By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing...

48
By NEERAJ AGRAWAL General Manager/Civil/ DFCCIL November 21, 2013

Transcript of By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing...

Page 1: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

By

NEERAJ AGRAWALGeneral Manager/Civil/ DFCCIL

November  21, 2013

Page 2: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

Scope of Presentation

Dedicated Freight Corridor Project

At a GlanceGenesis of DFC in IndiaBasic Design FeaturesUnique Project FeaturesFunding ArrangementsProject UpdatesO t itiOpportunitiesRoad Ahead

ICEMA 2013  www.dfccil.org

Page 3: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

AT A GLANCEAT A GLANCE

ICEMA 2013  www.dfccil.org

Page 4: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

What DFC means for Railway Industry ?

350 million m3 of Earthwork / Subgrade20 million m3 of Stone Ballast20 million m3 of Stone Ballast Hundreds of thousand cum. of RCC / PSC 11 million Ties / Sleepers11 million Ties / Sleepers Close to a million Ton of Structural steelA million Tonne of Rail procurement /layingA million Tonne of Rail procurement /laying7,000 small/big bridgesMore than 50 Rail to Rail FlyoversMore than 50 Rail to Rail Flyovers1000 ROBs/RUBs

( All quantities are approximate )( All quantities are approximate )

ICMEA 2013  www.dfccil.org

Page 5: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

What DFC means for Railway Industry?

54 Traction sub-stations.162 Traction Switching Station (SP & SSP).g ( )6000 Km of Contact & Catenary Wire (Copper/ Copper Alloy).6000 Km of Aluminum (ACSR/ AAAC) Conductor.Over 3 Lacs Insulators.MT of Steel Structures for OHE & Switching Stations.81 Traction Transformers.600 Auto Transformers.TCP/ IP based SCADA.

( All quantities are approximate )

ICMEA 2013  www.dfccil.org

Page 6: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

What DFC means for Railway Industry?

More than 100 Stations Signaling complete with Electronic Interlocking and Track Detection.

More than 2000 Signals.

1 Master Switching Centre, 5 Base Switching Centre, 3201 Master Switching Centre, 5 Base Switching Centre, 320 Base Transmitters and 1400 Cab Radios (OPH+GPH+GSM Hand Set) for GSM®.

More than 100 Telecom Facilities (Exchanges).

6000 Kms OFC and Quad Cables & Laying.y g

More than 100 OFC Nodes.

( All quantities are approximate ) 

ICMEA 2013  www.dfccil.org

Page 7: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

GENESIS OF DEDICATED FREIGHT CORRIDORS IN INDIA

ICMEA 2013  www.dfccil.org

Page 8: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

Indian Railways – An Overview

MANIFOLD GROWTH OF FREIGHT TRAFFIC – BUTTER & BREAD OF IRMANIFOLD GROWTH OF FREIGHT TRAFFIC  BUTTER & BREAD OF IR

473.5400

500

FREIGHT TRAFFIC (MILLION TONNES)

73.20

100

200

300

AN INCREASE OF 400.3 MT OVER 50 YEARS

1950‐51 2000‐01

FREIGHT TRAFFIC (MILLION TONNES)

Freight Traffic (MT)

1950‐51 2000‐01

975.2

600

700

800

900

1000

AN INCREASE OF 502 MT

473.5

0

100

200

300

400

500 AN INCREASE OF 502 MT FROM 2000‐01

0

2000‐01 2010‐11

Freight Traffic (MT)

2011‐122000‐01

ICMEA 2013  www.dfccil.org

Page 9: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

Golden Quadrilateral & Its Diagonals

High Density 

Corridor 

(Golden (

Quadrilateral 

+ Diagonals) DELHI

16% of route 

Km carries KOLKATTA52% of 

passenger & 

58 % ofMUMBAI

KOLKATTA

58 % of 

freight

CHENNAICHENNAI

Page 10: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

Areas Of Concern

Falling market share

Capacity constraints on high density network.

Differential speeds of trains p

Inadequate Ports / Mines connectivity

I bilit t l /h i t iInability to carry longer/heavier trains

Lower throughput / longer turn-around

ICMEA 2013  www.dfccil.org

Page 11: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

Scope For Improvement

Only following possibilities :--

Upgrading the existing networkUpg ad g t e e st g et oCreation of a new passenger corridorCreation of a new dedicated freightCreation of a new dedicated freight corridor

ICMEA 2013  www.dfccil.org

Page 12: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying
Page 13: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

Dedicated Freight Corridor ‐ Eastern Corridor

TIBET

HARYANA

UTTARAKHANDPUNJABLUDHIANA

AMBALA

SAHARANPUREXISTING LINE

DFC LINE (PARALLEL)

(EXISTING STNS

LEGEND

NEPAL

HARYANAMEERUT

HAPUR

KHURJA

ALIGARHHATHRAS

(EXISTING STNS.

RAJASTHANUTTAR PRADESH

HATHRAS

TUNDLA

ETAWAH BHAUPURKANPUR

BIHAR

BANGLADESH

NEW GANJKHWAJA

PREMPUR

ALLAHABAD

MUGHALSARAI

SONNAGAR

NEW KARWANDIYA

MADHYA PRADESHJHARKHAND

BANGLADESHSONNAGAR

MADHYA PRADESH

CHHATISGARHWEST BENGAL

DANKUNI

Page 14: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

HARYANAREWARI PIRTHALAREWARI

Dedicated Freight Corridor ‐Western Corridor

DADRI

UTTAR PRADESHRAJASTHAN

PHULERA

REWARI PIRTHALANIM KA THANA

RINGAS

PHULERA

AJMER

PAKISTANMARWAR

AJMER

SENDRA

MARWAR

SIROHI

MAHESANA

PALANPUR

ABU RD.

PALANPUR

MAHESANA

MADHYA PRADESH

GUJARATMAKARPURA

SANAD AHMADABAD

VADODRA

BHARUCH

GOTHANGAMSANJALI

SURAT

VALSAD

SANJAN

EXISTING LINE

DFC LINE (PARALLEL)

LEGEND

MAHARASHTRAARABIAN SEA

VASAI

JNPT

DAHANU

PANVEL

VASAI

( )

DFC LINE(DETOUR)

DFC JUNCTION STNS.

EXISTING STNS.

Page 15: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

Objectives Of The Project

Create additional rail infrastructure to cater to

Increase rail share in freight market infrastructure to cater to

high levels of transport demand

IT k i f

freight market

OBJECTIVES

Reduce unit cost of transportation resulting in market

IT packaging of Freight Services

OBJECTIVES resulting in market competitive rail tariff for customer

Create rail connectivity to bulk customers not using rail network through

Provide seamless end to d l ti t thSegregate freight infrastructure for

g gPPP model

end solution to the customers

Segregate freight infrastructure for focused approach on both passenger and freight business of Railways

ICMEA 2013  www.dfccil.org

Page 16: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

Operating Aspects of DFCC

• DFCC to manage train operation on DFC.

• DFCC to have own stations and control centers.

• Rolling stock ownership & its maintenance by IRIR.

Feeder Routes /Sidings to be upgraded by IR• Feeder Routes /Sidings to be upgraded by IR .

• All LCs to be replaced by ROBs / RUBs• All LCs to be replaced by ROBs / RUBs.

ICMEA 2013  www.dfccil.org

Page 17: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

BASIC DESIGNBASIC DESIGN FEATURESFEATURES

ICMEA 2013  www.dfccil.org

Page 18: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

Indian Railway DFC Routes

Basic Design Features

Height4.265 m 7.1 m 5.1m

Moving Dimensions

Indian Railway DFC Routes

Width

Western Corridor Eastern Corridor

3200 mm 3660 mm

Container Stack

700 m 700/ 1500 m

Train Length Western Corridor Eastern Corridor

700 m 700/ 1500 m

Train Load

4,000 Ton 15,000 Ton

ICMEA 2013  www.dfccil.org

Page 19: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

Basic Design Features (Contd.)

Heavier  Axle LoadsA l L d

Indian Railway       DFC Routes

Axle Load 22.9 t / 25 t 32.5t/25 t

Track Loading density

8.67 t/m 12 t/m

75 Kmph 100 Kmph

Maximum Speed

Grade Upto 1 in 100 1 in 200

ICEMA 2013 www.dfccil.org

Page 20: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

UNIQUEUNIQUE PROJECTPROJECT

FEATURES

ICMEA 2013  www.dfccil.org

Page 21: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

Unique Project FeaturesLand acquisition

Stupendous task of acquisition of 10,000 hectares of land insocio-political environment.

Leveraging domain expertise of State and Central Governmentd i l C t l l i l ti RAA 2008under special Central legislation RAA 2008.

Adoption of detours to mitigate social impact involving shiftingof habitats even at additional costs to the projectof habitats even at additional costs to the project.

Total involvement of PAPs has been the key to success: byTransparent process.Transparent process.Creating awareness about the project.Multi-level grievance Redressal MechanismDirected Skill Up gradation through CSR for PAPs.p g g

Over 94% achieved.ICMEA 2013  www.dfccil.org

Page 22: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

Unique Project Features(contd.)

Environmental Impact & Mitigation MeasuresImpact minimized by adopting alignment parallel tohighways/railways through environment sensitivezones, e.g. Wild Life Sanctuary/BirdSanctuary/CRZ/Forest, etc.

Environmental clearance from National Board of Wild Lifed th G B h f S C t f I diand the Green Bench of Supreme Court of India.

Noise pollution studies and mitigation measures inidentified zonesidentified zones.

Other environmental impact assessed during the EIA, e.g.Water Bodies etc considered for engineering planningWater Bodies, etc., considered for engineering planningand mitigation measures.

ICMEA 2013  www.dfccil.org

Page 23: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

Unique Project Features(contd.)

Contracting StrategyFIDIC Yellow Book customized for Design-Buildgrailway infrastructure works.

Slice & Package System - enhanced competition.g y p

PQ followed by one/two stage bidding-Pre-Qualification followed by two stage bidding – EDFCy g gPre-Qualification followed by single stage bidding – WDFCEngagement of consultant through Quality-Cum-Cost-Based-System (QCBS)

New technology encouraged.Alternate technologies invited.

ICMEA 2013  www.dfccil.org

Page 24: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

Unique Project Features(contd.)

ExecutionFunctional independence to contractors tocomplete the project in time by

Proposing most optimal state of the art designs.

Adopt global standards.

Adopt globally prevalent construction methods withappropriate mix of human and machinery resources.

To protect the environment around the construction site.

Adopt energy efficient methods and equipmentAdopt energy efficient methods and equipment

ICMEA 2013  www.dfccil.org

Page 25: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

Unique Project Features(contd.)

Other FeaturesHigher MMD/SOD to result in high cost cargoHigher MMD/SOD to result in high cost cargotransportation, e.g. automobiles, white goods, etc.

M lti d l l i ti k t f l th f i d tMultimodal logistic parks to fuel growth of industryand trade.

Paradigm shift in O&M methodology as a modernbenchmark for railway networks.

ICMEA 2013  www.dfccil.org

Page 26: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

FUNDINGFUNDING ARRANGEMENTSARRANGEMENTS

ICMEA 2013  www.dfccil.org

Page 27: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

DFC - Funding Arrangement

• Project Completion Cost US$ 16 billion

D bt E it 2 1• Debt:Equity 2:1

• Loans (Commited) US$ 10.930 billion (2.725 billion - World Bank + 8.205 billion – JICA)a 8 05 b o J C )

• Loan Agreements Signed US$ 9.180 billion (975 million - World Bank + 8.205 billion – JICA)

• Loans under Approval US$ 1750 million (World Bank)

• Western Corridor JICA Funded

• Eastern Corridor World Bank (Ludhiana-Mughalsarai)GOI (Mughalsarai Sonnagara)GOI (Mughalsarai-Sonnagara)PPP (Sonnagar-Dankuni)

ICMEA 2013  www.dfccil.org

Page 28: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

PROJECTPROJECT UPDATESUPDATES

ICMEA 2013  www.dfccil.org

Page 29: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

Project Update

Over 94% land Acquisition completed under Railway Amendment Act, 2008.

All environmental and wildlife clearances in place.

Ci il C t t d d f 1000 t k l thCivil Contracts awarded for over 1000 route km length of corridor and works in progress.

Tenders for civil works for about 1250 km invited.

System contracts (Elect., Signalling & Telecom) also y ( , g g )invited.

Mechanised Maintenance Contracts also plannedMechanised Maintenance Contracts also planned.

ICMEA 2013  www.dfccil.org

Page 30: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

OPPORTUNITIESOPPORTUNITIES

ICMEA 2013  www.dfccil.org

Page 31: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

OPPORTUNITIES

Great opportunity for construction (equipment &hi ) d f t i i d tmachinery) and manufacturing industry.

Opportunities in public private partnership (PPP) inconstructionconstruction.Developing more economic zones on the pattern ofDMICDC.High capacity Rolling stock for DFC.Setting up of logistic parks.g gFreight Business.

ICMEA 2013  www.dfccil.org

Page 32: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

OPPORTUNITIES – Construction Machinery

Mechanized Construction for faster progress and qualityconstructionAutomated Mechanised & Concreting Machinery

Major Bridge constructionMajor Bridge constructiono Machinery for Deep Friction Piles and End Bearing Piles

o Under-water Piling – Self Propelled Gantrieso Under water Piling Self Propelled Gantries

Mechanised Track Laying

Cable / OHE layingCable / OHE laying .Mechanized Maintenance of Assets

ICMEA 2013  www.dfccil.org

Page 33: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

Concrete BatchingConcrete Batching Plant at Muthani

Casting Yard at Muthani

Batching Plant at Muthani

Page 34: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

THANK YOUTHANK YOU

Page 35: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

THANK YOUTHANK YOU

Page 36: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

HYDRAULIC RIGS FOR INSTALLATION OF WORKING PILES IN GUJARAT SECTION

Page 37: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

THANK YOUTHANK YOU

Page 38: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

PSC Box Girder Launching

ASSEMBLING OF NRS LAUNCHER

Page 39: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

PSC Box Girder Launching

LAUNCHING OF GIRDER

Page 40: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

Construction Machinery – Electrification Works

Mechanical Digging of Foundation by Auguringgg g g gMast Erection MachineCantilever FixingMechanised Concrete MixuresWiring TrainClipping, Stagger AdjustmentsMechanised Cleaning of InsulatorsRail Cum Road Vehicles, Tower WagonsThermal Imagining

Page 41: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

Construction Machinery – Electrification Works

Automated Concreting Train for foundation and mast errection works.

Page 42: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

Construction Machinery – Electrification Works

Mechanised unwinding and anchoring of catenary and contact wires.

Page 43: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

OPPORTUNITIES (Contd..)

Scheduled Procurements*

•Civil and Track Works 1250 route KM (Double Line)

• Electrification Works 2250 route KM (Double Line)

• Signalling & Telecom Works 2250 route KM (Double Line)

• Package Size Generally more than US$ 200 million

* Next one year

ICMEA 2013  www.dfccil.org

Page 44: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

ROADROADAHEADAHEAD

ICMEA 2013  www.dfccil.org

Page 45: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

ROAD AHEAD

Future Corridors

East – West Corridor (Kolkata–Mumbai) 2000 Kms.North-South Corridor (Delhi-Chennai) 2173 Kms.East Coast Corridor (Kharagpur-Vijayawada) 1100 Kms.Southern Corridor (Chennai-Goa) 890 Kms.

RITES are conducting this study to be completed by Dec 2014RITES are conducting this study, to be completed by Dec 2014.

ICMEA 2013  www.dfccil.org

Page 46: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

Delhi – Mumbai Industrial Corridor (DMIC) –An Added Feature

• Focus is on ensuring high impact

developments within 150km distance onHaryana DadriHaryana

developments within 150km distance on

either side of alignment of DFC

• Area under Project Influence is 14% and

Rajasthan Uttar Pradesh

population is 17% of the Country

• Total Population in the Project Influence

Area : 178Mn

GujaratMadhya Pradesh Area : 178Mn

• Total Workers in the Project Influence

Area: 70.56MnJ N P

Maharashtra

As per Census‐2001

DFC Alignment

J.N.Port

gEnd Terminal

Page 47: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying

Green Project

Cumulative GHG emissions over 30 years

EnvironmentalCarbon Footprints of Dedicated Freight Corridor

Eastern Corridor(1975 Billion Tonne-Km)

Western Corridor(3241 Billion Tonne-Km)

- 2.5 x - 6 x

116466

2.5 x 6 x

47.5

77

Source: Report on ‘Green House Gas Emission Reduction Analysis for DFC’ by Ernst & YoungGreen DFC - to save 457 million-tonne CO2 over 30 years period.

Page 48: By NEERAJ AGRAWAL...yMajor Bridge construction o Machinery for Deep Friction Piles and End Bearing Piles o Under -water Piling – Self Propelled Gantries yMechanised Track Laying