-Gilmore Ave: Gibson Street ot SR
99
18/19 Traffic Count Program - Throughout Kern
County
Pedestrian improvements - Downtown Los Angeles
Broadway Historic Theater District Pedestrian
Improvements between 4th-6th Streets
Bike Path Improvements, dedicated two way bike lane
and new bike /pedestrian path - Michigan Avenue
Greenway: Completing Bike/Pedestrian Expo
Connection Over the Interstate - 10
Bike Path - South Water FrontPier J Bike and
Pedestrian Path
Delta Avenue Bicycle Boulevard
Pedestrian Walkway - Pedestrian Gap Closure
Improvements,
Bicycle Related - Other-Quarry Clasp/ Peck Park
Bike Trail
Class 2 and 3 bike lanes, bike signal detection and
bike parking at key locations. - Throughout Arcadia
and part of Sierra Madre to South City limit.
Install crosswalks, pedestrian scale lighting, bulb
outs, truncated domes, reallign crosswalks, etc-
Wilcox Avenue Avenue Complete Streets and Safe
Routes Project
Pedestrian and bicycle facility
Improvemento on corridors: Pedestrian & Bike
Path(2miles bikeway & 2.5 mile upgraded pedestrian
fac-The project includes improvements on corridors
near the Metro Aviation/LAX Station including
pedestrian and bicycle facilities
Improvements of curbs ramp, bulb-outs, signalized
crossings, non-signalized crossing, new sidewalk,-
Located in the Los Nietos-West Whittier community
Bike Path-Install bike paths along the Big Dalton
Wash between Irwindale Ave and Lark Ellen Ave and
between Arrow Hwy and Citrus Ave, and bike lanes
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
29
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
ATPL-5953(773) 07 LA 11/2/2018
ATPSB1L-5392(058) 07 VEN 10/29/2018
BPMPL-5953(764) 07 LA 9/12/2018
CML-5006(733) 07 LA 1/16/2018
CML-5006(779) 07 LA 6/15/2018
CML-5006(828) 07 LA 6/4/2018
CML-5006(836) 07 LA 11/30/2018
CML-5006(842) 07 LA 11/30/2018
CML-5006(859) 07 LA 6/8/2018
CML-5026(061) 07 VEN 12/18/2018
CML-5107(045) 07 LA 1/12/2018
CML-5107(046) 07 LA 1/18/2018
Construct improvts to the Wells Center Bus stop,
including new sidewalk, access ramp for ADA, etc -
On Wells Road between Carlos Street and Citrus
Drive
New bycycle connector ramp Beach Bike Path Ramp
Connection to Santa Monica Pier - Santa Monica Pier
from Ocean Avenue to Marvin Braude Bike Trail
Pedistrian improvement, lighting and curb extension,
bicycle improvement - 17th St. from Wilshire BLVD.
and 17th St. past Expo Station at Colorado Ave.
Michigan Ave from 14th St. to 19th Court.
Construct new sidewalks and curb ramps, retrofit
existing curb ramps to meet ADA requirements -
Sidewalks on Conejo School Road and WIllow Lane,
between Hampshire Road & Hillcrest Dr.
Misc - Install curb extensions (bulb outs), ramps,
countdown signal heads, etc. - Slauson Ave & Hooper
Ave; Slauson Ave & Compton Ave; Slauson Ave &
Holmes Ave; Compton AVe & 60th ST
BPMP --- Group 26-5 bridges located at Calabasas,
Palmdale & San Fernando
Pedestrian Improvement Project. Install pedestrian
and transit amenities - Western Av btw Exposition Bl
& I-10 Freeway
Sidewalk improvements, safety lighting, etc.-
Pasadena Ave Ped Connection to Gold Line Heritage
Sq Station
Hollywood Integrated Modal Information System-
Hollywood Area along Hollywood Blvd. and Sunset
Blvd. between Gower and La Brea.
Pedestrian Walkway - Metro Expo LR Station @
Western Ave and Exposition Blvd
Install 15 historic stanchions, guide books and internet
access to guide peds and transit users - Angel Walk
Central Avenue
Evergreen Park Street Enhancement Project(Pedest
Safety Program,improved sidewalks,etc)-Evergreen
Park Street Enhancement Project
1st St on North, Lorena St on East, 6th on South,
and Soto on West
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
30
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
CML-5334(063) 07 LA 3/5/2018
CML-5392(055) 07 VEN 8/27/2018
CML-5952(194) 07 VEN 11/27/2018
CML-5952(197) 07 VEN 12/21/2018
CML-5953(744) 07 LA 6/27/2018
ER-32L0(524) 07 LA 9/12/2018
ER-32L0(525) 07 LA 11/13/2018
ER-32L0(529) 07 LA 10/4/2018
ER-32L0(533) 07 LA 11/30/2018
FERPL16-5405(087) 07 VEN 1/31/2018
HPLUL-5112(013) 07 LA 5/25/2018
HSIPL-5006(789) 07 LA 1/30/2018
Grade & cut the slope to 1-1/2 to 1 to make it stable -
Kanan Rd @ MM 3.34
County forces to place 32 enviro block (2 rows)to act
as gravity wall in front of the damgd rockwall -
Fernwood Pacific Dr @ house no. 1447
Restoration: Restore the road and shoulder damage
and stabilize the slope failure. - Little Tujunga Canyon
Rd @ MM 9.06, MM 9.45, MM 10.25 & MM 11.86
Localized reconstruction, coldmilling and street
overlay, sidewalk, curb & gutter reconstruction, TRA -
First St from Fitzgerald Rd to Bluegrass St. and
Fitzgerald Rd from Appletone to Sequia Avenue.
Transit Center-Azusa Intermodal Transit Center
New Signals - Ventura Blvd/Lemona Ave, Ventura
Blvd/Columbus Ave, Ventura Blvd/Calhoun Ave, S
Crest Dr/W Pico Blvd, Alhambra Ave/Lowell Ave
Road Related - Other - Telegraph Rd.(Rio Hondo
River and Lakewood Blvd.); Rosemead Blvd.
(Passons Blvd. and San Gabriel River)
Install new sidewalks, install new and retrofit existing
curb ramps, modify vehicle stripping-Rancho Road
between Thousand Oaks Blvd and Haaland Drive.
Construct 1850 feet of sidewalk from Joan way to Rio
Mesa high school - In county of ventura,on Central
ave construct sidewalk from Joan way to Rio Mesa
high School
ClasII Bike lanes along west side of Sespe From
South Mountain rd. to Pasadena Ave. South of City of -
Sespe Street from South mountain Rd. to Pasadena
Ave.
Metro Green Line Vermont Station
Signage:Installation of wayfinding signage &
information/edu mtls-In the vicinity of Metro Green
Line Vermont Station
Repair damgd CMP pipe & flared inlet;fill the washed
slope, place rip rap & repave the edge of pavem-Lake
Hughes Rd @ MM 0.65
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
31
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
HSIPL-5006(791) 07 LA 4/16/2018
HSIPL-5006(793) 07 LA 1/30/2018
HSIPL-5006(794) 07 LA 2/5/2018
HSIPL-5006(843) 07 LA 1/26/2018
HSIPL-5064(074) 07 LA 8/6/2018
HSIPL-5064(084) 07 LA 7/31/2018
HSIPL-5069(013) 07 LA 5/11/2018
HSIPL-5111(067) 07 LA 3/5/2018
HSIPL-5149(020) 07 LA 4/23/2018
HSIPL-5202(018) 07 LA 6/5/2018
HSIPL-5240(035) 07 LA 6/12/2018
Install Activated Pedestrian Warning Devices
(APWDs); construct bulb-outs-Olympic Blvd/Orme
Ave, Olympic Blvd/Camulos St, Olympic Blvd/S
Evergreen Ave, Olympic Blvd/S Dacotah St
New Signals, Install a traffic signals - W 3rd St/Hoover
St; W Anaheim St/Bay View Ave; W Anaheim St/N
Marine Ave; E Century Blvd/Wadsworth Ave;
Hollywood Blvd/N McCadden Place
Install Rectangular Rapid Flashing Beacons - Citywide
list of 46 locations including W 3rd St/S Van Ness
Ave, etc
Install RRFBs at uncontrolled locations - citywide
Pedestrian Walkway ,Install pedestrian bulb-outs and
curb ramps; enhance striping-Fair Oaks
Ave./Colorado Blvd.; Lake Ave./Mountain St
Modify traffIic signal to install turn sign,corner curb
extn,left turn pockets,striping,etc.-Intersections of
Lake ave/Orange Grove blvd; Mountainst-Seco
St/Lincoln ave, and Lincoln ave/Forest ave.
Install pedestrian safety devices and crosswalk
lighting system; upgrade traffic signals-Huntinton
Dr./5th Ave.; Duarte Rd./Peck Rd.; Foothill
Blvd./Sunset Pl.; Foothill Blvd./California Ave.
Install LED countdown pedestrian heads, accessible
pedestrian signals with ADA compliant SH Button -
forty signalized intersections within the city of Whittier.
installation of larger Signal heads, signal masts &
reflective back plates at 3 major intersections;-Foothill
Boulevard(State Route 66) Corridor (1.5 miles) from
Damien Ave. in the west to Towne Center Dr. in the
east wheeler Avenue, Emerald Avenue and Fruit
Street/White Avenue.
Install protective left turn phasing at intersection,
installation of raised medians at approaches,-Glen
oaks Blvd from Hubbard Street to Arroyo Street
Replace existing permisive left turn
movementswithprotected permisive left turn
phases,new signals-Left Turn Phasing Project (12
intersections). Modify traffic signals to add left turn
phasing, bicycle and Pedetrian detection, ADA
improvements and Striping
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
32
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
HSIPL-5325(017) 07 LA 8/8/2018
HSIPL-5334(061) 07 LA 6/22/2018
HSIPL-5334(062) 07 LA 10/3/2018
HSIPL-5347(038) 07 LA 4/26/2018
HSIPL-5347(040) 07 LA 4/26/2018
HSIPL-5351(035) 07 LA 7/3/2018
HSIPL-5362(023) 07 LA 10/22/2018
HSIPL-5373(025) 07 LA 10/29/2018
HSIPL-5436(018) 07 VEN 6/12/2018
HSIPL-5952(190) 07 VEN 6/12/2018
HSIPL-5953(698) 07 LA 3/29/2018
HSIPL-5953(757) 07 LA 2/22/2018
HSIPL-5953(760) 07 LA 4/23/2018
Modification of the existing traffic signal from a
protective-permissive signal to a fully protected-
intersection of Bloomfield Ave & 166th Street
Upgrade Signals- Paramount Boulevard - Gardendale
Street to Telegraph Road
Upgrade Signals - Stewart and Gray - Old River
School Road to Firestone Boulevard
Upgrade Traffic Signals-Rosecrans Ave. between
Studebaker Rd and Carmenita Rd.
Upgrade traffic signals (incl fiber optic cable,new
controllers, new traffic management system,etc-On
SanAntonio Ave-Norwalk Blvd between Rosecrans
Ave & Civic Center,and On Civic Center between
Norwalk Blvd and Bloomfield Ave.
Upgrade Signals @ various locations (see below).-Int.
of Washington Bl / Crossway Dr, Paramount Bl /
Beverly Bl, Whittier Bl / Lindsey Av, Rosemead Bl /
Gallatin Rd & Paramount Bl / Rex Rd
Upgrade Traffic Interconnected system at 39
intersections - City wide : Eastern Ave. Telegraph Rd,
Atlantic, Garfield etc.
Install protected-permissive left turn phases and
signal heads etc. - Intersection of Eastern Ave at
Lubec St & Garfield Ave at Loveland St
Widening the existing road for class II bikeways,
construct curb and gutter, install two way lane, s-
Princeton Ave. between east of Spring road and south
of Condor Drive.
Pavement widening and striping for installation of a
two way left turn.-Pleasant Valley road between
Dodge Road and Hailes Road. East of City of Oxnard.
Bikeway access improvement project
Install traffic signal improvements - Intersections of
Las Virgenes Road at Mulholland Highway and at
Piuma Road, in Unincorporated LA County Area.
Remove exist. striping and install recessed
thermoplastic striping & recessed pavement markers.-
Glendora Mountain Road from Big Dalton Canyon
Road to East Fork Road .
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
33
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
SRTS-5202(013) 07 LA 4/16/2018
SRTSL-5202(016) 07 LA 4/2/2018
SRTSL-5212(008) 07 LA 6/18/2018
STPL-5006(826) 07 LA 8/3/2018
STPL-5006(871) 07 LA 3/5/2018
STPL-5064(088) 07 LA 1/12/2018
STPL-5069(014) 07 LA 7/13/2018
STPL-5108(183) 07 LA 3/15/2018
STPL-5111(070) 07 LA 8/22/2018
STPL-5144(072) 07 LA 4/16/2018
STPL-5325(018) 07 LA 8/24/2018
Roadway resurfacing and ADA compliant access
ramps (Project XVII) - Various Locations within the
City of Los Angeles
Road Rehabilitation - The project will resurface
Orange Grove Blvd. From Lincoln Ave. to Sierra
Madre Villa Ave.
Rd rehab: Rem/repl damaged conc panels,repl
curbing,upgrade handicap ramps,upgrade ped
counters..-Huntington Drive Phase II from Magnolia to
Shamrock
Pedestrian lighiting, pavement enhancement for the
entire length of the project, - Long Beach Blvd.
between Willow St., and 405 Freeway,
Asphalt overlay, class II bike lanes, ADA sidewalk and
wheelchair access ramp improvements.-Santa
Gertrudes Avenue from Whittier Blvd to Leffingwell
Road.
Road Rehabilitation--Colorado St: San Fernando
Rd/Central Ave, Columbus Ave, Colorado
St/Broadway
Road Rehabilitation-166th St. from Carmenita Rd. to
Bloomfield Ave.
Construct improvements such as bulb outs,
crosswalks, curb ramps, ped. Refuge island--
vicinities of Morningside, O'Melveny, San Fernando
Elementary Schools and San Fernando Middle School
Pedestrian Walkway-18 intersections adjacent to 11
schools (Gridley ES, Morningside ES, O'Mcheny ES,
San Fernando ES, San Fernando MS, and 6 private
schools)
Install Crosswalks, Flashing Beacons, Speed
Feedback Signs, Bike Facility, Signs (See Comments)-
Various streets adjacent to and in the vicinities of:
American Martyrs School, Grand View ES, Meadows
ES, Pacific ES, Robinson ES, Manhattan Beach MS.
Replace existing high voltage lighting system with low
voltage , etc.-Riverside Drive: Lankershim Blvd to
Camarillo Blvd, et al
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
34
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
STPL-5367(015) 07 LA 3/5/2018
STPL-5393(037) 07 VEN 4/23/2018
STPL-5419(054) 07 LA 10/1/2018
STPLG-5111(066) 07 LA 9/12/2018
STPLH-5348(031) 07 LA 3/9/2018
ATPL-5033(053) 08 SBD 5/4/2018
BRLKS-5433(014) 08 RIV 1/17/2018
BRLS-5074(015) 08 RIV 3/9/2018
BR-NBIL(533) 08 SBD 3/27/2018
CML-6164(021) 08 RIV 10/11/2018
ER-32A0(001) 08 SBD 2/22/2018
ER-32A0(002) 08 SBD 1/12/2018
Restoration - Cajon Blvd. from 0.75 SE of Kenwood N
to 1.32 South of Cleghorn Rd.
Restoration - Lone Pine Canyon from State Highway
138 to Post Mile Marker #3 (2460 ft total).
Street Rehab Improvements to Badillo st. from Covina
Blvd . to westerty city limit and Covina Hills - Badillo
St. from Covina Blvd to westerly City limit and Covina
Hills RD From Via Verde to westerly city limit. Utilizing
toll Credits
Resurfacing and overlay-Earl joseph drive from
Ponderosa Drive to Las Posas road
Replace aging signal operating equipment etc. at 9
locations in City of Lancaster. - Citywide ( 9 Locations)
Upgrade of 2 pedestrian signals to full traffic signals
for enhanced vehicle, bike and ped safety. Greenleaf
Ave at Putnam Street and the Whittier Greenwat Trail.
Resurfasing Bellflower BLVD. - Bellflower Blvd from
Flora Vista to Alondra BLVD.
Curb and gutter, sidewalk, ADA-compliant curb
ramps, crosswalk striping, and outreach-Intersections
of Pepper Ave. and Randall Ave., 48th St. and
Western Ave., and Pacific St. and Perris Hill Park
Road, and on Meridian Avenue from Belden Street to
Randall Ave
Low Water Crossing - Dune Palms Road over the
Coachella Valley Stormwater Channel (Whitewater
River), LWC #00L0070
Replace 2-lane bridge with a 4-lane bridge - Temescal
Canyon Road over Temescal Wash approximately 0.2
miles west of Lake Street, Br. No. 56C-0050
Replace 2-lane low water crossing with 2-lane bridge -
Split Rock Avenue across the Twentynine Palms
Flood Control Channel from Buena Vista Drive to
Bagley Avenue, LWC #00L0084
Signal synchronization - Throughout the Coachella
Valley
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
35
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
HPLUL-5460(006) 08 RIV 10/15/2018
HSIP-5075(021) 08 RIV 12/26/2018
HSIPL-5275(033) 08 RIV 2/12/2018
HSIPL-5275(034) 08 RIV 2/12/2018
HSIPL-5298(028) 08 SBD 3/5/2018
HSIPL-5412(014) 08 RIV 1/12/2018
HSIPL-5421(005) 08 SBD 2/26/2018
HSIPL-5441(070) 08 RIV 10/10/2018
HSIPL-5441(071) 08 RIV 10/2/2018
HSIPL-5483(005) 08 RIV 10/15/2018
HSIPL-5956(264) 08 RIV 3/8/2018
HSIPLN-5430(033) 08 RIV 2/26/2018
Roadway widening and improvements - County Line
Road from I-10 to 600 feet east of Calimesa
Boulevard and southbound Calimesa Boulevard from
County Line Road to 125 feet south
Install pedestrian countdown signal heads, APS push
buttons, ADA curb ramps and crosswalk striping -
Murrieta Rd, Menifee Rd, Newport Rd, Goetz Rd,
Haun Rd, McCall Blvd, La Piedra Rd, Antelope Rd,
and Scott Rd.
Traffic Related - Other - Sanderson Ave from
Cottonwood Ave to Ramona Expressway
Install signal timers and pedestrian countdown heads. -
Twenty-one (21) intersections Citywide
Install advanced speed feedback warning signs,
lighting, and upgrade pavement markings -
Intersections of Mount Vernon Avenue with Pico
Street, Van Buren Street, De Berry Street, Barton
Road, and Canal Street/Grand Terrace Road
Upgrade guradrail - 22 locations throughout the City of
Moreno Valley
Upgrade marked crosswalks on various arterial
roadways - Seven locations throughout the City of
Moreno Valley
Interconnect traffic signals and install pedestrian
countdown heads - 27 intersections throughout the
City
Construct Road Diet (from 4 to 2 w/ 2 left-turn , install
bikes lanes and parking - Avenue 44 from Monroe
Street to Palo Verde Avenue
Upgrade traffic signals and install pedestrian
countdown heads - Various intersections along Main
Street and Barstow Road
Upgrade guardrail and end treatments - Reche Vista
Drive and Reche Canyon Road north of the City of
Moreno Valley and La Sierra Drive from El Sobrante
Road to Orchard View Lane north of Lake Mathews
Advanced dilemma zone detection and countdown
pedestrian signal heads - Twenty (20) intersections
located throughout the City of Cathedral City
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
36
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
PNRSL-5449(033) 08 SBD 9/10/2018
SRTSL-5457(019) 08 SBD 12/24/2018
STPL-5058(102) 08 RIV 1/25/2018
STPLER-5954(083) 08 SBD 4/9/2018
BPMPL-5948(093) 09 INY 12/13/2018
BRLO-5948(076) 09 INY 2/8/2018
CML-5184(031) 09 KER 9/5/2018
CML-5399(025) 09 KER 4/10/2018
CML-5961(005) 09 KER 2/16/2018
CML-5961(010) 09 KER 12/10/2018
HSIPL-5385(059) 09 KER 6/18/2018
HSIPL-5385(060) 09 KER 5/25/2018
STPL-5184(032) 09 KER 11/27/2018
STPL-5385(057) 09 KER 4/9/2018
STPL-5399(026) 09 KER 2/8/2018
ATPL-5059(233) 10 STA 12/12/2018
Bridge Related - Other - 5 bridges in Inyo County
(48C0005, 48C0002, 48C0021, 48C0016, and
48C0047): LA Aquaduct, Pine Creek, Big Pine creek,
and Owens River.
Road rehabilitation and landscaping - Boulder Ave
from Greenspot Road to 525 ft S/O of Highland Ave
Safe Route to Schools - 12TH St between Ave E &
Kenturcky; 13th St between Ave E and Oak Glen Rd;
Oak Glen Rd bet 13th and Wilson Creek Trail.
Roadway Widening - Buchanan Street to Banbury
Drive
Class 1 bike path-Santa Ana River Trail from
Waterman Avenue in San Bernardino to the California
Street alignment, Phase III
Project initiation documents and studies - Walker
Creek Road over the Los Angeles Aqueduct south of
Olancha, Br. No. 48C-0039
Pedestrian Walkway-Cherry Ln. From Tucker Rd. to
Elm St.
Road Reconstruction - Mendiburu Rd from Hacienda
Blvd to Neuralia Rd in California City
Shoulder Widening - 90th Street West from Avenue A
to Rosamond Blvd in Kern County
New Signals - Intersection of Red Apple Ave. and
Westwood Blvd.
Signs-Downs St. and Bowman Rd. intersection
Pavement Markings-City Wide School Crosswalk
Upgrades
Road Rehabilitation - Tehachapi Blvd. from Cury St. to
Davis St. (length 0.50 miles)
Roadway Widening-on Downs Ave. from Upjohn to
Ridgecrest Blvd.
Road Rehabilitation - Randsburg-Mojave Rd.
Rehabilitation in California City, from Mendiburu Rd to
Memorial Dr
Pedestrian and Bicycle Safety Improvements -
Paradise Road
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
37
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
BPMP-5929(260) 10 SJ 3/15/2018
BRLO-5926(055) 10 AMA 1/25/2018
BRLO-5929(235) 10 SJ 5/29/2018
BRLO-5930(058) 10 CAL 8/2/2018
BRLO-5930(061) 10 CAL 2/2/2018
BRLO-5930(063) 10 CAL 4/24/2018
BRLO-5932(073) 10 TUO 7/9/2018
BRLO-5938(226) 10 STA 8/2/2018
BRLO-5940(118) 10 MPA 8/3/2018
BRLO-5940(119) 10 MPA 12/15/2018
BRLS-5932(039) 10 TUO 10/3/2018
BRLS-5938(199) 10 STA 1/10/2018
CML-5008(156) 10 SJ 5/29/2018
CML-5059(222) 10 STA 4/11/2018
CML-5059(223) 10 STA 3/15/2018
Replace existing one-lane bridge with a wider one-
lane bridge-Italian Bar Road over Rose Creek, Br. No.
32C-0037
Replace existing 2-lane bridge with a standard 2-lane
bridge-Pleasant Valley Road over South San Joaquin
Main Canal, Bridge 38C0154.
Replace existing 2-lane bridge with a standard 2-lane
bridge-Buckeye Road over Mariposa Creek, Br. No.
40C0036
Replace existing one-lane bridge with a wider one-
lane bridge (No Added Lane Capacity) - Oak Road
over Bear Creek, Br. No. 40C0060
Bridge Replacement and Realignment of approach
roadway - Rawhide Road over Woods Creek in
James Town, Br. # 32C-044
Replace 2-lane bridge with a standard 2-lane bridge
(seismic retrofit)
Turning Lane(Install Left Turn Lane on Thornton Road
Lower Sacramento Road)-Thornton Road at Hammer
Lane and Lower Sacramento Road
Upgrade Signals-1) Tully Rd & 9th St; 2) 11th St &
Needham Ave; 3) 1st St & H St; 4) Paradise Ave & H
St
Upgrade Signals - In the City of Modesto
Bridge Preventive Maintenance - replace railing and
approaches; relocate levee access roads - Corral
Hollow Rd @ DMC (Br 29C0186); Lammers Rd @
DMC (Br 29C0348); MacArthur Rd @ DMC (Br
29C0349); Koster Rd @ DMC (Br 29C0353).
Replace existing 2-lane bridge with a standard 2-lane
bridge - Carbondale Road over Willow Creek, Br.
26C0030.
Replace 2-lane timber bridge with a standard 2-lane
bridge-Wimer Road over N Br. Indian Creek, Bridge
29C0303
Replace existing two-lane bridge with a standard two-
lane bridge.-Lime Creek Road over Youngs Creek,
Bridge 30C0018.
Replace existing one-lane bridge with a standard two-
lane bridge - Dogtown Road over French Gulch,
Bridge 30C0048.
Replace existing one-lane bridge with a standard two-
lane bridge-Dogtown Road over Indian Creek, Bridge
30C0050.
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
38
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
CML-5059(229) 10 STA 3/29/2018
CML-5059(235) 10 STA 12/14/2018
CML-5153(024) 10 STA 2/28/2018
CML-5154(043) 10 SJ 3/5/2018
CML-5165(086) 10 STA 2/16/2018
CML-5172(027) 10 STA 1/23/2018
CML-5172(028) 10 STA 1/23/2018
CML-5406(028) 10 STA 2/23/2018
CML-5938(183) 10 STA 5/29/2018
CML-5938(223) 10 STA 3/5/2018
CML-5938(225) 10 STA 1/23/2018
CML-5938(247) 10 STA 2/2/2018
CML--5938(248) 10 STA 1/31/2018
CML-6089(075) 10 STA 1/18/2018
CML-6095(077) 10 MER 5/31/2018
CML-6305(014) 10 MER 2/15/2018
ER-30E0(003) 10 CAL 10/24/2018
ER-30E0(004) 10 CAL 10/24/2018
ER-30E0(005) 10 CAL 10/24/2018
New Signals - Crows Landing Rd at Grayson Rd
traffic signalization.
New Signals - Intersection of Carpenter Rd and
Whitmore Ave.
Transit Related - Other - Throughout the County
Rideshare - Stanislaus County to Bay Area
Regional Rideshare Program - StanCOG Region
Vanpool Program-Merced County Area
Implement Public Outreach and Marketing for
Yosemite Area Regional Transportation System
(YARTS) - In Merced County
Remove/Replace AC and Base, Replace Delineators -
Fricot City Rd MP 0.0 at Sheep Ranch Road
Remove and replace damaged AC - Jesus Maria Rd
MP 0.0 at State Route 26
Signal Synchronization - outside the Downtown core
in Modesto
Rideshare - Rideshare Program
Construct extension of Bike/Ped Trail for 1/4 mile. -
City of Oakdale- From end of existing Bike/PedTrail
under SR-120 near Stanislus River.
Install Traffic signal and street lighting; EVP, ADA
ramps, and new signage and striping - at Lockeford
St. and Stockton St.
Installation of traffic signal and related intersection
improvements - Intersection of W. Main St. and West
Ave.
Pedestrian and Bike Path - On Merced St from Inyo
Ave to Driskell Ave
Pedestrian and Bike Path - On Merced St from N St to
Sherman Parkway
Sidewalk - Along the north side of West Yosemite
from Western to Pasadena
Traffic Related - Construction of a Traffic Roundabout
& Installation of Drainage Facilities.-In South Turlock
Golden State Blvd/Golf Rd./Berkeley Ave.
Intersection.
Remove and replace damaged AC pavement,
roadside appurtenances - Jesus Maria Road MP 0.0
at State Route 26
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
39
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
ER-30E0(006) 10 CAL 10/24/2018
ER-30E0(007) 10 CAL 10/24/2018
ER-30E0(008) 10 CAL 10/24/2018
ER-30E0(009) 10 CAL 10/24/2018
ER-30E0(010) 10 CAL 10/24/2018
ER-30E0(011) 10 CAL 10/24/2018
ER-30E0(012) 10 CAL 10/24/2018
ER-30E0(013) 10 CAL 10/24/2018
ER-30E0(014) 10 CAL 10/24/2018
ER-30E0(015) 10 CAL 10/24/2018
ER-30E0(016) 10 CAL 10/24/2018
ER-30E0(017) 10 CAL 10/24/2018
ER-30E0(018) 10 CAL 10/24/2018
ER-30E0(019) 10 CAL 10/24/2018
ER-30E0(020) 10 CAL 10/24/2018
ER-32L0(464) 10 CAL 1/2/2018
ER-32L0(499) 10 CAL 2/22/2018
Remove and replace damage AC pavement - Jesus
Maria Road MP 0.0 at State Route 26
Remove and replace damaged AC pavement - Jesus
Maria Road MP 0.0 at State Route 26
Remove and replace burnt guardrail - Mountain
Ranch Road
Remove and Replace burnt Guardrail (approx 237 ft) -
Jesus Maria Road
Remove and replace damaged AC, replace burnt
delineators, restripe areas with new pavement -
Sheep Ranch Road
Remove and Replace damaged AC pavement, re-
stripe areas with new pavement - Sheep Ranch Road
Restoration - Sheep Ranch Road
Remove and replace damaged AC pavement and
base - Fricot City Rd MP 0.0 at Sheep Ranch Road
Remove and replace damaged AC pavement and
base - Fricot City Road MP 0.0 Sheep Ranch Road
Remove and replace damaged culverts - Fricot City
Rd MP 0.0 at Sheep Ranch Road
Remove and Replace damaged culverts - Jesus
Maria Road MP 0.0 at State Route 26
Removal and replace damaged culverts - Jesus Maria
Road MP 0.0 State Route 26
Remove and replace damaged culverts - Jesue Maria
Road MP 0.0 at State Route 26
Remove and replace damaged culverts - Jesus Maria
Road MP 0.0 at State Route 26
Remove and replace damaged culverts - Jesus Maria
Road MP 0.0 at State Route 26
Trench and replace culvert with 48" HDPE culvert.
Install flared end sect, slurry backfill, rip rap - Campo
Seco Road PM 0.6 near Watertown Road, Calaveras
County
Emergency Opening - 4 Roads in Calaveras County.
Jesus Maria Rd (MP 1.5), Rail Road Flat Rd (0.27
North of Struckman Rd) , Mountain Ranch Rd (MP 2.8-
9.5), Sheep Ranch Rd , Jesus Maria Rd (MP 6.0 -8.5)
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
40
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
ER-32L0(500) 10 TUO 3/29/2018
ER-32L0(513) 10 ALP 6/14/2018
ER-38P0(001) 10 TUO 6/28/2018
FERPL16-5939(125) 10 MER 11/9/2018
HRRRL-5008(163) 10 SJ 10/15/2018
HRRRL-5939(118) 10 MER 12/13/2018
HSIPL-5008(153) 10 SJ 9/14/2018
HSIPL-5008(162) 10 SJ 12/21/2018
HSIPL-5008(164) 10 SJ 8/2/2018
HSIPL-5008(166) 10 SJ 11/26/2018
HSIPL-5059(227) 10 STA 9/14/2018
HSIPL-5165(091) 10 STA 3/15/2018
HSIPL-5938(238) 10 STA 5/8/2018
Emergency Opening - Tuolumne Rd North (Various
Locations) , Ferretti Rd (830' east of Rocky Point Dr)
Replace damaged 24" culvert with 2'x4' reinforced
concret box culvert (RCB)-Diamond Valley Road at
Airport Rd
Close Damage Rs, establish detour. Replace 10'
Culvert, Reconstruct embankment and roadway-
Ferritti Road
Hilmar Community Pedestrian Improvements - Geer
Avenue from Pearl Street to SR-165 and SR-165 to
Spring Street.
Road Related - Other - N. El Dorado St. between
Essex St. and the Calaveras River Trail (near E.
Ingram St.
Enhance pedestrian crosswalks - In Le Grand, South
Dos Palos and Santa Nella
Other (Install high friction treatment and variable
speed warning signs at various locations)-Feather
River Drive/Driftwood Place. Brookside Road/McGaw
Street. Bianchi Road/Bidwell Palace, and Manthey
Road/Henry Long Blvd
Turning Lane - El Dorado Street, between Hammer Ln
and Morada Ln.
Road Related - OtherInstall raised median curb along
Pacific Ave. from Calaveras River to Hammer Ln-
Along Pacific Ave. from Calaveras River to Hammer
Lane.
Upgrade SignalsTraffic Signal Visibility
Improvements(Mast-arm) - Dr. Martin Luther King, Jr.
Blvd. between N. El Dorado St. and S. Aurora St., at
the intersections of S. San Joaquin St., California St.
and S. Grant St.
New signals, traffic signs and pavement markings-
Oakdale Road at Claratina Avenue
Pedestrian Safety Program - Intersections of North
Ave and Loyola Way, N. Johnson Rd and Carrigan St,
South Ave and Martinez St, and Berkeley Ave and
Heathernoel Way
Installation of bike lanes, raised median, & lighting-
Crows Landing Road (School Ave to Whitmore Ave)
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
41
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
RPL-5932(076) 10 TUO 3/29/2018
STPL-5008(172) 10 SJ 3/6/2018
STPL-5153(040) 10 STA 2/27/2018
STPL-5154(047) 10 SJ 4/23/2018
STPL-5192(043) 10 SJ 1/17/2018
STPL-5241(052) 10 STA 5/24/2018
STPL-5929(294) 10 SJ 8/7/2018
STPL-5929(296) 10 SJ 8/7/2018
STPL-6089(076) 10 STA 1/18/2018
ATPL-6066(129) 11 SD 12/10/2018
BPMPL-5004(189) 11 SD 1/24/2018
BRLO-5958(078) 11 IMP 2/7/2018
BRLS-5957(105) 11 SD 1/24/2018
Roadway Widening and Installation of Paved
Shoulders/Operational Improvements - Mono Way
Between Peaceful Oak Rd and Via Este. Sonora,
Tuolumne County
Asphalt Concrete Overlay - Various locations:Miner
Ave (between Center St and Aurora St), Arch Rd
(between B St and SR 99 SB On Ramp), March Ln
(between Feather River Dr. and Riverbrook Rd), and
Road Rehabilitation - G Street (Maag to Ventanas)
Pavement Resurfacing-On Church St from Kettleman
Ln to Lodi Ave, Hutchins St from Harney Ln to
Kettleman Ln, Industrial Way from Beckman Rd to
Guild Ave, and Cluff Ave from Vine St to Industrial
Way
Asphalt Concrete Overlay. Roadway Resurfacing -
Tracy Blvd from Center Court to 10th Street; Central
Ave from Deerwood ln to Tracy Blvd; Lowell Ave from
Orchard Pkwy to Corral Hollow Rd; Beverly Pl from
Bessie Ave to Parker Ave;
Road Rehabilitation. Roadway Resurfacing-Resurface
French Camp Road from 1,190 feet West of El
Dorado Street to Airport Way
Planning,Programming and Monitoring
Construct a Class1 Bike Path along Harbor Drive from
the 32nd Street Naval Station to Petco Park. - San
Diego Bayshore, Bikeway, Barrio Logan Segment
Bridge Preventive Maintenance on twelve bridges
throughout the City of San Diego - Bridge Preventive
Maintenance 2 (57C-0157, 57C-0310L, 57C-0310R,
57C0311, 57C-0414, 57C-0428, 57C-0577, 57C-
0580, 57C-0594, 57c-0607 (City's Br.), 57C-0626L,
57C-0627R, 57C-0285)
Bridge Replacement - Imperial County - Verde School
Rd/East Highline Canal Br # 58C-0115
Bridge Replacement - Live Oak Park Road over San
Luis Rey Tributary 57C-0709
Asphalt Concrete Overlay-Service Road - Central
Avenue to Blaker Road
Asphalt Concrete Overlay(Resurface existing roadway
with Hot Mix Asphalt)-Resurface existing roadway with
Hot Mix Asphalt from Blossom Road to Thornton
Road.
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
42
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
CML-5168(030) 11 IMP 7/12/2018
CML-5278(018) 11 IMP 3/8/2018
FERPL16-5167(040) 11 IMP 2/13/2018
FERPL16-5958(104) 11 IMP 10/18/2018
HPLUN-5203(027) 11 SD 10/23/2018
HSIP-5958(089) 11 IMP 1/5/2018
HSIPL-5957(126) 11 SD 5/9/2018
HSIPL-5957(128) 11 SD 4/3/2018
STPL-5169(049) 11 IMP 4/26/2018
TCSP-5381(036) 11 SD 1/24/2018
ATPL-5055(186) 12 ORA 2/6/2018
ATPL-5338(052) 12 ORA 3/30/2018
BRLS-5269(025) 12 ORA 7/13/2018
CML-5266(023) 12 ORA 2/21/2018
Road Rehabilitation - Rio Vista Avenue between
Cattle Call Dr and Allen Street. Demo ID: CA541
Road Reconstruction of access road to Valley Desert
Museum and parking improvement - Ocotillo, Imperial
Valley
I-5 Corridor Study between Main Street and SR-54
(e.g. study interchange) - I-5 Corridor between Main
Street and SR-54 and Light Rail Corridor paralleling
freeway
Realignment - Barbara Worth at All American Canal
Paving dirt road De Las Flores Street between Eady
Ave & Kloke Ave, const. of curb, gutter, sidewalk-De
Las Flores Street Improvement
Construct sidewalk, curb & gutter, bike lanes, and
traffic signal modification-Winter Gardens Blvd (from
Woodside AVe to Lemoncrest Dr).
Intall a New Signal and a raised median.-Jamacha
Blvd between Sweetwater Rd & Gillespe Dr
Construct new 4-lane faciltiy-Imperial Ave: from I-8 to
McCabe in 4-Phases
Wake Avenue: Imperial Avenue to Cypress Drive
Construct a new Pedestrian Structure (Bridge) linking
Sprinter Station to Palomar College - West Mission
Rd.
Sidewalk, curb and gutter, ADA-compliant driveways,
and drainage facilities - West St from Pearl Street to
North Street and the west side of Citron Street from
Sycamore Street to La Palma Ave
Road diet and Class IV bikeway - Garden Grove
Boulevard from 0.2 miles east of Valley View Street at
the EB SR 22 on-/off-ramps/NB I-405 off-ramp to EB
SR 22 on-ramp east of Goldenwest Street
Bridge replacement-Golden Avenue over Carbon
Canyon Channel, 0.2 miles west of Rose Drive, Br.
No. 55C-0192
Class I bikeway - Along the Union Pacific Railroad
(UPRR) right of way through La Habra from the west
city limits at the Wall Street alignment to the east city
limits at Lambert Road and Palm Street
Road Reconstruction - N. H and 8th Street, paving
from 7th & 8th Street and 8th St. to I St.
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
43
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
CML-5955(104) 12 ORA 12/11/2018
HSIPL-5055(187) 12 ORA 10/15/2018
HSIPL-5063(187) 12 ORA 1/24/2018
HSIPL-5063(188) 12 ORA 5/22/2018
HSIPL-5063(189) 12 ORA 1/24/2018
HSIPL-5063(190) 12 ORA 3/6/2018
HSIPL-5073(085) 12 ORA 7/26/2018
HSIPL-5073(086) 12 ORA 7/23/2018
HSIPL-5073(091) 12 ORA 7/23/2018
HSIPL-5133(045) 12 ORA 5/29/2018
HSIPL-5133(046) 12 ORA 5/29/2018
HSIPL-5181(180) 12 ORA 4/10/2018
HSIPL-5181(183) 12 ORA 4/3/2018
HSIPL-5181(184) 12 ORA 4/4/2018
HSIPL-5181(185) 12 ORA 4/5/2018
Install pedestrian signal at 12 signalized intersection in
the City of Orange
In the city of Fullerton, Various Location
In the city of Anaheim, Various locations.
Upgrade traffic signals for protected left-turn phasing-
Intersection of Newland Street at Slater Avenue
Signal interconnect conduit and upgrade traffic signals
for protective left-turn phasing-Intersection of Newland
Street at Ellis Ave.& Newland St. from Garfield
Avenue to Ellis Avenue
Signal interconnect conduit and upgrade traffic signals
for protective left-turn phasing-Goldenwest Street
from Warner Avenue to Heil Avenue
Upgrade accessible pedestrian signals-12
intersections located throughout the City of Orange
Protected left-turn signal phasing - Intersections of 1st
Street at Jackson Street and 5th Street at Euclid
Street
Pedestrian countdown signals, crosswalk striping, and
battery back-ups-33 intersections located throughout
the City of Orange
Signal interconnect conduit and upgrade traffic signals
for protective left-turn phasing-Slater Avenue from
Goldenwest Street to Gothard Street (Inconnect) &
modify traffic signal at Gothard St. & Slater Ave.
Intersection.
Class I Bikeway along Carbon Creek Flood Channel -
OC Loop Carbon Creek Channel (Segment D) from
Imperial Hwy. (SR-90) to Bastanchury Rd. in the City
of Placentia & Orange County Flood Control District
Median island and modify signals - Euclid Street from
Crescent Avenue to Glenoaks Avenue
Bike path - Flower Street from Civic Center Drive to
Warner Avenue
Upgrade non-standard 8" vehicle head with 12"
vehicle head assembly and associated hardware-
Various locations in the City of Santa Ana
New signals - Intersection of Main Street and 15th
Street
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
44
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
HSIPL-5181(186) 12 ORA 1/24/2018
HSIPL-5312(099) 12 ORA 2/2/2018
HSIPL-5402(031) 12 ORA 2/15/2018
Federal Aid Project
NumberDistrict County Project Description
Date
Signed
ER-32L0(112) 01 HUM 8/3/2017
ATPCML-5037(037) 03 BUT 11/17/2017
ER-32L0(206) 05 SB 12/8/2017
CML-5157(103) 06 MAD 8/10/2017
ER-32L0(468) 06 FRE 12/20/2017
HSIPL-5343(012) 06 KER 3/27/2017
STPL-5197(033) 06 FRE 9/7/2017
FERSTPL-5450(096) 07 LA 12/19/2017
BRLS-5938(199) 10 STA 1/10/2017
CML-5008(145) 10 SJ 12/26/17
Replace 2-lane bridge with a standard 2-lane bridge
(seismic retrofit)
Road Rehabilitation (Miner Ave.)
Upgrade signing with new LED stop signs, solar
speed limits signs, striping, & ADA improrvement
Road rehabilitation
Asphalt overlay
Esplanade Corridor Safety and Accessibility
Improvement project.
326 CE Approvals from previous reporting periods (prior to January 1, 2018) -- Local Assistance
Projects2
Restoration - Mattole Road PM 11.13
Upgrade Signals - (52) signalized Intersection along
various street. Najor street include Imperial HWY,
Bastanchury Road, Yorba Linda Ave, Orangethorpe
Ave, Rose Drive, Prospect Ave and Fairmont.
2 Includes approvals omitted in error from previous reporting period(s) (January 1, 2017-December 31, 2017) and other corrections, shown in
italics. Notes on project-specific corrections to the 23 USC 326 2017 Annual Report (dated January 22, 2018) are as follows:
- ATPCML-5037(037) Esplanade Corridor Safety : This CE determination was included in the 23 USC 326 2017 Annual Report in error; the
NEPA approval has not been completed to date.
- HSIPL-5343(012) Upgrade Signing - CE originally reported in error with an approval date of 3/27/17; CE was approved 3/27/18.
- BRLS-5938(199) Seismic retrofit - CE originally reported in error with an approval date of 1/10/17; CE was approved 1/10/18.
Footnotes
Emergency Opening - Auburry Road, 3 mi N/O
Copper Ave
New Signals - Howard Road and Westberry Blvd.
Emergency Opening and Restoration - Alisal Road
Signal interconnect conduit and upgrade signals -
Newland Street from Ellis Avenue to Warner Avenue
Raised center median - Harbor Boulevard from 19th
Street to Wilson Street
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
45
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
Federal Aid
Project NumberDistrict Project Description Type
Date
Signed
RPSTPL-5904(143) 1 HUM
Class I Multi-Use Path-
Adjacent to/west of, HUM-101
between Eureka & Bracut.
De minimis 7/13/2018
BRLO-5068(032) 2 SHABridge Replacement-Sharon
Avenue at A.C.I.D. canalDe minimis 5/4/2018
BHLO-5934(168) 4 SFBridge Rehabilitation-Islais
Creek Bridge De minimis 2/13/2018
STPL-6169(013) 4 SFPedestrian & Bike Path - San
Francisco: 19th StDe minimis 10/22/2018
ATPL-5946(167) 6 TUL
Pedestrian Walkway-
Earlimart Safe Routes to
School Community Projects
De minimis 4/5/2018
BRLO-5946(106) 6 TUL
Replace Two Lane Bridge
with Two Lane Bridge-Bridge
46C0196 on M375A Mineral
King Road over East Fork
Kaweah River
De minimis 8/24/2018
BRLS-5074(015) 8 RIV
Replace 2-lane bridge with a
4-lane bridge-Temescal
Canyon Road over Temescal
Wash
De minimis 3/9/2018
STPLER-5954(083) 8 SBD
Class 1 bike path - Santa Ana
River Trail from Waterman
Avenue in San Bernardino to
the California Street
alignment, Phase III
De minimis 4/9/2018
BRLS-5932(039) 10 TUO
Bridge replacement -
Rawhide Road over Woods
Creek in James Town, Br. #
32C-044
De minimis 10/3/2018
BRLS-5938(199) 10 STA
Replace 2-lane bridge with a
standard 2-lane bridge
(seismic retrofit)
De minimis 1/10/2018
BRLO-5958(078) 11 IMP
Bridge Replacement-Imperial
County - Verde School
Rd/East Highline Canal Br #
58C-0115
De minimis 2/7/2018
County
Local Assistance Projects - Section 4(f)
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018
46
23 USC 326 Categorical Exclusions
Caltrans 12-month Report to FHWA
January 1, 2018 - December 31, 2018 (Quarters 43-46)Report date: January 23, 2019
STPL-5169(049) 11 IMP
Construct new 4-lane faciltiy-
Imperial Ave: from I-8 to
McCabe in 4-Phases
Wake Avenue: Imperial
Avenue to Cypress Drive
De minimis 4/26/2018
Federal Aid Project
NumberDistrict County Project Description Type
Date
Signed
NONE
Approvals from previous reporting periods (prior to January 1, 2018) -- Local Assistance Projects -
Section 4(f)
23 USC 326 12-month Report: January 1, 2018 - December 31, 2018