Caltrain Modernization CMAA September 18, 2014

description

Caltrain Modernization. CMAA September 18, 2014. Caltrain Today. Key Facts. Diesel commuter rail system SF to SJ area 77 mile corridor, 32 stations 92 trains / weekday Ridership : ~ 55,000+ weekday. Caltrain Ridership. Note: Bike Ridership 11 % increase (FY14). - PowerPoint PPT Presentation

Transcript of Caltrain Modernization

Page 1: Caltrain  Modernization

Caltrain Modernization

CMAA September 18, 2014

Page 2: Caltrain  Modernization

2

Caltrain Today

Page 3: Caltrain  Modernization

Key Facts• Diesel commuter rail system

• SF to SJ area

• 77 mile corridor, 32 stations

• 92 trains / weekday

• Ridership: ~ 55,000+ weekday

3

Page 4: Caltrain  Modernization

Caltrain Ridership

4Note: Bike Ridership 11 % increase (FY14)

Page 5: Caltrain  Modernization

2014 Top Ridership Trains

5

Note: February 2014 counts (lower ridership season)

Page 6: Caltrain  Modernization

6

Caltrain Modernization

Page 7: Caltrain  Modernization

Advanced

Signal System (2015)

7

Page 8: Caltrain  Modernization

Project Description• Communications Based Overlay Signal

System (CBOSS) Positive Train Control (PTC)

• Fiber Optic Network

• Project Requirements‒ Includes federal mandate (PTC)

‒ Improves Caltrain performance

• Project Partners ‒ FRA, UP, CHSRA, JPB

8

Page 9: Caltrain  Modernization

DescriptionCost

(in millions)Milestones

Project Planning and Procurement

$5 2010 - 2011

Phase 1 - Critical Design $25 2012 – 2013

Phase 2 - Final Design, Data Communications Subsystem & Fiber Backbone Installation

$51 2013 – 2014

Phase 3/4 - Installation, Testing, Commissioning

$1502014 – 2016

(Revenue service Oct. 2015)

Total $231

Project Total Cost and Milestones

9

Page 10: Caltrain  Modernization

Peninsula Corridor Electrification Project (2019)

10

Page 11: Caltrain  Modernization

PCEP Project Description*

8

Area Project Service

51+ miles

San Francisco to San Jose (Tamien Station)

Electrification: • Overhead Contact

System (OCS)

• Traction Power Facilities

Electric Multiple Units (EMUs)

Up to 79 mph

Service Increase• 6 trains / hour / direction

• More station stops / reduced travel time

• Restore Atherton & Broadway service

Mixed-fleet service (interim period)

Cont. tenant service

*Proposed project not yet approved, pending environmental clearance

Page 12: Caltrain  Modernization

Key Milestones*

12

Activity 2013 2014 2015 2016 2017 2018 2019

Stakeholder Outreach              

Establish Owner’s Team          

Environmental Clearance              

Procure/Select Contractor Team              

Design/Manufacture/Build              

*Schedule subject to change

Page 13: Caltrain  Modernization

Funding Plan

13

Funding Source Electrification EMUsJPB Members 31 94

JPB (prior funding) 11

State Prop 1B 5 Prop 1A HSR 600

FTA (prior funding) 16

FTA (future) 122 315

Bridge Tolls 11

BAAQMD Carl Moyer 20

Total Funding $785M $440M

Note: 2009 cost estimate

Page 14: Caltrain  Modernization

Key Regional Benefits

14

Page 15: Caltrain  Modernization

High-Speed Rail

Partnership

15

Page 16: Caltrain  Modernization

Blended System Vision

16

*Based on LTK computer model simulation (March 2012)

2-track System (Primarily)Up to 110 mph

Partially Grade Separated6 Caltrains / peak hour per direction

Up to 4 HSR trains / peak hour per direction*

Community-driven Approach

Page 17: Caltrain  Modernization

Incremental Investments

17

CalMod ProgramCBOSS PTC 2015

Corridor Electrification 2019

Additional HSR Improvements

HSR StationsPassing Tracks

Maintenance FacilitySystem Upgrades (110mph)

Additional Caltrain Improvements

Longer Trains/ PlatformsLevel Boarding

State of Good Repair & Reliability/Capacity Improvements

Note: Orange has no funding plan; Green has funding plan

Downtown Extension (led by TJPA)

Page 18: Caltrain  Modernization

Q/A