By KELLY JESSICA MCLAUGHLINufdcimages.uflib.ufl.edu/UF/E0/04/16/66/00001/mclaughlin_k.pdf · HVAC...
Transcript of By KELLY JESSICA MCLAUGHLINufdcimages.uflib.ufl.edu/UF/E0/04/16/66/00001/mclaughlin_k.pdf · HVAC...
1
DECISION MATRICES FOR HVAC SYSTEMS FOR FLORIDA PUBLIC SCHOOLS
By
KELLY JESSICA MCLAUGHLIN
A THESIS PRESENTED TO THE GRADUATE SCHOOL OF THE UNIVERSITY OF FLORIDA IN PARTIAL FULFILLMENT
OF THE REQUIREMENTS FOR THE DEGREE OF MASTER OF SCIENCE IN BUILDING CONSTRUCTION
UNIVERSITY OF FLORIDA
2010
2
© 2010 Kelly Jessica McLaughlin
3
To my family for their unconditional love and support
4
ACKNOWLEDGMENTS
I would like to thank my family for their support and encouragement. I would also
like to thank Dr. Paul Oppenheim for his guidance throughout this study.
5
TABLE OF CONTENTS page
ACKNOWLEDGMENTS .................................................................................................. 4
LIST OF TABLES ............................................................................................................ 7
LIST OF ABBREVIATIONS ........................................................................................... 10
ABSTRACT ................................................................................................................... 11
CHAPTER
1 INTRODUCTION .................................................................................................... 13
Background ............................................................................................................. 13 Objective of the Study ............................................................................................. 13 Limitations ............................................................................................................... 14
2 LITERATURE REVIEW .......................................................................................... 15
HVAC System Selection Process ........................................................................... 15 Selection Matrix ...................................................................................................... 16 Life Cycle Cost Analysis ......................................................................................... 19
3 METHODOLOGY ................................................................................................... 25
Introduction ............................................................................................................. 25 Selection of Decision Matrix Criteria ....................................................................... 25
Life Cycle Cost Criteria ..................................................................................... 26 Design Selection Criteria .................................................................................. 27
Organization of HVAC Systems .............................................................................. 28 Development of Decision Matrix ............................................................................. 29 Life Cycle Cost Analysis ......................................................................................... 31
First Costs ........................................................................................................ 33 Energy Costs .................................................................................................... 37 Maintenance Costs ........................................................................................... 39 Replacement Costs .......................................................................................... 40
Replacement of HVAC units ...................................................................... 40 Replacement of miscellaneous equipment ................................................ 40
Life Cycle Cost ................................................................................................. 41 Design Criteria Analysis .......................................................................................... 41
Required Space ................................................................................................ 41 Complexity ........................................................................................................ 42 Life of the Unit .................................................................................................. 42 Noise ................................................................................................................ 45
6
Temperature Control ........................................................................................ 46 Humidity Control ............................................................................................... 47
4 DATA ...................................................................................................................... 48
Cost Criteria ............................................................................................................ 48 First Costs ........................................................................................................ 48 Energy Costs .................................................................................................... 50 Maintenance Costs ........................................................................................... 53 Replacement Costs .......................................................................................... 54 Life Cycle Cost ................................................................................................. 56
Design Criteria ........................................................................................................ 59 Required Space ................................................................................................ 59 Complexity ........................................................................................................ 59 Life of the Unit .................................................................................................. 64 Noise ................................................................................................................ 64 Temperature Control ........................................................................................ 65
5 RESULTS ............................................................................................................... 69
DX and Chiller Systems .......................................................................................... 69 Air Distribution Systems .......................................................................................... 69
6 CONCLUSIONS ..................................................................................................... 71
7 RECOMMENDATIONS ........................................................................................... 72
APPENDIX
A INSTALLATION COSTS OF FLORIDA SCHOOLS ................................................ 73
B PRESENT VALUE CALCULATIONS ...................................................................... 75
Energy Costs .......................................................................................................... 75 Maintenance Costs ................................................................................................. 77 Replacement Costs ................................................................................................ 79
LIST OF REFERENCES ............................................................................................... 82
BIOGRAPHICAL SKETCH ............................................................................................ 84
7
LIST OF TABLES
Table page 2-1 Decision Matrix for the Comparison of HVAC Systems ...................................... 17
2-2 Decision matrix using both performance and numerical rating ........................... 18
2-3 Decision Matrix with Weight Factors ................................................................... 19
2-4 System selection matrix utilizing both qualitative and quantitative rating methods .............................................................................................................. 21
3-1 HVAC systems included in study ........................................................................ 29
3-3 Life cycle cost parameters .................................................................................. 31
3-2 Example of the proposed decision matrix displaying the color coding and ranking of systems .............................................................................................. 32
4-1 First costs of DX and Chiller units based off of actual supplier quotes ............... 48
4-2 First Cost of Air Distribution devices based off of actual supplier quotes ........... 49
4-3 General quotes of the installation costs of DX systems ...................................... 50
4-4 Summary and ranking of the first cost per ton for DX and Chiller systems ......... 51
4-5 Summary and ranking of the first cost per unit for Air Distribution systems ........ 51
4-6 Calculation of energy costs of DX units .............................................................. 52
4-7 Calculation of energy costs of Chiller systems ................................................... 52
4-8 Summary and ranking of energy costs for the DX and Chiller units .................... 54
4-9 Present value of the cost of maintenance over a 50 year building life ................ 54
4-10 Summary and ranking of unit maintenance costs ............................................... 54
4-11 Calculation of periodic unit replacement costs ................................................... 57
4-12 Calculation of miscellaneous equipment costs ................................................... 58
4-13 Summary and ranking of DX and Chiller replacement costs .............................. 58
4-14 Summary and ranking of Air Distribution replacement costs .............................. 58
4-19 Explanation of rating system for the required space criterion ............................. 59
8
4-15 Summary and ranking of the life cycle costs for the DX and Chiller units ........... 60
4-16 Summary and ranking of the life cycle costs for the Air Distribution systems ..... 60
4-17 Space characteristics for typical designs of DX and Chiller systems. ................. 61
4-18 Calculation of the amount of required space needed for DX and Chiller systems. ............................................................................................................. 62
4-20 Space characteristics of typical Air Distribution systems .................................... 63
4-21 Calculation of required space for Air Distribution systems. ................................. 63
4-22 Ranking of the complexity of the DX and Chiller systems .................................. 63
4-23 Ranking of the complexity of the Air Distribution systems .................................. 64
4-25 Potential sources of noise in classroom ............................................................. 65
4-24 Summary of sources examined in the determination of unit service life ............. 66
4-26 Rating of noise characteristics for HVAC systems .............................................. 67
4-27 Ranking of the Air Distribution systems’ ability to control temperature of the space .................................................................................................................. 68
5-1 Completed decision matrix for DX and Chiller systems ...................................... 70
5-2 Completed decision matrix for the Air Distribution systems ................................ 70
A-1 HVAC system component costs for two elementary schools in Pasco County Florida ................................................................................................................ 73
A-2 Total costs for the installation of an air cooled chiller system in Pasco County elementary schools ............................................................................................. 74
B-1 Summary of costs and rates used in the calculation of the total present value of unit energy costs ............................................................................................ 75
B-2 Calculation of total present value of unit energy cost ......................................... 75
B-3 Summary of costs and rates used in the calculation of the total present value of unit maintenance costs ................................................................................... 77
B-4 Calculation of the total present value of unit maintenance cost .......................... 77
9
B-5 Summary of costs and rates used in the calculation of the total present value of miscellaneous unit replacement costs ............................................................ 79
B-6 Calculation of the total present value of miscellaneous unit replacement costs . 79
10
LIST OF ABBREVIATIONS
AHU Air Handling Unit
ANSI American National Standards Institute
ASHRAE American Society of Heating, Refrigerating and Air-Conditioning Engineers
DX Direct Expansion Systems
CFM Cubic Feet per Minute
EER Energy Efficiency Ratio
EFLOH Equivalent Full Load operating hours
HVAC Heating, ventilating and air conditioning
LCC Life Cycle Cost
LCCA Life Cycle Cost Analysis
VAV Variable Air Volume
11
Abstract of Thesis Presented to the Graduate School of the University of Florida in Partial Fulfillment of the
Requirements for the Degree of Master of Science in Building Construction
DECISION MATRICES FOR HVAC SYSTEMS FOR FLORIDA PUBLIC SCHOOLS
By
Kelly Jessica McLaughlin
May 2010
Chair: Paul Oppenheim Cochair: Charles Kibert Major: Building Construction
The purpose of this research was to develop a decision matrix that would aid the
Florida Department of Education in the selection of the most appropriate and cost-
effective HVAC system for Florida public schools. A decision matrix was developed that
included the system selection criteria most pertinent to the needs of school facilities.
This matrix contained both life cycle cost and design criteria. A general life cycle cost
analysis was performed in order to determine the most cost effective HVAC system.
Methods were developed to rate the design criteria. The results of these calculations
were placed in the proposed decision matrix to compare the systems.
From the research conducted it was found that a general life cycle cost analysis of
HVAC systems was not possible to perform. The HVAC industry does not track system
costs on a general basis. As such, the costs used in the life cycle cost calculations were
for the HVAC units only.
The proposed decision matrix effectively presented the HVAC unit performance in
both the cost and design criteria categories. The rating scales developed allowed users
to identify the HVAC system that would best fit their needs. The proposed decision
12
matrix could also be adapted to meet the specific needs of individual school districts
throughout the State of Florida.
13
CHAPTER 1 INTRODUCTION
Background
Heating Ventilating and Air Conditioning (HVAC) systems are very complex and
require careful design considerations in order to provide a healthy, safe, and
comfortable environment for the building’s occupants. Each project has a unique set of
criteria that should be considered during the design phase in order to select the most
appropriate system for the building function. During the mechanical design phase, such
design criteria will be defined based upon the owner’s specific requirements and needs.
Once defined, engineers will examine the performance capabilities of various HVAC
systems in order to see if they meet these criteria. The systems that successfully meet
the desired criteria are the ones that are considered for implementation in the project.
Traditionally, the HVAC system with the least initial cost is the one selected for the
project. However, this may not be the most cost-effective option over the life of the
system. Other costs such as maintenance, energy use, and replacement costs should
be analyzed in order to get a true sense of the cost of the system over its entire useful
life.
Objective of the Study
This study has two objectives. First, a decision matrix will be proposed that may be
used to assist school board and project team members in the selection of HVAC
systems for new construction projects in Florida public schools. The decision matrix will
contain both design selection criteria and cost criteria. As design criteria and needs vary
by county throughout the state, the matrix will assist users in determining the most
appropriate and cost effective system for the given building in question. A scale will be
14
developed to rate the performance levels of each of the criteria in the matrix. Only the
systems that have the greatest potential to be implemented in educational facilities will
be analyzed in this study.
The second objective of this study is to complete the decision matrix for the given
systems in question. A general life cycle cost analysis will be performed on these
systems. Methods of evaluating and rating the design criteria will either be developed or
be based upon standard industry practices.
Limitations
The proposed selection matrix is not intended to provide a definitive selection for the
mechanical system of an educational facility. Its intention is to provide an accurate and
practical tool to aid designers and school district personnel in narrowing the choices for
the selection of the most cost effective and appropriate HVAC system for their facility.
As this is a general study, the recommendations produced within should not replace the
detailed life cycle cost analysis recommendations performed by engineers for a specific
facility.
15
CHAPTER 2 LITERATURE REVIEW
HVAC System Selection Process
HVAC systems are responsible for maintaining the desired environmental
conditions of a space. This includes the control of the temperature, humidity, air
movement, and quality of the air in the conditioned space (American Society of Heating,
Refrigerating and Air-Conditioning Engineers (ASHRAE) 2008). There is no one right
system for a building and often there will be multiple systems that meet the design
requirements of a project (Elovitz 2002). The selection of which HVAC system will be
implemented in a building is a critical decision. The responsibility of making this decision
falls upon the design engineer. They must select a system that will satisfy the building
program and design intent of the client (ASHRAE 2008). In order to achieve this, the
design engineer should make a family of decisions that are based upon the
performance of a wide range of criteria (Elovitz 2002).
Criteria can be classified as either gating criteria or comparative criteria. Gating
criteria are those that may be answered with a “yes” or a “no” (Elovitz 2002). These are
aspects that the system in consideration will either meet or not meet. If the system in
consideration does not meet the gating criteria, it cannot be considered for the project
unless the owner changes their criteria (Elovitz 2002). Examples of gating criteria
include system performance, capacity, and spatial requirements. There are also many
requirements that cannot be answered with a simple “yes” or “no” response. Such
criteria is comparative and involves tradeoffs (Elovitz 2002). Comparative selection
criteria include first costs, operating costs, reliability, flexibility, and maintainability.
16
For a system selection to be successful, the criteria taken into consideration
should be reflective of the priorities and goals of the owner. These project specific
parameters should be included in the system analysis along with the basic design
constraints (ASHRAE 2008). The design engineer should collaborate with the owner to
identify and organize these criteria. With the desired design goals outlined, the design
engineer must next determine the constraints on the system. System constraints may
include the performance limitations, available capacity, available space, and available
infrastructure of a building (ASHRAE 2008). It should also include the constructability
constraints of the system such as the construction schedule and the ability to phase the
installation of the HVAC system (ASHRAE 2008). Ultimately the goal of the HVAC
system selection process is to narrow down the many choices of HVAC systems to
those that will work and those that will not work for a given project in order to find the
best system for the building (Elovitz 2002).
Selection Matrix
As a means of narrowing the choices of mechanical systems, the designer may
utilize a selection matrix. This matrix should present the advantages and disadvantages
of each of the systems considered for a particular project (Elovitz 2002). The use of
such a tool also allows for owner participation in the selection of the HVAC system
(Oppenheim 1992). It “forces the decision makers to assess what is important to them
for a successful outcome (Janis and Tao 2009).” A grading system should be applied to
the matrix in order to obtain an analytical analysis of the systems in question (ASHRAE
2008). The American Society of Heating, Refrigerating, and Air-Conditioning Engineers
or ASHRAE (2008) suggests two methods of analysis. First, systems may be rated on
their criteria performance levels with descriptive words such as poor, fair, good, and
17
excellent. Second, a numerical method may be used to rate the systems. This allows for
a quantitative result where the system with the highest value is that which is selected.
An advantage with the numerical rating method is that weighted multipliers may be
factored into some of the criteria if not all of the criteria carry the same weighted values
(ASHRAE 2008).
As with potential systems, there are numerous ways of evaluating selection criteria
during the design process. There is also no one right way of presenting the results of
the selection study (Elovitz 2002). Oppenheim (1992) presents a simple decision matrix
for the comparison of systems which can be seen in Table 2-1.
Table 2-1. Decision Matrix for the Comparison of HVAC Systems; Adapted from Oppenheim, P. (1992). “A Decision Matrix for Selection of Climate Control Equipment.” National Association of Industrial Technology, 8(4), 42-46.
Decision parameters
Examples of system options
Central four pipe system
Air source heat pump
Water source heat pump PTAC
Costs
First cost Maintenance cost Energy cost Operating cost Life expectancy
Operation
Noise Partial operation Humidity control Varying loads
Other Future needs Space requirements Structural impact
This matrix allows for the comparison of multiple systems based upon system costs,
operation, and other design parameters. These parameters are grouped together for
18
easy comparison amongst the systems in question. A specific grading system is not
outlined for use with this matrix, however, a qualitative or quantitative rating method
could be applied. Ottaviano (1993) uses both the performance and numerical rating
methods in his proposed matrix seen in Table 2-2. He associates a performance level
with a number. A “1” indicates that a system has a poor performance level for the given
criteria. Accordingly a “2” represents fair performance, a “3” represents good
performance, and a “4” represents excellent performance.
Table 2-2. Decision matrix using both performance and numerical rating. The table occurs as is in the original reference without any data in it. Adapted from Ottaviano, V. B. (1993). National Mechanical Estimator. The Fairmont Press, Lilburn, GA.
System number
Rating factors 1 2 3 4 5 6 7 8 9 10 11 12
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Ratings 4 - Excellent 3 - Good 2 - Fair
1 - Poor
19
Table 2-3 provides an example of how weighting factors may be applied to the
decision matrix. Each of the criteria is assigned a weight based upon the perceived
importance to the client (Janis and Tao 2009). The systems are then scored on a scale
of one to ten for their criteria performance levels. These scores are multiplied by the
weight factor in order to determine the weighted score. The weighted scores for the
selection criteria are summed in order to determine the system with the highest score.
A more complex selection matrix is presented by Elovitz (2002) in Table 2-4. This
matrix uses a combination of qualitative and quantitative rating methods. A key feature
of this matrix is that summary information for some of the criteria is listed in the table.
For example, the Floorspace design criteria which falls under Space Considerations
lists the equipment that takes up floor space in the table. This form of selection matrix is
an effective way of summarizing a lot of information for comparison.
Life Cycle Cost Analysis
Once potential mechanical systems have been narrowed to those that will satisfy
the owner’s requirements, the systems will be analyzed in order to determine which
would be the most economic option. There are two economic methods commonly used
to evaluate system selection: simple payback period and life cycle cost analysis. The
method of simple payback determines the time period it will take to recoup the initial
cost of implementing a more efficient system through recurring savings in energy (Janis
and Tao 2009). This payback period is determined by dividing the initial extra cost of the
system by the annual difference in operating cost. The system with the shortest
payback period will be the one selected. However, this method does not take into
account all of the associated costs of owning and operating an HVAC system.
20
Table 2-3. Decision Matrix with Weight Factors. Adapted from Janis, R. R. and Tao, W. K. Y. (2009). “Mechanical and Electrical Systems in Buildings.”
VAV reheat VAV/Dual duct Multizone Fan-coils
Score Weighted Score Weighted Score Weighted Score Weighted
Criteria Weight Comfort 8 5 40 5 40 5 40 7 56 Flexibility 6 10 60 8 48 1 6 7 42 Initial cost 3 10 30 6 18 4 12 6 18 Energy consumption 6 7 42 7 42 7 42 9 54 Ease of maintenance 6 7 42 9 54 10 60 5 30 Longevity 6 9 54 9 54 9 54 5 30 Acoustics 5 8 40 8 40 8 40 5 25 Total score
308
296
254
255
% score (normalized)
100%
96%
82%
83%
Grade
A+
B
C
C
21
Table 2-4. System selection matrix utilizing both qualitative and quantitative rating methods. Adapted from: Elovitz, D. M. (2002). "Selecting the right HVAC system." ASHRAE Journal, 44(1), 24-30.
Heat pump VAV with fan boxes Multiple rooftops Fan-coils Central / Increments
Comfort Considerations
Control options Can be flexible Highly flexible Limited Limited Can be flexible Control type On/Off Modulating On/Off Modulating On/Off Noise Noticeable Quiet Quiet Quiet Note 1 Ventilation Limited Very Good Good Limited Note 2 Overhead heat Yes Yes Yes Note 3 No Glass height Limited Limited Limited Note 3 Above unit only Filtration Low Good Good Low Good/Low
Effect of failure Total local Partial everywhere Total local Either note 4 Either note 5
Space considerations
Floorspace Boiler, pumps, storage tank, MUAU shaft
Shafts, boiler if gas heat Many shafts
MUAU shaft, pumps Shafts
Plenum space Least Medium Medium Least Medium Furniture placement Fully flexible Fully flexible Fully flexible Note 6 Least flexible Maintenance access Above ceiling On roof On roof Note 7 In rooms
Roofscape MUAU, cooling tower One or two large RTUs
Many smaller RTUS
MUAU, maybe chiller Several RTUs
First Costs System cost Depending on Job and Contractor Specifics, Any of These Systems Can be Competitive Cost to add zones Moderate Low Very High Low High Ability to increase capacity Expensive Inexpensive Expensive Inexpensive Expensive
Smoke control Separate system Adaptable Separate system Separate system Adaptable
22
Table 2-4. Continued
Heat Pump VAV with fan
boxes Multiple rooftops Fan-coils Central / Increments
Operating cost Energy cost 1 = Highest and 5 = lowest cost Gas 3 2 4 2 4
Electric 3 4 5 4 5
Maintenance cost Moderate Low High Low High
Free cooling Adaptable Inherent Available Adaptable Available Heat recovery Inherent Inherent None Adaptable None
23
Other costs that occur over the life of the system, such as operating, maintenance,
and replacement costs, are hard to financially ignore. A life cycle cost analysis (LCCA)
should be performed in order to determine which is the most cost effective option over
the life of the building. Such a method of analysis compares the cumulative costs
incurred over the life of the system from implementation through operating, maintaining
and eventually replacement (American Society of Heating, Refrigerating and Air-
Conditioning Engineers (ASHRAE) 2007). The life cycle cost method is effective in
evaluating the building design alternatives that satisfy a required level of performance
but may have different initial and annual costs (Fuller and Peterson 1996).
The life cycle cost for a building system is calculated by discounting future costs
back to a present value equivalent. Only those costs that are relevant and significant to
the decision need to be included in the life cycle cost analysis. Costs are considered to
be significant when they are large enough to affect the life cycle cost of a project
alternative (Fuller and Peterson 1996). Once these significant costs have been
identified, cost data must be obtained in order to compute the life cycle cost analysis.
The initial first costs for a project are the easiest to obtain since they occur in the
present (Fuller and Peterson 1996). First cost data may be obtained from suppliers and
manufacturers or construction cost estimating guides. Replacement costs may be
estimated by assuming the future costs are equivalent to the initial costs (Fuller and
Peterson 1996). These future costs are then converted into a present value. The
estimation of energy costs requires the calculation of the fuel used by the system.
Computer simulations may be used to estimate a building’s annual energy usage. The
annual energy costs are then obtained by multiplying energy usage and energy prices.
24
The maintenance and repair costs of a system are more difficult to estimate than other
system expenditures due to varying operating schedules and standards (Fuller and
Peterson 1996). It is therefore important to use engineering judgment in the estimation
of these costs. Maintenance cost may occur consistently on an annual basis or they
may change at some estimated rate per year (Fuller and Peterson 1996). They may be
computed from cost estimating guides or obtained from direct quotes from contractors
and vendors.
Florida Statutes. According to Section 1013.37(1)(e) of the Florida Statutes, a life
cycle cost analysis shall be performed for new educational facility construction projects
with a total air conditioning load of 360,000 BTUs per hour (30 tons) or greater (Florida
Department of Education (FLDOE) 2003). In this LCCA, at least three schemes of
HVAC systems shall be analyzed. Of these three schemes, one is required to be a
central system (FLDOE 2003). The Life Cycle Cost Guidelines for Materials and
Building Systems for Florida’s Public Educational Facilities report produced by the
Florida Department of Education (1999) lists the possible HVAC system types that may
be considered in the analysis. This report only describes the characteristics of potential
HVAC systems and does not provide any costing information. The system type with the
lowest life cycle cost will be the system that is installed in the new facility (FLDOE
2003). However, if any system alternatives are within four percent of the lowest life
cycle cost, the school district may make the final system selection from the systems that
fall within that range (FLDOE 2003).
25
CHAPTER 3 METHODOLOGY
Introduction
There are many different types of HVAC systems that may be utilized in the
construction of Florida public educational facilities. The selection of the mechanical
system to be used is a critical decision and requires the consideration of many different
aspects. The designer must work with the school district to select the most appropriate
system that will fulfill both the owner’s requirements as well as meet all associated
building codes. In order to do this, a wide variety of design criteria should be taken into
account during the design process. An effective way of presenting this information for
the comparison of different HVAC systems is through the use of a selection matrix.
The first objective of this thesis was to develop a decision matrix that can be used
as a tool to assist school board and project team members in the selection of HVAC
systems for the construction of new public educational facilities in Florida. In order to
provide an effective tool, the characteristics of the State of Florida needed to be
considered and understood. Florida is a large state that is comprised of varying sized
counties. Accordingly, school districts are also various sizes. Some counties are located
along the coast while others are located further inland. Some counties are rural, while
other locations have large population centers. Finally, educational facilities vary in size
throughout the state. Elementary and middle schools are a different size than high
schools.
Selection of Decision Matrix Criteria
The first step in the process of developing a decision matrix was to determine
which system selection criteria should be used. The criteria selected should reflect both
26
cost and design parameters in order to provide an effective means for the selection of
the most appropriate and cost effective HVAC system. The following are the criteria that
were selected for use in the decision matrix.
Life Cycle Cost Criteria
The associated costs of a system over its useful life are key factors in the selection
process. Florida Statutes require that a life cycle cost analysis be performed on at least
three different HVAC system types as part of the selection process. As such, the
associated costs that comprise the life cycle cost of a system should be included in the
decision matrix. The major categories of the costs that occur over the life of an HVAC
system are First Cost, Energy Cost, Maintenance Cost, and Replacement Cost. These
cost criteria are defined as follows:
First Cost. This is the initial capital cost of materials and installation of an HVAC
system.
Energy Cost. These are the costs associated with running the HVAC equipment
on a day to day basis. This includes the electricity cost to operate a system during
regular and demand hours.
Maintenance Cost. This is the cost associated with performing regular
preventative maintenance on the system so that it will perform at its optimal level. Such
tasks include changing filters and cleaning coils.
Replacement Cost. This is the cost associated with replacing any of the
equipment associated with an HVAC system over the useful life of a building. It includes
the costs to replace the unit at the end of its life as well as the costs to replace any
miscellaneous equipment throughout the life of the unit.
27
Life Cycle Cost. This is the cost of the system over its entire useful life. It includes
the system’s first cost, yearly energy and operating cost, yearly maintenance cost, and
replacement costs. The annual costs were converted to a present value in order to
compare system costs.
Design Selection Criteria
Costs are not the only criteria that need to be considered in the selection process.
Project specific parameters dictated by the owner’s needs should also be considered.
There are a wide variety of design criteria that may be analyzed during the selection
process. The needs of educational facilities were considered during the selection of
these parameters. The following factors, denoted as “Other” criteria, were determined to
be most relevant project specific parameters for Florida educational facilities.
Life of the Unit. This is the average useful life of an HVAC unit. The useful life of
a unit will dictate how many times it needs to be replaced over the life of a building
which can affect the life cycle cost of a system.
Required Space. This is the space needed to house the HVAC system. This
includes the footprint of the unit as well as any mechanical rooms needed to house any
associated ductwork and piping in the system. The required space of the system needs
to be accounted for in the design of the facility because some smaller building footprints
might not be able to support a large system.
Complexity of the System. This is the technological sophistication of a system.
This should be considered during the design phase as some counties may not be able
to support sophisticated systems. Location may limit the availability of qualified
maintenance and service personnel needed to maintain the system.
28
Noise. This reflects how much noise the system generates during operation. The
noise produced by a system is relevant to quality of the learning environment and will
also dictate design requirements. Acceptable sound levels in classrooms is critical for a
proper learning environment (ASHRAE 2007). The American National Standards
Institute (ANSI) Standard S12.60.2002 requires a maximum background sound level of
35 dB in classrooms (Siebein and Lilkendey 2004).
Temperature Control. This is the level of control the system has in maintaining
the desired air temperature of the conditioned space. This can affect the comfort level
experienced by the room’s occupants.
Humidity Control. How well the system can control and regulate the humidity
within the conditioned space. This parameter needs to be addressed in order to
maintain a proper level of air quality in the conditioned space.
Organization of HVAC Systems
The next step in the process of developing a selection matrix was to determine
which HVAC systems to analyze in the study. The 1999 edition of the Life Cycle Cost
Guidelines report produced by the Florida Department of Education was used as a
starting point in this process. Part 3 of this report outlines the systems that have been
implemented in Florida public schools. This list was analyzed and any outdated
configurations were discarded as options for use in this study. Any systems that were
similar in nature were combined. Systems not included in the 1999 report but with
potential to be implemented in educational facilities were included in the study. A list of
the systems that were analyzed in the study can be seen in Table 3-1.
With the HVAC systems in consideration defined, they were then grouped into
sections of similar system types to better allow for the comparison of the associated life
29
cycle costs and decision criteria. Direct Expansion or DX systems were analyzed first.
These types of systems are decentralized and are often suitable for smaller projects.
This section was followed by Chiller systems. Chillers are centralized systems and are
often used for larger facilities. Finally, Air Distribution systems were analyzed. These
systems use various methods to distribute air throughout the conditioned space and can
be used with DX and Chiller systems.
Table 3-1. HVAC systems included in study System classification Unit type DX systems Wall-mounted unit Package rooftop Split systems Water loop heat pump Geothermal heat pump Chiller systems Air cooled chiller Water cooled chiller Air Distribution systems Constant volume Variable air volume (VAV)
Fan-coil units
Development of Decision Matrix
With the decision criteria defined and the systems classified, the next step was to
create a matrix that would effectively display the information. Features of the selection
matrices presented in the literature review were combined to create a matrix that was
appropriate for the intended application. The selection criteria categories of Costs and
Other were clearly outlined for easy reference.
A method of rating the performance of the selection criteria was developed in
order to rate the HVAC systems in question. A combination of numerical ranking and
color coding was used to compare the performance levels of the system selection
criteria. The number scale was used to rank the performance of the unit types within
each selection criteria category. For each criterion, the unit types were numerically
30
ranked according to the number of systems in each system classification. For this study,
the DX and Chiller systems were combined into one system classification. These units
are the primary sources of conditioned air. By grouping them into one system
classification allowed these HVAC units to be compared against each other. The Air
Distribution systems were ranked in a separate system classification. These systems
are methods of distributing conditioned air and are therefore not directly comparable
with the DX and Chiller systems. A ranking of “1” denoted the best option for a given
criterion. For example, in the DX and Chiller system classification there were seven
systems being analyzed. Each Cost and Other criterion was ranked on a scale from “1”
to “7”. A ranking of “1” denoted the best unit type for the criteria in question. A tie within
this scale indicated that a significant difference between systems could not be
discerned. Weight factors were not used in this scale as the owner’s requirements will
vary. However, the owner may apply a weight factor to this scale for use in the selection
of equipment if they desire.
The color scale rated the units within each system classification over a range of
performance levels. This scale varied for each of the criteria in question and will be
described in the Data Chapter. The color coding was used to categorize each criterion
into three levels. Each level was represented by a different color: green, orange, or red.
For the Cost criteria, low costs were represented by green, moderate costs were
represented by orange, and high costs were represented by red. Each cost criterion had
different cost ranges. Therefore, the color coding scale for each cost criterion was
determined based on the range of the data collected. For the Other criteria the color
green signified that a system exceeded average performance levels for the given
31
criteria. Orange represented an adequate performance by the system for the given
criteria. Finally, red indicated that a system performed below average performance
levels. These levels applied on an overall basis. An example of both the numerical
ranking and color coding can be seen in Table 3-2.
Life Cycle Cost Analysis
The second objective of this thesis was to complete the decision matrix for the
HVAC systems in question. A general life cycle cost analysis was performed in order to
fill in the cost portion of the decision matrix. Data for this analysis was collected from a
variety of sources. School districts, general contractors, mechanical contractors, and
engineers were consulted for cost data. Once collected, any future costs were
converted into a present value. Table 3-3 shows the life cycle cost parameters that were
used in the computation of the present value of the system costs.
Table 3-3. Life cycle cost parameters Life cycle cost parameter Value Building service life 50 years General inflation rate 2.0% Energy inflation rate 4.0% Non-energy discount rate 2.7% Energy discount rate 3.0%
The present value of future costs were computed using Equation 3-1. For costs
that occur on an annual basis, such as energy and maintenance costs, this equation
was used to compute the present value of the annual cost for each year over the life of
the building. The present value of each year was then summed to get the total present
value for such an annual cost. For costs that occur periodically throughout the life of the
building, such as unit replacement costs, this equation was used to compute the present
32
Table 3-2. Example of the proposed decision matrix displaying the color coding and ranking of systems
Costs Other
Unit type First cost Energy cost
Maintenance cost
Replacement cost LCC
Required space Complexity
Life of unit Noise
Temperature control
Humidity control
System A 1 3 2 1 2 1 1 3 3 3 3 System B 2 2 1 2 1 2 3 2 2 2 2 System C 3 1 2 3 3 2 2 1 1 1 1
33
value for the year at which the cost was incurred. If multiple replacements occurred over
the life of the building, these were summed to get a total present value for the periodic
costs.
Equation 3-1
Where:
P = Present cost
F= Present value of future cost
i = Inflation rate
d= Discount rate
n = Number of periods
The following are descriptions of how the cost data was collected and converted
into a cost per ton for system comparison. Once the costs were in a similar units they
could be ranked according to the method described previously. Any future costs were
converted into a present value.
First Costs
Attempts were made to collect first cost data from manufacturers, engineers, RS
Means, and contractors. However, data was not obtained from all of these sources.
Major manufacturers of HVAC equipment do not produce information on the total
installation costs of mechanical systems. The Trane Company (1991) previously
published the Systems Manual which gave general costing information for different
types of systems in different types of building. A copy of this publication was able to be
obtained, however it was over 15 years old and therefore outdated. The engineers
consulted during the study recommended using RS Means to obtain material and
34
installation costs. RS Means CostWorks (2010) was consulted for data to be used as a
comparison of quotes received from contractors.
Local mechanical contractors were contacted in order to receive pricing quotes. It
was found that these contractors did not maintain a database of approximate prices,
such as cost per square foot or cost per cost per ton, for HVAC systems. This is due to
the uniqueness of each mechanical system. Given this situation, the best way to obtain
first costs was found to be by reviewing actual pricing quotes on pieces of equipment
from manufacturers. These manufacturer quotes only included the cost to furnish the
equipment. Installation costs were not included in these prices. Many of the quotes
reviewed contained multiple pieces of equipment, however only lump sum prices were
listed. This made it difficult to extract the actual costs of the equipment. The
manufacturer quotes that were able to be used to compute the cost per ton of
equipment are considered to be proprietary information. As such, they cannot be printed
in this study. In order to get costs, the total value of the equipment was divided by the
tonnage of the system it was serving. This gave a cost per ton for the piece of
equipment.
It was not possible to obtain a large sample of quotes for each of the systems in
question. Where multiple quotes were available, the costs were averaged. This average
cost was used as the first cost for the material of the unit. However installation costs for
the unit needed to be calculated. The daily labor output found in RS Means CostWorks
(2010) was used in the computation of the installation cost of the unit. Equation 3-2 was
used to calculate the total installation cost of the unit. It was assumed that the hourly
35
labor rate for an installation crew was $75.00/hr. For an eight hour work day this
equated to a $600/day labor rate.
Equation 3-2
The total labor cost of the unit was divided by the approximate unit tonnage to get the
labor cost per ton. The unit material cost per ton determined from the supplier quotes
was added to the labor cost per ton to get the total first cost per ton for the unit. These
costs were compared to the costs found in RS Means CostWorks (2010) in order to
determine if this was a reliable source for costing information. It was found that the
material costs of the units in RS Means were not comparable to the costs of the supplier
quotes.
For the systems where no supplier costing information was able to be obtained,
the first costs for the systems were based off of general quotes obtained from one of the
mechanical contractors that was contacted during the study. Their quotes included the
costs to furnish and install the unit.
For the DX Systems and Chiller Systems the first costs only included the cost per
ton to furnish and install the HVAC unit itself. The costs of ductwork or means of
distributing air were not included in these systems’ first costs. The first costs for the
methods of distributing air were included in the Air Distribution System section. This was
done since the methods of distributing air may be applied to any one of the HVAC units
in question. For the Air Distribution systems, the costs were done on a cost per unit
basis rather than a cost per ton basis. This was done since different quantities of VAV
boxes and Fan-Coil units will be used for different systems. It was also assumed that
the Constant Volume method of air distribution was the baseline cost for all air
36
distribution systems. As such, its first cost was considered to be zero. Ductwork is
needed to supply air to the conditioned space in all of the methods of air distribution.
For similar sized systems the ductwork to supply the air should be relatively the same
size. The only cost difference will come from the air terminal units.
The first costs presented only included the cost to furnish and install the
equipment. Tax, overhead, and markups were not included in these costs. Since school
districts are public entities, they are eligible for the Direct Purchase Program. This
program allows the school district to purchase the materials for the project tax free from
suppliers. The first costs of the systems that were obtained did not need to be converted
because they were already in present value form.
Costs of systems installed in Florida public schools. An attempt was also
made to collect the actual HVAC system costing information for schools that have been
recently built in the State of Florida. However, costing information for only two
elementary schools in Pasco County Florida was able to be obtained. These costs were
the actual prices that were paid by the state for construction of the school. Both of the
elementary schools had an air cooled chilled water system with Variable Air Volume
(VAV) boxes in place. This allowed for the approximate comparison of prices for this
type of system. The prices that were able to be obtained included:
• Cost to purchase the chillers • Cost to purchase the air distribution system • Total material costs (through the Direct Purchase Program) • Total mechanical contractor costs • Total building Costs
The total square footage of the school and tonnage of the chillers were also
obtained for the schools in question. With this data, the cost per ton for the chillers was
37
able to be calculated. Both the total material costs and the total fees for the mechanical
contractor were divided by the tonnage of the system to get an approximate cost per
ton. The total material costs were compared to the total mechanical contractor costs to
get an approximate percentage of the material costs to the costs for installation of the
system as a whole. A percentage difference was also calculated between the total cost
for the mechanical system (summation of the material and contractor costs) and the
total building cost. Since the costing information for only a few schools was able to be
obtained and it was for only one of the systems in question, this data was not able to be
used in the life cycle cost analysis. The costing information for these schools may be
found in Appendix A.
Energy Costs
Energy costs for the systems were computed by doing approximate hand
calculations. More detailed energy calculations may be obtained for a system through
the use of computerized energy models. However, such programs require the input of a
design of a building. Since this is a general study and no set building design was being
used, an energy model was not used to calculate the energy consumption of the HVAC
units. The computed annual energy costs were converted to a present value using
Equation 3-1. Water consumption charges were not included in this study.
The energy consumption costs for the HVAC units were computed by using the
recommended system efficiency rate given by the U.S. Department of Energy’s website.
These efficiency rates are greater than the base rates that are dictated by ASHRAE
Standard 90.1 but they are not the most efficient options available on the market
(USDOE 2008). For DX systems, the efficiency was given in terms of an energy
efficiency ratio (EER). The EER was converted into kW per ton by Equation 3-3.
38
Equation 3-3
The amount of hours that the system operates during the year needed to be
obtained to compute the energy costs. Systems do not always operate at their full load
throughout the entire year. Full load operation is only needed during the time of the year
where peak building cooling loads are experienced. Systems normally operate at partial
load levels throughout the majority of a year. These partial operating loads may be
converted into an equivalent number of hours that the system would have run if it only
operated at its full load. This number of hours is known as the equivalent full load
operating hours (EFLOH). The EFLOH can then be used to calculate system energy
costs. The actual equivalent full load operating hours for a system will vary based on the
overall design of the school and the school’s cooling and heating demands. The EFLOH
for a particular system design may be obtained by running energy modeling programs.
The value obtained will be a constant for the particular school design and will be used to
compute the energy costs for any systems that are considered for installation. For this
study, it was assumed that the EFLOH was 2000 hours as there was no set school
design. Assuming the equivalent full load operating hours allowed for the relative
magnitude of unit electricity costs to be established.
The cost of electricity used was $0.15/kWh. This is the average rate of electricity
for Gainesville, Florida and includes demand charges. The annual energy costs of the
systems were calculated using Equation 3-4.
Equation 3-4
39
Energy costs were only computed for the HVAC units themselves. All other associated
equipment was neglected for this study. Equipment such as pumps, air handlers, or
cooling towers will consume electricity. However, the number and size of such
equipment will be dependent on the system design.
Energy costs for the air distribution systems were not calculated for this study. The
methods used to distribute air can affect the amount of energy used by the HVAC unit
however, exact costs are design dependent and would need to be calculated through
the use of a computer energy model. In general, the method of VAV can reduce energy
costs from 10% to 20% over constant volume systems (USDOE). This is because the
VAV box varies the amount of air that is supplied to a space. This leads to reduced
costs to operate the fans in the system.
Maintenance Costs
Maintenance costs were obtained by receiving general quotes from a mechanical
contractor in the Gainesville area that performs regular maintenance services for local
schools. These quotes were reflective of the costs to perform regular preventative
maintenance. Such maintenance includes changing filters, lubricating bearings and
motors, and inspecting all equipment and controls. These quotes were based on the
contractor’s experience and were reflective of an approximate cost without a system
design. Maintenance costs will vary based on the quantity and type of equipment, the
equipment location and access, system complexity, and whether the units are located in
a harsh environment (ASHRAE 2007). This annual cost was converted to a present
value using Equation 3-1. Maintenance Costs were not available for the Air Distribution
Systems category. According to the quotes received from the mechanical contractors,
40
typical maintenance contracts do not include regular servicing of the devices employed
to distribute air.
Replacement Costs
The replacement costs were divided into the costs to replace the HVAC unit at
the end of its useful life and the costs to replace miscellaneous equipment over the life
of the HVAC unit. These two costs were totaled in order to determine the total present
value of the unit replacement costs.
Replacement of HVAC units
The cost to replace an HVAC unit would only include the price of the unit and the
labor to install it. Thus, the replacement costs for the units were assumed to be the
same price as the first costs of the units. These costs would occur at the end of the
useful service life of the unit. The year(s) of replacement was determined based upon
the life of the unit which is discussed in the Design Criteria Analysis section. For Air
Distribution Systems, it was assumed that the associated ductwork and grilles would not
be replaced during the life of the building. However, the VAV boxes and Fan-Coil units
would need to be replaced over the life of the building. These were the only costs
associated with the replacement of the Air Distribution Systems. The replacement costs
of HVAC units are periodic costs and were converted into a present value using
Equation 3-1.
Replacement of miscellaneous equipment
The costs to replace miscellaneous system equipment reflects the costs to
replace equipment that is needed in order for the HVAC system to work, but is not
critical enough to cause the unit to be replaced. These costs are difficult to predict. For
this study it was assumed that the cost to replace miscellaneous equipment was 6% of
41
the system first cost. This is an annual cost over the life of the unit except for the first
year after installation. The contractor and/or manufacturer will normally provide the first
year’s parts and labor warranty.
Life Cycle Cost
The life cycle cost was determined by summing the present worth values of the
first costs, energy costs, maintenance costs, and replacement costs. The HVAC unit
types in the DX and Chiller system classification and the Air Distribution system
classification were then ranked according to the scale described previously.
Design Criteria Analysis
The design criteria were evaluated by either developing simple rating methods or
by using standard industry practices. The following are descriptions of how the design
criteria were collected and calculated.
Required Space
The required space of the system was based upon the size and location of major
system components. A rating method needed to be developed in order to allow for the
ranking of the systems. The DX and Chiller systems were analyzed separately from the
Air Distribution systems for this design criterion.
First, typical design layouts for the systems were examined, and their space
characteristics were summarized in a table. For the DX Systems and Chiller Systems,
the summary table listed the typical size of the unit, any associated equipment, the
placement of the unit and associated equipment, required piping, required ductwork,
and mechanical rooms needed. Approximate dimensions of HVAC units were found by
looking at manufacturer specifications of typical unit sizes. This summary table was
used to complete a rating table that was used to compute an average score for the
42
required space of the DX and Chiller systems. The systems were rated on the size of
the unit, the piping in the system, the mechanical room space required, and the outdoor
space required. These criteria were rated on a scale of one to three with one being the
least amount/space and three being the most. Exact descriptions of the rating criteria
are given in the Data chapter. An average value for each system was taken and the
systems were ranked according to these averages.
The summary table for the Air Distribution systems listed any associated
equipment, the approximate size of that equipment, the required piping, and the
equipment placed in the ceiling space. A unit size was not associated with this rating
since the air distribution methods may be applied to any one of the HVAC units. This
summary table was used to complete a rating table that was similar to the one used for
the DX and Chiller systems. The Air Distribution systems were rated on the amount of
piping needed and the amount of equipment located in the ceiling space. An average
value for each system was taken and the systems were ranked according to these
averages.
Complexity
The complexity of the system was based upon the number of major components
that needed to be installed and how many points of maintenance the system has. The
summary tables that were created in determining the required space of the systems
were referred to in the rating of the systems. Each characteristic was rated on a scale of
one to three and were then averaged in order to determine a ranking of the systems.
Life of the Unit
There is no exact science to predicting the useful life of an HVAC unit. Service life
will be dependent upon a number of factors that are hard to accurately predict. Among
43
these factors is how well the system is maintained throughout its life and whether the
unit is located in a corrosive environment (ASHRAE 2007). The 2007 ASHRAE
Applications Handbook provides a table of median service life for mechanical
equipment. This table lists the estimated service life for various HVAC system
components that was based upon a 1978 ASHRAE funded research project by Akalin.
However, ASHRAE warns that these estimates may be outdated due to changes in
technology, materials, manufacturing techniques, and maintenance practices (ASHRAE
2007). As such, ASHRAE funded a project to develop an internet database to collect
HVAC equipment service life which was based on the findings of Abramson et al.
(2005). From these findings, survival curves were able to be created giving the median
service life for the HVAC equipment. These curves reflect the units still in service for a
given age and the units that are replaced at each age (ASHRAE 2007). The median
service life indicates the highest age that the survival rate stays at or above 50% while
the sample size is 30 or greater. At the time of this study, there was not enough data to
create accurate survival curves for all of the equipment in consideration.
The estimated service life for HVAC equipment was analyzed in a variety of ways
for this study. The findings of the methods tried during the study are summarized in
Chapter 4. First, a literature review was conducted in order to determine the estimated
service life recommended in HVAC design references. Through the literature review, it
was found that service life was generally given in a range of years. Also, most of the
available HVAC design references were over fifteen years old (Colen 1990; Ottaviano
1993; Akalin 1978). As stated previously, these estimates may be outdated and not
accurately reflect the mean service life of equipment.
44
Next, the internet database created from Abramson et al.’s (2005) findings was
examined for potential use in the estimation of median service life (ASHRAE 2010). The
database allows users to search for equipment through a variety of criteria. Among
these criteria are system type, building type, and state. A search was conducted to
determine if there was equipment service life information for schools from the State of
Florida. This search returned zero matches. Another search was conducted to
determine how many pieces of equipment from the State of Florida were available in the
database. This search returned 1470 equipment matches. From there a search on the
pieces of equipment in schools was conducted which returned 3,620. Individual
equipment types were analyzed to determine the available data. It was found that the
differences on the available data for each type of equipment varied significantly in total
pieces of equipment and location. It was concluded that statistically accurate median
service life data could not be extracted for the means of this study from this database
because of these differences.
The mechanical contractors that were asked to provide cost quotes were also
asked to provide an estimate on equipment service life for the study. However such
opinion based surveys produce age at replacement information (Hiller 2000).
Replacement of units can be for a number of reasons including failure, reduced
reliability, excessive maintenance costs, or changed system requirements (ASHRAE
2007). The age of replacement of units is different from the equipment service life (Hiller
2000).
Finally, the Median Service Life tables found in Chapter 36 of the 2007 ASHRAE
Handbook – HVAC Applications were analyzed. These tables listed the median service
45
life of equipment from the ASHRAE funded research projects by Akalin (1978) and
Abramson et al. (2005). The available median service life from Abramson’s (2005) study
was compared to the median service life given by Akalin (1978). It was found that most
of the differences were on the order of one to five years, with Abramson et al.’s findings
having the longer median service life (ASHRAE 2007). The result of Abramson et al.’s
(2005) findings was deemed to be the most accurate estimate of equipment service life
for this study since the results were based upon survival curves. However, at the time of
this study, there was not enough data available to create survival curves for all the
equipment in question. The median service life for the equipment that was available was
used as the life of the unit for this study. All other unit lives were taken from the
ASHRAE table. These median service life values were consistent with the other sources
examined and are the most credible source until more data is collected from the internet
database.
Noise
Noise generated by HVAC systems may be caused by a number of factors. Most
of these factors are determined by the design of the HVAC system. The HVAC units
generate noise during operation which may be transmitted to the space through the air,
walls, windows, doors, ductwork or ceilings (Siebein and Lilkendey 2004). Noise may
also be generated in the ductwork as air travels through it. There are a number or
methods that may be employed to reduce the noise generated by HVAC systems, but
they specifically pertain to the system’s design. ANSI Standards mandate that the
maximum background sound levels for classrooms be equal to 35 dB or less. The
design professional must take measures to reduce the noise generated by HVAC
system operation in order to meet the required background sound levels.
46
Since the noise heard in the classrooms is dependent upon system design and
this is a general study, the units were rated based on their potential to produce noise in
the classroom. This was done by analyzing the system components that generate noise
during operation and their relative location to the classroom. A summary table was
created to highlight the system noise characteristics. The summary table listed the
equipment located within the classroom space, equipment near the classroom space,
and any other potential sources of noise in the classroom. This summary table was then
used in the rating of the system’s potential to generate noise in the classroom. The
systems were rated on the sources of noise in the classroom, near the classroom, and
other potential noise. Each noise characteristic was rated from one to three with one
being no noise, two being a potential noise source, and three being a noise source. An
average value for each noise characteristic was taken and the systems were ranked
according to these averages.
Temperature Control
The comfort level in the conditioned space depends on the temperature and
humidity of the supply air, the velocity of the supply air as it leaves air terminals, and the
movement of air throughout the conditioned space. These are all factors that are
attributed to the design of a system as a whole. The individual HVAC units are
responsible for conditioning the air to the required temperature and humidity
specifications needed based on the cooling loads of the building. The units that are
installed are selected based upon these specifications. The process of regulating
temperature falls more under the method used to distribute the air throughout the
space. As such, only the Air Distribution systems were rated on their ability to control
the temperature of the conditioned space. The required space design criteria was
47
removed from the DX and Chiller system decision matrices since it is not applicable to
the units themselves. The Air Distribution systems were ranked according to their ability
to control the comfort level of multiple rooms throughout the conditioned space. This
was dependent on the thermostat control type.
Humidity Control
Humidity control is related to the amount of ventilation that is provided for the
conditioned space. ASHRAE Standards require that classrooms have a minimum of 15
cfm per person of ventilation (ASHRAE 2007). Ventilation is provided by supplying fresh
outdoor air to the space in order to remove indoor air pollutants generated by the room’s
occupants. Schools have a high occupant density which in turn results in large volumes
of outdoor air having to be supplied to the conditioned space (Fischer and Bayer 2003).
Florida has a very humid climate and this can put strain on the HVAC system to
properly condition the large levels of required ventilation air. Conditioning large volumes
of ventilation air must be taken into account during the design on the HVAC system of a
building. Some systems may experience part load humidity build up during operation.
This occurs as the unit cycles on and off. The moisture that condenses on the coiling
coil during operation may evaporate back into the air stream when the coiling coil is
cycled off unless the condensate pan is correctly sloped and the condensate drains
properly from the pan. The full latent capability of the unit is realized when the cooling
coil reaches its design temperature.
Part load build up of humidity is dependent upon the design of the system as a
whole. For this general study, a method for rating the systems on their ability to remove
humidity in the space was unable to be created. As such, this design criterion was
removed from the decision matrix for all of the systems in question.
48
CHAPTER 4 DATA
The following is the data that was collected during the study in order to complete
the decision matrix presented in the previous chapter.
Cost Criteria
First Costs
Table 4-1 lists the cost per ton for DX and Chiller units that was able to be obtained
from looking at equipment quotes. This table also shows the computation of the
installation costs of the units. These labor costs were based on the daily output given in
RS Means. Equation 4-1 was used to calculate the total labor cost to install the unit.
Equation 4-1
Table 4-1. First costs of DX and Chiller units based off of actual supplier quotes
Unit material cost per ton
Daily output
Labor rate ($/day)
Total unit labor cost
Labor cost per ton
Total first cost per ton of the unit
Wall- mounted unit $ 1,065.00 4 $ 600.00 $ 150.00 $ 150.00 $ 1,215.00
Split system
$ 633.00
$ 838.00
$ 960.00
$ 810.33 0.5 $ 600.00 $ 1,200.00 $ 240.00 $ 1,050.33
Air cooled chillers
$ 454.00
$ 431.00
$ 442.50 0.21 $ 600.00 $ 2,857.14 $ 19.05 $ 461.55 Water cooled chiller $ 495.00 0.13 $ 600.00 $ 4,615.38 $ 30.77 $ 525.77
It was assumed that the hourly labor rate for an installation crew was $75.00/hr. For an
eight hour work day this equated to a $600/day labor rate. The total labor cost to install
49
the unit was divided by the approximate unit tonnage to get the labor cost per ton. The
material cost per ton determined from the supplier quotes was added to the labor cost
per ton to get the total first cost per ton for the unit.
Table 4-2 shows the calculations of the first cost per unit of the Air Distribution
devices. The unit material costs were obtained by looking at equipment quotes from
suppliers. The labor rate to install the units and the total unit first cost was calculated in
the same manner as the DX and Chiller units. The first costs for these system types
were done on a cost per unit basis rather than a cost per ton basis because different
quantities of VAV boxes and Fan-Coil units will be used for different systems. It was
assumed that the Constant Volume method of air distribution was the baseline cost for
all air distribution systems. As such, its first cost was considered to be zero. Ductwork is
needed to supply air to the conditioned space in all of the methods of air distribution.
For similar sized systems the ductwork to supply the air should be relatively the same
size. The only cost difference will come from the air terminal units.
4-2. First cost of Air Distribution devices based off of actual supplier quotes
Material cost per unit Daily output
Labor rate ($/day)
Total labor cost per unit
Total unit first cost
VAV
$ 630.00
$ 643.00
$ 746.00
$ 673.00 9.00 $ 600.00 $ 66.67 $ 739.67
Fan-coil $ 1,119.00
$ 1,437.00
$ 1,278.00 7.00 $ 600.00 $ 85.71 $1,363.71
50
Since not all of the first costs of the DX systems in the study were able to be
obtained from actual supplier quotes, Table 4-3 shows the quotes that were obtained
from a local mechanical contractor for a general estimate on the cost to furnish and
install DX units.
Table 4-3.General quotes of the installation costs of DX systems
Unit type First cost of units (5 ton) First cost per ton
DX Systems
Wall-mounted unit $5,000.00 $1,000.00 Enhanced Wall-mounted unit $7,400.00 $1,480.00 Package rooftop - electric $5,800.00 $1,160.00 Package rooftop -Gas $6,500.00 $1,300.00 Split systems $6,500.00 $1,300.00 Enhanced split system $7,800.00 $1,560.00 Water source heat pump $4,500.00 $900.00 Geothermal heat pump $6,200.00 $1,240.00
An enhanced unit is one that provides ventilation as well as conditioned air. For this
study, the cost of the basic unit was used.
Table 4-4 gives a summary and ranking of the first cost per ton of the DX and
Chiller systems that were used for this study. Table 4-5 gives a summary and ranking of
the first cost per unit for the Air Distribution systems. The first costs listed for these
systems were rounded to the nearest ten dollars of the calculated costs. This was due
to the accuracy that was able to be obtained from the data.
Energy Costs
Table 4-6 and Table 4-7 show the calculation of the unit energy costs over the life of the
building for the DX and Chiller systems. These costs only reflect the energy usage of
the units themselves. The energy usage of other associated equipment, such as air
handlers, pumps, or cooling towers, have been neglected in the calculations. These are
only estimated energy costs to show the relative magnitude of energy savings from
systems with a higher efficiency. Water consumption charges were not included in this
51
study. The energy costs of the Air Distribution systems were not calculated for this study
as they will be dependent upon the design of the school.
Table 4-4. Summary and ranking of the first cost per ton for DX and Chiller systems
Unit type
First cost ($/ton) Rank
DX systems
Wall-mounted unit $ 1,220.00 6
Package rooftop $ 1,160.00 5
Split system $ 1,050.00 4
Key
Water loop heat pump $ 900.00 3
$0 to $600
Geothermal heat pump $ 1,240.00 6
$601 to $1000
Chiller systems
Air cooled chiller $ 460.00 1
$1001 and up
Water cooled chiller $ 530.00 2
Table 4-5. Summary and ranking of the first cost per unit for Air Distribution systems
Unit type First cost ($/unit) Rank
Key
Air Distribution
systems
Constant volume $ - 1
$0 to $500
VAV box $ 790.00 2
$501 to $1000
Fan-coil unit $ 1,360.00 3
$1001 and up
The unit efficiency rates used in the calculations were taken from the U.S.
Department of Energy’s website (USDOE ). These recommended rates are greater than
the base rates that are dictated by ASHRAE Standard 90.1 but they are not the most
efficient options available on the market. For the DX systems, the efficiency was given
in terms of an energy efficiency ratio (EER). The EER was converted into kW per ton by
Equation 4-2.
Equation 4-2
52
Table 4-6. Calculation of energy costs of DX units
Unit type EER kW/ton
Cost per kWh
Annual EFLOH operating hours
kWh per ton per year
Annual Energy Cost per ton
Inflation rate (%)
Discount rate
PV energy cost over 50 years
DX systems
Wall-mounted unit 11 1.09 $0.15 2000 2182 $330 4% 2.7% $21,111
Package rooftop 11 1.09 $0.15 2000 2182 $330 4% 2.7% $21,111
Split systems 12 1.00 $0.15 2000 2000 $300 4% 2.7% $19,192 Water loop heat pump 12 1.00 $0.15 2000 2000 $300 4% 2.7% $19,192 Geothermal heat pump 14.1 0.85 $0.15 2000 1702 $260 4% 2.7% $16,663
Table 4-7. Calculation of energy costs of Chiller systems
Unit type kW/ton Cost per kWh
Annual EFLOH operating hours
kWh per ton per year
Annual energy cost per ton
Inflation rate (%)
Discount rate
PV energy cost over 50 yrs
Chiller systems
Air cooled chiller 0.98 $0.15 2000 1960 $290 4% 2.7% $18,552
Water cooled chiller 0.49 $0.15 2000 980 $150 4% 2.7% $9,596
53
For this study, it was assumed that the units operated for 2,000 equivalent full load
operating hours. The cost of electricity used was $0.15/kWh and this included demand
charges. The annual energy costs of the units were calculated using Equation 4-3.
Equation 4-3
The annual energy costs listed for these systems were rounded to the nearest ten
dollars of the calculated costs due to the accuracy of the available data. The present
value of this annual cost was computed for each year over the life of the building. These
present values were summed to get the total present value of the unit energy cost over
the 50 year building life. These calculations can be found in Appendix B. Table 4-8
gives a summary and ranking of the cost per ton for the HVAC units.
Maintenance Costs
Table 4-9 shows the calculation of the unit maintenance costs over the life of the
building for the DX and Chiller systems. These costs were based off of general quotes
from mechanical contractors to perform regular preventative maintenance on the units
such as changing filters, lubricating bearings and motors, and inspecting all equipment
and controls. The maintenance cost of the Air Distribution systems were not included in
this study as normal maintenance contracts do not include regular servicing of the
devices that distribute the conditioned air.
The present value of this annual cost was computed for each year over the life of
the building. These present values were summed to get the total present value of the
unit maintenance cost over the 50 year building life. These calculations can be found in
Appendix B. Table 4-10 shows the ranking of maintenance costs for the units.
54
Table 4-8. Summary and ranking of energy costs for the DX and Chiller units
Unit type Annual energy cost per ton Rank
DX systems
Wall-mounted unit $ 330.00 5
Package rooftop $ 330.00 5
Key
Split systems $ 300.00 4
$0 - $150
Water loop heat pump $ 300.00 4
$151 - $300
Geothermal heat pump $ 260.00 2
$301 or greater
Chiller systems
Air cooled chiller $ 290.00 3 Water cooled chiller $ 150.00 1
Table 4-10. Summary and ranking of unit maintenance costs
Unit type
Annual maintenance cost per ton ($/ton) Rank
DX systems
Wall-mounted unit $ 160 4
Package rooftop $ 160 4
Key
Split systems $ 90 2
$0 - $50
Water loop heat pump $ 120 3
$51 - $150
Geothermal heat pump $ 120 3
$151 and up
Chiller systems
Air cooled chiller $ 9.30 1
Water cooled chiller $ 9.30 1
Replacement Costs
Table 4-11 gives the calculation of the present value of the periodic replacement
costs of the HVAC units. These occur at the end of the service life of the HVAC unit.
The replacement costs for the units were assumed to be the same price as the first
costs of the units. The year(s) of replacement was determined based upon the life of the
unit. For Air Distribution Systems, it was assumed that the associated ductwork and
grilles would not be replaced during the life of the building. However, the VAV
55
Table 4-9. Present value of the cost of maintenance over a 50 year building life
Unit type
Annual cost for 5 ton unit
Cost per year ($/ton)
Inflation rate (%)
Discount rate (%)
PV of maintenance costs over 50 years
($/ton)
DX systems
Wall-mounted unit $ 800.00 $ 160 2% 2.7% $ 6,799
Package rooftop $ 800.00 $ 160 2% 2.7% $ 6,799
Split systems $ 450.00 $ 90 2% 2.7% $ 3,824
Water loop heat pump $ 600.00 $ 120 2% 2.7% $ 5,099
Geothermal heat pump $ 600.00 $ 120 2% 2.7% $ 5,099
Chiller systems
Air cooled chiller $ - $ 9.30 2% 2.7% $ 395
Water cooled chiller $ - $ 9.30 2% 2.7% $ 395
56
boxes and Fan-coil units would need to be replaced over the life of the building. These
were the only replacement costs associated with the Air Distribution Systems.
Table 4-12 shows the calculations of the cost to replace miscellaneous unit
equipment. For this study it was assumed that the cost to replace miscellaneous
equipment was 6% of the system first cost. This is an annual cost over the life of the
unit except for the first year after installation. The contractor and/or manufacturer will
normally provide the first year’s parts and labor warranty. The present value of this
annual cost was computed for each year over the life of the building. These present
values were summed to get the total present value of the miscellaneous equipment
replacement cost over the 50 year building life. These calculations can be found in
Appendix B.
Table 4-13 gives a summary of the total replacement costs for the DX and Chiller
units. Table 4-14 gives a summary of the total replacement costs for the Air Distribution
systems. The total replacement costs were found by summing the present value of the
periodic unit replacement costs and the present value of the miscellaneous equipment
costs.
Life Cycle Cost
Table 4-15 summarizes all of the associated costs for the DX and Chiller units
over the life of the building. The life cycle costs of the unit include the first costs, energy
costs, maintenance costs, replacement costs. These costs were summed to get the
total life cycle cost for the unit. Table 4-16 summarizes all of the associated costs for the
Air Distribution systems over the life of the building. The only life cycle costs associated
with the Air Distribution systems were the first costs and the unit replacement costs.
57
Table 4-11. Calculation of periodic unit replacement costs
Unit Type Life of unit
# of replacements over 50 years Replace at year First cost per ton
PV of replacements ($/ton)
DX systems
Wall-mounted unit 15 3 15, 30, 45 $ 1,220.00 $ 2,992
Package rooftop 15 3 15, 30, 45 $ 1,160.00 $ 2,844
Split systems 15 3 15, 30, 45 $ 1,050.00 $ 2,575
Water loop heat pump 24 2 24, 48 $ 900.00 $ 1,412
Geothermal heat pump 24 2 24, 48 $ 1,240.00 $ 540
Chiller systems
Air cooled chiller 25 1 25 $ 460.00 $ 388
Water cooled chiller 25 1 25 $ 530.00 $ 447
The replacement costs for Air Distribution systems are given in cost per unit
Air Distribution
system
Constant volume 50 0 - $ - $ -
VAV 20 2 20, 40 $ 790.00 $ 1,290
Fan-coil units 20 2 20, 40 $ 1,360.00 $ 2,221
58
Table 4-12. Calculation of miscellaneous equipment costs
Unit type First cost per ton
Annual misc. replacement costs (6% of first cost)
PV of misc. replacement costs ($/ton)
DX systems
Wall-mounted unit $ 1,220 $ 73 $ 3,037
Package rooftop $ 1,160 $ 70 $ 2,888
Split systems $ 1,050 $ 63 $ 2,614
Water loop heat pump $ 900 $ 54 $ 2,241
Geothermal heat pump $ 1,240 $ 74 $ 3,087
Chiller systems
Air cooled chiller $ 460 $ 28 $ 1,145
Water cooled chiller $ 530 $ 32 $ 1,319
Table 4-13. Summary and ranking of DX and Chiller replacement costs
Unit Type
Total PV of replacement costs per ton Rank
DX systems
Wall-mounted unit $ 6,029 6
Package rooftop $ 5,732 5
Split systems $ 5,189 4
Key
Water loop heat pump $ 3,652 3
$0 to $2000 Geothermal heat pump $ 3,627 3
$2001 to $5,000
Chiller systems
Air cooled chiller $ 1,533 1
$5,001 or greater
Water cooled chiller $ 1,766 2
Table 4-14. Summary and ranking of Air Distribution replacement costs
Unit type Total PV of replacement costs per unit Rank
Key
Air Distribution
Constant volume $ - 1
$0 to $500
VAV $ 1,290 2
$501 to $2,000
Fan-coil units $ 2,221 3
$2,001 or greater
59
Design Criteria
Required Space
The required space of the system was based upon the size and location of major
system components. Table 4-17 gives a summary of the space requirements for typical
DX and Chiller systems. This summary table was used in the ratings of the required
space of the DX and Chiller systems which can be seen in Table 4-18. Each space
characteristic was rated on a scale of one to three with one requiring the least space.
Table 4-19 lists the meaning of the rating level for each of the space characteristics.
Table 4-19. Explanation of rating system for the required space criterion
Rating
Criteria 1 2 3 Size of the unit Small Medium Large Piping No piping Refrigerant piping Chilled water piping
Mechanical room space required
No mechanical room
Small mechanical room
Large mechanical room
Outdoor equipment space required
Little or no outdoor space
Moderate outdoor space Large outdoor space
Amount of equipment in ceiling space Basic ductwork
Typical air terminal units
Large air terminal units
Table 4-20 gives a summary of the space requirements for typical Air Distribution
Systems. This table was used in the rating of the required space of the Air Distribution
Systems which can be seen in Table 4-21. The space characteristics of a system were
rated on a level of one to three with one requiring the least space. The meaning of the
rating level for each of the space characteristics can be seen in Table 4-19.
Complexity
Table 4-22 shows the calculation of the ranking of the complexity of the DX and
Chiller systems. Table 4-17 was used as a reference in the completion of this table.
60
Table 4-15. Summary and ranking of the life cycle costs for the DX and Chiller units
Unit type First cost
PV energy cost
PV maintenance cost
PV replacement cost Life cycle cost Rank
DX systems
Wall-mounted unit $ 1,220 $ 21,111 $ 6,799 $ 6,029 $ 35,158 5
Package rooftop $ 1,160 $ 21,111 $ 6,799 $ 5,732 $ 34,802 5
Key
Split system $ 1,050 $ 19,192 $ 3,824 $ 5,189 $ 29,255 4
$0 to $25,000
Water loop heat pump $ 900 $ 19,192 $ 5,099 $ 3,652 $ 28,843 4
$25,001 to $30,000
Geothermal heat pump $ 1,240 $ 16,633 $ 5,099 $ 3,627 $ 26,599 3
$30,001 or greater
Chiller systems
Air cooled chiller $ 460 $ 18,552 $ 395 $ 1,533 $ 20,940 2
Water cooled chiller $ 530 $ 9,596 $ 395 $ 1,766 $ 12,287 1
Table 4-16. Summary and ranking of the life cycle costs for the Air Distribution systems
Unit type First cost NPV replacement cost Life cycle cost Rank Key
Air Distribution
systems
Constant volume $ - $ - $ - 1
$0 to $1,000
VAV box $ 790 $ 1,290 $ 2,080 2
$1,001 to $2,000
Fan-coil unit $ 1,360 $ 2,221 $ 3,581 3
$2,001 or greater
61
Table 4-17. Space characteristics for typical designs of DX and Chiller systems.
Unit type
Typical size of unit (H x W x D)
Associated equipment
Placement of unit / equipment Required piping
Ductwork / ceiling space
Mechanical room / closet needed
DX
syst
ems
Wall-Mounted Unit (1 ton) 48" x 32" x 15" N/A Mounted on wall No piping
No ductwork No
Package rooftop (20 ton) 55" x 133" x 91" N/A On roof No piping Typical No
Split systems (5 ton)
Condensing unit: 45" x 37" x 34" AHU: 58" x 24" x 21"
Condensing unit and AHU
Outside condensing unit and indoor AHU
Refrigerant piping between condensing unit and AHU Typical Yes
Water Loop Heat Pump (5 ton)
Condensing unit: 27" x 59" x 29" AHU: 58" x 24" x 21"
Boiler, cooling tower, pump
Unit, boiler, and pump in mechanical room / cooling tower outside
Piping from unit to boiler and cooling tower Typical Yes
Geothermal Heat Pump (5 ton)
Condensing unit: 27" x 59" x 29" AHU: 58" x 24" x 21" Pump
Unit and pump in mechanical room
Piping from ground to unit Typical Yes
Chi
ller s
yste
ms Air cooled
chiller (150 ton) 100" x 95" x 88"
Pumps, AHUS
Chiller and pumps in outside service area / AHUs in mechanical rooms throughout building
Chilled water piping to central AHUS Typical Yes
Water cooled chiller (150 ton) 75" x 170" 34"
Cooling tower, pumps, AHUS
Chiller & pumps in central mechanical room / outside cooling tower / AHUs in mechanical rooms throughout building
Chilled water piping to cooling tower and central AHUS Typical Yes
62
Table 4-18. Calculation of the amount of required space needed for DX and Chiller systems.
Unit type
Size of the unit
Piping required
Mechanical room space required
Outdoor space required Average Rank
DX systems
Wall-mounted unit 1 1 1 1 1.00 1
Package rooftop 2 1 1 2 1.50 2
Key
Split systems 2 2 2 2 2.00 3
1.00
Water loop heat pump 2 3 2 2 2.25 4
1.00 to 2.50
Geothermal heat pump 2 3 2 1 2.00 3
2.50 to 3.00
Chiller systems
Air cooled chiller 3 3 2 3 2.75 5
Water cooled chiller 3 3 3 3 3.00 6
63
Table 4-20. Space characteristics of typical Air Distribution systems
System
Associated equipment
Size of equipment (H x W x D)
Required piping
Equipment in ceiling space
Air Distribution
systems
Constant volume N/A N/A No piping
Ductwork only
VAV VAV boxes 13" x 34" x 10" (250 cfm) No piping
VAV boxes and ductwork
Fan-coil Fan-coil units 16" x 36"x 31" (1,000 cfm)
Chilled water piping to each fan-coil
Fan-coil units, piping and ductwork
Table 4-21. Calculation of required space for Air Distribution systems.
System type Piping
Amount of equipment in ceiling space Average Rank
Key
Air Distribution
systems
Constant volume 1 1 1.00 1
1.00
VAV 1 2 1.50 2
1.00 to 2.50
Fan-coil units 3 2 2.50 3
2.75 to 3.00 Table 4-22. Ranking of the complexity of the DX and Chiller systems
Unit type
Components to install
Points of maintenance Average Rank
DX systems
Wall-mounted unit 1 1 1.00 1
Package rooftop 1 1 1.00 1
Key
Split system 2 1 1.50 2
1.00 to 2.00
Water loop heat pump 3 3 3.00 4
2.00 to 3.00
Geothermal heat pump 2 2 2.00 3
3.00
Chiller systems
Air cooled chiller 3 3 3.00 4 Water cooled
chiller 3 3 3.00 4
1: Little to none 2: Average 3: Excessive
64
Each system complexity characteristic was rated on a scale from one to three with one
being the least complex.
Table 4-23 shows the calculation of the ranking of the complexity of the Air
Distribution systems. Table 4-20 was used as a reference in the completion of this table.
Each system complexity characteristic was rated on a scale from one to three with one
being the least complex.
Table 4-23. Ranking of the complexity of the Air Distribution systems
Unit type Components to install
Points of maintenance Average Rank
Air Distribution
systems
Constant volume 1 1 1.00 1
Key VAV 2 2 2.00 2
1.00 to 2.00
Fan-coil units 3 2 2.50 3
2.00 to 3.00
1: Little to none 2: Average 3: Excessive
3.00
Life of the Unit
Table 4-24 summarizes the sources that were examined in order to determine the
service life of units. The Air Distribution systems were rated separately from the DX and
Chiller systems but still follow the same key. It was found that unit life ranged from 15
years to 30 years. Any units with a life of 15 years up to 20 years were considered to be
poor. Units with a service life of 20 years up to 25 years were considered to have an
average service life. Units with a service life of 25 years or greater were deemed to
have an above average service life.
Noise
Table 4-25 summarizes the potential sources of noise heard in the classroom. This
table was used in the rating of the noise characteristics of the HVAC systems which are
calculated in Table 4-26. Each noise characteristic was rated on a scale of one to three.
65
Table 4-25. Potential sources of noise in classroom
Unit type
Equipment in classroom
Equipment near classroom
Other sources of noise in classroom
DX systems
Wall-mounted unit Fan
Compressor and condenser on outside wall of classroom
Vibration of building structure
Package rooftop None None Rooftop rumble
Split system None
AHU in mechanical closet; condensing unit outside None
Water loop heat pump None AHU in mechanical closet None Geothermal heat pump None AHU in mechanical closet None
Chiller systems
Air cooled chiller None AHU in central mechanical room / closet None
Water cooled chiller None
AHU in central mechanical room / closet None
Air Distribution
systems
Constant volume Ductwork above ceiling None
Air moving through ductwork
VAV
VAV boxes above ceiling (no fan)
Potential placement of VAV above corridor
Air moving through ductwork
Fan-coil Units
Fan-coil above ceiling or in mechanical closet
Potential placement of fan-coil above corridor
Air moving through ductwork
It should be advised that these rankings do not guarantee that a system will fall
within the required 35 dB sound level. It only highlights the potential of the system to
generate noise in the classroom. The design professional must take measures to
reduce system generated noise in the specific design of the system.
Temperature Control
Temperature control was only able to be determined for the Air Distribution
systems. Table 4-27 shows the ranking of these systems’ ability to control temperature
in the conditioned space.
66
Table 4-24. Summary of sources examined in the determination of unit service life
Unit type
From literature review
Contractor's estimate
From ASHRAE table (2007)
From Abramson et al. (2005)
Service life used in study Rank
DX systems
Wall-mounted unit 92 16+ 15 N/A 15 4
Package rooftop 10 to 151, 122 15 15 N/A 15 4
Split systems 122 12 to 15 15 N/A 15 4
Water loop heat pump 10 to 151, 122 16 to 18 19 >24 24 2
Key
Geothermal heat pump N/A 18 19 >24 24 2
25 or greater
Chiller systems
Air cooled chiller (centrifugal) 25 to 301 10 to 15 20 N/A 20 3
20 - 25
Water cooled chiller (centrifugal) 25 to 301 15 to 20 20 >25 25 1
15 - 20
Air Distribution systems were ranked separately from the DX and Chiller systems
Air Distribution
systems
Constant Volume (ductwork) N/A N/A 30 N/A 50 1
VAV box 162 N/A 20 N/A 20 2
Fan-coil unit N/A N/A 20 N/A 20 2
1 Colen (1990); 2 Ottaviano (1993)
67
Table 4-26. Rating of noise characteristics for HVAC systems
Unit type
Sources of noise in classroom
Sources of noise near classroom
Other sources of noise in classroom Average Ranking
DX systems
Wall-mounted unit 3 3 3 3.00 3
Package rooftop 1 1 2 1.33 1
Split system 1 3 1 1.67 2
Key
Water loop heat pump 1 2 1 1.33 1
1.00 to 1.50
Geothermal heat pump 1 2 1 1.33 1
1.50 to 2.00
Chiller systems
Air cooled chiller 1 2 1 1.33 1
2.00 to 3.00
Water cooled chiller 1 2 1 1.33 1 Air Distribution systems were rated separately from the DX and Chiller systems
Air Distribution
systems
Constant volume 1 1 2 1.33 1
VAV 1 1 2 1.33 1
Fan-coil units 2 2 2 2.00 2
1: No noise from equipment 2: Possible source of noise 3: Source of noise
68
Table 4-27. Ranking of the Air Distribution systems’ ability to control temperature of the space
Unit type Control type Rank
Air Distribution systems
Constant volume On/Off 2
VAV Modulating 1
Fan-coil units Modulating 1
The constant volume air method is considered to be the standard method of air
distribution. It delivers air to the space by cycling the HVAC unit on or off as needed.
Both the VAV and Fan-Coil methods of air distribution use modulating controls to
regulate the temperature of the conditioned space. This allows for better control of the
temperature of the space.
69
CHAPTER 5 RESULTS
The following are the completed decision matrices based on the calculations in the
previous chapter.
DX and Chiller Systems
Table 5-1 gives that completed decision matrix for the DX and Chiller systems.
This table is a summary of all the color and numerical rankings for both the cost and
design criteria. The values obtained for the costs of these systems in this general study
did not have a large variation. However, three different ranges in costs were seen.
These ranges are represented by the color scale. Due to the accuracy of the costs that
were able to be obtained during this study, the color scale is the more accurate of the
two scales used in the matrix. It allows the user to quickly identify which range of costs
the system falls within. The numerical ranking of the matrix would be more effective for
use with a specific building design versus a general study such as this one.
Air Distribution Systems
Table 5-2 gives the completed decision matrix for the Air Distribution systems.
This table is a summary of all the color and numerical rankings for both the cost and
design criteria. The variation in costs was not as large for these systems as with the DX
and Chiller systems. However, the color scale again allows the user to quickly identify
which range of costs the system falls within.
70
Table 5-1. Completed decision matrix for DX and Chiller systems
Costs Other
Unit type First cost Energy cost
Maintenance cost
Replacement cost LCC
Required space Complexity
Life of unit Noise
Wall-mounted unit 6 5 4 6 5 1 1 4 3
Package rooftop 5 5 4 5 5 2 1 4 1
Split system 4 4 2 4 4 3 2 4 2
Water loop heat pump 3 4 3 3 4 4 4 2 1
Geothermal heat pump 6 2 3 3 3 3 3 2 1
Air cooled chiller 1 3 1 1 2 5 4 3 1
Water cooled chiller 2 1 1 2 1 6 4 1 1
Table 5-2. Completed decision matrix for the Air Distribution systems
Costs Other
Unit type First cost
Replacement cost LCC
Required space Complexity
Life of unit Noise
Temperature control
Constant volume 1 1 1 1 1 1 1 2
VAV 2 2 2 2 2 2 1 1
Fan-coil units 3 3 3 3 3 2 2 1
71
CHAPTER 6 CONCLUSIONS
From the research conducted it was found that a general life cycle cost analysis of
HVAC systems was not possible to perform. Because each system is unique to the
design of a building, only the approximate costs for the HVAC units were able to be
obtained for this study. Even then costs varied based upon the size and placement of
the unit. Exact cost data was found to be difficult to obtain as the HVAC industry does
not track general cost information. Pricing is done for a specific system according to its
design specifications.
The decision matrix created proved to be a valuable tool in the selection of an
HVAC system for Florida public schools. It effectively presented the HVAC unit
performance in both the cost and design criteria categories so that the units may be
compared. The color scale allows the user to quickly identify the units that fall within the
desired performance levels. The numerical scale allows the user to determine the best
choice within these performance levels. However, the numerical ranking would be more
effective for use with a specific building design versus a general study such as this one.
The proposed decision matrix could be adapted to meet the specific needs of individual
counties in Florida.
72
CHAPTER 7 RECOMMENDATIONS
This study was based on a broad scope. For future studies it would be effective to
narrow the scope to individual counties. Obtaining the costs of HVAC systems that are
constructed in a particular county would provide a more accurate analysis of the costs
for a specific region. The matrix developed in this study could be further developed or
changed to accurately reflect the specific needs of the school district being analyzed.
One of the difficulties of this study was finding accurate cost data for individual
system components and systems as a whole. Further research could focus on collecting
a larger source of quotes of HVAC units. This would provide a more accurate estimate
of the cost per ton of a unit. The first costs of entire HVAC systems could also be
analyzed. A life cycle cost analysis of an entire HVAC system would more accurately
reflect the costs that a school district would incur.
Median service life of HVAC systems could also be analyzed. The median service
life used in this study was based off of ASHRAE’s recommendations. However, this
service life was calculated using the time of replacement for units all over the United
States. The replacement of units in other climatic regions could be different than those
for the State of Florida. A database could be created to track the year at which
equipment is installed in schools and the year when it is replaced. The creation of such
a database would better help the state estimate life cycle costs.
73
APPENDIX A INSTALLATION COSTS OF FLORIDA SCHOOLS
Table A-1 lists the costs of the major HVAC equipment that was put installed in
two schools in Pasco County, Florida. Both schools used the same HVAC system
design of an air cooled chiller with VAV units for air distribution. The materials for these
systems were purchased through the Direct Purchase Program. This allows the State to
purchase materials tax free.
Table A-2 gives a summary of the total costs of the HVAC systems that were
installed in the schools. It calculates the cost per ton of the materials and the installed
cost per ton. It also shows the percentage of material costs to the total mechanical
system cost and the percentage of the mechanical system costs to the total school cost.
Table A-1. HVAC system component costs for two elementary schools in Pasco County Florida
System component costs Cost Tons Cost per ton
Watergrass Elementary (LEED Gold
Certified)
2Aair cooled chillers $ 136,027.00 300 $ 453.42
AHU, VAVs, blower coils $ 71,922.42
2 DX mini-splits $ 11,355.00
Ductwork $ 5,789.34
Total air distribution $ 96,387.00
Gulf Trace Elementary
(LEED Silver Certified)
2 Air cooled chillers $ 129,115.24 300 $ 430.38
AHU, VAVs, blower coils $ 72,340.40
Ductwork $ 4,920.00 Total air distribution $ 80,590.00
74
Table A-2. Total costs for the installation of an air cooled chiller system in Pasco County elementary schools
Total costs Cost per ton
Wat
ergr
ass
Elem
enta
ry
Total material cost $ 486,521.04 $ 1,621.74
Total mechanical contractor amount $ 1,191,478.96 $ 3,971.60
Total cost for HVAC system $ 1,678,000.00 $ 5,593.33 Total construction cost of school $ 11,322,720.00
Percentage of material cost to total mechanical cost 41%
Percentage of mechanical system cost to total construction cost 15%
Gul
f Tra
ce E
lem
enta
ry
Total material cost $ 357,997.16 $ 1,193.32 Total mechanical contractor amount $ 1,131,202.84 $ 3,770.68
Total cost for HVAC system $ 1,489,200.00 $ 4,964.00 Total construction cost of school $ 11,820,540.91
Percentage of material cost to total mechanical cost 32%
Percentage of mechanical cost to total construction cost 13%
75
APPENDIX B PRESENT VALUE CALCULATIONS
Energy Costs
Table B-1 gives a summary of the annual unit energy costs that were used in the
calculation of the total present value of the energy cost. It also gives the inflation rate
and the discount rate. Table B-2 shows the calculation of the total present value of the
annual energy costs for the HVAC units over the 50 year building life.
Table B-1. Summary of costs and rates used in the calculation of the total present value of unit energy costs
Unit HVAC unit Annual energy cost 1.0 Wall-mounted unit $ 330 2.0 Package rooftop $ 330 3.0 Split systems $ 300 4.0 Water loop heat pump $ 300 5.0 Geothermal heat pump $ 260 6.0 Air cooled chiller $ 290 7.0 Water cooled chiller $ 150 Inflation rate 4.0% Discount rate 3.0%
Table B-2. Calculation of total present value of unit energy cost Year 1.0 2.0 3.0 4.0 5.0 6.0 7.0 0 $ 330 $ 330 $ 300 $ 300 $ 260 $ 290 $ 150 1 $ 333 $ 333 $ 303 $ 303 $ 263 $ 293 $ 151 2 $ 336 $ 336 $ 306 $ 306 $ 265 $ 296 $ 153 3 $ 340 $ 340 $ 309 $ 309 $ 268 $ 299 $ 154 4 $ 343 $ 343 $ 312 $ 312 $ 270 $ 301 $ 156 5 $ 346 $ 346 $ 315 $ 315 $ 273 $ 304 $ 157 6 $ 350 $ 350 $ 318 $ 318 $ 276 $ 307 $ 159 7 $ 353 $ 353 $ 321 $ 321 $ 278 $ 310 $ 160 8 $ 357 $ 357 $ 324 $ 324 $ 281 $ 313 $ 162 9 $ 360 $ 360 $ 327 $ 327 $ 284 $ 316 $ 164 10 $ 363 $ 363 $ 330 $ 330 $ 286 $ 319 $ 165 11 $ 367 $ 367 $ 334 $ 334 $ 289 $ 323 $ 167 12 $ 371 $ 371 $ 337 $ 337 $ 292 $ 326 $ 168
76
Table B-2. Continued Year 1.0 2.0 3.0 4.0 5.0 6.0 7.0 13 $ 374 $ 374 $ 340 $ 340 $ 295 $ 329 $ 170 14 $ 378 $ 378 $ 343 $ 343 $ 298 $ 332 $ 172 15 $ 381 $ 381 $ 347 $ 347 $ 301 $ 335 $ 173 16 $ 385 $ 385 $ 350 $ 350 $ 303 $ 338 $ 175 17 $ 389 $ 389 $ 354 $ 354 $ 306 $ 342 $ 177 18 $ 393 $ 393 $ 357 $ 357 $ 309 $ 345 $ 178 19 $ 396 $ 396 $ 360 $ 360 $ 312 $ 348 $ 180 20 $ 400 $ 400 $ 364 $ 364 $ 315 $ 352 $ 182 21 $ 404 $ 404 $ 367 $ 367 $ 318 $ 355 $ 184 22 $ 408 $ 408 $ 371 $ 371 $ 322 $ 359 $ 186 23 $ 412 $ 412 $ 375 $ 375 $ 325 $ 362 $ 187 24 $ 416 $ 416 $ 378 $ 378 $ 328 $ 366 $ 189 25 $ 420 $ 420 $ 382 $ 382 $ 331 $ 369 $ 191 26 $ 424 $ 424 $ 386 $ 386 $ 334 $ 373 $ 193 27 $ 428 $ 428 $ 389 $ 389 $ 337 $ 376 $ 195 28 $ 433 $ 433 $ 393 $ 393 $ 341 $ 380 $ 197 29 $ 437 $ 437 $ 397 $ 397 $ 344 $ 384 $ 199 30 $ 441 $ 441 $ 401 $ 401 $ 347 $ 388 $ 200 31 $ 445 $ 445 $ 405 $ 405 $ 351 $ 391 $ 202 32 $ 450 $ 450 $ 409 $ 409 $ 354 $ 395 $ 204 33 $ 454 $ 454 $ 413 $ 413 $ 358 $ 399 $ 206 34 $ 458 $ 458 $ 417 $ 417 $ 361 $ 403 $ 208 35 $ 463 $ 463 $ 421 $ 421 $ 365 $ 407 $ 210 36 $ 467 $ 467 $ 425 $ 425 $ 368 $ 411 $ 212 37 $ 472 $ 472 $ 429 $ 429 $ 372 $ 415 $ 214 38 $ 476 $ 476 $ 433 $ 433 $ 375 $ 419 $ 217 39 $ 481 $ 481 $ 437 $ 437 $ 379 $ 423 $ 219 40 $ 486 $ 486 $ 442 $ 442 $ 383 $ 427 $ 221 41 $ 490 $ 490 $ 446 $ 446 $ 386 $ 431 $ 223 42 $ 495 $ 495 $ 450 $ 450 $ 390 $ 435 $ 225 43 $ 500 $ 500 $ 455 $ 455 $ 394 $ 439 $ 227 44 $ 505 $ 505 $ 459 $ 459 $ 398 $ 444 $ 229 45 $ 510 $ 510 $ 463 $ 463 $ 402 $ 448 $ 232 46 $ 515 $ 515 $ 468 $ 468 $ 406 $ 452 $ 234 47 $ 520 $ 520 $ 472 $ 472 $ 409 $ 457 $ 236 48 $ 525 $ 525 $ 477 $ 477 $ 413 $ 461 $ 239 49 $ 530 $ 530 $ 482 $ 482 $ 417 $ 466 $ 241 Total PV $ 21,111 $ 21,111 $ 19,192 $ 19,192 $ 16,633 $ 18,552 $ 9,596
77
Maintenance Costs
Table B-3 gives a summary of the annual unit maintenance costs and that were
used in the calculation of the total present value of cost. Table B-4 shows the
calculation of the total present value of the annual maintenance costs for the HVAC
units over the 50 year building life.
Table B-3. Summary of costs and rates used in the calculation of the total present value of unit maintenance costs
Unit HVAC unit Annual maintenance cost per ton
1.0 Wall-mounted unit $ 160
2.0 Package rooftop $ 160
3.0 Split systems $ 90
4.0 Water loop heat pump $ 120
5.0 Geothermal heat pump $ 120
6.0 Air cooled chiller $ 9.30 7.0 Water cooled chiller $ 9.30 Inflation rate 2.00% Discount rate 2.70%
Table B-4. Calculation of the total present value of unit maintenance cost Year 1.0 2.0 3.0 4.0 5.0 6.0 7.0 0 $ 160 $ 160 $ 90 $ 120 $ 120 $ 9 $ 9 1 $ 159 $ 159 $ 89 $ 119 $ 119 $ 9 $ 9 2 $ 158 $ 158 $ 89 $ 118 $ 118 $ 9 $ 9 3 $ 157 $ 157 $ 88 $ 118 $ 118 $ 9 $ 9 4 $ 156 $ 156 $ 88 $ 117 $ 117 $ 9 $ 9 5 $ 155 $ 155 $ 87 $ 116 $ 116 $ 9 $ 9 6 $ 154 $ 154 $ 86 $ 115 $ 115 $ 9 $ 9 7 $ 153 $ 153 $ 86 $ 114 $ 114 $ 9 $ 9 8 $ 151 $ 151 $ 85 $ 114 $ 114 $ 9 $ 9 9 $ 150 $ 150 $ 85 $ 113 $ 113 $ 9 $ 9 10 $ 149 $ 149 $ 84 $ 112 $ 112 $ 9 $ 9 11 $ 148 $ 148 $ 83 $ 111 $ 111 $ 9 $ 9 12 $ 147 $ 147 $ 83 $ 111 $ 111 $ 9 $ 9 13 $ 146 $ 146 $ 82 $ 110 $ 110 $ 9 $ 9
78
Table B-4. Continued Year 1.0 2.0 3.0 4.0 5.0 6.0 7.0 14 $ 145 $ 145 $ 82 $ 109 $ 109 $ 8 $ 8 15 $ 144 $ 144 $ 81 $ 108 $ 108 $ 8 $ 8 16 $ 143 $ 143 $ 81 $ 108 $ 108 $ 8 $ 8 17 $ 142 $ 142 $ 80 $ 107 $ 107 $ 8 $ 8 18 $ 141 $ 141 $ 80 $ 106 $ 106 $ 8 $ 8 19 $ 141 $ 141 $ 79 $ 105 $ 105 $ 8 $ 8 20 $ 140 $ 140 $ 78 $ 105 $ 105 $ 8 $ 8 21 $ 139 $ 139 $ 78 $ 104 $ 104 $ 8 $ 8 22 $ 138 $ 138 $ 77 $ 103 $ 103 $ 8 $ 8 23 $ 137 $ 137 $ 77 $ 103 $ 103 $ 8 $ 8 24 $ 136 $ 136 $ 76 $ 102 $ 102 $ 8 $ 8 25 $ 135 $ 135 $ 76 $ 101 $ 101 $ 8 $ 8 26 $ 134 $ 134 $ 75 $ 100 $ 100 $ 8 $ 8 27 $ 133 $ 133 $ 75 $ 100 $ 100 $ 8 $ 8 28 $ 132 $ 132 $ 74 $ 99 $ 99 $ 8 $ 8 29 $ 131 $ 131 $ 74 $ 98 $ 98 $ 8 $ 8 30 $ 130 $ 130 $ 73 $ 98 $ 98 $ 8 $ 8 31 $ 129 $ 129 $ 73 $ 97 $ 97 $ 8 $ 8 32 $ 129 $ 129 $ 72 $ 96 $ 96 $ 7 $ 7 33 $ 128 $ 128 $ 72 $ 96 $ 96 $ 7 $ 7 34 $ 127 $ 127 $ 71 $ 95 $ 95 $ 7 $ 7 35 $ 126 $ 126 $ 71 $ 94 $ 94 $ 7 $ 7 36 $ 125 $ 125 $ 70 $ 94 $ 94 $ 7 $ 7 37 $ 124 $ 124 $ 70 $ 93 $ 93 $ 7 $ 7 38 $ 123 $ 123 $ 69 $ 93 $ 93 $ 7 $ 7 39 $ 123 $ 123 $ 69 $ 92 $ 92 $ 7 $ 7 40 $ 122 $ 122 $ 68 $ 91 $ 91 $ 7 $ 7 41 $ 121 $ 121 $ 68 $ 91 $ 91 $ 7 $ 7 42 $ 120 $ 120 $ 68 $ 90 $ 90 $ 7 $ 7 43 $ 119 $ 119 $ 67 $ 89 $ 89 $ 7 $ 7 44 $ 118 $ 118 $ 67 $ 89 $ 89 $ 7 $ 7 45 $ 118 $ 118 $ 66 $ 88 $ 88 $ 7 $ 7 46 $ 117 $ 117 $ 66 $ 88 $ 88 $ 7 $ 7 47 $ 116 $ 116 $ 65 $ 87 $ 87 $ 7 $ 7 48 $ 115 $ 115 $ 65 $ 86 $ 86 $ 7 $ 7 49 $ 114 $ 114 $ 64 $ 86 $ 86 $ 7 $ 7 Total PV $ 6,799 $ 6,799 $ 3,824 $ 5,099 $ 5,099 $ 395 $ 395
79
Replacement Costs
Table B-5 gives a summary of the annual costs to replace miscellaneous unit
equipment. It also gives the inflation and discount rates that were used in the calculation
of the total present value of these costs.
Table B-5. Summary of costs and rates used in the calculation of the total present value of miscellaneous unit replacement costs
Unit HVAC unit Annual miscellaneous replacement cost
1.0 Wall-mounted unit $ 73
2.0 Package rooftop $ 70
3.0 Split systems $ 63
4.0 Water loop heat pump $ 54
5.0 Geothermal heat pump $ 74
6.0 Air cooled chiller $ 28
7.0 Water cooled chiller $ 32 Inflation rate 2.00% Discount rate 2.70%
Table B-6 shows the calculation of the total present value of the miscellaneous
equipment replacement costs for the HVAC units over the 50 year building life. The
replacement cost for the first year after installation (year zero) has been neglected in
these calculations as the manufacturer or mechanical contractor will provide a one year
warranty on the parts and labor of any replacements.
Table B-6. Calculation of the total present value of miscellaneous unit replacement costs
Year 1.0 2.0 3.0 4.0 5.0 6.0 7.0 1 $ 73 $ 69 $ 63 $ 54 $ 74 $ 27 $ 32 2 $ 72 $ 69 $ 62 $ 53 $ 73 $ 27 $ 31 3 $ 72 $ 68 $ 62 $ 53 $ 73 $ 27 $ 31 4 $ 71 $ 68 $ 61 $ 53 $ 72 $ 27 $ 31 5 $ 71 $ 67 $ 61 $ 52 $ 72 $ 27 $ 31 6 $ 70 $ 67 $ 60 $ 52 $ 71 $ 26 $ 31
80
Table B-6. Continued Year 1.0 2.0 3.0 4.0 5.0 6.0 7.0 7 $ 70 $ 66 $ 60 $ 51 $ 71 $ 26 $ 30 8 $ 69 $ 66 $ 60 $ 51 $ 70 $ 26 $ 30 9 $ 69 $ 65 $ 59 $ 51 $ 70 $ 26 $ 30 10 $ 68 $ 65 $ 59 $ 50 $ 69 $ 26 $ 30 11 $ 68 $ 65 $ 58 $ 50 $ 69 $ 26 $ 29 12 $ 67 $ 64 $ 58 $ 50 $ 69 $ 25 $ 29 13 $ 67 $ 64 $ 58 $ 49 $ 68 $ 25 $ 29 14 $ 67 $ 63 $ 57 $ 49 $ 68 $ 25 $ 29 15 $ 66 $ 63 $ 57 $ 49 $ 67 $ 25 $ 29 16 $ 66 $ 62 $ 56 $ 48 $ 67 $ 25 $ 29 17 $ 65 $ 62 $ 56 $ 48 $ 66 $ 25 $ 28 18 $ 65 $ 62 $ 56 $ 48 $ 66 $ 24 $ 28 19 $ 64 $ 61 $ 55 $ 47 $ 65 $ 24 $ 28 20 $ 64 $ 61 $ 55 $ 47 $ 65 $ 24 $ 28 21 $ 63 $ 60 $ 55 $ 47 $ 64 $ 24 $ 28 22 $ 63 $ 60 $ 54 $ 46 $ 64 $ 24 $ 27 23 $ 63 $ 59 $ 54 $ 46 $ 64 $ 24 $ 27 24 $ 62 $ 59 $ 53 $ 46 $ 63 $ 23 $ 27 25 $ 62 $ 59 $ 53 $ 46 $ 63 $ 23 $ 27 26 $ 61 $ 58 $ 53 $ 45 $ 62 $ 23 $ 27 27 $ 61 $ 58 $ 52 $ 45 $ 62 $ 23 $ 26 28 $ 60 $ 57 $ 52 $ 45 $ 61 $ 23 $ 26 29 $ 60 $ 57 $ 52 $ 44 $ 61 $ 23 $ 26 30 $ 60 $ 57 $ 51 $ 44 $ 61 $ 22 $ 26 31 $ 59 $ 56 $ 51 $ 44 $ 60 $ 22 $ 26 32 $ 59 $ 56 $ 51 $ 43 $ 60 $ 22 $ 26 33 $ 58 $ 56 $ 50 $ 43 $ 59 $ 22 $ 25 34 $ 58 $ 55 $ 50 $ 43 $ 59 $ 22 $ 25 35 $ 58 $ 55 $ 50 $ 43 $ 59 $ 22 $ 25 36 $ 57 $ 54 $ 49 $ 42 $ 58 $ 22 $ 25 37 $ 57 $ 54 $ 49 $ 42 $ 58 $ 21 $ 25 38 $ 56 $ 54 $ 49 $ 42 $ 57 $ 21 $ 25 39 $ 56 $ 53 $ 48 $ 41 $ 57 $ 21 $ 24 40 $ 56 $ 53 $ 48 $ 41 $ 57 $ 21 $ 24 41 $ 55 $ 53 $ 48 $ 41 $ 56 $ 21 $ 24 42 $ 55 $ 52 $ 47 $ 41 $ 56 $ 21 $ 24 43 $ 55 $ 52 $ 47 $ 40 $ 55 $ 21 $ 24 44 $ 54 $ 52 $ 47 $ 40 $ 55 $ 20 $ 24 45 $ 54 $ 51 $ 46 $ 40 $ 55 $ 20 $ 23
81
Table B-6. Continued Year 1.0 2.0 3.0 4.0 5.0 6.0 7.0 46 $ 53 $ 51 $ 46 $ 39 $ 54 $ 20 $ 23 47 $ 53 $ 50 $ 46 $ 39 $ 54 $ 20 $ 23 48 $ 53 $ 50 $ 45 $ 39 $ 54 $ 20 $ 23 49 $ 52 $ 50 $ 45 $ 39 $ 53 $ 20 $ 23 Total PV $ 3,037 $ 2,888 $ 2,614 $ 2,241 $ 3,087 $ 1,145 $ 1,319
82
LIST OF REFERENCES
Abramson, B., Herman, D., and Wong, L. (2005). Interactive Web-based owning and operating cost database (TRP-1237). ASHRAE Research Project, Final Report.
Akalin, M.T. (1978). “Equipment life and maintenance cost survey (RP-186).” ASHRAE Transactions, 84(2), 94-106.
American Society of Heating, Refrigerating and Air Conditions Engineers (2010). “ASHRAE: HVAC Maintenance Cost Database.”, <http://xp20.ashrae.org/publicdatabase/maintenance.asp> (Feb. 27, 2010).
American Society of Heating,Refrigerating and Air Conditioning Engineers , and Knovel. (2008). 2008 ASHRAE handbook [electronic resource] : heating, ventilating, and air-conditioning systems and equipment. ASHRAE, Atlanta, Ga.
American Society of Heating,Refrigerating and Air Conditioning Engineers, and Knovel. (2007). 2007 ASHRAE handbook [electronic resource] : heating, ventilating, and air-conditioning applications. ASHRAE, Atlanta, Georgia.
Colen, H. R. (1990). HVAC systems evaluation. R.S. Means Company, Kingston, MA.
Elovitz, D. M. (2002). "Selecting the right HVAC system." ASHRAE J., 44(1), 24-30.
Fischer, J. C., and Bayer, C. W. (2003). "Report Card on Humidity Control." ASHRAE J., 45(5), 30-2, 34, 36-9.
Florida Department of Education (2003). Instructions for Life Cycle Cost Analysis of School HVAC Systems. <http://www.fldoe.org/edfacil/pdf/lcca.pdf> (Feb. 27, 2010)
Florida Department of Education (1999). Life Cycle Cost Guidelines for Materials and Building Systems for Florida’s Public Educational Facilities.
Fuller, S. K., and Peterson, S. R. (1996). "Life-Cycle Costing Manual for the Federal Energy Management Program." U.S. Government Printing Office, Washington, DC.
Hiller, C. C. (2000). "Determining equipment service life." ASHRAE J., 42(8), 48-54.
Janis, R. R., and Tao, W. K. Y. (2009). "Mechanical and Electrical Systems in Buildings." Prentice Hall, Upper Saddle River, NJ, 15-16.
Oppenheim, P. (1992). "A Decision Matrix for Selection of Climate Control Equipment." National Association of Industrial Technology, 8(4), 42-46.
Ottaviano, V. B. (1993). National Mechanical Estimator. The Fairmont Press, Lilburn, GA.
83
RS Means (2010). “CostWorks.”, <http://www.meanscostworks.com/> (Feb. 27, 2010).
Siebein, G. W., and Lilkendey, R. M. (2004). "Acoustical Case Studies of HVAC Systems in Schools." ASHRAE J., 46(5), 35-6, 38-9, 41-2, 44, 46-7.
The Trane Company (1991). Systems Manual.
US Department of Energy (2009). “Purchasing Specifications for Energy-Efficient Products.”, <http://www1.eere.energy.gov/femp/technologies/eep_purchasingspecs.html> (Feb. 27, 2010).
84
BIOGRAPHICAL SKETCH
Kelly McLaughlin was born and raised in West Palm Beach, Florida. She is the
daughter of Jack and Nadean McLaughlin and has a younger brother Stephen. She
attended the University of Florida where she obtained her Bachelor of Science in
Mechanical Engineering in 2008. She then pursued a Master of Science in Building
Construction. Upon graduation Kelly plans to work for Walt Disney World as a
construction project manager.