CAISSON FOUNDATION. INTRODUCTION The term caisson has been derived from the French word...
-
Upload
agnes-miller -
Category
Documents
-
view
225 -
download
5
Transcript of CAISSON FOUNDATION. INTRODUCTION The term caisson has been derived from the French word...
INTRODUCTION
The term caisson has been derived from the French word ‘CAISSEE’, meaning BOX.
It can be round or rectangle in plan.
It is commonly used where foundation under water is done.
It can sunk from surface of either land or water to the desired depth.
OPEN CAISSON
Also called as well caisson.
They are open at both the ends.
These are boxes of timber, steel or R.C or masonry.
Small caisson consists of one opening or well, while larger one contain a series of wells.
PROCEDURE
The caisson is cast and flatted to the site and sunk.
When it reaches the required depth concrete is deposited through water to some depth.
After the concrete gets hardened, the water will be pumped out.
The caisson is finally filled completely with concrete.
BOX CAISSON
Also called as Floating caisson.
They are open at top and closed at bottom.
They can be made of steel, R.C or timber.
The caisson is built on land, then launched and brought to the site where they have to be sunk.
They are filled with concrete or stone masonry and sunk until it rests on the river bed, which has been prepared to receive it, or on a pile cluster to form a lower part of a bridge pier.
PROCEDURE
APPLICATIONS OF BOX CAISSON
Bearing stratum is available at shallow depth
Loads are not heavy
For wharfs and break waters
PNEUMATIC CAISSON
“Pneumatic" means "with air" “Caisson" means "a box“
The pneumatic caisson method works on the same principle as a cup pressed into some water upside down
EXECUTION OF THE PNEUMATIC CAISSON
1.Preparation of the ground for installation
We level surface of working site where the caisson
is to be installed and improve the surface conditions
so that appropriate supporting force can be supplied.
2.Construction of working chamber
We construct a working chamber at a bottom of
the caisson, in which earth is excavated and removed.
The chamber is pressurized to the same pressure as
the ground water pressure to make it watertight
EXECUTION OF THE PNEUMATIC CAISSON
3. Rigging
Cylindrical steel shafts are used for workers to
enter or exit the pressurized working chamber and to
remove excavated earth.
4. Repeated excavation to sink & construct
caisson
We excavate and construct the caisson every 4m
height, and repeatedly sink it by excavating the
ground and constructing it to the desired depth.
EXECUTION OF THE PNEUMATIC CAISSON
5. Testing the bearing capacity of soil
After the caisson has sunk to the specified depth,
we test and confirm that if sufficient bearing
capacity of soil has been obtained.
6. After concrete filling for working
chamber
After confirming the bearing capacity, we remove
equipments in the working chamber and fill
concrete, which means completion of works.