C.3 Foundation Redesign ~ tructural - Penn State College ... · PDF fileC.3.4.1.B O C.3.4.1.C...
Transcript of C.3 Foundation Redesign ~ tructural - Penn State College ... · PDF fileC.3.4.1.B O C.3.4.1.C...
C.3
Sean
Founda
The Cand is
• C.3.1 • C.3.2 • C.3.3 • C.3.4
o o o o
o o o o o o o
n Flynn –
tion Red
Current Founs broken dow
Problem ProposedAnalysis Analysis C.3.4.1.A OC.3.4.1.B OC.3.4.1.C GC.3.4.1.D F
C.3.4.2.A OC.3.4.2.B MC.3.4.2.C MC.3.4.2.D MC.3.4.2.E MC.3.4.2.F OC.3.4.2.G M
– Constru
design ~ S
Figure
ndation Systwn as follow
Statementd Solution Steps Result Ov
Overview ofOriginal EstiGeotechnicalFoundation C
Overview ofMat FoundatMat FoundatMat FoundatMat FoundatOther Mat FoMat Foundat
uction M
Structural
e 1: Foundat
tem for the Wwed:
t
verviewf the Currentimate and Scl Report SumConstruction
f the Foundattion Concepttion Design Btion Design Ition Design oundation Dtion Schedul
W
BUI
Manageme
l Breadth
tion Excavat
Wellington C
t Foundationchedule mmary n
tion Redesigt Applied to BackgroundInput Data a
esign Considle Implicatio
Wellington
SprLIDING F
ent
h
tion
Condominium
n System
gn Wellington
d and Assumpt
derations ons
n Condo
ring ThesiFOR THE
Page 9
ms has been
Pa Pa Pa Pa
Condominiu
tions
ominiumExton, PA
is ResearchE FUTURE
5 of 147
n analyzed
age 96 age 96 age 96 age 97
ums
s A h E
Wellington Condominiums Exton, PA
Spring Thesis Research BUILIDING FOR THE FUTURE
Sean Flynn – Construction Management Page 96 of 147
o C.3.4.2.H Mat Foundation Budget Implications • C.3.4.3 Comparison of the Two Foundation Systems Page 113
C.3.1 Problem Statement
With poor subsurface conditions prevalent, can the foundation system be redesigned to possibly reduce cost and time spent without interfering with architects or owner needs? This problem was identified through the geotechnical reports, change orders, and project manager interviews. A lot of money, time, and energy were spent by the project team having to deal with poor subsurface conditions. An analysis communicating some potential solutions is one study of great interest to many on the Wellington Condominiums Project.
C.3.2 Proposed Solution A possible solution to the Wellington Condominiums Project is for a structural redesign of the foundation system. A structural breath will be utilized in the analysis of the comparison between the current and proposed systems. The current foundation system makes use of single slab column footings and will be challenged through the redesign of a matt slab foundation. A matt slab foundation system is proposed and will be researched to do the following possibilities:
1. Save time and money by not having to excavate as deep in rock material. 2. If footing depth can be decreased possible savings in the dewatering system
could happen. 3. Using a matt slab could reduce the strength needed for foundation concrete
and also if designed correctly act as a slab on grade. This could potentially save time and cost to the project.
C.3.3 Analysis Steps
The procedure to investigating if a matt slab foundation system would be more viable than a traditional single slab column footing is as followed:
1. Learn in more detail and have available the single slab column footing’s estimate, schedule, design documentation, specifications, and methods of construction.
2. Redesign the foundation system utilizing a matt slab foundation. Figure out how much material, cost, and time would be spent to construct.
3. Compare the two systems and create a matrix chart based on the owner requirements of which system overall is better for the project.
C
Sean
.3.4 AnalyThe mpourispentsystemconstPSI cpouriway b
C.3.4.1.AThe Wconcrformwdetail Footi
n Flynn –
ysis Resultmatt slab fouing single slat to rock excm and suppotruction to thconcrete for fing the entireby the owne
A OverviewWellington Crete that wasworks and cl as followed
ings: Norm
28 day6,000 record
Reinfo Avera Minim Minim
– Constru
t Overviewundation sysab column foavate by rocort equipmenhe winter mofootings. One slab may brs inputs of
w of the CurrCondominius done on theoncrete placd:
mal weight coys (This wasPSI compre
d.) forcing will cage size of comum of 3 feemum allowab
Figure
uction M
w tem at first sootings. Whck hammerinnt, weeks of onths, and thnce you lookbe a better althe foundati
rent Wellinm’s foundate constructiocement meth
oncrete with s value enginessive streng
consist of A6olumn footinet below finible bearing p
2: Wellingt
W
BUI
Manageme
seems to be aen looking a
ng, putting inf delays that whe structural k at all those ternative. Alion system b
gton Condotion consists on site. The tods of the fo
a minimum neered due togth in the con
615, Grade 6ng 15’L X 1ished surfacepressure of 3
on Condomi
Wellington
SprLIDING F
ent
an ironic sysat the follown a extensivewould push engineer spevariables thlso the analy
based on a m
ominium’s Fof a large p
type of horizoundation ar
compressivo the CM quntract docum
60 5’W X 18”De where expo3,500 PSF
inium’s Fou
n Condo
ring ThesiFOR THE
Page 9
stem to selecwing items: coe permanent back the faç
ecifying the he cost and eaysis can be s
matrix chart.
Foundation art of the cazontal and vere described
e strength ofuestioning thments by the
D osed to frost
undation
ominiumExton, PA
is ResearchE FUTURE
7 of 147
ct rather thanost and timedewatering
çade use of 6,000ase of simplwayed eithe
System st in place ertical in more
f 3,000 PSI ahe specified engineer of
t
s A h E
n e
0 ly er
at
Sean
Slab
Fountower
Sincecolumwas tlocatiextershapeformwformwand cplace
n Flynn –
on Grade: 5 inch
3,000 Reinfo
crushe
ndation Bear walls)
8” andstreng
e the soil at tmn footings to situate theions requiredior walls ande very quickwork was cowork was secolumns. Foled with a con
– Constru
hes of normaPSI at 28 da
forced with 6ed stone sub
ring and Sh
d 12” normagth of 3,000
Figure 3: S
the time had did not requ
e footing rebd. Once the d columns toly with a 12
onnected andet and properllowing inspncrete pump
uction M
al weight conays 6 X 6 – W2.1b base and va
hear Wall C
al weight reinPSI at 28 da
Substructure
enough cohuire any horizar and placefootings werook form wit0 ton AmQud reinforced rly supported
pection from and allowed
W
BUI
Manageme
ncrete with a
1 X W2.1 weapor barrier
Construction
nforced concays
from RAM
hesion to stayzontal or ver
e the concretre to the streth large gang
uip crane tippinto place wd, the rebar wthe project m
d time to gai
Wellington
SprLIDING F
ent
a minimum c
elded wire fa
n: (includes e
crete with a
Concept
y in place, thrtical formwe with a con
ength requireg forms. Theping up each
with lateral bwas placed imanagementin strength.
n Condo
ring ThesiFOR THE
Page 9
compressive
fabric, over a
exterior and
minimum co
he foundatiowork. The onlncrete pump ed, the foundese large forh one into poracing. Aftein the foundat team, the c
ominiumExton, PA
is ResearchE FUTURE
8 of 147
e strength of
a 14 inch
stair and
ompressive
n strip and ly task left at the
dation’s rms took osition. The r the ation walls concrete was
s A h E
s
Sean
C.3.4.1.BThe Wdetail Origi
•••••
Origi
C.3.4.1.C The W
engininveswere were the prof Ea
n Flynn –
B Original EWellington Cled as follow
inal Estima
• Single Sl• Wall Stri• Foundatio• Foundatio• Slab on G
~See
inal Schedu
C GeotechniWellington Cneer and geostigation for completed fconducted broject team’
arth Engineer
– Constru
Estimate anCondominiuwed:
ate:
lab Column Fip Footings: on Walls: on Columns
Grade:
e Attached A
ule:
~See Att
ical Report Condominiulogist compathe site condfor the invesby Main Lins specificatioring supervi
uction M
d Schedule m’s original
Footings:
s:
Total:
Appendix f
Total:
tached App
Summary m’s project any located ditions at Westigation frome Drilling Cons by the sused and mon
W
BUI
Manageme
l foundation
$104, 37$13,070$133,13$33,488$73,048
$357,11
for Detaile
83 WorMon 1/
pendix for
team hired oin East Norrellington Com May 23 thompany of Wurveyor Hopnitored the te
Wellington
SprLIDING F
ent
system estim
74 0 39 8 8
19
ed Structur
rk Days = 1716/06 – Mon
Full Sched
on Earth Engriton PA, to pondominiumhrough May Wayne, PA apkins and Scest boring ac
n Condo
ring ThesiFOR THE
Page 9
mate and sch
ral Takeoff
7 Weeks n 5/1/06
dule~
gineering, a gperform a ges. Fifteen tes25, 2005. Thand were fiecott, Inc. A rctivities.
ominiumExton, PA
is ResearchE FUTURE
9 of 147
hedule are
ff~
geotechnicaleotechnical st borings he borings
eld located toepresentativ
s A h E
l
o ve
Sean
The laccora fairas murecomdrainSubstthe co
C.3.4.1.D
The pand thand pto raiincrebuildpoor ensuramou
n Flynn –
laboratory rerding to ASTr drainabilityuch as 5 feetmmends raisnage system ttantial soil aorrect soil be
~
D Foundatioproject team herefore too
permanent deise the finishase in elevat
ding less archsubsurface c
re a proper founts of chang
– Constru
Figure
esults indicatTM specificay record. Grot above the ping the finisto maintain g
and rock excaearing pressu
~See Attach
on Construcarmed with
ok the recommewatering syhed floor gration would mhitecturally pconditions anfoundation dege orders had
uction M
4: Site Bori
ted that the sations was saoundwater wproposed finihed floor grgroundwateravations belure.
hed Appen
ction this informa
mendation oystems to theade due to themake the parpleasing. Dund had to takesign. Durind to be cond
W
BUI
Manageme
ing Investiga
soil classificandy silt. It h
was encounteished floor gade or provir levels beloow the exist
ndix for Tes
ation knew tof Earth Enge foundatione parking garking garage uring excavake extra meang the courseducted to cor
Wellington
SprLIDING F
ent
ation
cation for a mhas a bearingered at all of garage. Earthiding permanw the propoting grade m
st Boring R
that soil condgineering to pn system. Thearage at the f
more visiblation the projasures througe of excavatirrect the poo
n Condo
ring ThesiFOR THE
Page 1
majority of thg capacity of
f the boring lh Engineerinnent waterprsed finished
must be done
Results~
ditions woulprovide watee architects dfoundation lee and possib
oject team engh change orion the followr subsurface
ominiumExton, PA
is ResearchE FUTURE
00 of 147
he soil f 4 KSF andocations and
ng roofing and d floor grade
to achieve
ld be an issuerproofing did not wantevel. An bly make thencountered rders to wing
e conditions:
s A h E
7
d d
.
ue
t
e
Sean
The t$610The eweekreaso
C.3.4.2.AWith whethanalyviablfrom
12345
6
7
n Flynn –
total amount,278. This enencounter ofks. This creatons why the f
A Overviewthe encount
her or not thysis to decidee solution. Tthe Building
. Adequate
. Bearing C
. Settlemen
. Quality:
. Adequatefracture omust conf
. Adverse conditionmovemen
. Seismic Fearthquak
– Constru
Fig
t for change nded up beinf poor subsurted a dominofaçade const
w of the Founter of poor suhe foundatione whether or
The selectiong Design and
e Depth: PreCapacity Fant: Must notMust have ae Strength:
or break aparform to desigSoil Changes. Expansive
nt of the founForces: Founke without ex
uction M
gure 5: Foun
orders was $ng a 70% incrface conditio effect to thtruction was
ndation Redubsurface con system shor not a redesin of a particud Constructi
eventing froailure: Fount settle to theadequate quaMust be bui
rt under supegn specificates: The foune soils such andation and ndation musxcessive sett
W
BUI
Manageme
ndation Chan
$253,159 ancrease in theions led to dhe entire sche
pushed to th
design onditions theould have beign of the foular foundatiion Handboo
st damage anndation muste extent that ality so that iilt to sufficieerstructure lotions.
ndation mustas silt and cldamage to tht be able to stlement or la
Wellington
SprLIDING F
ent
nge Orders
d resulted ine total budgedelaying the pedule and whe middle of
ere was an opeen changed.oundation sysion was baseok by Merrit
nd undermint be safe agait damages t
it is not subjent strength soads. The fou
t be able to rlay could exphe structure.support the s
ateral movem
n Condo
ring ThesiFOR THE
Page 1
n a total payoet for the fouproject by m
was one of thef winter.
pportunity to. It is throughstem would ed on a numbtt and is as fo
ning by scouainst failure. the structureected to deteso that it doeundation con
resist adversepand or shrin structure dur
ment.
ominiumExton, PA
is ResearchE FUTURE
01 of 147
out of undations. more than 3 e major
o investigateh this be deemed aber of factorollowed:
ur.
e. erioration. es not nstruction
e soil nk, causing
ring an
s A h E
7
e
a rs
Sean
Footiwere Welli
123
456
All thcapacvaryiutilizsoil.
FromCondTherethe W
n Flynn –
ing types othused as a gu
ington Cond
. Bearing C
. Very larg
. Soil undeor differen
. Good bea
. Potential
. Varying s
hese reasonscity can onlying subsoil czing large an
m Figure 6, itdominiums isefore due to
Wellington C
– Constru
her than spreuide from thedominiums fo
Capacity of se footings arr footing is vntial settlem
aring soil is dfor scour act
subsoil cond
s apply to they be designedconditions wid deep footi
t can be shows poor and ththe reasons
Condominium
uction M
ead footings e 2007 RS M
foundation re
soil is very lore required, very compre
ment. deep. tion exists.
ditions within
e Wellingtond to withstanithin the buings to preve
Figure 6:
wn that the bhat the drainlisted above
ms foundatio
W
BUI
Manageme
are usually uMeans Assemedesign:
ow. at a cost disa
essible, with
n building pe
n Condominind 3500 PSIilding perimeent excessive
Properties o
bearing capanability is bete, it was deteon system by
Wellington
SprLIDING F
ent
used for the mblies Data t
advantage. the probabil
erimeter.
ium Foundat which is coeter, comes te settlement
of Soils
city for the stween the ra
ermined to any utilizing a m
n Condo
ring ThesiFOR THE
Page 1
following reto the selecti
lity of causin
tion. The beonsidered fairthe requiremand have go
soils at Wellange of fair analyze the remat foundati
ominiumExton, PA
is ResearchE FUTURE
02 of 147
easons and ion of the
ng excessive
aring rly low. Wit
ment of ood bearing
lington and poor. edesign of ion.
s A h E
7
e
th
Wellington Condominiums Exton, PA
Spring Thesis Research BUILIDING FOR THE FUTURE
Sean Flynn – Construction Management Page 103 of 147
C.3.4.2.B Mat Foundation Concept Applied to Wellington Condominiums According to the Building Design and Construction Handbook by Merritt, a mat foundation is defined: as a single combined footing for an entire building unit. It is economical when building loads are relatively heavy and the safe soil pressure is small. Based on economic considerations according to the Building Design and Construction Handbook by Merritt, mat foundations are constructed for the following reasons and are judged against the Wellington Condominiums circumstances:
1. Large Individual Footings: A mat foundation is often constructed when the sum of individual footing areas exceeds about ½ of the foundation area. Wellington Condominiums Calculation:
• 259’ x 121’ Building Area = 31,339 SQ FT • 36 Footings x (20’ x 20’ Max Footing Area) = 14,400 SQ FT • (14,400 SQ FT / 31,339 SQ FT) x 100 = 45.95% < 50% SUM
From the calculation, it can be determined that approximately 46% of the footing area is below the rule of thumb value but is within consideration for mat foundation.
2. Cavities or Compressible Lenses: Mat foundation used when subsurface exploration indicates that there will be unequal settlement below the foundation due to small cavities or compressible lenses. A mat foundation would distribute the load more evenly and create better conditions for any possible settlement.
Wellington Condominiums Analysis Viewpoint:
• Cavities or Compressible Lenses have not been indicated in the geotechnical reports or have been an issue during construction.
• Minimal value has been placed on cavities or compressible lenses for this analysis.
3. Shallow Settlements: A mat foundation can be recommended when shallow settlements predominate and the mat foundation would minimize differential settlements.
Wellington Condominiums Analysis Viewpoint:
• Differential Settlement was identified in the geotechnical report and has been a large concern to the project team.
• Large consideration has been placed on how the foundation settlements would be with a mat foundation system.
4. Unequal Distribution of loads: Large disparity in building loads acting on different areas of the foundation can be subjected to excessive differential settlement with conventional spread footings. Using a mat foundation would tend to distribute the unequal building loads and reduce the differential settlements.
Wellington Condominiums Exton, PA
Spring Thesis Research BUILIDING FOR THE FUTURE
Sean Flynn – Construction Management Page 104 of 147
Wellington Condominiums Analysis Viewpoint:
• The column and wall loading varies and therefore different column sizes and spread footings are utilized. The largest spread footings are constructed at the corners and center of the foundation.
• Unequal distribution of loads is something to consider but is not a major focus for the design of the Wellington Condominiums mat foundation redesign analysis. Load distribution will be considered in the analysis for completeness.
5. Hydrostatic Uplift: A mat foundation could be used to resist uplift forces due to a high groundwater table. Wellington Condominiums Analysis Viewpoint:
• Groundwater at the project site is of huge concern to the project team. Extensive groundwater measures had to be in place before construction could ever begin.
• Any reduction in waterproofing or groundwater measures from the utilization of a mat slab would be of great savings in budget and schedule.
C.3.4.2.C Mat Foundation Design Background The design background for a mat foundation tends to be very complicated and requires
extensive knowledge and experience. Being said there are many articles and programs that engineers use when considering the design of a mat foundation system. Some of the design criteria outlined in the Building Design and Construction Handbook by Merritt are as followed:
1. Weight of soil excavated for the foundation decreases the pressure on the soil under the mat. If excavated soil weighs more than the building, there is a net decrease in pressure at mat level from that prior to excavation.
2. When the mat is rigid, a uniform distribution of soil pressure can be assumed and the design can be based on a statically determinant structure as shown in the Figure 7 below.
3. If the centroid of the factored loads does not coincide with the centroid of the mat area, the resulting nonuniform soil pressure should be used in the strength design of the mat.
4. Strength-design provisions for flexure, one-way and two-way shear, development length, and serviceability should conform to ACI 318 Building Code Requirements.
Sean
C.3.4.2.D A ma
StrucBeforfound
n Flynn –
D Mat Founat foundationcture Point. Tre utilizing tdation condi
• Eathexunwatotbe
• Co
• So
• St
– Constru
Figure 7: D
ndation Desin design wasThis softwarthe software tions had to arth Engineee column loa
xceed 10 kipnbalanced malls. Based otal settlemen
e within toleroncrete
o Compro Unit Wo Youngo Poisso
oil o Subgrao Allowa
teel o Yield S
uction M
Design Cond
ign Input Ds created throe specializesand inputtinbe identified
ering has assads will not s per lineal f
moments or laon these assunt to be less rable limits.
ression StrenWeight: 145 Pg’s Moduluson’s Ratio: 0
ade Modulusable Pressur
Strength: 60
W
BUI
Manageme
ditions for a
Data and Assough the utils in the compng data, inford. umed and inexceed 473 foot. Earth Eateral loads aumptions, Eathan one inc
ngth: 3 KSIPCF : 3155.92 KS.15
s: 50 KCF re: 3.5 KSF
0 KSI
Wellington
SprLIDING F
ent
Rigid Mat F
sumptionslization of Pplicated desirmation back
ndicated in ckips, and th
Engineering are imposed arth Engineech and the di
SI
n Condo
ring ThesiFOR THE
Page 1
Footing
CA MAT® ign of mat fokground abo
contract docuat the wall lohas assumedon the colum
ering estimatifferential se
ominiumExton, PA
is ResearchE FUTURE
05 of 147
Software byoundations. out the
uments that oads will nod that no mns and ted that the ettlement to
s A h E
7
y
ot
Sean
C.3.4.2.E Once
progrthick changgoal icost ocontr
For th
appro84”, 7defle
n Flynn –
• De
• Co• Sl• Lo
E Mat Foune the data hasram, results ca mat slab h
ging the thicis to get the of concrete arol over hydr
he design anopriate for th72”, 60”, 48ction settlem
– Constru
o Youngesign Param
o Minimo Top an
olumn Dimelaved Nodesoads and Loa
o Servico Ultima
ndation Desis been inputtcan be quickhas to be to pckness in thethickness of
and reinforcerostatic uplif
F
nalysis the fohe Wellingto”, 36”, 24”,
ment, and mo
uction M
g’s Modulusmeters mum Reinfornd Bottom R
X-DirectioY-Directio
ensions (from: Rx Degreead Combinae ate
ign ted and assigkly attained. properly supe input data wf the mat fouement. Also ft, load distri
Figure 8: PC
ollowing thicon Condominand 12”. Wi
oment capac
W
BUI
Manageme
: 29,000 KSI
cing Ratio (%Reinforcing
n: 3.25 inchn: 3.5 inches
m constructioe of Freedomations
gned to elemThe advanta
pport the requwill update tundation as th
by decreasinibution, and
CA MAT® S
ckness will bniums mat foith each thicity will be d
Wellington
SprLIDING F
ent
I
% of gross a
es s on documen
m
ments in the Page to this souired loads ohe results fohin as possibng the depthsettlements
Software
be looked at oundation sy
ckness the amdetermined. T
n Condo
ring ThesiFOR THE
Page 1
area): 0.18
nts)
PCA MAT®oftware is anof the structuor the viewerble due to th
h of the founwill occur.
to determineystem: 120”,mount of reinThe best com
ominiumExton, PA
is ResearchE FUTURE
06 of 147
® Software nalyzing howure. Simply r to see. The he controllingdation better
e the most , 108”, 96”, nforcing, mbination of
s A h E
7
w
g r
f
Sean
the thresult
Fromfoundmat smixemat scommside o
C.3.4.2.F
One ocondiFinishfeet rthe gr
n Flynn –
hree will resuts of the ana
m the PCA Mdation lies beslabs which ad rebar sizes
slab be utilizmonly foundof the given
~
F Other Maof the majoritions was thhed Floor El
respectively.roundwater
– Constru
ult in the selalysis using t
MAT® Chartetween 48” aare unnecesss and bad setzed due to thd in construct
results.
~See AttachA
at Foundatior concerns adhe high watelevation (G.F With a 4 fodepth level.
uction M
lected mat fothe PCA MA
, it can be shand 36”. Absary to carryttlement cone settlementting foundat
hed AppenAnd Analy
on Design Cddressed on ter table. As aF.F.E.) and g
oot mat found
W
BUI
Manageme
oundation thAT® Softwar
hown that thove the resu
y the structurntours. Theret contours antions. This v
dix for PCysis Calcula
Consideratiothe project s
an example igroundwaterdation there
Wellington
SprLIDING F
ent
ickness. There.
e ideal thickults creates laral load. Beloefore it is recnd typical rebalue tends to
CA Mat® Cations~
ons site other than Figure 9, tr depth is at will be an a
n Condo
ring ThesiFOR THE
Page 1
e chart below
kness for the arge rebar siow the resulcommended bar sizes thao be on the c
Contours
an poor subsuthe Boring B429.00 feet dditional 2 f
ominiumExton, PA
is ResearchE FUTURE
07 of 147
w shows the
mat zes and thickts creates that a 48”
at are conservative
urface B-5 Garage and 423.00
feet above
s A h E
7
k
Sean
More1, B-to be dewawhenconstthe pedelayteam conce The ppumpPVC 429.7pipinrecomthe mgreat
n Flynn –
Figu
e concern by6, and B-11.done. The p
atering systemn constructintruction workermanent de
ys and produdid an excel
erning groun
permanent dp backup. Thunder the 5”
71’. The maxng slope. Themmended tha
mat foundatioer need for t
– Constru
ure 9: Geote
y the project . The groundproject team m and an ex
ng the foundakers with the
ewatering syuctivity decrellent job conndwater dept
ewatering syhe current gr” slab on graximum travee drainage piat the pipingon system. Dthe dewaterin
uction M
echnical Bor
team was gidwater table decided at thcellent wateation systeme dewateringstem was noeases could hncerning watth should rem
ystem utilizeravity flow sade from a stel distance isiping currentg system remDoing so mayng and wate
W
BUI
Manageme
ring Results
iven for the dwas above the beginningrproofing sy
m. Even thougg system werot installed phave resultedterproofing amain the sam
es a gravity fystem utiliztarting elevas approximattly runs betw
main the samy result in a rproofing sy
Wellington
SprLIDING F
ent
from Earth E
depth of the the G.F.F.E.g of the projystem. This pgh the soil wre provided
prior to foundd. It is in thiand the desigme.
flow system es a 6” DIA
ation of 430.tely 379’ witween columne but be dropgreater influ
ystem. With
n Condo
ring ThesiFOR THE
Page 1
Engineering
groundwate and somethect to installproved to pawas considera dry area todation constrs analysis thgn for the m
with an elecA perforated
75’ to a gravth a 0.03 in/fn and footingpped 4’ to ac
ux of water athis increase
ominiumExton, PA
is ResearchE FUTURE
08 of 147
g
er table at B-hing needed l first the
ay dividends red poor, o work in. If ruction,
hat the projecat foundatio
ctrical sump drainage vity outfall oft drainage gs and it is ccommodateand create a e in demand
s A h E
7
-
f
ct n
of
e
Wellington Condominiums Exton, PA
Spring Thesis Research BUILIDING FOR THE FUTURE
Sean Flynn – Construction Management Page 109 of 147
for water removal may create a possible backlog of additional hydrostatic pressure that cannot be forgotten about. With a possibility of increased hydrostatic pressure with the utilization of the same drainage system comes to the responsibility of the designer as to what to do. Through advice of structural engineers and contractors it was recommended that once you start constructing your foundation that the dewatering system must be in effect to reduce the possibility of high hydrostatic pressure on the foundation system. With a permanent dewatering system installed prior to construction, it will alleviate any potential risk during construction of hydrostatic pressure. The following calculation is provided as to give a rule of thumb to the structural load interaction of the Wellington Condominiums Project: Allowable Bearing Pressure of Soil Conditions: 3.5 KSF Square footage of Mat Foundation: 259’ x 121’ 31,339 SF Allowable Total Load Transferred to Soil Conditions: 109,687 K Maximum Column Load: 473 K x 36 Columns 17,028 K Maximum Wall Load: 10 K/FT x 760 FT 7600 K Total Mat Foundation Load: 24,628 K The mat foundation load is less than the allowable mat foundation load; therefore the foundation has enough strength to allow for the prevalent soil conditions. There is a 4.45 safety factor on this analysis which will allow for any additional hydrostatic pressure and uplift from the soil conditions present. With the permanent dewatering system installed prior to foundation construction and continued throughout the project; there is no additional analysis to consider.
C.3.4.2.G Mat Foundation Schedule Implications The schedule effect to the implementation of the mat foundation system is shown in Figure 10.A along with the original schedule in Figure 10.B.
Sean
n Flynn –
~S
– Constru
Figure
Figure 10
See Attache
uction M
10.A: Mat F
0.B: Original
ed Appendi
W
BUI
Manageme
Foundation S
l Foundation
ix for the C
Wellington
SprLIDING F
ent
System Sche
n System Sch
Complete S
n Condo
ring ThesiFOR THE
Page 11
dule
hedule
Schedule~
ominiumExton, PA
is ResearchE FUTURE
10 of 147
s A h E
7
Wellington Condominiums Exton, PA
Spring Thesis Research BUILIDING FOR THE FUTURE
Sean Flynn – Construction Management Page 111 of 147
From the schedules the important dates to take notice are highlighted in blue and listed as followed for analysis: Mat Foundation System:
• Construction: 340 Days Mon 1/16/06 – Fri 5/4/07 • Substructure: 149 Days Wed 2/22/06 – Mon 9/18/06 • Foundation and Columns: 61 Days Mon 3/13/06 – Mon 6/5/06 • Superstructure: 169 Days Tue 9/5/06 – Fri 4/27/07
Original Foundation System:
• Construction: 340 Days Mon 1/16/06 – Fri 5/4/07 • Substructure: 132 Days Wed 2/22/06 – Thu 8/24/06 • Foundation and Columns: 39 Days Mon 3/13/06 – Thu 5/4/06 • Superstructure: 186 Days Fri 8/11/06 – Fri 4/27/07
Key: Red – Schedule Push Back Green – Schedule Pull Back Some interesting results have occurred that are worth noting for the comparison between schedules. The construction of the mat foundation in comparison to the original foundation system will result in as followed:
• Construction: Entire Construction of the project will be the same start and finish date with no increase or decrease in project schedule.
• Substructure: The construction of the substructure will increase by 17 days. The substructure construction will start on the same day but finish at a later time.
• Foundation and Columns: Foundation and Columns will increase by 22 days. The foundation and column construction will start on the same day but finish at a later time.
• Superstructure: The superstructure will decrease in time of construction by 17 days. The start time will be pushed back but will finish on the same day as the original schedule.
What this data is revealing is that there is float within the schedule and the utilization of a mat foundation system will not delay the overall project. There is an increase in parts of the schedule but due to superstructure float was able to take on those extra days of construction and still finish on time. Therefore based on these observations, more analysis must be conducted further as to whether or not to utilize a mat foundation system for the Wellington Condominiums Project.
Wellington Condominiums Exton, PA
Spring Thesis Research BUILIDING FOR THE FUTURE
Sean Flynn – Construction Management Page 112 of 147
C.3.4.2.H Mat Foundation Budget Implications The current budget for the Wellington Condominiums Foundation system is based on the following estimates: Original Estimate:
• Single Slab Column Footings: $104, 374 • Wall Strip Footings: $13,070 • Slab on Grade: $73,048 • Change Orders $253,159
Total: $443,651
Mat Foundation Estimate @ 4’ Thickness:
• 2007 RS Means Building Construction Data • Cubic Yards of Mat Foundation: 259’ x 121’ x 4’ 4,643 CY • 2 Crews (C-14C) Totaling:
o 2 Foreman o 12 Carpenters o 4 Rodmen (reinf.) o 8 Laborers o 2 Cement Finishers o 2 Gas Engine Vibrators
• Material Cost: $174/CY $807,882 • Labor Cost: $70/CY/Crew x 2 Crews = $140/CY $650,020 • Equipment: $0.38/CY/Crew x 2 Crews = $0.76/CY $3,529
Total: $1,461,431
Mat Foundation Estimate @ 3’ Thickness:
• 2007 RS Means Building Construction Data • Cubic Yards of Mat Foundation: 259’ x 121’ x 3’ 3,482 CY • 2 Crews (C-14C) Totaling:
o 2 Foreman o 12 Carpenters o 4 Rodmen (reinf.) o 8 Laborers o 2 Cement Finishers o 2 Gas Engine Vibrators
• Material Cost: $174/CY $605,868 • Labor Cost: $70/CY/Crew x 2 Crews = $140/CY $487,480
C
Sean
•
Fromtimesthe cofoundAlso found If thewhat based
C.3.4.3 ComThe cbased
The cmatriscale categreasomat f
n Flynn –
Equipmen
m the estimats over the oriost is 3.3 timdation system84% of the
dation system
e owner weresystem shou
d on these es
mparison comparison od on the own
comparison aix chart baseof 1-12. Eac
gories. For inonable price foundation w
– Constru
nt: $0.38/CY
e analysis, aiginal found
mes over the m, 53% of thoriginal costm.
e to decide suld be utilizestimates.
of the Twof the two fo
ner requirem
and contrasted on what wch system wnstance, the cand was com
was deemed a
uction M
Y/Crew x 2 C
at a minimumdation estima
original fouhe total struct would have
solely on theed. It would
wo Foundaoundation sy
ments of whic
t of the two fwas most impwould be grad
cost for the ommented as bas poor due
W
BUI
Manageme
Crews = $0.7
T
m 3’ mat fouate. At the prundation estimctural systeme to be put to
estimates ginot be benef
tion Systeystems have ch system ov
foundation sportant throuded on how woriginal founbeing great ato the high c
Wellington
SprLIDING F
ent
76/CY
Total:
undation thicreferred 4’ mmate. If utili
m would be powards the c
iven here forficial to use
ems been created
verall is bette
ystems haveugh the ownewell it perfondation systeadvantage tocost imposed
n Condo
ring ThesiFOR THE
Page 11
$2,646
$1,095,99
ckness the comat foundatioized the 4’ mput towards tconstruction
r the projecta mat found
d through a mer for the pro
e been createer’s perspect
orms in each em was deemo the project d onto the pr
ominiumExton, PA
is ResearchE FUTURE
13 of 147
94
ost is 2.5 on thickness
mat the redesignof the mat
t budget as todation system
matrix chart oject.
ed through a tive on a of the 12
med as a budget. The
roject budget
s A h E
7
s
.
o m
e t.
Wellington Condominiums Exton, PA
Spring Thesis Research BUILIDING FOR THE FUTURE
Sean Flynn – Construction Management Page 114 of 147
The results have indicated that a score of 67.6% and 69.4% for the original and mat foundation system respectively. Both are indicated as an okay system but it is the mat foundation which should be selected by the owner. This provides an interesting perspective in that the mat foundation even though cost was a number one concern and was over three times the original foundation system; the mat foundation should be perused if given the correct amount of funding availability. The advantages of the mat foundation in subsurface interaction and load distribution create just enough of an advantage to spend the extra money on the system. If however other variables were to change; it could give the possibility of the original foundation system being preferred over the mat foundation system. But with the current information provided, if the amount of funding is available, the mat foundation system should be selected for the Wellington Condominiums Project.