California 20 2009 - CEG
-
Upload
construction-equipment-guide -
Category
Documents
-
view
232 -
download
0
description
Transcript of California 20 2009 - CEG
By Erik PisorCEG CORRESPONDENT
For more than a decade, a portion of Route 101 inMendocino County, Calif., has experienced regular winterroad delays due to landslides and slipouts.
These often five-hour plus delays have affected travelersand the transportation of goods and services into the area.
The landslides also have caused multiple-day road clo-sures, which from 1997 to 2006 resulted in more than $33million in maintenance and restoration expenses to Caltrans.
This winter however, delays and closures along the por-tion of Route 101 known as Confusion Hill will be a thingof the past, as the $65 million Confusion Hill RoadwayRealignment Project is nearly complete.
The project involved relocating approximately 1.5 mi.(2.4 km) of Route 101 by constructing a 255-ft. (77 m) tall,three span, cast-in-place segmental bridge; and a 142-ft. (43m) tall, three span, cast-in-place concrete box girder bridgeabove the Eel River, according to Evan Paine, project man-ager for Sacramento-based MCM construction.
Construction of a short section of new highway, whichinvolved an approximately 400,000 cu. yds. (305,800 cu m)rock cut and the installation of two steel soldier pile retain-ing walls, also was part of the Federal HighwayAdministration-funded project that began in June 2006.
However it was the bridgework that set the project apart.“Each bridge has a unique design due to time and cost
restraints placed on project development,” said Phil Frisbie,public information officer for Caltrans District 1.
The south, segmental bridge has 30-degree slant legs thatallowed the foundations to stay above the 100-year floodplain and reduced environmental permit requirements.
“The segmental bridge is only the sixth of its kind built in
California,” Paine said.Sloping piers, are a feature of the north, box girder bridge,
which because of steep and rugged site access required an80-ft. (24 m) high, 300-ft. (91 m) long work trestle to con-struct.
The main cranes utilized by MCM for the bridgeworkincluded a Maintowoc 4000, a Maintowoc 3900, a Link-Belt
LS-518 and a Link-Belt LS-338, according to Paine, whoadded a pair of self-launching travelers were used duringconstruction of the south, segmental bridge.
All the crane equipment was owned by MCM, who wasselected based on being the lowest qualified bidder.
The three-span, south segmental bridge has a main span
Confusion Hill Realignment Project Nearly Complete
Gov. Arnold Schwarzenegger announcedthat more than $2 billion in Recovery Actfunding has now been federally obligated to620 highway transportation infrastructureprojects statewide. Focused on pumpingRecovery funding into the California econo-my quickly, effectively and responsibly,California has obligated more Recovery Actfunding federally designated for highwaytransportation infrastructure than any other
state in the nation.“We are working around the clock with
the federal government to ensure PresidentObama’s Recovery funding is pumped intoCalifornia quickly, effectively and responsi-bly,” said Schwarzenegger. “California is thefirst state in the nation to obligate $2 billionof this funding, which will improve ourstate’s transportation infrastructure for gen-erations to come while stimulating our econ-
omy, creating jobs and helping driveCalifornia down the road to economic recov-ery.”
Under the Recovery Act, states weregiven 120 days to obligate half of their fed-eral stimulus transportation funding to proj-ects — which California completed morethan two months ahead of federal deadline.
California also was the first state in thenation to obligate $1 billion in stimulus
funding to improve its highways, localstreets, public transit and airports.
“From day one, our focus has been andcontinues to be ensuring that California getsthe maximum benefit from federal stimulusfunding,” said Caltrans Director RandyIwasaki. “With the help of billions in stimu-lus dollars, we’re putting people to work andbuilding better roads, bridges, and transit forCalifornians.”
California Leads Nation With More Than $2B in Federal Funds
CALIFORNIA STATE SUPPLEMENT
Your California Connection – Frank Strazzulla – 1-877-7CEGLTD – [email protected]
September 262009
Vol. IV • No. 20“The Nation’s Best Read Construction Newspaper… Founded in 1957.”
97
139395
395
29989
4444
299
101
101
1011
20
9970
50
49
36
89
89
299
70
65
1
1
152
33
101
101
198
198
33
180
41
190
395
395
6
120
140
120
99
99
49
120
395
101
1
46 178
65
58
127
395
1 101
14
86
95
14
5
5
5
5
5
515
15
15
40
10
505
280
880
80
5
5
5
5
5
515
15
15
40
10
505
8
280
880
80
80
680
580
1010
Crescent City
EurekaRio Dell
Burney
ChicoOroville
Leggett
FortFortBraggBragg
Point ArenaTahoe City
Auburn
SacramentoSanta Rosa
San Francisco OaklandOaklandBerkleyBerkley
San JoseSan Jose
Santa Cruz
Modesto
Sonora
San Diego
Oceanside
Palm SpringsPalm Springs
Riverside
San Bernadino
Long BeachSanta AnaSanta Ana
Los AngelesLos AngelesGlendale
Santa Monica
BarstowBarstow
Santa Barbara Ventura
Santa Maria
San Luis Obispo
BakersfieldBakersfield Baker
Death Valley JunctionDeath Valley Junction
Montery
MaderaMaderaFresno
King City
LuciaLucia
SouthLakeTahoe
Pictured is the completed South Bridge.
see CONFUSION page 6
Page 2 • September 26, 2009 • www.constructionequipmentguide.com • California State Supplement • Construction Equipment Guide
www. johnson-machinery.com
WITH INDUSTRY-LEADING PERFORMANCE AND PRODUCTIVITY, NO OTHER PRODUCT LINE CAN COMPARE TO THE FULL LINE OF CAT COMPACT EQUIPMENT AND WORK TOOL ATTACHMENTS FROM JOHNSON MACHINERY. AND NOW WITH SPECIAL FINANCING THERE’S NO BETTER TIME TO GET A CATMACHINE ON YOUR JOBSITE.
Stop by or call us today for more details on these offers or to demo a Cat Skid Steer Loader, Compact Track
Loader, or Compact Excavator today. See how to propel your business into higher productivity and add to
your bottom line with Cat Equipment and say so long to John and Bob.p p yp
©2009 Caterpillar All rights reserved. CAT, CATERPILLAR, their respective logos, “Caterpillar Yellow,” the “Power Edge” trade dress as well as corporate and product identity used
herein, are trademarks of Caterpillar and may not be used without permission. *Price includes tax and a bucket. Terms and conditions may apply. Offers expire 10/31/09. OAC.
226 CAT® SKID STEER LOADER
$823/month*0% for 42 months with a 36 month warranty.
303 CAT COMPACT EXCAVATOR
$1,087/month*0% for 42 months with a 36 month warranty.
289 CAT COMPACT TRACK LOADER
$1,666/month*0% for 42 months with a 36 month warranty.
FONTANAINDIO
RIVERSIDETEMECULA
VICTORVILLE951-686-4560
Construction Equipment Guide • California State Supplement • www.constructionequipmentguide.com • September 26, 2009 • Page 3
Spartakoss Valverdini is a retired Marinecolonel and a former Apache helicopterpilot.
He likes speed…the faster, the better.Speed is not what he expects when work-
ing as a finish blade operator in the con-struction industry. But speed is what heexperienced on a John Deere 750J dozerduring a recent hands-on demonstration ofthe fastest machine control technology onthe market today.
Topcon Positioning Systems’ (TPS) 3D-MC2 technology, according to publishedinformation and accounts from end-users,allows a dozer operator to go “twice as fastwith twice the accuracy” of a regular 3D-GPS system, and four to five times as fast asa dozer without any machine control system.
Valverdini, a finish blade operator versedin the use of laser grade control, GPS andATS systems, and a member of theOperating Engineers Union, said, “3D-MC2
allows you to go fast all right. But that’s justpart of the job. More importantly, it givesyou the smooth, accurate, finish grade of agrader…with a dozer. I’ve never seen any-thing like it.”
After minimal instructions and a couple ofpasses on a football field-size test site nearthe company’s headquarters in Livermore,Calif., John Dice, TPS senior training man-
ager, put Valverdini behind the joystick con-trols of the dozer.
Valverdina made a slow pass in manual,then a return pass at about the same speed,still in manual control. Grading at about 1.8to 2 mph., his passes were “acceptable,” helater said.
Engaging the 3D-MC2 system, his thirdand fourth passes were at about 4 mph. Thecuts were definitely smoother…finish gradequality.
The fifth pass had Valverdini pushing theDeere dozer wide open, between 6 and 7mph. The cut, trimmed on both sides by thedozer tracks was ultra-smooth. A leveldemonstration showed it was “on bubble.”
“That was something,” Valverdini said. “Ihave read about 3D-MC2 technology, andlistened to what John Dice said. But untilyou actually run it, it does not compute whathe can actually do.”
He admitted that is was “hard to jump thedozer up as fast as I finally did. Operators arenot used to doing that. We are used to con-trolling the dozer, not the dozer controllingthe cut regardless of the speed.”
Dice complimented Valverdini’s perform-ance, saying, “He’s a good operator at anyspeed. But just because he’s a good operator,he didn’t close his mind to the possibilities of
what 3D-MC2 can do. If you accept thepremise this machine can make you moreproductive, thus saving time and money, it’sa natural progression from running with nomachine control system, or even a GPS-onlysystem, to running with 3D-MC2.”
With normal GPS machine control having10 and 20 grade corrections per second, it’s“hard to believe you can jump from that to
100 corrections per second,” Valverdini said.“But all you have to do is make a couple ofpasses, and look at the finish grade you get atthat speed and it makes you a believer in ahurry.”
To think, he said, “that you can use onedozer to do the work of two, and do finishgrade work equal to that of a grader…isunbelievable.”
Spartakoss Valverdini is a retired Marine colonel and a former Apache helicopterpilot.
Spartakoss Valverdini (2nd from L) discusses specs with the other attendees infront of a John Deere 750J dozer.
After minimal instructions and a couple of passes on a football field-size test sitenear the company’s headquarters in Livermore, Calif., John Dice (R), TPS seniortraining manager, put Spartakoss Valverdini behind the joystick controls of thedozer.
Construction Starts on Key SoCal Freeway in San BernardinoSAN BERNARDINO, Calif. (AP) Construction has
begun on a freeway widening project through downtownSan Bernardino that’s received $128 million in federal stim-ulus funding and promises to create thousands of jobs.
Federal Highway Administrator Victor Mendez, state and
local officials celebrated the groundbreaking of the latestphase of the Interstate 215 project Sept. 14.
Officials say it’s the largest stimulus-funded freeway proj-ect to begin construction. They say the money will support
about 2,000 jobs per year for the next four years in a regionthat has some of the nation’s worst unemployment and fore-closure rate.
The full project is expected to finish in 2013 for about$800 million.
Former Helicopter Pilot Gets Up to Speed With MC2 Dozer
Page 4 • September 26, 2009 • www.constructionequipmentguide.com • California State Supplement • Construction Equipment Guide
RDO Equipment Co. AcquiresB&B Heavy Equipment in Calif.
RDO Equipment Co. has acquired B&BHeavy Equipment Sales & Rentals Inc., oneof the largest heavy equipment rental suppli-ers servicing southern California andbeyond.
“We are thrilled to have B&B EquipmentRental join our company. They are an estab-lished business with excellent employees, agreat reputation in the region, and superbcustomer service,” said Christi Offutt, RDOEquipment Co. chief executive officer.
“The combination of B&B EquipmentRental and RDO Equipment Co. will be ableto provide customers an expanded rentalequipment offering through more locationsin southern California and Arizona.”
Bob Wheelington, B&B EquipmentRental’s former president and newlyappointed vice president and general manag-er, will provide the day-to-day leadership forthe rental operation.
“Becoming part of the RDO EquipmentCo. family is an exciting transition for us,”he said. “We will be better able to providecustomers with the equipment, parts, andservice solutions they need.”
About RDO Equipment Co.Founded in 1968, RDO Equipment Co. is
a family-owned and operated company ded-icated to provide and support John Deere(agriculture, construction, lawn and garden)and Vermeer customers. The corporation’sheadquarters are in Fargo, N.D. The compa-ny has 55 locations in nine U.S. states, andemploys more than 1,400 people.
For more information about B&BEquipment Rental, visitwww.BBRental.com.
For more information about RDOEquipment Co., visitwww.rdoequipment.com.
Caltrans Reopens Bay AreaBridge After Repairs CompletedBy Sudhin ThanawalaASSOCIATED PRESS WRITER
SAN FRANCISCO (AP) The SanFrancisco-Oakland Bay Bridge reopenedSept. 8 just in time for the start of the workweek after transit officials hastily announcedthat crews were able to make a crucial repaira day ahead of schedule.
“Traffic seems to be flowing smoothly,”California Department of Transportationspokesman Bart Ney said after the bridgereopened just before 7 a.m. “I think it’s stilla surprise.”
Officials had pushed the reopening to 5a.m. Sept. 9 after crews discovered a crackSept. 5 while conducting seismic upgradeson the 73-year-old bridge.
The bridge, which carries about 260,000vehicles a day between San Francisco andheavily populated cities to its east, wasclosed over the Labor Day weekend so afootball-field-sized, 3,300-ton (2,993 t) sec-tion of the eastern span could be cut out andreplaced with a new double-deck section.
The new section connects the bridge witha short detour that will be used until a neweast span is completed by 2013.
Crews used the opportunity to inspect thebridge and found a 2-in. (5 cm) -thick steel
link cracked halfway through.Ney said a contractor worked throughout
the night to make a replacement part andcomplete the work. An inspection followingthe repair “went without a hitch,” he said.
“The bridge has been inspected and it’ssafer than it was when we closed it,” saidCaltrans director Randy Iwasaki.
The bridge shut down the night of Sept. 3,and other bridges and public transportationsystems were able to accommodate extrariders Sept. 4, the first time that the bridgewas closed on a working day since a majorearthquake in 1989.
Meanwhile, the Sept. 8 morning rush hourwas still heavy on several other Bay Arearoadways including the Golden Gate Bridge,said Sgt. Trent Cross, spokesman for theCalifornia Highway Patrol’s Golden Gatedivision.
“I think most motorists weren’t aware ordidn’t know that the bridge was open,” Crosssaid.
Public transit also was busier than usualdespite the early reopening.
Bay Area Rapid Transit spokesman JimAllison said the commuter rail line could stillset a record. Officials expected some 7,700more passengers than the previous week. Itaverages about 340,000 commuters a day.
Profits get hammered two ways. First, when your breaker fallsapart, you’re not working. Second, some parts are so expensivethat it’s better to cut into your bottom line and buy a newhammer to get a fresh warranty. That’s theway it is with most hammersand their warranties.
But, Huskie is really different. If you own a HuskieHydraulic Hammer, you arecovered front cap to back capby Huskie’s industry-leadingLIFETIME Limited Warranty*.
• LIFETIME Coverage for FrontCap, Back Cap and Main Body
• THREE YEAR Protection for AllComponents except
• TWO YEAR Warranty for All Seals• UNLIMITED HOURS of Use
Forever is a long time. But, if you own a Huskie Hammer, that’s how long youcan expect to run it 24/7 and still becovered by the revolutionary HuskieLifetime Warranty.
Ask your dealer for a demo.
*Limited warranty. Normal wear items are not covered. See warranty statement for detailsand exceptions. Effective on all Huskie Hydraulic Hammers purchased after July 1, 2005.
The Huskie logo and Huskie Hydraulic Hammer are registered trademarks of IPC Industries, Inc. © 2008 IPC-Huskie Hydraulic Hammer
*Limited warranty. Normal wear items are not covered. See warranty statement for detailsand exceptions. Effective on all Huskie Hydraulic Hammers purchased after July 1, 2005.
The Huskie logo and Huskie Hydraulic Hammer are registered trademarks of IPC Industries, Inc. © 2008 IPC-Huskie Hydraulic Hammer
H U S K I E H Y D R A U L I C H A M M E R
Protected By Lifetime Warranty*
6188 Paramount Blvd.Long Beach, CA 90805Phone: 562-272-7400
Fax: 562-272-7444
12435 Foothill Blvd.Sylmar, CA 91342Phone: 818-890-3353 Fax: 818-890-5013
1930 E. Lockwood St.Oxnard, CA 93036Phone: 805-485-2106 Fax: 805-485-7963
888 East Ave. L-4Lancaster, CA 93535Phone: 661-948-9993Fax: 661-723-5613
3216 WestminsterSanta Ana, CA 92703Phone: 714-265-5500 Fax: 714-265-5505
1950 Roemer PlaceSanta Maria, CA 93454Phone: 805-922-8329 Fax: 805-922-4582
4252 Saco RoadBakersfield, CA 93308Phone: 661-399-3600 Fax: 661-399-8782
When We Say
“Forever”...We Mean Forever!
Construction Equipment Guide • California State Supplement • www.constructionequipmentguide.com • September 26, 2009 • Page 5
For more information about the full range of JCB Construction Equipment and to find the dealer nearest you, please visit www.jcb.com
From humble beginnings in 1945, JCB has grown to become one of the largest equipment manufacturers in the world and still remainsfamily owned. Not only do we produce the world’s best selling backhoe loaders and telescopic handlers, we also offer complete equip-ment solutions from skid steer loaders to mass excavators and everything in between. Discover how JCB and your local JCB dealer arecommitted to Helping You Get the Job Done!®
CONTACT YOUR LOCAL JCB DEALER TODAY TO FIND OUT ABOUT CURRENT OFFERS.
Kern Machinery310 High St.
Delano, CA 93215661-725-3841
Fax: 661-725-0377
520 S. Mt. Vernon Ave.Bakersfield, CA 93307
661-833-9900
24526 Lerdo HighwayButtonwillow, CA 93206
661-746-6363www.kernmachinery.com
Muniquip3000 W. Capitol Ave.
West Sacramento, CA 95691866-417-4302
Fax: 916-375-2048www.muniquip.com
N & S Tractor1215 W. Glenwood Ave.
Turlock, CA 95380209-634-1777
Fax: 209-634-3128www.nstractor.com
Page 6 • September 26, 2009 • www.constructionequipmentguide.com • California State Supplement • Construction Equipment Guide
Confusion Hill Realignment Target to Finish by Octoberof 571 ft. (174 m) and end spans of 348 and436 ft. (106 and 132 m). The structure depthvaries from 31.5 ft. (9.6 m) at the piers to11.5 ft. (3.5 m) at the midspans and abut-ments, Paine said.
The bridge is comprised of more than15,000 cu. yds. (11,470 cu m) of concrete,some of which is high, early strength con-crete, and nearly 5 million lbs. (2.2 millionkg) of reinforcement.
The foundations consist of 11 piles, each5 ft. (1.5 m) in diameter and approximately100 ft. (30.5 m) long, at each of the twopiers. At each of the abutments are 16-in. (40cm) diameter piles.
During bridge pours a concrete deliverysystem pumped concrete approximately 255vertical ft. (77 m) and another 285 horizon-tal ft. (86 m) at the extreme lengths, Painesaid, adding a mobile concrete batchplantwas located onsite.
The pile caps at the bridge’s pier footingsare nearly 50 by 36 ft. (15 by 10.9 m) and10.5 ft. (3.2 m) deep.
The architectural piers are nearly 25 by 19ft. (7.6 by 5.8 m) at the base, but vary as theystair step in at two locations.
The majority of the bridge’s deck is on a 5percent incline with a 2 percent cross slope,according to Paine, who said at the peak ofconstruction MCM had more than 60employees working onsite.
As of July 7 of this year, southbound traf-fic began using the new segmental bridgeand new alignment, according to Frisbie.
The northbound, three-span, box girderbridge has a main span of 229.3 ft. (69.8 m),end spans of 175.8 ft. (53.5 m) and was openfor commuter use in late August.
More than 4,400 cu. yds. (3,360 m) ofconcrete and more than 1.5 million lbs.(700,000 kg) of reinforcement comprise thebridge.
The piers of the bridge were sloped 30degrees from vertical and varied in dimen-sions from about 17 by 7 ft. (5 by 2.1 m), atthe base, to about 17 by 14 ft. (5 by 4.2 m) atthe top of the pier, Paine said.
Because of the slope and the bridge cur-
vature, the pier was trapezoidal rather thanrectangular.
Aside from bridge construction, a thru cutthat removed of more than 400,000 cu. ydsof rock and soil was required in order to con-struct a new portion of highway.
Blasting also was required to make wayfor the new highway realignment.
During the thru cut and blasting, Cat 735trucks hauled rock and soil across the com-pleted north bridge.
The Cat 735s were either rented or ownedby subcontractor Ladd and Associates, whowas responsible for structureexcavation/backfill and roadway rock exca-vation, Paine said.
Construction of the new highway alsoincluded the installation of two, steel soldierpile retaining walls with tieback anchors.
The first wall is nearly 375 ft. (114 m)long and varies in lagging height, whichreached as high as 20 ft. (6 m).
The wall includes more than 300 ft. (91m) of wide flange soldier pile and 43tiebacks, and received an architectural sur-
face resembling rock formations.The second wall is 504 ft. (153 m) long
and has a lagging height of up to 40 ft. (12m).
This wall contains 62 wide flange soldierpiles, with a combined length of 3,100 ft.(944 m), and utilized concrete whalers toanchor each of the 77 tiebacks.
At the point where the existing Route 101meets new the alignment, MCM andCaltrans used nearly 3,748 tons (3,400 t) ofshredded tires to raise the old highway to theheight of the newly constructed highway.
Known as tire derived aggregate, the recy-cled material is about half the weight percubic foot of rocky soil and has a lower costthan other lightweight alternatives, such asexpanded polystyrene blocks.
The lower weight allowed the largearched culvert below the highway to handlethe added road height without reinforce-ment.
Reinforcing the culvert would haveincreased the project cost, and increased thedevelopment time, which would havedelayed the start of construction, according
to a Caltrans release.Because the project site was in a remote
area and involved the construction of 1.5 mi.(2.4 km) of new bridges and roadways, theproject had little impact on the surroundingcommunity.
All aspects of the realignment project willbe complete by the middle of October, Painesaid.
Besides Ladd & Associates, other subcon-tractors on the project included: CMCFontana Steel, furnish/place reinforcement;Schwager Davis Inc, prestressing; MercerFraser, furnish concrete, base, and ACpaving; Drill Tec, soldier pile walls; PacificCoast Drillers, bridge CIDH piles; FinleyEngineering Group, segmental constructionengineering; Roadway Electrical Works,underground and bridge electrical and seis-mic; Apex Fence Company, metal beamguard rail installation and removal; andTraffic Solutions, striping and rumble strips.
(This story also can be found onConstruction Equipment Guide’s Web site atwww.constructionequipmentguide.com.)CEG
Hawthorne CAT, Laser West Positioning Form New AllianceHawthorne CAT, an authorized Caterpillar dealer, and
Laser West Positioning Inc., a Global Positioning Systems(GPS) and equipment company, recently formed a newalliance to offer GPS technology and service to contractorsin San Diego and Hawaii.
Based in Vista, Calif., Laser West Positioning Inc. sellsGPS systems and laser machine control guidance equipmentto contractors. The company also is the local distributor ofTrimble products. Trimble is a provider of advanced posi-tioning solutions that maximize productivity and enhance
profitability. Though best known for GPS technology,Trimble integrates a wide range of positioning technologiesincluding GPS, laser, optical and inertial technologies withapplication software, wireless communications, and servicesto provide complete commercial solutions. Its integratedsolutions allow customers to collect, manage and analyzecomplex information faster and easier, making them moreproductive, efficient and profitable.
“This alliance will accelerate the introduction of solutionsthat will enable contractors to better manage the work site
and all the machines in their fleet,” said Tom Butler, ownerand president of Laser West Positioning.
“The teaming of our two organizations will furtherenhance and support our customer’s experience, productivi-ty and profitability. Tom is extremely well respected in ourindustry and this alliance will produce tremendous customersatisfaction in support of our machine control and guidanceinitiative,” said Steve Sager, Hawthorne’s vice president ofcorporate sales and rental.
For more information, visit www.hawthornecat.com.
Pictured is the completed North Bridge.
CONFUSION from page 1
Construction Equipment Guide • California State Supplement • www.constructionequipmentguide.com • September 26, 2009 • Page 7
Quality Used Equipment...
Ready to Ship. Sold Worldwide.
Email us for a complete inventory list of used equipment.
Quality Used Power...Ready to Ship. Sold Worldwide.
Email us for a complete inventory list of generator sets, individual engines and marine engines.
Used Equipment Sales Manager
Phone: 858-974-6804
Email: [email protected]
Jim FellisUsed Equipment Project Manager
Phone: 858-974-6835
Email: [email protected]
www.hawthornecat.com© 2009 Caterpillar All Rights Reserved. CAT, CATERPILLAR, their respective logos, “Caterpillar Yellow” and the “POWER EDGE” trade dress,
as well as corporate and product identity used herein, are trademarks of Caterpillar and may not be used without permission.
1997, CAB w/ AC, Push Pull, Good Condition,Ready to Work, 50% plus Tires
EACH
2006, 475 hrs., Tier 3, CAB w/ AC, SU Blade, Ripper
S/N 0KPZ01351
Ingersoll Rand
2005, 2554 Engine hrs, 669 Drifter Hrs, Dust Collector, Water Injection, Cummins 6CTAA 8.3 Liter Engine, 260 hp, 2 level drilling controls, Cab w/ AC.
S/N 009278BA
Ass’t Used Equipment Mgr.
Tel: 858-674-7131
Email:
Jim GilchristUsed Equipment Sales Rep.
Tel: 858-674-7046
Email:
SN: 5YR00239
5YR00240
5YR00248
5YR00251
Page 8 • September 26, 2009 • www.constructionequipmentguide.com • California State Supplement • Construction Equipment Guide
The California Department of Transportation received bidsfor transportation-related improvement projects.
Following is a list of some of the projects let.
Counties: Orange, RiversideContract Number: 12-0G0404.Location: In Anaheim, Yorba Linda and near Corona.Project: Widen freeway and bridges.Number of Working Days: 665.Contractors and Bid Amounts:
• Brutoco Engineering and Construction Inc., Fontana,Calif. — $40,855,853.
• Sema Construction Inc., Lake Forest, Calif. —$42,656,351.
• Flatiron West Inc., San Marcos, Calif. — $42,672,469.• C.C. Myers Inc., Rancho Cordova, Calif. —
$44,651,172.• Griffith Co., Santa Ana, Calif. — $45,552,886.• Skanska USA Civil West California District Inc.,
Riverside, Calif. — $46,650,867.• Riverside Construction Co. Inc., Riverside, Calif. —
$47,781,072.• Chumo Construction Inc., Baldwin Park, Calif. —
$49,256,254.• Diablo Contractors Inc., San Ramon, Calif. —
$51,994,167.
County: ShastaContract Number: 02-378904.Location: Near Lakehead from 0.2 mi. north of AntlerSummit overcrossing to 0.3 mi. north of Antler underpass.Project: Bridge replacement.Number of Working Days: 1300.Contractors and Bid Amounts:
• Tutor Saliba Corp., Sylmar, Calif. — $124,677,700.• Flatiron Manson A Joint Venture, Benicia, Calif. —
$142,510,910.• Balfour Beatty Infrastructure Inc. Golden State Bridge
Inc., Fairfield, Calif. — $146,163,925.• M.C.M. Construction Inc., North Highlands, Calif. —
$149,771,124.• Kiewit Pacific Co., Concord, Calif. — $157,069,098.
County: StanislausContract Number: 10-0G7704.Location: In Newman from Inyo Avenue to 0.1 mi. south ofJensen Road and in Patterson from Sperry Avenue to WardAvenue.Project: Rehabilitate roadway.Number of Working Days: 45.Contractors and Bid Amounts:
• Knife River Construction, Stockton, Calif. —$1,303,729.
• Granite Construction Co., Watsonville, Calif. —$1,395,956.
• George Reed Inc., Sonora, Calif. — $1,513,168.• Teichert Construction, Turlock, Calif. — $1,536,647.
Counties: Kings, TulareContract Number: 06-3568U4.Location: Approximately 0.5 mi. east of Hanford.Project: Convert two lane highway.Number of Working Days: 500.Contractors and Bid Amounts:
• Flatiron West Inc., Benicia, Calif. — $45,178,321.• Granite Construction Co., Watsonville, Calif. —
$45,849,382.• De Silva Gates Construction, Dublin, Calif. —
$46,734,866.• R and L Brosamer Inc., Walnut Creek, Calif. —
$48,832,380.• Coffman Specialties Inc., San Diego, Calif. —
$48,865,000.• Teichert Construction, Turlock, Calif. — $49,029,348.• Security Paving Co. Inc., Sun Valley, Calif. —
$49,596,165.• Diablo Contractors Inc., San Ramon, Calif. —
$50,812,453.• Top Grade Construction Inc., Livermore, Calif. —
$51,498,226.• Agee Construction Corp., Clovis, Calif. —
$51,975,576.• Lees Paving Pave Tech JV, Visalia, Calif. —
$54,568,289.• Emmetts Excavation Inc., Clovis, Calif. —
$55,168,964.• Berry Wood JV, Selma, Calif. — $55,612,745.
County: KernContract Number: 06-442534.Location: Near Lost Hills on Route 46 and Route 33.Project: Widen Route 46 and realign Route 33.Number of Working Days: 320.Contractors and Bid Amounts:
• Griffith Co., Bakersfield, Calif. — $22,999,250.• Security Paving Co. Inc., Sun Valley, Calif. —
$23,114,827.• Papich Construction Co. Inc., Pismo Beach, Calif. —
$24,280,820.• W. Jaxon Baker Inc., Redding, Calif. — $24,396,952.• Granite Construction Co., Watsonville, Calif. —
$25,105,463.• Sukut Construction Inc., Riverside, Calif. —
$25,320,405.• Teichert Construction, Fowler, Calif. — $25,547,195.• Sim J. Harris Inc., San Diego, Calif. — $25,705,000.• Sierra Nevada Construction Inc., Sparks, Nev. —
$25,947,007.• John Madonna Construction Co. Inc., San Luis
Obispo, Calif. — $26,566,133.
County: SonomaContract Number: 04-4A8704.Location: Near Kellogg at Maacama Creek Bridge from 0.2mi. west to 0.3 mi. east of Redwood Creek Bridge.Project: Replace bridges.Number of Working Days: 260.Contractors and Bid Amounts:
• Viking Construction Co. Inc., Rancho Cordova, Calif.— $5,033,181.
• Gordon N. Ball Inc., Alamo, Calif. — $5,112,449.• Golden State Bridge Inc., Martinez, Calif. —
$5,306,393.• Granite Construction Co., Watsonville, Calif. —
$5,396,537.• M.C.M. Construction Inc., North Highlands, Calif. —
$5,666,666.• Shasta Constructors Inc. and Argonaut Constructors
JV, Redding, Calif. — $5,767,612.• Disney Construction Inc., Pacifica, Calif. —
$5,990,739.
Placer • Siskiyou • Shasta Butte• Marin • Solano • Sonoma • Calaveras • Tuolumne • Kern • Glenn • Nevada • Orange • San Diego • Riverside• Los Angeles • San Bernardino • Santa Cruz • Trinity • Stanislaus • Inyo • Imperial • Fresno • Mendocino • Santa Barbara • El Dorado • Yolo• Contra Costa • Merced • Marin • Placer • Siskiyou • Shasta Butte• Marin • Solano • Sonoma • Calaveras • Tuolumne • Kern • Glenn • Nevada• Orange • San Diego • Riverside • Los Angeles • San Bernardino • Santa Cruz • Trinity • Stanislaus • Inyo • Imperial • Fresno • Mendocino •Santa Barbara • El Dorado • Yolo • Contra Costa • Merced • Marin Placer • Siskiyou • Shasta Butte• Marin • Solano • Sonoma • Calaveras •
California...
‘Golden State’ Highway Lettings
Construction Equipment Guide • California State Supplement • www.constructionequipmentguide.com • September 26, 2009 • Page 9
™
>
Serious productivity demands serious thinking. Many of the numerous improvements in the K-Series came from the brightestminds in the industry - loader owners and users such as yourself. Armed with fresh insights from this Customer Advocate Group,we enlarged the cab, redesigned the cooling, enhanced the hydraulics, refined the ergonomics, and offered even more options.All with the goal of increasing productivity and uptime, while lowering daily operating costs. Owners, operators, and maintenancepersonnel will all benefit from big ideas found in the 844K loader.
Stop in today to your local California John Deere Dealer to see why this isn't just another loader.
Think. Big.Think. Big.Think. Big.
N o t h i n g r u n s l i k e a D e e r e .
www.coastlineequipment.com
6188 Paramount Blvd.Long Beach, CA 90805
562-272-7400 • Fax: 562-272-7444
12435 Foothill Blvd.Sylmar, CA 91342
818-890-3353 • Fax: 818-890-5013
1930 E. Lockwood St.Oxnard, CA 93036
805-485-2106 • Fax: 805-485-7963
888 East Ave. L-4Lancaster, CA 93535
661-948-9993 • Fax: 661-723-5613
3216 WestminsterSanta Ana, CA 92703
714-265-5500 • Fax: 714-265-5505
1950 Roemer PlaceSanta Maria, CA 93454
805-922-8329 • Fax: 805-922-4582
4252 Saco RoadBakersfield, CA 93308
661-399-3600 • Fax: 661-399-8782
RDO EQUIPMENTwww.rdoequipment.com
83-300 Avenue 45Indio, CA 92201760-342-8900
13625 Danielson StreetPoway, CA 92064
800-905-1150
3275 Hwy 86Imperial, CA 92251
800-464-4331
20 Iowa AveRiverside, CA 92502
800-494-4863
www.papemachinery.com
Newark800-231-2060 • 510-790-3600
Fax: 510-790-9120
Sacramento800-227-3399 • 916-922-7181
Fax: 916-922-4532
French Camp800-619-6319 • 209-983-8122
Fax: 209-983-1105
Fowler559-834-4774
Fax: 559-834-4754
Rohnert Park800-325-9401 • 707-584-9161
Fax: 707-584-4786
Gilroy800-848-4150 • 408-848-4150
Fax: 408-848-5163
Redding530-241-4555
Fax: 530-241-0619
COASTLINE EQUIPMENT PAPE MACHINERY
Page 10 • September 26, 2009 • www.constructionequipmentguide.com • California State Supplement • Construction Equipment Guide
Calif. Approves HUSS MKRetrofit System for Volvo Iron
In late 2008, Volvo ConstructionEquipment entered into a strategic partner-ship with HUSS LLC to provide retrofit sys-tems for Volvo construction equipment thatwill significantly reduce exhaust emissions.The HUSS MK system now has finalapproval from California for Volvo Tier IIIIEGR-equipped machines in that state.
The HUSS MK system,approved for use on Volvoengines utilizing V-ACTtechnology with internalexhaust gas recirculation(IEGR), meets California’sCARB Level 3+ require-ments. Volvo equipmentowners can utilize the sys-tem to help comply with the“In-Use Off-Road DieselVehicle Regulation,” or toprovide the best availablecontrol technology (BACT)for the newest machines inowners’ fleets. Previously,engines using any type ofEGR had been excludedfrom applying exhaust retro-fit technology in California.This has now changed withthe recent system verifica-tion by the state.
The HUSS retrofit systemfor Volvo equipment is capa-ble of collecting up to 99 percent of dieselparticulate matter (PM) emissions, substan-tially exceeding the California CARBrequirements, according to the manufacturer.
How the Retrofit System WorksThe retrofit system is equipped with a
HUSS control unit that constantly monitorsfilter function to precisely control diesel PMloading and regeneration. This is an activefilter regeneration system, accomplishedthrough an integrated fuel burner system.Regeneration typically takes place afterapproximately 8 to 10 operating hours and iscompleted during breaks or shift change in 5to 35 minutes with no external support need-ed. Engine exhaust backpressure is set toVolvo requirements.
In addition to the reduction of 99 percentPM, there is no increase of NO2 or other sec-ondary emissions. The HUSS technology isadaptable to low and high-horsepowerequipment (up to 700 hp) providing reliableinstallations for both rubber tired and trackedmachines.
With the active system, there is no need tobe concerned with exhaust temperature pro-files, changing duty cycles, ULSD fuel,stocking extra filters or incur undue down-
time swapping filters due to the clogging andcleaning cycle of misapplied passive sys-tems, according to the manufacturer.
HUSS LLC, Palm Springs, Calif., is aspecialist in exhaust aftertreatment for dieselengines with more than 20 years of experi-ence in the manufacturing and servicing ofdiesel particulate filtration systems. HUSS
was one of the first to have ARB verificationand to establish system sales, technical sup-port and components warehousing inCalifornia to serve the North American mar-ketplace. A recent moving to upgraded facil-ities will now serve the North Americanmarket even better.
Applications of the HUSS systemsinclude construction and mining equipment,industrial and refuse trucks, transit andschool buses, heavy-duty on-highway vehi-cles and stationary generator sets.
A Cleaner EnvironmentThe Volvo/HUSS emissions reduction
retrofit system may be installed on all Volvoequipment in customer fleets and in additionto improving the environment, customersusing the system may be able to realize thou-sands of dollars in savings by keepingmachines in their current fleets and avoidingthe costly process of total engine replace-ment. They also may be eligible for state andfederal grants and incentives by meetingever-increasing emissions requirements.Retrofit now, receive available funding andearn double credits in some areas.
For more information, call 828/650-2000or visit www.volvo.com.
The Volvo/HUSS emissionsreduction retrofit system maybe installed on all Volvoequipment in customer fleetsand in addition to improvingthe environment, customersusing the system may be ableto realize thousands of dol-lars in savings by keepingmachines in their currentfleets.
www.coastlineequipment.com
6188 Paramount Blvd.Long Beach, CA 90805
562-272-7400 • Fax: 562-272-7444
12435 Foothill Blvd.Sylmar, CA 91342
818-890-3353 • Fax: 818-890-5013
1930 E. Lockwood St.Oxnard, CA 93036
805-485-2106 • Fax: 805-485-7963
888 East Ave. L-4Lancaster, CA 93535
661-948-9993 • Fax: 661-723-5613
3216 WestminsterSanta Ana, CA 92703
714-265-5500 • Fax: 714-265-5505
1950 Roemer PlaceSanta Maria, CA 93454
805-922-8329 • Fax: 805-922-4582
4252 Saco RoadBakersfield, CA 93308
661-399-3600 • Fax: 661-399-8782
Construction Equipment Guide • California State Supplement • www.constructionequipmentguide.com • September 26, 2009 • Page 11
®
Introducing ConstructionEquipment Guide’s
Newest Western SalesManager, Frank
Strazzulla.Call for Advertising or Editorial Information.
Toll Free 877-7CEGLTD949-459-1767 • Fax: 949-203-2859
E-Mail: [email protected]
Approximately
9,000Qualified
Buyers
DON'T MISS
THE NEXT
CALIFORNIA
SUPPLEMENT!
Closing: October 15th
Publishing: October 24th
THE CALIFORNIASTATE EDITION
Page 12 • September 26, 2009 • www.constructionequipmentguide.com • California State Supplement • Construction Equipment Guide