1
Training Support Package
Fixed Bridging
PREPARED BY
MANEUVER SUPPORT
CENTER
TSP: 052-12C30-C
DATE:001023
Student Handout
SFC Timothy Girard __________ 001023 ___________
12C30 COURSE MANAGER Date
_Mr. Harold Drossel ___________ 001023___________
Chief, CMF 12 DOTD Date
_Mr. Ollie Jackson_____________ 001023___________
Chief, Warrior Engineer Division Date
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 2/39
2
MEDIUM GIRDER BRIDGE MEDIUM GIRDER BRIDGE
BAILEY BRIDGE BAILEY BRIDGE
DIRECT ASSEMBLY OF A BAILEY BRIDGE Pages 3 - 13
ORGANIZE DUTIES OF MEDIUM GIRDER BRIDGE
ASSEMBLY CREWS Pages 14 - 22
DIRECT SITE LAYOUT FOR MEDIUM GIRDER
BRIDGE Pages 23 - 27
DIRECT ASSEMBLY OF A MEDIUM GIRDER
BRIDGE Pages 28 - 39
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 3/39
3
HISTORY AND DESCRIPTION: At the outset of world war II, the United States (US) Army sought
a versatile bridge that could span a variety of gaps and be quickly assembled by manpower alone. For
this reason, we adopted the design from the British prefabricated Bailey bridge, US nomenclature M1.
We revised the design to provide a greater roadway width of 121/2 feet and designated it the Panel
Bridge, Bailey M2. The Bailey bridge is a through-type bridge, the roadway being carried between two
main girders. The trusses in each girder are formed by 10-foot panels pinned end to end. The main
girders on each side of the bridge can be assembled in multiple widths and heights to provide added
strength and/or length of span. The Bailey bridge system is highly labor-intensive but also a highly
versatile system. Some of the different types of structures that can be constructed are two lane,
through-type bridge; deck type bridge; bridge on piers; railway bridge; and floating bridges. In some
case, because it can be assembled in multiple heights and widths, it is the only tactical bridge suitablefor long spans and heavy loads.
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 4/39
4
PANEL
TRANSOM
TRANSOM CLAMP
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 5/39
5
RAKER BRACE
BRACING FRAME
SWAY BRACE
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 6/39
6
BASE PLATE
PLAIN RAMP
BUTTON RAMP
RAMP PEDESTAL
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 7/39
7
PLAIN STRINGER
BUTTON STRINGER
FEMALE END POSTMALE END POST
BEARING
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 8/39
8
CHESS
RIBAND
RIBAND BOLT
JACK
JACK SHOE
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 9/39
9
PANEL PIN
SHORT PANEL PIN
TIE PLATE
BRACING BOLT
CHORD BOLT
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 10/39
10
ROCKING ROLLER
PLAIN ROLLER
TRANSOM ROLLER
LAUNCHING NOSE LINK
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 11/39
11
ROCKING ROLLER TEMPLATE
PLAIN ROLLER TEMPLATE
CARRYING TONGS
CARRYING BAR
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 12/39
12
DIFFERENT TYPES OF WRENCHES USED FOR BAILEY BRIDGE
WRENCH USE
1. 1 1/8” offset 90 degree socket wrench
2. 1 1/2” offset structural wrench
3. 1 1/2” offset structural wrench
4. 17/8” offset structural wrench
5. Reversible ratchet - wrench with
a. 1 1/8” and
b. 1 1/8” sockets
Tightening 3/4” (bracing) bolts
Tightening 3/4” (bracing, ribband) bolts
Tightening 1” (sway-brace) lock nut
(use tail of wrench for tightening turnbuckle)
Tightening 1 1/4” (chord) bolts
a. Tightening 1 1/4” (chord) bolts
b. Tightening 3/4” (bracing) bolts
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 13/39
13
NOTES
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 14/39
14
EQUIPMENT CHARACTERISTICS AND CAPABILITIES: The Medium Girder Bridge (MGB) is a
two girder deck bridge. The wide upper surfaces of the girders, and deck units laid between them form a
roadway 13ft 2in (4.0m) wide. The girders can be constructed in two forms: a shallow single story
construction or a deeper double story construction. The double story can be reinforced by adding
components of the Link Reinforcement Set (LRS) this permits longer Military Load Class (MLC) 70
bridges can be constructed
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 15/39
15
*
SSB Span Work Party Work Party Tasks
Up to 32 feet 1 NCO Supervision
8 soldiers All soldier’s
responsible to place
deck units
1*, 2, 3, 4 Left hand panels and
launching nose
5*, 6, 7, 8 Right hand panels
and roller beam
* Party leaders responsible for inserting pins and locking rollers.
WORK CREWS, (b) SINGLE STORY (MGB)
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 16/39
16
*
SSB Span Work Party Work Party Tasks
38 to 50 feet 1 NCO Supervision
16 soldiers All soldier’sresponsible to place
deck units
1*, 2, 3, 4 Left hand panels,
launching nose and
bankseat beams
5*, 6, 7, 8 Right hand panels
and roller beam
9*, 10, 11, 12 Left hand panels
13*, 14, 15, 16 Right hand panels
* Party leaders responsible for inserting pins and locking rollers.
WORK CREWS (c), SINGLE STORY (MGB)
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 17/39
17
*
SSB Span Work Party Work Party Tasks
56 to 74 feet 1 NCO Supervision
16 soldiers All soldier’s
responsible to placedeck units
1*, 2, 3, 4 LH panels, launching
nose and bankseat
beam
5*, 6, 7, 8 RH panels, roller
beam and bankseat
beam
9*, 10, 11, 12 LH panels
13*, 14, 15, 16 RH panels
* Party leaders responsible for inserting pins and locking rollers.
LH=left hand/ RH=right hand
WORK CREWS (d), SINGLE STORY (MGB)
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 18/39
18
DSB Span Work Party Work Party Tasks
36 to 102 feet 1 NCO Supervision
24 soldiers All soldier’s responsible toplace deck units
1,2,3,4 LH bottom panel crew
5,6,7,8 LH top panel crew
9*,10,11,12,13,14 Center bridge crew,launching nose, swaybraces, roller locks
15* LH party leader, pin & jack man
16* RH party leader, pin &
jack man
17,18,19,20 RH bottom panel crew
21,22,23,24 RH top panel crew
* Party leaders insert pins/ LH=left hand/ RH=right hand
(a) (b) (c) (d)
Double story Single Span
Working party
Time by day (hours)
Time by night (hours)
1 + 24 1 + 24 1 + 24
1-4 Bays 5-8 Bays 9-12 Bays
3/4 1 1 1/2
1 1/4 1 1/2 2
2E+1through12 bays
without link
WORK CREWS, (b) DOUBLE STORY (MGB)
*
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 19/39
19
DSB Span Work Party Work Party Tasks
108 to 162 feet 1 NCO Supervision
24 soldiers All soldier’s responsibleto place deck units
1,2,3,4 LH bottom panel crew
5,6,7,8 LH top panel crew
9*,10,11,12,13,14 Center bridge crew,launching nose, swaybraces, roller locks
15* LH party leader, pin & jack man
16* RH party leader, pin & jack man
17,18,19,20 RH bottom panel crew
21,22,23,24 RH top panel crew
* Party leaders insert pins/ LH=left hand/ RH=right hand
(a) (b) (c) (d)
Double story Single Span
Working party
Time by day (hours)
Time by night (hours)
1 + 24 1 + 24 1 + 24
13 Bays 14-18 Bays 19-22 Bays
1 1/2 1 3/4 2
2 2 3/4 3
2E+13through22 bays
without link
WORK CREWS, (c) DOUBLE STORY (MGB)
*
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 20/39
20
DSB Span Work Party Work Party Tasks
108 to 162 feet 2 NCO’s Supervision
32 soldiers All soldier’s responsible toplace deck units
1,2,3,4 LH bottom panel crew
5,6,7,8 LH top panel crew
9*,10,11,12,13,14 Center bridge crew,launching nose, swaybraces, roller locks
15* LH party leader, pin & jack man
16* RH party leader, pin &
jack man17,18,19,20 RH bottom panel crew
21,22,23,24 RH top panel crew
Link reinforced 25*,26,27,28 LH reinforcement crew
party 29*,30,31,32 RH reinforcement crew
* party leaders insert pins/ LH=left hand/ RH=right hand
(a) (b) (c) (d)
Double story Single Span
Working party
Time by day (hours)
Time by night (hours)
2 + 32 2 + 32 2 + 32
13 Bays 14-18 Bays 19-22 Bays
2 2 3/4 3
3 4 4 1/2
2E+13 through 22 bays
with link set
WORK CREWS, (d) DOUBLE STORY (MGB)
*
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 21/39
21
* These parts are carried in the basket
MANPOWER REQUIREMENTS
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 22/39
22
NOTES
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 23/39
23
MEDIUM GIRDER BRIDGE
PROFORMA SHEET 1
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 24/39
24
MEDIUM GIRDER BRIDGE
PROFORMA SHEET 2
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 25/39
25
MEDIUM GIRDER BRIDGE
PROFORMA SHEET 3
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 26/39
26
MEDIUM GIRDER BRIDGE
PROFORMA SHEET 4
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 27/39
27
NOTES
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 28/39
28
BOTTOM PANEL
TOP PANEL
BANKSEAT BEAM
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 29/39
29
END TAPER PANEL
JUNCTION PANEL
DECK
SHORT RAMP
LONG RAMP
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 30/39
30
SWAY BRACE
CURB
GUIDE MARKER
BRACING PIN
HEADLESS PIN
PANEL PIN
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 31/39
31
LIGHT LAUNCHING NOSE, FRONT
LIGHT LAUNCHING NOSE REAR
HEAVY LAUNCHING NOSE
LAUNCHING NOSE PIN
ROLLER BEAM
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 32/39
32
LANDING ROLLER
LANDING ROLLER PEDESTAL
LAUNCHING NOSE ROLLER ADJUSTABLE
SUPPORT
Launching Nose Cross Girder Post
Launching Nose Cross Girder
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 33/39
33
LONGITUDINAL GIRDER
FRAME CROSS GIRDER
FRAME
JACK SEAT
JACK SUPPORTJACK POST
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 34/39
34
SINGLE STORY BASEPLATE
DOUBLE STORY BASEPLATE
PUSH BAR CROSS GIRDER
PUSH BAR
PUSH BAR ADAPTER
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 35/39
35
BUILDING PEDESTAL
CARRYING BAR
CARRYING HANDLE
PULLER (TURFER JACK)
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 36/39
36
CAPSILL ROLLER BEAM
CAPSILL PIN
ROCKING ROLLER
DAVIT POST ASSEMBLY
POST TENSIONING ASSEMBLY
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 37/39
37
LONG REINFORCEMENT LINK
SHORT REINFORCEMENT LINK
ANCHOR ASSEMBLY
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 38/39
38
FOOT WALK BEARER
FOOT WALK
7/27/2019 C-handout
http://slidepdf.com/reader/full/c-handout 39/39
NOTES